Agile meeting/ Agile Ceremonies-
In Agile meeting we have different meeting
1. Grooming meeting
2. Sprint planning meeting
3. Scrum meeting/ Daily stand meeting
4. Sprint review meeting
5. Retrospective meeting.
Meeting Purpose Duration/ Involved
1. Grooming meeting 1. User story/ Req. To understand 30 min/ 1hr PO, PM,
(Before the start of sprint Design, Dev Team,
or Any time) Testing Team,client
2. Sprint planning 1. Current sprint US add/ work decide – 30 min PM, BA,
meeting BA, PM, Design Design, Dev Team,
(Start of sprint) 2. Estimation/ story point –Time for dev Testing Team
& testing
Ex. 1US = 16hr Dev + 8hr Test = 24 hr (3
days)
3. Scrum meeting/ Daily 1. What we have yesterday 15 min PM, Design,
stand meeting 2. What we are doing today Dev Team, Testing
(Daily – every day) 3. Issue/ Rock block Team, BA (optional)
4. Sprint review meeting 1. Current sprint US Review/ Demo 30 min/ 1hr
(Last day of sprint OR Demo will give by Tester (Client BA/Client, Designer,
start day of next sprint) Interaction) Dev team, Test Team,
PM
5. Sprint retrospective 1. Current sprint Good/ Bad things we 30 min PM, Designer,
meeting done- dissuasion dev team, Testing team,
(Last day of sprint) 1st Sprint complete 2nd Sprint BA (optional)
Grooming Meeting:-
Sprint duration – 2 week
Sprint 1
- Sprint start date – 23 may 2022
- Sprint End date- 5 June 2022
Grooming Meeting:- (20 May 2022)
Duration – 1 to 2 hr
This meeting will happen before start of sprint or any time middle of sprint.
- Client – 20 US
Phn pay-- 5
Gpay-2
FB--3
Whatsup--10
Purpose of meeting:-
To understand US.
To discuss user stories which are coming from client ..or client will explain all requirement.
People involvement:-
Client involved.
1. Dev team and lead
2. Tester team and lead
3. Product owner.
4. Design.
2. Sprint planning meeting:-
Duration – 1 hr
23 May 2022
Purpose of meeting:-
- In this meeting we assign US to Dev team.
- Also we decide the Story point for each and every US.
-
-
- People involvement:-
- DEV team
- Tester Team
- Design
- Product owner
- Project manager / scrum master.
This meeting will happen once in every sprint.
Story point – is nothing but time required to complete US which given by DEV and Tester.
1 Story point== 8 hr
50 SP---sprint 1
Ticket -2===5
20SP-
50-23===27
15US===50SP
US pending====5
Planning poker – it is used for Story point decide.
DCTACH- 101
Dev = 16 hr
Tester – 8hr
Total = 24hr/8
SP= 3
SP=====DEV work+ tester work
SP – imp
1 , 2 , 3 , 5 , 8 ,13
Dctach-100-
We have to fetch data and upload data into prod data base.
Dctach 101-----We have to fetch data
2 SP
DCTACH-102---upload data into prod data base.
SP -3
DCTACH-102
Rohan – 2 sp
Jeevan- 3 sp
Gaurav- 5 sp
Akshay-2 sp
Pallavi- 2 sp
3. Daily stand-up meeting/ Scrum meeting:-
This meeting will happen daily till sprint end.
Duration – 15 min
People involved-
- Dev
- Tester
- Product owner.
Agenda meeting:-
- What we are done yesterday?
- What we will do today?
- What are the road blocks/issue while doing regular work.
-