Inspection & Testing Plan For Plaster Work
Project : Construction of Block-J Boulevard-1,2 (B+G+9+R) on plot no.15/3288 & Boulevard-3(B+G+9+R) on Plot no.2/15/3288, Sharjah , UAE
Client: Aljada developments LLC
DeveloperArada Development LLC
ConsultanArcadia Middle East
Verification Code: H-Hold Point, W-Witness Point, R-Review Point, S-Surveillance, I-Inspection, A- Revision: 00
Legend: SC-Subcontractor, C-Contractor, Er.- Engineer, CL-Client
Approval Date:14.02.2022
Verifying Party
Remarks / Verifying
Serial No. Activity Reference Documents Acceptance Criteria
SC C Er. CL Documents
1 Material Approval
1.1 • Pre-mixed Cementitous Dry spry As per Specification Section 09 42 00 Manufacturer's product data for Pre mixed cementitious dry plaster. Test report Approved Document
plaster div 2.7 with information of Minimum compressive strength. -- H A A Transmittal
1.3 Plaster Accessories As per Specification Section 09 42 00 Approved Document
div 2.8 Expanded galvanized steel sheets diamond mesh weight not less than 1.61 -- H A S Transmittal
kg/m2 or as approved by Engineer
2 Material inspection
2.1 Material receiving inspection Material approvals / Product data sheet Material delivered complying to material approvals / approved drawings. Material delivery notes /
-- H I S
Material inspection report
3 Field constructed Mock-Ups
3.1 Mock-Up sample As per Specification Section 09 42 00 Plaster Mock-ups build on site locations approximately 1m X 1m or as agreed Site Mock-up visual
-- H H S
with engineer inspection.
4 Installation
4.1 Surface prepration and Installation As per Specification Section 09 42 00 • Hack / Roughen concrete surface thoroughly
of Plaster Accessories div 3.7 • 150 mm wide strip lath to be fixed over dissimilar material
• External angel beads to ensure a true straight arises.
• Fixed the control joint beads indicated as per the approved shop drawing or -- I A/H -- WIR
not more than 6m center.
• Bonding Coating to be applied for all concrete surface
4.4 Final inspection As per specification section 09 42 00 •Finished plaster water cured for period of 48 hours minimum.
•Make all the surface clean and free from cracks. -- I A/H -- WIR