Name: _____________________________________                                         Section: _______________
_____________________________________                                      Score: ________________
PERFORMANCE TASK
Mr. Dela Cruz would like to renovate the conference hall to be used for the ASEAN Summit. He consulted an engineer to
give him an estimate of the number of days the conference hall will be fully renovated. The engineer estimated that 7
workers can finish the job in 30 days. What if Mr. Dela Cruz would like to expedite the job and wants to have it done in the
following days:
    a.   25 days
    b.   20 days
    c.   15 days
    d.   10 days
    1. How many workers are needed to do the job?
       NUMBER OF         NUMBER OF DAYS OF
      WORKERS (W)              WORK (D)
           7                       30
                                   25
                                   20
                                   15
                                   10
Show the solution of how each unknown number of workers is determined:
   a. Determine the constant
    b. Write the equation
    c. Use the equation to solve for the unknown in the table
    2. If each worker is paid 350 each, how much would the labor cost be? (JOINT variation)
 RATE /CONSTANT             NUMBER OF                   NUMBER OF DAYS OF               LABOR COST
                            WORKERS (W)                     WORK (D)                         (L)
            350                     7                          30                          73 500
            350                                                25
            350                                                20
            350                                                15
            350                                                10
   3. If you are Mr. Dela Cruz, how many days of work is it more practical to choose if you need to consider monetary
      aspect? Why?
DECISION and REASON: