Gantt Chart

This document outlines a project schedule from September 2022 to February 2023. It includes 27 tasks related to recruitment, training, customer research, platform development, and launch. Key tasks include finding collaborators and consultants from late September to late October, gathering requirements and developing access policies in early October, developing a marketing plan from mid-October to early November, and designing, developing and testing the platform from mid-December to early February. The overall project aims to launch a new platform by February 3rd, 2023.

Uploaded by

Khang Nguyễn
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
60 views1 page

Gantt Chart

This document outlines a project schedule from September 2022 to February 2023. It includes 27 tasks related to recruitment, training, customer research, platform development, and launch. Key tasks include finding collaborators and consultants from late September to late October, gathering requirements and developing access policies in early October, developing a marketing plan from mid-October to early November, and designing, developing and testing the platform from mid-December to early February. The overall project aims to launch a new platform by February 3rd, 2023.

Uploaded by

Khang Nguyễn
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Name Duration Start September 2022 October 2022 November 2022 December 2022 January 2023 February

ctober 2022 November 2022 December 2022 January 2023 February 2023
5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 2 5
19 Recruitment 7 days Fri 9/9/22
20 •Team division 1 day Tue 20/9/22
21 •Training 4 days Wed 21/9/22
2 •Customer demand 4 days Tue 27/9/22
Survey
3 •Interview potential 1 day Tue 27/9/22
customer
22 •Finding Collaborators 14 days Tue 27/9/22
23 •Finding Consultants 14 days Tue 27/9/22
4 •Data analysis 3 days Mon 3/10/22
11 •Research other 15 days Mon
platforms 3/10/22
5 •Requirement gathering 2 days Thu 6/10/22
10 •Access Policy 14 days Thu 6/10/22
development
6 Project charter 7 days Mon 10/10/22
1 Develop marketing plan 14 days Wed 19/10/22
7 •Club contract for 7 days Wed
marketing 19/10/22
24 •Attract capital 60 days Wed 19/10/22
12 •Planning 30 days Mon 24/10/22
13 •Find contractors 30 days Mon 24/10/22
8 •Booth in FTU 30 days Tue 8/11/22
9 •Poster display 30 days Tue 8/11/22
14 •Deal on the price with 7 days Mon
platform contractor 5/12/22
15 •Design, Develop platform30 days Wed 14/12/22
25 •School data gathering 15 days Wed 14/12/22
26 •Club data gathering 15 days Wed 14/12/22
27 •Market research for data15 days Wed 14/12/22
16 •Render the platform 7 days Wed 25/1/23
17 •Fix platform's errors 7 days Wed 25/1/23
18 •Launch 1 day Fri 3/2/23

Task Project Summary Manual Task Start-only Deadline

Project: Project1 Split Inactive Task Duration-only Finish-only Progress


Date: Fri 9/9/22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone