Files
Files
ASA recently published T HR CI 12130 ST Track Drainage, (standard) version 2.0. As a result,
the cross-referencing to the standard and some content in the manual is now superseded.
Manual T HR CI 12130 MA version 1.0, Section 2.2, notes that the shaded sections are extracts
from the standard. Due to the associated standard being revised, the content of all shaded
sections (in between the horizontal bars) in this manual shall be ignored and the replacement
content shall be obtained from the current track drainage standard.
Furthermore, as noted in Section 2.2 of the standard (T HR CI 12130 ST version 2.0), where a
conflict in requirements exists between the standard and any other referenced standard or
document, which includes the manual (T HR CI 12130 MA), the standard takes precedence.
Manual T HR CI 12130 MA version 1.0, Section 9.2, provides guidance only for 'External party
development discharging onto or through the rail corridor'. External development requirements
are in T HR CI 12080 ST External Developments.
Authorisation:
Technical content Checked and Interdisciplinary Authorised for
prepared by approved by coordination release
checked by
Signature
Date
Name Malcolm Peake Richard Hitch Peter McGregor Andrea Parker
Position Senior Engineer Lead Civil Engineer A/Chief Engineer A/Executive Director
Structures
Durability requirements are now contained in T HR CI 12002 ST Durability Requirements for Civil
Infrastructure.
Authorisation:
Technical content Checked and Interdisciplinary Authorised for
prepared by approved by coordination release
checked by
Signature
Date
Name Richard Hitch Richard Hitch Jason R Gordon Jagath Peiris
Position Lead Civil Engineer Lead Civil Engineer Chief Engineer Director
Network Standards
and Services
Manual
Track Drainage
Version 1.0
Issued date: 04 September 2015
Important Warning
This document is one of a set of standards developed solely and specifically for use on Transport Assets (as defined in the Asset
Standards Authority Charter). It is not suitable for any other purpose.
You must not use or adapt it or rely upon it in any way unless you are authorised in writing to do so by a relevant NSW Government
agency. If this document forms part of a contract with, or is a condition of approval by a NSW Government agency, use of the document
is subject to the terms of the contract or approval.
This document is uncontrolled when printed or downloaded. Users should exercise their own skill and care in the use of the document.
This document may not be current. Current standards may be accessed from the Asset Standards Authority website at
www.asa.transport.nsw.gov.au.
Standard governance
Owner: Lead Civil Engineer, Asset Standards Authority
Authoriser: Chief Engineer Rail, Asset Standards Authority
Approver: Executive Director, Asset Standards Authority on behalf of the ASA Configuration Control
Board
Document history
Version Summary of Changes
1.0 First issue
Preface
The Asset Standards Authority (ASA) is an independent unit within Transport for NSW (TfNSW)
and is the network design and standards authority for defined NSW transport assets.
The ASA is responsible for developing engineering governance frameworks to support industry
delivery in the assurance of design, safety, integrity, construction, and commissioning of
transport assets for the whole asset life cycle. In order to achieve this, the ASA effectively
discharges obligations as the authority for various technical, process, and planning matters
across the asset life cycle.
The ASA collaborates with industry using stakeholder engagement activities to assist in
achieving its mission. These activities help align the ASA to broader government expectations
of making it clearer, simpler, and more attractive to do business within the NSW transport
industry, allowing the supply chain to deliver safe, efficient, and competent transport services.
The ASA develops, maintains, controls, and publishes a suite of standards and other
documentation for transport assets of TfNSW. Further, the ASA ensures that these standards
are performance-based to create opportunities for innovation and improve access to a broader
competitive supply chain.
This document expands upon content in the ASA standard T HR CI 12130 ST Track Drainage.
This document supersedes RailCorp standard TMC 421 Track Drainage, Version 1.2. The
changes to previous content include the following:
• replacement of RailCorp organisation roles and processes with those applicable to the
current ASA organisational context
Foreword
This manual is intended to be used by competent personnel engaged in the provision of
services relating to rail infrastructure. Compliance with the advice in this manual will not, by
itself, be sufficient to ensure that satisfactory outcomes will be produced. Personnel providing
services based on the manual need to bring appropriate expertise to the matters under
consideration.
If, when using the manual, it is considered that the intent of stated advice is not clear, a
clarification should be sought from the ASA.
Table of contents
1. Introduction .............................................................................................................................................. 7
2. Purpose .................................................................................................................................................... 7
2.1. Scope ..................................................................................................................................................... 7
2.2. Application ............................................................................................................................................. 7
3. Reference documents ............................................................................................................................. 7
4. Terms and definitions ............................................................................................................................. 8
5. Types of track drainage ........................................................................................................................ 10
5.1. Surface drainage ................................................................................................................................. 10
5.2. Subsurface drainage ............................................................................................................................ 12
6. Design of track drainage ....................................................................................................................... 24
6.1. Design criteria ...................................................................................................................................... 25
6.2. Design investigation ............................................................................................................................. 34
6.3. Estimation of the required drainage system capacity .......................................................................... 35
6.4. Surface drain design ............................................................................................................................ 38
6.5. Subsurface drain design ...................................................................................................................... 46
6.6. Other design considerations ................................................................................................................ 51
7. Construction of track drainage ............................................................................................................ 52
7.1. Line and grade ..................................................................................................................................... 52
7.2. Site preparation ................................................................................................................................... 53
7.3. Excavation ........................................................................................................................................... 54
7.4. Surface drain construction ................................................................................................................... 54
7.5. Subsurface drain construction ............................................................................................................. 56
7.6. Other types of construction .................................................................................................................. 61
7.7. Inlets and outlets .................................................................................................................................. 62
8. Maintenance of track drainage ............................................................................................................. 62
8.1. General ................................................................................................................................................ 62
8.2. Surface drainage ................................................................................................................................. 65
8.3. Subsurface drainage ............................................................................................................................ 66
8.4. Typical problems and solutions ........................................................................................................... 68
8.5. Preparation for flooding ....................................................................................................................... 75
9. Documentation guide ............................................................................................................................ 76
9.1. Drawing guide ...................................................................................................................................... 77
9.2. External party development discharging onto or through the rail corridor ........................................... 81
Appendix A Flow charts ......................................................................................................................... 83
A.1. Flow chart 1 – overall design process ................................................................................................. 83
A.2. Flow chart 2 – surface drainage design ............................................................................................... 84
A.3. Flow chart 3 – subsurface drainage design ......................................................................................... 85
Appendix B Drainage design checklist ................................................................................................ 86
Appendix C Design investigation form ................................................................................................. 94
1. Introduction
This manual specifies the design, construction, and maintenance guides for track drainage
systems. It covers drainage of the track formation, supporting embankments, and cuttings.
The potential effects of any drainage work need to be considered and mitigated to ensure safety
so far as is reasonably practicable in accordance with the requirements of T HR CI 12130 ST
Track Drainage.
2. Purpose
The purpose of this manual is to provide a comprehensive guide for the design, construction,
and maintenance of effective track drainage.
Regular examination, inspection, and routine maintenance of drainage systems are essential in
maintaining the integrity of the track formation, supporting embankments, and cuttings.
Inspection of track drainage is included in track engineering manual TMC 203 Track Inspection.
2.1. Scope
This document covers drainage of the track formation, supporting embankments and cuttings.
This standard does not cover drainage from platforms, buildings, overbridges, footbridges,
airspace developments, external developments, access roads, roads outside the rail corridor,
council drains, or properties adjacent to the rail corridor.
2.2. Application
The guidance given in this document applies to Authorised Engineering Organisations (AEOs)
that are involved in track drainage works across the full life cycle. This includes activities such
as design, construction, maintenance, and decommissioning works, which take place within the
TfNSW heavy rail corridor.
The shaded sections in this manual are extracts from ASA standard T HR CI 12130 ST Track
Drainage. Horizontal bars are also shown at the beginning and end of these requirements.
3. Reference documents
The following documents are cited in the text. For dated references, only the cited edition
applies. For undated references, the latest edition of the referenced document applies.
Australian standards
TMD 0001 CAD and Drafting Manual - All Design Areas – Sections 1 and 2
AEO Authorised Engineering Organisation; a legal entity (which may include a Transport
Agency as applicable) to whom the ASA has issued an ASA Authorisation.
ASA Authorisation an authorisation issued by the ASA to a legal entity (which may include a
Transport Agency as applicable) which verifies that it has the relevant systems in place to carry
out the class of asset life cycle work specified in the authorisation, subject to any conditions of
the authorisation. The issue of ASA Authorisation confers the status of ‘Authorised Engineering
Organisation’ or AEO on the entity.
average recurrence interval the average or expected value of the periods between
exceedances of a given flood event accumulated over a given duration
catch drain intercepts overland flow or run-off before it reaches the track and related structures
such as cuttings or embankments
cess area from the edge of the ballast profile to either the edge of the embankment or the toe of
the cutting
cess drain drain located at formation level at the side of the track
Darcy-Weisbach equation an equation which relates head loss due to friction along a given
length of pipe to the average velocity of the fluid flow
down rail identified with back to Sydney as normal, the down rail will be on the left
dynamic load allowance the dynamic load allowance for railway live load effects is a
proportion of the static railway live load calculated in accordance with AS 5100
mitre drain connected to cess and catch drains to remove water or to provide an escape for
water from these drains
peak flow rate the highest flow discharged from the catchment under consideration having
evaluated storm durations with a particular average recurrence interval
railway corridor comprises the full volume, both above and below ground, between the centre-
line of opposing boundary fences. If no boundary fences are present, the extent of the rail
corridor will be taken as 15 m from the centre-line of the outermost rail.
track drainage drainage of the track formation including diversion of water away from cuttings
and embankments
If the permanent way or track structure is to be maintained at a suitable standard for the
passage of freight or high-speed passenger trains, adequate drainage needs to be installed in
new or upgraded track, and existing drainage needs to be maintained so that it works
effectively.
• surface drainage
• subsurface drainage
Basic grading of the ground on either side of the track is a form of surface drainage, and allows
removal of water flowing out of the track structure.
Shoulder grading may be used in very flat areas where it is difficult to get sufficient fall for either
surface or subsurface drains. This type of grading is shown in Figure 1.
There are three main types of surface drainage. These are the following:
• cess drains
• catch drains
• mitre drains
Cess drains are most frequently found in cuttings where water running off the formation cannot
freely drain away.
Surface drains can be constructed on flat grades, as they are easily cleared of any sediment
that may collect in them.
Catch drains are generally located on the uphill side of a cutting to catch water flowing down the
hill and remove it prior to reaching the cutting.
If this water was allowed to flow over the cutting face, it may cause excessive erosion and
subsequent silting up of cess drains.
Catch drains may be used alongside tracks that cut across a slight downhill grade.
"If a drainage system is required to remove ground water and seepage, a detailed hydrological
and geotechnical investigation is required to determine the volume of water for the sizing of
drains."
The volume of water from other systems is determined from the outlet capacity of that system.
Subsurface drains are used where adequate surface drainage cannot be provided due to some
restriction or lack of available fall due to outlet restrictions. Locations where these
circumstances may occur are the following:
• platforms
• cuttings
• junctions
• multiple tracks
• bridges
"Subsurface drainage shall be provided in locations where the water table is at or near
earthworks level. Subsurface drainage shall also be provided where artesian conditions exist to
relieve water pressure.
Subsurface drainage shall be provided along the cess, between, across, or under tracks as
required."
Advice should be sought from the Principal Engineer Geotech, ASA, before designing and
installing subsurface drainage.
"Subsurface drainage systems shall be designed to transfer surface runoff, ground water and
seepage, and water collected from other drainage systems to which the new system is being
connected."
• collection of infiltration water that seeps into the formation (capping layer), as shown in
Figure 6
Horizontal and vertical drains are more specialised and are seldom used for track drainage.
Horizontal drains are generally used to drain wet soils and speed consolidation of earth
structures.
Vertical drains may also be used to speed consolidation. Another type of vertical drain is used
to drain water from behind retaining walls or bridge abutments.
• aggregate drains
• pipe drains
• geotextile drains
Aggregate drains
These drains consist of permeable granular material. The aggregate should be coarse enough
to be free draining, but not so coarse as to allow the migration of fines into or through the
permeable material. The graded aggregate is to be wrapped in a geotextile (Figure 14).
Pipe drains
These consist of perforated or slotted pipes, installed by trenching and backfilling. Some type of
filter material around the pipe or permeable backfill is normally required to minimise clogging of
the drain perforations or slots (see Figure 15, Figure 16, and Figure 17).
Figure 15 - Cross-section of a typical subsoil drain used in impervious soil (for example,
clayey soils)
Figure 16 - Cross-section of a typical subsoil drain used in pervious soil (for example,
sandy soil)
Geotextile drains
A geotextile drain may be a horizontal, vertical, or inclined blanket whose purpose is to collect
subsurface water and convey it along the plain of the fabric to an outlet. The drain needs to act
as a filter to keep soil particles out of pores and prevent clogging. An example is shown in
Figure 18.
Figure 18 - Geotextile drain behind a retaining wall. A similar arrangement may be used
behind bridge abutments
Figure 19 shows a typical arrangement for a collector drain and carrier pipe located between
two tracks. The subsurface water is collected by the collector drain between the two sumps
shown. The collector drain then conveys the water to the downstream sump where it can enter
the carrier pipe and be removed without any risk of it re-entering the subgrade. See Figure 34
for an example of this system used in yard drainage.
The main purpose of inlet and outlet protectors is to reduce erosion. Where outlet velocities are
expected to be high, some form of energy dissipater should be installed. In addition, where the
sediment load of the water being discharged from a drainage system is high, a silt trap should
be installed (see Figure 20 below).
Figure 20 - Typical silt trap installed in drains with high sediment loads
Some typical examples of inlet and outlet protection are the following:
NOTE: As mentioned in Figure 25, on the downstream side of the outlet, water getting
under the headwall structure and causing scouring and the eventual washaway of the
headwall is a problem that cannot be overlooked. The best way to help prevent this
occurring is to provide a cut-off wall at the end of the headwall (see Figure 23 for an
example).
Proper drainage design, using the design process detailed in this section, may allow problems
to be discovered early and enable easier construction.
This section discusses the design process from the initial concept through to the detailing of the
drain capacity and components required.
"Track drainage is to be designed to capture water flows calculated in accordance with this
standard.
The design, maintenance and construction of track drainage shall only be done by an
authorised engineering organisation (AEO)."
"The design average recurrence interval (ARI) for track drainage (excluding siding track
drainage) shall be 50 years.
Siding track drainage shall have a design average recurrence interval (ARI) of 25 years.
The minimum design life of all track drainage components shall be 50 years.
The following configurations are not approved for track drainage on the RailCorp network:
Drainage cell systems shall only be used with the approval of the Lead Civil Engineer, ASA."
Cess drains
"The flow capacity of the open channel cess drain shall be greater than the peak flow rate.
For ease of maintenance, over-sized channels can be adopted to allow a certain degree of
sediment build up to occur and still work effectively."
Figure 26 shows the dimensions of two channel types, trapezoidal and rectangular. If concrete
is used to form a channel then the dimension ‘B’ may be reduced to zero thereby producing a
vertical face.
The location of the open channel shall comply with the formation shoulder distance specified in
ESC 410 Earthworks and Formation.
Where track drainage is incorporated within existing track constraints (for example, cuttings,
between tracks) and the shoulder distance cannot be achieved, open channels shall be at an
adequate distance from the track to prevent ballast spill into the channel area. In this case, the
edge of the channel closest to the track shall be a minimum of 2800 mm from the design track
centre. This minimum edge distance shall be increased as required based on track
configuration (rail size, sleeper type, ballast depth) and track curvature.
The top of lined channels shall be no higher than the top of the adjacent track formation(s).
With multiple tracks, drainage is to be provided by sumps and pipes in the ‘six-foot’ between
each alternate track.
Catch drains
"Catch drains shall be provided on the uphill side of a cutting to divert water from the cutting
face. Drains shall be 1000 mm minimum from the top edge of the cutting.
Catch drains shall be provided on the downhill side of embankments to divert water from the
embankment toe. Drains shall be 1000 mm minimum from the toe of the embankment.
Catch drains may be either lined or unlined depending on the local soil conditions. Half round
pipes or dish drains may be used instead of lined channels.
The location of drains shall comply with the requirements of ESC 410."
Mitre drains
"Where mitre drains are required, they shall be provided at regular centres with a drain located
approximately every 100 m maximum. They shall be installed at the ends of cuttings.
The ends of mitre drains shall be splayed to disperse water quickly and reduce scouring."
• pipes
• aggregate filter
"Subsurface drains are used where adequate surface drainage cannot be provided due to some
restriction or lack of available fall due to outlet restrictions.
Subsurface drainage shall be provided in locations where the water table is at or near
earthworks level. Subsurface drainage shall also be provided where artesian conditions exist to
relieve water pressure.
Subsurface drainage shall be provided along the cess, between, across, or under tracks as
required.
Subsurface drainage systems shall be designed to transfer surface runoff, ground water and
seepage, and water collected from other drainage systems to which the new system is being
connected.
If a drainage system is required to remove ground water and seepage, a detailed hydrological
and geotechnical investigation is required to determine the volume of water for the sizing of
drains.
The volume of water from other systems is determined from the outlet capacity of that system."
Pipes
"The capacity of the proposed drainage system shall be determined using the peak flow rate
calculated by the Rational method, with adjustment made for subsurface water and water
collected from other systems. Alternatively, the Hydrograph method may be used. The peak
flow velocity within the pipe shall be less than the manufacturer recommended maximum limits.
Pipes larger than the design size may be adopted to reduce the likelihood of the system
becoming blocked and also enable easier cleaning. The minimum pipe diameter shall be 225
mm (for ease of maintenance).
The gradient of pipes shall be 1 in 100. Where this is not achievable, pipes shall be laid at 1 in
200 minimum.
Depth of pipes under the track shall be 1600 mm minimum from top of rail to top of pipe or pipe
encasing.
Depth of pipes running parallel to the track shall be 600 mm minimum from the design cess
level to top of pipe.
At sites where it is not possible to comply with the pipe depth requirements stated in this section
and achieve an effective drainage system design, the pipe depth may be reduced to the
following:
• 1200 mm minimum from top of rail to top of pipe or pipe encasing for under track pipes
• 300 mm minimum from the design cess level or 1000 mm from top of adjacent rail
(whichever produces the lowest invert level) to top of pipe for pipes running parallel to the
track
• reinforced concrete
• steel
Approved proprietary products shall be designed and installed in accordance with the
manufacturer’s specifications.
Steel pipes shall be designed to mitigate the effects of electrolysis and stray track currents.
Designs shall be in accordance with the requirements stated by the Lead Electrical Engineer,
ASA.
Both slotted and unslotted pipes may be used depending on the system type and its means of
collecting and carrying water.
Slotted pipes are preferred, as these do not rely on surface flow between sumps to collect
water.
Slotted pipes and perforated pipes shall not be used for under track pipe work.
Minimum strength requirements are detailed in Table 1. The strength of reinforced concrete and
fibre reinforced concrete pipes shall be determined in accordance with AS/NZ 3725.
If railway live loads are applicable, then the pipes shall be designed for train loads specified in
ESC 310 Underbridges. AS 5100 does not provide guidance on a suitable impact factor for
railway loads distributed on fill. A dynamic load allowance (DLA) shall be adopted which varies
linearly from 1.5 at 0.3 m depth to 1.0 at 3.5 m depth or greater (where the depth is measured
from the top of rail).
Where slotted pipes are used, strength reductions for the slots shall be included in the design
and shall be based on manufacturer’s recommendations.
Pipes located under sections of the rail corridor used for road vehicle access along the rail
corridor, shall be designed for the R20 design load. See Appendix A for details of the R loading
configuration.
Refer to CV 0205421 – Track Drainage - Typical Sections and Notes for details of typical cross
sections."
After the layout and required capacity of the drain has been established, it is necessary to detail
the various items that will make up the system. This enables the correct components to be
ordered quickly in the construction phase.
Trenching
"The minimum trench width shall be pipe diameter plus 150 mm on each side.
For longitudinal drains located either within 2500 mm of the track centre line or between tracks
where track centres are less than 6000 mm, the minimum trench width shall be pipe diameter
plus 100 mm on each side.
For pipes running in parallel, a clear space of 300 mm between pipes shall be provided to allow
compaction to take place.
Trenches shall be backfilled with suitable material and compacted to not less than 95%
maximum dry density as determined in Test 5.1.1 and Test 5.3.1 (Standard Compaction) of AS
1289.
Reference shall be made to ESC 540 for further requirements on trenching within the rail
corridor."
"When determining the class of pipe to be specified in a subsurface drainage system the
bedding type assumed shall be appropriate for what can be achieved during construction. Most
under track drainage is constructed during track possessions where the more stringent
requirements for placement and compaction of bedding material cannot always be satisfied.
For under track crossings to be constructed during a limited track possession, type ‘U’ bedding
in accordance with AS 3725 shall be used in design."
"Sumps are required as access points for surface water and for maintenance of the drainage
system.
Sumps shall be spaced at 30 m to 50 m centres, except through platforms where spacing shall
be 20 m to 30 m centres. Reduced centres may be applicable in the 6-foot between tracks to
account for track curvature.
The minimum internal plan dimensions of a sump shall be 600 mm x 600 mm for depths greater
than 1 m. Minimum internal plan dimensions of 450 mm x 450 mm are acceptable for depths
less than 1 m.
Precast sumps with risers used to accommodate varying depths shall be adopted in preference
to cast in-situ sumps.
All sumps shall be provided with a minimum Class D grate in accordance with AS 3996. All
grates shall be galvanised. In addition, for all sumps within 2800 mm of a track centre, or where
site restraints dictate the possibility of ballast covering a pit, a ballast cage (lobster pot) shall be
provided in accordance with CV 0400998. Ballast cages shall be positioned to the outside
edges of the sump. When installed the cages shall not extend above the top of sleeper level.
For locations where access for off-track equipment is limited, sump grates shall be designed for
easy manual removal; for example, grates on a sump shall be manufactured in two sections
rather than one. These grates shall be lockable.
Where the internal sump height (including risers) exceeds 1200 mm, the following shall be
provided:
• step rungs shall be provided at 300 mm vertical centres. If possible, the step runs shall be
located on the face looking at the oncoming train traffic (that is, either Sydney face for the
down track or Country face for up track)
• sump riser heights shall be selected such that step rungs do not come within 50 mm of the
top or bottom of the riser
Where sumps are located in the 6-foot between tracks, the internal dimensions of the sump
shall be increased to a minimum of 600 mm wide (perpendicular to the tracks) x 900 mm to
accommodate inspection access. The width shall be the maximum size available to enable
proper placement of the sump and ballast cage (lobster pot) without clashing with the sleepers.
The internal dimensions of the sump in areas beyond the 6-foot, shall be increased to a
minimum of 900 mm x 900 mm to accommodate inspection access.
Sumps shall be set out to ensure the minimum amount of pipe cutting is required during
installation (that is, whole pipe lengths shall be used between pits).
Only wet cast concrete pits are permissible. Dry cast concrete pits are not permitted."
Flushing points
"Ground water and seepage (subsoil) drains shall have flushing points. Flushing points shall be
provided generally at intervals of not more than 60 m and at abrupt changes of grade and
alignment. On long and straight pipe runs (for example, straight pipe lengths of 1 km or more)
flushing points can be installed at a maximum interval of 120 m.
Flushing points shall consist of ‘T’ or ‘L’ connections in the subsurface pipe, with pipe
connections extending to the surface for regular flushing with water to clear the subsurface
drain of fouling material."
Aggregate drains
"Aggregate drains are only suitable for use where a small flow of ground water or seepage is
expected. They are not to be used for the collection of surface water.
The design of permeable drains may be carried out using the Darcy-Weisbach equation.
The permeability of clean gravel can range from 0.01 to 1.0 m/s. The aggregates used in
aggregate drains are either 20 mm nominal diameter or 53 mm diameter (ballast). The
permeability of these aggregates is as follows:
Aggregate drains shall be lined with permeable geotextile fabric in accordance with
Section 7.8."
A minimum 100 mm layer of aggregate may be placed on top of the geotextile to protect it from
damage.
Geotextiles
"The main purpose of a geotextile used in subsurface drainage is to act as a filter, which helps
prevent silting--up of the drain it is protecting. The selected geotextile is to achieve the following
characteristics:
An appropriate geotextile filter fabric shall be selected which satisfies both the filtration criteria
suited to the in-situ soil and the site drainage conditions.
The selected geotextile is to exhibit the following mechanical properties as a minimum when
tested in accordance with AS 3706:
• G Rating of 2000
Geotextiles used in subsurface drainage shall fully line the trench and have a minimum lap at
the top of 200 mm but not exceeding 50% of the width at the top. The wrapped trench shall be
covered by a minimum of 100 mm of aggregate."
Some typical examples of inlets and outlets are rip-rap, grouted rip-rap, sand bags, wire baskets
(that is, gabions and reno mattresses), revetment mattresses, precast concrete units, and cast
in place concrete. Example diagrams can be found in Section 5.2.4.
"To prevent soil erosion, all inlet and outlet points shall be provided with an appropriate size
concrete headwall to suit the ground profile. Refer to CV 0497068 and CV 0497069 for standard
concrete headwalls.
These drawings are not suitable where the face of the headwall is closer than 2150 mm to the
track centreline. These drawings are also not suitable where railway surcharge applies to the
headwall. In these instances, the concrete headwalls shall be designed by the AEO to provide
strength and stability to resist the applied loadings to AS 5100.
The ground covering at the pipe exit points shall be capable of withstanding the exit flow rates.
The maximum permissible velocities provided in Table 1 shall be used as the ground covering
limits.
Where the sediment load of the water being discharged from a drainage system is high, a silt
trap shall be included."
• identification of the problem and therefore the drainage objective. That is, what area is to
be drained and for what reason.
• determination of the information required. That is, location, outside influences, fall
available, possible outlets, access, site safety requirements, and so forth)
All available information from adjacent sites or the locality in general should be studied
before embarking on any fieldwork. This will often save unnecessary fieldwork or may point
out particular problems or aspects that should receive special attention.
Included in this stage should be a full service search. This involves the check of the
location of both TfNSW and public services. This may also involve site inspections with
representatives from various bodies to accurately locate services, the position of which
should then be marked, either on a plan or pegged.
Other types of information that may be of use are aerial photographs, maps (topographic,
geological, soil, and so forth), charts, and meteorological and hydrological information.
• site inspection
A checklist should be prepared prior to the actual investigation so that the maximum
amount of information may be extracted from the site in a minimum time (see the form in
Appendix C).
Items that should be looked at during a site inspection include the following:
o access to and from the proposed site and any possible restrictions
o type and location of any existing drainage systems and any possible reasons for its
failure
o any other likely drainage outlets. Determine the outlet conditions and any likely
restrictions because these may affect the design of the drainage system.
o adjacent structures that may impact on the drainage design, or where the drainage
design may cause instability to the structure
The catchment area for the drainage system needs to be estimated during the site
inspection. This may be checked by comparison with maps of the area.
A further inspection may be required at a later stage so that the area may be surveyed to
establish the available fall and invert level for the inlet and outlet.
The type of system chosen for each location is dependent on the site restraints, water source,
track structure, and long-term maintenance issues. The two types of drainage systems are
surface and subsurface.
If possible, surface drains should be used in preference to subsurface drains since surface
drains are easily inspected and maintained.
Note: care needs to be taken to ensure that the right drainage system is designed for
each location. For example, using a slotted system to drain surface run-off that could
have been collected by sumps may not be the best solution. This could lead to a
quicker failure of the system by allowing an easier route for water to pass (seep) into
the formation.
The next step is to estimate the quantity of water that the drain will need to carry, so that the
size of the drain and its various components may be determined.
The quantity of water (QPF) that the drain is required to carry generally is given by Equation 1.
QPF = QR + QS + QC
Where:
3
QPF = water quantity (m /s or l/s)
3
QR = run-off quantity collected (m /s or l/s)
3
QS = subsurface water quantity intercepted (m /s or l/s)
3
QC = collected water quantity from a drain of a connecting system (m /s or l/s)
The calculated quantity (QPF) represents the peak flow that the drain will be required to carry, for
a short time only.
The quantity (QR) is calculated for the catchment size and critical rainfall duration by using the
Rational method. Alternatively, the Hydrograph method may be used.
The value of intercepted subsurface water 'QS' is difficult to determine. If a drainage system is
required to remove intercepted subsurface water, a detailed hydrological investigation or
geotechnical investigation, or both is usually required.
The volume of water conducted from other systems, 'QC', is estimated from the outlet capacity
of the system to which the new system is being connected. Provided the catchment area, drain
size, and slope are known (or can be measured), the maximum value of 'QC' can be determined
using the Rational method. This information may also be available from the authority owning the
asset (such as a council).
If the connecting system is a complex network of drainage, a detailed study may be required.
Account needs to be taken of all water flowing onto the rail corridor from adjoining properties
and streets.
If incorporating computer modelling in the design process, then a range of storm events
representing varying rainfall duration needs to be investigated. The drainage design will be
carried out adopting the critical rainfall event.
Hydrology and hydraulic computer packages can be utilised for the design of track drainage.
The following procedure deals with hand calculation methods only.
The Rational method is detailed fully in Australian Rainfall and Runoff (AR&R) published by the
Institution of Engineers, Australia.
The AR&R publication recommends the following steps for flow rate determination for sites in
eastern New South Wales.
The form in Appendix D breaks down these steps and can be used as a calculation sheet.
1. calculate the critical rainfall duration (tC) for the area under investigation
Two methods may be adopted to calculate the critical rainfall duration. These methods are
the following:
• equal area stream slope - recommended for hilly or undulating sites as it gives a more
realistic flow response time (refer to AR&R for this procedure)
Where:
The catchment areas required for peak flow rate calculations need to be determined
using (in order of preference) site survey, site measurements, or suitably scaled
topographic maps.
This step comprises of looking up a series of basic rainfall intensities, skewness factors, and
geographical factors from contour style maps found in Volume 2 of the AR&R guide.
These values can be plotted on a log-Pearson Type III diagram (LPIII) or incorporated in
interpolation formulas found in Book 2 of AR&R volume 1.
From either of these two methods the 50 year design rainfall intensity ‘Icr,50’ for the critical
duration tC can be determined.
3. determine the 50 year run-off coefficient (C50) for the geographical area by determining the
following:
• read the 10 year run-off coefficient value (C10) from Figure 1.1 in Volume 2 of the AR&R
• geographical zone B is adopted from Figure 1.2 (AR&R) – for Sydney Metropolitan Area
• interpolate or calculate the 50 year frequency factor FF50 from Table 1.1 (AR&R) based
on site elevation
Where:
3
Q50 = peak flow rate (m /s) for ARI = 50 years
The peak flow rate is used in determining how much water is likely to rain onto a catchment and
therefore enabling the sizing of the drainage system under consideration.
For surface drains, 'QS' and 'QC' can usually be neglected. In this case, Equation 1 becomes QPF
3
= QR = Peak flow rate (m /s).
Example 1
3
A rainfall run-off quantity of 0.15 m /s was calculated to act on a catchment for the 50 year ARI
critical duration storm (from the 'Rational method'). There is no subsurface water intercepted,
3
but a nearby stormwater pipeline enters the channel and adds 0.07 m /s. What is the total water
quantity the channel will need to be designed for?
Solution 1
The design flow capacity can be determined from Equation 1.
3
QPF = QR + QS + QC = 0.15 + 0 + 0.07 = 0.22 m /s.
3
The channel will need to be sized to take a 0.22 m /s flow rate or greater.
Where:
3
Q = flow rate or capacity (m /s)
R = A/P where P = wetted perimeter (that is, the surface in contact with the water)
0.67
If X = A x R then Equation 4 becomes:
0.5
Q = (1/n) × X × S
See Table 7 for values of 'X' for various channels. See Figure 26 - Channel types for a review of
the trapezoidal and rectangular channel types referred to in Table 7.
Note: Smaller channels tend to become blocked with built up sediment very quickly.
The following are typical examples of calculations to determine the capacity of an open channel.
Example 2
For a trapezoidal channel (shown in Figure 27 below) with a slope of 1 in 200 and a roughness
coefficient 'n' of 0.030. Calculate the channel capacity using a) Equation 4 and b) Equation 5
and Table 7:
n = 0.030
R = A/P
P = 2 ×√((300)×2+(450)×2)+600
P = 1682 mm
P = 1.682 m
R = 0.315/1.682
R = 0.187 m
0.67 0.5
Q = 1/n × A × R S
0.67 0.5
Q = 1/0.03 × 0.315 × (0.187) × (0.005)
3
Q = 0.243 (m /s)
n = 0.030
Equation 5
0.5
Q = 1/n ×X × S
0.5
Q = 1/0.03 × (0.103) × (0.005)
3
Q = 0.243 (m /s)
Example 3
Check that the channel in Example 2 has sufficient capacity to cater for the design storm as
calculated in Example 1.
Solution 3
3
The channel capacity 'Q' of 0.243 m /s (Example 2) is greater than the design storm flow rate
3
'QPF' of 0.220 m /s (Example 1). Therefore, it has sufficient capacity.
V=Q/A
Where:
V = velocity (m/s)
3
Q = flow rate (m /s) calculated using Equation 1
2
A = area of selected channel (m )
Example 4
Calculate the flow velocity of water within the channel in Example 2.
Solution 4
3
Q = 0.22 m /s
2
A = 0.315 m (from example 1 - assumed flowing full)
Lining a channel changes the roughness coefficient 'n', and therefore the capacity of the
channel may be altered either up or down (See Table 3, Table 4, Table 5, and Table 6).
A lining is selected such that the allowable velocity for the type of lining is greater than that
calculated in step F. This is used as a first trial value.
Example 5
The channel in example 4 is lined with grass covering. Is it sufficient to withstand the flow
velocity?
Solution 5
Velocity of water in channel = 0.69 m/s (solution 4).
The maximum permissible velocity of grass lining = 1.8 m/s (Table 8).
Therefore, grass has the required resistance and the lining is sufficient.
Example 6
Calculate the required channel size and lining type given that the required capacity of the
3
channel is 0.40 m /s. The existing soil is clay.
Solution 6:
Trial 1:
3
Step A: No subsurface water or connecting system. So QPF =0.40 m /s
Step G: Clay has permissible velocity capacity of 0.9 m/s (Table 8) which is less than the design
flow of 1.48 m/s. Could modify size or change lining. Opt for a change of lining type to grass
covered (capacity 1.8 m/s).
Trial 2: Try lining with higher permissible velocity – say grass lining
3
Steps A, B & C: QPF =0.40 m /s. n=0.024 (Table 7). S=0.01
2
Step D: Same channel no. 14 from Table 7. A = 0.270 m . X = 0.085
0.5 3
Q= (1/0.024) × (0.085) × (0.01) = 0.35 m /s (Equation 5)
3
< 0.4m /s therefore no good. Could modify size or change lining.
Trial 3: Try smoother lining, with high permissible velocity - say asphalt
3
Steps A, B & C: QPF =0.40 m /s. n=0.013 (Table 7). S=0.01
2
Step D: Same channel no. 14 from Table 7. A = 0.270 m . X = 0.085
0.5 3
Q = (1/0.013) × (0.085) × (0.01) = 0.65 m /s (Equation 5)
3 3
Step E: Channel capacity 0.65 m /s > design capacity 0.40 m /s. Okay.
Step G: Asphalt has capacity of 3.0 m/s (Table 8) which is greater than the design flow of
1.48 m/s. Therefore, it is satisfactory.
Alternatively, the capacity of the pipe can be found by using Manning's Equation (Equation 4).
Notes to Table 9
4. PVC pipes are not to be used for track drainage design. They are included in
Table 9 for assessment of existing pipe systems.
3
5. To convert m /s to l/s multiply by 1000 (that is, 1000 litres = 1 cubic metre)
6. The values of Manning's roughness co-efficient used in the calculations for the
values given in Table 8 are as follows:
• concrete: n = 0.011
• P.V.C.: n = 0.009
If pipes are within a 45 degree projection of the outside of the sleeper (in any direction), then
railway loading needs to be included. Dynamic loads will also be applied – Refer to
Section 6.1.2.
If pipes are situated within a 45 degree projection of the outside of an access road (in any
direction) then the loads applicable to the access vehicle need to be included. Dynamic loads
will also be applied – Refer to Section 6.1.2.
Pipe strength is also highly dependent on the type of trench excavation, fill material, and
compaction technique. When determining the class of pipe to be specified in a drainage system,
type 'U' bedding should be assumed, even if better bedding is specified on the drawings. Most
track drainage is constructed during track possessions where the specified placement and
compaction of bedding material cannot always be achieved.
Where slotted pipes are used, strength reductions for the slots need to be included in the design
and will be based on manufacturer’s recommendations.
Manufacturer supplied computer software is acceptable for this purpose of pipe strength design,
provided it is in accordance with AS 3725.
Complete example:
Example 7
3
A rainfall run-off quantity of 0.10 m /s was calculated to act on a catchment for the 50 year
average recurrence interval (ARI) critical duration storm (from the Rational method). There is no
subsurface water intercepted, but a nearby stormwater pipeline enters the system and adds
3
0.02 m /s. What size reinforced concrete pipe is required to satisfy flow requirements?
Solution 7
Step F: Flow rate within the pipe V=Q/A = 0.12/(3.142 × 0.375 × 0.375/4) = 1.1 m/s which is less
than the acceptable limit for concrete (6 m/s). Therefore, okay.
The capacity of an aggregate drain may be determined using Darcy's equation (Equation 7).
Q=k×i×A
Where:
3
Q = flow (m /s)
The permeability of clean gravel can range from 0.01 m/s to 1.0 m/s. The aggregates used in
aggregate drains are either 20 mm nominal diameter or 53 mm diameter (ballast). The
permeability of these aggregates is:
Q=K×A
Table 10 gives values for 'K' for use in Equation 8 to determine the capacity of aggregate drains.
Example 8
3
If Q = 0.01 m /s or 10 l/s an aggregate drain using 20 mm aggregate at a slope of 1 in 200, what
size drain is required?
Solution 8
Therefore:
A = 0.01 / 0.00075
2
A = 13.3 m
For the same flow using 53 mm aggregate at a slope of 1 in 200, the area required is:
A = 0.01 / 0.002
2
A = 5.0 m
"When selecting a pipe, the type of environment (whether, the water is abrasive, acidic or
alkaline) shall be considered. The manufacturer's specifications shall be referred to in relation to
the various environmental conditions and circumstances for which the pipe is deemed to be
suitable.
The possible effects of non-standard ballast profiles, other track infrastructure and track
geometry shall be considered.
The configuration issues arising from placing straight pipes alongside curved tracks shall be
considered (for example, this situation may require reduced sump centres).
The permanent effects of the drainage system located alongside existing structures such as
overhead wiring structures, retaining walls, platforms, embankments, shall be taken into
account. The likelihood of destabilising an existing structure during the excavation stage shall
also be identified and accounted for.
Potential conflicts with existing services shall be considered. Service searches shall be
conducted and the locations of these services indicated on the design documentation. Service
searches shall be supplemented by trial pits to ensure the accuracy of the service search
information and determine the depths of the services."
One important consideration is that each site needs to be assessed on its own merits. No two
sites are the same. This will be taken into account when selecting the site protection,
equipment, and personnel required for each particular site.
This section discusses the various steps involved in the construction of both surface and
subsurface drainage systems.
i. stakes, spikes, shiners (small reflective metal discs), marks, or crosses set at the surface
on an offset from the desired centre line
ii. stakes set in the trench bottom on the pipeline as the rough grade for the pipe is completed
iii. elevations given for the finished trench grade and pipe invert while laying the pipe or
excavating the trench is in progress
Of these three methods, method (i) is the most commonly used for track drainage.
Method (i) involves stakes, spikes, shiners, or crosses being set on the opposite side of the
trench from where the excavated material is to be cast at a uniform offset, in so far as
practicable, from the drain’s centreline. A table known as a cut sheet is prepared. This is a
tabulation of the reference points giving the offset and vertical distance from the reference point
to either: the trench bottom, the pipe invert, or both. When laying the pipe it may be more
practical to give two vertical distances, one to the trench bottom (excavation depth), and one to
the top of the pipe, which is generally easier to measure to than the pipe invert. The grade and
line may be transferred to the bottom of the trench by using batter boards, a tape and level, or
patented bar tape and plumb bob unit.
This method may be adapted to suit. For example, it is common practice to have the proposed
route surveyed with the reference points marked on the datum rail (either the down rail or the
low rail on a curve). The offset and vertical height may be easily transferred from the rail by use
of a straight edge, spirit level, and tape (see Figure 28).
Figure 28 - Method of measuring the depth of a trench and offset to pipe centreline
If the track is on a constant grade that is suitable for the pipeline and trench, this grade may be
adopted. This gives a constant vertical depth from the datum rail to the trench bottom and
pipeline, making construction and grade control much easier.
Another method of controlling the line and grade is the use of lasers. A laser beam is passed
through the centre of the pipeline at the desired grade. It strikes opaque targets attached to the
end of the pipe, and the pipe may then be either lifted (packed) or lowered until the laser passes
through the centre of the target.
• clearing
The success of the construction phase depends to a great degree on the thoroughness of the
planning and the execution of the site preparation work.
7.3. Excavation
With favourable ground conditions, excavation can be accomplished in one simple operation.
Under conditions that are more adverse, it may require several steps, such as clearing, rock
breaking, ripping or blasting, and excavation. When excavating for a pipeline, the trench at and
below the top of the pipe should be wide enough to ensure adequate compaction on the sides
of the pipe can be achieved. The minimum width on either side of the pipe will be in accordance
with Section 6.1.2.
The amount of excavation and the types of equipment required may vary, so each site needs to
be assessed on its merits to determine the type and quantity of equipment necessary.
Excavation near structures or platforms will comply with TMC 411 Earthworks.
Particular conditions that should be taken into account when selecting equipment are the
following:
• site access
• whether the plant item required has to be floated to the site (if so the offloading conditions
and a suitable area should be checked)
• backhoe
• tiltable dozers
• graders
• tracked excavators
• hydraulic excavators
7.4.1. Requirements
The main purpose of surface drains is to remove surface water from near the tracks and
disperse it as quickly as possible. To do this, the drainage trench or ditch should be constructed
at a uniform even grade, with no low sections where water may pond and seep into track
formation, thereby defeating the purpose of the drainage system.
The grade of the drainage trench should be a minimum of 1 in 200 where practicable. Flatter
grades may be used but require more regular inspection and maintenance, since they tend to
become blocked with sediment more quickly than drains with steeper grades.
Where the velocity of the water is greater than that shown in Table 8 in Section 6.4, some form
of scour protection is required, for example, lining the channel. Where doubts exist as to the
erodability of a soil, the Lead Civil Engineer at ASA needs to be consulted. Where any surfaces
are cleared of vegetation, these areas will be re-vegetated at the end of construction, to prevent
unnecessary build-up of silt in nearby drains.
• Survey the proposed drainage route. This may be carried out during the preliminary
investigation.
• Establish and mark out reference points for use during construction. Marking out may
consist of paint marks on the datum rail or star pickets. The interval used for the reference
marks depends on the length of the drainage system. For example, for a short drain the
interval may be five metres.
• Clear the site. This should be part of any site preparation work carried out. This may
involve relocation of signal troughing, clearing vegetation, and so forth.
• Excavate to required level. When excavating the trench, use a bucket width equal to the
width of the trench base, then add a batter to the sides of the trench formed. Monitor
excavation with the method described in Section 7.1. Once the trench has been
constructed, level and compact the trench base making sure that no low points exist.
• Check for risk of erosion. If this is expected to be high, the drain may require lining.
Note: It is good practice to work from the lowest to the highest point. That way, if work
is interrupted for any reason, at least part of the drainage system will function correctly
if it rains before completion.
• longitudinal drains
• lateral drains
• blanket drains
• sump installation
ii. establish the reference points. These may be paint marks on the rails or star pickets. The
purpose of these marks is to provide points from which the depth of the trench and pipe
invert level may be measured accurately. (See Section 7.1).
iii. excavate to the desired level. The type of equipment used to excavate the trench differs
from location to location, depending on such parameters as access, material, volume to be
excavated, and clearances for the safe operation of equipment.
iv. the depth of the excavation depends on the pipe location, and outlet and inlet
requirements. For pipes running parallel to the track, the minimum pipe cover is to be
600 mm below the design cess level. Where this is not feasible, the minimum pipe cover is
to be 300 mm below the design cess level or 1000 mm below the adjacent rail level
(whichever produces the lowest invert level). The design track formation profile will be as
set out in TMC 411. The width of trenches should only be as wide as necessary to ensure
proper installation and side compaction. The minimum width will be pipe diameter plus
150 mm on each side. For longitudinal drains located either within 2500 mm of the track
centre line or between tracks where track centres are less than 6000 mm, the minimum
trench width will be pipe diameter plus 100 mm on each side. See Figure 29 for a visual
representation of these width requirements. A vertical sided trench with no support may
only be suitable for a shallow trench. Geotechnical advice may be sought to determine if
shoring or benching is required for certain ground conditions or deeper trenches.
The method of installing this type of subsoil drain depends on the type of subsoil and other
conditions encountered, such as the following:
i. impervious soil - aggregate filled excavation (that is, most clays are relatively impervious).
Refer also to Figure 15.
a. lay the geotextile in the bottom of the trench. Where joints need to be made in the
geotextile a minimum overlap of 1 m should be made.
b. place a layer of aggregate in the bottom of the trench approximately 50 mm thick. The
aggregate used for this should be 20 mm nominal diameter aggregate.
c. lay the pipe sections, one section at a time, on top of the aggregate
e. check and adjust the pipe level and grade if necessary by packing aggregate under
the pipe
f. place aggregate around and over the pipe, tamping the aggregate on the sides of the
pipe as the trench is filled. Once the pipe is covered, complete the filling of the trench
compacting the aggregate in layers no greater than 150 mm thick, using a vibrating
plate compactor or similar.
g. fold geotextile over the top of the trench, ensuring that the ends are overlapped a
minimum of 300 mm
h. place a minimum 100 mm thick layer of aggregate over the geotextile and grade the
surface
i. pack knockouts from the inside of the pits using sand or cement mortar (or geotextile if
detailed in this manner)
j. complete associated works (for example, pit lids or pots, ballasting, and so forth)
ii. pervious soil – aggregate filled excavation (for example sandy soils). Refer also to
Figure 16.
When laying a drain in pervious soil, it is necessary to place an impervious layer in the
base of the trench. Typical impervious layers are concrete, cement or lime stabilised fill, or
clay fill. The impervious layer is to be 100 mm thick at the edges of the trench and slope
towards the centre of the trench, where it is to be 50 mm thick. Once an impervious layer is
installed, the remaining construction steps are the same as steps '(a)' to '(j)' for drains in
impervious soils above.
Sometimes it is beneficial to wrap the pipe inside a geotextile rather than around the
outside of a trench. In this case, repeat the procedure of point 'i' with the exception of: step
'a', the geotextile is wrapped and lapped a minimum 300 mm around the pipe and step 'g'
is not required.
a. place bedding sand or roadbase in the trench and compact as per the design
b. lay the pipe sections, one section at a time on top of the bedding
c. check and adjust the pipe level and grade if necessary. Adjust pipes by removal of
base material or ramming additional bedding under the pipe. Alternatively, slings may
be used around pipe ends.
e. place side zone material and compact to the required relative density as shown on the
drawing
f. place a 150 mm maximum layer of material over the pipe and use a vibrating plate
compactor or similar to compact the fill to the required relative density. Repeat
backfilling and compaction until fill is at final level.
g. pack knockouts from the inside of the pits using sand or cement mortar (or geotextile if
detailed in this manner)
h. complete associated works (for example, pit lids or pots, ballasting, and so forth)
In some locations, a subsoil drain cannot be located deep enough to prevent it being
disturbed by track maintenance machines. In this case, the pipe may be wrapped in
geotextile, and then placed in the trench on a bed of aggregate to allow any adjustments to
the level and grade of the pipe to be made. The trench may then be filled with a suitable
pervious fill and compacted in layers.
Where isolated pockets of ash are encountered, an impervious membrane may be placed
in the trench before the fabric is laid. This membrane should cover the ash pocket and
extend approximately 2 m either side of it. The rest of the drain is constructed as set out in
point 'i' above. This method is used only where the soil on either side of the ash pocket is
impervious; otherwise, the drain is constructed as per point 'ii' above. If an impervious
membrane is not available, the section of the drain above the ash pocket may be
constructed as for a drain in a pervious soil. See Figure 30 for the treatment of ash
pockets.
For embankment drainage, a lateral trench is excavated to the desired level, using a backhoe or
similar. Once the trench is excavated to the desired level, the base is graded to fall away from
the embankment centre. The construction methods are the same as for longitudinal drains
(point 'iv' in Section 7.5.1).
• excavate. For embankment widening or slip repair, steps should be cut into the existing
embankment (see TMC 411 Earthworks)
• level and compact the base with a fall away from the embankment centre
• lay out the geotextile. Any joints should have a minimum 1 m overlap.
• fold sides of geotextile up over the top of the aggregate, then cover with a layer of
geofabric over the top of the aggregate
• place riprap (100 mm to 150 mm stone) over the exposed face of the drainage blanket as
protection
The most commonly used vertical drain is used to drain water from behind retaining walls and
bridge abutments. This drain consists of a geotextile layer placed at the back of the wall and
connected to a pipe at the base of the wall.
Water reaching the geotextile can flow along the plain of the fabric that is down the back of the
wall, and is then removed by the pipe at the base. This may also be combined with horizontal
layers of geotextile to collect water seeping through the embankment or backfill behind the wall,
which is conducted towards the vertical drain, and then to the carrier pipe and removed.
This type of drain may be placed during construction and backfilling, or an area behind the wall
can be excavated for their installation.
"Sumps shall be spaced at 30 m to 50 m centres, except through platforms where spacing shall
be 20 m to 30 m centres. Reduced centres may be applicable in the 6-foot between tracks to
account for track curvature."
At the location at which a sump is to be placed, the trench is widened and deepened to
accommodate for the sump. The base of the trench is then levelled and covered with a layer of
compacted sand or road base, which is a minimum 150 mm deep. This layer may be added to
so that the sump is positioned at the correct height.
Prior to placing the sump, the wafer of concrete covering the inlet and outlet is knocked out to
approximately the desired size. Drains using slotted pipes and geotextile are connected to
sumps as shown in Figure 31 below. Once the pipe is in place, any remaining gaps between the
pipe and the sump are grouted. The trench is then filled and compacted.
• pipe jacking
• tunnelling
• augering
• cast in place
These are seldom used for track drainage, and therefore are not covered in this document.
Inlet and outlet protection is to be installed as shown on the drawings and in accordance with
manufacturers’ instructions.
8.1. General
Good track maintenance and effective track drainage are closely associated. The stability and
condition of the track and the formation is intimately related to the effectiveness of the drainage
systems.
The consequences of poor or blocked drains can range from small areas of foul ballast to large
washaways or embankment failures.
Water needs to be drained away from the track as quickly as possible, so that it does not affect
the track stability.
Where sub-drainage work has been carried out, the outlets need to be kept clean to allow water
to run-off.
The cesses in cuttings need to be kept formed so that the water will run at the toe of the batter.
On banks, the cesses need to be graded away from the track.
Where bog holes exist, ample metal ballast should be kept on hand to replace the continued
loss of metal through fettling. The attention of the team manager needs to be drawn to this so
that they can have sub-drainage work carried out, when practicable.
Effective drainage is a major factor in minimising maintenance work necessary on welded track.
• Allow water to drain away. It is important that water be drained away from the track
structure as quickly as possible.
• Keep water flowing. If there are low spots in the drainage path, water will pond and will
saturate the sensitive track structure and weaken the material in that area.
• Control the path of water. Water should not be permitted to flow from the drain into areas
that will be damaged by water, for example, flowing into sinkholes or from the cess back
into the track because of debris in the cess.
• Control the flow rate of water. Water should not flow too slowly as to cause saturation
(ponding) or too rapidly as to cause erosion.
• Reduce erosion. Certain materials are prone to erosion and require additional treatment,
otherwise drains block rapidly, or slopes become undercut and cause instability.
• Keep water as far away as possible. Where the countryside is very flat and recommended
grades cannot be achieved, water should be drained away from areas that can be
damaged by saturation. For example, allow water to pond at the railway boundary rather
than the toe of the embankment.
• pumping sleepers
• rotting sleepers
• silted drains
• pools of water
Pools of stagnant water lying near the track will be drained and the problem that caused them
rectified. The proper action in this situation is to do the following:
• broken pipes
• street gutters
• septic tanks
If team leaders cannot do the necessary work, they should do the following:
Backhoes, bobcats, small bulldozers, and dumpers are some equipment that can be used to
clear drains.
• weed control
• removal of sediment
• regrading
A build-up of weeds within the surface drain tends to slow the passage of water through the
drain, which, in turn, allows sediment to settle leading to a blockage of the drain. Such a
blockage can render a drain useless and lead to a decline in the effectiveness of other drains in
the system. For example, if a cut-off drain at the top of a cutting becomes blocked, water may
overflow the drain, run down the cutting face thereby increasing erosion of the face, and the
cess drain will eventually block up due to the additional sediment load.
Sleepers and rails, for example, left in the cess drains after maintenance work, tend to act as
dams allowing water to pond alongside the track and seep into the formation. This will also
allow sediment to settle. Therefore, old sleepers and rails should be removed to a suitable
dump at the completion of any track work.
When a drain fills with sediment, whether it is due to a blockage or a flat grade, this sediment
should be removed and the drain regraded if necessary. The type of equipment used to remove
the sediment depends on the extent of the blockage and the accessibility (equipment used may
range from a shovel to a gradall). Regrading is sometimes necessary due to scouring, or to
increase the grade of the drain slightly to reduce the amount of sediment that can settle in the
ditch (channel).
Where cutting faces are exposed, therefore undergoing unnecessary cutting face erosion
leading to an acceleration of sediment build-up in cesses, these cutting faces need to be
protected. Forms of protection commonly used are spray grasses, seeding, sodding, and
shotcrete.
Sumps can be cleaned by digging the sediment, ballast, and rubbish out of the silt traps, or by
using a vacuum device (mainly used for deep sumps). Sumps filled with ballast are most
effectively cleaned using post-hole shovels, but these are ineffective for the removal of fine non-
cohesive silt. Square nose shovels of varying widths are suitable only where sediment fills the
silt trap. Where a sump is deeper than two metres, it becomes too difficult to clean using
shovels. In this case, a vacuum device may be used.
After the sumps have been cleaned, the adjoining pipes can be cleaned if necessary, by
rodding, hydroblasting, or similar.
Rodding of the pipes involves the pushing of a circular plug, of slightly less diameter than the
inside of the pipe, through the pipe using flexible rods. Rodding is done working from sump to
sump, starting at the downstream end. Any sediment or other debris pushed out of the pipe is
then cleaned out of the sumps.
Hydroblasting involves the removal of sediment by using a low-pressure, high volume water jet.
Low-pressure with high volume is used because high-pressure low volume water jets tend to
damage pipes. Hydroblasting is most effectively carried out using experienced contractors. The
process involved is as follows:
• sections of the pipe network are cleaned from sump to sump working from the outlet pipe
• various nozzles are used to break up any encrustations and remove debris. This is done by
either jetting it out into the sump or by relying on the volume of water and the grade of the
pipe to create a self-cleaning effect, and remove any sediment.
• after this operation is completed the sumps are cleaned either by the methods previously
mentioned or by sludge pumps
This process is then repeated in the next pair of sumps and so on.
Care needs to be taken to replace any displaced sump grates or covers removed during the
cleaning and inspection of the drainage system.
8.3.2. Outlets
Outlets are the most critical element of a subsurface drainage system because they are
susceptible to events that can impede the free flow of water. The main concerns are blockages
due to weed growth, siltation of the adjacent ditch or stream, debris from the track or slope, and
the activities of animals or humans. A system of marking outlets of subsurface drains should be
implemented to enable easy location of outlets.
TfNSW recommends that outlets and outlet markers be inspected and repaired, if necessary, as
part of routine maintenance at least once a year. As with the inspection of other drainage
system components, this should preferably be carried out in the period of least rainfall.
8.4.1. Cuttings
Drainage problems are exhibited by the following:
• water ponding
• rock pumping
• blocked cess drains, that is, drains silted up due to cutting face erosion or debris (for
example, sleepers and spent ballast)
• foul ballast, that is, spillages from coal and wheat trains or mud causing the water to be
trapped in the ballast. Another possible cause is the damming of water caused by the
dumping of spoil by ballast cleaners at the ballast toe.
Another problem associated with cuttings is where cut-off drains have been provided but not
maintained. Therefore, water can pond within these drains, resulting in the saturation of the
cutting face which would lead to slipping, slumping, or piping of the cutting face. This may also
allow water to overflow the drains and run down the cutting face causing excessive cutting face
erosion, which in turn causes the cess drain to silt up quicker.
There are a number of solutions to these problems depending on the size of the cutting and the
number of tracks. These solutions are discussed in the following sections.
The other alternative is to install subsoil drains. The cess is deepened and a subsoil drain
installed, and the ballast is then allowed to fall over the drain. Therefore, if the surface (cess)
drain becomes blocked (that is, silted up) the subsurface water is still being drained away from
the formation. This system can also be used on multiple track, provided the formation be in
good condition and graded towards the cess drains. Otherwise, the formation may need to be
reconstructed.
This method should be used where easy access is available, allowing regular maintenance to
be carried out.
Note: Cutting faces should be stabilised to reduce erosion and subsequent silting up
of cess drains. For example, spray grassing.
8.4.4. Embankments
The main drainage problems associated with embankments are water being trapped in the
ballast due to fouling of the ballast (either from spillages or mud), and the build-up of spoils from
previous ballast cleaning operations.
Another problem is that of water ponding at the embankment base, which may lead to slips.
This water may cause saturation of the embankment base consequently causing further
consolidation and settlement of the embankment.
To prevent water being trapped in the ballast, leading to formation failures, the shoulders of the
embankment need to be kept clean and graded away from the track. Therefore, windrows of
spent ballast cannot be allowed to build up on embankment shoulders. Depositing ballast
cleaning spoil over the side of the embankment stops water being trapped in the ballast but can
cause water to be trapped in the embankment itself. The spent ballast tends to form an
impermeable layer over the outside of the embankment.
Catch drains will be installed and maintained such that water is prevented from ponding at the
embankment base. An alternative to catch drains in flat areas is to grade surrounding ground
away from the embankment such that if water does pond in the area, it is away from the
embankment base.
On multiple tracks where drainage problems have been encountered it may be necessary to
install a transverse drain with suitable outlets to drain water effectively from the ballast.
The provision of suitable drainage to preserve the stability of the formation is of prime
importance.
The disposal of the impounded water from these depressions is achieved by excavating to the
lowest level and providing suitable permanent outlet drains.
Before deciding the actual method of treatment, the local conditions need to be investigated.
The objective of the investigation is to try to determine the source of the water and to obtain the
depth of the water pocket or depression.
To investigate a soft spot, trial holes are sunk at approximately 2 m intervals. This will determine
the depth of ballast and soft formation. This enables selection of the best type of drainage
system or solution to the problem.
i. Determine the position and depth of the outlet drain or 'tap' drain by using trial holes to
locate the depth of ballast or the soft area.
ii. Excavate and remove the 'soft spot' and foul ballast. The lower level of the trench for any
sub drains used needs to be graded longitudinally at least 1:100 toward the outlet drain.
Sub drains should be lined or covered with a geotextile fabric and filled with clean new
ballast.
iii. Cess drains are also upgraded so that surface water will not penetrate the treated area
upon completion of the work. Where possible, they should be widened and graded
uniformly to the mouth of the cutting. This will help in allowing the water to run freely away.
iv. If the capping layer has been disturbed then it is then restored with crossfall angled
towards the drains.
In flat country, embankments may become submerged and saturated. If the water level rises
uniformly on both sides of the bank, there will not be a great amount of water flow. As a result,
little damage will occur. If, however, the flooding is confined to one side of the line, bridge and
culvert openings will be liable to scour. Should the water run over the top of the track, very
serious damage can result. The amount of damage will be dependent on the velocity or rate of
flow of the water. Any steps taken to reduce the velocity therefore will assist in reducing
damage.
The danger point is reached as water first commences to trickle over the formation. Scouring
then starts, first in the ballast and then in the formation. If there is a large difference in the water
levels on the two sides of the bank, the velocity will be high and damage extensive.
During heavy flooding, washaways may be numerous. They may range from small sections of
ballast washed away to deep cuts where the whole embankment has been removed. The
method of doing temporary repairs will depend on the nature and size of the washaway and the
materials and equipment available.
If the ballast only is scoured out and it is not possible to get ballast to the site, quick repairs may
be made by redistributing the remaining ballast. This will lower the track into a long 'slack' and is
only a temporary measure to restore traffic. Repairs that are more permanent need to be
completed as soon as possible.
Where shallow scouring of the formation occurs, continuous sleeper pigsties may be used. For
deeper scouring, pigsties, trestles, and temporary beams will be required.
Permanent repairs will then require the closure of the track and reconstruction of the
embankment.
8.4.7. Slips
This type of earthwork failure comes within the experience of nearly every person associated
with track maintenance. Slips need not be large to cause serious damage and are very
dangerous in that they can occur suddenly and without warning.
It is desirable, in the initial construction of the track, to avoid unsuitable soils. However, track
staff are generally involved with tracks constructed for many years. As such, conditions need to
be dealt with as they are found.
Terracing and flattening of slopes will assist in bringing about stable conditions. Cuttings, in soft
material or in slopes liable to fail, may be widened to provide space for falling debris clear of the
track. Material removed from cuttings should not be placed on or pushed over embankment
sides without prior investigation of the embankment stability. Embankments can only be
widened using the correct procedures.
Advice on the appropriate batter slope, terraces, and procedures for the widening of
embankments should be sought from the Lead Civil Engineer, ASA.
Small slips may be foreseen and prevented by the removal of loose material or the building of
some form of protective structure. The removal of only the 'toe' of a slip will lead to increased
sliding. When it is necessary to clear the toe, only the minimum quantity to permit the passage
of trains should be removed. Mud flows, which result mainly from heavy rainfall, cannot always
be foreseen and prevented but continual maintenance of top drains will assist in reducing their
incidence.
Flow movements
The soil material of a hillside or side slope may become so saturated with water that it moves
downward in the form of a mud flow. The rate of flow may be slow or rapid depending on the
degree of saturation and type of material. The slopes from which the flow starts need not be
steep if excess water is present.
The potential effect of this type of slip is to cover the track, push it out of line, or destroy any
form of support or retaining wall.
Shear failure
Sometimes an embankment or hillside is composed of soil without any great strength or
cohesion between its particles. It may be standing too steeply and cracks may develop which
will permit the entrance of water.
Movement of a large part of the slope takes place slowly at first, but can become very rapid as
complete failure takes place.
This type of slip may occur at any time, even many years after the railway is constructed. The
effect on the track is seen as a depression if the movement is minor or a total loss of support if
major movement occurs.
Slope adjustment
This is a natural occurrence due to erosion. Quantities of spoil or rock fall away from the sides
of cuttings and fall onto the track. They may be composed of fine material or rocks that are large
enough to derail trains.
Protection against the damage can be afforded by periodically removing any loose stones, and
by the provision of a wide bench at the toe of the cutting in which debris may collect clear of the
track.
8.4.8. Platforms
The main problem associated with platforms is the ponding of water that consequently causes
formation failures, exhibited as poor track alignment, pumping sleepers, and bog holes.
The solutions available depend upon the severity of the problem. The solutions include the
following:
• completely excavate problem area and replace with densely compacted fill up to the next
formation level, then provide a 150 mm compacted granular capping layer and 300 mm of
ballast cover. During reconstruction, install a subsurface drainage system.
Also at stations with island platforms, there is often a problem with water ponding at the ends of
the platform. This can be remedied by placing a sump in the 6-foot connected to an existing
drainage system or suitable outlet.
Note: Run-off from station buildings and platforms can be piped into sumps. This
provides relatively clean water which can be used to help flush drainage systems.
8.4.9. Turnouts
With the increased axle loads and cyclic forces exerted on turnouts it takes very little water for
them to start pumping mud up through the ballast, consequently fouling the ballast and
compounding the problem.
• Deepen and widen the cess drains on each side to drain water from the ballast and keep it
clear of the formation.
• Install subsurface drains under problem areas during turnout reconditioning or renewal.
Major problem areas are under heel blocks and crossings. These are points where the
most pounding (greatest impact load) tends to occur. Standard concessions to
T HR CI 12130 ST Track Drainage are required for subsurface drains within 10 m of a
turnout or crossing.
In some cases, during turnout and crossing renewals asphaltic concrete has been used as a
capping layer to help make the formation more impermeable, thereby giving it a longer life.
The simplest solution for any drainage problems in yards is to clean and regrade cesses and
provide regular outlets in the form of sumps, such that the best possible grades can be applied
to the surface drains.
The most effective method is to have the formation graded as shown in Figure 33 below.
Subsurface drains are located at the low points. If large flows are expected it may be necessary
to install carrier pipes. Carrier pipes may be placed at a deeper level thereby allowing the
grades of subsoil drains to be increased between sumps. Figure 34 shows a carrier pipe
arrangement.
Weep holes are required at and above the capping layer level as well as at the base of a wall.
Weep holes should also be located at regular intervals down the wall, so if the bottom holes
become blocked the upper ones can still allow some water to escape.
Existing weep holes should be cleared during routine bridge maintenance. New holes should be
bored through the wall if no holes exist or the existing holes are inadequate, especially if there
are no weep holes present above the capping layer level.
8.5.1. General
Each Region is to have an emergency plan for dealing with major flooding that would affect train
operations.
Major flooding can occur with little warning and quick action may be necessary without time to
prepare.
The 'flood plan' is to be documented and regularly updated. Copies are to be issued to each
team manager and other senior staff. In particular, a copy is to be part of the 'handover notes'
for relief officers.
The Regional staff should be the railway source for forecasting the effect of a flood on railway
facilities and be the adviser to Network Control. The civil maintenance engineer is to arrange
this service when a flood is forecast.
The heights of water levels at bridges, culverts, and on railway embankments should be marked
so that flood levels may be recorded.
At large bridges, the water level may be different at each end or on up and down stream sides.
Levels at all of these points should be recorded. Any appreciable difference in the up and down
stream flood levels at a bridge may indicate an inadequate waterway.
The records of previous floods in each river in the Region are to be kept up-to-date.
Frequency and severity of flooding are usually available on working plans and office files. Other
instructions require all flood heights to be recorded.
Local councils and other local bodies can provide a wealth of information on flood heights that
will allow upriver peak height information to be related to timing and severity of railway bridge
flooding levels.
Local papers and local residents can also advise on the time the river takes to rise, water
movements, and other essential local knowledge.
Bureau of Meteorology rainfall patterns assist in assessing run-off rates, saturation figures, as
well as river peaks and times.
From all available information a river flow chart should be prepared that will provide an accurate
forecast of the effect of future floods in the river systems on railway facilities once upriver
reports are received.
9. Documentation guide
The aim of this section is to provide a guide for external consultants in the preparation of design
drawings and hydrology reports for minor track drainage projects within the rail corridor. It also
covers external party development works discharging onto or through the rail corridor where this
has been approved by the concession process TS 10765 Concessions to ASA Requirements.
The requirements are also applicable to field staff doing track drainage design.
Minor drainage works within the railway corridor include open cess, pipes, pits, covers such as
lobster cages, and minor under track drainage openings.
9.1.1. General
For CAD drafting, refer to the documents TMD 0001 CAD and Drafting Manual - All Design
Areas – Sections 1 and 2, TMD 0001 CAD and Drafting Manual – Civil Design - Section 3, and
TMD 0001 CAD and Drafting Manual – Track Design - Section 7.
All drawings are to be completed using CAD (Microstation or AutoCAD). There is to be only one
drawing sheet per CAD file.
Drawings are to be detailed using standard TfNSW drawing sheets (A1 size). An electronic
template file of the standard TfNSW title block can be downloaded from ASA website.
Each drawing is to have a unique electronic document management system (EDMS) number.
These numbers can be requested from the TfNSW planroom.
Title blocks are to be filled out to the TfNSW requirements as detailed in TMD 0001.
9.1.2. Plan
Plan drawings require the following:
• drainage layout drawn at a minimum scale of 1:200 with Sydney shown on the left
• the layout will include identification or marking of drainage pits and sumps, for example pit
P1, P2, and so forth
• all railway tracks (including turnouts, crossovers, and sidings) to be shown and labelled, for
example, Main West - Down
• kilometrage marks to be shown along the track – say at 20 m centres. Text labelling at
even 100 m centres (20.100 km). Note that overhead wiring structure (OHWS) numbers
might not coincide with track kilometrage.
• show the top and bottom of cuttings, embankments, drainage channels, depressions, and
so forth
• show and label trackside furniture - if applicable (for example, signal footings, signal
troughing, air lines, train stops, services, face of platforms, retaining walls, bridge
abutments and piers, and so forth)
• show and label any applicable surveyed items (for example, trees, power poles, nearby
buildings, edge of roads or access roads, and so forth)
• show locations of any external services (as determined from a dial before you dig request-
submitted by the consultant)
• proposed drainage with dimensions of extent, pipe size or type or class. Arrows indicating
flow direction. Each pit to be labelled (for example, P1).
• pipe jacking - temporary excavation lines shown and pipe jacking direction indicated
• OHWS shown with footing outline and structure number indicated. Note that an OHWS
comprises a pedestal and either piled or spread footing base. Normally only the pedestal is
visible. TfNSW bridges and structures design personnel might be able to help determine
the footing size and type if a structure number is known.
The plan will be drawn from and based on a detail survey. However, at the discretion of TfNSW
(due to time or budgetary restraints), a schematic layout such as a 'track diagram' may be
inserted into the drawing. If a 'track diagram' is used, then the following note is to be included
alongside:
• This plan has been taken from track books and is not to scale.
• The effects of track curvature and clashes with existing OHWS footings or trackside
furniture are to be confirmed on site prior to ordering materials or construction or both.
• The possible effects of undermining of existing structures have been investigated and are
covered in the design.
• label “From Sydney” and “To Country” at the edge of the map
• show nearest track and dimension the offset to the centreline of the drainage system
• dimension the depth below rail of the pipe system and the pipe cover to ground surface
• indicate width of trench, pipe type or size, geofabric type and fill and bedding material.
Dimension and label the compaction layers.
• if an open channel is adopted, fully dimension the channel and label any scour protection.
A table can be incorporated if the channel size varies along the length.
• if different methods of pipe installation are covered, then a typical section is required for
each method (for example, cess pipe installation different from undertrack pipe installation)
• cross-sections are typically required at all track crossings, adjacent to OHWS and where
there is a change in track configuration
• table along the bottom of the longitudinal section with headings indicating ‘Track km’,
‘design rail level (low rail)’, ‘cess level’ and ‘pipe invert level’
• indicate track kilometrage, rail levels, and cess levels at a minimum of 20 m centres and at
pit locations
• all levels nominated need to be to Australian Height Datum (AHD). Where assumed level is
adopted, the assumed benchmark needs to be clearly identified.
9.1.8. Notes
Notes can include the following:
• design criteria (for example, design: average recurrence interval (ARI) of 50 years, loading:
pipes designed for 300 load allowance plus DLA train live load, and so forth)
The report will look at an average recurrence interval (ARI) of 50 years and should investigate a
range of storms from 5 minutes to 24 hour duration.
Note: TfNSW will accept reports done for ARI 100 years (as stipulated by some
councils) as long as the results satisfy TfNSW requirements.
It is TfNSW’s policy to reject any submission where the development will adversely affect
discharge rates onto or through the rail corridor. To control this, the developer may be required
to incorporate a retention and detention system within the developer’s property. Such a system
will be covered in the hydrology and hydraulics report. It will also be the consultant’s
responsibility to submit a ‘long-term maintenance management plan’.
It is TfNSW’s policy to reject any submission where the development will increase scouring
potential within the railway boundary. A drainage solution particular to the site may be required
to disperse flow effectively. Alternatively, provision of scour protection may be required.
Where the existing track drainage is found to be inadequate to accommodate the site discharge,
the developer will document the upgrade of the track drainage required at their costs. The costs
(to be borne by the developer) will include of upgrading of the TfNSW drainage system.
9.2.2. Drawings
Where upgrading of the TfNSW track drainage system is required, or additional drainage works
are required within the railway boundary, the documentation needs to be prepared in
accordance with Section 9.1.
Where the developer confines all drainage works to within their property, they need to supply a
layout plan that conveys the overall stormwater drainage system. This will include any pipes,
pits, basins, channels, and downpipes, and is to include the outline of the proposed dwelling
and ground contour lines (including any ground level survey points taken). Any labelling of pipes
or pits or both will conform to the labelling conducted in the hydraulics and hydrology report. All
pipe inverts will be clearly identified in plan or on cross-sections. Any non-related information
will be filtered out.
For construction works carried out within the railway boundary, work-as-executed drawings are
to be submitted once works have been completed.
Responsibility needs to be clearly defined in the maintenance plan. For example, the
maintenance plan needs to show who is responsible for the nominated inspection and who is
responsible for carrying out the maintenance tasks.
Any costs incurred by TfNSW as a direct consequence of failure of the stormwater system will
be passed onto the developer or owner.
The cost of design, documentation, and construction for any works within the railway boundary
will be borne by the developer. The developer will ensure that works are carried out in
accordance with railway safety requirements with appropriate TfNSW safety accreditation for all
workers.
Design investigation
1. Objective
2. Information required
3. Collection and study of existing information
4. Site investigation
5. Catchment estimation
Rational method
Section 6.3.2
Is the
drainage system required
a surface or subsurface
system?
Surface Subsurface
yes Is Q1 ≈ QPF? no
yes
yes
yes
QPF = QR + QS + QC (Equation 1)
Is the
subsurface drain a pipe or
pipe aggregate
aggregate
drain?
Determine the slope of the drain (standard is 1 in 100) Determine the slope of the drain
Size pipe for all pipe materials (min diameter 225 mm).
Select pipes from Table 9 such that max flow > QPF Select the size of the aggregate
determined from Equation 1
no
Is the
flow rate in the
pipe acceptable? Choose a value for K from Table 10
yes
Project identification
Location:
Line:
Details:
Project number or identification:
File:
Design delivery manager:
Target dates:
Deliverable requirements
Prepared by:
What type of drainage is it? (i) track (ii) bridge – UB/culvert (i) (ii) (iii)
(iii) external party development
Has a scope of works been provided for Civil Works? Yes No
Has a project brief been provided? Yes No
Have the key design parameters been defined in the scope Yes No
or brief?
Are mandatory legislative or regulatory requirements defined Yes No N/A
in the scope or brief?
Have any validation methods been established in the scope Yes No N/A
or brief?
Is a technical maintenance plan (TMP) required? Yes No N/A
Has functional and performance requirements been identified Yes No
by the client?
Have interface requirements been scoped (see below)? Yes No N/A
Are there any future proposals that have been identified (for Yes No
example, access road, embankment widening,
quadruplication, turnbacks, upgrades, track lifts, and so
forth)?
Do installation or maintenance manuals need to be Yes No
developed or changed?
Do you know the class of line? Yes No N/A
Do you know the speed? Yes No N/A
Do you know the maximum axle load? Yes No N/A
Do you know the operation (inspection and maintenance Yes No N/A
regime, and so forth)?
Do you know the usage factors such as numbers of trains? Yes No N/A
Will the configuration change affect the conditions of Yes No
operation?
Is training required prior to the installation of the design? Yes No
Have all the stakeholders (both internal and external) been Yes No
identified?
Have external hydrology reports been carried out in the area Yes No
(for example, local council and previous reports)?
Are external bodies required to be involved? Yes No
• local council Yes No
• RMS Yes No
• EPA Yes No
• water authorities Yes No
• land owner Yes No
• external development Yes No
Consultant:
Site data
Is the proposed works located in an (i) embankment, (ii) (i) (ii) (iii)
cutting, or (iii) open track
Project type: (i) renewal, (ii) refurbishment (UB and culvert), (i) (ii) (iii)
or (iii) upgrading for track drainage
Is there possible impact with existing structures – OHWS, Yes No
signal gantry, bridges, footings (for example, alignment
conflicts, undermining of footings, embankment stability
concerns)?
Site access – is there an existing access road? Yes No
Is there surrounding drainage systems? For example, local Yes No
council, RMS, private parties
Are there possible scouring concerns or evidence of site Yes No
scouring?
Are details (drawings) of existing drainage available? Yes No
Are there physical interfaces with other property owners or Yes No
Stakeholders?
• road crossings (including private crossings) Yes No
• interface between earthworks and other properties Yes No
• drainage flow to other properties Yes No
• installations such as pipelines laid within the corridor Yes No
• private sidings and bridges Yes No
• other statutory authority requirements for example, Yes No
environment?
justified?
Standards - have relevant drafting standards and practices Yes No
been adhered to?
Standards - is the drawing presentation consistent with Yes No
TfNSW drafting standards?
References - are all the necessary cross-references Yes No
included?
Status - has the drawing status been updated? For example, Yes No
from tendering and construction
Title - is the drawing titled according to TfNSW practice? Yes No
Corrections - if corrections have already been marked on a Yes No N/A
previous check print held by the checker, are they included in
the current print?
Distribution - have the drawings been distributed to the Yes No
relevant stakeholders by the Design Delivery Manager
(DDM)?
Drafting checker
Designer
Have independent actions have been taken to verify the Yes No N/A
design as detailed on the drawings?
Independent verifier
Approver
I certify that I have reviewed the design and have approved its issue.
Accepted
5. Restraints? Such as inlet and outlet, existing adjacent structures, track curvature, and so
forth:
7. Site access:
1. Location:
Note: this procedure determines the amount of water passing at a single point based
on the original catchment area. If multiple catchment areas are incorporated into a
system, then this process should be repeated for each catchment.
Australian standards
CV 0517945 Twin Pipe Headwall (Splayed Wings) to Suit Pipes 225-600 mm Diameter
CV 0517946 Twin Pipe Headwall (Splayed Wings) to Suit Pipes 675-1800 mm Diameter
CV 0517947 Twin Pipe Headwall (Straight Wings) to Suit Pipes 225-600 mm Diameter
CV 0517948 Twin Pipe Headwall (Straight Wings) to Suit Pipes 675-1800 mm Diameter