We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF or read online on Scribd
You are on page 1/ 5
eeeoecoeorvveeceoeeeeveeveeouved
KK Plaka Maren,
Ap; WDE DE, Coe
[Reprinted from Proceedings Forty-seventh
Research Session of the CBIP, Hubli-Dharwar. Karnataka,
November 1978, Vol. 1V] 7
Elimination of Surge Tanks—A Critical Study
J.P. Gupta
‘Superintending Engineer
H.R. Sian”
Executive Engineer
Design Organisation, Irrigation Department, Roorkee, (U.P)
SYNOPSIS
Umil recently surge tank was considered an integral part of hydro-electric
schemes having long pressure conduits.
of such hydro power stati
possibilities of reducing the
eliminating the surge tanks.
deciding the necessity or otherwise of a surge tank.
The successful performance of a number
fons with no surge tanks have, however, indicated the
‘cost and period of construction of these schemes by
The present paper discusses the criterion for
The likely adverse effects on
the water conductor system and on the power system as a result of surge tank
climination and their remedial measures have also been discussed. A few exam-
ples have been given where surge
affecting the stability of the systein.
system for the proposed Tehrl undergroun
city of 1600 MW indicates the possibility of dispensing with the surge tanks.
Detaijed studies are in progress to arrive at a final conclusion.
). Introduction
0.1 A surge tank is an artificial reservoir introduced
along the pressure-conduit system at a suitable point
upstream and‘or downstream of a hydro power plant.
Depending upon the topography of the work, area
this may be designed as a chamber excavated in the
mountain or as a tower Tising high above the sur-
rounding terrain. ‘The surge tank has three primary
functions : (A) to provide a free reservoir surface
close to the terminal discharge mechanism as a q
ree of compensating water hammer reflections 10
limit the pressures in the penstock and materially
reduce them inthe main conduit, the initial reflec.
tions being negative in the case of closure and
positive in the case of opening, (B) to supply the
Additional water required by the turbine during load
demand until the conduit velocity has accelerated to
the new steady state value ; and (C) to store water
during load rejection until tHe conduit velocity has
been decelerated to the new. steady state value.
0.2 ‘The conventional surge tanks include ‘simple
urge tank, throttled orrestricted orifice surge tank,
differential surge tank ‘and surge tanks having upper
tanks have been
A preliminary siudy of the water conductor
id power house with an installed capa
dispensed with without
andjor lower expansion chambers or galleries or
spilling arrangements, etc. A conventional surge
tank is usually located between the almost horizontal
head race tunnel and the steeply sloping pressure
shafi(s) with its top either open to the atmosphere
or connected fo it through a suitable conduit. Such
an arrangement necessitates an adit at the top of the
surge shaft the access to which is generally difficult
and costly. This can be avoided in many cases by
the adoption of a closed surge chamber with air
i which the mass oscillations are absorbed
min the pressure of the compressed,
the val
air (Figure 1).
3. Until recently the surge tank was considered an
jntegral part of hydro-electric schemes having long
ressure conduits. For the first time the surge tank
Nas eliminated at the Paotina(?) hydro power plant
in Tasmania, Australia which is fed through a 8150 m
Tong pressure conduit and has a gross head of 833 m_
and jnstalled capacity of 5x60 MW. The elimina
tion of the surge tank did increase the pressure in the’
penstock but not enough to justify the cost of surge
Yank. The successful operation of Paotina fed to the
elimination of surge tanks at the Rowallan, Wilmot,Aa =
7 te
As C lem Poe)
ko
apes eh ve
SRN P Ne 2c Canam, GUPTA AND SHARMA
te
pew nates ee
1 = SPECIFIC WEGHT OF WATER
Peg PRESSURE. OF AIR CUBHOH
int
— conventional svace TAN
Te Kiaceusien suace: rank
FIGURE 1: Se
through power plant with
‘surge tank.
Lemonthyme and Fisher developments in Australia,
‘Similarly, the surge tanks were eliminated on the head
race tuanels of the first and second line of the Nurek(?)
hydro power station
the stal
increase slightly the
in U.8.S.R. without affecting
iy of the system, ft was found necessary to
Fesponse time and introduce
minor power restrictions. The conduits of the first
line of the station are
}020 m long und of the second
line 1265 m, the maximum head being 375m and
386 m respectively.
another interesting example in which’
been eli
Jordan Rives
wer Plant(*) is
airge tok hus
fated... ‘The water conductor, system com-
prises 5750 m D-shaped, mostly unlined, pressure
funnel with a equivalent diameter of 4.9m and
1400 m of steel penst
cock reducing in diameter from
3.2m at the upstream end to 2.7m at the power
house which has a single 153.68 MW Francis turbine
near the power"house,
working under a net head of 265.5 m. Because top.
graphy did not permit an economical surge tank
‘a pressure regulating valve was
Provided to keep the transient pressures within
Gesiga limits and to ensure stable transient operation.
0.4 The elimination
of surge tank does not only
feduce the petiod and cost of construction of the
water conductor system of a hydro power project but
fiso increases annual production of electrical “energy
by eliminating the hea:
tunnel with the surge t
'd losses at the junction of the
‘ank. Therefore, for hydro elect-
tie schemes having long pressure conduits itis advisa-
bie to carefully exam
‘ne the possibility of eliminating
surge tanks, The elimination of surge tank would no
doubt increase the pi
tend to make the syster
esse in the conduit, would
m unstable and put more strain
fn the governor. The system can, however, be made
feasonably stable by increasing the response time, the
fiywheel moment, constant inertia of the pipe lines
ans by introducing
minor power restrictions. The
present paper discusses the role of the above para-
Meters and the possi
Yanik.
ibility of eliminating the surge
J. Ceiterlon for Providing Surge Tank:
1.L Whenever there is a change in the power demand
‘of the electric system, a dilfereat level of power fi
Absorbed. by the goterater and an unbalanced torque
xistson the turbine Which gives se to a speed
change. The basic equation for speed change eat be
written at Tail
i ‘ae Tur
Tonto wal)
where, J=Polar moment of inertia ‘of rotating parts,
Tyaenet torque being applied to unlt, and
Werangulur acceleration,
‘The polar moment of Inectia includes the rotating
mechanical parts and fluid, although ina turbines
Fonerator combination the Muld f& generally x Ammall
tion of the total mars and {s usually neglected,
jeretore,
wR
1 y 9)
where, Waewoight 4
Restadius of gyration,
The term WR" is known as dywheel effect and is
defined as the capacity of a rotating mass to store of
supply energy. It will, therefore, have a tendency to
maintain constant speed of the turbine while the
governor adjusts the flow of water to limit speed
variation after a change of load.
1.2. Tho regulation of the machines causes sudden
positive and negative pressure variations ot water
Jammer in the pressure conduit which has, thereforey
to be designed to resist the bursting effect duc to
positive pressures and the collapsing, effect due to
Thegative pressures. The interisities of those pressures
depend upon the length of the pressure condult (1),
the velocity of flow in the conduit (V), and the timo
fof closure or opening of the gitide vanes (7,), | ‘The
excess pressures can be reduced considernbly by
increasing the time of closure (Figure 2). Howeve!,
the time (Te) is governed by the allowable maximum
speed. variation and is also dependent upon the pata-
theters of generator design, eg, its flywheel, effect,
tte ‘The transient irregular operation of the unit
With load shedding ic expressed as,
Pinas~Me
F mae 3)
where, no is the normal speed of rotation, and Minas
js the maximum speed of rotation during the transient.
The value of mer is usually taken(*) as 0.40.5.
‘The need to limit speed and pressure variations thus
ee eeeBLIMINATION OF SURGE TANKS—A CRITICAL STUDY 3
VELOCITY OF PROPAGATION OF PRESSURE WAVE
fen TIME OF COMPLETE CLOSURE OF VALVE.
= Lenatn oF conouit
VELOCITY OF FLOW WW CONDUIT
toute
INTAKE vive
Weve
dargeue
ante
nase db
FIGURE 2: Variation of maximum pressure rise along the
Demntock for “Bnite time of clovere Une pre-
avare rise ds expressed im height of a
‘water
‘colema). r
imposes a corresponding limit upon the unregulated
length of the pressure conduit, namely the equivalent
length ftom the machines to the first free water sur-
face. To avoid undesirable speed-rise a governor is
fitted 10 the machine. The mechanism is sensitive to
speed variations and operates automaticelly to re-
duce the ater supply Zon redocton of toad aad vice
versa. fe closure or-opening timed
equaey ‘Valles from Ito Wie or a given tbo
geherator (i.¢, given WR*) ‘the shotter the governor
time, the smaller the speed rise. On the other hand,
the more rapidly the governor adjusts the guide
vanes, the greater will be the resulting pressure varie
ation or water hammer for which the conduit has to
de designed.
1.3 It can be shown that the speed and pressure veri-
ations are to some extent dependent upon the hydrau-
lic inertia of the water mass enclosed in the pressure
sonduit (VL/H). This inertia is characterised by the
fime constant (Tw) of the inertia of the penstock,
i Zhi Vi
Twn
ao)
where, Li and Vi are the length and velocity of the
flow at different sections of the high pressure stretchi,
e.g., penstock, scroll casing, draft tube, etc., and Ho
is the net head on the turbine. The elimination of
‘surge tank results in an increase in the inertia of the
water “mass enclosed in the high pressure. stretchy
Other things being equai shorter length of penstock
means better speed contro! and smatler pressure rise.
Formerly the value of Tw over 2 seconds was seldom.
used, The curreht norms permit the value of Tw Up
to 5 and above for hydro power plants whose capa-
ity does not exceed 20 percent of the power system(*).
king Tw as 2.5 seconds and the maximum wumriel
velocity as $ m/sec Equation (4) yields,
L=5 Ho 65)
‘Therefore, if the length of pressure tunnel is less thay
five times the net head on the machines, normally no.
surge tank is needed. Further, if the contribution of
the power station in the total grid is less than 20 per-
cent, the surge tank can be eliminated from the water
conductor system having equivalent length upto 10
times the head on the machines,
2. Design Modifications to Eliminate Surge Tank
2.1 One of the important functions of the surge tank
is to provide a free reservoir surface close to the
power house and thereby limit the maximum over
Pressures in the penstock by reflected water hammer
waves and prevent the tunnel upstream of the surge
tank from being subjected to high over pressures, In
the absence of a surge tank, the water hammer pres-
sures can be substantially reduced by increasing the
closure and opening time of the turbine guide vanes
and adopting a high value for the permissible
speed variation of the unit during the transients... -
This solution was adopted for four Kuban hydro. |
electric stations by the Gidroprockt Eperimental”
Design Office on the basis of a detailed investigation
of transients on the units and_penstocks in addition
to frequency regulation and active power on, the
system. The total saving on these power stations,
according to the Gidroprockt data, was more-than
11 percent of their total cost (*).
2.2, Mosonyi(?) recommends that the goyerngr-vand
the inlet valve ahead of the turbine should prefetably
be so adjusted as to prevent over: pressu‘es from
exceeding , :
up to 50 m head, 50 percent '
up to 150 m head, 25 percent
over 250 m head, 15 percent i
Should this require a closure impermissibly long. the
fpotaliion offessare rele valves become necsbsay.
“These, however, have no effect on the pressure drop
‘occurring in the penstock.
&4 GUPTA AND SHARMA
2.3. Besides, the elimination of surge tank can also be
ade possible by increasing the diameter of the pres-
sure conduit and thereby reducing the time constant
Of the inertia of the penstock, Tw This would, how-
ever, increase the capital outlay and has to be decided
after comparing the same with the cost of the surge
chamber.
2.4 The second and third functions of the surge tank
{para 0.1) enable the turbines to pick up their new
oad quickly and thereby to control speed variation,
and voltage and frequency change in the system.
The latter is not important if the contribution of the
power station in the total grid is not significant. In
the absence of the surge tank these functions can be
performed toa great extent by the increased inertia of
the rotating mass if found economical. Besides,
minor power restrictions may also be necessary.
3, Examining the Possibility of Surge Tank Elimina-
tion at Tehri Dam Project
3.1 Tehri Dam Project envisages the construction of a
260.5 m high earth and rockfill dam across River
Bhagirathi about 1-5 km downstream of its confluence
with River Bhillangana near Tehri town. The design
flood has been adopted as 15,300 m?/sec and a chute
spillway with a designed capacity of 13,150 m*jsec is
proposed to be located on the right bank. According
to the latest plans an undergcound power house with
an installed capacity of, $200 MW (likely to be
modified to 8x 250 MW) is proposed to be located on
the left bank. Two open intakes will supply water
to the power house through two 12'S m diameter head
race tunnels, each feeding four tinits. According to
the present location of the power house, the overall
Jength of each head race tunnel including penstocks
works out to approximately 900 m. The: gross: he
on the machines varies from a maximum of 231%
at normal maximum reservoir level of 830.0 to a
minimum of#T41'3'm at the dead storage level of
40:00. ‘The maximum discharge required to generate |
1600 MW at the minimum reservoir level works out
to 1472 m'/see which gives a maximum velocity of
6 m/sec through each head race tunnel The average
head losses work out. to approximately 12%. The
two diversion tunnels on the left bank will later serve
as tail-race tunnels. The proposed layout of the scheme -
is shown in Figure 3.
a
3.2 The peaking capacity of the power grid in Uttar
Pradesh is likely to be of the order of 11,750 MW and
the -total installed capacity of more than 14,000 MW
by the time Tehri dam Project is completed. Thus,
the contribution of Tehri power house to the (tal
grid will be of the order of 11 to 12 precent.
SCALE Remenals METRES
coe
SHEL bo abo so 0 gf
‘SURGE TANKS.
O25m a)
POWER HOUSE
(ax 200Mw)
Se
FIGURE 3: Layout of works of Tehrl Dam Scheme.
SRM la l Pelt DAD PD. BP PADPRPRPPHDEDHHDPDEH DOLD=~ wT ewer rer weer wwe ewe ewT ewe eweewe wwe we w~Twwerwwwvwvs we wo
. cs!
k
io
ELIMINATION OF SURGE TANKS—A CRITICAL STUDY
3.3, According to the’ present design of water con-
ductor system for the Tehri power house, the time
constant of the inertia of the penstock works out to,
oe ELV 9006 eGR,
Two Ho ~ F81K (aT 3 )
Since according to the current norms a value of Tw
upto 5 and above is permitted(*) for hydro power
plauts whose capacity does not exceed 20 percent of
the power system, there appears to be a possibility of
inating the two 32°5.m diameter surge tanks at
Tehri dam project. With a view to find a suitable site
for the location of the power house cavity further
upstream, goological investigations are in progress,
IP it is found feasible to. locate the power house
further upstream, the possibility of the elimination of
surge tank will further increase. Besides, by adopting
certain modifications in the design of the water con-
ductor system and of the turbo-generator as indicated
in para 2, the system can be made steble without the
surge tanks. However, detailed analysis of the system
vis-a-vis economic considerations has to be carried out
before arriving at a conclusion. These studies are in
progress.
4. Conclustons
4.1 The climination of a surge tank from the water
conductor system of a hydro power plant docs not only
teduce the cost of its installation and the petiod of
construction of the scheme but also increases. the
annual production of electrical energy by curtailiag the
ocal head losses at the junction of the pressure con-
J duit with the surge shaft. 7
4.2 Asa general rule, if the unreguisted tength of
the pressure tunnel is less than five times the net head
on the machines, no surge tank is normally needed.
4.3 The value of the time constant of the inertia of
{the penstock [ Equation (4) } upto 5 and above can be
permitted if the capacity of the hydro power plant in
question does not exceed 20 percent of the capacity of
the grid to which the station is connected. The time
constant of the inertia of the penstock can be reduced
by increasing the diameter of the conduit within, eco-
s
4 In the absence of a surge tank the pressure
variations in the pressure conduit can be reduced to a
great extent by increasing the response time of the
governor. The extent of over pressures can be further
Teduced by installing a pressure relief valve. The
system ean be made stable by increasing the inertia of
the rotating mass’ and putting some minor power res-
trictions, if needed.
4.6 _A preliminary study of the water conductor system
for the proposed Tehri hydro power plant shows that
there is a possibility of eliminating the surge tanks.
However, detailed analysis of the system needs to be
carried out before coming to a definite conclusion.
5. References
() SHARMA, H.R. and PETER, J.C: “Air Cushion
Surge Tank". Proceedings, Voll, Alf india Symposium
on “the Economic and Civil Engineering Aspects of
Hydro-etectric Schemes, Roorkee, 14-16 Aprit, 1978
(2) GRIFFITHS, P.7.A.:_ “Surge Problems of the Hydro-
electric Commission ‘of Tasmania, International Con-
ference, on Pressure Surges held’ at the University of
Kent, Canterbury, England, 68 September, 1972.
(3) POKROVSKII, BLM. etal : “Regulation of the Hydra.
lic Units of the Nurek. Hydro-electric Station without
‘Translated
11, pp. 13-14,
Surge Shafts in the Head Race. Tunnels’
from’ Gidro-teknicheskoe Stoltel'stevo N
November 1971,
(8) PORTFORS, B.A‘and CHAUDHRY, MAHL: “Analysis
and Prototype Verification of Hydraulic. Transients in
Jordan River Power Plan”. International Conference
‘on Pressure Surges held at the University of Kent, Can:
terbury, England, 6-8 September 1972.
() STREETER, V.L, and WYLE, E.B. : “Hydraulic Transl-
ento™, McGraw-Hill Book Company, New York, ‘St.
Louis, San Francisco, Toropto, London, Sydney, 1967
(6) ARSHENEVSKIL, N.N. and TRUBITSYN, YUN.
“Significance of Dispensing with Surge, Chambers to
Lower the Cost of Hydro-electric Stations". ‘Transl
from Gidro-technicheskoe Stroitel'stevo’ No. 9,
10-14, September 1971
(7) MOSONY!, EMIL : “Water Power Development Vol,
2". Publishing House of the Hungarian Academy of
Sciences, Budapest, 1960.
PP.
@
BROWN, J. GUTHRIE: tric Engineering
nomical range. o
: Pracice-Vol, 1; Civil Eagieering’ lacke& Son
4.4 In many cases it 8 possible’-and advisable to dis- Mala eae Eusen |
pense with the surge tank. Therefore, the possibility (10) DAVIS. CV. and SORENSEN, K-E. | “Hand Book of
Of surge tank elimination should be thoroughly exa. — PUlled, Macrawlee oat ee MgntoT end
mined in each case. Kogakusha Company Ltd., Toky9.
4)
YW