REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE BUILDING OFFICIAL
ILOILO CITY
NET METERING
2 WAY, 280 WATTS OUTPUT = 230 V, 60 Hz
DPWH
BUILDING OFFICIAL
60A, 2P
INPUT = 600 V, 3200W OUTPUT = 305 V, 2500 Wp
15A, 2P 15A, 2P
1 2 INVERTER
20A, 2P 20A, 2P
3 4
ELECTRICAL
30A, 2P
5
FROM GRID LINE 10 pcs. 250 Wp Polycrystaline solar panel
(PECO)
NOTE: SEE DETAILS IN SPICIFICATION
i
ONE LINE DIAGRAM, P1
NOTES:
SOLAR DESIGN ANALYSIS:
1. THIS LOAD SCHEDULE IS PREPARED USING EXCEL, COMPUTATIONS ARE DONE HERE.
2. 1 Full Load = VA/Voltage (see Column O) NOTE: KWp is Killowatt per Panel
3. 180 VA per outlet at pf =1 CONSUMPTION = 10 KW-HR
4. Ampacity of conductors used is 1.25* of Full- load current (MINIMUM)(see Column P)
5. Protection is 2.5* Full-load current (MAXIMUM)(see Column S) KWp x Peak Sun Hour = KW-HR
6. Ground wire shall 14.0 sq mm colored GREEN.
7. Complete design analysis that includes computations of short circuit and voltage drop will be done next semester. Iloilo Peak Sun Hour = 5.5
KWp = 5000 W-HR/ 5.5
KWp = 1818.18
Design of Solar Panels = 2500 Wp
10 pcs. 250 Wp Polycrystaline solar panel
PREPARED FROM THE OFFICE OF: CERTIFIED AND SEALED BY: P.R.C. NO.: PROJECT TITTLE: APPROVED BY: SHEET CONTENTS: SHEET NO:
P.T.R NO.:
ONE LINE DIAGRAM, PANEL P1
SCHEDULE OF LOADS
T.I.N. NO.: BATUIGAS RESIDENCE GRID TIDE POWER SUPPLY DESIGN ANALYSIS
NOTES
DATE:
DRAWN BY:
ISSUED: LOCATION: OWNER i