0% found this document useful (0 votes)
351 views8 pages

Change Orders

This document discusses key aspects of construction contract administration including addenda, change orders, and claims. Addenda are issued pre-bid to make changes to bidding documents, while change orders are issued post-contract to modify the scope, cost, or schedule. Common reasons for change orders include owner requests, unforeseen conditions, and errors/omissions. Claims arise from disagreements over work performance and differences that could lead to later filing of a claim if unresolved. Settlement of claims is encouraged through mediation or arbitration rather than litigation.

Uploaded by

Anton_Young_1962
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
0% found this document useful (0 votes)
351 views8 pages

Change Orders

This document discusses key aspects of construction contract administration including addenda, change orders, and claims. Addenda are issued pre-bid to make changes to bidding documents, while change orders are issued post-contract to modify the scope, cost, or schedule. Common reasons for change orders include owner requests, unforeseen conditions, and errors/omissions. Claims arise from disagreements over work performance and differences that could lead to later filing of a claim if unresolved. Settlement of claims is encouraged through mediation or arbitration rather than litigation.

Uploaded by

Anton_Young_1962
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
You are on page 1/ 8

Construction Contracts Administration

– Addenda, Change
Orders, and Claims

Addenda
• Addendum: An addition to bidding documents
issued to the bidders (plural: Addenda)
• A change in the specifications or one of the
contract documents during the bidding phase
requires an addendum
• Reasons for issuing addenda include the
following:
– To correct errors
– To add owner-initiated changes
– To furnish clarifications
– To add or delete products
– To change stated requirements
Addenda II

• Guidelines to go by when issuing addenda


– No addendum should be issued later than
5 days prior to the bidding due date
– Addenda should be issued only in proper
written form
– A procedure should be established that
requires acknowledgment of the receipt of
all addenda

Change Orders

• Change Order: An order issued by an owner


and agent of the owner according to the
terms and conditions of a construction
contract to the contractor to make a specific
change in the work that may result in a
change in the scope of the contract's work,
the contract sum, or the contract time,
depending on the change order’s purpose
and substance
Change Orders II

• Change Order is After Contract


– Addenda is pre-bid
• Impact
– Cost = +/-
– Time = Schedule
– Quality
– Scope

Change Orders III

• Reasons for issuing change orders:


– Owner has secured additional financing
– Emergence of unforeseen conditions
during construction
– Material nonconformance with original
specifications
– Correct errors or omissions in the original
documents
– Changes requested by the owner,
contractor, or design professional
Change Orders IV

• Reasons for issuing change orders


(Continued):
– Over/Under runs in quantities beyond
limits
– Changes instituted by regulatory agencies
– Impossibility/Impracticability of
performance

Change Orders V

• The change order clause provides:


– Means by which the owner can adjust
plans and specifications
– Means by which the contractor may
incorporate suggestions
– An outline for organizing and presenting
claims for additional compensation
Change Orders VI

• Initiation of Change Orders


– Owner
– Engineer
– Contractor
• Change Order Preparation
– Clear, Concise, and Explicit
– Standard Forms
– Drawing and Specifications

Change Orders VII

• Information required on change orders


– Name and title of the project
– Date of the change order
– Number of change order
– Reason for Change
– Changes required under this order
– Change in the contract price
– Change in time of completion
– Required signatures
Change Orders VIII

• Problems of change orders


– Does it fall within the scope of the
project?
– Who has the authority to make the
change?
– Is the time requirement appropriate?
– Are markups properly applied to ensure
contractors will not lose money?

Change Orders IX
• Contract changes do more than alter the
scope of the work, they:
– Disrupt orderly sequences
– Change prior coordination
– Change schedule logic
– Change methods for work not otherwise
addressed by the change
– Cause a contractor to remain mobilized
on site longer than originally planned
– Continue to add administrative costs
resulting from rework
Claims

• Potential claims applies to any differences


arising out of the performance of the work
that might reasonably lead to the later
filling of a claim by the contractor if the
differences cannot be resolved in the field

Claim’s Tree
Contract

Disagreement

Potential claim

Review: Facts, Timeliness of submission

Claim has merit Disagreement Resolved no issue

Becomes a File claim


change order
Settle claim
Claims

• Settlement of claims
– Some contracts encourage settlements
of claims through:
• Mediation
• Arbitration
– Both methods are considered better
alternates over litigation

You might also like