TABLE OF CONTENTS
INTRODUCTION.........................................................................................................5
1 Structures ..................................................................................................................7
  1.1 Operative Structures for Work Breakdown Structure (WBS) ...................7
     1.1.1      Define Special Characters for Projects............................................7
     1.1.2      Define Project Coding Mask ..............................................................8
     1.1.3      Create Status Profile ........................................................................ 10
     1.1.4      Define Partner Determination Procedures and Roles ................ 22
     1.1.5      Create Project Profile ....................................................................... 25
     1.1.6      Create Project T ypes for WBS Elements ..................................... 28
     1.1.7      Specify Applicants for WBS Elements .......................................... 28
     1.1.8      Specify Persons Responsible for WBS Elements ....................... 29
     1.1.9      Define Priorities for WBS Elements ............................................... 30
     1.1.10 Define Field Selection for Work Breakdown Structures............. 31
     1.1.11 Create User- Defined for WBS Elements ..................................... 34
     1.1.12 Maintain Substitutions ..................................................................... 35
  1.2 Operative Structures for Network.............................................................. 47
     1.2.1       Maintain network types ................................................................... 47
     1.2.2      Specify Parameters for Network Type .......................................... 52
     1.2.3      Maintain network profiles ................................................................ 54
     1.2.4      Set Up Number Ranges for Network............................................. 62
     1.2.5      Define Control Key ........................................................................... 62
     1.2.6      Account Assignment Categories and Document Types for
                Purchase Requisitions..................................................................... 65
     1.2.7      Specify person responsible for work center ................................. 67
     1.2.8      Define parameters for Subnetworks.............................................. 67
  1.3 Operative Structures for Milestones.......................................................... 69
     1.3.1 Define Milestone Usage...................................................................... 69
  1.4 Project Planning Board .................................................................................. 70
     1.4.1      Define Time Profiles......................................................................... 70
     1.4.2      Define profiles for time scales (Optional) ..................................... 72
     1.4.2      Define Profiles for the Project Planning Board ............................ 74
2 Costs...................................................................................................................... 77
  2.1    Activate Project Management in Controlling Area ............................... 77
  2.2    Maintain Value Categories ...................................................................... 79
  2.3    Assign Cost Elements to Value Categories.......................................... 81
  2.4    Create/Change Planning Profile ............................................................. 84
  2.5    Assign Plan Profile to Project Profile ..................................................... 85
  2.6    Define Costing Variants ........................................................................... 85
  2.7    Maintain plan costing variants for network types ................................. 87
  2.8    Maintain Budget Profiles.......................................................................... 87
  2.9    Stipulate Default Budget Profile for Project Definition......................... 88
  2.10 Create Number Ranges for Budgeting .................................................. 89
  2.11 Define Tolerance Limits ........................................................................... 91
  2.12 Define default cost elements for down payments ................................ 91
  2.12 Create Allocation Structure...................................................................... 92
  2.13 Create Settlement Profile......................................................................... 96
  2.14 Specify Default Settlement Profile for Project Definition..................... 97
  2.15 Define Strategies for Determining Settlement Rules ........................... 98
PS Configuration                        Page 3 of 122                    www.sapficoconsultant.com
 2.16 Assign Strategies and Default Rules to Network Types ...................100
 2.17 Specify Default Settlement Profiles for Networks ..............................101
 2.18 Determine Strategy for Settlement Rule ..............................................102
 2.19 Assign Strategy to Project Profile .........................................................104
3 Dates...................................................................................................................104
 3.1 Define Parameters for WBS Scheduling ................................................104
4 Material ...............................................................................................................106
 4.1 Availability check........................................................................................106
    4.1.1 Define Checking Rules ......................................................................106
    4.1.2 Define Checking Scope.....................................................................106
    4.1.2 Define Checking Control ...................................................................109
5 Confirmation ......................................................................................................114
 5.1 Define Confirmation Parameters..............................................................114
6 Final check.........................................................................................................116
 6.1 Finally check the Project Profile ...............................................................116
PS Configuration                       Page 4 of 122
INTRODUCTION
Projects irrespective of its size require precise planning of the various detailed
activities involved in execution of the project. The project manager has the job
of ensuring that the project is executed efficiently, on time, and within budget -
which he or she achieves by ensuring that the required resources and funds
are available as and when needed.
Projects are generally part of the internal processes of a company. To be able
to control all tasks in project execution, you need an organizational form that
is specific to the project and which is shared by all departments involved.
Before you can carry out a project in its entirety, the project goals must be
precisely described and the project activities to be carried out must be
structured. A clear, unambiguous project structure is the basis for successful
project planning, monitoring, and control.
A project is struc tured as per the following points of view:
   ü   By structures, using a work breakdown structure (WBS)
   ü   By process, using individual activities (work packages)
Project managers usually distinguish between two types of project:
   ü   Externally financed projects
           v   Custom er projects
   ü   Internally financed projects
           v   Overhead cost projects
           v   Capital investment projects
The Project system has no organizational structures of its own. You
incorporate into your existing structure by making assignments to the
organizational units.
Thus each project starts with the definition and classification of the structures
required for processing and incorporating these into existing enterprise
structure.
PS Configuration          Page 5 of 122         www.sapficoconsultant.com
Project System Organizational structure
         Project Definition
         WBS Elements
            Networks
             Activities
                Internally Processed
                      Activities
               Externally Processed
                     Activities
              General Costs Activities
              Material Components
PS Configuration           Page 6 of 122
1 Structures
For configuration we use the following path on the SAP application screen:-
SAP Menu à Tools à AcceleratedSAP à Customizing à SPRO - Edit
Project à
We will not refer the above path henceforth; we will directly refer to the
IMG node.
1.1 Operative Structures for Work Breakdown Structure
    (WBS)
1.1.1 Define Special Characters for Projects
IMG à Project System à Structures àOperative Structures à Work
Breakdown Structure (WBS) à Project Coding Mask àDefine Special
Characters for Projects
Here you specify how a project number is coded for editing. You can maintain
the following parameters for editing the project number:
   •   The length of the key for project coding.
       Here you can assign up to five places for the key.
   •   an indicator specifying whether the key must have this exact length or
       whether it can also be shorter
   •   special characters to enter WBS elements faster
   •   an indicator specifying whether only coded project numbers can be
       used to create projects
Avoid the following special characters: *,+,? and %. These special characters
are used for specific functions in the system.
PS Configuration         Page 7 of 122        www.sapficoconsultant.com
Thus for the above configuration our project code will start with a single digit
alphanumeric code.
We have defined a special character = in the field ET (entry tool for wbs
element) as an entry aid. (You can use any character as entry aid, the system
will always copy the identifier of the superior WBS element)
E.g. You want to insert a new wbs element below the wbs element
V-6691001.05
In this case you only have to type in =01, system will automatically
supplement the key as V-6691001.05.01
1.1.2   Define Project Coding Mask
IMG à Project System à Structures àOperative Structures à Work
Breakdown Structure (WBS) à Project Coding Mask à Define Project Coding
Mask
This configuration is already done while creating the investment management
configuration. The Appropriation request number and the Project system
number (Top WBS) will be the same.
Here you define the coding masks for Project numbers. You can create a
coding mask for each key that you plan to use.
PS Configuration         Page 8 of 122
The system determines the coding key that it should use based on the
first character of the coding key.
You can use the following symbols:
   •   X for alphanumeric characters
   •   0 for numeric characters
   •   special symbols for the structure o f the appropriation request number
We enter the following code mask for key
V -0000000.00.00.00.00
Thus the project number V66910010301 is automatically edited to
V-6691001.03.01
The configuration was already done in Investment management which can be
seen below.
The appropriation request number and the top level wbs element
number will be the same.
Click on
PS Configuration         Page 9 of 122       www.sapficoconsultant.com
1.1.3   Create Status Profile
IMG à Project System à Structures àOperative Structures à Work
Breakdown Structure (WBS) à WBS User Status à Create Status Profile
You can set your own user status for an event.
You need to create status profile, create user status and assign various
business transactions whic h will influence the user status.
Click on
Update the following:-
Click
Double click
Update the following:-
PS Configuration         Page 10 of 122
Click on
Click
PS Configuration   Page 11 of 122   www.sapficoconsultant.com
Update the following:-
Click on
PS Configuration         Page 12 of 122
Now you need to assign the user status to the business transaction.
Double click
Click on
Update the following:-
PS Configuration         Page 13 of 122      www.sapficoconsultant.com
Budgeting permitted.
Release permitted
Write plan line items
Click on
Click      to update business transaction for the next status.
PS Configuration          Page 14 of 122
Click
PS Configuration   Page 15 of 122   www.sapficoconsultant.com
Click
Click on
Click
Click on
Click
Click on
PS Configuration   Page 16 of 122
Click on
Click
PS Configuration   Page 17 of 122   www.sapficoconsultant.com
Double click
Click on
Click
PS Configuration   Page 18 of 122
Click on
Double click
Click
PS Configuration   Page 19 of 122   www.sapficoconsultant.com
PS Configuration   Page 20 of 122
Update the following:-
Double click      and update the following business transaction.
PS Configuration         Page 21 of 122      www.sapficoconsultant.com
1.1.4   Define Partner Determination Procedures and Roles
IMG à Project System à Structures àOperative Structures à Work
Breakdown Structure (WBS) à Define Partner Determination Procedures and
Roles
Here you define partner roles, assign them to keys dependent on the logon
language, and define partner structures and assign partner roles to them.
Double click
PS Configuration      Page 22 of 122
Click on
PS Configuration   Page 23 of 122
Update the following:-
Select
Double click
Click on
PS Configuration         Page 24 of 122   www.sapficoconsultant.com
Update the following:-
Click on
1.1.5   Create Project Profile
IMG à Project System à Structures àOperative Structures à Work
Breakdown Structure (WBS) à Create Project Profile
This step has already been configured in Investment Management
configuration step 4.1.2
Here you define project profiles for capital investment measures. The most
important control feature in the project profile of capital investment measures
is the investment profile. You can assign the investment profile in the step
Define investment profiles.
The project profile contains default values such as controlling area, company
code and other control parameters such as the planning method for dates and
PS Configuration         Page 25 of 122
costs. The data that you enter in the project profile will be copied into a project
in its project definition or in the WBS elements which can later be overwritten.
Let us see the configuration parameters for project profile
Double click on
Click
PS Configuration          Page 26 of 122         www.sapficoconsultant.com
Remove the costing sheet and interest profile
Click on
PS Configuration        Page 27 of 122
1.1.6      Create Project Types for WBS Elements
IMG à Project System à Structures àOperative Structures à Work
Breakdown Structure (WBS) à Create Project Types for WBS Elements
The project type does not influence program control or screen selection.
You can use the project type as a filtering criterion in the information system
We will use the project type IP.
1.1.7      Specify Applicants for WBS Elements
IMG à Project System à Structures àOperative Structures à Work
Breakdown Structure (WBS) à Specify Applicants for WBS elements
You can define here Applicants for WBS elements
Click on
PS Configuration         Page 28 of 122         www.sapficoconsultant.com
Update the following:-
Click on
1.1.8      Specify Persons Responsible for WBS Elements
IMG à Project System à Structures àOperative Structures à Work
Breakdown Structure (WBS) à Specify Persons Responsible for WBS
Elements
You can define here persons responsible for WBS elements
Click on
Click on
PS Configuration         Page 29 of 122
1.1.9   Define Priorities for WBS Elements
IMG à Project System à Structures àOperative Structures à Work
Breakdown Structure (WBS) à Define Priorities for WBS Elements
You can define here priorities for WBS elements. There are already some
standard priorities defined in SAP. We will work with them and not configure
new ones.
PS Configuration       Page 30 of 122
1.1.10       Define Field Selection for Work Breakdown Structures
IMG à Project System à Structures àOperative Structures à Work
Breakdown Structure (WBS) à User Interface Settings à Define Field
Selection for Work Breakdown Structures
Here, you can make a field selection for the screens of the project definition
and the WBS elements.
You can specify modifiable and influencing fields.
PS Configuration        Page 31 of 122
PS Configuration   Page 32 of 122
PS Configuration   Page 33 of 122
1.1.11         Create User- Defined for WBS Elements
IMG à Project System à Structures àOperative Structures à Work
Breakdown Structure (WBS) à User Interface Settings à Create User-
Defined Fields for WBS Elements
User defined text fields can be used as additional information. The user
defined fields are not checked by the SAP system. But checks can be done
through an enhancement.
The fields available are:-
General text fields
Quantity fields
Value fields
Date fields
Check boxes
The key words for the user-defined fields are determined by a key word ID.
Let us see an SAP standard Field key.
Double click
PS Configuration             Page 34 of 122
1.1.12        Maintain Substitutions
IMG à Project System à Structures àOperative Structures à Work
Breakdown Structure (WBS) à Maintain Substitutions
We will create a substitution:-
If responsible person entered in WBS is 200 - Jerry Jones then update the
responsible cost center as 9104001
If responsible person entered in WBS is 201 - Angeline Reyes then update
the responsible cost center as 9104002
PS Configuration          Page 35 of 122
Position the cursor on WBS element and Click
Update the following:-
Click
PS Configuration         Page 36 of 122
Click
Select
Click
PS Configuration   Page 37 of 122   www.sapficoconsultant.com
Click
Click
PS Configuration   Page 38 of 122
Update the following:-
Double click
PS Configuration         Page 39 of 122
Double click
Click   to scroll down the fields
PS Configuration         Page 40 of 122
Click
The technical names as well as short description will be displayed.
Further click
PS Configuration        Page 41 of 122
Double click
PS Configuration   Page 42 of 122
Click
Click
Update the following:-
Take a drop down in the field and select
Double click
PS Configuration         Page 43 of 122
Update the following:-
Click on
Position cursor on
Click
Click on
Click back and again open
PS Configuration         Page 44 of 122
Double click
Double click
Change 00000200   to 00000201
PS Configuration        Page 45 of 122
Double click
PS Configuration   Page 46 of 122
Update the following:-
Click on
1.2     Operative Structures for Network
1.2.1      Maintain network types
IMG à Project System à Structures àOperative Structures à Networkà
Settings for Networks à Maintain network types
The network type contains information for controlling and managing networks.
In the SAP System, the network is a special form of the work order which has
a structure in common with production, maintenance and inspection orders.
Every network you create must have a network type allocated to it.
Click on
PS Configuration         Page 47 of 122
Update the following:-
Click on
Click on
PS Configuration         Page 48 of 122
Click
Click
Click on
Click
PS Configuration   Page 49 of 122
Click
Click
Click
Click on
Click
Similarly create Network type for activity type account
Click on
PS Configuration         Page 50 of 122
Update the following:-
Click on
Click
Similarly create a group and assign a number range.
PS Configuration         Page 51 of 122     www.sapficoconsultant.com
1.2.2 Specify Parameters for Network Type
IMG à Project System à Structures àOperative Structures à Networkà
Settings for Networks à Specify Parameters for Network Type
Here you define the parameters per plant and network type.
Click on
Update the following:-
PS Configuration         Page 52 of 122
Click on
Click
Click on
Update the following:-
Click on
PS Configuration         Page 53 of 122
1.2.3 Maintain network profiles
IMG à Project System à Structures àOperative Structures à Networkà
Settings for Networks à Maintain network profiles
The network profile contains default values and parameters for controlling the
processing of networks, such as control keys for activities.
The data which you enter here in the network profile is copied into the header,
activities, and activity elements when you create a network. You can overwrite
these values in each new network.
Select
Click
PS Configuration        Page 54 of 122
PS Configuration   Page 55 of 122
Update the following:-
PS Configuration         Page 56 of 122
Click
PS Configuration   Page 57 of 122
Click
Press enter
Click on
Select
Click
PS Configuration   Page 58 of 122
Update the following:-
PS Configuration         Page 59 of 122
Click
PS Configuration   Page 60 of 122
Click
Press Enter
Click on
PS Configuration   Page 61 of 122
1.2.4 Set Up Number Ranges for Network
IMG à Project System à Structures àOperative Structures à Networkà
Settings for Networks à Set Up Number Ranges for Network
We had already created the number groups and number ranges while
configuring the network which can be seen by clicking
1.2.5 Define Control Key
IMG à Project System à Structures àOperative Structures à Networkà
Settings for Networks à Define control key
Here you create the control keys for different activities and activity elements.
The control key determines which business transactions are carried out when
an activity is processed whether it is internal activity, external activity or both
is possible.
You specify the indicators and keys for the various func tions in the control
key.
We have used the SAP standard control keys PS01, PS02 and PS05 for
networks.
Let us check the settings.
PS Configuration          Page 62 of 122
Double click
PS Configuration   Page 63 of 122
Let us now check the settings of PS02
PS Configuration       Page 64 of 122
Let us also check the settings for control key PS05
1.2.6 Account Assignment Categories and Document Types for
      Purchase Requisitions
IMG à Project System à Structures àOperative Structures à Networkà
Settings for Network Activities à Account Assignment Categories and
Document Types for Purchase Requisitions
Here you specify purchasing item categories and a purchasing document type
for purchase requisitions in the network
PS Configuration        Page 65 of 122
Change the Acct. assgmt. Gen from F to N
Click on
PS Configuration       Page 66 of 122
1.2.7 Specify person responsible for work center
IMG à Project System à Structures àOperative Structures à Network à
Work Center à Specify person responsible for work center
Here we create person responsible for work center for a plant.
Click on
Update the following:-
Click on
1.2.8 Define parameters for Subnetworks
IMG à Project System à Structures àOperative Structures à Network à
Define parameters for subnetworks
Here you maintain the following parameters for subnetworks:-
Network type for the subnetwork
Network type of the activity which is replaced by the subnetwork
Click on
PS Configuration         Page 67 of 122
Click on
Click
Click on
Update the following:-
PS Configuration         Page 68 of 122
Click on
1.3 Operative Structures for Milestones
1.3.1 Define Milestone Usage
IMG à Project System à Structures àOperative Structures à Milestones à
Define Milestone Usage
Here you define milestone usages.
It is used for:-
1)    Trigger for earned value analysis
2)    It is generally used in the area of engineering and design.
The usages values can be used in selection in the information system
There are standard milestone usages defined in the system.
PS Configuration         Page 69 of 122
1.4 Project Planning Board
1.4.1 Define Time Profiles
IMG à Project System à Structures à Project Planning Board à Define
Time Profiles
With a time profile you specify the various time periods for working in the
project planning board.
Evaluation period
The evaluation period defines the time frame for working with and displaying
data in the project planning board.
Planning period
The planning period defines the time frame for carrying out current planning in
the project planning board. The planning period can be smaller or the same
as the evaluation period. The planning period is always in reference to the
project start date.
If the start date is later than the current date, the planning period begins with
the start date.
If the start date is earlier than the current date, the planning period begins with
the current date.
PS Configuration          Page 70 of 122
Click on
Update the following:-
Click on
Click
Click on
PS Configuration         Page 71 of 122
Update the following:-
Click on
1.4.2 Define profiles for time scales (Optional)
IMG à Project System à Structures à Project Planning Board à Define
profiles for time scales
Here you define the time scale profile. A time scale profile describes the
properties of all possible scales using headings for the time axis (day scale,
week scale etc.).
The time fence is derived from the possible scales.
Depending on the current scale the time scale is generated from one or more
scales.
There are scales with the following headings:
   •   Yearly split
   •   Quarterly split
   •   Monthly split
   •   Weekly split
PS Configuration         Page 72 of 122
   •   Daily split
   •   Hourly split
   •   Minute split
   •   Shift split
We will work with the standard time scale profile SAPPS_Z001 - PS: Standard
We will check the configuration settings for the profile
PS Configuration         Page 73 of 122         www.sapficoconsultant.com
1.4.2 Define Profiles for the Project Planning Board
IMG à Project System à Structures à Project Planning Board à Define
Profiles for the Project Planning Board
You can maintain different values in the profile of the project planning board:
   •    Default values
   •    Graphics profile
   •    Fields that are displayed in the table area of the project planning board
   •    Parameters for the time display
   •    Change indicator
Click
Click
PS Configuration           Page 74 of 122
Update the following:-
Click on
PS Configuration         Page 75 of 122
Click
PS Configuration   Page 76 of 122
Click
Click on
2 Costs
2.1 Activate Project Management in Controlling Area
IMG à Project System à Costs à Activate Project Management in
Controlling Area
Here you activate the project management in controlling area
Select
PS Configuration        Page 77 of 122
Double click
The check box should be selected       to activate
Click on
PS Configuration      Page 78 of 122
2.2    Maintain Value Categories
IMG à Project System à Costs à Value Categories à Maintain Value
Categories
Here you define value categories.
Value categories are intervals of:
   •   Cost elements
   •   Commitment items
   •   Statistical key figures
These are required for:
   •   Updating the project information database
   •   Defining structure reports for costs, revenues, and payments
   •   Updating quantities in the project info database RPSQT
Update the following:-
PS Configuration          Page 79 of 122
Click on
Click on
PS Configuration   Page 80 of 122
2.3 Assign Cost Elements to Value Categories
IMG à Project System à Costs à Value Categoriesà Assign Cost Elements
to Value Categories
Update the following:-
Click on
Update the following:-
Click on
PS Configuration         Page 81 of 122   www.sapficoconsultant.com
Click
Similarly assign other value categories to cost elements.
Click on
PS Configuration        Page 82 of 122
Update the following:-
Click on
Click
Similarly assign the following category to cost elements:-
Value category              Cost element              Cost element category
Z01                         943204                    43      (Internal   activity
                                                      allocn)
Z04                         430004                    1 (Primary cost element)
Z07                         400013                    1 (Primary cost element)
Z12                         981000                    50 (Proj related incoming
                                                      order)
PS Configuration         Page 83 of 122
2.4 Create/Change Planning Profile
IMG à Project System à Costs à Planned costs à Manual Cost Planning in
WBS à Hierarchical Cost Planning à Create/Change Planning Profile
This step was already configured in the Investment Management step number
4.1.4
PS Configuration       Page 84 of 122
2.5 Assign Plan Profile to Project Profile
IMG à Project System à Costs à Planned costsà Automatic Costing in
Networks/Activities à Costing à Define Costing Variants
Update the following:-
Click on
2.6 Define Costing Variants
IMG à Project System à Costs à Planned costsà Automatic Costing in
Networks/Activities à Costingà Define Costing Variants
Let us see the configuration of Standard SAP costing variant PS02
PS Configuration         Page 85 of 122
Double click
PS Configuration   Page 86 of 122
2.7   Maintain plan costing variants for network types
IMG à Project System à Costs à Planned costsà Automatic Costing in
Networks/Activities à Costingà Maintain plan costing variants for network
types
Here you maintain the default plan costing variant for your network type.
Click on
2.8   Maintain Budget Profiles
IMG à Project System à Costs à Budgetà Maintain Budget Profiles
This step was already configured in Investment Management configuration
step 4.1.5
PS Configuration        Page 87 of 122
2.9   Stipulate Default Budget Profile for Project Definition
IMG à Project System à Costs à Budgetà Stipulate Default Budget Profile
for Project Definition
Here you assign the budget profile to the project definition.
PS Configuration         Page 88 of 122
Update the following:-
Click on
2.10    Create Number Ranges for Budgeting
IMG à Project System à Costs à Budgetà Create Number Ranges for
Budgeting
The following number ranges are defined in the standard system:
       ü   01 Project budget
       ü   02 Project plan
       ü   03 Order plan
       ü   04 Order budget
We will work with the standard number ranges.
PS Configuration         Page 89 of 122
Click   to display the number range
PS Configuration      Page 90 of 122
2.11    Define Tolerance Limits
IMG à Project System à Costs à Budgetà Define Tolerance Limits
Here you enter the tolerance limits for availability control.
Availability control can identify budget overruns in a project at an early stage
and initiates various actions.
You activate availability control for you budget profile. You can specify one or
more tolerance limits for each activity group for a budget profile.
This step was already configured in the Investment Management step 4.1.6
We will see the configuration done.
2.12    Define default cost elements for down payments
IMG à Project System à Costs à Actual Costs and Forecastà Update
Down Payments à Define default cost elements for down payments
Here you define the cost/revenue elements, under which down payments are
updated as expenses in CO.
For down payments referring to a purchase order, SAP system uses the
purchase order cost element. If there is no reference, in this the case, you
need to define one cost element (category 01 = primary cost elements
general) for credit-side down payments in each controlling area, or one
revenue element (category 11 = revenue elements) for debit-side down
payments .
PS Configuration          Page 91 of 122
When you assign down payment or purchase order costs, SAP System
updates the account assignment objects cost center, order, make-to-order
production order, WBS element, and network.
Update the following:-
Click on
2.12       Create Allocation Structure
IMG à Project System à Costs à Automatic and Periodic Allocationsà
Settlement à Settlement Profile à Create Allocation Structure
In Allocation structure you define the target cost element.
Here 2 options are available:-
            1) Using the original source cost element
            2) Using the settlement cost element
Click on
PS Configuration          Page 92 of 122       www.sapficoconsultant.com
Update the following:-
Click
Select
PS Configuration         Page 93 of 122
Double click
Click on
Update the following:-
Click
Update the following:-
Select
PS Configuration         Page 94 of 122
Double click
Update the following:-
The above cost element group contains all the cost elements (primary as well
as secondary cost elements)
Double click
PS Configuration         Page 95 of 122
Click on
Update the following:-
Click on
2.13       Create Settlement Profile
IMG à Project System à Costs à Automatic and Periodic Allocationsà
Settlement à Create Settlement Profile
Here you create a settlement profile for settling costs from networks to the
WBS elements.
The settlement profile contains a range of control parameters for settlement.
Assign the allocation structure Z1 to the settlement profile.
Click on
PS Configuration         Page 96 of 122
Update the following:-
Click on
2.14    Specify Default Settlement Profile for Project Definition
IMG à Project System à Costs à Automatic and Periodic Allocationsà
Settlement à Create Settlement Profile
Here you assign the settlement profile Z9 created in the Investment
management material to the project definition.
PS Configuration         Page 97 of 122
Update the following:-
Click on
2.15    Define Strategies for Determining Settlement Rules
IMG à Project System à Costs à Automatic and Periodic Allocationsà
Settlement à Define Settlement Rule for Network à Define Strategies for
Determining Settlement Rules
Here you define a strategy to determine the settlement rule in the network.
You must define the strategy for the settlement rule in the parameters for the
network type.
You enter the sequence in which the settlement rule is determined for each
strategy:
   •   Copy the settlement rule from the WBS element
   •   Copy the settlement rule from the project definition
   •   Generate a settlement rule to the WBS element
PS Configuration         Page 98 of 122
   •   Generate a settlement rule by default (predefined by the system)
   •   Maintain a settlement rule manually
The SAP standard strategies for settlement rule are given below
Take a drop down in the field Typ
We have assigned the strategy 03 in the parameters for network type Z901
and Z902 in the earlier step which can be seen below
PS Configuration        Page 99 of 122
We have assigned 03 default rule which has automatic generation of
settlement rules.
2.16    Assign Strategies and Default Rules to Network Types
IMG à Project System à Costs à Automatic and Periodic Allocationsà
Settlement à Define Settlement Rule for Network à Assign strategies and
default rules to network types
Here you assign a strategy and a default rule to the network type. The
assignment regulates control of the settlement rule for activities created later
in the network.
PS1 is SAP standard default rule for network to WBS elements settlement.
PS Configuration         Page 100 of 122
2.17    Specify Default Settlement Profiles for Networks
IMG à Project System à Costs à Automatic and Periodic Allocationsà
Settlement à Define Settlement Rule for Network à Specify Default
Settlement Profiles for Networks
We assign the settlement profile ZNWBS9 created by us earlier to the network
type Z901 and Z902.
Update the following:-
Click on
PS Configuration         Page 101 of 122
2.18       Determine Strategy for Settlement Rule
IMG à Project System à Costs à Automatic and Periodic Allocationsà
Settlement à Settlement Rule for Work Breakdown Structure Elementà
Determine Strategy for Settlement Rule
Here you define the strategy for automatic generation of settlement rules.
The strategy is used to determine:
To which objects the settings apply:
   Ø Billing element
   Ø Account assignment element
   Ø Neither
Click on
Select
Double click
PS Configuration        Page 102 of 122
Click on
Update the following:-
Click on
PS Configuration         Page 103 of 122   www.sapficoconsultant.com
2.19    Assign Strategy to Project Profile
IMG à Project System à Costs à Automatic and Periodic Allocationsà
Settlement à Settlement Rule for Work Breakdown Structure Elementà
Assign Strategy to Project Profile
Here you assign the strategy Z1 to our project profile.
Update the following:-
Click on
3 Dates
3.1 Define Parameters for WBS Scheduling
IMG à Project System à Dates à Date Planning in WBS à Define
Parameters for WBS Scheduling
The profile for WBS scheduling, for example, contains the following control
parameters:
PS Configuration         Page 104 of 122
       ü whether the dates are to be recalculated automatically when saving
       ü whether the error log is displayed automatically if errors were
         determined during scheduling
       ü the number of days the start may be in the past
       ü whether basic dates are to be adapted if the earliest or latest dates
         of the network change
       ü maximum reduction level for reduction
The profile for WBS scheduling is stored in the project profile.
Click on
Update the following:-
Click on
PS Configuration         Page 105 of 122
4 Material
4.1 Availability check
Here we configure all the settings necessary to configure the material
availability check in networks.
4.1.1 Define Checking Rules
IMG à Project System à Material à Availability Checkà Define Checking
Rules
There are standard checking rules available in SAP system.
The checking rule relevant for us is PS as shown below
4.1.2 Define Checking Scope
IMG à Project System à Material à Availability Checkà Define Checking
Scope
Checking group and checking rule determine the checking scope.
You can specify:
   •   which elements relevant to MRP (goods receipts/goods issues) are
       taken into account (for example purchase requisition, purchase order)
PS Configuration        Page 106 of 122
   •   which stock categories are taken into account
   •   whether replenishment lead time is checked
Checking rule PS is maintained for : -
01 Daily requirement
02 Individual requirement
CH Batches
PS Configuration         Page 107 of 122
PS Configuration   Page 108 of 122   www.sapficoconsultant.com
4.1.2 Define Checking Control
IMG à Project System à Material à Availability Checkà Define Checking
Control
Here you define the control for the availability check of materials, production
resources/tools and capacities.
Which check rule is to be used and whether a check is to be carried out, is
specified depending on plant and network type and the business transaction,
for example, whether the check is to take place when creating or releasing a
network.
PS Configuration        Page 109 of 122
Click on
Update the following:-
Click on
Click on
PS Configuration         Page 110 of 122
Update the following:-
Click on
PS Configuration         Page 111 of 122
Click on
Update the following:-
Click on
PS Configuration         Page 112 of 122
Click on
Update the following:-
Click on
PS Configuration         Page 113 of 122
5 Confirmation
5.1 Define Confirmation Parameters
IMG à Project System à Confirmation à Define Confirmation Parameters
The configurations for the confirmation are specified for each plant and
network type.
You can specify the following parameters:
      ü    when confirming, a final confirmation is automatically proposed
      ü    the dates of the confirmation may lie in the future
      ü    the error log for cost calculation is displayed
      ü    percentages for the allowed deviation from work and duration
Click on
Update the following:-
PS Configuration         Page 114 of 122       www.sapficoconsultant.com
Click on
Click on
Update the following:-
PS Configuration         Page 115 of 122
Click on
6 Final check
6.1 Finally check the Project Profile
IMG à Project System à Structures àOperative Structures à Work
Breakdown Structure (WBS) à Create Project Profile
Double click
PS Configuration   Page 116 of 122
Update the substitution rule we created earlier in the project profile.
Also update the status profile we created for WBS elements
PS Configuration         Page 117 of 122
Click
PS Configuration   Page 118 of 122
Change the items which are encircled
Also change the planning methd/basic
PS Configuration       Page 119 of 122
Further also change the following:-
PS Configuration        Page 120 of 122
PS Configuration   Page 121 of 122
Click on
PS Configuration   Page 122 of 122