Material Inspection Request (MIR)
Ref / MIR / …… / ….. /…../……../01                                                                                 Rev : ……….......
                                                                                                                            Date : ........ / ........ / ........
                                                                                          Owner: …
Project :                  …..
Contractor:                …….                                                            Consultant : …….
Stru                                                                             Surv                                                              Landscape
Arch                                                                             Elec                                                              Infra
Steel                                                                           Mech                                                              Other
Required inspection date:…../……../……….                                                                                   Required Time:
Description:………………
Approved MT Ref:……………….
Location:…………………..
QC comment :…………………
   S.N                                         Description                             Manufacturer supplier                    Unit            Quantity              Action
     1
The Contractor QC Manager:
Name:.......................................................           Signature:.....................................                 Date: ......./......../........
*the approved MT to be attached
The consultant comments :
(A)Approved                              (B) approved as noted                                (C)Revise and Resubmit                              (D) Rejected
 The consultant
Name:.......................................................           Signature:.....................................              Date: ......./......../........
A: Approved                                                     B:Approved as noted (work may proceed after following Comments)
C:Revise and resumbit (work can't proceed)                       D:Rejected