Hydroelectric Power Plant
Hydroelectric Power Plant
Submitted by:
Submitted to:
June 2021
Acknowledgement
From the perseverance of the proponents to complete this capstone design, it would not be possible
without the assistance and supervision from the different persons who were asked and approached
concerning this topic. It was a deep appreciation and profound gratitude for the proponents to reach out
Foremost, we would like to thank the Almighty God for His guidance and empowering the strength
throughout this journey. Also, for providing the courage to continue and surpass the different obstacles
To Engr. Nicanor L. Serrano, Department Chair of Mechanical Engineering T.I.P Manila for his guidance in
To our Parents, that never failed to encourage us to give us our needs in order to get through this capstone
design and their never ending understanding and unconditional love for us, specially at times of hardships
Lastly, the proponents would like to commend their co-members for their never-ending patience despite the
hardships they had shared together and most importantly able to collaborate, taking their ideas in
1
Abstract
As technology advances the demand for electric power increases since recent advancements in technology
requires the usage of electricity which means that as our country progresses in technology our demand for
power grows, as one of the countries in Asia that is still progressing, our country is need of many electric
power sources, as current news shows, Luzon is in yellow alert which means that the power supplied is not
enough for the grid’s power demand which can cause power outages in some places in Luzon specially
those that are far from the distribution lines or power substations, with this we need to increase the number
of power sources such as power plants. The proponents decided to design a 5 MW power plant situated in
San Jorge, Samar to be able to reach the power demand by 2025, the proponents design three (3)
alternative turbines, which are Tubular Bulb-type Turbine, Kaplan Turbine and Francis Turbine knowing that
these type of turbines has the potential to supply the needed power in the Province of Samar to reduced
power outages and for the customers of SAMELCO I to be satisfied. Nowadays power generation is still
progressing, but it is not progressing as much as our technologies. Therefore we have power outages and
the power demand is increasing while the power supply is constant, thus creating a gap between the
2
TABLE OF CONTENTS
CHAPTER 1 5
INTRODUCTION 5
1.1 Introduction 5
1.2 Project Background 6
1.3 Topography 9
1.4 Site Selection 11
1.5 Electric Cooperative 12
1.6 The Project 16
1.6.1 Computation of Design Capacity 16
1.7 Client 17
1.8 Project Objective 18
1.8.1 General Objective 18
1.8.2 Specific Objectives 18
1.9 Scope and Limitations 18
1.10 Project Development Flow 19
CHAPTER 2
DESIGN INPUT 21
2.1 Hydroelectric Power Plant 21
2.2 Type of Hydroelectric Power Plant 21
2.3 Advantages and Disadvantages 23
2.4 System Components 24
2.5 Penstock requirements 27
2.5.1 Arrangement and Material Selection 27
2.6 Formulas 29
Solving for Specific Speed of the Turbine, Ns: 32
Solving for Number of Poles of the Generator, P: 32
2.7 DESIGN ALTERNATIVES 33
2.7.1 ALTERNATIVE 1 Hydroelectric Power Plant: Tubular Turbine 33
2.7.2 ALTERNATIVE 2 Hydroelectric Power Plant: Francis Turbine 36
2.7.3 ALTERNATIVE 3 Hydroelectric Power Plant: Kaplan Turbine 39
2.8 Manufacturer’s Data 42
Design Alternative 2: Francis Turbine 44
Design Alternative 3: Kaplan Turbine 45
CHAPTER 3 46
PROJECT DESIGN 46
3
3.1 Design Alternative 1: Tubular Turbine 46
3.2 Design Alternative 2: Francis Turbine 48
3.3 Design Alternative 3: Kaplan Turbine 50
CHAPTER 4 52
STANDARDS, CONSTRAINTS AND TRADEOFFS 52
4.1 Standard and Codes 52
4.1.1 RA 9275 - Philippine Clean Water Act 52
4.1.2 PD 1152 – Philippine Environmental Code 53
4.1.3 PD 1067 – Water Code of the Philippines 55
4.1.4 Occupational Safety and Health Standards – As amended, 1989 57
4.1.5 Philippine Mechanical Code 62
4.2 Constraints Selection 64
4.3 Constraints and Trade-offs 69
4.3.1 Economical Constraint 69
4.3.1.1 Considerations 69
4.3.1.2 Trade-offs 69
4.3.1.3 Justification 70
4.3.2 Sustainability Constraint 70
4.3.2.1 Considerations 70
4.3.2.2 Trade-offs 71
4.3.3 Environmental Constraint 72
4.3.3.1 Considerations 72
4.3.3.2 Trade-offs 73
4.3.3.3 Justification 74
4.3.5 Trade-off Summary 74
4.4 Sensitivity Analysis 74
4.4.1 Arrangements 75
4.4.2 Sensitivity Analysis Summary 77
Manufacturer’s Data for Design Alternative 3: Kaplan Turbine 81
APPENDIX A 83
APPENDIX B 98
APPENDIX C 112
APPENDIX D 128
References 137
4
CHAPTER 1
INTRODUCTION
1.1 Introduction
Electricity is the flow of electric charge, it is a commonly used form of energy in different areas. The
electricity is not freely available in nature in large amounts, so it must be produced. Electricity generation is
the central component that retains the society working by providing power energy. This process has a huge
impact in the industries, it converts the energy into electricity. The component that is capable of the
production of electricity is the power station. Electricity is most often generated at a power plant by
electromechanical generators, primarily driven by heat engines fueled by combustion or nuclear fission but
also by other means such as the kinetic energy of flowing water and wind. Power plant is an industrial
facility that produces electricity from essential energy. Most power plants use one or more generators that
convert mechanical energy into electrical energy in order to transmit power to the electrical station to
distribute for consumer electrical needs. There are different types of power plants, the power plants that
exist in the Philippines are Biomas, oil, Geothermal, Gas, Solar, coal and hydro power plants.
Renewable Energy lands on the useful and clean energy that comes from the regular source or process
that is continuously replenished. Renewable Energy resources include Geothermal, Hydropower, Biomass
5
1.2 Project Background
6
According to IEA World Energy Statistics Balance, as of 2015 the Electricity Gross Generation in the
Philippines was at 82.413 TWh and we can see that the majority of source is coming from the coal-fired
As of 2019, the gross generation went up to 106.041 TWh. The year 2019 is characterized by a significant
increase in electricity consumption and peak demand attributed to several factors such as the increase in
temperature and utilization of cooling equipment aggravated by the strong El Niño, the conduct of National
and Local elections during the first half of the year, increase in economic growth, and entry of large power
generating plants.
7
VISAYAS GRID:
In 2019, Visayas grid registered a peak demand of 2,224 MW showing a growth of 8.3% from the previous
year.
8
Power plants within the Visayas grid registered 16.059 TWh of gross generation in 2019. The region
continued to remain as the renewable energy dominated grid in the country with 47.2% share of generation
coming from renewable energy technologies with corresponding shares of geothermal at 39.1%, solar at
4.1%, biomass at 2.2%, wind at 1.4%, and hydro at 0.4%. For the fossil-based power plants, coal
generation increased and still is the largest producer at 49.6% with the entry of new coal-fired power plants
Around the world, renewable energy use is on the rise, and these alternative energy sources could hold the
key to combating climate change. Renewable Energy is generated from sources that naturally replenish
themselves and never run out. The common sources are solar, wind, hydro, geothermal and biomass.
Renewable energy has many benefits: it can combat climate change because it doesn't emit carbon gas
and can decrease pollution and therefore reduce threats to everyone's health.
Humans have been harnessing the energy of river currents for centuries, using water wheels spun by rivers
initially to process grains and cloth. Moving water is a powerful source of energy. The power harnessed
from moving bodies of water is called hydroelectric power. The Philippines make use of two methods in
order to harness power; dam storage or impoundment, and run-of-river. While impoundment makes use of
man-made dams in order to store water, run-of-river relies on flowing bodies of water like waterfalls. Both
1.3 Topography
Samar is a province in the Philippines located in Eastern Visayas Region. It has a total land area of
13,428.8 square kilometers and a coordinate of 11°49’48” N, 125°0’0” E. It consists of 2 districts, with 24
9
Fig. 1-6: Topography of Philippines and San Jorge, Samar from Google Map
San Jorge, officially the Municipality of San Jorge, is a 4th class municipality under 1st district in the
province of Samar, Philippines. The municipality has a land area of 241.20 square kilometers which
Its population as determined by the 2015 census has an estimated population of 17,184 people which
accounts for 2.20 percent of the total population in Samar Province, or 0.39 percent of the overall
population of the Eastern Visayas region. San jorge is divided into 41 barangays. Based on these figures,
the population density is computed at 71 inhabitants per square kilometer or 185 inhabitants per square
mile.
Generally, San Jorge is a landlocked municipality. Almost the entire place is filled with trees, rice farms, and
the citizens are residing near roads. Though the place is landlocked, there is a big river, Gandara River
10
1.4 Site Selection
The land on which the powerhouse is going to be built must be at a reasonable price and secondly the
Since water is the primary requirement of the hydro-electric power station. Water availability must be in
huge quantities.
The site selected for the hydro-electric plant must be accessible by transport facility. So that heavy
The figure shown above is the Gandara River that will supply to the hydroelectric power plant.
11
Fig. 1-8: Projected Location based on Google Map
The figure shows the projected location of the Gandara river which is in the boundary of San Jorge, Samar
and has a length of approximately 11.85 kilometers. Determining the right location will decide the feasibility
12
SAMAR I ELECTRIC COOPERATIVE, INC. (SAMELCO I) was incorporated and registered with the
National Electrification Commission on February 27, 1974. It started actual operation three months later on
May 27, 1974. The Coop coverage area is composed of Calbayog City, Tinambacan District, Oquendo
District, and the Municipalities of Sta. Margarita, Gandara, San Jorge, Pagsanghan, Taranghan,
Matuguinao, San Jose de Buan and the island Municipality of Almagro. In 1996, the Island municipalities of
Tagapul-an and Sto. Niño were added to its franchise which were energized under NPC’s Small Island Grid
13
Fig. 1-11: SAMELCO I Profile
(Source: http://www.kuryente.org.ph/electric-company/rates/85)
14
Fig.1-12: SAMELCO I Load Distribution
It has a total of 54,414 Captive Customer Connection with different types of customer classification
(Residential, Commercial, Industrial and others) within the 427 barangays of it’s coverage area. The
15
(Source: Department of Energy)
The chosen Electric Cooperative for the design is Samar I Electric Cooperative, Inc. (SAMELCO I) as the
main electric distribution benefactor of the proposed power plant design. The Samar I Electric Cooperative,
Inc. (SAMELCO I, Inc) is a franchise distribution utility that operates power service in the province of
Samar. The designers have proposed a hydroelectric power plant which is the most appropriate to the
location which is mostly surrounded by elevated bodies of water in the mountain ranges.
The information that is used is based on the statistical data published by the Department of Energy (DOE).
𝑃𝑜𝑤𝑒𝑟 𝑁𝑒𝑒𝑑𝑒𝑑 = 𝑃𝑟𝑜𝑗𝑒𝑐𝑡𝑒𝑑 𝑃𝑒𝑎𝑘 𝐷𝑒𝑚𝑎𝑛𝑑 (2025) − 𝐴𝑐𝑡𝑢𝑎𝑙 𝑃𝑒𝑎𝑘 𝐿𝑜𝑎𝑑 (2017)
𝑃𝑜𝑤𝑒𝑟 𝑁𝑒𝑒𝑑𝑒𝑑 = 4. 1 𝑀𝑊
16
𝑃𝑜𝑤𝑒𝑟 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 = 4. 5 𝑀𝑊 ≈ 5 𝑀𝑊
The computed capacity resulted in 4.5 MW but it was decided to settle with 5 MW to ensure that the
consumers are receiving enough power, also to consider the practical choices of materials and/or
1.7 Client
Samar I Electric Cooperative, Inc. (SAMELCO I) covers (3) Districts and (10) Municipalities
namely:
● Gandara ● Tagapul-an
● Pagsanghan
17
1.8 Project Objective
The main objective of the study is to design a Hydroelectric Power Plant with a capacity of 5 MW that can
● Design a Hydroelectric Power Plant using 3 different turbines namely Kaplan, Francis and
Crossflow.
● To analyze and assess the three (3) alternative designs in accordance to the Codes and Standards
● To decide on which of the best options among the alternative designs and options are best suited
and efficient for San Jorge, Samar using constraints and trade-offs.
The project aims to build three (3) alternative turbine designs for the 5 MW Hydroelectric Power Plant
located in San Jorge, Samar. The planned power plant was intended to increase the supply and help
Samar to adapt to future power demand. The proponents focused on designing the necessary components
of the power plant. That being said, a detailed power plant lay out will not be provided, and the other minor
The proposed Hydroelectric power plant with three (3) alternative turbine designs will be evaluated and will
be tested using design constraints, trade-offs, and computations. Among the three (3) alternative designs,
one will be selected by evaluating and assessing the computations and will serve as the main design for
18
1.10 Project Development Flow
● Potential Clients – the proponents identified areas wherein to supply future power demands.
19
● Power Plant Design – the proponents designed a hydroelectric power plant to be
● Scope and Limitation – the proponents focused on designing the power plant with only
● Analysis and Computation of Gathered Data – based on the gathered data, the
proponents analyzed and calculated the power needed to supply the municipalities covered by
SAMELCO I.
● Constraints Identification – the proponents identified the constraints for each alternative
design.
● Methods for Trade-offs – the proponents compared the constraints identified using
different arrangements.
● Alternative Design Selection – the proponents selected the design based on the results of the
trade-offs.
20
CHAPTER 2
DESIGN INPUT
The world’s first hydroelectric project was used to power a single lamp in the Cragside country house in
Northumberland, England, in 1878. Four years later, the first plant to serve a system of private and commercial
customers was opened in Wisconsin, USA, and within a decade, hundreds of hydropower plants were in operation.
Hydroelectric energy or also called hydropower, refers to the renewable energy that employs the power of
water in motion. The system that uses and harnesses the power of the flowing or falling water to drive
mechanical devices which convert the kinetic energy into electric energy.
Hydropower plant is the facility that produces electricity from generators driven by turbines and any
mechanical component that converts the potential energy of moving water into mechanical energy. It is an
eco-friendly power plant, it is fueled by water and it wont pollute the environment like other power plants
that burn fossil fuels, such as coal and natural gas. The amount of electricity that can be produced depends
on how far the water drops and how much water passes through the system.
The hydropower facilities have three types, which are impoundment, diversion and pump storage. The
impoundment facility uses a dam to put river water in a reservoir, a typically large hydro power system.
Diversion or also called run-of-river, a type of hydropower plant facility that channels a portion of a river
through a canal or penstock. It may not require the use of a dam. Run-of-river or diversion resources are
not meant to store water resources; rather they use water resources alongside the river by diverting the
21
river through channels to harness the kinetic energy. Portions of the water are channeled and run through a
powerhouse, generating electricity. The water is then returned to the river, reducing environmental impacts.
Since the design proposes a 5 MW Hydroelectric Power Plant, the category falls under Small Hydropower
Plant.
Low Head ➔ Use river current or tidal flows of 30 meter or less to produce energy.
➔ These applications do not need a dam or retain water to create a hydraulic
head.
22
High Head ➔ A power station operating under heads above 300m.
➔ A head of 200/250m is considered as the limit between medium and high
heads power stations.
● A Cheap Source of Energy - Despite expensive upfront building costs, hydroelectric power is one
of the cheapest sources of energy. The good thing about hydroelectricity is they require a low cost
● The Renewable Nature - Hydroelectricity is considered a renewable source of energy as it uses the
earth’s water to produce electricity. Water is a never-ending source as water is recycled back
● Clean Energy Source - Hydropower is one of the clean and green alternative sources of energy.
Unlike traditional fuel energy sources, hydroelectric energy doesn’t release harmful pollutants into
the environment.
● Lessens Pollution - Hydropower doesn’t rely on fossil fuels to produce energy, rather it uses water
and the process is so clean that it doesn’t release any greenhouse gases or harmful waste into the
● Flexible - Hydropower is a flexible source of energy as hydropower plants can be scaled up and
down easily to meet the changing energy demands. When the electricity demand is high, the flow
of water can be increased and can also be decreased when the demand falls.
Disadvantages of Hydropower
● Environmental Damage - The main con of hydropower is its effect on the environment. Interruption
in the natural flow of water has serious impacts on the river ecosystem and environment. This
23
leads to disrupted animal migration paths, issues with water quality, and human or wildlife
displacement.
● High Building Cost - Hydroelectric Power plants are incredibly expensive to build, however
operating cost and maintenance costs are minimal. Also, hydropower projects take a long period to
finish and will have to operate for a long period to recover the capital spent.
● May Cause Droughts - Water availability directly affects electricity generation. The occurrence of
local droughts is one of the major downsides of setting up hydroelectric power plants.
● Risks of the Flood - As dams hold back large volumes of water, which can be catastrophic to
24
For run-of-the-river hydro projects, a portion of a river’s water is diverted to a channel, pipeline, or
pressurized pipeline (penstock) that delivers it to a waterwheel or turbine. The moving water rotates the
wheel or turbine, which spins a shaft. The motion of the shaft can be used for mechanical processes, such
Before water enters the turbine or waterwheel, it is first funneled through a series of components that
control its flow and filter out debris. These components are the headrace, forebay, and water conveyance
1. Headrace
The headrace is a waterway running parallel to the water source. A headrace is sometimes
necessary for hydropower systems when insufficient head is provided. They often are constructed
of cement or masonry. The headrace leads to the forebay, which also is made of concrete or
masonry.
2. Forebay
It functions as a settling pond for large debris which would otherwise flow into the system and
damage the turbine. Water from the forebay is fed through the trash rack, a grill that removes
additional debris. The filtered water then enters through the controlled gates of the spillway into the
3. Penstock
Penstocks are like large pipes laid with some slope which carries water from the intake structure or
reservoir to the turbines. They run with some pressure so, sudden closing or opening of penstock
gates can cause water hammer effect to the penstocks. So, these are designed to resist the water
hammer effect apart from this penstock is similar to normal pipe. Steel or Reinforced concrete is
25
4. Hydraulic Turbines
Turbines are more commonly used today to power small hydropower systems. The moving water
strikes the turbine blades, much like a waterwheel, to spin a shaft. But turbines are more compact
in relation to their energy output than waterwheels. They also have fewer gears and require less
● Impulse Turbine - if the turbine wheel is driven by the kinetic energy of the fluid that strikes
the turbine blades through the nozzle or otherwise, the turbine is known as an impulse
pressure. Impulse turbines are usually suitable for high head and low flow rates.
● Reaction Turbine - a reaction turbine develops power from the combined action of
pressure and moving water. The runner is placed directly in the water stream flowing over
the blades rather than striking each individually. Reaction turbines are generally used for
sites with lower head and higher flows than compared with the impulse turbines.
5. Power House
Power house is a building provided to protect the hydraulic and electrical equipment. Generally, the
whole equipment is supported by the foundation or substructure laid for the power house. In case
of reaction turbines some machines like draft tubes, scroll casing etc. are fixed within the
foundation while laying it. So, the foundation is laid in big dimensions.
6. Draft Tube
If reaction turbines are used, then the draft tube is a necessary component which connects the
turbine outlet to the tailrace. The draft tube contains a gradually increasing diameter so that the
water is discharged into the tailrace with safe velocity. At the end of the draft tube, outlet gates are
7. Tailrace
26
Tailrace is the flow of water from turbines to the stream. It is good if the power house is located
nearer to the stream. But, if it is located far away from the stream then it is necessary to build a
channel for carrying water into the stream. Otherwise the water flow may damage the plant in many
ways like lowering turbine efficiency, cavitation, damage to turbine blades etc.
● The material is selected according to the ground conditions, accessibility, weight, jointing system
and cost,
● The diameter is selected to reduce frictional losses within the penstock to an acceptable level,
● The wall thickness is selected to resist the maximum internal hydraulic pressure, including transient
As regards the location of the penstock, two different solutions may be discerned which are characteristics
1.) Buried penstocks are supported continuously on the soil at the bottom of a trench backfilled after placing
the pipe. The thickness of the cover over the pipe should be about 1 to 1.2 m.
a) The soil cover protects the penstock against effect of temperature variations
d) They are safer against rock slides, avalanches and falling trees.
Disadvantages are:
27
a) Such pipes are less accessible for inspection, faults cannot be determined easily,
c) On steep hillsides, especially if the friction coefficient of the soil is low, such pipes may slide,
2. Exposed penstocks are installed above the terrain surface and supported on piers (briefly called
supports or saddles). Consequently, there is no contact between the terrain and the pipe itself, and the
d) Such pipes are readily accessible and maintenance and repair operations can be carried out
easily.
c) Owing to the spacing of supports and anchorages significant longitudinal stresses may develop
Steel to be used for the fabrication of penstocks of a hydro-electric project should meet the following
requirements:
28
c) It should have required impact strength to be able to deform plastically in the presence of stress
2.6 Formulas
Penstock diameter:
29
The power available from the flow and head is given by the equation:
𝑃 = 𝑄𝐻γη
Where,
3
Q - flow discharge (𝑚 /𝑠)
P - power (𝑘𝑊)
D - diameter (𝑚)
3
γ- specific weight of water (9. 8066 𝑘𝑁/𝑚 )
η- overall efficiency
𝐸𝑃
𝐵𝑃 = 𝑛 𝑔
𝐵𝑃
𝐴𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 𝑃𝑤 = 𝑛 𝑟
ℎ = ℎ𝑔 − ℎ𝑓
ℎ𝑔 = ℎℎ𝑤 − ℎ𝑡𝑤
30
1. Using Darcy’s Equation:
2
𝑓𝐿𝑣
ℎ𝑓 = 2𝑔𝐷
𝐴𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 𝑃𝑤 = γ𝑄ℎ
𝐴𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 𝑃𝑤
𝑄= γℎ
π 2
𝐴 𝑝
= ( 4 )(𝐷 𝑝
)
𝑠 𝑦
𝑃𝐷 𝑝
𝐹.𝑆.
= 2𝑡 𝑝
𝐹.𝑆.(𝑃𝐷 𝑝)
𝑡 𝑝
= 2𝑠 𝑦
𝐷𝑑 = 2𝐷𝑖 + 𝐷𝑝
𝐻𝑑 = (2 𝑡𝑜 3. 5)(𝑑)
31
For the number of Pipes needed for the Penstock, 𝑛𝑝
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑃𝑒𝑛𝑠𝑡𝑜𝑐𝑘
𝑛𝑝 = 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑃𝑖𝑝𝑒 𝐿𝑒𝑛𝑔𝑡ℎ 𝑝𝑒𝑟 𝑃𝑖𝑒𝑐𝑒
(𝐹)(𝐹.𝑆)
𝑛𝑏 = (𝐴𝑏)(𝑆𝑡)
𝑄
𝑣= 𝐴𝑝
𝑁 𝐵𝑃
𝑁 𝑠
= 𝑠/4
ℎ
120𝑓
𝑃= 𝑁
Machine Foundation
For Length,
𝐿 = 𝑏 + 2𝑐
For Width,
𝑊 = 𝑎 + 2𝑐
32
For volume of foundation,
𝑉𝐹 = (𝐴𝑇)(ℎ) = 𝐿 × 𝑊 × ℎ
𝑊𝐹
ℎ= δ𝐹×𝐿×𝑊
𝑚𝑖𝑛 𝑊𝐹 ≈ 1. 25 𝑊𝑒
𝑊𝐹+𝑊𝑒
𝑆𝐼 = 𝐴𝐵
𝑆𝐵𝐶
𝑆𝐷 = 𝐹.𝑆
𝑉𝐹
𝑁𝑜. 𝑜𝑓 𝑏𝑎𝑔𝑠 𝐶 = 𝑌𝐼𝐸𝐿𝐷
δ𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙
𝑎𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙𝑠 = 𝐵𝑢𝑙𝑘 𝑆𝐺×𝑠𝑡𝑑. δ𝑤𝑎𝑡𝑒𝑟
33
2.7 DESIGN ALTERNATIVES
For the alternative design 1, the type of turbine that will be used is a Tubular turbine. It is widely used in a
hydro power stations with the head of 2-30meters,The blades are fixed or can adjust manualy the efficient
turbine of this kind can produce a large quantity of water flow which passes unimpededly.
(Source:https://images.app.goo.gl/SzZuan9pZP6cgWNM9)
Tubular turbine is the horizontal shaft water turbine of which the flow channel approximates straight, it does
not have a water diversion volute and the blades could be fixed or rotary. According to the different types of
generator device, it could be classified as rim generator turbine and half-tubular turbine. The rotor of the rim
generator turbine was directly installed on the rim of the running wheel. The advantages are that the flow
channel is straight, the water flow is strong and high efficiency. But the linear velocity and perimeter of the
34
outer rim of blades is big, thus the rotating seal is difficult. Currently, the rim generator turbine model has
been rarely used. The half-tubular turbine was classified into S-type turbine、pit turbine and bulb turbine.
The structure of S-type turbine and pit turbine are simple, maintenance is easy but is low efficiency. They
are applicable for small-scaled hydropower stations generally. At present, the bulb turbine has been widely
used because of compact structure, steady operation and high efficiency. The power-making device was
decorated in a steel light bulb which flowed by water, the turbine and generator could connect directly or
Discussion:
From the topographic map, the water coming from an elevation of 12 m will reach down to 6 m below where
the powerhouse will be located. The difference between 12 m and 6 m results in 6 meters, which meets the
35
Fig 2-3: Topographic Map for Alternative 1
36
2.7.2 ALTERNATIVE 2 Hydroelectric Power Plant: Francis Turbine
The Francis turbine is a type of reaction turbine, a category of turbine in which the working fluid comes to
the turbine under immense pressure and the energy is extracted by the turbine blades from the working
fluid. A part of the energy is given up by the fluid because of pressure changes occurring in the blades of
the turbine, quantified by the expression of degree of reaction, while the remaining part of the energy is
extracted by the volute casing of the turbine. At the exit, water acts on the spinning cup-shaped runner
features, leaving at low velocity and low swirl with very little kinetic or potential energy left. The turbine's exit
tube is shaped to help decelerate the water flow and recover the pressure.
Discussion:
From the topographic map, the water coming from an elevation of 23 m will reach down to 2 m below where
the powerhouse will be located. The difference between 23 m and 2 m results is 21 meters, which meets
37
Fig. 2-6: Topographic Map for Alternative 2
38
Fig. 2-7: Total distance of the penstock for Alternative 2
For alternative 3, the type of Water Turbine that will be used is Kaplan Turbine. It works on the principle of
axial flow reaction where the water flows through the runner along the direction parallel to the axis of
(Source: https://theconstructor.org/practical-guide/kaplan-turbine-component-working/2904/)
The water coming from the penstock is made to enter the scroll casing. The guide vanes direct the water to
the runner blades. The vanes are adjustable and can adjust themselves according to the requirement of
39
flow rate. The water takes a 90 degree turn, so the direction of the water is axial to that of runner blades.
The runner blades start to rotate as the water strikes due to the reaction force of the water. From the runner
blades, the water enters into the draft tube where its pressure energy and kinetic energy decreases. Kinetic
energy gets converted into pressure energy resulting in increased pressure of the water. The rotation of the
turbine is used to rotate the shaft of the generator for electricity production.
Discussion:
From the topographic map, the water coming from an elevation of 15 m will reach down to 6 m below where
the powerhouse will be located. The difference between 15 m and 6 m results in 9 meters, which meets the
40
Fig.-9: Topographic Map for Alternative 3
41
Fig. 2-10: Total distance of the penstock for Alternative 3
42
(Source: http://www.electway.net/product/100-2000kW_tubular_turbine.html)
Discharge 3
98. 8 𝑚 /𝑠
43
Design Alternative 2: Francis Turbine
(source:https://www.alibaba.com/product-detail/5MW-High-Efficiency-Francis-Hydro-Turbine_62022146805.html?spm
=a2700.galleryofferlist.normal_offer.d_title.17f84bd10R2aaV)
Discharge 28. 3 𝑚 /𝑠
3
Power 5350 KW
Efficiency 90.7%
44
Design Alternative 3: Kaplan Turbine
(Source:http://www.electway.net/product/500-5000kW_ZZK_kaplan_turbine(head_10-20m_).html)
Water Head 9m
Discharge 63.5 𝑚 /𝑠
3
45
CHAPTER 3
PROJECT DESIGN
Parameters Result
Generator Efficiency 95 %
46
MACHINE FOUNDATION:
Parameters Result
PROJECT COSTING:
Parameters Result
47
Return of Investment 24.16%
For the computation of Project Costing, See Appendix D.
Parameters Result
Net Head 21 m
MACHINE FOUNDATION:
Parameters Result
48
Weight of Engine, 𝑊𝑒 147 metric tons
PROJECT COSTING:
Parameters Result
49
Net income of the power plant 421,416,980 PHP
Parameters Result
Net Head 9m
MACHINE FOUNDATION:
Parameters Result
50
Weight of Engine 142 metric tons
PROJECT COSTING:
Parameters Result
51
CHAPTER 4
SECTION 1. Short Title. - This Act shall be known as the "Philippine Clean Water Act of 2004."
SECTION 2. Declaration of Policy. - The State shall pursue a policy of economic growth in a
manner consistent with the protection, preservation, and revival of the quality of our fresh, brackish,
and marine waters. To achieve this end, the framework for sustainable development shall be
52
c) To formulate a holistic national program of water quality management that recognizes
that water quality management issues cannot be separated from concerns about water
sources and ecological protection, water supply, public health and quality of life;
e) promote commercial and industrial processes and products that are environment
f) To encourage cooperation and self-regulation among citizens and industries through the
application of incentives and market-based instruments and to promote the role of private
industrial enterprises in shaping its regulatory profile within the acceptable boundaries of
pollution prevention;
i) To formulate and enforce a system of accountability for short and long-term adverse
j) To encourage civil society and other sectors, particularly labor, the academe and
and motivate 81 the people in addressing pertinent environmental issues and problems at
SECTION 3. Coverage of the Act. - This Act shall apply to water quality management in all water
bodies: Provided, that it shall primarily apply to the abatement and control of pollution from
land-based sources: Provided, further, That the water quality standards and regulations and the
53
civil liability and penal provisions under this Act shall be enforced irrespective of sources of
pollution.
Chapter 1 Standards
Section 5: Community Noise Standards. Appropriate standards for community noise levels shall be
established considering, among others, location, zoning and land use classification.
Section 6: Standards for Noise-Producing Equipment. There shall be established a standard for
engines, and electrical or electronic equipment and such similar equipment or contrivances. The
standards shall set a limit on the acceptable level of noise emitted from a given equipment for the
protection of public health and welfare, considering among others, the magnitude and condition of
use, the degree of noise reduction achievable through the application of best available technology
and the cost of compliance. The Installation of any noise-producing equipment shall conform with
the requirements of 77 Presidential Decree No. 1096 and other applicable laws as well as their
Section 15. Classification of Philippine Waters. The National Pollution Control Commission, in
coordination with appropriate government agencies, shall classify Philippine waters, according to
their best usage. In classifying said waters, the National Pollution Control Commission shall take
(a) the existing quality of the body of water at the time of classification.
54
(b) the size, depth, surface area covered, volume, direction, rate of flow, gradient of stream; and
(c) the most beneficial uses of said bodies of water and lands bordering them for residential,
Section 18. Water Quality Standards. The National Pollution Control Commission shall prescribe
quality and effluent standards consistent with the guidelines set by the National Environmental
Protection Council and the classification of waters prescribed in the preceding sections, taking into
(a) the standard of water quality or purity may vary according to beneficial uses; and
Section 24. Location of Industries. In the location of industries, factories, plants, depots and similar
industrial establishments, the regulating or enforcing agencies of the government shall take into
consideration the social, economic, geographic, and significant environmental impact of said
establishments.
may be declared by the Department of Natural Resources (DENR) as a protected area. Rules and
regulations may be promulgated by such Department to prohibit or control such activities by the owners or
occupants thereof within the protected area which may damage or cause the deterioration of the surface
water or groundwater or interfere with the investigation, use, control, protection, management or
55
202.1 Basis of Structure Design. For Industrial works, the utilization demand of the industry
for which the building is to be used were of utmost importance in the design of buildings.
Aside from geographical location and economic consideration, the mechanical and
electrical equipment requirements are extremely important for all modern buildings,
particularly factories.
● The weight of the machine plus the weight of the foundation should be
bearing stress within the safe bearing capacity of the soil with a factor of
measure of Portland cement of two (2) measures of sand and four (4)
56
measures of screened crushed stones. The machine should not be placed
on the foundation until seven (7) days have elapsed or operated until
(a) Materials. The foundation should be concrete of 1-part cement, 2 parts sand
and 4 parts broken stone or gravel (maximum of 50 mm); the entire foundation
should be poured at one time, with no interruptions that are required for spading
and ramming. The top should be level and left rough for grouts. After pouring, the
top should be covered and wet down twice daily until the 76 forms are removed at
the end of the third or fourth day. The engine should not be placed on the
foundation until 10 days have elapsed, nor operated until after another 10 days.
(b) Soil Bearing Pressure. The first objective is achieved by making its supporting
area sufficiently large. The safe loads vary from about 4,890 kg/m^2 for alluvial
soil or wet clay, to (12,225 kg/m^2. The latter is assumed to be a safe load
(c) Depth. The foundation may be taken as a good practical rule, to be 3.2 to 4.2
times the engine stroke, the lower factor for well-balanced multi-cylinder engines
and higher factor for engines with fewer cylinders, or on less firm soil.
57
1012.01: Work Conditions or Practices Not Covered by Standards Any specific rule applicable to a
condition, practice, means, methods, operations or processes shall also apply to other similar work
death or serious physical harm before abatement under the enforcement procedures can
be accomplished.
● When an enforcement officer finds that an imminent danger exists in a workplace, he shall
inform the affected employer and workers of the danger and shall recommend to the
Regional Director the issuance of an Order for stoppage of operation or other appropriate
action for the abatement of the danger. Pending the issuance of the Order the employer
● Upon receipt of such recommendation, the Regional Director shall immediately determine
whether the danger exists and is of such a nature as to warrant the issuance of a
● The Order shall require specific measures that are necessary to avoid, correct or remove
such imminent danger and to prohibit the presence of any worker in such location where
such danger exists, except those whose presence are necessary to avoid, correct or
of operation is ordered, the Order shall allow such correction, removal, or avoidance of
danger only where the same can be accomplished in a safe and orderly manner.
● Immediately after the issuance of a Stoppage Order, the Regional Director shall furnish the
Secretary, through the Director, within forty-eight (48) hours a copy of the Order and all pertinent
58
papers relating thereto, together with a detailed description of the work conditions sought to be
corrected, the safety and health rule violated by the employer, and the corrective measures
imposed. The Secretary shall review the Order issued by the Regional Director and within a period
of not more than five (5) working days, issue a final Order either lifting or sustaining the Order of
● For purposes of this Standards, the following are considered "hazardous workplaces:"
● Where the nature of work exposes the workers to dangerous environmental elements,
● Where the workers are engaged in construction work, logging, firefighting, mining, quarrying,
● Where the workers are engaged in the manufacture or handling of explosives and other
pyrotechnic products;
● Where the workers use or are exposed to power driven or explosive powder actuated tools;
● Where the workers are exposed to biologic agents such as bacteria, fungi, viruses, protozoa,
1074.01: Threshold Limit Values for Noise The threshold limit values refer to sound pressure that
represents conditions under which it is believed that nearly all workers may be repeatedly exposed
without adverse effect on their ability to hear and understand normal speech.
● Feasible administrative or engineering controls shall be utilized when workers are exposed
to sound levels exceeding those specified in Table 8b hereof when measured on a scale of
59
a standard sound level meter at slow response. If such controls fail to reduce sound within
the specified levels, ear protective devices capable of bringing the sound level to
permissible noise exposure shall be provided by the employer and used by the worker.
1074.03:
(1) The values specified in Table 4-1 apply to total time of exposure per working day regardless of
whether this is one continuous exposure or a number of short-term exposures but does not apply
(2) If the variation in noise level involves maximum intervals of one (1) second or less, it shall be
considered as continuous. If the interval is over one (1) second, it becomes impulse or impact
noise. (3) When the daily noise exposure is composed of two or more periods of noise exposure of
different levels, their combined effect should be considered rather than the effect of each.
60
1412.01: Health and Safety Committee At every construction site there shall be organized and
maintained a Health and Safety Committee conforming with Rule 1040 and a medical and dental
1412.02: Alternative Methods and Materials In the application of this Rule, the construction,
composition, size, and arrangement of materials used may vary provided that the strength of the
1412.04: Machine Guarding: All moving parts of machinery used shall be guarded in accordance
1412.08: Pipelines: Repair work on any section of a pipeline under pressure shall not be
undertaken until the pipeline is released of the pressure or the section under repair is blocked off
1412.09: Protection of the Public: A safe covered walkway shall be constructed over the sidewalk
for use by pedestrians in a building construction work less than 2.3 m. (7 ft.) from a sidewalk or
public road.
1412.10: Protection from Falling Materials: (1) Steps shall be taken to protect workers from falling
materials, such as the provision of safety helmets and safety shoes. (2) Tools, objects and
materials (including waste materials) shall not be thrown or tipped from a height, but shall be
properly lowered by crane, hoist or chutes. If such is not practicable, the area where the material is
thrown or lowered shall be fenced and no person allowed in the fenced area.
1412.12: Protection against Collapse of Structure: (1) All temporary structures shall be properly
supported by the use of guys, stays, and other fixings necessary for stability during construction.
(2) Where construction work will likely reduce the stability of an existing or adjacent building,
shoring shall be undertaken to prevent the collapse or fall of any part of the structure.
61
1412.20: Personal Protective Equipment: Personal Protective equipment as required in Rule 1080
2.1 Basis of Structure Design. For Industrial works, the utilization demand of the industry
for which the building is to be used are of utmost importance in the design of buildings.
Aside from geographical location and economic consideration, the mechanical and
electrical equipment requirements are extremely important for all modern buildings,
particularly factories.
2.2 Requirements for number, size, location and height of rise for elevators with particular
● General requirements for plumbing with particular attention to the location of soil
stacks, standpipes, main pumps, water storage tanks and sprinkler systems.
and accessories, such as fuel storage, the probable location of steam mains and
ducts and their approximate sizes in order to avoid interference with a structure
locations may influence the framing of the building and the necessary space
required for the electric conduits often affect the floor design.
62
● For industrial buildings, all specific demands of the manufacturing processes such
identified.
5.1 All machines/equipment which characteristically generate noise shall be provided with
appropriate enclosures to control emissions so as not to cause ambient noise level higher
than the quality standards set by the government agency concerned. If impractical, the
building housing the same should be appropriately designed or should be provided with
5.2 Buildings intended for noisy manufacturing activities should be appropriately designed
or should be provided with means so as not to cause ambient noise levels higher than the
Chapter 4 – Machine guards and safeties at points of operation and danger zones
considered the last line of defense against hazards in the work environment. The engineer
shall specify and require the use of PPE to protect personnel from known or possible
16.2 Employers shall protect their employees by providing appropriate and approved
protective tools, devices, equipment and appliances such as but not limited to the
following:
● Head Guards
● Face Shields
● Eye Goggles
63
● Ear Muffs
● Nose Aspirator
● Hand Gloves
The proponents will consider the 6 types of constraints based on the requirement for the Mechanical
● Economical - This will include the costs that will have an impact on budget allocation. Such
considerations are Capital Cost, Net Income of the Powerplant and Return of Investment.
● Environmental - This factor honors the ecosystem integrity of the design. Air pollution is highest in
this consideration, branching up to global warming, defining the carbon emission of each design.
● Societal - Societal concern is a relatively new term and refers to hazards with the capability to
decision makers for they oftentimes have major policy implications yet frequently lack the analytic
64
● Health and Safety - This factor shall answer the safety of both workers and the public. This shall
also assess the long-term and short-term health impacts of the design during operation, which may
can be made (or manufactured.) Manufacturability is in many ways dictated by a part’s design, and
can have huge implications as to the cost and effectiveness of the end product.
● Sustainability - Sustainability is the balance between the environment, equity, and economy. When
we hear the word “sustainability” we tend to think of renewable fuel sources, reducing carbon
emissions, protecting environments and a way of keeping the delicate ecosystems of our planet in
balance.
Economical 1 1 1 1 1 5
Environmental 0 1 1 0 1 3
Manufacturability 0 0 0 0 0 0
Sustainability 0 1 1 1 1 4
Societal 0 0 0 1 0 1
Total 15
Table 4-2: Pairwise Comparison
For value of x,
100% = 4x + 3x + 5x
65
x = 8.333 %
Economical vs Environmental
When choosing which factor is always considered, the client always tends to look at the budget allocation
first rather than considering the things that might affect the environment. The way how the power plant will
be constructed will be the one to decide what will happen to the environment.
66
Economical vs Health & Safety
Preparing for the budget allocation is always being considered by the client most of the time. Meanwhile,
ensuring the safety of everyone is a must. Before considering the safety of men, it is also important that the
Economical vs Manufacturability
Efficient limitation was given greater need over manufacturability requirement on the grounds that as
specialists, should esteem the customer's financial limit and assets. Likewise, engineers are entrusted to
rearrange plans and not over muddle them in this way prompting a lot of costly expenses.
Economical vs Sustainability
Sustainable power source ventures require immense capital speculations. In any case, if the said ventures
end up being a progressively maintainable type of vitality creation, manageability's advantages far exceed
monetary limitations.
Economical vs Societal
Jobs are created once the power plant has been installed, any of the alternatives would offer a job to
society. And from the point of view of the proponent, it is easier to give priority to considering which of the
It has been the premier obligation of a mechanical designer to survey the wellbeing and security of general
society. Natural laws ensure the government assistance of the general population. The proponents picked
Environmental vs Manufacturability
Ecological imperative was given a need over manufacturability limitation. It isn't best if the force plant is
simpler to build, however it will possess a huge territory of land, utilize a huge volume of water sources
67
Environmental vs Societal
The estimation of the natural effect for the structure power plant is generally important. The force plant can't
be raised on the off chance that it might influence the lives living among it. In this way, the chance of work
for the individuals won't be conceivable. In this way, advocates esteem nature more than culture.
The health and safety of the people must be prioritized first. To ensure the good production of the power
plant, the workers must be healthy, first. So, the proponents considered health and safety over
manufacturability.
To provide the needs that must be met within the society caused by the design, health and safety must be
evaluated first. The proponents have considered health and safety as more important.
Sustainability vs Environmental
Even if the proponents give value to the importance of the environment, especially the use of land for the
residents, the proponents decided to give a higher priority to Sustainability. Without giving it high
consideration, the power plant’s life span might not be for long.
The proponents choose to design a Hydro electric power plant because we need a sustainable source of
electricity, although health and safety is a major concern, sustainability should be given more importance.
Sustainability vs Manufacturability
The materials and availability of materials are no doubt important but ensuring the source of energy and the
plant’s lifespan is given more importance by the proponents
Sustainability vs Societal
68
Sustainability was given priority over societal. Societal concerns such as public disturbances due to
irregularly distributed noise impulses and almost continuous noise within the community are necessary
sacrifices if it means that the power plant can sustain the demand for electricity.
Societal vs Manufacturability
Raising a force plant is essential to guarantee that it is fit for keeping up or meeting the structure limit. Be
that as it may, open unsettling influence is one of the cultural elements to be considered. The administration
or a region won't permit the erection of a force plant in the event that it is a disturbance to people in
4.3.1.1 Considerations
● Capital Cost - It is the total cost needed to bring a power plant project to a commercially operable
status. For investors, cost of capital is the opportunity cost of making a specific investment.
● Annual Net Income - In business and accounting, net income (also total comprehensive income,
net earnings, net profit, bottom line, sales profit, or credit sales) is an entity's income minus cost of
● Return of Investment - Return of Investment or ROI is a financial ratio used to calculate the benefit
an investor will receive in relation to their investment cost. It is most commonly measured as net
income divided by the original capital cost of the investment. The higher the ratio, the greater the
benefit earned.
69
4.3.1.2 Trade-offs
Capital Cost 2 3 2
Return of Investment 2 3 2
Score 6 9 6
Table 4-4: Economical Trade-offs
Analysis of data:
In terms of the Economical Constraint, Alternative 2 is the most favorable as it has a lower capital cost
among the three (3), and has an annual income and Return of Investment greater than the two (2), hence
Alternative 2 scored 9 while Alternative 1 and 3 both scored 6 because of their equal results.
4.3.1.3 Justification
4.3.2.1 Considerations
● Efficiency - This criteria specifies the overall capacity that is produced by a Hydropower plant.
70
● Flexibility - The ability of the Hydropower plant to manufacture power output to the unstable
● Maintenance and Operation - Maintaining the quality of the Hydropower plant will guarantee an
excellent result of operation. A properly executed operation and solidity of the equipment ensure
the efficiency of the performance and life span of the power plant.
● Installation - This specifies the estimated time the Hydropower plant will be installed.
4.3.2.2 Trade-offs
Efficiency 1 2 3
Flexibility 1 1 3
Installation 3 1 2
Maintenance and 3 1 2
Operation
Score: 8 5 9
Table 4-7: Sustainability Trade-offs
The table states that the favorable option of the plant for criteria of sustainability are both the alternatives 1
and 3. For efficiency, alternatives 1 and 2 have almost the same value lower than alternative 3. The latter is
also more flexible as it is suitable for either low and medium head range, whereas alternative 1 is more
efficient for a home hydropower station while alternative 2 is more efficient with a range of 100-300 m head.
71
As for the installation, the three (3) got different scores, being alternative 1 the highest. Due to it’s small
dimension and less submergence needed, this is easier to install than the two (2, same goes for the
maintenance and operation. Alternative 2 got the lowest score as dismantling of its parts is hard.
4.3.2.3 Justification
Efficiency The turbine efficiency of The turbine efficiency of The turbine efficiency of
alternative 1 based on alternative 2 based on alternative 3 based on
the computation is the computation is the computation is
90.53%. 90.7%. 93.92%.
Installation More favourable flow Installation gets more The Kaplan turbine
conditions because the complex when the rock offers an advantage
dimension may be available is at very high with its smaller
smaller than Kaplan and depth. dimensions than
construction period is Francis. It is easy to
also short. The flow construct and space
condition will also requirement is less.
reduce the cavitation
risk for the bulb turbine,
which means a less
submergence is
needed.
Maintenance and Since the size may be Because the casing is Cavitation may also be
Operation smaller than Kaplan and stranded, it is very hard a problem but can be
a less submergence is to dismantle the runner. solved to some extent
needed, it is easier to The repair and by choosing the right
resolve the sand inspection are much blade.
erosion. The flow harder reasonably. The
72
condition of Alternative cavitation may be
1 can also reduce the reduced but the turbine
cavitation risk. and the outlet channel
must be placed lower
than the lake or sea
level outside.
4-8: Sustainability Justifications
4.3.3.1 Considerations
● Preservation of Ecology - This category reduce harm to the environment from human activities
especially logging.
● Impact on Aquatic Habitat - The impoundment of water and subsequent changes to flow velocity
and natural flow regimes have a demonstrated potential to negatively affect the diversity and
abundance of stream invertebrates that provide key trophic resources in river networks. Increased
velocity causes erosion of silt and sediment and sometimes wash away the aquatic organism's
colony.
4.3.3.2 Trade-offs
Preservation of Ecology 3 1 2
Impact on Aquatic 3 2 3
Habitat
Score 6 3 5
Table 4-9: Environmental Trade-offs
Analysis of the data:
73
The proponents base the scoring of preservation of ecology on the penstock’s length because trees might
be cut during the power plant construction. Alternative 1 got the highest points for having short length
among the three, alternative 3 had average length and got a score of 2. Lastly, alternative 2 got the lowest
For the impact on aquatic habitat, the proponents base the scoring on the fish habitats that will affect
because of the water flow velocity. Alternative 1 and 3 got the tie score of 3 and Alternative 2 ranked the
lowest.
4.3.3.3 Justification
Formula:
Result = Score ×percentage
74
Environmental (24.99%) 1.5 0.75 1.25
Sensitivity Analysis is the investigation of unclearness, in view of the yield of a framework can be
disseminated to various wellsprings of dubiousness in its sources of info which is implemented by the
proponents in order to select the best option of design based on the different constraints that were chosen.
The proponents give thought to the different possible arrangements of the (3) major constraints.
The total number of the possible arrangements can be solved using n! Where n is the number of chosen
constraints, if n = 3; n! = 3! ≈ n! = 6
4.4.1 Arrangements
75
Weight Total 2.31 2.31 2.35
Table 4-11: Arrangement 1
76
Weight Total 2.13 1.98 2.10
Table 4-15: Arrangement 5
Based on the Arrangement 1, the weight total of alternative 1 and alternative got the same score while
alternative 3 ranked first. For arrangement 2, it was alternative 1 and 3 which had the same score with the
alternative 2 winning. For arrangement 3, alternative 3 won but for arrangement 4 and 5, alternative 1
ranked first. Meanwhile on arrangement 6, alternative 1 and 3 got the same score while alternative 2 loses.
77
Total Average Score = Total Score/6
CHAPTER 5
FINAL DESIGN
5.1 Conclusion
After analyzing the data, considering the constraints and evaluating the trade-offs, the proponents
concluded that the Alternative 3 is the ideal type of Hydropower plant in Gandara river for the San, Jorge
Samar.
78
Figure 5.1 Topography map of the Alternative 3
From the topographic map, the water coming from an elevation of 15 m will reach down to 6 m below where
the powerhouse will be located. The difference between two points equals 9 meters, for the alternative 3
79
Net Head 9m
MACHINE FOUNDATION:
Parameters Result
80
No. Bags of cement 1,537 pcs
PROJECT COSTING:
Parameters Result
81
Manufacturer’s Data for Design Alternative 3: Kaplan Turbine
Water Head 9m
Discharge 63.5 𝑚 /𝑠
3
82
APPENDIX A
𝐻𝑁𝐸𝑇 = 𝐻𝐺𝑅𝑂𝑆𝑆
𝐻𝐺𝑅𝑂𝑆𝑆 = 12 𝑚 − 6 𝑚
83
𝐻𝐺𝑅𝑂𝑆𝑆 = 6 𝑚
Where:
𝐸𝑙𝑒𝑐𝑡𝑟𝑖𝑐𝑎𝑙 𝑃𝑜𝑤𝑒𝑟
η𝑔 = 𝑇𝑢𝑟𝑏𝑖𝑛𝑒 𝑃𝑜𝑤𝑒𝑟
5000 𝐾𝑊
η𝑔 = 5263 𝐾𝑊
η𝑔 = 0. 9500 ≈ 95. 00 %
Where:
3
γ 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟 = 9. 8066 𝑘𝑁/𝑚
3
𝑄 𝑜𝑓 𝑇𝑢𝑏𝑢𝑙𝑎𝑟 𝑇𝑢𝑟𝑏𝑖𝑛𝑒 = 98. 8 𝑚 /𝑠
𝑃𝑊 = γ𝑄𝐻𝑁𝐸𝑇
3
𝑘𝑁 𝑚
𝑃𝑊 = (9. 8066 3 )(98. 8 𝑠
)(6 𝑚)
𝑚
𝑃𝑊 = 5, 813. 35 𝑘𝑊
𝑇𝑢𝑟𝑏𝑖𝑛𝑒 𝑃𝑜𝑤𝑒𝑟
η𝑡 = 𝑊𝑎𝑡𝑒𝑟 𝑃𝑜𝑤𝑒𝑟
5263 𝑘𝑊
η𝑡 = 5813.35 𝑘𝑊
84
Where:
𝐻 = 𝑛𝑒𝑡 ℎ𝑒𝑎𝑑
𝑥 = 𝑑𝑖𝑠𝑡𝑎𝑛𝑐𝑒 𝑓𝑟𝑜𝑚 𝑠𝑢𝑐𝑡𝑖𝑜𝑛 𝑝𝑖𝑝𝑒 𝑡𝑜 𝑑𝑖𝑠𝑐ℎ𝑎𝑟𝑔𝑒 𝑝𝑖𝑝𝑒 (312. 5 𝑚 𝑏𝑎𝑠𝑒𝑑 𝑜𝑛 𝐹𝑖𝑔. 2 − 10)
−1 𝐻
θ = 𝑡𝑎𝑛 ( 𝑥
)
−1 6𝑚
θ = 𝑡𝑎𝑛 ( 312.5 𝑚 )
θ = 1. 09
𝐻
𝐿𝑝 = 𝑆𝑖𝑛θ
6𝑚
𝐿𝑝 = 𝑆𝑖𝑛(1.099944)
𝐿𝑝 = 312. 55 𝑚
2 2
(𝑛𝑝) (𝑄) (𝐿𝑝) 0.1875
𝐷𝑝 = 2. 69[ 𝐻𝑔
]
Where:
85
2 3 2
(0.012) (98.8 𝑚 /𝑠) (312.55 𝑚) 0.1875
𝐷𝑝 = 2. 69[ 6𝑚
]
𝐷𝑝 = 6. 0169 𝑚
2
Π(𝐷𝑝)
𝐴𝑝 = 4
2
Π(6.0169 𝑚)
𝐴𝑝 = 4
2
𝐴𝑝 = 28. 43 𝑚
𝑃𝐷𝑝𝐹.𝑆
𝑡𝑝 = 2𝑆𝑦
Where:
𝐹. 𝑆 = 2 (𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑)
As for,
𝑃 = γℎ
𝑘𝑁
𝑃 = (9. 8066 3 )(6 𝑚)
𝑚
86
𝑃 = 58. 8396 𝑘𝑃𝑎
Hence,
𝑡𝑝 = 0. 0014 𝑚
𝐻𝑑 = (2 𝑡𝑜 3. 5)𝐷𝑝
𝐻𝑑 = 16. 5465 𝑚
𝐷𝑑 = 2𝐷𝑖 + 𝐷𝑝
87
Where:
𝐷𝑖 = 𝑖𝑛𝑐𝑟𝑒𝑎𝑠𝑒 𝑖𝑛 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟
Sin law,
𝐷𝑖 𝐻𝑑
◦ = ◦
𝑠𝑖𝑛 4 𝑠𝑖𝑛 86
◦
𝑠𝑖𝑛 4
𝐷𝑖 = 𝐻𝑑( ◦ )
𝑠𝑖𝑛 86
◦
𝑠𝑖𝑛 4
𝐷𝑖 = 16. 5465 𝑚 ( ◦ )
𝑠𝑖𝑛 86
𝐷𝑖 = 1. 157 𝑚
Then,
𝐷𝑑 = 2𝐷𝑖 + 𝐷𝑝
𝐷𝑑 = 8. 3309 𝑚
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑃𝑒𝑛𝑠𝑡𝑜𝑐𝑘
𝑛𝑝𝑖𝑝𝑒 = 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑝𝑖𝑝𝑒 𝑙𝑒𝑛𝑔𝑡ℎ 𝑝𝑒𝑟 𝑝𝑖𝑒𝑐𝑒
88
Where:
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑃𝑒𝑛𝑠𝑡𝑜𝑐𝑘
𝑛𝑝𝑖𝑝𝑒 = 𝑚
6 𝑝𝑖𝑒𝑐𝑒𝑠
312.55 𝑚
𝑛𝑝𝑖𝑝𝑒 = 𝑚
6 𝑝𝑖𝑒𝑐𝑒𝑠
𝑆𝑡 𝐹 (𝐹)(𝐹.𝑆)
𝐹.𝑆
= (𝐴𝑏)(𝑛𝑏)
→ 𝑛𝑏 = (𝐴𝑏)(𝑆𝑡)
Where:
𝐹. 𝑆 = 2 (𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑)
𝐹
𝑃= 𝐴𝑝
→ 𝐹 = (𝑃)(𝐴𝑝)
2 2
𝐹 = (58. 8396 𝑘𝑁/𝑚 )(28. 43 𝑚 )
𝐹 = 1672. 8098 𝑘𝑁
89
And Area of Bolts,
2
Π(0.02541 𝑚)
𝐴𝑏 = 4
2
𝐴𝑏 = 0. 000507 𝑚
Therefore,
(𝐹)(𝐹.𝑆)
𝑛𝑏 = (𝐴𝑏)(𝑆𝑡)
(1672.8098 𝑘𝑁)(2)
𝑛𝑏 = 2 2
(0.000507 𝑚 )(100,000 𝑘𝑁/𝑚 )
𝑄
𝑄 = 𝐴𝑝𝑉→𝑉 = 𝐴𝑝
3
98.8 𝑚 /𝑠
𝑉= 2
28.43 𝑚
𝑉 = 3. 475 𝑚/𝑠
Machine Foundation
First step in designing a machine foundation: Start with the simplest form which is the rectangular block
machine foundation.
90
For safety purposes,
𝑊𝑓 ≥ 𝑚𝑖𝑛. 𝑊𝑓
Then,
The foundation mass should be from 3 to 5 times the weight of the machinery it is supposed to support.
𝐿 = 𝑏 + 2(𝑐)
Where:
also, clearance (c) to be used is 1 m for the TBOC (Turbine Bearing Oil Control) and for the turbine to be
use,
so,
𝐿 = 𝑏 + 2(𝑐)
91
𝐿 = 5 + 2(1)
𝐿 = 7𝑚
Note: since the equipment to be supported is circular, we will use a square type foundation.
𝐴𝑇 = 𝐴𝐵 = 𝐿 𝑥 𝑊
2
𝐴𝑇 = 7 × 7 𝑚
2
𝐴𝑇 = 42 𝑚
ℎ = 5𝑚
𝑉𝑓 = 𝐿 𝑥 𝑊 𝑥 ℎ
3
𝑉𝑓 = 7 × 7 × 5 𝑚
3
𝑉𝑓 = 245 𝑚
92
Solving for Weight of the Foundation, 𝑊𝑓
𝑘𝑔
𝑛𝑜𝑡𝑒: γ𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 = 2, 400 3
𝑚
𝑊𝑓 = γ𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 𝑥 𝑉𝑓
𝑘𝑔 3
𝑊𝑓 = 2, 400 3 × 245 𝑚
𝑚
𝑊𝑓 = 588, 000 𝑘𝑔
𝑊𝑒 = 𝑊𝑇 + 𝑊𝐺𝑒𝑛
From Possible Steps in Designing Machine Foundation by Power Plant Engineering by Frederick T. Morse.
𝑚𝑖𝑛. 𝑊𝑓 = 3 𝑡𝑜 5 𝑥 𝑊𝑒
1000 𝑘𝑔
𝑚𝑖𝑛. 𝑊𝑓 = 3 × 143 𝑚𝑒𝑡𝑟𝑖𝑐 𝑡𝑜𝑛𝑠 × 1 𝑚𝑒𝑡𝑟𝑖𝑐 𝑡𝑜𝑛
93
𝑚𝑖𝑛. 𝑊𝑓 = 429, 000 𝑘𝑔
Hence,
𝑊𝑓 ≥ 𝑚𝑖𝑛. 𝑊𝑓
Distribute the weight of the machine, the machine bed plate, and its own weight over a safe subsoil area.
𝑆𝑖 <𝑆𝑑
𝑊𝑓 + 𝑊𝑒
𝑆𝑖 = 𝐴𝐵
588,000 𝑘𝑔 + 143,000 𝑘𝑔
𝑆𝑖 = 2
42 𝑚
2
𝑆𝑖 = 17, 404. 762 𝑘𝑔/𝑚
𝑆𝐵𝑃
𝑆𝑑 = 𝐹.𝑆
94
Where: SBP = Soil Bearing Pressure
Ashlor Masonry 25 – 30
Sand 2–6
𝑒𝑛𝑔𝑙𝑖𝑠ℎ 𝑡𝑜𝑛
𝑆𝑜𝑖𝑙 𝐵𝑒𝑎𝑟𝑖𝑛𝑔 𝑃𝑟𝑒𝑠𝑠𝑢𝑟𝑒 = (5 − 8) 2
𝑓𝑡
𝑒𝑛𝑔𝑙𝑖𝑠ℎ 𝑡𝑜𝑛
𝑆𝐵𝑃𝐴𝑣𝑒 = (6 2
𝑓𝑡
2
𝑒𝑛𝑔𝑙𝑖𝑠ℎ 𝑡𝑜𝑛 2000 𝑙𝑏𝑠 1 𝑓𝑡
𝑆𝐵𝑃𝐴𝑣𝑒 = (6) 2 × 1 𝑈𝑆 𝑡𝑜𝑛
× 2 2
𝑓𝑡 0.3048 𝑚
𝑘𝑔
𝑆𝐵𝑃𝐴𝑣𝑒 = 129, 166. 925 2
𝑚
95
Note: Safe bearing pressure of soils for machine foundation area from quarter to a half of the above values.
𝑘𝑔
129,166.925 2
𝑚
𝑆𝑑 = 4
𝑘𝑔
𝑆𝑑 = 32, 291. 731 2
𝑚
Therefore,
𝑆𝑖 ≤𝑆𝑑
3 3
γ 𝑜𝑓 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 = 2, 400 𝑘𝑔/𝑚 = 149. 9339 𝑙𝑏𝑓/𝑓𝑡
3
γ 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟 =62. 4 𝑙𝑏𝑓/𝑓𝑡
96
Sand Gravel (𝒇𝒕3 Yield (𝒇𝒕3) 𝒐𝒇
(𝒇𝒕3 / /𝒃𝒂𝒈) 𝒄𝒐𝒏𝒄𝒓𝒆𝒕𝒆
Cement Cement (Bag C) 𝒃𝒂𝒈) 𝒃𝒂𝒈 𝒐𝒇
𝒄𝒆𝒎𝒆𝒏𝒕
AA 1 1.5 3 4.15077
A 1 2 4 5.063004
B 1 2.5 5 5.97524
C 1 3 6 6.88748
D 1 3 6 8.71195
Where,
For Cement,
𝑙𝑏 𝑓
94 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 = 𝑙𝑏𝑓
(3.15)(62.4 3 )
𝑓𝑡
3
𝑓𝑡 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 =. 478225 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
For Sand,
97
𝑙𝑏𝑓 𝑓𝑡
3
(110 3 )(2 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 )
𝑓𝑡
𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑠𝑎𝑛𝑑 = 𝑙𝑏𝑓
(2.64)(62.4 3 )
𝑓𝑡
3
𝑓𝑡 𝑜𝑓 𝑠𝑎𝑛𝑑
𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑠𝑎𝑛𝑑 = 1. 335470 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
For Gravel,
𝑙𝑏𝑓 𝑓𝑡
3
(96 3 )(4 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 )
𝑓𝑡
𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑠𝑎𝑛𝑑 = 𝑙𝑏𝑓
(2.66)(62.4 3 )
𝑓𝑡
3
𝑓𝑡 𝑜𝑓 𝑔𝑟𝑎𝑣𝑒𝑙
𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟 = 2. 313476 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
For Water,
3
𝑔𝑎𝑙 1 𝑓𝑡
𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟 = 7 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
𝑥 7.48 𝑔𝑎𝑙
3
𝑓𝑡 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟
𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟 =. 935829 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
3
𝑓𝑡
𝑌𝐼𝐸𝐿𝐷 = Σ(. 478225 + 1. 335470 + 2. 313476 + . 935829) 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
3
𝑓𝑡
𝑌𝐼𝐸𝐿𝐷 = 5. 063 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
𝑉𝑓
𝑁𝑜. 𝑜𝑓 𝐵𝑎𝑔𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 = 𝑌𝐼𝐸𝐿𝐷
98
3
3 3.28 𝑓𝑡
245 𝑚 ( 3 )
1𝑚
𝑁𝑜. 𝑜𝑓 𝐵𝑎𝑔𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 = 𝑓𝑡
3
5.063 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
Volume of Sand,
3
𝑓𝑡 𝑜𝑓 𝑠𝑎𝑛𝑑
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙 = (2 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 )(1708 𝐵𝑎𝑔𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡)
3
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑆𝑎𝑛𝑑 = 3416 𝑓𝑡 𝑜𝑓 𝑠𝑎𝑛𝑑
Volume of Gravel,
3
𝑓𝑡 𝑜𝑓 𝑔𝑟𝑎𝑣𝑒𝑙
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐺𝑟𝑎𝑣𝑒𝑙 = (4 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 )(1708 𝐵𝑎𝑔𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡)
3
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐺𝑟𝑎𝑣𝑒𝑙 = 6, 832 𝑓𝑡 𝑜𝑓 𝐺𝑟𝑎𝑣𝑒𝑙
Volume of Water,
3
𝑓𝑡 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟 = (. 935829 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
)(1708 𝐵𝑎𝑔𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡)
3
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐺𝑟𝑎𝑣𝑒𝑙 = 1598. 396 𝑓𝑡 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟
99
𝑊𝑅𝑆𝐵 = (. 5% − 1%) 𝑊𝑓
Taking the average from 0.5% to 1%, we will get 0.75% or 0.0075,
𝑊𝑅𝑆𝐵 = 4, 410 𝑘𝑔
APPENDIX B
𝐻𝐺𝑅𝑂𝑆𝑆 = 23 𝑚 − 2 𝑚
𝐻𝐺𝑅𝑂𝑆𝑆 = 21 𝑚
𝐺𝑒𝑛𝑒𝑟𝑎𝑡𝑜𝑟 𝑃𝑜𝑤𝑒𝑟
Solving for the Generator Efficiency; η𝑔 = 𝑇𝑢𝑟𝑏𝑖𝑛𝑒 𝑃𝑜𝑤𝑒𝑟
Where:
5000 𝐾𝑊
η𝑔 = 5350 𝐾𝑊
100
Solving for the Available Water Power, 𝑃𝑊; 𝑃𝑊 = γ𝑄𝐻𝑁𝐸𝑇
Where:
3
γ 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟 = 9. 8066 𝑘𝑁/𝑚
3
𝑄 𝑜𝑓 𝐾𝑎𝑝𝑙𝑎𝑛 𝑇𝑢𝑟𝑏𝑖𝑛𝑒 = 28. 3 𝑚 /𝑠
3
𝑘𝑁 𝑚
𝑃𝑊 = (9. 8066 3 )(28. 3 𝑠
)(21 𝑚)
𝑚
𝑃𝑊 = 5, 828. 1 𝑘𝑊 ≈ 5. 828 𝑀𝑊
𝑇𝑢𝑟𝑏𝑖𝑛𝑒 𝑃𝑜𝑤𝑒𝑟
Solving for the Turbine Efficiency; η𝑡 = 𝑊𝑎𝑡𝑒𝑟 𝑃𝑜𝑤𝑒𝑟
5350 𝑘𝑊
η𝑡 = 5828.1 𝑘𝑊
𝐻
Solving for the length of Penstock; 𝐿𝑝 = 𝑆𝑖𝑛θ
Where:
𝐻 = 𝑛𝑒𝑡 ℎ𝑒𝑎𝑑
101
θ = 𝑎𝑛𝑔𝑙𝑒 𝑓𝑟𝑜𝑚 𝑠𝑢𝑐𝑡𝑖𝑜𝑛 𝑝𝑖𝑝𝑒 𝑡𝑜 𝑑𝑖𝑠𝑐ℎ𝑎𝑟𝑔𝑒 𝑝𝑖𝑝𝑒
−1 𝐻
θ = 𝑡𝑎𝑛 ( 𝑥
)
−1 21 𝑚
θ = 𝑡𝑎𝑛 ( 413.83 𝑚 )
θ = 2. 905009701
21 𝑚
𝐿𝑝 = 𝑆𝑖𝑛(2.905009701))
𝐿𝑝 = 414. 3625 𝑚
2 2
(𝑛𝑝) (𝑄) (𝐿𝑝) 0.1875
Solving for the size of Penstock; 𝐷𝑝 = 2. 69[ 𝐻𝑔
]
Where:
2 3 2
(0.012) (28.3 𝑚 /𝑠) (414.3625 𝑚) 0.1875
𝐷𝑝 = 2. 69[ 21 𝑚
]
𝐷𝑝 = 3. 1384 𝑚
2
Π(𝐷𝑝)
Solving for the Area of the Penstock, 𝐴𝑝; 𝐴𝑝 = 4
2
Π(3.1383 𝑚)
𝐴𝑝 = 4
2
𝐴𝑝 = 7. 7358 𝑚
𝑃𝐷𝑝𝐹.𝑆
Solving for the Thickness of the Penstock, 𝑡𝑝; 𝑡𝑝 = 2𝑆𝑦
Where:
102
𝐹. 𝑆 = 2 (𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑)
As for,
𝑃 = γℎ
𝑘𝑁
𝑃 = (9. 8066 3 )(21 𝑚)
𝑚
Hence,
𝑡𝑝 = 0. 002585 𝑚
𝐻𝑑 = 8. 6306 𝑚
103
For the diameter of the draft tube, ; 𝐷𝑑 = 2𝐷𝑖 + 𝐷𝑝
Where:
𝐷𝑖 = 𝑖𝑛𝑐𝑟𝑒𝑎𝑠𝑒 𝑖𝑛 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟
𝐷𝑖 𝐻𝑑
Sin law; ◦ = ◦
𝑠𝑖𝑛 4 𝑠𝑖𝑛 86
◦
𝑠𝑖𝑛 4
𝐷𝑖 = 𝐻𝑑( ◦ )
𝑠𝑖𝑛 86
◦
𝑠𝑖𝑛 4
𝐷𝑖 = 8. 6306 𝑚 ( ◦ )
𝑠𝑖𝑛 86
𝐷𝑖 = 0. 6035 𝑚
Then,
𝐷𝑑 = 2𝐷𝑖 + 𝐷𝑝
104
𝐷𝑑 = 4. 3454 𝑚
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑃𝑒𝑛𝑠𝑡𝑜𝑐𝑘
Solving for the number of pipes needed for the penstock; 𝑛𝑝𝑖𝑝𝑒 = 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑝𝑖𝑝𝑒 𝑙𝑒𝑛𝑔𝑡ℎ 𝑝𝑒𝑟 𝑝𝑖𝑒𝑐𝑒
Where:
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑃𝑒𝑛𝑠𝑡𝑜𝑐𝑘
𝑛𝑝𝑖𝑝𝑒 = 𝑚
6 𝑝𝑖𝑒𝑐𝑒𝑠
414.3625 𝑚
𝑛𝑝𝑖𝑝𝑒 = 𝑚
6 𝑝𝑖𝑒𝑐𝑒𝑠
𝑆𝑡 𝐹 (𝐹)(𝐹.𝑆)
Solving for the number of bolts; 𝐹.𝑆
= (𝐴𝑏)(𝑛𝑏)
→ 𝑛𝑏 = (𝐴𝑏)(𝑆𝑡)
Where:
𝐹. 𝑆 = 2 (𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑)
𝐹
As for the Force; 𝑃 = 𝐴𝑝
→ 𝐹 = (𝑃)(𝐴𝑝)
2 2
𝐹 = (205. 9386 𝑘𝑁/𝑚 )(7. 7358 𝑚 )
105
𝐹 = 1593. 0998 𝑘𝑁
2
Π(0.02541 𝑚)
And Area of Bolts; 𝐴𝑏 = 4
2
𝐴𝑏 = 0. 000507 𝑚
Therefore,
(𝐹)(𝐹.𝑆)
𝑛𝑏 = (𝐴𝑏)(𝑆𝑡)
(1593.0998 𝑘𝑁)(2)
𝑛𝑏 = 2 2
(0.000507 𝑚 )(100,000 𝑘𝑁/𝑚 )
𝑄
Solving for Water Velocity; 𝑄 = 𝐴𝑝𝑉→𝑉 = 𝐴𝑝
3
28.3 𝑚 /𝑠
𝑉= 2
7.7358 𝑚
𝑉 = 3. 6583 𝑚/𝑠
Machine Foundation
First step in designing a machine foundation: Start with the simplest form which is the rectangular block
machine foundation.
106
The foundation mass should be from 3 to 5 times the weight of the machinery it is supposed to support.
Where:
also, clearance (c) to be used is 1 m for the TBOC (Turbine Bearing Oil Control) and for the turbine to be
use,
𝐿 = 𝑏 + 2(𝑐)
𝐿 = 6 + 2(1𝑚)
𝐿 = 8𝑚 = 𝑊
Note: since the equipment to be supported is circular, we will use a square type foundation.
2
𝐴𝑇 = (8)(8) 𝑚
107
2
𝐴𝑇 = 64 𝑚
ℎ = 5𝑚
3
𝑉𝑓 = (8 * 8 * 5) 𝑚
3
𝑉𝑓 = 320 𝑚
𝑘𝑔
𝑛𝑜𝑡𝑒: γ𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 = 2, 400 3
𝑚
𝑘𝑔 3
𝑊𝑓 = 2, 400 3 × 320 𝑚
𝑚
𝑊𝑓 = 768, 000 𝑘𝑔
108
𝑊𝑒 = 147 𝑚𝑒𝑡𝑟𝑖𝑐 𝑡𝑜𝑛𝑠
From Possible Steps in Designing Machine Foundation by Power Plant Engineering by Frederick T. Morse.
1000 𝑘𝑔
𝑚𝑖𝑛. 𝑊𝑓 = 4 × 147 𝑚𝑒𝑡𝑟𝑖𝑐 𝑡𝑜𝑛𝑠 × 1 𝑚𝑒𝑡𝑟𝑖𝑐 𝑡𝑜𝑛
𝑊𝑓 ≥ 𝑚𝑖𝑛. 𝑊𝑓
Distribute the weight of the machine, the machine bed plate, and its own weight over a safe subsoil area.
𝑆𝑖 <𝑆𝑑
𝑊𝑓 + 𝑊𝑒
For Induced Strength; 𝑆𝑖 = 𝐴𝑇
768,000 𝑘𝑔 + 147,000 𝑘𝑔
𝑆𝑖 = 2
64 𝑚
2
𝑆𝑖 = 14, 296. 875 𝑘𝑔/𝑚
109
𝑆𝐵𝑃
For Design Stress, 𝑆𝑑; 𝑆𝑑 = 𝐹.𝑆
Ashlar Masonry 25 – 30
Sand 2–6
𝑒𝑛𝑔𝑙𝑖𝑠ℎ 𝑡𝑜𝑛
𝑆𝑜𝑖𝑙 𝐵𝑒𝑎𝑟𝑖𝑛𝑔 𝑃𝑟𝑒𝑠𝑠𝑢𝑟𝑒 = (5 − 8) 2
𝑓𝑡
Using 7 as a value,
𝑒𝑛𝑔𝑙𝑖𝑠ℎ 𝑡𝑜𝑛
𝑆𝐵𝑃𝐴𝑣𝑒 = (5) 2
𝑓𝑡
2
𝑒𝑛𝑔𝑙𝑖𝑠ℎ 𝑡𝑜𝑛 2000 𝑙𝑏𝑠 1 𝑓𝑡
𝑆𝐵𝑃𝐴𝑣𝑒 = (5) 2 × 1 𝑈𝑆 𝑡𝑜𝑛
× 2 2
𝑓𝑡 0.3048 𝑚
110
𝑘𝑔
𝑆𝐵𝑃𝐴𝑣𝑒 = 107639. 1042 2
𝑚
Note: Safe bearing pressure of soils for machine foundation area from quarter to a half of the above values.
𝑘𝑔
107639.1042 2
𝑚
𝑆𝑑 = 4
𝑘𝑔
𝑆𝑑 = 26909. 7761 2
𝑚
3 3
γ 𝑜𝑓 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 = 2, 400 𝑘𝑔/𝑚 = 149. 9339 𝑙𝑏𝑓/𝑓𝑡
3
γ 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟 =62. 4 𝑙𝑏𝑓/𝑓𝑡
111
Sand Gravel (𝒇𝒕3 Yield (𝒇𝒕3) 𝒐𝒇
(𝒇𝒕3 / /𝒃𝒂𝒈) 𝒄𝒐𝒏𝒄𝒓𝒆𝒕𝒆
Cement Cement (Bag C) 𝒃𝒂𝒈) 𝒃𝒂𝒈 𝒐𝒇
𝒄𝒆𝒎𝒆𝒏𝒕
AA 1 1.5 3 4.15077
A 1 2 4 5.063004
B 1 2.5 5 5.97524
C 1 3 6 6.88748
D 1 3 6 8.71195
Where,
𝑙𝑏 𝑓
94 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
For Cement; 𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 = 𝑙𝑏𝑓
(3.15)(62.4 3 )
𝑓𝑡
3
𝑓𝑡 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 =. 478225 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
𝑙𝑏𝑓 𝑓𝑡
3
(110 3 )(2 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 )
For Sand; 𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑠𝑎𝑛𝑑 = 𝑓𝑡
𝑙𝑏𝑓
(2.64)(62.4 3 )
𝑓𝑡
112
3
𝑓𝑡 𝑜𝑓 𝑠𝑎𝑛𝑑
𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑠𝑎𝑛𝑑 = 1. 335470 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
𝑙𝑏𝑓 𝑓𝑡
3
(96 3 )(4 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 )
For Gravel; 𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑠𝑎𝑛𝑑 = 𝑓𝑡
𝑙𝑏𝑓
(2.66)(62.4 3 )
𝑓𝑡
3
𝑓𝑡 𝑜𝑓 𝑔𝑟𝑎𝑣𝑒𝑙
𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟 = 2. 313476 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
3
𝑔𝑎𝑙 1 𝑓𝑡
For Water; 𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟 = 7 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
𝑥 7.48 𝑔𝑎𝑙
3
𝑓𝑡 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟
𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟 =. 935829 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
3
𝑓𝑡
𝑌𝐼𝐸𝐿𝐷 = Σ(. 478225 + 1. 335470 + 2. 313476 + . 935829) 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
3
𝑓𝑡
𝑌𝐼𝐸𝐿𝐷 = 5. 063 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
𝑉𝑓
For Number of Bags of Cement; 𝑁𝑜. 𝑜𝑓 𝐵𝑎𝑔𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 = 𝑌𝐼𝐸𝐿𝐷
3
3 3.28 𝑓𝑡
320 𝑚 ( 3 )
1𝑚
𝑁𝑜. 𝑜𝑓 𝐵𝑎𝑔𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 = 𝑓𝑡
3
5.063 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
113
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙 = (𝑃𝑟𝑜𝑝𝑜𝑟𝑡𝑖𝑜𝑛 𝑜𝑓 𝑀𝐴𝑡𝑒𝑟𝑖𝑎𝑙)(𝑁𝑜. 𝑜𝑓 𝐵𝑎𝑔𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡)
3
𝑓𝑡 𝑜𝑓 𝑠𝑎𝑛𝑑
Volume of Sand; 𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑆𝑎𝑛𝑑 = (2 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 )(2230 𝐵𝑎𝑔𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡)
3
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑆𝑎𝑛𝑑 = 4460 𝑓𝑡 𝑜𝑓 𝑠𝑎𝑛𝑑
3
𝑓𝑡 𝑜𝑓 𝑔𝑟𝑎𝑣𝑒𝑙
Volume of Gravel; 𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐺𝑟𝑎𝑣𝑒𝑙 = (4 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 )(2230 𝐵𝑎𝑔𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡)
3
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐺𝑟𝑎𝑣𝑒𝑙 = 8920 𝑓𝑡 𝑜𝑓 𝐺𝑟𝑎𝑣𝑒𝑙
3
𝑓𝑡 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟
Volume of Water; 𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟 = (. 935829 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
)(2230 𝐵𝑎𝑔𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡)
3
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟 = 2086. 8987 𝑓𝑡 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟
𝑊𝑅𝑆𝐵 = (. 0065)768000 𝑘𝑔
𝑊𝑅𝑆𝐵 = 4992 𝑘𝑔
APPENDIX C
114
𝐻𝑁𝐸𝑇 = 𝐻𝐺𝑅𝑂𝑆𝑆
𝐻𝐺𝑅𝑂𝑆𝑆 = 15 𝑚 − 6 𝑚
𝐻𝐺𝑅𝑂𝑆𝑆 = 9 𝑚
Where:
𝐸𝑙𝑒𝑐𝑡𝑟𝑖𝑐𝑎𝑙 𝑃𝑜𝑤𝑒𝑟
η𝑔 = 𝑇𝑢𝑟𝑏𝑖𝑛𝑒 𝑃𝑜𝑤𝑒𝑟
5000 𝐾𝑊
η𝑔 = 5264 𝐾𝑊
η𝑔 = 0. 9498 ≈ 94. 98 %
Where:
3
γ 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟 = 9. 8066 𝑘𝑁/𝑚
3
𝑄 𝑜𝑓 𝐾𝑎𝑝𝑙𝑎𝑛 𝑇𝑢𝑟𝑏𝑖𝑛𝑒 = 63. 5 𝑚 /𝑠
𝑃𝑊 = γ𝑄𝐻𝑁𝐸𝑇
3
𝑘𝑁 𝑚
𝑃𝑊 = (9. 8066 3 )(63. 5 𝑠
)(9 𝑚)
𝑚
𝑃𝑊 = 5, 604. 47 𝑘𝑊
𝑇𝑢𝑟𝑏𝑖𝑛𝑒 𝑃𝑜𝑤𝑒𝑟
η𝑡 = 𝑊𝑎𝑡𝑒𝑟 𝑃𝑜𝑤𝑒𝑟
115
5264 𝑘𝑊
η𝑡 = 5604.67 𝑘𝑊
Where:
𝐻 = 𝑛𝑒𝑡 ℎ𝑒𝑎𝑑
−1 𝐻
θ = 𝑡𝑎𝑛 ( 𝑥
)
−1 9𝑚
θ = 𝑡𝑎𝑛 ( 351.8 𝑚 )
θ = 1. 46
𝐻
𝐿𝑝 = 𝑆𝑖𝑛θ
9𝑚
𝐿𝑝 = 𝑆𝑖𝑛(1.46546)
𝐿𝑝 = 351. 97 𝑚
116
2 2
(𝑛𝑝) (𝑄) (𝐿𝑝) 0.1875
𝐷𝑝 = 2. 69[ 𝐻𝑔
]
Where:
2 3 2
(0.012) (63.5 𝑚 /𝑠) (351.97 𝑚) 0.1875
𝐷𝑝 = 2. 69[ 9𝑚
]
𝐷𝑝 = 4. 8309 𝑚
2
Π(𝐷𝑝)
𝐴𝑝 = 4
2
Π(4.8309 𝑚)
𝐴𝑝 = 4
2
𝐴𝑝 = 18. 32 𝑚
𝑃𝐷𝑝𝐹.𝑆
𝑡𝑝 = 2𝑆𝑦
Where:
𝐹. 𝑆 = 2 (𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑)
As for,
117
𝑃 = γℎ
𝑘𝑁
𝑃 = (9. 8066 3 )(9 𝑚)
𝑚
Hence,
𝑡𝑝 = 0. 0017 𝑚
𝐻𝑑 = (2 𝑡𝑜 3. 5)𝐷𝑝
𝐻𝑑 = 13. 2850 𝑚
𝐷𝑑 = 2𝐷𝑖 + 𝐷𝑝
118
Where:
𝐷𝑖 = 𝑖𝑛𝑐𝑟𝑒𝑎𝑠𝑒 𝑖𝑛 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟
Sin law,
𝐷𝑖 𝐻𝑑
◦ = ◦
𝑠𝑖𝑛 4 𝑠𝑖𝑛 86
◦
𝑠𝑖𝑛 4
𝐷𝑖 = 𝐻𝑑( ◦ )
𝑠𝑖𝑛 86
◦
𝑠𝑖𝑛 4
𝐷𝑖 = 13. 2850 𝑚 ( ◦ )
𝑠𝑖𝑛 86
𝐷𝑖 = 0. 9290 𝑚
Then,
𝐷𝑑 = 2𝐷𝑖 + 𝐷𝑝
𝐷𝑑 = 6. 6889 𝑚
119
Solving for the number of pipes needed for the penstock
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑃𝑒𝑛𝑠𝑡𝑜𝑐𝑘
𝑛𝑝𝑖𝑝𝑒 = 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑝𝑖𝑝𝑒 𝑙𝑒𝑛𝑔𝑡ℎ 𝑝𝑒𝑟 𝑝𝑖𝑒𝑐𝑒
Where:
𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑃𝑒𝑛𝑠𝑡𝑜𝑐𝑘
𝑛𝑝𝑖𝑝𝑒 = 𝑚
6 𝑝𝑖𝑒𝑐𝑒𝑠
351.97 𝑚
𝑛𝑝𝑖𝑝𝑒 = 𝑚
6 𝑝𝑖𝑒𝑐𝑒𝑠
𝑆𝑡 𝐹 (𝐹)(𝐹.𝑆)
𝐹.𝑆
= (𝐴𝑏)(𝑛𝑏)
→ 𝑛𝑏 = (𝐴𝑏)(𝑆𝑡)
Where:
𝐹. 𝑆 = 2 (𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑)
120
𝐹
𝑃= 𝐴𝑝
→ 𝐹 = (𝑃)(𝐴𝑝)
2 2
𝐹 = (88. 2594 𝑘𝑁/𝑚 )(18. 32 𝑚 )
𝐹 = 1616. 9122 𝑘𝑁
2
Π(0.02541 𝑚)
𝐴𝑏 = 4
2
𝐴𝑏 = 0. 000507 𝑚
Therefore,
(𝐹)(𝐹.𝑆)
𝑛𝑏 = (𝐴𝑏)(𝑆𝑡)
(1616.9122 𝑘𝑁)(2)
𝑛𝑏 = 2 2
(0.000507 𝑚 )(100,000 𝑘𝑁/𝑚 )
𝑄
𝑄 = 𝐴𝑝𝑉→𝑉 = 𝐴𝑝
3
63.5 𝑚 /𝑠
𝑉= 2
18.32 𝑚
𝑉 = 3. 466 𝑚/𝑠
121
Machine Foundation
First step in designing a machine foundation: Start with the simplest form which is the rectangular block
machine foundation.
𝑊𝑓 ≥ 𝑚𝑖𝑛. 𝑊𝑓
Then,
The foundation mass should be from 3 to 5 times the weight of the machinery it is supposed to support.
𝐿 = 𝑏 + 2(𝑐)
Where:
122
also, clearance (c) to be used is 1 m for the TBOC (Turbine Bearing Oil Control) and for the turbine to be
use,
so,
𝐿 = 𝑏 + 2(𝑐)
𝐿 = 5 + 2(1)
𝐿 = 7𝑚
Note: since the equipment to be supported is circular, we will use a square type foundation.
𝐴𝑇 = 𝐴𝐵 = 𝐿 𝑥 𝑊
2
𝐴𝑇 = 7 × 7 𝑚
2
𝐴𝑇 = 42 𝑚
ℎ = 4. 5 𝑚
123
𝑉𝑓 = 𝐿 𝑥 𝑊 𝑥 ℎ
3
𝑉𝑓 = 7 × 7 × 4. 5 𝑚
3
𝑉𝑓 = 220. 5 𝑚
𝑘𝑔
𝑛𝑜𝑡𝑒: γ𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 = 2, 400 3
𝑚
𝑊𝑓 = γ𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 𝑥 𝑉𝑓
𝑘𝑔 3
𝑊𝑓 = 2, 400 3 × 220. 5 𝑚
𝑚
𝑊𝑓 = 529, 200 𝑘𝑔
𝑊𝑒 = 𝑊𝑇 + 𝑊𝐺𝑒𝑛
From Possible Steps in Designing Machine Foundation by Power Plant Engineering by Frederick T. Morse.
124
𝑚𝑖𝑛. 𝑊𝑓 = 3 𝑡𝑜 5 𝑥 𝑊𝑒
1000 𝑘𝑔
𝑚𝑖𝑛. 𝑊𝑓 = 3 × 142 𝑚𝑒𝑡𝑟𝑖𝑐 𝑡𝑜𝑛𝑠 × 1 𝑚𝑒𝑡𝑟𝑖𝑐 𝑡𝑜𝑛
Hence,
𝑊𝑓 ≥ 𝑚𝑖𝑛. 𝑊𝑓
Distribute the weight of the machine, the machine bed plate, and its own weight over a safe subsoil area.
𝑆𝑖 <𝑆𝑑
𝑊𝑓 + 𝑊𝑒
𝑆𝑖 = 𝐴𝐵
529,200 𝑘𝑔 + 142,000 𝑘𝑔
𝑆𝑖 = 2
42 𝑚
125
2
𝑆𝑖 = 15, 980. 9524 𝑘𝑔/𝑚
𝑆𝐵𝑃
𝑆𝑑 = 𝐹.𝑆
Ashlor Masonry 25 – 30
Sand 2–6
𝑒𝑛𝑔𝑙𝑖𝑠ℎ 𝑡𝑜𝑛
𝑆𝑜𝑖𝑙 𝐵𝑒𝑎𝑟𝑖𝑛𝑔 𝑃𝑟𝑒𝑠𝑠𝑢𝑟𝑒 = (5 − 8) 2
𝑓𝑡
126
𝑒𝑛𝑔𝑙𝑖𝑠ℎ 𝑡𝑜𝑛
𝑆𝐵𝑃𝐴𝑣𝑒 = (6. 5) 2
𝑓𝑡
2
𝑒𝑛𝑔𝑙𝑖𝑠ℎ 𝑡𝑜𝑛 2000 𝑙𝑏𝑠 1 𝑓𝑡
𝑆𝐵𝑃𝐴𝑣𝑒 = (6. 5) 2 × 1 𝑈𝑆 𝑡𝑜𝑛
× 2 2
𝑓𝑡 0.3048 𝑚
𝑘𝑔
𝑆𝐵𝑃𝐴𝑣𝑒 = 139, 930. 8354 2
𝑚
Note: Safe bearing pressure of soils for machine foundation area from quarter to a half of the above values.
𝑘𝑔
139,930.8354 2
𝑚
𝑆𝑑 = 4
𝑘𝑔
𝑆𝑑 = 34, 982. 7089 2
𝑚
Therefore,
𝑆𝑖 ≤𝑆𝑑
127
3 3
γ 𝑜𝑓 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 = 2, 400 𝑘𝑔/𝑚 = 149. 9339 𝑙𝑏𝑓/𝑓𝑡
3
γ 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟 =62. 4 𝑙𝑏𝑓/𝑓𝑡
AA 1 1.5 3 4.15077
A 1 2 4 5.063004
B 1 2.5 5 5.97524
C 1 3 6 6.88748
D 1 3 6 8.71195
Where,
For Cement,
128
𝑓
𝑙𝑏
94 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 = 𝑙𝑏𝑓
(3.15)(62.4 3 )
𝑓𝑡
3
𝑓𝑡 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 =. 478225 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
For Sand,
𝑙𝑏𝑓 𝑓𝑡
3
(110 3 )(2 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 )
𝑓𝑡
𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑠𝑎𝑛𝑑 = 𝑙𝑏𝑓
(2.64)(62.4 3 )
𝑓𝑡
3
𝑓𝑡 𝑜𝑓 𝑠𝑎𝑛𝑑
𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑠𝑎𝑛𝑑 = 1. 335470 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
For Gravel,
𝑙𝑏𝑓 𝑓𝑡
3
(96 3 )(4 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 )
𝑓𝑡
𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑠𝑎𝑛𝑑 = 𝑙𝑏𝑓
(2.66)(62.4 3 )
𝑓𝑡
3
𝑓𝑡 𝑜𝑓 𝑔𝑟𝑎𝑣𝑒𝑙
𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟 = 2. 313476 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
For Water,
3
𝑔𝑎𝑙 1 𝑓𝑡
𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟 = 7 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
𝑥 7.48 𝑔𝑎𝑙
3
𝑓𝑡 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟
𝐴𝑏𝑠𝑜𝑙𝑢𝑡𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟 =. 935829 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
3
𝑓𝑡
𝑌𝐼𝐸𝐿𝐷 = Σ(. 478225 + 1. 335470 + 2. 313476 + . 935829) 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
129
3
𝑓𝑡
𝑌𝐼𝐸𝐿𝐷 = 5. 063 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
𝑉𝑓
𝑁𝑜. 𝑜𝑓 𝐵𝑎𝑔𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 = 𝑌𝐼𝐸𝐿𝐷
3 3
3 3.28 𝑓𝑡
220.5 𝑚 ( 3 )
1𝑚
𝑁𝑜. 𝑜𝑓 𝐵𝑎𝑔𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡 = 𝑓𝑡
3
5.063 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
Volume of Sand,
3
𝑓𝑡 𝑜𝑓 𝑠𝑎𝑛𝑑
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙 = (2 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 )(1, 537 𝐵𝑎𝑔𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡)
3
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑆𝑎𝑛𝑑 = 3, 074 𝑓𝑡 𝑜𝑓 𝑠𝑎𝑛𝑑
Volume of Gravel,
3
𝑓𝑡 𝑜𝑓 𝑔𝑟𝑎𝑣𝑒𝑙
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐺𝑟𝑎𝑣𝑒𝑙 = (4 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡 )(1, 537 𝐵𝑎𝑔𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡)
3
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐺𝑟𝑎𝑣𝑒𝑙 = 6, 148 𝑓𝑡 𝑜𝑓 𝐺𝑟𝑎𝑣𝑒𝑙
Volume of Water,
130
3
𝑓𝑡 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟 = (. 935829 𝑏𝑎𝑔 𝑜𝑓 𝑐𝑒𝑚𝑒𝑛𝑡
)(469 𝐵𝑎𝑔𝑠 𝑜𝑓 𝐶𝑒𝑚𝑒𝑛𝑡)
3
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐺𝑟𝑎𝑣𝑒𝑙 = 1, 438. 3692 𝑓𝑡 𝑜𝑓 𝑊𝑎𝑡𝑒𝑟
𝑊𝑅𝑆𝐵 = (. 5% − 1%) 𝑊𝑓
Taking the average from 0.5% to 1%, we will get 0.75% or 0.0075,
𝑊𝑅𝑆𝐵 = 3, 969 𝑘𝑔
APPENDIX D
131
The Table D-1 shows the CAPEX or Capital Expenses and O&M or Operation and Maintenance in 2015
(Source: IACSIT International Journal of Engineering and Technology, Vol. 4, No. 3, June 2012)
The graph shows the Distribution of Investments on a Hydropower Plant from Costing of Hydropower
Projects by Sachin Mishra et al. The major components of civil works are diversion channel, spillway and
power house building. The major Electro-mechanical component of the power plant is the inlet valve,
turbine, draft tube, gates, generator, control and protection equipment and substation for transformation of
power to the transmission line. In terms of space requirement and cost the major items are the turbine and
generator.
132
Table D-2: Plant Values for Alternative 1
The highlighted row is the classification that covers the data of the design for alternative 1 which are the
Capital Cost; 𝐶𝑎𝑝𝑖𝑡𝑎𝑙 𝐶𝑜𝑠𝑡 = (𝑃𝑟𝑖𝑐𝑒 𝑜𝑓 𝐶𝑎𝑝𝑖𝑡𝑎𝑙 𝐶𝑜𝑠𝑡 𝑝𝑒𝑟 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦)( 𝑃𝑙𝑎𝑛𝑡 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦)
𝑈𝑆𝐷 𝑃𝐻𝑃
𝐶𝑎𝑝𝑖𝑡𝑎𝑙 𝐶𝑜𝑠𝑡 = (7, 277 𝑘𝑊
× 47. 75 𝑈𝑆𝐷
)(5, 000 𝑘𝑊)
𝑇𝑢𝑟𝑏𝑜 𝐺𝑒𝑛𝑒𝑟𝑎𝑡𝑜𝑟 𝑆𝑒𝑡 𝐶𝑜𝑠𝑡 = (1, 737, 383, 750 𝑃𝐻𝑃)(0. 30)
𝐸𝑙𝑒𝑐𝑡𝑟𝑖𝑐 𝑅𝑒𝑔𝑢𝑙𝑎𝑡𝑖𝑜𝑛 𝑎𝑛𝑑 𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐸𝑞𝑢𝑖𝑝𝑚𝑒𝑛𝑡𝑠 𝐶𝑜𝑠𝑡 = (1, 737, 383, 750 𝑃𝐻𝑃)(0. 22)
𝐸𝑙𝑒𝑐𝑡𝑟𝑖𝑐 𝑅𝑒𝑔𝑢𝑙𝑎𝑡𝑖𝑜𝑛 𝑎𝑛𝑑 𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐸𝑞𝑢𝑖𝑝𝑚𝑒𝑛𝑡𝑠 𝐶𝑜𝑠𝑡 = 382, 224, 425 𝑃𝐻𝑃
133
For Construction and Engineering Management,
𝐶𝑜𝑛𝑠𝑡𝑟𝑢𝑐𝑡𝑖𝑜𝑛 𝑎𝑛𝑑 𝐸𝑛𝑔𝑖𝑛𝑒𝑒𝑟𝑖𝑛𝑔 𝑀𝑎𝑛𝑎𝑔𝑒𝑚𝑒𝑛𝑡 𝐶𝑜𝑠𝑡 = (1, 737, 383, 750 𝑃𝐻𝑃)(0. 08)
𝑈𝑆𝐷 𝑃𝐻𝑃
𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑜𝑛𝑎𝑙 𝑎𝑛𝑑 𝑀𝑎𝑖𝑛𝑡𝑒𝑛𝑎𝑛𝑐𝑒 𝐶𝑜𝑠𝑡 = (125 𝑘𝑊
× 47. 75 𝑈𝑆𝐷
)(5, 000 𝑘𝑊)
Note: Based on Fig. 1-10, the generation rate of SAMELCO I is 10.2646 php/kwh.
134
𝑁𝑒𝑡 𝑃𝑟𝑜𝑓𝑖𝑡 = 𝐴𝑛𝑛𝑢𝑎𝑙 𝐺𝑟𝑜𝑠𝑠 𝐼𝑛𝑐𝑜𝑚𝑒 − 𝑂&𝑀 𝐶𝑜𝑠𝑡
𝑁𝑒𝑡 𝐼𝑛𝑐𝑜𝑚𝑒
For Return of Investment ; 𝑅𝑂𝐼 = 𝐶𝑎𝑝𝑖𝑡𝑎𝑙 𝐶𝑜𝑠𝑡
𝑥 100
419,745,730 𝑝ℎ𝑝
𝑅𝑂𝐼 = 1,737,383,750 𝑝ℎ𝑝
𝑥 100
The highlighted row is the classification that covers the data of the design for alternative 2 which are the
Capital Cost; 𝐶𝑎𝑝𝑖𝑡𝑎𝑙 𝐶𝑜𝑠𝑡 = (𝑃𝑟𝑖𝑐𝑒 𝑜𝑓 𝐶𝑎𝑝𝑖𝑡𝑎𝑙 𝐶𝑜𝑠𝑡 𝑝𝑒𝑟 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦)( 𝑃𝑙𝑎𝑛𝑡 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦)
𝑈𝑆𝐷 𝑃𝐻𝑃
𝐶𝑎𝑝𝑖𝑡𝑎𝑙 𝐶𝑜𝑠𝑡 = (6, 363 𝑘𝑊
× 47. 75 𝑈𝑆𝐷
)(5, 000 𝑘𝑊)
135
For Capital Cost Breakdown
𝑇𝑢𝑟𝑏𝑜 𝐺𝑒𝑛𝑒𝑟𝑎𝑡𝑜𝑟 𝑆𝑒𝑡 𝐶𝑜𝑠𝑡 = (1, 519, 166, 250 𝑃𝐻𝑃)(0. 30)
𝐸𝑙𝑒𝑐𝑡𝑟𝑖𝑐 𝑅𝑒𝑔𝑢𝑙𝑎𝑡𝑖𝑜𝑛 𝑎𝑛𝑑 𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐸𝑞𝑢𝑖𝑝𝑚𝑒𝑛𝑡𝑠 𝐶𝑜𝑠𝑡 = (1, 519, 166, 250 𝑃𝐻𝑃)(0. 22)
𝐸𝑙𝑒𝑐𝑡𝑟𝑖𝑐 𝑅𝑒𝑔𝑢𝑙𝑎𝑡𝑖𝑜𝑛 𝑎𝑛𝑑 𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐸𝑞𝑢𝑖𝑝𝑚𝑒𝑛𝑡𝑠 𝐶𝑜𝑠𝑡 = 334, 216, 575 𝑃𝐻𝑃
𝐶𝑜𝑛𝑠𝑡𝑟𝑢𝑐𝑡𝑖𝑜𝑛 𝑎𝑛𝑑 𝐸𝑛𝑔𝑖𝑛𝑒𝑒𝑟𝑖𝑛𝑔 𝑀𝑎𝑛𝑎𝑔𝑒𝑚𝑒𝑛𝑡 𝐶𝑜𝑠𝑡 = (1, 519, 166, 250 𝑃𝐻𝑃)(0. 08)
𝑈𝑆𝐷 𝑃𝐻𝑃
𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑜𝑛𝑎𝑙 𝑎𝑛𝑑 𝑀𝑎𝑖𝑛𝑡𝑒𝑛𝑎𝑛𝑐𝑒 𝐶𝑜𝑠𝑡 = (118 𝑘𝑊
× 47. 75 𝑈𝑆𝐷
)(5, 000 𝑘𝑊)
136
For the Net Income of the Power Plant
Note: Based on Fig. 1-10, the generation rate of SAMELCO I is 10.2646 php/kwh.
𝑁𝑒𝑡 𝐼𝑛𝑐𝑜𝑚𝑒
For Return of Investment ; 𝑅𝑂𝐼 = 𝐶𝑎𝑝𝑖𝑡𝑎𝑙 𝐶𝑜𝑠𝑡
𝑥 100
421,416,980 𝑝ℎ𝑝
𝑅𝑂𝐼 = 1,519,166,250 𝑝ℎ𝑝
𝑥 100
137
Table D-4: Plant Values for Alternative 3
The data that will be used is under the 1-10 MW plant capacity since the design capacity is 5 MW with the
Capital Cost
𝑈𝑆𝐷 𝑃𝐻𝑃
𝐶𝑎𝑝𝑖𝑡𝑎𝑙 𝐶𝑜𝑠𝑡 = (7, 277 𝑘𝑊
× 47. 75 𝑈𝑆𝐷
)(5, 000 𝑘𝑊)
𝑇𝑢𝑟𝑏𝑜 𝐺𝑒𝑛𝑒𝑟𝑎𝑡𝑜𝑟 𝑆𝑒𝑡 𝐶𝑜𝑠𝑡 = (1, 737, 383, 750 𝑃𝐻𝑃)(0. 30)
138
𝐸𝑙𝑒𝑐𝑡𝑟𝑖𝑐 𝑅𝑒𝑔𝑢𝑙𝑎𝑡𝑖𝑜𝑛 𝑎𝑛𝑑 𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐸𝑞𝑢𝑖𝑝𝑚𝑒𝑛𝑡𝑠 𝐶𝑜𝑠𝑡 = (1, 737, 383, 750 𝑃𝐻𝑃)(0. 22)
𝐸𝑙𝑒𝑐𝑡𝑟𝑖𝑐 𝑅𝑒𝑔𝑢𝑙𝑎𝑡𝑖𝑜𝑛 𝑎𝑛𝑑 𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝐸𝑞𝑢𝑖𝑝𝑚𝑒𝑛𝑡𝑠 𝐶𝑜𝑠𝑡 = 382, 224, 425 𝑃𝐻𝑃
𝐶𝑜𝑛𝑠𝑡𝑟𝑢𝑐𝑡𝑖𝑜𝑛 𝑎𝑛𝑑 𝐸𝑛𝑔𝑖𝑛𝑒𝑒𝑟𝑖𝑛𝑔 𝑀𝑎𝑛𝑎𝑔𝑒𝑚𝑒𝑛𝑡 𝐶𝑜𝑠𝑡 = (1, 737, 383, 750 𝑃𝐻𝑃)(0. 08)
𝑈𝑆𝐷 𝑃𝐻𝑃
𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑜𝑛𝑎𝑙 𝑎𝑛𝑑 𝑀𝑎𝑖𝑛𝑡𝑒𝑛𝑎𝑛𝑐𝑒 𝐶𝑜𝑠𝑡 = (125 𝑘𝑊
× 47. 75 𝑈𝑆𝐷
)(5, 000 𝑘𝑊)
Note: Based on Fig. 1-10, the generation rate of SAMELCO I is 10.2646 php/kwh.
139
8,760 ℎ𝑟𝑠 𝑝ℎ𝑝
𝐴𝑛𝑛𝑢𝑎𝑙 𝐺𝑟𝑜𝑠𝑠 𝐼𝑛𝑐𝑜𝑚𝑒 = (5000 𝑘𝑤 × 𝑦𝑒𝑎𝑟
)(10. 2646 𝑘𝑤ℎ
)
And,
𝑁𝑒𝑡 𝐼𝑛𝑐𝑜𝑚𝑒
𝑅𝑂𝐼 = 𝐶𝑎𝑝𝑖𝑡𝑎𝑙 𝐶𝑜𝑠𝑡
𝑥 100
419,745,730 𝑝ℎ𝑝
𝑅𝑂𝐼 = 1,737,383,750 𝑝ℎ𝑝
𝑥 100
𝑅𝑂𝐼 = 24. 16 %
140
References
Linquip Team (2021) Types of Turbines: Classifications and Types. Retrieved from
https://www.linquip.com/blog/types-of-turbines/
Jordan Hanania, Kailyn Stenhouse, Jason Donev (2020) Pelton Turbine. Retrieved from
https://energyeducation.ca/encyclopedia/Pelton_turbine
Water Power Technology Office (2020) Types of Hydropower Turbines. Retrieved from
https://www.energy.gov/eere/water/types-hydropower-turbines#:~:text=There%20are%20two%20main%20t
ypes,set%2C%20efficiency%2C%20and%20cost.
Paul Dang , Jordan Hanania, Kailyn Stenhouse, Jason Donev (2020) Francis Turbine. Retrieved from
https://energyeducation.ca/encyclopedia/Francis_turbine
S.O. Otuagoma Otuagoma, E.A. Ogujor and P.A.Kuale (2016) DETERMINATION OF HEAD FOR SMALL
https://www.ajol.info/index.php/njt/article/view/132439/122038#:~:text=The%20net%20head%20
is%20defined,measured%20and%20pipe%20loses%20calculated.
https://www.alibaba.com/product-detail/5MW-High-Efficiency-Francis-Hydro-Turbine_62022146805.html?sp
m=a2700.galleryofferlist.normal_offer.d_title.17f84bd10R2aaV
https://www.nationalgeographic.com/environment/article/hydropower
Solenergy Systems Inc. on Solar Panels Philippines (2021) RENEWABLE ENERGY SPOTS IN THE
141
Bethel Afework, Jordan Hanania, Kailyn Stenhouse, Jason Donev (2020) Power Plant. Retrieved from
https://energyeducation.ca/encyclopedia/Power_plant
Department of Energy, Philippines (2019) 2019 Power Situation Report. Retrieved from
https://www.doe.gov.ph/sites/default/files/pdf/electric_power/2019-power-situation-report.pdf
USGS (2020) Hydroelectric Power: Advantages of Production and Usage. Retrieved from
https://www.usgs.gov/special-topic/water-science-school/science/hydroelectric-power-advantages-productio
n-and-usage?qt-science_center_objects=0#qt-science_center_objects
National Renewable Energy Laboratory (2001) Small Hydropower Systems. Retrieved from
https://www.nrel.gov/docs/fy01osti/29065.pdf
Prof. Dr. Atil BULU (2020) Hydroelectric Power Plants. Retrieved from
https://web.itu.edu.tr/~bulu/hyroelectic_power_files/lecture_notes_12.pdf
Energize RE 4: Renewable Energy Supplement (2016) Run-of-river hydropower systems. Retrieved from
https://www.ee.co.za/wp-content/uploads/2016/03/Energize-RE-4-Vol-4-pg-38-41.pdf
Gophal Mishra (2012) Kaplan Turbine - It’s Components, Working and Applications. Retrieved from
https://theconstructor.org/practical-guide/kaplan-turbine-component-working/2904/
https://honestproscons.com/advantages-and-disadvantages-of-hydropower/
National Renewable Energy Laboratory (2020) 2020 Annual Technology Baseline (ATB) Cost and
https://data.nrel.gov/submissions/145
Sachin Mishra, S. K. Singal, and D. K. Khatod (2012) Costing of a Small Hydropower Project. Retrieved
https://openei.org/wiki/Definition:Electricity_generation
142
Hydroelectricity Technology (2009) Run of the River Method: hydroelectricity generation. Retrieved from
https://hydroelectric-energy.blogspot.com/2010/12/run-of-river-method-hydroelectricity.html
Pankaj Mishra (2018) What is Kaplan Turbine and How It Works?. Retrieved from
https://www.mechanicalbooster.com/2018/02/kaplan-turbine.html
Mechstudies (2021) Kaplan Turbine: Parts, Components, Working, Applications. Retrieved from
https://www.mechstudies.com/kaplan-turbine-parts-working/#Advantages_of_Kaplan_Turbine
Amrit Kumar (2016) Francis Turbine: Parts, Working, Efficiency, Advantages, Disadvantages. Retrieved
from https://learnmechanical.com/francis-turbine/
Rajkumar Gupta (2020). Working of Kaplan Turbine | Main Parts of Kaplan Turbine. Retrieved from
https://mechanicaljungle.com/working-of-kaplan-turbine-what-is-a-kaplan-turbine-main-parts-of-kaplan-turbi
ne
Darren Ryder, Karl Vernes, Lobzang Dorji, Stevie Armstrong, Cornelia Brem, Rebecca Di Donato, Lindsey
Frost and Ian Simpson (2010) Experimental effects of reduced flow velocity on water quality and
https://bes.org.bt/wp-content/uploads/2018/02/Proceedings-of-BES_2015_2.2Experimental-effects-of-reduc
ed-flow-velocity-on-water-quality-and-macroinvertebrate-communities-implications-for-hydropower-develop
ment-in-Bhutan-.pdf
Bethel Afework, Jordan Hanania, Kailyn Stenhouse, Jason Donev (2020). Energy Education, Power Plant.
http://chemistry.elmhurst.edu/vchembook/193sources.html#:~:text=Electricity%20is%20produced%20at%2
0a,or%20nuclear%20energy%20produces%20heat.&text=The%20spinning%20turbine%20interacts%20wit
h,wires%20to%20homes%20and%20business.
143
Department of Energy (2021). What’s New?. Retrieved from
https://www.doe.gov.ph/electric-power?ckattempt=1
https://www.eia.gov/energyexplained/electricity/
https://www.slideshare.net/bibhabasumohanty/hydroelectric-power-13443211
Farheen Jawaid, Arisha Anwer Aiesha ,Jaweed Masjah (2014) Hydro Power. Retrieved from
https://www.slideshare.net/srgirlsdk/hydro-power-ppt
United State of Geological Survey (2012). Hydroelectric power works. Retrieved from
https://www.usgs.gov/special-topic/water-science-school/science/hydroelectric-power-how-it-works?qt-scie
nce_center_objects=0#qt-science_center_objects
United State of Geological Survey (2012). Hydroelectric power use. Retrieved from
https://www.usgs.gov/special-topic/water-science-school/science/hydroelectric-power-water-use?qt-science
_center_objects=0#qt-science_center_objects
144