M.V Guana Inicial

The survey found that the vessel GUANA loaded with magnesite in bulk at the TGS Pier I terminal in Aratu Port, Brazil. Initial draft measurements found the forward draft was 5.738m and aft was 5.872m. Final measurements after loading showed the forward draft increased to 6.06m and aft increased to 7.399m. The net displacement increased from 6,169.575MT initially to 8,392.966MT after loading, indicating around 2,223.391MT of cargo was loaded onto the vessel.

Uploaded by

Josefhi Charlles
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
244 views2 pages

M.V Guana Inicial

The survey found that the vessel GUANA loaded with magnesite in bulk at the TGS Pier I terminal in Aratu Port, Brazil. Initial draft measurements found the forward draft was 5.738m and aft was 5.872m. Final measurements after loading showed the forward draft increased to 6.06m and aft increased to 7.399m. The net displacement increased from 6,169.575MT initially to 8,392.966MT after loading, indicating around 2,223.391MT of cargo was loaded onto the vessel.

Uploaded by

Josefhi Charlles
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

REPORT OF SHIP'S DRAFT SURVEY INITIAL

PORT ARATU PORT VESSEL GUANA


CARGO DESCRIBED AS MAGNESITE INBULK TERMINAL TGS PIER I

Initial Final
Date November 23,2022 November 23,2022

Time 6:30 08:00


Location ARATU PORT ARATU PORT

1. Draft Forward Corrected 5.7380 m 6.0600 m


Draft Aft Corrected 5.8720 m 7.3990 m
Draft Fore & Aft Mean 5.8050 m 6.7295 m
2. Draft Amidships PORT 5.7690 m 6.5020 m
Draft Amidships STBD 5.7390 m 6.8520 m
Draft Amidships Keel correction 0.000 m 5.7540 m 6.6770 m

3. Draft Corrected for Deformation 5.7668 m 6.6901 m

4. Displacement 12,866.779 MT 15,184.049 MT

5. Trim Correction -4.319 MT -20.950 MT


Initial Final 12,862.460 15,163.099
6. Density Correction kg/m3 1.0250 1.0250 Corr. 0.000 MT 0.000 MT

7. Displacement Corrected for Density 12,862.460 MT 15,163.099 MT

8. Consumables, Ballast, Etc.


(a) Fuel Oils 340.000 340.000
(b) Diesel Oil 79.000 78.000
(c) Fresh Water 23.743 75.190
(d) Ballast 6,223.242 6,250.043
(e) OTHERS 26.900 26.900
Total Consumables, etc. … 6,692.885 MT 6,770.133 MT

9. Net Displacement 6,169.575 MT 8,392.966 MT

10. CARGO LOADING -2,223.391 MT

Remarks: Initial Final


Manifested cargo : 12,000.000 MT
Net displac. Initial : (2,223.391) MT
Light ship : 5,966.250 MT
Const. Declared : 185.000 MT
Cargo Found : - 8,374.641 MT
Diference : -20,374.641 MT Surveyor Surveyor

-169.789 %
Swell Initial: 0.20 m

Calculated cargo based on declared


constant.
Calculated cargo based on declared
constant. Chief Officer Chief Officer

All inspections are carried out to the best of our knowledge and ability, and our responsibility is limited to the exercise of reasonable care.