100% found this document useful (3 votes)
651 views6 pages

MEP FP Inspection Checklist

This document provides a master checklist for inspecting MEP and fire protection construction. It contains over 200 individual inspection items organized under categories for civil/site utilities, plumbing, fire protection, mechanical, electrical, fire alarm, and telecommunications. The checklist is intended to be used from rough-in through final inspection and punch-out on construction projects to ensure minimum requirements are met for applicable inspection items.

Uploaded by

Mohanad Suliman
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (3 votes)
651 views6 pages

MEP FP Inspection Checklist

This document provides a master checklist for inspecting MEP and fire protection construction. It contains over 200 individual inspection items organized under categories for civil/site utilities, plumbing, fire protection, mechanical, electrical, fire alarm, and telecommunications. The checklist is intended to be used from rough-in through final inspection and punch-out on construction projects to ensure minimum requirements are met for applicable inspection items.

Uploaded by

Mohanad Suliman
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

Ball State University Engineering

MEP and FP Construction Inspection


Master Checklist
Updated 11/30/17

Project: __________________________________________________________

Civil/Site Utilities

 Meter pits have meters or spool piece same size as meter installed
 Link seals around all vault pipe penetrations with bolt heads inside the vault
 Tamper switches on the PIV and other FP valves present
 Sump pump installed in vault complete
 Buried water piping is 5’0” deep minimum
 HHW piping is ductile iron with granular insulation
 CHW is HDPE
 Thrust blocks are installed
 Piping tracer wires are installed.
 HHW and CHW valves are installed and boxes are at finished grade and the correct lids are
installed
 Electrical duct banks are concrete encased. Warning tape installed.
 Duct bank conduits have been swabbed and mandrel pulled through
 All piping systems have been flushed
 Domestic disinfection complete with test reports turned over
 Hydrostatic pressure test report on fire, domestic, CHW and HHW received
 All excavations have been properly backfilled and compacted
 Flow fill used around valve boxes and CHW piping
 Natural gas service installed and active
 Field set of as-builts checked periodically
Plumbing

 Drains are cast iron


 Domestic water is copper with soldered joints
 Backflow preventers are Watts 909
 Pump bases are grouted
 Cleanouts are accessible and per plan
 Hammer arresters are accessible and per plan
 Shut off / isolation valves are accessible and per plan
 Steam pressure is verified and PRV is correct
 Insulation is fiberglass and correct thickness
 Valves and accessories are insulated per specs
 Vents are through roof instead of using air admittance valves
 Natural gas piping is black iron painted yellow
 NG pressure is acceptable
 Compressed air is per plans and is 80 psi minimum
 Water lines have been flushed and disinfected and reports turned over
 Pressure test reports turned over
 Storm drains are insulated
 Autoflush valves tested and operational
 Mop sink H/C supply lines have check valves installed
 Thermostatic mixing valves are set up and witnessed operational
 Stored HW is 140 degrees minimum
 Hand washing sink HW is 100 - 120 degrees
 Dishwashing sink HW is 110 - 120 degrees
 HW system has thermometers and pressure gages per plan
 Water heater(s) are plumbed per plan and piped to drain
 Condensing water heaters have neutralizer kits installed
 Water softener(s) are plumbed per plan and piped to drain
 Water softener(s) are set up and tested. Hardness report turned over
 Initial softener salt fill is supplied
 Exterior spigots/hydrants present per plan
 Basement pipe penetrations are sealed with link seals with bolt heads inside.
 Field set of as-builts checked periodically
Fire Protection

 Design drawings submitted to FM Global and the State w/ comments received


 Mains schedule 40. Roll grooved, not cut grooved
 Complete drain down is possible. Piped to drain. Incl. fire pump test header
 No traps without drains
 Pressure ratings (175 or 300) per specs
 Head temps are per drawings and specs
 Hydrostatic pressure test reports turned over
 Sprinkler bell is present and functioning
 FDC is 5” Storz
 Test header is located near a storm drain, easily hose accessible
 All flows and tampers are wired and tested
 All dry/preaction points are monitored by the fire alarm system
 Preaction system panel is installed and tested complete
 Concealed heads in finished spaces
 Zone valves are accessible and equipped with flow switches and drains/insp. test
 Fire pump transfer switch has been tested and pump run on generator
 Pump controller alarm points monitored by the fire alarm system
 Jockey pump is accessible
 Air compressor is accessible
 Risers have automatic air vents
 Hydraulic calcs and name plates present
 All testing complete and test reports turned over
 All valves are locked and monitored
 Fire pump room lighting is on emergency power
 Fire pump normal power feed is from pad mounted xfmr and thru a fused disconnect
 Field set of as-builts checked periodically
Mechanical

 Incoming HHW and CHW basement penetrations sealed with link seals
 Copper hydronic piping is brazed joint
 Pump bases grouted
 Pumps aligned
 Belts aligned and tensioned
 All equipment and system startup tasks complete and documented
 Isolation valves installed per plan and accessible
 Control wiring installed in conduit
 Data jacks installed near BAS system control panels
 LED displays are installed on the front of main control panels
 Laminated copies of control drawings are located in control panels
 BTU Meters are installed per manufacturer’s recommendations and are Onicon system 10 with
F-3500 flow meters
 Roller hangers are used where HHE or steam pipe exceed 100’ of straight length
 Filter sections accessible
 HHW incoming full flow bag filter installed
 Bridges installed per plan
 Incoming HHW and CHW S/R are labeled
 Fire and smoke dampers installed and accessible
 Control boxes on VAV’s and FCU’s are accessible
 Volume dampers installed and accessible with handles left on
 Correct insulation and thickness installed complete incl. at valves and accessories
 Insulation sealed
 Piping system and direction labeling complete
 Valve tags installed and charted
 Piping and ductwork pressure test witnessed and reports received
 Duct openings sealed throughout construction
 Equipment clearances maintained
 Piping systems flushed and treated
 Flex duct limited to 5’0” max
 Air vents installed at high points
 Piping per details incl. all accessories
 TAB complete and pencil copy and final copies of reports turned over
 Commissioning visits documented and deficiency reports addressed
 Commissioning complete
 BMS user interface (laptop/tablet) has been turned over
 Air handling units, fan coil units and blower coil units have been cleaned including all internal
sections
 All air filters are new and an extra set has been provided for each piece of equipment.
 Field set of as-builts checked periodically
Electrical

 Correct feeder/service main bonding jumper arrangement


 Correct generator bonding arrangement (3P/4P ATS’s)
 Ground ring installed and/or bonded to
 Transformers properly grounded and bonded
 Breakers are set per Engineer’s settings report
 No water piping over electrical equipment
 Panel covers are hinged door-in-door style
 Working clearances maintained
 All box supports in stud walls span 2 studs
 Box rough-in heights are correct
 No back-to-back boxes
 No MC/AC cable except for fixture whips
 Fixture whips are 6’0” or less and are only from box to fixture, not daisy chained
 Conduits run in center of stud walls to avoid drywall screw penetration
 Conduits supported within 3’ of boxes
 EMT fittings are steel (no die cast)
 Rigid elbows used for floor slab penetrations
 Minimum conduit size is 3/4"
 No conduits run within floor slabs
 Exposed exterior conduits are GRC
 Office and conference room sensors are vacancy mode set to 30 minutes
 Corridor and RR sensors are occupancy and set to 30 minutes
 All sensors are PIR only with the most sensitive setting
 Generator housing is true walk-in
 Generator fuel initial fill provided
 Generator testing and training complete
 Arc flash labels are installed
 Meters are installed in main switchgear and have Ethernet jack installed
 Field set of as-builts checked periodically
Fire Alarm

 All fire alarm cabling is installed in conduit


 Metasys cabinet furnished and installed
 All flows and tampers are wired and accessible
 Sprinkler bell is wired through FACP
 Fire pump control panel is monitored (all points)
 Preaction system panel is monitored and/or controlled
 All smoke and heat detectors are accessible incl. duct detectors
 Owner’s witnessed testing is 100% complete
 Final test reports are turned over
 Internet connectivity demonstrated
 All mass notification functions tested and demonstrated
 All panel bypasses tested and demonstrated
 Training is complete
 Copy of the software is turned over
 Field set of as-builts checked periodically

Telecommunications

 All box supports in stud walls span 2 studs


 Minimum conduit size is 1” and is stubbed to corridor skeletal openings
 Data cabling is CAT 6A with blue jacket
 All cabling is plenum rated
 MDF and IDF’s are built per the drawings
 Data jacks are installed at each meter, each BMS panel, FACP and each access control panel
 Copper and fiber test results turned over
 Field set of as-builts checked periodically

NOTE: The above list is meant to be used as a tool for both all involved to use for MEP construction
inspection from rough-in through punch-out. It is not an all-inclusive list and is not project specific but
rather a "one size fits all" minimum requirement for the applicable items on any given project. Some
projects may require more or less inspection.

You might also like