This document is a Saudi Aramco inspection checklist for the handling, storage, and preservation of electrical equipment. It lists acceptance criteria for document review and handling of electrical equipment, referencing Saudi Aramco and other industry standards. The checklist contains items to ensure equipment documentation and identification is correct, handling and storage procedures meet specifications, and equipment is moved and stored properly to prevent damage.

Uploaded by

aneeshjokay
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
327 views1 page

Saic P 3002

This document is a Saudi Aramco inspection checklist for the handling, storage, and preservation of electrical equipment. It lists acceptance criteria for document review and handling of electrical equipment, referencing Saudi Aramco and other industry standards. The checklist contains items to ensure equipment documentation and identification is correct, handling and storage procedures meet specifications, and equipment is moved and stored properly to prevent damage.

Uploaded by

aneeshjokay
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

SAUDI ARAMCO ID/PIEU - 14- May 2018 - REV. 2018.03.00 (Standards Cutoff -March 31, 2018) Rev. 2018.03.

Rev. 2018.03.00 31-Mar-18

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

General - Electrical Equipment, Storage, Handling &


SAIC-P-3002 14-May-18 ELECT-
Preservation
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A. Document Review

Schedule Q
Purchase order and Data Sheet criteria shall be confirmed and compared
A1 Att. IV
with electrical equipment documentation, and checked for damage.
Sec.3.3

Electrical equipment shall be identified by using tags, stamps, color Schedule Q


A2 coding, stencils or labels. The location and method of identification shall Att. lV
not affect the function or quality of the material. Sec.4.2

The CONTRACTOR shall include procedures for handling, storage, and Schedule Q
A3 preservation of material as specified in all applicable specifications, Att. IV
manufacturer recommendations and SAUDI Aramco's standards. Sec. 5

The procedure shall list all inspection schedules for maintaining the quality Schedule Q
A4 of the material or equipment as well as provide for documentation that the Att. IV
required activities have been performed. Sec. 5

Shipping crates shall be marked with handling and storage instructions.


Labels on the shipping crate shall state the storage conditions, date of SAES-P-100
A5
shipment, and the date beyond which the product must not be stored. Sec 5.2
(NFPA 70, NEC Art. 110.3(B), & manufacturer's instructions)

B. Handling

Electrical equipment should be moved and stored in an upright position.


SAES-P-100
B1 [(NFPA 70,
Sec 5.2
NEC Art. 110.3 (B), & manufacturer's instruction )]

Electrical equipment shall be checked to be free from visible damage by


store yard personnel prior to acceptance of shipment, unloading, or SAES-P-100
B2
handling. Sec 5.2
[(NFPA 70, NEC Art. 110.3(B) & manufacturer's instructions)]

Shipper and receiving store yard personnel shall be fully aware of


manufacturer's special handling instructions prior to unloading or handling. SAES-P-100
B3
Special handling instructions shall be followed. Sec 5.2
[(NFPA 70, NEC Art. 110.3(B) & manufacturer's instructions)]

Electrical equipment wooden boxes, crates and panels shall not be


SAES-P-100
B4 dropped.
Sec 5.2
[(NFPA 70, NEC Art. 110.3 (B) & manufacturer's instructions)]

Electrical equipment shall be handled with care to prevent damage to


SAES-P-100
B5 components or special finishes.
Sec. 5.2
[(NFPA 70, NEC Art. 110.3 (B) & manufacturer's instructions)]