Bullah Analysis of Rate

1. This document provides an analysis of rates for various tasks related to non-sal bullah piles including collecting, conveying, stacking, driving piles, tying pieces, providing sand bags, supplying empty cement bags, GI wire, and MS cut clasp nails. 2. Rate details are provided for each task, including base rates, conveyance charges, labour cess, and total rates per unit of measurement (e.g. per RM, per number, per kg). 3. Rates are specified for 150-200mm diameter non-sal bullah piles at a depth beyond 1.5m, half bullah tying pieces, sand bags filled and placed using empty cement bags, empty cement bags
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
649 views2 pages

Bullah Analysis of Rate

1. This document provides an analysis of rates for various tasks related to non-sal bullah piles including collecting, conveying, stacking, driving piles, tying pieces, providing sand bags, supplying empty cement bags, GI wire, and MS cut clasp nails. 2. Rate details are provided for each task, including base rates, conveyance charges, labour cess, and total rates per unit of measurement (e.g. per RM, per number, per kg). 3. Rates are specified for 150-200mm diameter non-sal bullah piles at a depth beyond 1.5m, half bullah tying pieces, sand bags filled and placed using empty cement bags, empty cement bags
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

ANALYSIS OF RATE

1. Collecting, Coveying and Stacking at worksite Non-sal Bullah 175 mm. mean dia of
any length including cost, carriage, labour Cess and all other taxes etc. Complete as
per the direction of Engineer-in-charge.
(i) Cost of Non-sal Bullah 150mm. to 200mm. mean dia =` 73.86
(ii) Conveyance charges per 1 Rm. =` 20.10
=` 93.96
Add 1% Labour cess =` 0.94
Total = ` 94.90 /Rm.
Say = ` 94.90 /Rm.
2. Labour for driving Non-sal Bullah piles and fixing in position 150mm. to 200mm. dia
beyand 1.50m. depth including sharpening the end etc. including labour Cess etc
complete as per the direction of Engineer-in-charge.

(Rate as per S/R 2014, P-34, Sl. No. 4) = @ ` 24.62/Rm.


( "2006" when labour rate was @ ` 55.00/Each)
So, Present rate is = ` 24.62 / 55.00 X 311.00 =` 139.21 /Rm.
Add 1% Labour cess =` 184.67 /Rm.
Total = ` 323.88 /Rm.
Say = ` 323.90 /Rm.
3. Labour for half bullah tying pieces fitted and fixed with nails etc. including labour
Cess and other taxes etc. complete as per the direction of Engineer-in-charge.

(Rate as per S/R 2014, P-34, Sl. No. 13) = @ ` 5.96/Rm.


( "2006" when labour rate was @ ` 55.00/Each)
So, Present rate is = ` 5.96 / 55.00 X 311.00 =` 33.70 /Rm.
Add 1% Labour cess =` 0.34 /Rm.
Total = ` 34.04 /Rm.
Say = ` 34.00 /Rm.
4. Providing and lying in position sand bags, filled with sand in empty cement bags
with all leads, lifts and delifts including for filling empty cement bags, cost of sewing
srtings and cost, carriage with royalty of sand and excluding cost of empty cement
bags with all taxes and labour Cess etc.Complete. as per direction of Engineer-in-
Charge
a) Cost & Conveyance of Sand
Sand (Filling) 1.00 Cum.@ ` 42.86 /Cum. =` 42.86
Carriage of Sand 1.00 Cum.@ ` 184.67 /Cum. =` 184.67
=` 227.53 /Cum.
(Assuming 0.0283 cum. /each sand bag)
So 1 no. = 0.0283cum. 0.0283 Cum.@ ` 227.53 /Cum. =` 6.44 /Nos.
b) Labour for filling empty cement bags sewing and lying in position including cost of
sewing, strings etc. complete
(Rate as per A/R 2014, P-40, Sl. No. 7) = @ ` 0.96/Each.
( "2006" when labour rate was @ ` 55.00/Each)
So, Present rate is = ` 0.96 / 55.00 X 311.00 =` 5.43 /Nos.
c)Supplying empty cement bags of good quality stacking at worksite including cost ,
conveyance and other taxes etc.
Total (a+b) = ` 11.87 /Nos.
Add 1% Labour cess =` 0.12 /Nos.
Total = ` 11.99 /Nos.
Say = ` 12.00 /Nos.
5. Supplying empty cement bags of good quality stacking at wprksite including cost
, conveyance and other taxes etc.
=` 3.13 /Nos.
(Rate as per A/R 2014, P-6, Sl. No. 127(a))
Add 1% Labour cess =` 0.03 /Nos.
Total
=` 3.16 /Nos.
Say = ` 3.15 /Nos.
6. Supplying G.I. wire of 10 SWG for tying to the runner bullah including cost,
conveyance, labour,labour Cess and other taxes etc complete.
Rate as per A/R 2014, P-6, Sl. No. 125 =` 67.23
Add 1% Labour cess =` 0.67
Total = ` 67.90 /Kg.
Say = ` 67.90 /Kg.
7. Supplying M.S. Cut clasp nails including cost, conveyance, labour,labour Cess and
other taxes etc complete.
Rate as per A/R 2014, P-6, Sl. No. 120 =` 51.06
Add 1% Labour cess =` 0.51
Total = ` 51.57 /Kg.
Say = ` 51.60 /Kg.

Assistant Engineer Asst. Executive Engineer Executive Engineer


Dhamnagar Irr. Section Dhamnagar Irr. Sub-Division, Jajpur Irrigation Division,
Dhamnagar Dhamnagar Jajpur