STAGE BACK-UP COMPUTATION
Construction of Multi-Purpose Building, Brgy. Alacan
San Fabian, Pangasinan
803(1)a - Structure Excavation (Common Soil)
Qty = 24.74 m³
C2F2 = 0.65 x 0.65 x 1.50 x 8.00
= 5.07 m³
C3F3 = 1.00 x 1.00 x 1.50 x 3.00
= 4.50 m³
WF = 0.60 x 0.80 x 31.60 x 1.00
= 15.17 m³
V TOTAL = 24.74 m³
804(1)a - Embankment (from Structure Excavation)
Qty = 24.74 m³
C2F2 = 0.65 x 0.65 x 1.50 x 8.00
= 5.07 m³
C3F3 = 1.00 x 1.00 x 1.50 x 3.00
= 4.50 x
WF = 0.60 x 0.80 x 31.60 x 1.00
= 15.17 m³
V TOTAL = 24.74 m³
804(4) - Gravelfill
Qty = 11.07 m³
C2F2 = 0.65 x 0.65 x 0.10 x 8.00
= 0.34 m³
C3F3 = 1.00 x 1.00 x 0.10 x 3.00
= 0.30 x
V(Slab on Fill) = 12.00 x 7.00 x 0.10 x 1.00
= 8.40 m³
Stage Stair = 1.50 x 0.90 x 0.10 x 1.00
= 0.14 m³
WF = 0.60 x 31.60 x 0.10 x 1.00
= 1.90 m³
V TOTAL = 11.07 m³
900(1)c2 - Structural Concrete for Footing and Slab on Fill (Class A, 28 days)
Qty = 12.01 m³
C2F2 = 0.65 x 0.65 x 0.20 x 8.00
= 0.68 m³
C3F3 = 1.00 x 1.00 x 0.30 x 3.00
= 0.90 x
V(Slab on Fill) = 12.00 x 7.00 x 0.10 x 1.00
= 8.40 m³
Stage Stair = 1.50 x 0.90 x 0.10 x 1.00
= 0.14 x
WF = 0.60 x 31.60 x 0.10 x 1.00
= 1.90 x
V TOTAL = 12.01 m³
900(1)c4 - Structural Concrete for Column (Class A, 28 days)
Qty = 2.65 m³
C2 = 0.15 x 0.20 x 5.50 x 8.00
= 1.32 m³
C3 = 0.25 x 0.25 x 7.10 x 3.00
= 1.33 x
V TOTAL = 2.65 m³
900(1)c6 - Structural Concrete for Beams (Class A, 28 days)
= 1.45 m³
LB-1 = 0.25 x 0.30 x 3.00 x 4.00
= 0.90 m³
LB-2 = 0.25 x 0.10 x 11.00 x 2.00
= 0.55 x
V TOTAL = 1.45 m³
902(1)a - Reinforcing Steel, Grade 40
= 1,672.79 kgs.
C2 = 32.00 - 16 mm Ø x 7.50 m = 378.80 kgs.
= 48.00 - 10 mm Ø x 6.00 m = 177.56 kgs.
556.36 kgs.
C3 = 24.00 - 16 mm Ø x 7.50 m = 284.10 kgs.
= 27.00 - 10 mm Ø x 6.00 m = 99.88 kgs.
383.98 kgs.
C2F2 = 6.00 - 16 mm Ø x 7.50 m = 71.03 kgs.
71.03 kgs.
C3F3 = 5.00 - 16 mm Ø x 7.50 m = 59.19 kgs.
59.19 kgs.
Slab on Fill = 63.00 - 10 mm Ø x 6.00m = 233.05 kgs.
233.05 kgs.
Stage Stair = 4.00 - 10 mm Ø x 7.50 m = 18.50 kgs.
4.00 - 10 mm Ø x 6.00m = 14.80 kgs.
33.29 kgs.
LB-1 = 12.00 - 16 mm Ø x 7.50 m = 142.05 kgs.
= 24.00 - 10 mm Ø x 6.00 m = 88.78 kgs.
230.83 kgs.
LB-2 = 8.00 - 12 mm Ø x 7.50 m = 53.27 kgs.
= 14.00 - 10 mm Ø x 6.00 m = 51.79 kgs.
105.06 kgs.
903(2) - Formworks and Falseworks
Qty = 71.90 m²
C2 = 0.70 x 5.50 x 8.00
= 30.80 m²
C3 = 1.00 x 7.10 x 3.00
= 21.30 x
LB-1 = 0.85 x 3.00 x 4.00
= 10.20 m²
LB-2 = 0.60 x 8.00 x 2.00
= 9.60 m²
A(TOTAL) = 71.90 m²
1046(2)a1 - 100mm CHB Non-Load Bearing(Incldg. Reinforced Steel)
Qty = 57.20 m²
Perimeter = 3.60 x 25.00 x 1.00
= 57.20 m²
1046(2)a2 - 150mm CHB Non-Load Bearing(Incldg. Reinforced Steel)
Qty = 40.00 m²
Embankment wall = 0.80 x 25.00 x 2.00
40.00 m²
A(TOTAL) = 40.00 m²
1027(1) - Cement Plaster Finish
Qty = 177.60 m²
C2 = 0.70 x 5.50 x 8.00
= 30.80 m²
C3 = 1.00 x 7.10 x 3.00
= 21.30 m²
Stage = 0.80 x 25.00 x 1.00
= 52.10 m²
Stage Wall = 3.60 x 25.00 x 1.00
= 73.40 m²
1032(1)a - Painting Works (Masonry/Concrete)
Qty = 148.70 m²
C2 = 0.70 x 4.50 x 8.00
= 25.20 m²
C3 = 1.00 x 4.50 x 3.00
= 13.50 m²
Stage = 0.80 x 25.00 x 1.00
= 20.00 m²
Stage Wall = 3.60 x 25.00 x 1.00
= 90.00 m²
PREPARED BY:
ERNESTO M. FLOR
Engineer II