Activity

This document outlines the steps and dependencies required to transport a house across a lake via barge. It involves calculating the house weight, designing the barge and ramps, procuring materials, manufacturing pieces, assembling the barge, cutting the house in half, moving each half onto the barge via ramps, sailing across the lake, and offloading each half at its final location. Careful scheduling is needed to ensure all teams have the necessary pieces completed on time and the large project stays on track.

Uploaded by

Abdu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
40 views2 pages

Activity

This document outlines the steps and dependencies required to transport a house across a lake via barge. It involves calculating the house weight, designing the barge and ramps, procuring materials, manufacturing pieces, assembling the barge, cutting the house in half, moving each half onto the barge via ramps, sailing across the lake, and offloading each half at its final location. Careful scheduling is needed to ensure all teams have the necessary pieces completed on time and the large project stays on track.

Uploaded by

Abdu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Activity Activity Description Predecessors

ID
1000 Start of Work Start Milestone
1010 Calculation of weight of the To Start work
house
1020 Making the design of barge Calculation of weight and stability studies for
the house
1030 Procurement of material for Making the design of barge
making barge
1040 Design calculations for Calculation of weight of the house
ramps
1050 Procurement of material for Design calculations for ramps
making ramps
1060 Material delivery for barge Procurement of material for making barge,
and ramps Procurement of material for making ramps
1070 Manufacturing individual Material delivery for barge and ramps
pieces of barge and ramps
1080 Arranging flatbed trucks for Material delivery for barge and ramps
carrying barge pieces
1090 Carrying of manufactured Arranging flatbed trucks for carrying barge
individual pieces of ramps to pieces, Manufacturing individual pieces of
lake barge and ramps
1100 Assembly of barge Carrying of manufactured individual pieces of
ramps to lake
1110 Arrangement of machinery Calculation of weight of the house
for cutting the house
1120 Cutting of the house into half Arrangement of machinery for cutting the
house, Calculation of weight and stability
studies for the house
1130 Arrangement of wheeled Calculation of weight and stability studies for
dollies for carrying the the house
house
1140 Assembly of ramps on the Carrying of manufactured individual pieces of
lake ramps to lake
1150 Arrangement of tow trucks Calculation of weight and stability studies for
with winches the house
1160 Making arrangements to Arrangement of wheeled dollies for carrying
shift the house the house, Arrangement of tow trucks with
winches, Assembly of barge
1170 Shifting the house Arrangement of wheeled dollies for carrying
the house, Arrangement of tow trucks with
winches, Assembly of barge
1180 Fastening the house onto Shifting the house
the barge.
1190 Sailing across the lake Fastening the house onto the barge.
1200 Uninstalling ramp and Sailing across the lake
installing in other end of the
lake
1210 House reaching other end of Sailing across the lake
the lake
1220 Making arrangements to House reaching other end of the lake
offload the house
1230 Offloading the house Making arrangements to offload the house
1240 Arranging tow trucks with Uninstalling ramp and installing in other end of
winches and dollies the lake
1250 Pulling the house Arranging tow trucks with winches and dollies
1260 Fixing at location Pulling the house
1270 Repeating the process for Fixing at location
second half
4-If I was the project manager for this job, I believe the scheduling challenges would be is to have
everyone on the same page. This is a huge project so if one group is off it will throw off the whole
project. For example imagine if the crane team did not show up on the day to help move the house this
would set the date behind. Also being able to have everyone there at the same time would probably be
an issue. In order to ensure project success you would need to select the right people for the job. Make
sure you have a team and executive buy in which is A specific person at the top of the organization
needs to take ownership and show support of the project. The next thing would be to reduce work in
progress, which strain the project and causes all projects to suffer. Project success also needs to have
regular meetings weekly sometimes daily to make sure each team is on track on the project. Scope,
Schedule and Budget are well known touchstones for keeping a project on track.

Assemble Barge2Attach Motor Boats13Move Dock and Boathouse4Move Barge to


house25Build Ramp ontoBarge46Cut House in Half7Move 1stHalf ontoBarge5,68Disassemble
Ramp79Move 1stHalf to finalresting place810Assemble Exit Ramp911Pull 1sthalf up thehill to
final restingplace1012Disassemble Ramp1113Move Barge to @ndhalf of house1214Build Ramp
ontoBarge1315Move 2nd Half ontoBarge1416Disassemble Ramp1517Move 2nd Half tofinal
resting place1618Assemble Exit Ramp1719Pull 2ndhalf up thehill to final restingplace18