CHAPTER 2
METHOD OF BUILDING ESTIMATE
Example 1. — Estimate the quantities of brickwork and plastering required in a wall 4m long,
3mhigh and 30cm thick. Calculate also the cost if the rate of brickwork is Rs. 320.00 per cu mand
of plastering is Rs. 8.50 per sq m.
Quantity of brickwork = LB x H = 4mx3 mx 30 = 3.6 cum,
Quantity of plastering (two faces) = 2x Lx H = 2x 4m x3 m= 24.sq m.
Cost of brickwork = 3.6 x 320,00 Rs, 1152.00.
Cost of plastering = 24 x 8.50 = Rs. 204.00.
Total cost = 1152.00 + Rs. 204.00 = Rs. 1356.00.
Example 2. — Prepare a detailed estimate of part of a wall of a building from the given plan
and section and general specifications (Figs. 2-1 and 2-2).
GENERAL SPECIFICATIONS :
(1) Foundation concrete shall be of lime concrete.
(2) Foundation and plinth shall be of Ist class brickwork in lime mortar.
(3) Damp Proof Course — 2.5 mm c.c. |: 1% : 3 with water proofing compound.
(4) Superstructure — Ist class brickwork in lime mortar.
(5) Wall finishing — Inside wall [2 mm Cement plastered I : 6 and white washed 3 coats.
Outside wall 12 mm cement plastered I : 6 including 10 cm below ground level and finished
with two coats of colour wash over one coat of white washing.
RATES : Assume local current rates.
Note: — Fig. 2-1 and Fig. 22 are plan and cross-section of the wall with standard modular
brick and with traditional brick respectively. For simplicity only a portion of a wall has been taken
and licnce there are no footings at the ends.ESTIMATING OF WALL
Pi nd Section
Plana Fig. 2-1
WALL WITH STANDARD MODULAR BRICKS.
Inside
‘Super Structure Wall
2.5m D.P.c,
Plinth Level
2nd. Footing
Ist. Footing
«Lime Cone
CROSS SECTION
Fig. 2-2
WALL WITH TRADITIONAL BRICKS.
800m. 4
CROSS SECTION
a)
———I
eee COUT
PLAN AT PLINTH.
With Standard Bricks, Fig. 2-1 —
45.7 om,
Dimensions
sagem |
k}-———_ 600m. ————
PLAN AT PLINTH.
DETAILS OF MEASUREMENT AND CALCULATION OF QUANTITIES (Ex. 2)
T | Quantities!
tem! Description of items of work | No. }— i | ot Total
No Length Breadth) Ht, or | Contents. |yuansities
Depth |
1 iiesanenre ation in foun- | |
arthwork in excavation in eee
| dation : 00m] 80 | 90m 4.32 eum
2. | Lime conerete in foundation ..,| 1 |6.00m) .80.m om) 14d [LAs cum
2. | fst elass brickwork in lime mortar | |
in foundation and plinth | : |
Ist footing 1 |6.00.m | 60 m 20m | 72
| Ind footing 1 |6.00m| 50m | 20m 60 ||
| Plinth wall up to GL “| 1 [6.00:m| 40m | 20m) AK F324 crm
Plinth wall above G1 + [6.00 m] 40m | 60m) 44? |
deontd,
|
SS
i STIMATING AND COSTING
] Dimensions Quantities
fem) Deseription of items of work No. — — or | Total
No. Length [Breadth] Ht. or | Contents | quantitiey
| | Depth
4. | 2.5m Damp proof course(D.P.C.) | fo i a
jee 3 e| 1 {6.00 me} 40 m ae 2dunas|
5. | First. class Brickwork in lime | ao
| mortar for superstructure +-| 1 [600m 30m /3.50m| 63 | 63cum
6. 12 mm plaster of Cement sand | | \*
16 |
Inside | 1 |6.00m
Outside including 10 em below | 46.294 m
GL. | j 1 |6.00m 25,
7. | White 3 coats (inside) 1 {6.00 m 21.0 | 21.0 sqm
%. Colour washing 2 coats over one} | |
coat of white washing (outside| | |
above Gb) ea | 1 |6.00.m 24.6 |24.6 sqm
ABSTRACT OF ESTIMATED COST (Ex. 2)
. i. 2re | Amount
Item Description of Items of Work (Quantity) Unit Per z
No. | em eee _ I { . | Rs.
|. | Earthwork in excavation in Foundation} 4.32 | cum | 350.00 [eum | 15.12
2. | Lime concrete in foundation with white |
lime, surkhi and brick ballast 1.44 | cum | 220.00 | percum 316.89
3. | Ist class brickwork with white lime and | | |
|surkni mortar 1; 2 in foundation and
| plinth 3.24 | cum | 300.00 |percum 972.00
4. | 2.5 em thick cc. 1 : 14 : 3 Damp proof 1 |
course with water proofing compound | 24 | sqm | 20.00 | persqm) 48.00
5. | Ist class Brickwork with white lime and |
surkhi |: 2 mortar in super-structure | 6.3. | cum | 320.00 | Per eum] 2016.00
6. |12 mm cement and local sand plaster |
1:6 46.2 | sqm 8.50 | persym) 392.70
7. | White washing 3 coats 21.0 | sqm | 0.75 |persqm, 15.75
8. | Colour washing 2 coats over one cout of | |
white washing [246 | sam | 082 |persqm| 20.17
a Total .., 3796.54
Add for Contingencies 3% : 113.90
Add for Workcharged Establishment 20% | 75.93
Grand Total... | 3986.37
wall have not been taken into consideration: and the outer plinth offset of Sem has
Note : — For the items of plastering and white washing or colour washing the end faces of the
been neglected.METHOD OF BUILDING ESTIMATE,
Trench Filling. — Earthwork in trench filli i I ed
fe ae ee ke usually not taken into account. If require
Quantity of earthwork in trench filling = Quantit i antity of concrete +
Y yy in excavation — Quantity of concrete
Quantity of brickwork upto G.L. = 4.32 — (1.44 + 1.80) = 1.08 cu m >
For simplicity the earthwork in trench filling may be taken as I /5 of earthwork in excavation.
Example 2 —
ional Bricks, Fig. 2.2 —
_. With traditional bricks, the items of foundation concrete, Plastering, White washing and
Colour washing are same as for above. The earthwork, Brickwork in foundation and plinth,
Brickwork in superstructure, and D.P.C. differ and are as calculated below :—
Item 1. — Earthwork in excavation in founda-
tion v1 6,00 m x .80 m x.75 m= 3.69 cum
Item 3. — Ist class brickwork in lime mortar
in foundation and plinth —
Ist footing v1 6,00 m x 686 m x 15 m = 0.62 cum
2nd footing 1 6.00 m x .571 mx .15 m= 0.52
Plinth wall above footing ve 1% 6.00 m x .457 m x .75 m = 2.06
Toial = 3.20 cum
Item 4, — 2.5 cm thick D.P.C.1:1%:3 0... 1* 6.00 mx 457 m = 2.74 sqm
irst class brickwork in lime mortar
in superstructure a 1 x 6.00 m * 343 m x 3.5 m= 7.20 cum
Abstract of cost may be prepared accordingly.
Item S. -
METHODS OF BUILDING ESTIMATE
The dimensions, length, breadth and height or depth are to be taken out from the drawing —
plan, elevation and section. From the study of the drawings, the building is to be imagined and
pictured in the mind and the dimensions are to be taken out correctly. Thereis no hard and fast rule
for finding out dimensions from the drawing but the dimensions are to be taken out accurately.
‘Junctions of wall at the corners and at the meeting points of walls require special attent
For symmetrical foundation which is the usual case, earthwork in excavation in foundation,
foundation conerete, brickwork in foundation and plinth, and brickwork in superstructure may be
estimated by either of the following two methods.
METHOD I
Separate or individual wall method. — In this method, measure or find out the external length
of walle running in the longitudinal direction generally the long walls out-to-out, and the internal
lengths of walls running in the transverse direction in-to-in i.e. of cross or short walls in-to-in, and
calculate quantities multiplying the length by the breadth and the height of wall. The same rule
applies to the excavation in foundation, to concrete in foundation and to masonry. Care should be
taken to note the difference in dimensions at different height due to offset, or footings. It is
convenient to imagine plans at different level of heights as foundation trench plan, foundation
concrete plins of each footing, etc. and dealing each plan or part separately.~
30 ESTIMATING AND COSTING
[The simple methodis o take the long walls and short or cross walls separately and to find ou
the centre to centre lengths of long walls and short walls from the plan, Foreseoreen footing on
either sides, the centre line remains same for superstructure and for foundation and plinth."
For fong walls add to the centre length one breadth of wall, which
out-to-out, multiply this length by the breadth and the height and
(Long wail length out-to-out = centre to centre length
y + half breadth on one side + half breadth
on the other side = centre to centre length + one breadth).
For short or cross walls subtract (instead of adding) from the centre length one breadth of wall,
Which gives the length in-to-in, and repeat the same process as for che long walls, subtracting one
breadth instead of adding.
(Short wall length in-to-in = centre fo centre length — one breadth).
Thatis, in case of long wall add one breadth and in case of short w:
all subtiact one breadth from
the centre length to get the corresponding lengths,
zn foundation the offset of concrete on either side may be 10 em to 20 em depending on the
(hickness of concrete (usually less thgn the thickness of conerete). The offset once of brick
wall of standard bricks is 5 cm, and of traditional bricks is 5.7 em,
This method can also be worked out in a quicker way. For long walls find the length of the
foundation trench of the long wall out-to-out in the same manner ae explained above, the length of
{he foundation concrete is the same, for the length of the first footing or first step of brick wall
subtract two offsets in foundation conerete from the length of the trench or concrete: for tre eens
footing subtract from the length of Ist footingtwo offsets in footing ie.25- len oney eins
cm for traditional bricks), for the third footing subtract from the length of the 2nd footing two
olfsets i.e. 10 em (11.4 cm for traditional bricks) in this way deal the long walls up to the
cnpersiTucture. [For 25.4 em x 12.7 em x 7.6 cm (10" x 5" 314") bricks, one offset in footing - 6.35,
cm and two offsets = 12.7 em].
For short wall follow the same method but instead of subtracting, add two offsets to get the
corresponding lenyih in-to-in.
twill be noticed that by taking dimensions in this way, the long walls are gradually decreasing
in length from foundation to superstructure, while the short walls are increasing in length.
It may also be noted that the wall which is taken first is to be treated as lot
ng wall though its
length may be lesser, and the other wall be treated as short wall.
This method is simple and accurate and there is no chance of any mistake. This method may b
naried as Long wall and short wall method, or general method.METHOD OF BUILDING ESTIMATE a
The following examples (Exs. 3a, 4a, and 5a) illustrate this method :—
Example 3(a). — Fig. 2-
building of Sm x 4m, and §
Estimate the quantities of —
the plan represents the plan of superstructure wall of asingle room
ections represent the cross-sections of the walls with foundat'o
(1) Earthwork in excavation in foundation, (2) Concrete in foundation, (3) Brickwork in
foundation and plinth and (4) Brickwork in superstructure
‘The length of long wall centre to centre = 5.00 + 14% .30 + 4 x.30=5.30m. The length of short
wall centre to centre = 4.00 + 4 x .30 + 4 x 30 = 4.30 m.
SECTION ON AB
2
|
30.em.
PLAN OF SUPERSTRUCTURE WALL.—r
|
>
8 eM esmonng
2 4JedNg 10 UBid
TENA Ute} $0 UBled
+t Bd
[2 ory 22 woer—
1
ue
4q 2u0 yeep aq Aru pied yore
Jo Uror-ur jem Lys ayy pur
urorur yem Fuop 21 wry]
PC Big Ur UaAI se pourteur’
oq Aew jjen jo sdois 46
sdunooy yoeajo ued ay7 ‘a1a19
-uo9 uonepunoy pur yous
‘2409 spuno: uonepunoy jo urd 241 ‘89a
fe pune yo eg -huenb 2y) ovens op
i 29 WOES ——e
bing o11n6 Wem buoy A
‘S13A37 LN3Y33410 LY SNVId
ONILSOS GNV ONILVWILSS weMETHOD C# BUIT. DING ESTIMATE 3
DETAILS OF MEASUREMENT AND CALCULATION OF QUANTITIES (Ex. 3a)
Item| Particulars of 7 Height a
No. | Items No.|Length Breadth] or |Quantity| Explanatory note
oo Depth
1. | Earthwork in | - ceoe —_
|excavation in|
foundation — |
Long walls 6.20 m Length = 5.30 + 90
Breadth = 4.30 - .90
Re
Short walls... 3540:
2. | Conerete in
| foundation — i i
Long walls 6.20m| 90m | 30m] 3.35 | Length same as for excavati
| Short walls 3.40 m| 90m | 30m | 1.83 | Quantity = '/; of excavate
Total | 5.18
cum
3. | Brickwork in
foundation and
plinth —
Long walls —
Ist footing 2 |5.90m| .60m | 30m | 2.13 | Length = 5.30 + .60
and footing ...| 2 |5.80m| .50m4.30m | 1.74 | Length = 5.30 +5
Plinth walls -- 2 |5.70m| 40m | 60m 2.74 | Length = 5.30 + 4
Short walls —
Ist footing ...| 2 |3.70m| 60m) 30m] 1.33 Length = 4.30 ~ .60 = 3.70 m
2nd footing ...| 2 3.80 m| 50m | 30m 1,14 | Length = 4.30 - 50 = 3.80 m
Plinth walls ... | 2 |3.90m 40m | 60m 1,87. | Length = 4.30 - 40 = 3.90m
Total | 10.95
cum
4. | Brickwork in
superstructure
Long walls... 2 |5.60m)| 30m 2.50 m| 11.76 | Length = 5.30 + .30 = 5.60 m
| Short walls | 2 |4.00m| .30m |3.50m| 840 | Length = 4.30 206 4.00 m
Total | 20.16
cum
Note: The door openings,
superstructure as usual.
See next page (page 34) for further ch
Tt may be noted that in the case of long wall, the lengths of the 2nd footing, 3rd foc
differ by 10 cm and each is shorter than the previous one by 10 em,Similarly for short wall the length
is longer than the previous footing by 10 cm, Thus the lengths can be obtained by subtracting 0:
‘ndding 10 cm as the case may be. For traditional bricks (22.9 cm x 11.2 cm » 7.6 cm) the length can
be obtained by subtracting or adding 11.2 em, (For 25.4 cm ¥ 12.7 cm * 7.6 em bricks ada or
subtract 12.7 cm).
window openings, lintels, etc. shall have to be deducted trom
ete,4 ESTIMATING AND COSTING
As study of the plans and elevations (Fig. 2-5) will make it clear. The plan (i) shows the
foundation footings. The long walls and short walls may be imagined to be constructed Separately,
first the long walls and then the short walls, From the elevation (iii) and (v) it will be clear that the
length of each successive footing of long walls is reduced in length and that of the short walls each
successive footing is increased in length,
The corresponding breadth and height can be obtained from the cross-section of wall
PLAN AND ELEVATION OF WALLS (EARTH REMOVED).
Super structure
}
t
E
g
3
+
Plinth wall ¥ 40cm
=
2nd. Footing Xen
Ist Footing
Foundation Cone. -|
(v) PLAN OF SHORT WALL (DETACHED)
5s0moe |
Fig. 2-5 ()) PLAN OF FOUNDATION & FOOTING
i in fir ind footins
ith traditional bricks, the breadth of wall in first footing, seco
it et Exar ee ire wall will ‘be 68.6cm, 57.1 cm, 45.7 cm and 34.3 cm respectively. Th
oe aay Sib ‘problem having walls with traditional bricks.
studentMETHOD OF BUILDING ESTIMATE 35
Example 4(a). — Estimate the quantities of the following items of a two roomed building
from the given plan and section (Fig. 2-6) :—
(1) Earthwork in excavation in foundation, (2) Lime concrete in foundation, (3) Ist class
brickwork in cement mortar I: 6 in foundation and plinth, (4) 2.5 cmc.c. damp proof course, and
(5) Ist class brickwork in lime mortar in superstrueturé.
TWO ROOMED BUILDING
7.5.om L.C. Terrace Over 13 em A.C.C.
‘All Walls are of same section
Lintels over Doors. Windows and
‘Shelves ar@ 15 om thick R.B.
Doors D-1.20 m x 2.10m
Windows W-1.00 x 1.50 m
‘Shelves S-1.00 m x 1.50 m
GROSS SECTION OF WALL ON AA. Fig. 2-6
Note : — No beanrhas been shown in the plan as the object of this example is to explain the
metknd of estimating the walls only.36
DETAILS OF MEASUREMENT AND CALCULATION OF QUAN
ESTIMATING AND COSTING
TITIES (Ex, 4a)
Ttem] Particulars of “| THeight] ~ ——
No. | Items No. |Length|Breadth} or |Quantity| Explanatory note
_| Depth a
! Long wall, c/c. length = 44
7 6+ 30+2%%0 = 10.60 m
Short and Inter walls, c/c.
1, | Earthwork in length = 6 + 2x 0 = 6.30 m
excavation in
foundation —
Long walls ...! 2 {11.70 m| 1.10 m} 1.00 m] 25.74 | L = 10.60 + 1.10 = 11.70 m
Short walls ...] 3. | 5.20.m]1.10m|1.00m]| 17.16 | L = 6.30-1.10=5.20m
Total | 42.90
cum
2. | Lime concrete in
foundation —
Long walls ...} 2 |11.70 m| 1.10 m| 30m | 7.72 | Length same for excavation
Short walls ...] 3 | 5.20 m}1.10m| .30m | 5.15 — | Quantity=3/10 of excavation
Total | 12.87
3. | Ist class brick- cum
work in I : 6
cement mortar
in foundation
and plinth —
Long walls — \
Ist footing ...| 2 [11.40 m] 80m] 20m] 3.65 | L = 10.60 + .80= 11.40 m
2nd footing...| 2 |11.30m] .70m] 10m] 1.58 | L= 10.60 + .70¢ 11.30m
3rd footing ...| 2 |11.20m] .60m] .10m| 1.34 | L= 10.60 + .60=11.20m
4th footing ...| 2 [11.10 m} 50m] 10m] 1.11 | L= 10.60 +.50= 11.10 m
Plinth wall
above footing | 2 |11.00m] .40m| .80m| 7.04 | L = 10.60 + .40= 11,00 m
Short walls — =
Ist footing ...| 3 | 550m) .80m] 20m] 2.64 | L=6.30~.80=5.50m
‘and footing...| 3 | 560m] .70m] 10m] 1.18 |L=6.30-.70= 560m _
be obtained
Not 1
simply by deducting 10 cm fro!
1 : — Length of subsequent footings of long walls after Ist footing may
um first footing.METHOD OF BUILDING ESTIMATE n
Item] Particui J (Ex 4a Contd.)
tem] Particulars of ; -
Height
ena No. |Length|Breadth) or —|Quantity| Explanatory note
= ie Depth
3rd footing ...| 3] 5.70m) 60m] .10m| 1.03 [L=6.30-.60=5.70m
4th footing ..| 3 | 5.80m| 50m] .10m| 0.87 | L=6.30-.50= 5.80 m’
Plinth wall
above footing | 3 | 5.90m| 40m |_.80m| 5.66 | L~=6.30-.40=5.90m
Total | 26.10
cum
4. | Damp proof
course
2.5 em thick
ce. —
Long walls ...] 2 {11.00m| 40m] — | 8.80 | Lengths same as for plinth
Short walls ..] 3 | 5.90m| 40m|_— | 7.08 | wallinitem3.
Total | 15.88
Deduct door :
sills 2 | 120m) 4om| — |" 096
Net | Total | 14.92
sqm
5. | 1st class brick-
work in lime
mortar in
superstructure
Long walls ...| 2 |10.90:m| 30m [4.20m| 27.47 | L= 10.60 +.30= 10.90m
Short walls ..| 3 | 6.00 m| .30m [4.20 m| 22.68 | L=6.30-.30=6.00m
Total | 50.15
cum
Deduct —
Door openings | 2 [120m] .30m 210m) 151
Window
eens 4 {1.00 m! 30m |1.50m| 1.80
Shelves 2 |1.00m) .20_m |1.50.m] 0.60 | Back of eves 10 om thick
ee ;
Lintels over |» |1.50m| .30m'| .15m| 0.14 | Bearing 15 em
Lintels over :
wwindows 4 [130m] 30m] 15m} 0.23 | Bearing 15 em
intels over .
- Shelves 2 [1.30 m| 30m | .15m| 0.12 | Bearing 15em
Total off deduc-| tion | 4.40 |cum
Net_| Total | 45.75 jcum -
obtained simply
Note =
by adding 10 cm from first footing.
— Length of subsequent. footing of short walls ai Ist footing: ‘may be:ESTIMATING AND COSTING
RESIDENTIAL BUILDING
1.20 mie—
38
&
=
a]
g
g
g
8 ‘W,/cw
= 2.00 m ver.
A.
PLAN
10cm L. C. Over 120m A.C.
7.5. cm. L.C. Over 10cm R.C.C.
Yr som
4— 15cm
R.C.C. Lintel
20cm
Pillar
300m x 150m 7 q— 2.00m—4
Dycw
Doors:-
D, = 120. cm x 210 cm (1.20m x 2.10)
D,— 100 emx 200 em (1.00 m x 2.00 m)
D, - 75 cm x 180 cm (.75 m x 1.80 m),
Windows:-
W, ~ 100 em x 150m (1.0m x 1.50)
W, ~ 200 om x 150 em (2.00 m x 1.50)
W,-75.¢m x 120m (.75m x 1.20m)
CW. = 75 om x 60 cm (.75.m x 60°)
Shelves:
S100 om x 150 cm (1.00 m x 1.50
Lintel Over Doors, Windows Etc.
150mRB.
2.5emC.C. Over.
2.5m D.P.C. (T 7.5cm. LC. FLOOR
G pal >
+ 30cm ped
Bon 20cm 20cm
zuem 200m
G2s)- Ie— 500m =e ons
Aq cmk> Yocm :
CROSS SECTIONOF MAIN WALLS CROSS SECTION AB OF VERWALL
_Alfwalls of Drawing Rooms and Bath Roc walls have similar
ed Rooms have same section _ Section,
Note—No beam has been shown in the plan.
Fig. 2-7METHOD OF BUILDING ESTIMATE. 39
Example 5(a). — Estimate the quantities of the following items of a residential building from
the given drawings (Fig. 2-7) :—
(1) Earthwork in excavation in foundation, (2) Lime concrete in foundation, (3) First class
brickwork in I: 6 cement sand mortar in foundation and plinth, (4) 2.5 cm Damp proof course,
and (5) First class brickwork in lime mortar in superstructure. e
Centre to centre lengths of wall —
For estimating it is convenient to find the centre to centre lengths of different walls first. The
centre to centte lengths of different walls have been worked put below :—
Drawing and left hand side bed room combined —
c. to c. long walls = 6.00 + 4.00 + .30 + 2x .15 = 10.60 m.
c. to c. short walls = 5.00 + 2 x .15 = 5.30 m.
Bed rooms right side (both combined)
c. to c. long walls = 5.00 + 4.00 + .30 + 2x .15 = 9.60 m.
c. to c. short walls = 4.50 + 2x .15 = 4.80 m.
Front verandah —
Front wall c. to c. length = 5.00 + 4.00 + 2 x .30 +9020. 9.65 m.
Side wall c. to c. length = 2.00 +32
20.
37 2.25 m.
Back verandah including bath room —
c. to c. long wall (rear wall including bath room) 9.65 m same as front ver. wall.
¢. 10, length of side wall of bath room: = 2,50 +=32.+20.= 2.75 m.40 ESTIMATING AND COSTING
DETAILS OF MEASUREMENT AND CALCULATION OF QUANTITIES (Ex. 5a)
Item) Height .
No. No. |Length|Breadth] or |Quantity| Explanatory note
Depth
Earthwork in exca- |
vation in
foundation —
Drawing room and
left bed room —
Long walls 2 {11.50 m) .90 m |-1.00 m| 20.70 0.60 + .90 = 11.50 m
Short walls 3 | 4.40 m| 90m | 1.00 m| 11.88 30 - .90 = 4.40 m
Bed rooms right
side (both) —
Long walls
2 | 9.60 m| 90 m [1.00 m} 17.28
Short walls ...| 2 [3.90m) .90m|1.00m| 7.02
Front verandah
a 1 | 950m] 60m} .5om| 2.85
Side short wall 1 | 150m] 60m | som| 0.45
Back verandah
including bath
room
—Long wall (rear
wall including
bath) 1 | 9.50m| 60m} .som| 285 6:
Short walls
(remaining walls of
bath) “| 2 | 200m) 60m | 50m] 1.20 | fa2.7s 20-9 00m
2. | Lime conerete in
foundation —Draw- Total | 64.23
ing and left bed cum
room
Long walls...) 2 |11.50m} 90m] 30m} 6.21 | Lsame as for earthwork in
excavation
Short walls ...! 3 | 4.40m|.90m| 30m] 3.56
Bed, room right side
(both) —
Long walls ...| 2 | 9.60 m| .90m| 30m 5.18 | L same as for earthwork in
excavation.
Short walls ...| 2 | 390m] .90m| 30m] 211 |. :
Front verandah
Front long wall’.
9.70 m| 60m] 20m] 1.16 | L=9.65 - 50 +:
Side short wall ...|
1.70 m| .60 m | .20m 0.20 | L=2.25METHOD OF BUILDING ESTIMATE
‘articulars of
Ttems
| Back verandah,
including bath
room
Long wall including
bath
Short wall
(remaining walls of
bath)
Ist class brickwork
in foundation and
plinth in | : 6
cement mortar
bed room Long
walls —
Ist footing
2nd footing
Plinth wall above
footing
Short walls —
Ist footing
2nd footing
Plinth wall above
Drawing and left |—
Length
1 | 9.70 m|
2.20 m|
11.20 m)
11.10 m|
11.00 m|
4.70 m
4.80 my
footing
Bed rooms right
side (both) —
Long walls —
Ist footing
2nd footing
Plinth wall
above footing
9.60 m|
9.60 m|
9.60 m|
4.90 m | |
Breadth]
60m
60m
60m
50m
40m
60m
50m
atm
60m
50m
40m
*| Height
or
Depth
20m
20m
20m
90m
20m
20m
90m
20m
20m
Quantity
1.16
0.53
cum
2.69
2.22
7.92
1.69
1.44
5.29
2.31
1,92
6.91
41
(Ex. Sa Contd.)
Explanatory note
L=9.65 50
+ 0.
2 2
70m
7 50 60 4 4
122.75 5 -=2.90m
L = 10.60 + .60 = 11.20 m
L = 11.20 - 2x.05 = 11.10m.
L= 11.10 -.10= 11.00 m
L = 5.30 - .60 = 4.70 m
L= 4.70 + 2x 05 = 4.80 m
L= 4.80 + 10 = 4.90 m42 ESTIMATING AND COSTING
Item] Particularsof = || ~— | Height - —
No. | Items No. |Length Breadth] or |Quantity| Explanatory note
Depth
Short walls a
Ist footing 2 | 420m) 60m] .20m| 1.01 | L=4.80~ 60 = 4.20 m
2nd footing 2 | 430m) 50m | 20m] 0.86 |L=4.20+2x 05= 4.0m
Plinth wall above
footing _ ao 2 | 4.40 m| .40m | .90m 3.17 L = 4.30 + 10= 4.40 m
Front verandah —
Front wall —
Footing | 1 |9.65m| .49 | 20m} 0.77 |L=9.65 - a + 965m
Plinth wall above
footing 1 1 | 960m] 30m] .70m| 2.02 |1=9.65 - or + des, 60m
Side short wall
Footing | 1 | 185m} 40m | 20m} 0.15 |L=225- 49-4 185m
| 1 | 190m) 20m} .70m| 0.40 j1-2.25 4} -30-1.90m
including bath
room —
Lorig wall —
Footing we{ 1 | 9.65 m} 40m | 20m | 0.77 |) Length same as for fron
‘ verandah long wall
Plinth wall
above footing —...| 1 | 9.60.m| 30m] .70m| 2.02
Short walls
(remaining walls of
bath)
Footing | 2 | 235m) 40m | 20m] 0.38
Plinth wall 0
above footing =| 2 | 2.40m| 30m | .70m| 1.01 Sac
‘ Total | 44.95
“Note — It may be noted that for length of long walls of right side bed rooms. hall brea "
the left side has been deducted, and half breadth on the right side has been added.
For long walls of front and back verandah, half breadth of main walls on the lef hander,
thesame level, has been deducted, and half breadth of the verandah wall on the right han!
been added to get lengths. no
For cross walls of the rooms and side wall of front verandah. half nw educted
same level has been deducted for inner side, and half breadth of veran
for the outer side to get the lengths.
‘breadth of main
dah wall has beenMETHOD OF BUILUING ESTIMATE a3
_ _ (Ex. Sa Contd.)
Item| Particulars of Height ~ _
No. | Items No. |Length [Breadth] or |Quantity| Explanatory note
_ Depth
2.5 cm Damp proof ~ OO
course
Drawing and left
bed rooms —
Long walls 2 [11.00 m| 40m] — | 8.80 | L same as plinth wall.
Short walls 3 | 4.90 m| 40m - 5.88 | L same as plinth wall.
Bed rooms inner
side — .
| Long walls 2 | 9.60m| .40m| — | 7.68 |Lsame as plinth wall.
Short walls 2 | 4.40 m| 40m] — | 3.52 | Lsameas plinth wall.
Verandah Pillars ...] 4 | 0.50m| 30m] — oko 5 om extra on all sides.
Bath room — 7
Rear wall | 1 | 2.50m) 30m] — | 0.75 {L=2.20+2%.15=2.50m
Side and inter
walls w| 2 | 240m) 30m] — | 144
Total | 28.67
sqm
Deduct —
Door sills Di ...| 6 | 1.20m) 40m] —-| 2.88
Door sills D2... | 2 | 100m) 40m) — 0.80
Door sillsD; ...| 1 | 0.75m| 30m | — 0.23
[Total of] deduction 3.91
sqm
| Net | Total | 24.76
sqm
5. | Ist class brick-work
in superstructure in
lime mortar—Draw-
ing and left bed
| room —
| Longwalls | 2 |10.90.m/ .30m | 4.00 m} 26.16 | L.= 10.60 + 30 = 10.90 m
| Short walls 3 | 5.00 m} .30 m | 4.00 m} 18.00 | L = 5.30 30 = 5.00 mESTIMATING AND COSTING
44
|Particulars of
|e No. | Length [Breadth
Bed room right
side —
Long walls 2 | 9.60 m} 30m
Short walls 2 | 450m) .30
Front verandah
Front wall as
od 1 | 9.60 m) .20m
Side wall as
solid 1 | 2.00 m| .20 m
Back verandah
including bath
room —
Back long wall
as solid 1 | 9.60 m) .20m
Side and inter walls
of bath 2 | 2.50 m) .20m
Deduct —
Door openings
D. openings D, 6 | 1.20 m| 30m
D. openings Dz 2 | 1.00 m] 30m
D. openings Ds || 1 | 0.75 m} 20m
Window openings
W. openings W, 11] 1.00 m| 30m
|W. openings Wo 1 | 2.00 m} 30 m
'W. openings W3 2 | 0.75 m) 20m
Clerestory window
(C.W.) opening | 18 | 0.75 m| 30m
Shelves opening ... | 5 | 1.00 m| .20m
Front verandah
opening in between
pillars =| 1 | 8.40 :m) .20m
Front verandah
opening side 1 | 2.00 m} .20 m
Back verandah
opening 1 | 6.80 m| .20 m
Height
or {Quantity
Depth
4.00 m| 23.04
4.00 m| 10.80
3.05m) 5.86
3.05m} 1.22
3.05m| 5.86
3.05m) 3.05
Total | 93.99
cum
210m) 4.54
200m) 1.20
180m) 0.27
150m] 4.95
150m] 0.90
120m] 0.36
0.60m| 2.43
1.50 m 1.50
240m} 4.03
240m] 0,96
2.40m| 3.26
Explanatory note
L=9.60 - 30. 5 60m
L=480-30= 450m
L=9.65 - x + 20-9.60m
L same as front verandah.
Back of shelves 10 cm thick
wall.
L = 9.60 - 3x .40= 840m
L=9,60 - 2.40 - 40 = 6.80"METHOD OF BUILDING ESTIMATE 45
a _ (Ex. Sa Contd.)
Item| Details of Height
No. | Items No. |Length|Breadth| or —|Quantity| Explanatory note
Depth
_{|—_ —j—} _ | " frert —
Lintels
Over doors
D. doors Di s+ | 6 | 150m} 30m | 15m | 0.405 | Bearing 15 cm
ID doors D2 2 | 1.30 m) 30m | 15m] 0.117 | Bearing 15 cm
D. doors Ds 1 | 95m) 20m .15m| 0.029 | Bearing 10 cm
Over windows
W. windows Wi... | 11] 1.30 m| 30m] .15m] 0.644 | Bearing 15 cm
W.windows W2 ...} 1 | 2.30m) 30m] .15m] 0.103 | Bearing 15 cm
©. windows Wy) ...| 2 | 95m) .20m| .15m| 0.087 | Bearing 10 em
Over C.W. aes 18| 95m) 30m] .1Sm| 0.770 | Bearing 10 cm
Over shelves... | 5 | 1.30) .30m| .15m| 0.293 | Bearing 15 em
Verandah lintels
Front we| 1 {975m} 20m] 15m} 0.293 | L=9.60+.15=9.75 m
Side we| 1 | 215m) 20m | 15m} 0.065 | L= 2.00 + .15= 2.15 m
| Back ..| 1 | 7.50m} 20m} 15m} 0.225 |L=9.60-2.40+2x 15
= 7.50 m
Total off deduction 27.401 | cum
| Net | Total | 66.59 |cum
Note:— Verandah walls above lintel, verandah pillars, and bath room walls may be taken
separately and no deduction for verandah openings need be made.
ABSTRACT OF QUANTITIES (Ex. 5a)
1. Earthwork in excavation in foundation 64.23 cu m.
2. Lime concrete in foundation 20.22 cu m.
3. Ist class brickwork in foundation and plinth in 1:6 cement.mortar ... 44.95 cum.
4, 2.5 cm damp proof course 24.76 sq m.
5. Ist class brickwork in superstructure in lime mortar wee 66,59 cum.
Note:— Steps have not been taken into consideration as the object of this example is to
illustrate the method of estimating of walls only.ESTIMATING AND COSTING
46
METHOD I
. 5 hod sum-total length of,
Method. — In this method known as centre line met length of cente
eee and short, has to be found out. Find the total length of centre lines of walls, of
. d short having same type of foundations and footings and then fing th
suantities | ee multiplying the total centre length by the respective breadth and the height. In he
method, the length will remain same for excavation in foundation, for concrete in foundation, for
all footings and for superstructure (with slight difference when there are cross walls or numberof
junctions). This method is quick but requires special attention and consideration at the junction,
meeting points of partition or cross walls, etc.
For rectangular, circular polygonal (hexagonal, octagonal, etc.) buildings having no inter o,
cross walls, this method is quite simple. For buildings having cross or partition walls, for every
junction of partition or cross walls with main walls, special consideration shall have to be made to
find the correct quantity. For each junction half breadth of the respective item or footing is tobe
deducted from the total centre length. Thus in the case of a building with one partition wall or cros
wall having two junctions, for earthwork in foundation trench and foundation concrete deduct one
breadth of trench or concrete from the total centre length (half breadth for one junction and one
breadth (2 x 4 = one for two junctions). For footings, similary deduct one breadth of footing for
two junctions from the total centre length, and so on. If two walls come from opposite directions
and meet a wall at the same point, then there will be two junctions.
For building having different types of walls, each set of walls shall have to be dealt separately
Find the total centre length of all walls of one type and proceed in the same manner as. described
above. Similarly find the total centre length of walls of second type and deal this separately, andso
on.
In the case of a building having different type of walls, suppose the outer (main) walls are of
type and inter cross walls are of B type, then all A type walls shall be taken jointly first, and thenall
Btype walls shall be taken together separately. In such cases no deduction of any kind need be made
for A type walls, but when B type walls are taken, for each junction deduction of half breadth of A
type wall (main wall) shall have to be made from the total centre length of walls.
It may be noted that at corners of the building where two walls are meeting no substraction or
addition is required.
When there are number of footings, the length of the first footing is to be determined by
deducting half breadth of footing per ‘junction from the total centre line length and then the length
of the subsequent footing can be obtained simply by adding one offset of footing i.e. cm forever)
Junction to the length of the previous footing.
The examples 3(a), 4(a) and 5(a) which have been solved by method I in the previous pages.
have been solved again under examples 3(b), 4(b) and 5(b) in the following pages, by method Il0
illustrate this method. These illustrations will make this method quite clear.
Note.— Student should practice method J first and when they have become sufficica'!
acquainted with method 1, then only they should take up the method I
Example 3(b).— Estimate by centre line method the quantities of the following items of *
single room building Fig. 2-3 of example 3a (page 31)— (1) Earthwork in excavation in foundalo™
(2) Concrete in foundation, (3) Brickwork in foundation and plinth, and (4) Brickwork i*
superstructure.METHOD OF BUILDING ESTIMATE 47
Total centre length of walls = AB + BC +CD + DA = 5.30 + 4.30 + 5.30 + 4.30 = 19.20 m
Fig, 2-8 represents the foundation trench plan.
If the total centre length is multiplied by
the breadth and the depth we get the quantity
of earthwork in excavation. By doing so we
take certain portion twice and leave an equal
portion but this does not affect the quantity
The quantity of excavation = ABx 90cm
x90. cm + BCX 90cm x 90 cm + CD x 90. cm *
90 em + DA x 90 cm x 90 cm. It may be
noticed that the portions P,QR and S
marked with double hatch lines come twice
while the portions K,L,M,N left blank do not
come at all, but these portions being equal in
‘magnitude, we get the correct quantity.
‘The same principle applies to foundation con- ¥——_8.0m.cle., ————
crete, footings, plinth wall and superstructue wall.
DETAILS OF MEASUREMENT AND CALCULATION OF QUANTITIES (Ex. 3b)
Item] Description of Height
No. | Items No. |Length Breadth} or _|Quantity| Explanatory notes
| Depth
1. | Earthwork in
excavation in foun-
dation | 1 {19.20 m) 90m] 90m| 15.55 | Total centre length of all
| cum | walls = 19.20m
2. | Conerete in founda-
tion | 1 {19.20 m| 90m) 30m) 5.18
cum
3. | Brickwork in
foundation and
plinth
rioting | 1 (19.20m| .60m| 30m) 3.46
ee eh
Plinth wall 7 1 {19.20 m| .40m| .60m 4.61
Total | 10.95
| | cum
4. | Brickwork in super-
| structure | 1 |19.20 ml .30m|3.50m| 20.16 | Door and window open-
| | cum. | ings, lintels, ete. to be
| deducted.
Note. The above may be compared with the solution by method I given in page 33.—
48 ESTIMATING AND COSTING
Example 4(b).— Estimate by centre line method the quantities of the following items of atwo
roomed building Fig. 2-6 Example 4a (page 35)—
(1) Earthwork in excavation in foundation, (2) Lime concrete in foundation, (3) Ist class
brickwork in cement mortar 1:6 in foundation and plinth, (4) 2.5 em c.c. damp proof course, and
(5) Ist class brickwork in lime mortar in superstructure,
In this problem there are two junctions of the inter wall with the main wall.
2x. to. ¢. of long wall + 3 * c. toc. of short wall.
Total centre length of wal
2x 10.60 + 3 x 6,30 = 40.10 m
Fig. 2-9 represents the foundation trench plan.
Fig. 2-9
If the total centre length is multiplied by the breadth and depth, at the junction the portions A
and B shown by hatch lines in Fig. 2-9 come twice, and we get the quantity in excess by these
portions, and these excesses shall have to be deducted. The'deduction may be effected reducing the
centre length by half breadth for each junction.
Thus the quantity of earthwork in excavation —
= [Total centre length —(2 4 breadth)] x breadh x depth.
= (40.10 - 2x % x 1.10) x 1.10 x 1.00 = 39.00 x 1.10 x 1.00 = 42.90 cu m.
The same principle applies to foundation concrete, to footings, plinth wall and superstructure
wall. At every stage deduction of half breadth of the main wall at that particular level shall have to
be made per junction (i.e. one breadth for two junctions) from the total centre length, and this net
centre length after deduction shall be multiplied by the respective breadth and the height or depth to
get quantities. :
The estimate of the quantities of this Example 4(b) is as follows: —
asMETHOD OF BUILDING ESTIMATE
4“
ETAILS OF MEASUREMENT AND CALCULATION OF QUANTITIES (Ex. 4b)
Particulars of Height
Items No. |Length|Breadth| or /Quantity| Explanatory notes
_ Depth
Total centre length = 40.10
Earthwork in
excavation in foun- 1
— cee} 1 [39.00 m} 1.10 m] 1.00 m} 42.99 | L= 40.10 -2* ——
Lime conerete in = 39.00 m
foundation... | 1 39.00 m|1.10m| .30m] 12.87 | L same as above.
cum
Ist class brick-work
in 1:6 cement
mortar in
foundation and
plinth—
Istfooting | 4 39.30m] .80m| 20m| 6.29 | L=40.10-2* 89 = 39.30m
dnd footing | 1 |39.40m) 70m| 10m] 2.76 | L=40.10- 2% 2 = 39.40m
3rd footing | 1 {39.50 m| 60m| .10m| 237 | L=40.10-2* -=39.50m
th footing | 1. {39,60 m) .50m| 10m| 1.98 | L=40.10-2* 53-= 39.60m
Plinth wall above
footing ..| 1 [39.70 m| .40m| .80m| 12.70 | L=40.10 - 2 AC =39.70m
Total | 26.10
cum
Damp proof course
eC 1 [39.70 m| 40m] — | 15.88
Deduct door sill ..| 2 | 120m] 40m] — | 096
Net | 1492
cum
Ist class brick-work
in lime mortar in
superstructure... | 1 (39.80 m| .30m/4.20m| 50.15 | L=
Deduct door,
window, shelve
openings and
lintels | 1 | Same | as per [etait in
page 37| 4.40 | Deduction to be made as
neces as 79| ota
cum
Note. — The length of 2nd footing can be obtained simply by adding 10cm (i.e. 2x 5cm) to the
hof the Ist footing, the length of 3rd footing by adding 10cm to the length of the 2nd footing
50 on.
This may be compared with the solution by method I worked out in pages 36-37.50 ESTIMATING AND COSTING
Example 5(b).—Estimate by centre line method the quantities of the following items of a
residential building, Fig. 247 of Example Sa (page 38).
(1) Earthwork in excayation in foundation, (2) Lime concrete in foundation, (3) First class
brickwork in 1:6 cement sand mortar in foundation and plinth, (4) Damp proof course and (5) First
class brickwork in lime mortar in superstructure.
Total centre length of all 30 cm walls (same type) of main rooms
=Total centre length of walls of drawing and left side bed room + Total centre length of walls of
bed rooms right side
= (2X, toc. length of long wall + 3 xc. to c. length of short walt)
+ (2c. toc. length of long wall + 2 xc. toc. Jength of short wall)
(2 x 10.60 + 3 x 5.30) + (2 x 9.60 + 2 x 4.80)
7.10 + 28.80 = 65.90 m.
Number of junctions for these walls is 6 marked ‘x’ in the plan Fig. 2-7, page 38 and all these
junctions are with main walls of 30 cm.
Total centre length of all 20 cm walls (same type) of front verandah, back verandah and bath
room
=(c. toc. length of front wall + c, to c, length of side wall) + (c. to c. length of back verandah
Tong wall including bath + 2 c. to c. length of cross walls of bath room)
= (9.65 + 2.25) + (9.65 + 2X 2.75) = 11.90 + 15.15 = 27.05 m.
Number of junctions of these wall is 5 is marked ‘+" and one is,marked ‘-"in the plan Fig. 2-7,
page 38.
Five junctions are with main walls of 30 cm and one junction with similar wall of 20 cm.
‘See page 39 for centre length of different walls.
The estimate of the different items by cenive line method is as follows —METHOD OF BUILDING ESTIMATE SI
tem] Particulars of Height
No. | Items No. |Length Breadth] or |Quantity| Explanatory notes
ee Depth
1. | Earthwork in exca~ T : =
vation in
foundation —
Wall of main room
(Gixjunetions) || 1 63.20m) .90 m| 1.00 m| 56:88 | L=65.90- 6%-0-= 63.20m
including bath (five | -
and onejunctions)...| 1 124.50 m| 60 m| s0m| 7.35 |L=27.05-5x-92- 1 x-$0
4.50 mi
a)
Total | 64.23
. oum
2. | Lime conerete in
foundation —
Walls of main
rooms + | 1 {63.20 m} 90m} 30m] 17.06 | L same as above.
Walls of verandah
ee =| 1 25.50.m| .60m| 20m] 3.06 |i =27.05 5x52 1x60
= 25,50 m
(Minus half breadth per
Total | 20.12 | junction at the same level
cum
3. | Ist class brick-work
in foundation and
plinth in |: 6
cement mortar —
Walls of main
rooms — ,
Ist footing 1 l64.10 m) .60 m| .20m| 7.69 | L=65.90 - 6 x-$2-= 64.10m
2nd footing 1 [6440] 50m] 20m| 6.44 | L= 65.90 ~6 x32 =64.40m
Plinth wall above
footing 1 [64.70 m| .40m| 90 m| 23.29 | L=65.90 - 6 x3 = 64.70m
(Length of subsequent
footing after first can be
obtained by adding 6 * 5 =
Walls of verandah ie cm to the previous
and bath — footing). moe
Footing 1 [25.85m} 40m) .20m| 2.07 |L=27.05-5x=>- 13>
= 25.85 m
Plinth wall above maf
footing 1 [25.90 m} 30m] 70m] 5.44 | L=27.05-5x-37- 19>
| —__] = 25.90. m
Total | “44.93
cumESTIMATING AND COSTING
Item| Particulars of
L same as for plinth wall,
L=(2.20+2x.15)+2x
4030)
(295-8) = 130m
Details of deduction as usual
L=27.05 - 5 x"- 1 x=
= 26.20 m 7 :
Details of deduction as
Height
No. | Items No. |Length Breadth} or —|Quantity’
ao Depth
4. | 2.5m Damp proof a 7
course
Walls of main
rooms w | 1 64.70m} 40m}.— | 25.88
Verandah pillars ...| 4 | 0.50m| .30m| — | 0.60
Bath room (total o
3 walls) | 1 {730m} 30m] — | 249
Total | 28.67 |
Deduct door
sills Same | as per |detail in|
page | 43 391
Net | Total | 24.76
sqm
5. | Ist class brick-work
in superstructure in
lime mortar— .
Walls of main
a 1 65.00 m) .30 m}4.00 m| 78.00
Walls of verandah
and bath (as solid)| 1 |26.20m} .20m|3.05 m| 15.98
Total | 93.98
Deduct openings ian
and lintels Same | as per {detail in|
pages | 44-45 27.40_| usual.
Net | Total | 66.58
cum
i 5.
‘Note. —This solution may be compared with that of by method I worked out in pages 40-45
Method I, ‘Long wall and Short wall” method as explained in
followed in the Engineering Department. The measurement of the wor
foreach wall for preparing bill for payment and the quantity foreach wall as per:
be compared with the estimated quantity.
ly
sages 2910 45 is general!
Fi done, is taken separate
measurement mayESTIMATING OF R.C.C. FRAMED BUILDING 215
‘om the given
Example 1. — Prepare a detailed estimate of a small R.C.C. framed building fr
te of
plan, elevation and sectional elevation (Figs. 5~ -3). Fi i
Building. The General Specifications wre asollowss ee
eH — All 20 cm panel walls shall be of Ist class brickwork in | : 6 cement sand
mortar. Half brick wall shall be of Ist class in | : 3 cement sand mortar with hoop iron 25 mm *
1.5 mm or equivalent reinforcement at every fourth layer.
Reinforced work. — Exposed surfaces ofall R.C.C. work shal be fair finished with plastering
or floating with | : 3 cement sand mortar of sufficient thickness just to give a smooth and even
surface without any extra payment, Mild steel reinforcement shall be estimated separately. The
percentage reinforcement for different reinforced works are as follows :—
@ R.C.C. footing of columns — 0.5% (iv) R.C.C. chujja and sunshade — 0.5%
(ii) R.C.C. beams — 1.0% (v) R.C.C. roof slab — 0.8%
(iii) R.C.C. columns — 1.5%
Doors and Windows. — Doors and windows shall be of Ist class teak wood and finished with
2 coats of painting over one priming coat. All chaukhats shall be 12 x 8 cm. Door shutters shall be
4 cmthick panelled and Window and fan light shutters shall be 4 cm thick glazed. Rates of shutters
shall be excluding fittings. Windows shall be provided with 16 mm dia. bars.
Finishing. — Exposed surface of brickwork and half brickwork shall be plastered 12mm
thick I : 6 cement sand mortar. Inside shall be finished with 3 coats of white washing, and outside
shall be finished with 2 coats of colour washing over one coat of white washing.
(ID) Calculate also the P.A. Rate.
20cm
60cm 10cm L.C. Terrace
aE
semdiaC-LPi
HRP eg =a rary
SEE era
R.C.C, Som,
Thick AV w=
R.C.C. Footing For Col.
SECTION ON. ABC Fig. 5-2
4 Elevation see next page Fig. 5-3
Note.-- For Plan anR.C.C. FRAMED BUILDING
LI
(
:
PL
Kitchen
2.10m-x 3.70m
2.10m
goon
Livi
10cm x-210em Panelled
ing Room 3.70cm x 5.50cm
370m
106m Brick Wall Above Plinth
20cm Brick Wall upto Plinth
above R.C.C. Beam
Door 120cm x 210m
PD with 500m High Fanlight
—s
140 omx 180cm:R.C.C. FRAMED BUILDING a
Detai
pose tails of Measurement and Calculation of Quantities (Ex. 1)
Item] Particulars of ee ___—
No. | items and detail | ig)
ares Is | No. | Length |Breadth! aoe Quantity] Explanatory notes
m m m
1. | Earthwork in
excavation in
foundation—
Columns an 90
Cee 90 | 1.30 | 9.48
columns —
Front and back
walls wef 2 | 430} 20 | 1S
Side and inter
walls we
Walls in between
kitchen and
verandah afd
3 3.90 20 AS
1.30 20 AS
21.60 [x .20%] IS | =
Steps and side walls
including 6”
projections— Step including side walls
@ {a | 180} 70} .i7 | 021 { Sp ienten.
7) fa | tao] to |_17_| 0.02 _| step extended portion.
L Total | 10.36
Deduct for column ;
Portion doubly taken.
right side of gate | 1 | 075 0.35 | 17 | 0.05
Net. | Total | 10.31 |cum
2, | Earthwork in filling
in plinth—
Living room 1 | 3.70} 5.50
Kitchen s] yp | 200 | 3.70
1 | 2.00 | 1.70
Verandah
3. | Sand filling in
plinth—
Livingroom | | | 370 5.50 | 1S | 3.05
Kitchen 1 | 200] 370] 15 | LU
Verandah 1 | 200] 1.70 | 15 | 05!218.
ESTIMATING AND COSTING
a Particulars of aa: =
jo. | items and details No. | Length |Bread: leight ; —
of works readth| Da Quantity| Explanatory notes
a m m
4. | Cement concrete i ef ff _
1:3:6 in ee
foundation—
Column base 9 l-
Steps and side 90 | 90 | 10 | 0.729
walls —
@ w.{ 1 | 180] 70 | 07
i) ~ | : ; 0.088
(ii) | 1 | 110} 10 | 07 | 0.008
5 Total | 0.825 |cum
beams, slabs and
chujjas fair finished
excluding steel
reinforcement and
its bending but
including centering
and shuttering and
binding steel-
Footing of cols— Total of footing
Sq. bottom 9 | 90} 90 | 1S | 1.094 }f2.147 cum
‘Trapezoidal portion =
h/6 (Ar + Az +
4An) ce] 9 [3092] + 32 fa 6} 1.053
Columns | 9 | 20] .20 | 4.35 | 1.566
Plinth beams — “ ;
Front and back ...| 2 5.70 20 30. Total length excluding col.
Sides and inter ...| 3 | 530] .20 | .30 soem”
In between kitchen .
and verandah i} a | 200] .20 | 30 joe ons
79,30 | 0.20 x} 0.30= | 1.758
Roof beams —
Front and back 2! 5.20}| 20] 40
Sides and inter 3 | 5.30] .20 | .40
In between kitchen
and verandah 1 | 200] .20 | .40 ree
39.30 [x20] 0.40 =| 2.344 | Total of beams
. pat
R.CC. work in columns, beams. ‘slabs and chujjas each one may be a oan : : oat for
item as the rates differ. But in this estimate all \ypes weR.C.C. work are take
‘simplicity.R.C.C. FRAMED BUILDING a
(Ex. 1 Contd.)
Ttem| Particulars of —| Height
No. | items and details .
ii (orl No. | Length |Breadth| con Quantity Explanatory notes
| m | mj am
Roof slab | 1 | 630] 5.90 7 a 7
ee . 12 | 4.460
sunshades—Chuijja /
front w| 1 | 5.76] 60 | 06
Chujjaleft side ...] 1 | 356] .60-| .06
9.32 |x0.60x| 0.06=| 0.336
Sun-breakers
vertical 12 | 0 | .06 | 1.80 | 0.151 | 10 em inside wall
Sunshade over right
side windows ---| 2 | 150] .45 | .05
Total of chujja and
Sunshade over back
windows wef i 2.10 AS 05 sunshades =0.633 cum
1 1.40 45 05
6.50 |*0.45x| 0.05=| 0.146
Total | 12.908 | cum
6 | Mild steel including
bending in
reinforcement in
R.C.C, works—
R.C.C. footing 9.147 x| 5.x | 78.54 | 0.843 4 | Density of steel
@ 05% cum | 100 78.5 q/cum
R.C.C. column 1,566 x{_L2 x) 78.54 18444
@15% ' Sam | 100
R.C.C. beams 4.138 x|_L2 x) 78.54 | 3.248 4
@ 1.0% ~ cum | 100
R.C.C. roof slab 4.460 x|_2_*] 78:54 | 2804
@ 0.8% ae Py |
R.C.C. chujjas
and sunshades
@ 0.5%Item) Particulars of |
items and details No.
ESTIMATING AND COSTING
of works
Ist class brickwork
in 1 : 6 cement
mortar —
Living room —
Front and back
walls 2
Right side wall
excluding column | 1
Kitchen—
Front and back |
walls 2
Left side walls 1
‘Wall in between
ver. and living room
Height
Length Breadth] or |Quantity
Depth
m m m
3.70 20 3.05
5.30 .20 | 3.05
2.00 .20 | 3.05
3.70 .20 3.05
1.60 .20 | 3.05
22.00 | x0.20x| 3.05=| 13.420
3.70 20 AS
2.00 20 45
1.60 |" .20 45
Plinth wall—
Under 10 cm
partition wall 1
Under verandah
front parapet 1
Under verandah
side parapet - 1
Steps (i) f
(iii) 1
Walls by the side
of steps 2
Parapet wall over
roof slab—
Front and back 2
| Sides 2
Deduct openings—
Door
Windows
Rene
730 | *0.20x| 0.45=| 0.657
Loo | 75 | 25 | 0.188
100 | 25 | 15 | 0.038
60 30 70° | 0.252
Explanatory notes
Full height in between
plinth and roof beams.
20 cm wall up to floor.eS BSULLDING
—Ppantculars of —-—
| particulars of - a
na items and details No. |Lengsa [Breadth Height
of works or |Quantity’
Depth
— | m m
g | Half brick masonry caalaaen 4
Ist class in 1: 3
cement mortar with
hoop iron 25 mm x
| 1.5mm or equivalent
reinforcement at
every fourth course
Wall in between
kitchen and living
room a 705) 121) 2.00) | 9.62)
Ver. parapet wall
front eels 2.00 80 1.60
| Ver. parapet wall
side . 1 1.60 oa 80 1.28
Total | 12.50
Deduct opening—
Door oe (i k 1.00 = 2.10 2.10
Gate 1 1008 sce 80 0.80
9. |10 cm Lime Total | of ded juction 2.90
concrete in roof Net | Total | 9.60
terracing
finished with gur
| and belsiri : 2 es
treatment 1 | 5.90 | £50 °
10 | Teak wood
wrought, frazaed
and fixed in door
and windowchaukhat 1 5.28 2 08
| (framed) —Doot |
200m a
Boor with fan light |) | 7,68 2 | 08
120%260 cm - \
12.30 | -12 | 08
Window 170%1806m can 690 | 12 | 08
Window 110*180e™ 2) % : ,
6.60 | 12 | 08
Window 100*1800m an nee ee {
64.56 |x0.12x| 0.08=| 0.620
- *4cm insertion #
221
(Ex. | Contd.)
Explanatory notes
sqm
«floor for verticals of door chaukhat.
2 verts. — 2.14 m*
Uhors. — 1.00 m
2 verts. — 2.64 m
2 hors, — 1.20 m
4 verts. — 1.80 m
{
{
{
3 hors. — 1.70 m
G verts. — 1.80 m
3 hors. — 1.10m
2 verts. — 1.80 m
3 hors. —1.00 m
cum
———
&222
ESTIMATING AND COSTING
Item
No.
Particulars of
items and details
of works
No.
Length
m
/Breadth|
Height
or
Depth
m m
Quantity
Explanatory notes
Door shutters
4 cm thick panelled
of teak wood
excluding fittings—
Door 100210 cm
Door 120x210 cm
Window shutters 4
em thick glazed of
teak wood
excluding fittings—
Window 170x180cm
including fan-light
Window 110x180cm
including fan-light
including fan-light
Fan-light over
Door 120«50cm
Brass fittings in
doors and windows,
supplying and fixing
Iron work in hold
fasts and. window
bars—
Hold fasts—
Door 120x260cm
Door 100x210cm
Window 6 nos.
Window bars
16 mm dia.
(10 cm c/c approx.)
Window 110x180cm
excluding fan-Light
Fan-light of above
Window 100x180cm
excluding fan-light
Window 100x180cm |.
1x8
1x6
6x6
50
87
1.07
97
87
1.07
Same
nos.@
1.30
1.10
2.03
2.03
1,766
2.172
Total
1.62
1.62
1.62
45
Total
items
+11.207|
as for
=3.938
23.40
4.40
20.80
3.938
=15.145
50 kg
Ht = 210-8 +
1.5 - 5 = 203 cm
sqm
L=170 - (4x8) +
(6*1.5)=147 cm
Ht.=180 - (38)
+(4x1.5)=162 em
sqm
ll and 12)
sqm
4 on each side.
3 on each side.
3 on each side.
2 nos. horizontals.
1.30
Note— Rebate of door and window shutters 1.5 cm, clearance at the bottom of door shutters SemR.C.C. FRAMED BUILDING
223
ere >———
Particulars of a B
tem ems and details | No. |Length [Breadth] cs” © 1 Conia)
of works Depth (Quantity! Explanatory notes
_|—— cs m m
Fan‘light of above .|2x2| 1.00] = :
4.00 m| 2.nos. horizontals.
Windows 170%180 cm
excluding fan-light 2x15} 1.30
Fanlight of above |2x2| 1.70| = ice
oe 80 m| 2 nos. horizontals
ee 155.47
ke
Flat bars 25x6 mm |
horizontal at the |
middle of window—
Windows
foxig0cm «sf 2X1] LO | = ]220m
Windows
100x180cm | 2x1] 1.00) = |2.00m
Windows
Iox180cm [2X1 | 1-70 | = [340m
7.60 rm| @ 1.2 | kg= | 9-12 ke
Total |214.59| ke= | 2.1464
Iron gate (grill)
framed, fixed ..-| 1 | 1.00) — 80 | 80
sqm
12 mm plaster in | :
6 cement mortar—
INSIDE—
Living room walls | 2 | 550 | — o
3.70 | — | 2 :
Kitchen walls 2 3.70 | — 260 Bactoding R.C-C- Peas
2 | 210) — oa
Vv wf dl = \5
erandah walls = | 260
133.0 | x |260=| 87.36
Verandah parapet— 80 1.28 :
Inner face side 1 | 160) ~ | ‘go | 0.80 | Excluding gate
Inner face front 1 | 100) ~ au ;
Vertical'jamb of ‘io | 80 | 0.08 | One side
pate wf dl == ||224 ESTIMATING AND COSTING
Item| Particulars of Height | ]
No. | items and details | No. |Length|Breadth| or {Quantity Explanatory notes
of works Depth |
| m)om | m
Upper surface of
Pparapet—
Front ve) 1} 100] 10 O10 |
| Side «| Lf] eo) co | 0.16 |
| Jambs of door
| and fan-light |
120*260 cm | 2 08 | 260 | 0.42
| Jambs and sills of ;
large window L=180+180
170%180cm, s+} 2] 530} 08 | — +170=530 cm
| Total
Deduct openings—
Door 100120em ..,) 2 | 1.00 — | 1:20 | 240 | Both faces, jambs being
| small and no sills and
Door 120260 2 | 120! — | 260 | 6.24 | soffits.
Total | of ded | uction| 8.64
OUTSIDE— Total | inside | 82.41 | sqm
Back wall (whole
length) cl! 1 | 630 3.05
Right outer side -..) 1 | §.90| — | 3005 Excluding beams,
Front livingroom | 1 | 410| — | 3.05 including plinth.
Left outer side
| of kitchen v-} L | 440} — | 305
20.40 |] 3.05=| 62.22
| Verandah parapet
front vf 1 | 120] — | was | 13g
Verandah parapet Excluding band.
side Brat et ey) | tl! oy)
Side wall steps—
Outer sides 2/ 6} — | 6 | o7
Inner sides 2! 60 30 | 0.36 | Average height
Top “| 2 | 60| — | 30 | 036
Parapet above roof
am—
Inner faces front
and back Seas 0} ee 60 | 7.08
Inner facessides ... | 2 | 5159 | _ 60 | 6.60
Top front and
back 2 \ 630) 20) — | 259
Top sides --1 2 | 5.50] 20 | — | 239
Outer faces of front
and back including
grooveSx Sem... | 2) 630) — 85 | 10.71
—Do— sides 5.90 85 | 10.03 Sus. =60+ 10+ (3x5)=85 om
pees tL toRoo
CC. FRAMED BUILDING
225
vem) Particulars of : 5 (Ex. 1 Contd.)
No. | items and details No. Length Breadth ight
‘of works | Dea ‘ Quantity) Explanatory notes
ee ee |
Deduct openings—
Windows
TOxI80em | xt 396
Windows :
oox180em | 2x1 Jone face.
te oe line bs and sills
faces, jambs
Ve ] 12.24 | taken separately
led 19.80 |
| Total |outside| 86.45 | sqm
Total | of nsi | de
Pirates si | de and | outside | 168.86 sq m
steps in 1 : 3 cement |
mortar finished neat
ement floated—
Tread and rise 1 | 1.00 | 1.35 135
Ends of step 42 - 15 0.05 | Beyond side walls.
1.40 | sqm
18 | Brick band
10x10 cm in
1:4 cement mortar
complete with
plastering—
Front (Horizontal) | 1 | 4.10| — | — | 4.10
Side 1] 350] — | — |. 350
front vertical 2| 70) — | — | 140
| Total | 9.00 |rm
19 25emC.C.1:2:4
over and including
7.5 cm L.C. floor
finished with neat
cement floating—
Living room 1 | 3.70} $50 | — a
Kitchen 1} 240) 370) — | 27
Verandah 1 | 210} 1.70 | - ci ' i
Door sill 1] 100] 10) — | oq "yo. 1c. in sil
Door sill 1 | 220 |e
Total | 32.03 |sqm
0] White washing ,
coats inside— side | plaster
Wa inside | laste
Ceiling living room =
Ceiling kitchen . _
—_|Ceiting verandah =226 TIMATING AND COSTING
Htem| Particulars of Height
No. | items and details Breadth) or | Quantity Explanatory notes
Sf works | Depth
| om m m
Inner face of root |
cams
Living room 2 | 3.70
Living room 2 | 550 |
Kitchen 2 | 200) =
| Kitchen 12 | 370] —
j 29.80
Kitchen—soffit
of beam 1] 370) a0 | 0.37 | Over partition wall,
Verandah 2 | 200) — 40 | 1.60
| Verandah 2 | 160) — 40 | 1.28
Verandah soffit
of beam s+| 1 | 200] 20 | — | 040
Verandah soffit
of beam s+ 1] 160} 20} — | 032
Lower faces of
chujjas and
sunshades—
Chujja front 1 | 5.70] 60 | — 3.42 | Lower face white washed.
Chujja side 1 | 350] 60 | — | 210
Sun-breaker 2 60; — | 180) 2
Sunshades
over windows 2} 450 | 45 |y—
Sun shades
over windows...) 1 | 210 | 45 | \—
Sun shades
overwindows ...| 1 | 1.40 | 45 |) —
| 6.50x] 0.45 | = 2.93
Total | 139.86 | sqm
21 | Colour washing 2
coats over one coat
white washing—
Outside walls oe Same | as for |outside| plaster
initem| (16) 86.45
Outer faces of roof
slab, roof beams
and plinth beam
above G.L.— ‘
Front and back 2} 630) — 60 | 7.56 | Ht.=40 + 12 + 15 - 7=60em
Sides 2 | 590 | — 60 | 7.08
Upper faces of
chujjas and
Sun-shades—
Chuja front 1) 5.76] .66 | — | 3.80 | Upper faces and edges
Chujja side se[ 1 | 3.56 | 66 | — ) 235 | colour washed
Sun-breaker =. .| 2 | 66 | 1.80 | 238 |
L7 oa Lee —FRAMED. BUILDING
227
< rticulars of > (Ex, I Contd.)
lem | ems and details | No |Length|Breaath| "8" 1 - ontd.)
Now of works Depth Quantity| Explanatory notes
$$ — m m
inshade over > ~ —y — _
indows | 2 | 150
Sunshade over 7 153, |
windows =| 1} 20} si} — |
| Sunshade over i 1.07 |
inane |) to) st | — | on |
| Total
Deduct step ef | 60 | — | *5' | "33
Net | Total
2 | Painting doors and otal | 112.69 | sqm
windows two coats
over one priming
coat—
Panelled door... 1x24) 1.00 | — | 210 | 4.73 :
|Panelled door... 1x24) 1.20 | — | 210 | S67 }} 2% time one surface.
| Glazed fan-light
over door -.| Pt] 1.20 | — | 50 | 0.60 | One surface for both sides
| Glazed window ax1| 170 | — | 180 | 612 |
Glazed window 2x1 1.10 _- 1.80 3.96 ne surface for both sides.
Glazed window ...|2x1| 1.00 | — | 1.80 | 3.60
Iron gate (grill) ...|1x1| 1.00 | — | 80 | 0.80
Window bars
(excluding
chowkhat) w.[>a| 154) — | 164 | 5.05
| ax1| 94) — | 1.64 3.08 ‘One surface for over all.
| ax1| 84 oa | 2.7
Bars of fan-light
over door | ba] 104) — 42 \_ 0.44
| Total | 36.81 \sq.m.
23 | Solignum paint
two coats in back of
| chaukhat —
oor
| 100x120 cm ww) 1 | 5.28) 12] — | 063
Door with fan-light
1202260. me ea) ae lS oe
Window 170180cm | 2 | 12.30) 12 | — fee
Window 110x180em | 2 | 6.90) -12 | — ee
Window 100x180cm | 2 | 6.60 | — |
Total | 7.74 |sqm
ne mm Dia. C.1.
tain water pipe 21m -
_|fitted and painted | 2 | 100) — | oo)228 ESTIMATING AND COSTING
ABSTRACT OF ESTIMATED COST (Ex. 1)
Hem |
No. | Particulars of items
1 | Farthwork in excavation in founda
2) Farthwork in filling in plinth
3 | Sand filling in plinth (Local sand)
4 Cement cones
with brick balls
1.3:6 in toundation
RCC. work 1 2:4 fair finished
| excluding steel reinforcement and
but including centering
shuttering and binding steel
© | Mild steel reinforcement in R.C.C. work
7 | Lelass brickwork in 1: 6 cement
| mortar (one brick. 20 em thick)
i
8 | Halt brick masonry [-class in I : 3 cement
| mortar including hoop iron reinforcement
9 | 10cm lime concrete in roof terracing
| finished with gur and belgiri-treatment
10 | Teak wood wrought, framed and fixed in
chowkhat
LL | Door shutters 4em thick panelled of
teak wood excluding fittings
12 | Window shutters 4 em thick glazed of teak
| wood excluding fittings
13. | Brass fittings in doors and windows.
supplying and fixing
14 | Iron work in hold fasts and window
bars
] Rate | ‘Amount
Quantity] Unit _| Per
| [Rs Rs. P.
10.31 cum) 350.00 /% cum) 36.08.
10.90 cum) 275.00 |% cu m) 29.97
4.67 cum) 30.00) cum 140.10
0,825 cum) 300.00 cum| 247.50
| |
i |
| |
| |
12.944 |cu m| 675.00 | cum) 8737.20
8.985 | q |515.00/ q | 4627.28
14.694 cu m] 340.00] cum! 4995.95
9.60 'sqm! 50.00! sqm! 480.¢9
32.45 bq m| 35.00/ sqm| 1135.75
0.620 cu m}9200.00| cum | $704.00
|
3.938 |sq m| 200.00! sqm! 787.60
| 11.207 [sq m| 150.00| sqm | 1681.05
15.145 |sqm! 40.00| sqm! 605.80
2.146 | q | 700.00) q 1502.20
C.0. | 3071049 _