Building Construction Cost Estimate
Building Construction Cost Estimate
6
S/F sal woodfor door & window frame
door(D) 5.00 5.16 0.08 0.10 0.20
.76)kg/m2
6
S/F sal woodfor door & window frame
door(D) 5.00 5.16 0.08 0.10 0.20
door(D1) 2.00 4.40 0.08 0.10 0.07
window 5.00 7.26 0.08 0.10 0.29
0.56 Cum 242062.57 135555.03
7 s/f Flush door shutter
iii 6" th. Cement conctre Block wall work 1.00 10.00 0.15 1.00 1.50 Cum 9909.23 14863.84
with 1:4 c/s ratio with all complete work
10 gauge Fencing Jali 75x75 With angle
iv 1.00 10.00 0.65 6.50 sqm 400.00 2600.00
Frame
21 S/F gyp. Board ceailing works 2.00 3.00 3.00 18.00 Sqm 1276.67 22980.06
Flooring works
i Bouler Soling & Leveling work 1.00 6.00 8.50 0.10 5.10 Cum 3210.00 16371.00
ii P.C.C. (1:3:6 ) work 1.00 6.00 0.10 0.60 Cum 10510.45 6306.27
total civil works 1047998.52
Electrification works on building and
22
supply from service line to building
1 7x22 wire 2.00 2.00 2300.00 4600.00
2 3x22 4.00 4.00 1040.00 4160.00
3 20mm listi 30.00 30.00 30.00 900.00
4 swich socket 25.00 25.00 30.00 750.00
5 lead bulb 12.00 12.00 170.00 2040.00
6 M.C.B 6.00 6.00 500.00 3000.00
7 Submeter 1.00 1.00 1200.00 1200.00
16650.00
Watersupply works from main line to
23 18814.50
building
iii 1/2" dia. G.I Pipe 15.00 r/m 545.46 8181.90
iv G.I Shocket 8.00 Nos 59.89 479.12
vi 3" long nipple 4.00 Nos 30.51 122.04
vii 1/2"G.m Gate valve 1.00 set 1038.86 1038.86
ix 1/2" union socket 2.00 Nos 198.88 397.76
10219.68
Issuing Officer :
Certified that this books contains 2 Page of pre - numbered measurement sheets.
Er.
Jr.Er.Dipa
1 2 Building Construction Works User's Commettee Shyam Jee
Chapagain
Bastola
पोखरा लेखनाथ
25
महानगरपालिका
नगरपालिकाको कायार्लय
न्यूरोड, कास्की
४ नं प्रदेश, नेपाल
–Renovation of shed & Const. of Compound wall sfo{ k'/f ug]{ ldlt – sfo{
2063/;DkGg
/ k|ltj]bg v'b nfu]sf] vr{ :- 98349.82
sfof{:yfg M–Parsyang Children Park ,PLMC - 05 Estimate eGbf a9L jf 36L M–
sfo{ ;"? ldlt M– 2075-06-16 Estimated Amount :- 1326776.7 36L jf a9Lsf] k|ltzt –
v'b nfu]sf] vr{ 1115676.7 sfo{ ;DkGg ug]{ dfWod M– User's Commette
l;=g+= ljj/0f O{li6d]6 cg';f/ v'b nfu]sf] vr{ km/s kg{ cfPsf]
परिमाण दर रकम परिमाण दर रकम परिमाण प्रतिशत रकम
A Building Construction Works
E/W Exacavation in soft soil
1 6.83 504.7 3447.10 6.83 504.7 3447.10
including 10m lead & 1.5m
2 Boulder Soling and levelling 1.95 3210 6259.50 1.95 3210 6259.50
3 P.C.C. (1:2:4 ) work in lintel / sill 0.36 12256.46 4412.32 0.36 12256.46 4412.32
4 R/R stone Masonary Wall 1:4 c/s 7.23 10862.93 78538.98 6.76 10862.93 73433.40 0.47 5105.5771
6"and 4" th. Cement conctre Block
6 wall work in 1:4 c/s ratio with all
complete work 18.62 7582.15 141179.63 16.38 7582.15 124195.61 2.24 16984.016
S/F sal woodfor door & window
7
frame 0.56 242062.57 135555.03 0.56 242062.57 135555.03
8 s/f Flush door shutter 10.32 7635.12 78794.43 10.32 7635.12 78794.43
s/f Glazed window shutters with
9 5.45 9093.03 49557.01 5.45 9093.03 49557.01
4mm th. Glass
10 s/f grill for window 67.25 152.55 10258.98 67.25 152.55 10258.98
11 Roofing Works (Black Pipe) 201.37 163.85 32994.47 200.25 163.85 32810.96 1.12 183.512
S/f 26 BWG Colour C.G.I Sheet
including J hook & Bitumen
washer ,nutbolt etc. all complete 61.16 1005.12 61473.13 61.16 1005.12 61473.13
12 Frooring Works
i Stone soiling works 3.51 3210.00 11267.10 3.51 3210.00 11267.10
38mm thick 1:2:4 cement concrete
ii floor carting including finishing by
rubbing cement (Excluding Toilet) 44.7 609.99 27266.55 44.70 609.99 27266.55
iii Tiles works 13.99 2631.57 36815.66 13.99 2631.57 36815.66
12.5 mm th. Cement plaster works
13
in on Wall 1:4 C/S motar 129.02 364.43 47018.75 114.57 364.43 41752.74 14.45 5266.0135
पोखरा लेखनाथ
26
महानगरपालिका
नगरपालिकाको कायार्लय
न्यूरोड, कास्की
४ नं प्रदेश, नेपाल
sfo{ ;DkGg k|ltj]bg
14 M.S Rod 10 104.52 1045.20 10.00 104.52 1045.20
15 Painting Works
Two Coat distemper painting over
i
one coat primer 130.96 107.77 14113.55 116.51 107.77 12556.28 14.45 1557.2765
Two coat Readymade enamel paints
ii over one coat of wood primer for door
& window 26.58 286.19 7606.93 26.58 286.19 7606.93
16 Dress Stone Cladding Works 6.77 2206.80 14940.03 6.77 2206.80 14940.03
17
s/f Sanitary Works
S/f 1000Ltr Poly Water
of 20" polorized Tank
orissa pan with
withall
i complete setcystern with all complete
10lts plastic
1.00 18694.00 18694.00 1.00 18694.00 18694.00
ii set
S/f of 20"x16" hand wash basin with 1.00 9876.65 9876.65 1.00 9876.65 9876.65
iii all complete set 2.00 7417.94 14835.88 2.00 7417.94 14835.88
iv s/f Commode all complete set 1.00 11582.95 11582.95 1.00 11582.95 11582.95
v s/f Commode spray 1.00 850.00 850.00 1.00 850.00 850.00
vi Angle Stop cock 3.00 5251.00 15753.00 1.00 5251.00 5251.00
vii s/f 4" PVC pipe 5.00 541.34 2706.70 5.00 541.34 2706.70
viii 4" PVC Tee 2.00 630.00 1260.00 2.00 630.00 1260.00
ix 4" PVC Shocket 1.00 125.00 125.00 1.00 125.00 125.00
x s/f 1.5" PVC pipe 6.00 220.00 1320.00 5.00 220.00 1100.00
xi 20x16" looking mirror 1.00 938.25 938.25 1.00 938.25 938.25
xii 3" dis. Resolving shower 1.00 1053.20 1053.20 1.00 1053.20 1053.20
17 Septic Tank Construction Works
a E/W excavation in B.M.S. soil 10.90 504.70 5501.23 10.90 504.70 5501.23
b Bolder soling and levelling works 0.45 3210.00 1444.50 0.45 3210.00 1444.50
c Stone masonary works in 1:6 c/s mortar 3.50 9909.23 34682.30 3.50 9909.23 34682.30
PCC for RCC including material
d collection (1:2:4) 0.44 12256.46 5392.84 0.44 12256.46 5392.84
e Form work with local wood 4.46 640.40 2856.18 4.46 640.40 2856.18
Ms Works 53.58 104.52 5600.18 53.58 104.52 5600.18
18 Soak pit Construction Works
पोखरा लेखनाथ
27
महानगरपालिका
नगरपालिकाको कायार्लय
न्यूरोड, कास्की
४ नं प्रदेश, नेपाल
sfo{ ;DkGg k|ltj]bg
a E/W excavation in B.M.S. soil 4.08 504.70 2059.17 4.08 504.70 2059.17
b Bolder soling and levelling works 0.22 3210.00 706.20 0.22 3210.00 706.20
PCC for RCC including material
c collection (1:2:4) 0.13 12256.46 1593.33 0.13 12256.46 1593.33
d Form work with local wood 2.23 640.40 1428.09 2.23 640.40 1428.09
Brick masonary works in 1:6 c/s
e mortar 0.74 15088.33 11165.36 0.74 15088.33 11165.36
f Ms work Work 26.78 104.52 2799.04 26.78 104.52 2799.04
Compound wall construction
19
Works(For Children Park)
i E/W excavation on BMS 2.88 504.70 1453.53 2.88 504.70 1453.53
ii Bouler Soling & Leveling work 0.96 3210.00 3081.60 0.96 3210.00 3081.60
iii Rubble stone masonary 1:6 c/s (side) 12.08 9909.23 119703.49 9.32 9909.23 92354.02 2.76 27349.475
10 gauge Fencing Jali 75x75 With
iv 400.00 400.00
angle Frame 60.80 24320.00 - 60.80 24320
12.5 mm th. Cement plaster works in
v on Wall 1:4 C/S motar 39.04 364.43 14227.34 26.40 364.43 9620.95 12.64 4606.3952
Compound wall construction
20
Works(For trafic Building) 0.00 0.00
i E/W excavation on BMS 0.9 504.70 454.23 0.90 504.70 454.23
ii Bouler Soling & Leveling work 0.3 3210.00 963.00 0.30 3210.00 963.00
6" th. Cement conctre Block wall
iii work with 1:4 c/s ratio with all 9909.23 9909.23
complete work 1.83 18133.89 1.50 14863.84 0.33 3270.0459
10 gauge Fencing Jali 75x75 With
iv
angle Frame 19 400.00 7600.00 6.50 400.00 2600.00 12.50 5000
21 S/F gyp. Board ceailing works 18 1276.67 22980.06 18.00 1276.67 22980.06
Flooring works
i Bouler Soling & Leveling work 5.1 3210.00 16371.00 5.10 3210.00 16371.00
ii P.C.C. (1:3:6 ) work 5.1 10510.45 53603.29 0.60 10510.45 6306.27 4.50 47297.025
पोखरा लेखनाथ
28
महानगरपालिका
नगरपालिकाको कायार्लय
न्यूरोड, कास्की
४ नं प्रदेश, नेपाल
sfo{ ;DkGg k|ltj]bg
1199981.19 1047998.51
Electrification works on building
22 and supply from service line to 3% of civil works 35999.44
building
1 7x22 wire 2.00 2300.00 4600.00
2 3x22 4.00 1040.00 4160.00
3 20mm listi 30.00 30.00 900.00
4 swich socket 25.00 30.00 750.00
5 lead bulb 12.00 170.00 2040.00
6 M.C.B 6.00 500.00 3000.00
7 Submeter 1.00 1200.00 1200.00
18814.50
Watersupply works from main line
23
to building
i Road cutting deposite 20500.00 -
E/w in excavation for pipe laying in
ii
pitch cutting 4.05 576.80 2336.04 -
iii 1/2" dia. G.I Pipe 40 545.46 21818.40 15 545.46 8181.90 25.00 13636.5
iv G.I Shocket 8 59.89 479.12 8 59.89 479.12
v water meter 1 2200.00 2200.00 -
vi 3" long nipple 6 30.51 183.06 4 30.51 122.04 2.00 61.02
vii 1/2"G.m Gate valve 1 1038.86 1038.86 1 1038.86 1038.86
ix 1/2" union socket 3 198.88 596.64 2 198.88 397.76 1.00 198.88
24 site clearance works L.S. 3000.00 3000.00
10219.68
Total 1288132.75 1,077,032.70 211100.05
Contengencies @ 3 % 38,643.98 38,643.98
Grand Total 1326776.73 1,115,676.68 211100.05
पोखरा लेखनाथ
29
महानगरपालिका
नगरपालिकाको कायार्लय
न्यूरोड, कास्की
४ नं प्रदेश, नेपाल
sfo{ ;DkGg k|ltj]bg
less
The following features in this workbook are not supported by earlier versions of
Excel. These features may be lost or degraded when you save this workbook in
an earlier file format.
Some cells or styles in this workbook contain formatting that is not supported 24
by the selected file format. These formats will be converted to the closest
format available.
Compatibility Report for building work in children park.xls
Run on 9/25/2018 20:39
The following features in this workbook are not supported by earlier versions of
Excel. These features may be lost or degraded when you save this workbook in
an earlier file format.
Some cells or styles in this workbook contain formatting that is not supported 14
by the selected file format. These formats will be converted to the closest
format available.
Compatibility Report for building work in children park.xls
Run on 9/25/2018 20:43
The following features in this workbook are not supported by earlier versions of
Excel. These features may be lost or degraded when you save this workbook in