Headquarters' Procurement Process and Summary of Evaluation Report
3 Obbo Desalegn Tadesse VP – Retail and SMEs Banking Until May 23, 2022
4 Obbo Liko Tolesa VP – HC and Projects Management Until May 23, 2022
           7     Obbo Anteneh Demerew    Manager – Construction Projects Management   Until May 23, 2022
Headquarters' Procurement Process and Summary of Evaluation Report
  2.2 Current Construction Steering Committee (From May 24, 2022 to date)
       No.                 Name                           Designation                        Running
3. Procurement Committee
                      Chapter Three
    BID No. 03 – Bid Three Process through Short listing
        1. List of Invited Consultants
          The Employer announced a call to bidders (including DAR from the previous bid process) to
          participate on the bid through invitation letter dated on January 12, 2022 to the
          understated International Consultant – as per the direction forwarded by the Construction
          Steering Committee (with its minute CSC-1-2022).
               S/No   Bidders Name
                 1    Solidus S.R.L
                 2    Treinador International Services (PVT)
                 3    Dar Al-Handasah Consultant
                 4    ECG Consultant
                 5    CIMOLAI
                 6    General Group AG
       2. Bid Submission
          During bid submission dated February 21, 2022, out of the aforesaid six (6) Consultants, only
          two (2) Consultants submitted packages of technical and financial proposals.
Headquarters' Procurement Process and Summary of Evaluation Report
Headquarters' Procurement Process and Summary of Evaluation Report
             3.Bid Opening
    Attendance of purchase approval committee during bid opening
Headquarters' Procurement Process and Summary of Evaluation Report
       The evaluation has been done on the basis of RFP evaluation criteria which were prepared
       in the light of PPAs 2011 Guidelines by Public procurement agency, for Procurement of
       Goods, Works & Services.
  1.2.Technical Qualifications, Competence, and Experience of the Consultant (ITC Clause 16)
     A. The Consultant has successfully completed at least three (3) similar Contracts for Banks
        or similar high-rise building projects with a construction value of at least USD 20,000,000
        (Twenty Million USD) , in the past ten (10) years;
             The number of points to be assigned to each of the positions or disciplines shall be determined
             considering the following three sub-criteria and relevant percentage weights:
       ❑ There are 8600 staff currently working world wide and among them 5955 are professionally
         qualified Engineers, Architects, Town planners, Environmentalist, Economist, Finance,
         Marketing and Management specialist, Quantity surveyors and others,
       ❑ More than 150 of their professionals are found to be at higher level with minimum of 15
         years’ experience.
       Accordingly, we found the bidder full filled the must meet criteria
    Bidder 2: - Engineering Consultants Group (ECG)
       ❑ There are 3143 staff currently working world wide among them 2496 are professionally
         qualified Engineers, Architects, Town planners, Environmentalist, Economist, Finance,
         Marketing and Management specialist, Quantity surveyors and others and,
       ❑ More than 150 their professionals are found to be at higher level with minimum of 15 years’
         experience.
       Accordingly, we found the bidder full filled the must meet criteria
   2.Technical Qualifications, Competence, and Experience of the Consultant (ITC Clause 16)
      Headquarters' Procurement Process and Summary of Evaluation Report
                                             The project consists of 12 towers with varying floor from 30 to 50         Concept design, Detail design,
                                                                                                                                                              2012 to
  5     Ministry of Finance   Saudi Arabia   stories and total built up area 1.5 million square meters with             Tender document preparation and
                                                                                                                                                                2019
                                             construction cost of USD 4.2 Billion                                       Construction supervision
Headquarters' Procurement Process and Summary of Evaluation Report
Headquarters' Procurement Process and Summary of Evaluation Report
                                                                                                                   ●Concept Design
                                                                   The project consists of 12 towers with varying
    Ministry of Finance (Abraj                                     floor from 30 to 50 stories and total built up ●Detail design
2                                Makkah, Kingdom of Saudi Arabia                                                                                 2012- 2019
              Kudai)                                               area 1.5mil m2 with construction cost of USD ●Tender documents
                                                                   4.2Billion                                     ●Supervision of Construction
  Headquarters' Procurement Process and Summary of Evaluation Report
                                                   ●Project                                                                                             ●Project
                      The Park Tower consists                                                                                                           Management
                                                   Management                                       Ocean Heights Facilities include 310 meters
                      of 49 floors with built up   ●Detail design                                                                                       ●Detail design
    DAMAC                                                            2004-       DAMAC              Ocean Heights Soars with 87 floors. The                              2006-
3                UAE area of 185,800m2 with                                  3                UAE
                                                                     2011                                                                                                2010
    Properties                                     ●Supervision of               Properties         approximate construction cost is USD 205 Million ●Supervision of
                      construction cost of USD     Construction                                                                                         Construction
                                                                                                    and service fee for consultant is USD 4.1 Million
                      603,280,000 million.
Headquarters' Procurement Process and Summary of Evaluation Report
      Bidders were requested to present the average annual turnover calculated as total
      certified payments received for contracts in progress or completed within the last five
      (5) years must exceed USD 50,000,000.00 (Fifty million USD).
      Accordingly Both Bidders has full filled as per the criteria
4.2.Bidder result under Qualification with points
      4.2.1.Personnel Experience (100%)
       ❑ Total Experience = 30.00%
       ❑ Experience in similar works = 40.00%
       ❑ Experience in proposed position = 30.00%
      With the following Team Composition
      ❑   Environmental and Social Impact Assessment Plan
      ❑   Preparation of Bidding Documents
      ❑   Design Review Team
      ❑   Concept Design Team
      ❑   Construction Supervision and Contract Administration Team
      Headquarters' Procurement Process and Summary of Evaluation Report
         Accordingly the bidders submitted the required personnel as per the terms of reference and scored
         the following point
       MEP, HVAC, ICT & Fire Precaution                                       MEP, HVAC, ICT & Fire Precaution
IV                                         14.50     10.15              IV                                        14.50      10.1
       Service Design Team                                                    Service Design Team
        Accordingly, Out of 30% both bidders Dar Al-Handash Consultant and ECG have scores 30%
      4.2.3.Currencies of Financial offer in%
       ❑ Bidder were requested to present the financial proposal offer in the employer country and in
         foreign currency in the following option.
    After thoroughly discussing on the agenda, the members of the Construction Steering Committee
    unanimously forwarded the following condition with its minute CSC-4-2022, i.e. order was given to
    proceed with the Second Bid Opening (Financial Proposal Opening) and is to be conducted on April 9,
    2022.
                   Picture Captured during Financial Proposal Opening
Headquarters' Procurement Process and Summary of Evaluation Report
  Headquarters' Procurement Process and Summary of Evaluation Report
                                                     Total Amount
                          Total Amount Before                          Deviation after
                                                    After arithmetic                               Remarks
    No   Bidders Name   arithmetic check (in USD)                      arithmetic check
                                                    check (in USD)
                                                                           (in USD)
         Engineering
                                                                                          The price offered includes
    1    Consultants         17,395,244.00           17,395,202.00         -42 USD
                                                                                          payable local taxes and
         Group (ECG)
                                                                                          Vat (15%)
8.Consolidated Evaluation
                                                   Technical Score
     S/No    Firm Name         Technical Score out of      Converted Technical score to 60%                 Remark
                                       100%
 1          DAR                        89.69                              53.82
 2          ECG                        83.52                              50.11
                                                   Financial Score
     S/No          Firm Name                   Financial offer             Converted Financial              Remark
                                                                               score to 40%
 1           DAR                                10,158,538.0                       40
 2           ECG                                17,395,202.0                      23.36
9. Direction’s Passed by Construction Steering Committees on different issue related with Evaluation
Negotiation with the Responsive Bidders (DB Consultant) – Headquarters Building (HQ) – CSC-6-2022
  Technical and Financial negotiation points were raised to both bidders and detailed discussion and responses were
  forwarded accordingly. DAR was not ready at the moment but ECG forwarded discount offer of USD 9,788,494.00 (with
  VAT and TAXs) and hard currency (USD) to local currency (BIRR) proportion is 75% to 25% respectively.
  After thoroughly discussing on the agenda, the Construction Steering Committee recognized the aforesaid facts and
  unanimously forwarded the following direction, i.e.:
  ❑ Both bidders (Dar Al-Handasah Consultants and ECG Qatar) were requested to take the necessary
      discussion/negotiation points into account and submit their final discount offer by May 20, 2022.
Compiled summary of financial offer after negotiation
11. Conclussion
After thoroughly discussing on the recent situation, the Construction Steering Committee unanimously forwarded the
following decision with its minute CSC-7-2022, i.e.:
❑ Partially revise the Original RFP, reference to the aforementioned changes in scope of work/services,
❑ Partially cancel the recent bid process and communicate both bidders (Dar Al-Handasah Consultants and ECG Qatar) to submit a revised
   Financial Proposal and a revised Technical Proposal (if need be) reference to the aforementioned changes in scope of work/services; which
   are stated hereunder: -
     ➢ Project - A, on the 6,322 m2 plot, originally envisaged to be a 65 story skyscraper building shall be changed to a 40 story
        skyscraper building,
     ➢ Project - B with the following understated two (2) options:-
           ✓ Project – B1 (Option - 1), on the recently approved 11,244 m2 plot, shall be envisaged to be a 65 story skyscraper building,
           ✓ Project – B2 (Option - 2), on the 20,000 m2 plot to be approved in the near future, shall be envisaged to be a 65 story skyscraper
               building,
❑ Finally, Procurement Committee was ordered to thoroughly communicate the two (2) bidders (Dar Al-Handasah Consultants and ECG Qatar)
   on the new directions forwarded so that they can accordingly submit their revised proposals for the Bank’s subsequent action to follow.
       Headquarters' Procurement Process and Summary of Evaluation Report
         Picture Captured in the process of the new land Acquisition on requesting of 20,000m2 land
                                                                                 The Bank President at Addis A/A City
Letter submitted for A/A City Administration                                     Administration and Processing the new
                                               Proposal submitted for A/A City
land Bureau in requesting 20000sqm land                                          land for the bank
                                               Administration land Bureau
                                                 A proposal for
                                                 Construction of
                                                   Coopbank
                                                  Skyscraper
Headquarters' Procurement Process and Summary of Evaluation Report
   Headquarters' Procurement Process and Summary of Evaluation Report
                        Chapter Four
         BID No. 04 – Partial Cancelation of Bid and Request for Proposal
    ❑ Work plan
    ❑ Organization and staffing
    ❑ Work schedule/Master work schedule
    ❑ Team composition and task assignment Staffing schedule
Even though the previous project scope has been changed, the submitted technical document by both bidders
was not changed significantly and also can’t affect the prior awarded technical point. Thus the evaluation
team, after thoroughly review the technical document, have reached on the following recommendation.
    ❑ The submitted technical documents highly strengthen the previous technical document.
    ❑ The submitted additional technical document shall be considered during contract signing.
    ❑ RFP amendment made only on the project scope hence the evaluation criteria and the allotted points
       shall remain the same.
    ❑ Thus, the new technical document does not alter the previous technical score.
Headquarters' Procurement Process and Summary of Evaluation Report
 Therefore, by considering the above raised points, the evaluation teams have recommended that the
 previous technical evaluation report result for both bidder to be considered and at the same time
 it recommended to go to the next bid proceedings.
 Thorough discussion was made on the recommendation and the Construction Steering
 Committee unanimously forwarded the following decision with its minute CSC-9-2022 i.e.:
 ❑ Concerning the Technical Evaluation Report: it was decided to proceed as recommended by the assigned
    evaluation team – which is not to alter both bidders (Dar Al-Handasah Consultants and ECG Qatar) previous
    Technical Point and Score,
 ❑ And accordingly, order was given to proceed with the Second Bid Opening (Financial Proposal Opening) and
    shall be conducted on July 11, 2022.
Headquarters' Procurement Process and Summary of Evaluation Report
2.Financial Evaluation
   Financial Proposal before and after arithmetic check (The price is inclusive of local taxes and VAT)
                        Project - A                                                             0.00
                        Plot size 6322sqm            7,464,000           7,464,000
          Engineering
          Consultants
          Group (ECG)   Project - B1                                   12,584,000.16            -0.16
     1
                            Plot size 11244sqm       12,584,000
                        Project - B2                                                            -0.16
                            Plot size 20000sqm       12,584,000        12,584,000.16
Headquarters' Procurement Process and Summary of Evaluation Report
Financial Proposal before and after arithmetic check (The price is inclusive of local taxes and VAT)
                        Project - A                                                             0.00
                        Plot size: 6322sqm             8,296,100            8,296,100
         Dar Al-
    2    Handasah       Project - B1                                       16,427,175           0.00
         Consultant     Plot size:11244sqm            16,427,175
             Project - B1 on Plot
             size 11244sqm                                                    30.64
                                                 40
 Project-B
             Project – B2 on Plot
             size 20000sqm
                                                 40                           22.69
Headquarters' Procurement Process and Summary of Evaluation Report
  Project-A
  Plot size 6322sqm           50.11            40           90.11         53.82          35.99       89.81
 After thoroughly discussing on the aggregate point, the members of the Construction Steering Committee unanimously forwarded the
 following direction, i.e.:
 ❑ The Committee agreed to onboard both bidders for negotiation to minimize the risk which could arise from awarding both projects
     to one Consultant. The Committee also agreed that this could be realized if Dar Al-Handasah Consultants agrees to make further
     discount,
 ❑ In addition to risk minimization, the Committee reached consensus that willingness of Dar Al-Handasah Consultants for further
     discount and engagement on one of the two projects will also help the Bank commence the project on top urgent given that Dar Al-
     Handasah Consultants has already established a branch office here in Addis Ababa and is locally registered plus managing a
     project (like Ethiopian Airlines Skylight Hotel Expansion Project),
 ❑ Furthermore, the Committee also agreed that triangulation of technical expertise to be deployed by the two Consultants will
     significantly aid in administering both projects,
 ❑ Accordingly, Procurement Committee was ordered to arrange a negotiation meeting with both bidders (Dar Al-Handasah
     Consultants and ECG Qatar).
Headquarters' Procurement Process and Summary of Evaluation Report
4. Negotiation
Negotiation Meeting for DB Consultant Selection (as per the revised RFP) – Headquarters
Building (HQ) – CSC-12-2022
 As per the directions forwarded on previous Steering Committee Meeting, Negotiation meeting was conducted and both
 bidders were communicated on sharing the two projects,
 ❑ Due to the highlighted interest in commencing with Project – A on top urgent, the Committee expressed to DAR that the
    Bank is willing to work with them if it considers further financial discount relative to its competitor (ECG Qatar). DAR
    replied that they are willing to comply with the Bank’s latest interest forwarded and will make the necessary logical reviews
    on their financial offer for Project – A,
 ❑ In the same manner, ECG Qatar was inquired on the same session whether it is willing or not to engage on only one of
    the two projects; and if it is willing, it was also inquired to choose one of the two projects. In consequence, ECG Qatar
    replied that they duly understand the Bank’s perspective and are willing to work on one of the two projects and
    accordingly selected Project – B1 or B2 with its latest financial offer.
 Subsequent Construction Steering Committee’s direction:
 ❑ The Committee instructed DAR to submit its revised financial offer,
 ❑ Moreover, the Committee also instructed Procurement Committee to schedule opening of the revised financial offer in
    the presence of the Construction Streaming Committee members.
 Headquarters' Procurement Process and Summary of Evaluation Report
5. Final Decision
   Revised Financial Proposal Opening and Overall Evaluation Report Review (as per the
   revised RFP) – Headquarters Building (HQ) – CSC-13-2022
   ❑ Following the instruction forwarded on the previous Construction Steering Committee Meeting, only DAR submitted
      a Revised Financial Proposal for Project – A only; which is USD 7,397,663.00 (including VAT and applicable TAXs),
   ❑ Revised Financial and Overall Evaluation was conducted and is summarized as follows.