We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF or read online on Scribd
You are on page 1/ 7
iT la
Cee ae
idely used n areas of high standards
Soe
meat
Peace cs
Rr ee eee
eee
cn)
Pan)
ag
ts)
Tes
en the risk of un-
ee eeu)
Methods for performing the induced
eee aca aT ey
eee ae
eaten Ruse etd
Beet cen
oc
cn
Sy
KEYWORDS
Cee Seay
voltage testing, partial di
presto
harge
co
Diagnostic testin
of cast-resin
of
transformers
‘The development of cast-resin
transformers was initiated many decades
ago because of the flammable nature of
‘mineral oil and the risk of oil spillage with,
the related contamination of the ground.
Since then transformer
technologies have been well developed
and are now widely used in applications
where safety is of major importance,
for example in buildings, in industrial
applications, or for ecologically sensitive
areas, such as ground water protection
areas, The powerand the nominal voltage
of cast-esin transformers were increased.
cast resin
im the last few years. Nowadays, cast
resin transformers are built up to 72.5kV
and more than 60 MVA. They can also
be equipped with on-load tap changers
(LTO),
Although cast-resin transformers are
called “maintenance free, periodic
diagnostic measurements are requested
often — in particular, when outages
would cause high follow-up costs. Some
insurance providers offer cheaper tariffs
when the risk of outages is minimized by
periodic diagnostic measurements. For
cast-resin transformers the diagnostic
tools are limited. During manufacturing
TRANSFORMERS MAGAZINE | Volume 5, Issue 2ng routine tests are performed
according to TEC 60076-11 (1)
+ Tums ratio measurement
+ Winding DC resistance measurement
+ Measurement of voltage ratio and
phase displacement
+ Measurement of short-circuit
impedance
Load and no-load measurement
Applied voltage test
Induced AC withstand voltage test
Partial discharge measurement
(Un >3.6 KV, acceptance level 10 pC)
Figure 1. CPC 100 with matching transformers
www.transformers-magazine.com
In order to determine the transformer
condition directly on site, only a limited
amount of test procedures can be used
Especially when it comes to assessing
the insulation condition, common test
methods which are typically performed
‘on oil-filled transformers are not suitable
For instance, dissolved gasin oil (DGA)
analysis on cast-resin transformers is
not applicable. Vice versa, the power/
dissipation factor measurement on cast
resin transformers is highly affected
by the ambient conditions. Therefore,
partial discharge (PD) measurements
yield the most valuable information on
theinsulation condition. On-siteinduced
voltage test on cast-resin transformers,
combined with PD measurements, is
described in the following section
2. Partial discharge
Measurement
For partial discharge (PD) measurements
the frequency of the test voltage should
be higher than the nominal frequency to
avoid excessive excitation current during
the test,
‘The most common reason for failures
of cast-resin transformers is the electric
breakdown of the cast-resin insulation
between turns or parts of the windings.
In many cases, partial discharges occur
before the breakdown happens. By
testing the windings with induced
voltage in combination with a sensitive
PD measurement, the risk of unforeseen
breakdowns can be minimized,
TSN sean
For on-site PD tests on cast-resin
transformers, a voltage source with
adequate power is needed. ‘The frequency
ofthe outputvoltage should be higher than.
the nominal frequency of the transformer
to avoid excessive magnetizing currents.
In order to minimize the required power,
the source should deliver an output
voltage with variable frequency. The main
inductance of the magnetic core, the
capacitance of the high voltage winding
and the coupling capacitor build a parallel
resonance circuit. The frequency ofthe test
‘voltage should be tuned to the resonance
frequency of this parallel resonance
circuit to reduce the needed power to the
lowest level If the resonance frequency
is too high, an additional capacitor
can be connected to the low voltage
winding to reduce the frequency down
to the upper limit of 500 Hz, according to
TEC 60060-3 [2]. Figure 1 shows the setup
with the CPC 100, a compact voltage
source with a weight of 30 kg/ 66 Ibs
‘he built-in amplifier can deliver up to
SKVA at frequencies from 15 to 400 Hy.
Tt has a “Soft switching” design to avoid
disturbances by the switching semi-
conductors. With an additional matching
transformer, the output vollage of the
amplifier can be matched to the required
excitation vollage of the transformers
low voltage side. This universal matching
transformer can deliver voltages. from
50 V up to 400 V in steps of 50 V (at
frequencies of 100 Hz or higher) and
up (o 800 V (at frequencies of 200 Hz or
higher). During the factory acceptance
The most common cause of cast-resin
turns or parts of the windings
See
iz
87DIAGNOSTICS
Field experience has shown that voltages
up to 130 % of the rated voltage are a good
compromise to find partial discharge faults
but not stress the coil too much
er tegiee) eo atsi2}
*»
ros
°
°
Figure 2. Impedance ofthe test circuit vs. frequency
test (FAT), three phase generators re used
as voltage source. To check the integrity of
the coils onsite, tis sulicient to test each
phase individually using single phase
‘excitation, In the worst-case scenario a
voltage rise above the rated voltage could
lead to PD activity which remains active
‘even afier returning to nominal operation
voltage. Exceeding the nominal voltage
during testing helps to identify such
PD activity and to classify its severity
According to [1], during the FAT a pre-
siress voltage is applied for 30 seconds
Afterwards, the test voltage is applied for
another three minutes. On site, either
these test cycle durations can be used oran
Matching
‘Transformer
Matching
‘Transformer
Matching
“Transformer
Figure 3, Test system for 15 KVA with three CPC 100
88
adapted cyclecan be agreed upon. In order
to avoid unwanted breakdowns of older
ransformers, high-voltage ests. should
only be performed with lower voltages
than those used on new transformers in
the factory: Field experience has shown
that voltages up to 130 % of the rated
‘voltage are a good compromise to find PD
faults but not stress the coil too much.
Power transformers up to 3 MVA can
be tested using a test power of 5 KVA,
With the CPC 100, the impedance of
the whole test circuit can be measured
in amplitude and phase angle. Fig. 2. If
the frequency is set to the maximum
impedance (red curve), the required test
power is minimized
If the required power to energize the
transformer exceeds the power output
of one CPC 100, up to three devices can
operate in parallel, Fig. 3. One CPC 100
works as a master; the other two work
in a synchronous mode as slaves. To-
gether they can deliver 15 kVA on three
230 V 1/16 A plugs. With this portable
test system, cast-tesin transformers up
to 25 MVA can be tested directly on site
3, Electromagnetic
interference from the
surroundings
PD measurements outside of Faraday
cages are troublesome due to electro-
Transformer
under Test
TRANSFORMERS MAGAZINE | Volume 5, Issue 2Frequency 2
Pulse in 3CFRD after —"®
addition of phasors
Frequency 1
Frequency 3
Figute 4. Single PD impuise entered inthe 3CFRO diagram
When higher power is required, up to three
CPC 100 devices can operate in parallel,
allowing on-site PD testing of transformers
up to 25 MVA
‘magnetic interference from the surround
ings. Modern digital PD instruments
provide special filtering methods which
can reduce or even eliminate such noise
problems,
One possibility to separate PD signals
from ambient noise sources is to use the
BPARD or 3CFRD method (3). Both
Dar De
Se
pri’
beth baa ji |
beixdiidis |
Peake open te
methods make use of a so-called star
diagram which represents the relations
between three measured signals. ‘The
3PARD method uses three units to si
‘ultaneously pick up PD signals, while
for the 3CFRD method, the digital PD
instrument can measure PD impulses si
multancousy at three different frequen.
cies. For each frequency, a PD impulse is
evaluated. Afterwards, the discharge lev
dls obtained at three frequencies, using
a single instrument, are used to mark a
corresponding point in a star diagram,
Fig 4
Assuming that different PD and noise
sources differ in their frequency
spectrum, each source will show in a
different cluster in the star diagram. By
tuning the three frequency’ settings, an
optimal separation of the individual
clusters can be achieved. As a last step.
each luster is evaluated separately
without interference from the remaining
sources. This way a reliable evaluation
of all PD sources can be achieved on
site, even while strong disturbances are
present, Fig 5.
4. Case studies
4.1 Case 1
‘A PD measurement was performed
on a 33 MVA cast-resin transformer
with a rated voltage of 30 kV. Figure 6.1
shows the “Phase resolved PD” (PRPD)
diagram at 40 KV. The noise is about
8 pC. The analysis with the 3CFRD is
shown in Figure 6.2. The filtered signal,
in Figure 6.3, shows a clear pattern of
internal void discharges [4] with 6 pC,
although the PDs are below noise level.
‘The extinction voltage was above 36 KV,
which is 20 % higher than the rated volt-
age. As a conclusion, during normal
service no PD sources are active inside
the transformer.
Fitered interference signals ‘Separation through 3PARD or 3CFRD representation
‘Separated PO activity
Figure 5, Separation through 3PARD or 3CFRD representation
www.transtormers-magazine.com 9DIAGNOSTICS
Figure 6. (1) PRPD without 3CFRD filtering with interference; (2) star diagram with noise (op cluster) and PD cluster (marked); (3) PD pattem of
voids with 3CFRD filtering
Figure 7. Breakdown fault on cast-resin transformer
42 Case2
After a single-phase failure of 2.5 MVA.
cast-resin transformer, Fig. 7, it was in-
vestigated whether the remaining two
windings had also been damaged, A
partial discharge measurement on both,
outer windings was undertaken with
130 % of the rated voltage to prove that
these windings were free of PD. No PD.
could be detected above the noise level
of 15 pC. It was then decided to replace
the faulty winding and to put the trans-
former back into service
Figure 8 shows the PD_ measurement
results of phase B after installing the new
winding on the transformer. During the
on-site PD measurement interference
signals of 17 pC were measured. The
only visible cluster was related to the
ambient noise. In this case, the so-
called inverse 3CFRD was used, The
only visible cluster was selected and
filtered out, Fig. 82 Instead of showing
the impulses related to this cluster all
Figure 8 (1) Unitered PO measurement; (2) 3CFRD cluster selection; (3) PRD with inverse SCFRD fering
90
TRANSFORMERS MAGAZINE | Volume 5, Issue 2remaining pulses outside this cluster
ae shown. Figure 8.3 shows the inverse
principle of 3CFRD filtering while the
noise cluster was selected. Itcan be seen
that no other impulses are visible, which
leads to the conclusion that the new
installed coil has no measurable PD.
‘The inverse 3CFRD filtering should be
performed carefully in order to avoid
filtering out any PD signals
43 Case 3
In an industrial 20 KV grid, all cables
are equipped with HF PD couplers
at the terminations to make biannual
routine monitoring measurements of
the whole grid. including the cables
and the transformers, During 2 routine
‘monitoring test. partial discharges were
detected on one ofthe cable terminations.
‘To find out ifthe PDs are in the cable or
in the connected transformer, an off-line
PD measurement was catried through.
‘The cable did not show any PD, but
the transformer did. Figure 9 shows
the setup of a PD measurement on the
transformer under test. On all. phases
PDs were detected and showed typical
patterns of internal voids with discharge
levels up to 101 pC, Fig 10. "The inception
voltage was found tobe 1.0xUs, while the
extinction voltage was below nominal
voltage (0.6* Us) on all three phases.
‘This means that the transformer has
continuous partial discharges during
‘operation and should be replaced. As a
consequence, the operator decided to
replace the transformer completely
44 Case 4
PD measurements were done ona 30 KV /
6 KV 1.17 MVA cast-resin transformer,
Figure 11 shows the applied test setup
In order to energize the 6 kV side of the
transformer, an additional step-up trans-
former was needed, The required 10 kW
power to create excitation of one phase of
both transformers was delivered by three
synchronized CPC 100s, The test volt-
age of 1.3xU, was applied for 60 seconds
as agreed upon on site. Figure 12 shows
the PD measurement result of phase B,
which shows no PD impulses above the
noise level of 8 pC
Conclusions
On-site induced voltage testing in com-
bination with partial discharge measure
www.transformers-magazine.com
ane o
Figute 10, PO measurement results
Modern digital PD
nals from ambient n
struments separate
@ sources using
3PARD or 3CFRD methods
ments is a powerful tool to assess the
insulation condition of cast-resin trans
formers.
In order to conduct the measurement,
a voltage source with variable frequen:
cy is needed, Depending on the power
consumption, up to three OMICRON
CPC 100 units can be synchronized. By
doing so, the output power can be in-
creased up to 15 kVA. Depending on
the transformer design and the required
1DIAGNOSTICS
The 3CFRD method
evaluates discharge
levels obtained with
three different fre-
quency settings and
uses star diagram to
identify clusters which
separate PD and noise
sources
test voltage, power transformers up to
25 MVA can be measured using this syn-
chronization functionality. Nevertheless,
itis stlla flexible and portable solution for
‘on-site testing, asall required components
‘weigh less than 30 kg/ 66 Ibs each,
Usually, different types of noise sources
arepresent during on-site measurements
‘Thus, the digital PD instrument
offers several ways to cope with high
disturbances. One proven. tool for
filtering noise and separating different
PD sources is the so-called 3CFRD
‘method. Evaluating the discharge levels,
obtained with three different frequency
settings, the influence of noise sources
‘ean be minimized and each PD source
«can be evaluated individually.
Bibliography
1] IEC 60076-11, Power transformer
Part 11: Dry-type transformers,
national Electrotechnical Commission,
Geneva, 2004
2] IEC 60060-3, High-voltage test tech-
niques, Part 3 Definitions and require
ments for on-site testing, International
Electrotechnical Commission, Geneva.
2006
3] K.Rethmeier, A. Obralic, A. Kraetge,
M. Krdger, W. Kalkner, R. Plath,
Improved Noise Suppression by real
time pulse-waveform analysis of PD
pulses and pulse-shaped disturbances,
International symposium on high volt-
age engineering (ISI), Cape Town, 2009
iA] Cigré 676, Partial Discharges in
Transformers, Working Group D1.29,
Cigte 2017
92
C
foes cat
Eri
i
e
N step-up TR
Peis
Figure 12. PD measurement results on phase B
Authors
‘Michael Kriiger is principal engineer with OMICRON
clectronics GmbH in Klaus, Austria. He studied electrical
engineering at the Technical University of Aachen
(RWTH) and the University of Kaiserslautern (Germany)
and graduated in 1976 (Dipl.-Ing }.In 1990 he received the
Dr. (PHD) degree from the Technical University of Vienna
) | Michael Krager has more than 35 years of experience in
high voltage engineering and insulation diagnosis on GIS,
instrament transformers, cables, power transformers and rotating machines
He has published many papers about electrical measurements on different
assets and holds 15 patents. He is a member of VDE, Cigre and IEEE and
participates in several working groups for OEVE, IEC and
Christoph Engelen holds an MSc degree in electrical
engineering from the RWTH Aachen University
in Germany, After he graduated in 2013, he started
his professional career as an application engineer at
OMICRON electronics where he focused on transformer
diagnosis Since 2017 hes part of the product management
and specializes in the business development of cast-resin
transformer testing
TRANSFORMERS MAGAZINE | Volume 5, Issue 2