3g Quality Checklist

This document is a site quality checklist for a 3G telecom implementation audit. It contains over 75 items across various sections that are checked and scored on installation, documentation, cabling, commissioning and other areas. The checklist ensures sites meet specifications and identifies any issues that need rectification.

Uploaded by

wafa wafa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
67 views2 pages

3g Quality Checklist

This document is a site quality checklist for a 3G telecom implementation audit. It contains over 75 items across various sections that are checked and scored on installation, documentation, cabling, commissioning and other areas. The checklist ensures sites meet specifications and identifies any issues that need rectification.

Uploaded by

wafa wafa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Site ID: Dated:

Site Name: Auditor:


Site Quality Checklist for 3G Telecom Implementation
Subcon: PTID
Audit
Score Resp.
Result
Item Severity Rectified
Description Remarks
number Level OK / Subcon/ Date
NG NSN

5102-5103 HEALTH & SAFETY GENERAL

5013 Site clear of any hazardous substances (or under controlled storage) 2
Personal Protective Equipment "PPE" (helmet, harness, etc.) on site
5102 and used when necessary 1
5501-5602 DOCUMENTATION
5501 Site Folder on site 4
5509 Site integration checklist completed 4
5510 Commissioning tests passed according to specification 2
5513 All microwave installation data entered into the site folder 3
All microwave commissioning data and results entered into the site
5514 folder and all tests passed 3
No visible damage to implementation equipment (e.g. scratch, broken
5602 part) 3

6001-6021 INSTALLATION(CABINET)
6001 Cabinet installed according to specifications 2
6002 Cover doors and locks properly adjusted 3
6003 Cable entry kits / bridging kits and sealing installed correctly 3
6006 Plinth air guide installation done correctly 3
Internal Plug-in unit / Modules installed correctly and to Project /
6012 customer configuration 2
6018 Spare material left on site according to requirement/specification 4
6019 wrist straps used correctly 2
6021 Site clean and tidy 4

6101-6113 CABLING(INTERNALLY)

6101 Internal cables installed correctly 2


Cabinet (and all its elements) grounding done correctly (cable,
6102 position, stops washer, etc…) 2
6103 AC/DC supply power cables installed according to specification 1
6104 External alarms cabling done correctly 2
6108 Unused and used connectors are covered whit IP seals 2
6109 Cables between BTS modules are routed via correct cable entries 3
6110 Flexi WCDMA BTS modules are grounded to the plinth 2
6111 Cable ties installed properly (no sharp or jagged edges) 4
6112 Spare cable securely tied and labeled as such. 3
6113 All connector tightened according to specification 2

6503-6507 INSTALLATION (DDF/ALARM)


6503 Labeling done according to specifications 4
6504 Alarm panel installed correctly(External) 2
6505 DDF rack installed correctly 1
6506 DDF module installed correctly 1
6507 DDF is grounded to the grounding busbar 2

6551-6560 CABLING (DDF/ALARM)

6551 Cables preparations (stripping cutting ...) according to specifications 2


6552 Cables labeled correctly 3
6554 Connectors labeled correctly 3
6555 Cable installed over specified route 4
6557 Connections done correctly according to specifications 2
6559 Cabling done correctly according to specifications 2
6560 Grounding cable done correctly according to specifications 2

6615-6708 INSTALLATION(ANTENNA)
6615 OVP installed correctly 2
6701 Correct antenna types on each sector 2

6703 Tilting (mechanical &/or electrical) done according to specifications 3


6704 Antennas orientation according to specification 2
6705 Antennas properly mounted and secured 2

6708 Equipment painted according to local requirement and specifications 4

6751-6760 CABLING(ANTENNA LINE)

Page 1 of 2
6751 Jumper installed correctly 3
6752 Feeder and/or jumpers installed correctly through cable entry 3
6753 Feeder and/or jumpers labeled correctly 4
6754 Connectors installed and tightened correctly 2
6755 EMPs properly installed and grounded 2
6756 All connectors tightened to specified torque setting 2
6757 Waterproof on connectors according to specifications 3
6758 Grounding kits number and positioning according to specifications 3
6759 Grounding kits installed according to specification 2
6760 Feeder installed correctly (bending, clamps, radius, etc…) 2

6801-6802 COMMISSIONING
Measured Commissioning results & parameters are within specified
6801 range 2
6802 Measures executed with calibrated instruments 2

7001-7003 INSTALLATION(TRANSMISSION RACK)


7001 Rack(s) installed at specified position 3
7002 Rack(s) secured correctly 3
7003 Rack(s) grounded correctly 2

7201-7204 INSTALLATION INDOOR UNIT (FIU/SDH/MUX)


7201 Indoor Unit installed at specified position 3
7202 Indoor Unit grounded correctly 2
7203 Indoor Unit power connection correct 2
7204 Indoor Unit labeled correctly 4

7301-7311 INSTALLATION(ODU/MW)
Installation done like shown in the documentation (pole, direction,
7301 height,…) 3
Alignment unit and antenna are installed properly and screws are
7302 tightened 2
7303 Antenna polarization according to specifications 1
Coupler & Waveguide is properly mounted (Separate antenna or HSB
7304 configuration) 2
7305 The serial number of the antenna is recorded 3
OU is installed properly (screws are tightened, sealing is in right
7306 position, ...) 2
7307 Enough space left for removing Outdoor Unit 4
7308 OU is grounded properly 2
7309 Outdoor Unit labeled according to specifications 4
Installation according to planning data (frequency, polarization, signal,
7310 etc) 1

7311 Equipment painted according to local requirement and specifications 4

7501-7510 CABLING between ODU & IDU


7501 Cables properly installed 2
7502 All connectors tightened properly 2
7503 Q1 bus cable properly installed 3
Indoor Unit to Outdoor Unit cables grounding kits properly installed
7504 and waterproofed (including quantity & position) 2
7506 Cables entry glands sealing done properly 3
7507 Cables labeled according to specifications 4
7508 OU connector is sealed according to specifications 2
7509 External PAM cables installed correctly and tested 2
7510 External Fiber Optic cables installed correctly, cleaned and tested 2

Page 2 of 2