0% found this document useful (0 votes)
169 views1 page

Dupa - 18

This document provides a detailed unit price analysis for painting 1,237.68 square meters of masonry. It lists the labor costs for a construction foreman, 18 skilled workers, and 9 laborers over 113.92 hours. It also includes the costs for minor tools at 10% of the labor cost and calculates a total cost of 274,817.32 for the painting work.

Uploaded by

Zheby
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
169 views1 page

Dupa - 18

This document provides a detailed unit price analysis for painting 1,237.68 square meters of masonry. It lists the labor costs for a construction foreman, 18 skilled workers, and 9 laborers over 113.92 hours. It also includes the costs for minor tools at 10% of the labor cost and calculates a total cost of 274,817.32 for the painting work.

Uploaded by

Zheby
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

DETAILED UNIT PRICE ANALYSIS (DUPA)

18. PAINTING WORKS (Masonry


Item No./Description : 1032(1)a
Painting)
Unit of Measurement : sq.m. Quantity : 1,237.68
Output per hour : 18.9 Units : sq.m.

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman 1 113.92 115.25 13129.73
b. Skilled 18 113.92 83.32 170858.48
c. Laborer 9 113.92 64.22 65845.72

Sub-Total for A 249833.93

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

B. Equipment
Minor Tools (10% of Labor Cost) 24983.39

Sub-Total for B 24983.39


C. Total (A+B) 274817.32