0% found this document useful (0 votes)
60 views1 page

Dupa - 16

The document provides a detailed unit price analysis for stone cladding work including labor costs, equipment costs, and totals. Labor costs include 17.29 hours each for a construction foreman at $115.25/hr, 4 skilled workers at $83.32/hr each, and 4 laborers at $64.22/hr each. Equipment costs account for 10% of labor costs for minor tools. The total cost of stone cladding work per 28.15 sqm is $13,414.28.

Uploaded by

Zheby
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
60 views1 page

Dupa - 16

The document provides a detailed unit price analysis for stone cladding work including labor costs, equipment costs, and totals. Labor costs include 17.29 hours each for a construction foreman at $115.25/hr, 4 skilled workers at $83.32/hr each, and 4 laborers at $64.22/hr each. Equipment costs account for 10% of labor costs for minor tools. The total cost of stone cladding work per 28.15 sqm is $13,414.28.

Uploaded by

Zheby
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 16. Stone Cladding


Unit of Measurement : sq.m. Quantity : 28.15
Output per hour : 2 Units : sq.m.

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman 1 17.29 115.25 1992.39
b. Skilled 4 17.29 83.32 5761.59
c. Laborer 4 17.29 64.22 4440.82

Sub-Total for A 12194.80

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

B. Equipment
Minor Tools (10% of Labor Cost) 1219.48

Sub-Total for B 1219.48


C. Total (A+B) 13414.28