J ANITO

This document provides a list and cost breakdown for materials needed to construct a garage located in Manuel Teves, Camboilao Bais City. It includes costs for hardware and lumber, footings, columns, and electrical materials totaling P374,725. Labor is estimated at 45% of materials cost, bringing the total project cost to P576,789. Key materials include 200 pieces of 2x2x12 coco lumber, 5 sheets of 1/4" plywood, 162 sheets of corrugated roofing, and cement, rebar, and gravel for footings and columns.

Uploaded by

Molas Riema Jean
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
41 views2 pages

J ANITO

This document provides a list and cost breakdown for materials needed to construct a garage located in Manuel Teves, Camboilao Bais City. It includes costs for hardware and lumber, footings, columns, and electrical materials totaling P374,725. Labor is estimated at 45% of materials cost, bringing the total project cost to P576,789. Key materials include 200 pieces of 2x2x12 coco lumber, 5 sheets of 1/4" plywood, 162 sheets of corrugated roofing, and cement, rebar, and gravel for footings and columns.

Uploaded by

Molas Riema Jean
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

PROJECT : GARRAGE

LOCATION : MANUEL TEVES, CAMBOILAO BAIS CITY

HARDWARE & LUMBER :

200 pcs - 2x2x12 COCO LUMBER 23/balf - 18,400


5 sheets - ¼ x 4x8 marine plywood 580 580 - 2,900
6 kls - Qnn Assorted 90 kl - 540
26 pcs - ¼ x 2 Angle bar 1250 - 32,500
56 pcs - 3/16 x 2 Angle bar 895 - 50,120
57 pcs - 3/16 x1 ½ Angle bar 585 - 33,345
73 pcs - 15 mm x 2x3 C- purlins 720 - 52,560
6 gals - Epoxy primer grey 1100 - 6,600
3 gals - lacquer thinner 590 - 1,770
6 pcs - paint brush #2 (champ) 75 - 450
15 kls - welding electrode fuji 160 - 4,000
18 pcs - 3/16x 1 Angle bar 450 - 8,100
9 pcs - 3/16x 1 flat bar 410 - 3,690
162 sheets - G.I. corrugated # 0.4mmx8 - 96,390
16 pcs - 10mm round Angle bar 179 - 2,864
12 pcs - turn buckle #12 150 - 1,800
39 pcs - hardisinipa ½ x 12 x 8 471 - 18,840
450 pcs - tek screw #1 - 900
1,900 pcs - tek screw #2 ½ - 3,800
4 gals gals - flat latex (boysen) - 3,000
P 342, 569
FOOTINGS:
16 bags premium cement 215 - 3,440
1.5 m3 fine sand 950 - 1,425
2.0 m3 find gravel 1,100 - 2,200
12 pcs 16mm deform bar 465 - 5,460
2 kl tie wire #16 90 - 180
P 12, 705
COLUMN :
28 bags premium cement 215 - 6,020
3 m3 find gravel 1100 - 3,300
6 m3 sand 950 - 5,700
36 pcs 16mm deform bar sand 465 - 16,740
6 kls tie wire #16 90 - 540
P 32,300
ELECTRICAL
6 pcs ceiling socket 415 - 2,490
6 pcs lead lamp 13 watts 165 - 990
2 pcs 2 gauge switch(anam) 108 - 216
2 pcs 2 gauge outlet( anam) 108 - 216
3 pcs electrical big 30m 70 - 210
70 m T.W stranded #14 28m - 1,960
40 m T.W stranded # 12 38m - 1, 520
5 pcs junction box 50 - 250
4 pcs utility box 40 - 160
20 pcs electrical pipe # ½ 110 - 2,200
P 10,212
TOTAL MATERIAL : P 374,725.00
LABOR 45% : P 179,003.00
P 576,789.00