Procurement Risk Assessment Guide
Procurement Risk Assessment Guide
                                              NOTE
                            In this report, “$” refers to US dollars.
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make any judgments as to the legal or other status
of any territory or area.
                                                         CONTENTS
                                                                                                                                Page
I.     INTRODUCTION ............................................................................................................. 3
II.    PURPOSE ....................................................................................................................... 3
III.   COUNTRY AND SECTOR/AGENCY PROCUREMENT RISK ASSESSMENT................ 6
       A.        Phase I: Planning the Assessment ....................................................................... 6
       B.        Phase II: Conducting the Assessment................................................................ 10
IV.    PROJECT PROCUREMENT CLASSIFICATION ........................................................... 14
       A.        Procurement Environment Risk .......................................................................... 14
       B.        Project Characteristics ....................................................................................... 14
V.     PROJECT PROCUREMENT RISK ASSESSMENT....................................................... 17
       A.        Planning the Assessment................................................................................... 17
       B.        Conducting the Assessment .............................................................................. 18
       C.        Project Procurement Risk Assessment .............................................................. 18
VI.    IMPLEMENTATION SUPPORT..................................................................................... 22
VII.   CONCLUSION .............................................................................................................. 22
                                                       APPENDICES
                                                                                                                                Page
I. INTRODUCTION
     (i) identify risks that country, sector, agency or project systems and/or practices could result
           in sub-optimal use of ADB resources;
     (ii) assess the severity of the risk; and
     (iii) develop a practical risk management plan to address those risks that could adversely
           impact project implementation and/or achievement of project outcomes.
II. PURPOSE
4.     The procurement risk assessments are fiduciary in nature, intended to inform ADB’s own
operations in a given country and/or sector. They may not be sufficient for planning and/or
undertaking broad country or sector procurement reforms, where more comprehensive
diagnostic assessments is likely required.
1
     ADB. 2006. Second Governance and Anticorruption Action Plan. Manila.
2
     Sector procurement risk assessments are required for priority sectors based on ADB’s current and expected
     future operations
3
     ADB, 2013. ADB Procurement Governance Review, Manila.
4
     Midterm Review of Strategy 2020, April 2014
5
     The Procurement Reform – 10 Point Action Plan was approved by VPAC in 2014 as part of the Midterm Review
     of Strategy 2020
6
     ADB. 2011. Revised Guidelines for Implementing ADB’s Second Governance and Anticorruption Action Plan
     (GACAP II). Manila.
4
6.     The objective of the CPS is to formulate ADB’s strategic operational approach in a given
developing member country (DMC). The CPS seeks alignment between the country’s
development strategy and the corporate strategic priorities of ADB. The CSA form part of the
thematic and sector analysis undertaken to support the preparation of a new CPS. In particular,
the CSA responds to GACAP II requirements.
7.       The assessments take a two stage approach commencing with Phase I or a planning
phase which involves a literature review of existing country and ADB procurement assessments
and experience, using a tool for initial country procurement assessment and leading to
development of terms of reference (TOR) for field work and the final assessment. Phase II
involves mission and discussions with Government and other stakeholders, validation of the
initial country procurement assessment and culminating in the CSA. The CSA represents the
final assessment of country and sector/agency procurement risks in the form of a report and
informs the Procurement Risk Assessment and Management Plan (P-RAMP).
8.      The country team (which may include OSFMD staff) is responsible for the CSA. The
assessment may be conducted either by staff or a consultant(s) under the direction of the
country team with input from OSFMD. An initial desk review is required In order to plan the
assessment and determine the resources required and to assess the quality and timeliness of
existing procurement assessments as well as ADB’s procurement experience in the country and
across key sectors.
1. Literature Review
9.     The purpose of this step in the process is to identify information relating to public
procurement systems. These could include, but not be limited to:
       c.     Public Expenditure and Financial Accountability (PEFA): The PEFA Program was
              founded in 2001 as a multi-donor partnership to assess the condition of country
              public expenditure, procurement and financial accountability systems. The PEFA
              Framework assesses a country’s public financial management across 31
              indicators, one of which assesses the competition, value for money and controls
              in procurement. Publicly available PEFA assessments can be found on the PEFA
              website: www.pefa.org.
10.     In addition to the existing assessments of procurement systems, ADB’s own experience
at the country and sector/agency level should be reviewed.
       i)     Country Procurement Data Sheet: The current portfolio of active contracts in the
              country, and priority sectors, is reviewed to identify potential risks. The portfolio is
              reviewed from the perspective of total number of contracts, contract value,
              current procurement thresholds, active contracts by threshold as well as
              experience with contract variations. In addition indicators of procurement
              efficiency, competition and effectiveness are reviewed. A sample country
              procurement data sheet is provided as Appendix 1. Completed data sheets are
              available on OpsPedia.
       ii)    Existing CPS, Country Assistance Program Evaluation (CAPE) and/or CPS final
              review: The existing CPS and relevant lessons learned should be reviewed to
              better understand ADB’s operation at the country level, and sector and thematic
              priorities. For CSPs prepared after 2008, Procurement Risk Assessment and
              Management Plans (P-RAMPs) should be available for the country and a number
              of priority sectors. In particular, the quality, completeness and timeliness of the P-
              RAMPs should be assessed.
    iv)     Procurement Review for Effective Implementation (PREI) Reports: The PREI is
            an evaluation tool developed by OSFMD to assess procurement performance
            during project implementation. The objective is to identify actions that will assist
            executing and implementing agencies to more effectively manage procurement
            on time and within budget. The PREI assesses procurement plans,
            organizational effectiveness and risk management. The PREI Methodology and
            complete PREI reports are available on OpsPedia.
    v)      Country Portfolio Review Mission Report (CPRM): The purpose of the annual
            CPRM is to review the overall performance of the portfolio in terms of completing
            the projects within the approved time and budget as well as its contribution to
            sector outcomes and outputs. The CPRM (i)examines country-specific common
            project implementation problems and constraints, and work out appropriate
            remedial measures; (ii) reviews projects with EAs, and propose solutions for
            specific problems being encountered; (iii)undertakes field visits to selected
            problem projects to assess the magnitude and effects of identified problems; and
            (iv) agrees on a time-bound action plan with quantifiable and monitoring targets
            to remedy or improve the performance of the portfolio. The CRPM report and the
            Mission’s back to office report should be reviewed to identify potential
            procurement risks.
    vii)    National Competitive Bidding (NCB) Annex. The existing arrangements for NCB
            should be reviewed and an assessment should be made about whether these
            continue to be relevant, or if there is a need to supplement or amend the
            arrangements. The NCB Annex for some DMC can be found on OpsPedia.
11.   The initial country assessment identifies additional information required to complete the
CSA, determines the resources required to collect the information and the most appropriate
means by which to undertake the field work.
12.     The information gathered from literature review and ADB’s experience will be used to
answer basic questions about a country’s public procurement environment in terms of policies,
rules, regulations and institutions at the national level. The initial country assessment will result
in a preliminary score for each of the 154 indicators, an average score for each of the four pillars
and a total average score for the country. The scores will indicate the level of maturity in country
procurement systems.
13.     The country procurement assessment tool and scoring guide are provided in Appendix 2.
The tool is derived from the OECD MAPS and assesses the legislative and regulatory
framework governing public procurement, the institutional framework and management capacity,
procurement operations, market practices, the integrity and transparency of public procurement
systems. The tool also allows for an assessment of the gaps in information or where information
is dated, introduces some additional questions pertaining to e-procurement and additional
verification or updating that would be required during the CSA.
14.    Regarding e-procurement, this guide includes additional questions which should be used
where there is an e-procurement system in place. Depending on level of maturity of e-
procurement system(s) and their potential to be mainstreamed in ADB financed operations,
assessment of e-procurement system may separately be undertaken by project/country team in
accordance with PAI 3.08
15.     The final step of the planning process is to develop TOR to guide the country and
sector/agency procurement risk assessments. The TOR will guide the work of either ADB staff
or staff consultants who are engaged to support CPS preparation. At a minimum, the mission
would: (i) confirm the findings of the initial country procurement assessment updating
information gaps and narrative description of the country procurement systems where
necessary, including the use of e-GP system; (ii) assess sector procurement performance; (iii)
assess country and sector procurement risks and identify mitigating measures (i.e. prepare the
P-RAMP); (iv) propose appropriate country, and where applicable, sector procurement
thresholds; and changes, if any, required to the NCB Annex; and (v) prepare the Country and
Sector/Agency Procurement Risk Assessment Report. A sample Terms of Reference is
provided as Appendix 3.
5. Country Considerations
          (i)      For large DMCs, particularly when ADB’s program has a geographic
                   concentration or with a high degree of decentralized government services
                   (including procurement), consideration should be given to subnational
                   procurement assessments.
          (ii)     For smaller programs, with limited loan/grant financing, it may be more
                   appropriate to conduct the sector/agency procurement assessment as part of
                   project processing.
          (iii)    For larger programs, or with dominant sector agencies, the sector assessments
                   may be best conducted at the agency level, rather than aggregated at the sector
                   level.
          (iv)     If ADB loan and grant financed operations are focused on a particular subsector,
                   then it may be more appropriate to conduct the sector/agency assessment at the
                   level of that subsector.
17.    Once the planning has been completed, the Country Team should arrange for the
assessment with the concerned client Government and key sector agencies. Consideration
should also be given as to the level of involvement of Government counterparts and other
development partners. This would be particularly relevant if a joint CPS is being considered.
18.     The in-country assessment will involve discussions with all relevant stakeholders,
including the government, development partners, pertinent local industries and civil society
organizations (CSOs) that are active in ADB’s key sectors. The in-country assessment will
update and verify the information gathered during the desk review and assess sector/agency
procurement performance.
19.     The sector tool is provided as Appendix 4. The tool should be applied to each of the
sectors assessed to determine the degree of variability in procurement capacity across sectors
and as compared to the expectations embodied in the national procurement systems. The
sector includes a questionnaire that should be used when conducting interviews and a scoring
guide. The sector score should reflect the average score across agencies. The questionnaire
should be used by the assessor. It is not designed as a self-assessment tool.
7
    For further information with respect to FCAS planning considerations, refer to Working Differently in Fragile and
    Conflict-Affected Situations – A Staff Handbook, (ADB. 2012. Manila)
                                                                                                    11
20.     The results are analyzed and form the basis for completing the narrative assessment of
the country and sector/agency procurement systems. An outline for the Country and
Sector/Agency Procurement Assessment Report is provided in Box 1 below, an annotated
outline is available in Appendix 5.
        Executive Summary
        I.      Introduction
        II.     Country Procurement Assessment
                A.      Overview
                B.      Strengths
                C.      Weaknesses
                D.      Procurement Risk Assessment and Management Plan (P-RAMP)
        III.    Sector/Agencies Procurement Assessment(s)
                A.      Overview
                B.      Strengths
                C.      Weaknesses
                D.      Procurement Risk Assessment and Management Plan (P-RAMP)
        IV.     Country (and where applicable, Sector/Agency) Procurement Thresholds
        V       Conclusion
        Appendices
21.    For the country, and each priority sector assessed, the report should cover the
description of the procurement systems (at the country level) and procurement practices (at the
sector or agency level); the strengths of the procurement systems/practice (generally these
would include areas with a score of 2 or 3 on average) and any weaknesses identified
(generally these would be areas with a score of 0 or 1 on average).
22.    Risk Identification: The potential weaknesses in country procurement systems and
sector/agency procurement practices are further examined to determine the extent to which
these weaknesses pose risk to ADB loan or grant financed projects. An example of how to
convert an identified weakness into a potential risk is provided in Box 2.
Weakness: Key sector agencies use direct selection as the default procurement method
Potential Impact:      Lack of transparency, procurement delays, increased prices, reduced quality,
                       reduced life span of assets procured, reputation risk to ADB
23.     An initial long list of risk events should be prepared (a list of indicative procurement risks
at the country and sector/agency level is provided as Appendix 6). Additional information and/or
verification may be required to identify risks as a result of the diagnostic assessments. In other
words, if a weakness is identified, it may be necessary to gather additional information to
determine the root cause of the weakness and how it may result in a risk.
12
24.     Risk Assessment: Once risks have been identified, it is necessary to determine
whether or not the risk is likely to occur and if it were to occur, the likely impact it could have on
ADB financed operations. A risk would be considered “likely” if we would expect it to occur at
least once in every five procurement transactions. High impact would be if the risk could result
in larger than necessary costs, long delays and/or substandard goods and/or services procured.
The risks should be categorized as follows:
25.     Risk assessment requires knowledge not only of good procurement practices, but also of
country context and sector/agency specific conditions. The purpose of the risk assessment is to
identify situations or events and the extent to which they could hamper the effective
implementation of an ADB financed project. The categorization of risk also helps to guide the
nature and extent of mitigating measures required. An example is provided in Box 3.
26.    Risk Mitigation and Management: Risks are assessed and categorized to help focus
and prioritize remedial action. There are a variety of options for managing risks, these include:
27.    Particular attention should be accorded to mitigating high and substantial risks. The
purpose of risk mitigation is to strike a balance between the efficiency of the mitigation measure
and the cost of implementing it. In some cases, the only available mitigation measure may be
“avoidance”, for example, national procurement systems are so weak that 100% of ADB funds
                                                                                                    13
must be expended through ADB systems. Figure 3 provides a high level approach to
determining how and when to mitigate risks.
28. If an e-procurement system is used in the country (or by specific EAs), the assessment
should capture if this has helped in the management of procurement risks. The current scope
and plans to further improve the e-procurement system should be clearly mentioned. The report
should also mention risks related to use of e-procurement , if any and how they are planned to
be mitigated.
28.    Procurement Risk Assessment and Management Plan (P-RAMP): Once the risks
have been identified and categorized and mitigation measures identified, the P-RAMP is
prepared 8 . The risks should be disaggregated between the country level and the specific
sector/agency specific risk with overall risks ratings provided for both the country and individual
sectors assessed. The standard template is provided as Appendix 7.
29.     The final step of the risk assessment is to determine the overall country procurement risk,
the overall procurement risk in each of the core sectors reviewed, as well as the proposed
thresholds for the use of ICB/NCB method and for Prior Review. The overall risk should be rated
as “High”, “Substantial”, “Moderate” or “Low” and are reflected in the P-RAMP. In considering
the overall score, the assessor considers the cumulative impact of the risks identified and the
likely hood of that impact occurring. This requires professional judgment and should not simply
be a straight average of individual risk ratings. An example of how the P-RAMP should be
prepared is found in Box 4. Appendix 8 and 9 provide guide on setting thresholds for the use of
ICB/NCB method as well as thresholds for Prior Review of procurement for goods and works.
8
    The P-RAMP will be incorporated into the overall Risk Assessment and Management Plan in the Country
    Partnership Strategy itself.
14
30.    Project classification is a function of procurement environment in the country and sector
(or where applicable, agency) procurement systems and operations (as determined through the
country and sector/agency procurement risk assessments) and project specific characteristics.
31.      Projects are classified, as either “Category A” or “Category B” at concept stage to guide
project preparation and due diligence. While still at a very preliminary stage of preparation, it
should be possible to identify tentative procurement requirements at this stage, and this is taken
into account when considering project specific characteristics. OSFMD must confirm the
classification during interdepartmental circulation of the project concept paper. For Procurement
Category A projects, OSFMD’s active involvement is envisaged, throughout project preparation
and processing.
32.     The first step is to assess the procurement environment risk based on the country and
sector/agency risk assessment based on a three-point scale (Low, Medium, and High) as
indicated in Figure 4. Low risk implies that procurement procedures and practices are closely
aligned with international best practices. Medium risk implies that procurement procedures and
practices are generally aligned with international best practices. High risk implies that
procurement procedures and practices need improvements to align more closely with
international best practices. When both the country and sector risks are considered high and/or
substantial, the environment risk is considered high. Where country and sector risk combined is
high/substantial or moderate/low, the environment risk is considered medium. And when both
country and sector risk is moderate and/or low, the environment risk is considered low.
B. Project Characteristics
33.     At the concept stage, there is limited information available on specific characteristics of
project implementation. However, an initial project procurement classification is required which
is used to determine the nature and extent of project preparation and due diligence from a
procurement perspective. The following table provides some of the key procurement related
questions that can help at this stage to anticipate the procurement effort in the project:
                                                                                                15
34.     If the answer to one or more questions in Table 1 is ‘Yes’, the project officer shall make
an assessment (with comments, if necessary) and determine if additional procurement support
to the EA/IA will be required or if despite the assessment the EA/IA has adequate resources
and/or institutional capacity to address procurement issues. The project officer shall also assess
if the ADB project team includes sufficient experience/skills to deliver such support or additional
support will be required from OSFMD. If additional support is required from OSFMD
procurement specialist, the project should be recommended as Category A. If not, it should be
recommended as Category B. The level of involvement of OSFMD procurement specialist under
Category A and B projects is in Table 2 below.
C. Procurement Responsibilities
35.    For Category A projects, it would be expected that a procurement specialist is included
in the PPTA team and that the ADB’s project team includes sufficient procurement capacity.
This would typically require the active involvement of OSFMD staff to oversee the work of the
PPTA consultants and participate in project processing. However, during the PPTA following the
completion of the executing agency’s procurement capacity assessment, finalization of the
procurement plan or other procurement-related factors, the project classification could be
reconsidered. Table 2 provides an indicative level of procurement specialist involvement
through project preparation and due diligence; Table 3 provides an indicative level of
procurement specialist involvement through project implementation.
16
36.     ADB’s Project Administration Instructions require that project teams assess the capacity
of the executing agency (EA) and the implementing agency (IA), if any, to procure the goods,
works and consulting services as part of the project preparation process. The purpose of the
project procurement risk assessment (PRA) is to determine the overall procurement risk, and
establish appropriate review and supervision processes (including thresholds) and other
measures to mitigate these risks.
37.     The project procurement risk should be informed not only by the country and
sector/agency procurement risks, but also by the characteristics of the proposed project. For
example, although large, a project with a single contract may have less risk than a smaller
project, with multiple implementing agencies, multiple geographic locations and a large number
of low value contracting packages. The framework guiding procurement risk assessment at the
country, sector and project level is based on the cascading approach adopted under ADB’s
Governance framework and indicated in Figure 1.
38.     Risk assessment requires knowledge not only of good procurement practices but also of
country context and sector specific conditions. The purpose of the risk assessment is to identify
situations or events which could hamper the effective implementation of the ADB financed
project.
39.     The Project Team is responsible for the project procurement risk assessment. The
assessment may be conducted by staff9, the PPTA consulting team or a staff consultant under
the direction of the Project Team. In planning the assessment, consideration should be given to
the country and sector procurement risk assessments and whether the project has been
classified “complex” or “standard”.
40.     The first consideration should be to assess the quality, timing and continuing relevance
of the country and sector/agency procurement risk assessments if these were prepared during
the CPS. If the assessments are not available, or are outdated, it may be necessary to complete
at a minimum, the country procurement risk assessment to better understand the systemic
issues that could impact project performance.
41.      The project procurement risk assessment will usually involve, but not be limited to (i) the
review and, if necessary, update of country and sector/agency procurement risk assessments;
(ii) an assessment of project procurement arrangements and EA capacity; (iii) a narrative
assessment of procurement systems and capacity of EA including strengths and potential
weaknesses; (iv) risk assessment and preparation of a risk management plan; and (iv) initial
draft of the project’s procurement plans. An indicative TOR is provided in Appendix10.
42.    It is essential that the project procurement risk assessment is realistic because this is the
only way for appropriate risk mitigations to be identified and built into the project design. If the
EA’s capacity is overstated, the absence of appropriate risk mitigations will inevitably result in
9
     It is envisaged that staff from a regional department, resident mission or OSFMD, with procurement expertise,
     could conduct the review. For projects with a “complex” classification, it is expected that OSFMD will, at a
     minimum, oversee the conduct of the assessment and preparation of the project’s procurement plan.
18
implementation delays. It is also important that the assessment is conducted only on those units,
facilities and staff within the EA that will directly contribute to procurement activities under the
project (e.g. those within the Project Management Unit or separate Procurement Unit within the
EA). Assessing irrelevant entities will similarly distort the assessment resulting in inadequate
risk mitigation measures.
43.     The primary source of information will be interviews conducted with counterpart staff,
development partners and other stakeholders using the Procurement Risk Assessment
Questionnaire (Appendix 11). The assessor may also conduct a workshop for contractors from
the area in which the project will be implemented to give them advance notice of the project and
procurement requirements, and to confidentially seek information as to their experience and
qualifications. This information may contribute to the final bid packaging and verification that the
country ICB threshold is appropriate.
44.     The results are analyzed and form the basis for completing the narrative assessment of
the project procurement arrangements. An outline for the Project Procurement Risk Assessment
Report is provided in Box 1 below, an annotated outline is available in Appendix 10. The
methodology below describes how fiduciary risks should be incorporated into the Procurement
Risk Assessment and Management Plan (P-RAMP), which forms part of the Project
Procurement Risk Report.
       Executive Summary
       I.     Introduction
       II.    Project Procurement Risk Assessment
              A.      Overview
              B.      Strengths
              C.      Weaknesses
              D.      Procurement Risk Assessment and Management Plan (P-RAMP)
       III.   Project Specific Procurement Thresholds (if applicable)
       IV.    Procurement Plan
       V      Conclusion
       Appendices
45.      Risk Identification: The potential weaknesses in agency procurement capacity are
identified in the Procurement Risk Assessment Questionnaire. Additional information and/or
verification may be required to identify risks as a result of the diagnostic assessments. In other
words, if a weakness is identified, it may be necessary to gather additional information to
determine the root cause of the weakness and how it may result in a risk. See Box 2 for an
example.
                                                                                                          19
46.     Risk Assessment: Once risks have been identified, it is necessary to determine
whether or not the risk is likely to occur and, if it were to occur, the impact it could have on the
project. Guidance on how to assess the likelihood of a risk occurring is included in the Project
Procurement Risk Analysis (Appendix 11). The risks should be categorized as follows:
47.     Risk assessment requires knowledge not only of good procurement practices, but also of
country context and sector specific conditions. The purpose of the risk assessment is to identify
situations or events and the extent to which they could hamper the effective implementation of
the project. The categorization of risk also helps to guide the nature and extent of mitigating
measures required. An example is provided in Box 3.
48.    Risk Mitigation and Management: Through the Project Procurement Risk Analysis,
risks are assessed and categorized based on the responses in the Procurement Risk
10
  Any risk that may result in actions that are inconsistent with the ADB Procurement Guidelines or
Guidelines on the Use of Consultants should be assessed as having ‘high impact’.
20
Assessment Questionnaire to help focus and prioritize remedial action. A variety of options exist
for managing risks, these include:
49.    Particular attention should be accorded to mitigating high and substantial risks. The
purpose of risk mitigation is to strike a balance between the efficiency of the mitigation measure
and the cost of implementing it. In some cases, the only available mitigation measure may be
“avoidance”, for example, national procurement systems are so weak that 100% of ADB funds
must be expended through ADB systems.
If an e-procurement system is being used in the country (or by specific EAs), the assessment
should suggest areas (if any) where ADB financed transactions can benefit from its use. If the
use of e-procurement introduces additional risks, these should be candidly mentioned.
Figure 5 provides a high level approach to determining how and when to mitigate risks.
50.    Procurement Risk Assessment and Management Plan (P-RAMP): Once the risks
have been identified and categorized and mitigation measures identified, the P-RAMP is
prepared. The standard template is provided as Appendix 7.
51.     The final step of the risk assessment is to determine the overall project procurement risk
as well as the proposed project procurement thresholds for the use of ICB/NCB method and for
Prior Review. The overall risk should be rated as “High”, ”Substantial”, ”Moderate” or ”Low” and
are reflected in the P-RAMP. In considering the overall score, the assessor considers the
cumulative impact of the risks identified and the likely hood of that impact occurring. This
requires professional judgment and should not simply be a straight average of individual risk
ratings. An example of how the P-RAMP should be prepared is found in Box 4. Appendix 8 and
9 provide guide for setting project procurement thresholds for the use of ICB/NCB method as
well as thresholds for Prior Review of procurement of goods and works.
   Risk                   Risk
   Description         Assessment         Mitigation Measures or Risk Management Plan
52.     This guide, and associated tools, templates and terms of reference will be made
available on OpsPedia and will be updated as required. In addition, the Country Procurement
Data Sheet and other procurement related information will be updated regularly and also be
posted on OpsPedia. Training materials will be developed and training programs introduced for
OSFMD and RD staff.
VII. CONCLUSION
53.     This guide and associated tools are provided to assist country teams to better assess
procurement risk, to ensure that this is effectively mitigated or managed through project
procurement arrangements. However, guidelines cannot substitute for professional judgment. It
is up to the ADB country team to determine how best to obtain sufficient comfort that ADB funds
will be used for intended purpose, with due regards to efficiency and effectiveness.
                                                                                                  23
Appendix 1
  Note: (i) Contract information should be taken from last 2 to 3 years as described in paragraph
  10(i); (ii) Source of data may be expanded to include contracts financed by the government or
  from other sources; (iii) Information in these tables will be extensively used in this assessment,
  particularly for setting ICB, NCB and prior review thresholds as described in Appendix 8 and 9.
COUNTRY NAME:
DATA AS:
                                          Value
Description           Number            (Eqv. USD)
Total Country
By Sector:
 Transport
 Energy
 Education
 Water/Urban
 Other
*Based on consolidation of Table 1.3 through Table 1.5
  24
                                                                                                    Appendix 2
                          COUNTRY PROCUREMENT ASSESSMENT TOOL
                                                                               Narrative / Verification or
                      Indicators                             Score
                                                                                Clarification Required
1. Legislative and Regulatory Framework                     Average of
    {MAPS Indicators 1 and 2}                                1.1 – 1.5
1.1 Is there a comprehensive public procurement                          The Mission should provide a narrative
    law, with supporting regulations, standard bidding                   response and determine whether or not
    documents and operational manuals/guides?                            additional information or verification is
                                                                         required.
1.2 Does the legal framework make open competitive
    tendering the default method of procurement with
    clarity as to when other less competitive methods
    can be used?
1.3 Does the legal framework support non-
    discriminatory participation (i.e. all eligible
    bidders are allowed to participate, and it ensures
    that registration, if required, does not constitute a
    barrier to participation in tenders), and
    transparent tender processes (including
    advertisement, tender documentation, tender
    evaluation, complaints mechanism)?
1.4 Are there restrictions or preferences based on
    the nationality of bidders, consulting firms and/or
    origin of goods, works and services?
1.5 Does the legal and regulatory framework enable
    the use of an e-procurement system
2. Institutional Framework and Management                   Average of
    Capacity                                                 2.1 – 2.6
    { MAPS Indicators 3, 4, 5}
2.1 Is the procurement cycle required to be tied to an
    annual budgeting cycle (i.e. can a procurement
    activity commence only when budget has been
    duly appropriated for it?)
2.2 Does the system foster efficiency through the use
    of adequate planning?
2.3 Does the procurement system feature an
    oversight/regulatory body?
2.4 Is there a nationwide public procurement capacity
    development or professionalization program?
2.5 Is there a dedicated group institutionalized
    for e-procurement in the public procurement
    department?
                                          2 – The legal framework meets the conditions (a) and (b) and one of the
                                          remaining conditions.
                                          0 - The legal framework fails to substantially comply with any three of the
                                                                                                               29
1.5 Does the legal and regulatory      3 – National public procurement law requires the use of e-procurement by
    framework enable the use of        all of government, rules for e-procurement implementation included in the
    an e-procurement system            law and electronic and paper bid documents are considered equally valid.
                                    1 – Annual procurement plans are required, but the law does not provide
                                    for the preparation of multiyear or annual operating plans.
                                     0 – The private sector is not well organized and lacks capacity and
                                     access to information for participation in the public procurement market.
3.2 Do measures exist to ensure      3 – Detailed measures exist along with clear guidelines to check the
    the adequacy and accuracy of     adequacy and accuracy of cost estimates and proposed variations.
    cost estimates before bidding,
    and to manage contract price     2 – Some measures exist, but these do not provide sufficient guidance.
    variations?
                                     1 – There is a requirement to check the adequacy and accuracy of cost
                                     estimates and proposed variations, but no measure (indicator) or
                                     guidance provided.
32
3.4 Is there a mechanism to         3 – There is an independent review body that has clear authority and is
    receive and handle              bound by reasonable procedures and timelines.
    observations, complaints and
    protests?                       2 – There is an independent review body, but the mechanisms for
                                    decision-making and enforcement are unclear or cumbersome.
                                    0 – No
4.   Integrity and Transparency of the Public Procurement System
4.1 Is there a formal internal      3 – This is provided by law, and there are adequate internal control and
    control and audit framework?    audit mechanisms and institutions to oversee the procurement function.
                                    2 – This provided by law, and there are implementing guidelines, but the
                                    mechanisms and institutions are not adequately established.
                                   0 – The law does not provide for a formal internal audit and control
                                   system.
4.2 Is information pertaining to   3 – Information on procurement is easily assessable in media of wide
    public procurement easy to     circulation and availability. The information provided is centralized in a
    find, comprehensive and        common place, is relevant and complete.
    relevant?
                                   2 – Information is posted in media not readily and widely accessible or
                                   not user-friendly for the public at large OR is difficult to understand to the
                                   average user OR essential information is lacking.
                                   1 - The private sector and civil society are able to access a limited
                                   amount of national procurement information through the system
                                   0 - The private sector and civil society are not able to access national
                                   procurement information through the system
4.4 Does the country have ethics   3 – Tender documents including adequate provision on fraud and
    and anticorruption measures    corruption; fraud and corruption in procurement is defined; specific
    in place?                      measures are in place and implemented related to conflict of interest;
                                   responsibilities and consequences for those found guilty of fraud or
                                   corruption is clearly described; ample evidence of enforcement; special
                                   measures are in place for detection and prevention of corruption
                                   associated with procurement.
Appendix 3
A. Background
This section should include the background to the CSA, either to support a new CSP, to support
the preparation of an RBL, to support an update of the CSP etc. In addition, the results of the
initial country assessment should be included.
Purpose: The country and sector/agency procurement risk assessment is intended to (i) identify
risks that national or sector systems and/or practices could result in sub-optimal use of national
and/or ADB resources, either through leakage or inefficiency; and (ii) assess the severity of the
risk; and (iii) develop a practical risk management plan to address at a minimum high or
significant procurement risks at the country and sector level.
iii) Identify and evaluate procurement risks at the country and sector/agency level.
       iv)     Identify and assess procurement risks, on the basis of degree of impact and
               likelihood of occurrence using the following scale:
                       High:                 likely to occur, high impact if occurs
                       Substantial:          unlikely to occur, high impact if occurs
                       Moderate:             likely to occur, low impact if occurs
                       Low:                  unlikely to occur, low impact if occurs
       vi)     Determine overall country, and where applicable, sector/agency procurement risk
               rating.
D. Key Deliverables
Appendix 4
                                                  Summary Sheet
                                                            Initial    Verified      Sector/
                                                           Country     Country      Agency
                                                                                           11
                 Indicators/Questions                       Score       Score       Scores            Comments
1. Legislative and Regulatory Framework                    Average     Average      Average
1.1 Does the national public procurement law                                        Scores       Key features,
    (including supporting regulations, standard                                     should be    strengths and
    bidding documents and operational                                               provided     weaknesses that
    manuals/guides) apply to the sector?                                            for each     distinguish the sector
                                                                                    sector       from the country
                                                                                    assessed     assessment should
                                                                                                 be identified
11
     If the sector is fully consistent with the country procurement system on an issue, apply the score allocated to the
     corresponding question in the country assessment.
38
                                Have government-issued
                                documents been tailored to
                                meet sector requirements?
                                In absence of government-
                                issued documents, does the
                                sector have its own standard
                                bidding documents/
                                guidelines?
1.2 Is the supply               Is competitive bidding a
    market for the              common feature under the
    sector sufficiently         sector?
    competitive to give
    full effect to the          Is there a core of suppliers in
    national                    the sector who regularly
    procurement law             submit responsive bids?
    and/or open
    competitive                 What proportion, by %, of the
    tendering?                  sector’s procurement is
                                undertaken through open
                                competitive bidding?
12
     Describe how the sector meets the guidance applicable to the score allocated, or other justification for the score.
40
                                                                                  12
Indicators/Questions        Sector/Agency Questions           Score   Narrative
1.3 If there is a sector   Has the sector adopted non-
    specific legal         discriminator, transparent
    framework, does it     tender processes?
    support non-
    discriminatory         What is the average number
    participation,         of bidders for publicly bid
    transparent tender     contracts?
    processes
    (including
    advertisement,
    tender
    documentation,
    tender evaluation,
    complaints
    mechanism)?
1.4 Is the sector          Does the sector apply a
    subjected to           domestic preference scheme?
    excessive
    regulation or          Does the sector require pre-
    government control     registration of bidders?
    such that
    competition is         Are there acceptable
    limited or non-        provisions in the sector for the
    existent?              participation of State Owned
                           Enterprises?
1.5 Does the legal and     Does the sector/agency abide
    regulatory             by the rules, regulations and
    framework enable       guidelines for the use of e-
    the sector/agency      procurement incorporated in
    to use an e-           the national procurement
    procurement            laws?
    system
                           Are electronic and paper
                           documents considered as
                           equally valid by the
                           sector/agency?
                           How is e-procurement
                           positioned within the overall
                           sector/agency structure?
                            What percentage of
                            sector/agency’s total bids are
                            transacted through the e-
                            procurement system?
13
     This guide does not replace professional judgment about the capacity of the sector relative to that of the country
     procurement system. If considerations other than this guide are used, mention them in the ‘Narrative’ column of the
     questionnaire.
46
                                                                                              13
Indicators/Questions         Sector/Agency Questions                          Scoring Guide
                           related goods and services in
                           the domestic market?               0 – Competitive bidding in the sector is much
                                                              weaker than that generally seen in the country.
                                                              Suppliers tend to submit one-off,
                                                              nonresponsive bids. Less than 2 bidders on
                                                              average per contract. EAs rarely do not make
                                                              sufficient efforts to attract bids.
1.3 If there is a sector   Has the sector adopted non-        3 – At least 5 bidders on average per contract
    specific legal         discriminator, transparent
    framework, does it     tender processes?                  2 – At least 3 bidders on average per contract
    support non-
    discriminatory         What is the average number of      1 – At least 2 bidders on average per contract
    participation,         bidders for publicly bid
    transparent tender     contracts?                         0 – Less than 2 bidders on average per
    processes                                                 contract
    (including
    advertisement,
    tender
    documentation,
    tender evaluation,
    complaints
    mechanism)?
1.4 Is the sector          Does the sector apply a            3 – There are no restrictions on nationality of
    subjected to           domestic preference scheme?        bidders or origins of goods, there is no
    excessive                                                 domestic preference scheme, effective pre-
    regulation or          Does the sector require pre-       registration processes rigorously followed,
    government control     registration of bidders?           acceptable provisions govern participation of
    such that                                                 state owned enterprises.
    competition is         Are there acceptable
    limited or non-        provisions in the sector for the   2 – No restrictions on nationality of bidders or
    existent?              participation of State Owned       origin of goods, or pre-registration process
                           Enterprises?                       exists but not rigorously followed, or weak or
                                                              unclear provisions governing participation of
                                                              state owned enterprises.
2.6 If an e-procurement      What is the sector/agency’s e-   3 – At least 75% of e-procurement staff have
     system is used in       procurement capacity to          completed up to 3 weeks of national e-
     the sector/agency,      implement system?                procurement training
     is there a structured
     approach to
                             Does the agency/e-               2 – At least 55% of e-procurement staff have
     capacity building
                             procurement unit recognize       completed a one week e-procurement training
     and analyzing its
                             the need for knowledge and       program
     effective use?
                             skill building for the new way
                             of working under e-
                                                              1 - At least 25% of e-procurement staff have
                             procurement
                                                              completed a one day e-procurement training
                                                              program
3.2 Do measures exist       What percentage of contracts      3 – More than 75% of the contract awards
    in the sector to        is awarded for values less than   sampled
    ensure the              the original cost estimates?
    adequacy and                                              2 – 50 – 75% of contracts awards sampled
    accuracy of cost
    estimates before                                          1 – 20 - 50% of contracts awards sampled
    bidding, and to
    manage contract                                           0 – Less than 20% of contract awards sampled
    price variations?
3.3 Is the private sector   What functions exist and are      3 – Private sector is generally able to access
     able to access and     being used in the                 and participate competitively through e-
     fully participate in   sector/agency e-procurement       procurement; e-procurement system is an end-
     the sector/agency      system?                           to-end solution; there are no constraints
     e-procurement                                            prohibiting any firm to access or use
     activities                                               sector/agency e-procurement system
                            Are all forms
                            available/accessible online?
                                                              2 – e-procurement system is accessible to
                                                              private sector but there are only a concentrated
                            Do bidders pay any fees for
                                                              number of firms in the sector that are
                            the use of the system?
                                                              accessing and participating in bidding; use of
                                                              the system is limited to MDB funded projects
                            What other government IT
                            systems does the e-
                                                              1 – The use of e-procurement system in the
                            procurement system link to?
                                                              sector/agency is limited due to non-competitive
                                                              factors
50
                                                                                           13
Indicators/Questions        Sector/Agency Questions                        Scoring Guide
                           Are foreign bidders able to
                           participate in the               0 – The private sector does not have the
                           sector/agency e-procurement?     capacity to access e-procurement system;
                                                            there are major system constraints and
                           What percentage of               weaknesses that hinder the active participation
                           sector/agency’s total bids are   in e-procurement
                           transacted through the e-
                           procurement system?
3.4 Is there a             Are there sector-specific        3 – The complaint review system has precise
    mechanism in the       procedures to receive and        and reasonable conditions and timeframes for
    sector to receive      handle observations,             decision with clear enforcement authority and
    and handle             complaints and protests?         mechanisms; more than 90% of complaints are
    observations,                                           processed with stipulated timeframes;
    complaints and         Are complaints and protests in
    protests?              the sector processed within      2 – There are terms and timeframes for
                           the maximum time limit           resolution of complaints but authority for
                           provided for in the law?         enforcement is unclear; more than 75% of
                                                            complaints are processed within stipulated
                           Have bidders used the            timeframes;
                           complaint and protests
                           mechanisms?                      1 – Terms and timeframes for resolution of
                                                            complaints are vague; the time to resolve
                                                            complaints is tracked by the agency.
4.3 Can bidders and        What is civil society’s          3 – At least 80% of bids and awards
    other stakeholders     involvement in the               information are published and is readily
    easily access          ector/agency’s e-procurement     accessible at all times in e-procurement site;
    sector/agency’s        system?                          third party observers from CSOs and other
    procurement                                             partner groups are able to access and
    information through                                     download e-procurement information.
                           What kind of dynamics exist
    the e-procurement                                       Generally very cooperative relationship from all
                           between/among private sector
    system?                                                 stakeholder groups; CSOs and other partner
                           and other stakeholder groups
                                                            groups able use e-procurement system for
                                                            monitoring
                           Are bidders and other
                           stakeholders able to monitor
                                                            2 – At least 55% of bids and awards
                           all the agency’s e-procurement
                                                            information are published and readily
                           transactions?
                                                            accessible at all times in e-procurement site;
                                                            some third party observers from CSOs and
                                                            other partner groups are able to access and
                                                            download e-procurement information. Some
                                                            stakeholder groups are not supportive of e-
                                                            procurement; Some stakeholders use e-
                                                            procurement system to monitor process and
                                                            results
Appendix 5
EXECUTIVE SUMMARY
     Overall Assessment of country and sector procurement risk (High, Substantial, Moderate or Low)
     Summary of weaknesses and risks identified
     Summary of mitigation/management measures to be adopted
I.       INTRODUCTION
               The introduction should indicate that the assessment was prepared in accordance with
               the Approach to Assessing Country and Sector/Agency Procurement Risks and whether
               or not the CSA is being prepare to support the CPS. In addition, the assessment should
               indicate when and how the assessment was undertaken “The CSA was undertaken from
               <<< to <<<. Preparation activities included reviewing documents, ADB’s ongoing
               procurement experience, interviews with counterpart and discussions with stakeholders.”
         A.     Overview
                This section should provide a narrative description of the country procurement systems
                covering:
         B.     Strengths
                This section should identify strengths of the country procurement system, including those
                elements such as e-procurement where ADB may wish to rely upon. This should be
                based on the results of the Country and Sector Procurement Assessment tool, identifying
                those areas with scores of 2 or 3.
         C.     Weaknesses
                This section should identify weaknesses of the country procurement system. This should
                be based on the results of the Country and Sector Procurement Assessment tool,
                identifying those areas with scores of 0 or 1.
         A.     Overview
                This section should provide a narrative description of the sector/agency procurement
                systems covering:
54
               i.         Legislative and Regulatory Framework (from the sector perspective, this
                          should reflect the compliance/implementation of sector agencies with
                          national/country systems and frameworks)
               ii.        Institutional Framework and Management Capacity
               iii.       Procurement Operations and Market Practices (from the sector perspective,
                          the review of the market is particularly important. The assessment should
                          consider whether or not domestic systems support international competitive
                          bidding, the number of foreign bidders in domestic procurement, the percentage
                          of internationally bid procurements won by local bidders etc.)
               iv         Performance of e-procurement system (or plans to introduce one)
               v.         Integrity and Transparency of the Public Procurement System
       B.      Strengths
               This section should identify strengths of the sector agencies procurement practices,
               including those elements such as e-procurement where ADB may wish to rely upon. This
               should be based on the results of the Country and Sector Procurement Assessment tool,
               identifying those areas with scores of 2 or 3.
       C.      Weaknesses
               This section should identify weaknesses of the country procurement system. This should
               be based on the results of the Country and Sector Procurement Assessment tool,
               identifying those areas with scores of 0 or 1.
       The review should recommend the followings with links and justifications based on the
       assessments:
 Overall procurement risk rating at the country, and where applicable, sector level.
V. CONCLUSION
       The overall conclusion including an opinion as to whether or not country procurement legal,
       regulatory and institutional frameworks may be used for ADB financed projects, overall
       assessment of country procurement risk and procurement risk in priority sectors/agencies and the
       nature of risk mitigation/management measures required to address these risks in ADB’s
       operations.
Appendices:
      Completed Country Procurement Data Sheet, questionnaires, scoring tools, updated NCB Annex.
55
56
                                                                                                   Appendix 6
Appendix 8
A. Objective:
1.     The objective of this guide is to set monetary thresholds for procurement of goods and
works through International Competitive Bidding (ICB) and National Competitive Bidding (NCB)
methods in the country in view of five basic procurement principles mentioned in ADB’s
Procurement Guidelines, i.e. member country eligibility requirements, economy-efficiency, equal
opportunity, ADB’s interest in encouraging the development of domestic contracting and
manufacturing industries in the country of the borrower, and transparency in the procurement
process.
B. References:
2.     ADB Procurement Guidelines includes in paragraph 3.3 a provision which states that
NCB procedures may be the most appropriate way of procuring goods or works which, by their
nature or scope, are unlikely to attract foreign competition due to the facts that:
       a)   the contract values are small, or
       b)   works are scattered geographically or spread over time, or
       c)   works are labor intensive, or
       d)   the goods or works are available locally at prices below the international market
3.     ADB Project Administration Instructions (PAI) 3.05 further clarifies in paragraph 3 that
NCB may be appropriate if there are enough domestic producers or contractors who are
capable of providing the required quantity and quality of goods and related services or works at
reasonable costs and within the required time frame.
C. Prerequisite:
4.     The use of NCB and setting ICB and NCB threshold can be considered if country
procurement procedure is acceptable- or has been made acceptable to ADB (for example
through application of NCB Annex) to assure economy, efficiency, transparency, and broad
consistency with the provisions included in Section I of the ADB Procurement Guidelines.
D. Methodology:
 Example:
 Baseline Thresholds for the country are USD 25 million for Works and USD 2 to 5 million for Goods.
60
7.      Step 2 – Getting or Updating Country Procurement Information: Check for and assess
any revision and update to the country procurement procedures and map their acceptability as
per guidance and check list specified in ADB PAI 3.05 and PAI 3.08, Appendix 2 as well as the
existing country NCB Annex or other equivalent instruments.
8.      Step 3 – Capturing Country Procurement Profile: Capture country past procurement data
using Table 1.2 through 1.4 of Appendix 1. The Tables could provide general information on the
highest contract value profile for each procurement category. Particular attentions should be
given to the population profile of each range of contract values.
 Examples:
 Table 1.2 Total Contracts
                                                              Total Contracts
                                                                  Value                Average Contract Value
  Active Contracts                   Number                   (Eqv. 000 USD)                (Eqv. USD)
  Total Country                        10,530                       4,135,852                    392,768
  By Sector:
   Transport                            2,855                         2,220,078                     607,121
   Energy                                   9                           103,633                  11,514,804
   Education                              N/A                               N/A                         N/A
   Water/Urban                          7,666                         1,812,141                     200,240
   Other                                  N/A                               N/A                         N/A
 Table 1.3 Goods Contracts
                                                                       Number of contracts whose value is
                              Total Goods Contracts                                (Eqv. USD)
                                                                                      from
                                                                                        2       from
                                                 Average                   from      million  5 million   more
                                                 Contract      less      1 million    up to     up to      than
                                   Value           Value       than        up to        5         10        10
  Active Contracts   Number      (Eqv. USD)     (Eqv. USD)   1 million   2 million   million   million    million
  Total Country        155       27,842,940       179,632       153          1          1          0         0
  By Sector:
    Transport           37        11,125,227     300,682       36           0          1          0           0
    Energy             N/A            N/A          N/A         N/A         N/A        N/A        N/A         N/A
    Education          N/A            N/A          N/A         N/A         N/A        N/A        N/A         N/A
    Water/Urban        118        16,717,713     141,676       117          1          0          0           0
    Other              N/A            N/A          N/A         N/A         N/A        N/A        N/A         N/A
9.       Step 4 – Setting Candidate ICB Thresholds: This approach utilizes information in Table
1.8 of Appendix 1, which could be a good indication of the competition level in the country. In
this case the average of 3 largest ICB contracts awarded to local firms and the average of 3
smallest ICB contracts in which foreign firms participated for each procurement category are
compared with the highest contract value identified in Step 3. The lowest among these values
could be assigned as candidate for ICB thresholds if it is higher than the baseline ICB threshold
identified in Step 1. Otherwise, there may be strong justification to use the baseline ICB
threshold as the candidate ICB threshold for this assessment.
Examples:
Table 1.8 (all values in USD million)
                                        GOODS                                    WORKS
                           Average of 3        Average of 3         Average of 3       Average of 3
                            largest ICB        smallest ICB          largest ICB       smallest ICB
                        contracts awarded        contracts       contracts awarded       contracts
                          to Local Firms     in which Foreign      to Local Firms    in which Foreign
                                            Firms participated                      Firms participated
 Total Country                  4.31                 -                  25.23              25.62
 By Sector
 Transport                      1.98                 -                 23.42               31.13
 Energy                         5.30                 -                 15.76               20.10
 Agriculture                    1.21                 -                 22.34                 -
 Urban                          1.19                 -                 29.93                 -
 Based on the example, a value of USD 5 million (for goods) and USD 25 million (for works, which is
 an average of USD 29.93 million and USD 20.10 million) could be assigned as candidates for
 thresholds. However, based on the information obtained in Step 3, there is no contract for goods above
 USD 5 million, and the effective threshold should be between USD 1-2 million. Since Step 1 states that
 the minimum current threshold for goods is USD 2 million, therefore, the candidate thresholds for
 goods should now be set at USD 2 million.
international market, perform a general assessment of availability of these local firms to provide
the services in consultation with OSFMD.
 In the example, the country database information advises that there are quite a large number of local
 contractors which have experiences in performing contracts up to USD 25 million, and there are also
 quite large pools of local suppliers which have experiences in performing contracts up to USD 2 million.
12.    Step 7 – Threshold Comparison: Compare the candidate ICB thresholds with those of
other major donors’ in the country. If there are significant differences, then through consultation
with OSFMD further review of the thresholds must be conducted to decide whether the
candidate threshold should be retained or revised.
 In the example, the World Bank has the following thresholds for the country: USD 2 million for
 Procurement of Goods, and USD 25 million for Procurement of Works.
13.    Step 8 – Setting the Recommended ICB Thresholds: Setting the updated ICB thresholds
for ADB financed contracts in the country.
Appendix 9
Guide on Setting Prior Review Thresholds for Procurement of Goods and Works
A. Objective:
1.     The objectives of this guide are to identify the monetary prior review thresholds in the
country, and to mitigate procurement risks in ADB financed contracts.
B. Primary References:
2.      ADB Procurement Guidelines paragraph 1.2 states that, while the responsibility for the
implementation of the project, and therefore for the award and administration of contracts under
the project, rests with the borrower, ADB, for its part, has the obligation to ensure that the
proceeds of its financing are used with due attention to considerations of economy and
efficiency.
3.      ADB Procurement Guidelines paragraph 1.12 states that ADB supervision right includes
declaring misprocurement for expenditures for goods and works that are not procured in
accordance with the provisions of the financing agreement and the applicable ADB Procurement
Guidelines.
4.     ADB Project Administration Instructions (PAI) 3.02 paragraphs 3 and 5-9 state that the
country and sector/agency assessments are key to establishing appropriate country, and
where applicable, sector/agency procurement supervision thresholds.
C. Prerequisite:
5.     The ICB thresholds for country & sector/agency must already be determined or at least
they are being determined in parallel with these prior review thresholds.
D. Methodology:
6.     Step 1 – Getting the Baseline Information: If available, use the existing country and
sector/agency prior review thresholds as baseline information.
7.      Step 2 – Setting Candidate Prior Review Thresholds: Based on the country &
sector/agency procurement assessments, set the candidate for prior review thresholds. Use the
following guidance in PAI 3.02 paragraph 6 and set a threshold which does not exceed the ICB
thresholds:
 Following the example in Appendix 8, the following prior review thresholds are identified from Table
 13.1: Prior Review Thresholds (PAI 3.02 paragraph 6)
          Contract Type               Low Risk              Medium Risk                High Risk
       Works/Plant/Goods            Up to USD 20            Up to USD 10          Up to USD 5 million
                                       million                 million
       Direct Contract                   All                      All                     All
units in the particular agency or sector and determine the level of procurement that these
procuring units have to procure independently without a close supervision. In the absence of
any of these tables, in consultation with OSFMD, other qualitative practical assessment must be
conducted to measure the procurement performance and competence of the procuring units in
an agency or sector.
10.    Step 5 – Setting Recommended Prior Review Thresholds: The candidate prior review
thresholds (step 2) are qualitatively analyzed and superimposed against information in step 3
and step 4 to find out if the procuring units may be able to, respectively, work independently
and/or efficiently without close supervision. It should be noted, however, that these candidate
thresholds must not exceed the ICB thresholds.
In the example, based on step 2 above, a medium country procurement risk could have a maximum
threshold of USD 10 million. Furthermore, based on step 3 and 4, it is identified that the country’s
performance seems adequate. Therefore, a USD 10 million threshold could be a strong candidate for
country’s prior review threshold for both goods and works. However, since the recommended ICB
threshold for goods and works are USD 2 million and USD 25 million respectively (based on example in
Appendix 8), the candidate thresholds are set to USD 2 million (for goods) and USD 10 million (for works).
11.     Step 6 – Thresholds Comparison: Identification of the prior review thresholds of other
major donor(s) in the country as a comparison. If there are significant differences, in
consultation with OSFMD, a further review of the thresholds must be conducted to analyze the
situation or provide the justifications to retain the candidate thresholds.
In the example, the World Bank has the same prior review thresholds for the country, i.e. USD 2 million
(goods) and USD 10 million (works).
12.    Step 7 – Setting the Recommended Prior Review Thresholds: Setting the updated prior
review thresholds for ADB financed contracts in the country.
In the above example, under the medium risk, the following prior review thresholds are recommended to be set:
 USD 2 million (for goods), and USD 10 million (for works).
                                                                                              65
Appendix 10
A. Background
This section should include details pertaining to the project, as well as a description of the
country and sector procurement environment that could impact the country.
The purpose of the assessment is to (i) identify the capacity, procedural and organizational
constraints that could hinder effective Project implementation and agree on an action plan with
the EA/IA and the developing member country (DMC) concerned, to address these constraints;
and (ii) determine the overall procurement risk, and establish appropriate review and
supervision processes, including thresholds, to mitigate these risks.
       ii)     Assess strength and weaknesses in project procurement practices and capacity
               from the perspective of (a) organizational and staff capacity; (b) information
               management; (c) procurement practices (goods and works, consulting services
               and payment practices); (d) performance of e-procurement system or (plans to
               introduce one) (e) effectiveness; and (e) accountability measures.
       iii)    Identify and assess procurement risks, on the basis of degree of impact and
               likelihood of occurrence using the following scale:
D. Key Deliverables
Appendix 11
14
   Responses should include a discussion of the e-procurement component if an e-procurement system is in use or if
   is being planned for implementatioin.
15
   Questions indicated with * are associated with potentially ‘High’ or ‘Substantial’ risks due to the impact being ‘High’,
   therefore the strategy for managing those risks should be addressed in the Project Procurement Risk Analysis
   (Appendix 3).
68
E. ACCOUNTABILITY MEASURES
E.1 Is there a standard statement of                         *
    ethics and are those involved in
    procurement required to formally
    commit to it?
E.2 Are those involved with procurement                      *
    required to declare any potential
    conflict of interest and remove
    themselves from the procurement
    process?
E.3 Is the commencement of
    procurement dependent on external
    approvals (formal or de-facto) that
    are outside of the budgeting
    process?
E.4 Who approves procurement                                 *
    transactions, and do they have
    procurement experience and
    qualifications?
E.5 Which of the following actions
    require approvals outside the
    procurement unit or the evaluation
    committee, as the case may be, and
    who grants the approval?
     a) Bidding document, invitation to
        pre-qualify or RFP
     b) Advertisement of an invitation for
        bids, pre-qualification or call for
        EOIs
     c) Evaluation reports                                   *
     d) Notice of award                                      *
     e) Invitation to consultants to
        negotiate
     f)   Contracts                                          *
E.6 Is the same official responsible for:                    *
    (i) authorizing procurement
    transactions, procurement
74
                                                                                           Appendix 12
            PROJECT PROCUREMENT RISK ASSESSMENT – REPORT OUTLINE
EXECUTIVE SUMMARY
     Overall Assessment of project procurement risk (High, Substantial, Moderate or Low)
     Summary of weaknesses and risks identified
     Summary of mitigation/management measures to be adopted
I.     INTRODUCTION
       The introduction should indicate that the assessment was prepared in accordance with the
       Guidelines for Assessing Country, Sector and Project Procurement Risks. A brief description of
       the proposed project should be provided. In addition, the assessment should indicate when and
       how the assessment was undertaken “The CSA was undertaken from <<< to <<<. Preparation
       activities included reviewing documents, ADB’s ongoing procurement experience, and interviews
       with counterpart and discussions with stakeholders.”
       A.      Overview
               This section should provide a narrative description of the country procurement systems
               covering:
       B.      Strengths
               This section should identify strengths of project procurement arrangements, including
               those elements where ADB may wish to rely upon. This should include those elements
               considered fully capable or competent.
       C.      Weaknesses
               This section should identify weaknesses of the project procurement arrangements. This
               should be include those elements considered to be weak or need of improvement
V.     CONCLUSION
       The overall conclusion including an opinion as to whether or not the project arrangements with
       appropriate mitigation measures, are considered satisfactory.
Appendices:
76
     Completed questionnaires, procurement plans, P-RAMP
                                                                                                                     77
Appendix 13
 Using the Risk Categories at Figure 5, determine the risk management strategy to apply to each potentially
                                 High or Substantial risk (from Appendix 2)
16
   Any risk that may result in actions that are inconsistent with the ADB Procurement Guidelines or Guidelines on the Use
   of Consultants is assessed as ‘High’.
17
   ‘Likely’ or ‘Unlikely’ to occur in the life of the project, given the response to the question in Appendix 2 and the
   guidance note in the column.
18
   ‘Mitigate’ (either through the Procurement Plan including NCB Annex or through measure/s indicated in Appendix 5),
   ‘Monitor’ or ‘Avoid’.
78
Appendix 14
Background
e-Procurement is being promoted by the ADB because of its potential to enhance procurement
transparency and provide wider access to information and markets. It offers opportunities to
streamline public procurement for greater efficiency and economy.
These questions specific to the availability and use of country e-procurement systems should be
answered as part of the Procurement Risk Assessment and the findings should be integrated in the
discussions in the narrative assessment of the Procurement Assessment Report. The assessment
results will be useful in guiding the ADB to determine the kind of strategy and support it will extend
to facilitate procurement and mitigate e-procurement risks for ADB financed projects, whether it is
for strengthening or scaling existing DMC e-procurement systems or providing support to develop
and pilot a new system.
      Is the e-procurement system an end-to-end system that include all functions from
       procurement planning, advertising, bid submission, e-tendering to contract management
       and audit?
4. Benefits Achieved
      What is the impact of the e-procurement system to the government procurement function?
       to the private sector?
      How did government benefit from the use of e-procurement systems?
      If used in ADB or other MDB financed projects, how did ADB or other MDB procurement
       benefit from the use of the e-procurement?