S1

The document describes an 8-machine manufacturing process with 2 finishing stations. It provides details on the name, process, input, output, and processing time of each machine and station. It also lists the distances between the various machines and stations in meters. The overall process involves CNC punching, cutting, bending, welding, and other operations to produce 2 finished large products from raw materials over 1 or more shifts per day.

Uploaded by

Tik Tok
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
31 views6 pages

S1

The document describes an 8-machine manufacturing process with 2 finishing stations. It provides details on the name, process, input, output, and processing time of each machine and station. It also lists the distances between the various machines and stations in meters. The overall process involves CNC punching, cutting, bending, welding, and other operations to produce 2 finished large products from raw materials over 1 or more shifts per day.

Uploaded by

Tik Tok
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

C

G A

H B
F

Warehouse Warehouse of
finished product raw material
Machine A:
Name: AMADA AE 2510 NT for turret punch
Process: CNC turret punch
Total Process time to produce one product that’s has 200 parts:
10 hours.
Input: 20 metal sheets
Output: 200 parts

Machine B:
Name: plasma machine
Process: cutting the sheets by heat
Process time to produce one product that’s has 50 part: 8 hours.
Input: 10 metal sheets
Output: 50 parts
Machine C:
Name: AMADA HDS 1303 NT press brakes
Process: bending machine
Input: 30 parts 15%
Output: 30 parts
Total process time: 3 hours

Machine D:
Name: LVD & Press Brake
Process: For bending and punch the sheets
Input: 50 parts of product A 25%
Output: 50 parts of product A
Total process time: 6 hours
-------------- for product B
Input: 10 parts of product B 10%
output: 10 parts of product B
Total process time: 2 hours
Machine E:
Name: bending machine
Process: bending machine
Input: 30 parts 15%
Output: 30 parts
Total process time: 4 hours

Machine F:
Name: shearing machine
Process: shearing machine
Input: 20 parts
Output: 20 parts
Total process time: 3 hours

Station G:
Name: manual welding Station 1
Process: welding for product A
Input: 200 parts
Output: 1 large finished product
Total process time: 12 hours
Station H:
Name: manual welding Station 2
Process: welding for product B
Input: 50 parts
Output: 1 large finished product
Total process time: 14 hours

More info
 If a machine has 30 part as an output it dose not move to
the next machine until all 30 part are finished and the
material handling equipment is a forklift
 10 hours per shift
 1 shift pre day
Distance between machines and
stations in meters (m)

A to C 15
A to D 11
A to E 4
A to G 22
C to G 9
D to G 11
E to G 20
B to D 9
B to F 17
B to H 12
D to H 13
F to H 28