NUEVO
NUEVO
Abstract
Question: How lean construction can optimize the design phase to reduce the number of
design changes during the construction phase? What are the prevalent causes of
design changes that negatively affect the construction and how these changes can be
mitigated using lean construction tools and techniques?
Purpose: Design changes are considered to be one of the main causes of delay and cost
overrun in the construction industry. Many design improvement methodologies have
been developed with varying degrees of successes but still, the problem persists in
the industry. To address the issue, this study explores the interpretation and
application of lean design practices inherited from the principles of lean
construction.
Research Methodology: A systematic literature review is carried out in two phases: (1) to
identify the causes of design changes, (2) to identify lean tools that can mitigate the
detrimental effect of the design changes. Lean design practices are identified and
further classified into four improvement zones as a flow of information, customer
value, collaboration, integration of design with construction, and continuous
improvement. The efficacy of identified lean design practices is judged by mapping
them against prevalent causes of design changes in the construction. Resultantly,
each lean design practice can be assessed based on its capabilities to reduce the
design changes that emerged from the actions of owners, consultants, and contractor
Findings: This study identified twenty-three (23) lean design practices which can be used
as an effective tool to mitigate 38 actions leading to the design changes. It exposes
the strengths of each identified tool in effectively managing the design phase.
Limitation: This literature review study only includes peer-reviewed papers published by
the IGLC, American Society of Civil Engineers (ASCE), and Science Direct and
1 PhD Student, Department of Construction Management & Engineering, North Dakota State University, 202
Engineering Building, Dept 2475, P.0 Box 6050, Fargo, North Dakota, USA, 58108, Tel +17017292331,
mughees.aslam@ndsu.edu
2
Associate Professor, PhD., Department of Construction Management & Engineering, North Dakota State
University, 126 Engineering Building, 1315 Centennial Blvd, Dept 2475, P.0 Box 6050, Fargo, North Dakota,
USA, 58108, Tel: +17012318857, jerry.gao@ndsu.edu
3 Professor, PhD., Department of Construction Management & Engineering, North Dakota State University,
gary.smith@ndsu.edu
Lean Construction Journal 2020 page 176 www.leanconstructionjournal.org
http://creativecommons.org/licenses/by-nc-nd/4.0/
Aslam et al: Optimizing Construction Design Process Using the Lean Based Approach
Introduction
Design changes are inevitable in the construction industry. No matter, how well
projects are being managed, design changes during the construction phase are causing a
detrimental effect on construction outcomes (Chang, 2002). The construction industry is in
the continuous struggle for finding out the most appropriate method for reducing the
design changes. Different methods like design management as project management,
concurrent engineering, design process models, design as value management, design-build
procurement, and extensive information technology support are in use for improving
design management (Ballard and Koskela, 1998; Karlsson, Lakka, Sulanivi, Hanna and
Thompson, 2008; Tzortzopoulos, Sexton and Cooper, 2005; Hiley and Gopsill, 2000).
Although these state of the art methods have many thought-provoking and effective new
features but still considered to be fragmented and lacked a solid conceptual foundation
(Ballard and Koskela, 1998). Up till now, each approach was applied in isolation for
improving results without construing the prevalent causes of design changes in actual
construction.
With the development of lean construction since the 1990s, and after its successful
implementation in the projects, its effectiveness in the design phase was explored by
many researchers with positive results in terms of reducing design changes at later stages.
The theory of applying the lean philosophy in managing the design processes considers the
three different views of design processes as the conversion of inputs to outputs, the flow
of accurate and timely information, and value generation. Several studies have been
conducted which advocates the efficacy of lean design in reducing the design changes. The
application of lean design management on some building projects has also brought good
results (Franco and Picchi, 2016). With the recent development of Building information
modeling and the internet of things, the lean design approach is moving towards
collaboration, partnering, automation, and better visualization of the design product.
However, the concept of lean design is still to gain popularity and acceptance within
the construction industry and is required to be extensively researched in captivating the
confidence of the construction industry. At the moment, most of the research in lean
design is focused on discussing the individual practices like Last Planner System® (LPS®),
target value and set-based design, and use of building information modeling in the design
process (Freire and Alarcón, 2002; Franco and Picchi, 2016; Tauriainen, Marttinen, Dave
and Koskela, 2016; Cousins, 2011). This individuality approach in lean design practices has
limited the prospect of the addition of new practices that can be effective during the lean
design implementation phase. Few researchers have tried to introduce lean design
practices but failed to discuss the efficacy of these practices concerning actions causing
Lean Construction Journal 2020 page 177 www.leanconstructionjournal.org
http://creativecommons.org/licenses/by-nc-nd/4.0/
Aslam et al: Optimizing Construction Design Process Using the Lean Based Approach
the design changes in actual construction (Ballard and Zabelle, 2000; Gambetese and
Pestana, 2014; Marzouk, Bakry and El-Said, 2011). The lean design practices must be
explored based on its effect in mitigating the causes leading to the design changes.
An effort has been made in this study in identifying the best lean design practices
that can be effective during the design phase. The best practices are explored based on
the guiding principles of lean design as described in the literature. The literature review
revealed that many researchers have tried to explore the efficacy of lean design practices
during the design phase however a more rationalized approach is adopted in this study and
all the identified best lean design practices are discussed based on their impact in
reducing events triggering the design changes. The study is considered to be novel in its
approach as it tackles the issues of design changes by carefully combatting the causes of
design changes with the most appropriate lean tools and techniques. Very little research
has been carried out to explore the efficacy of lean tools and techniques using this
approach. The outcome of this study will make the construction industry and new lean
practitioners more prudent in making the design phase efficient.
generally identified by the Client. However, the biggest drawback in applying this
perspective to design is its fragmentation nature in which interaction between different
activities is not taken into account which leads to many persisting problems in design
management. As per Freire and Alarcon (2002), in a typical project management approach,
more influence is given in developing long chains of activities instead of identifying the
value or reducing the variabilities within the activities and if used in isolation will lead to
rework that could not be visualized.
Similarly, concurrent engineering can only be effective in managing the design
changes if collaboration and commitment by all parties exist (Kamara, 2003). The value
management approach can be successful if the value is correctly and mutually identified
by the architects, engineers, and clients. Like concurrent engineering, the design-build
approach has only contributed marginally in improving the design discrepancies because of
the lack of organizational integration, unclear clients requirement, and undefined scope of
work (Lam et al., 2003). The increased use of informational technology has certainly
brought many benefits but still could not optimize design management because of the lack
of communication and collaboration between the stakeholders. Even with the successful
implementation of Building Information modeling, the design discrepancies still exist in
construction. The bottleneck in construction design is not due to deficiencies in
information technology or its specific applications, but in short understanding of
engineering and construction.
One of the core reasons for these discrepancies is that the design process is
conceptualized as a series of different tasks without considering the internal relations
between them. An alternate approach was introduced by Ballard and Koskela in 1998 in
which design was viewed in three different views: design as the conversion of inputs into
outputs, design as a process of flow of information/processes, and design as a process of a
value generation. Later on, many researchers have admitted the efficacy of managing the
design with these three views (Tzortzopoulos and Formoso, 1999; Deshpande et al., 2011;
Marzouk et al., 2011). This perspective of managing the design was named as lean design
and derived from lean philosophy.
Lean Design
Initially, the concept of lean construction was introduced for improving the
workflow, meeting the customer's requirements most efficiently, and removing the waste
from the construction process/materials. The inspiration for applying lean construction
came from lean production, however, with the growing interest and users of lean
construction, the definition of lean construction assumed various transformations and
extensions (Mossman 2018). According to the Mossman, with the widespread
implementation of lean construction around the world, varieties of definitions of lean
construction exists to include practices emerging from within the communities. A few of
the authenticated definitions of lean construction frequently cited by the researchers are
summarized in Table 1.
From these definitions it can be seen that researchers have tried to highlight five
important aspects within lean construction definition: (1) it’s a new form of production
management, (2 ) aims, and objective of lean construction are waste reduction,
maximizing value, meeting customers’ requirements, and workflow reliability, (3) It is a
Howell (1999) “Lean construction results from the application of a new form of
production management to construction. Essential features of lean
construction include a clear set of objectives for the delivery
process, aimed at maximizing performance for the customer at the
project level, concurrent design of product and process, and the
application of production control throughout the life of the product
from design to delivery”
Abdelhamid (2013) “A holistic facility design & delivery philosophy with an overarching
aim of maximizing value to all stakeholders through systematic,
synergistic & continuous improvements in contractual arrangements,
product design, construction process design & methods selection, the
supply chain and the workflow reliability of site operations.”
Taking a lead from the lean construction, many of the authors have tried to explain
lean design as an approach to remove the wastes and non-value adding activities within
the design and engineering processes by applying the principles of lean production (Freire
and Alarcón, 2002; Gambetese and Pestana, 2014; Brookfield et al., 2004).
To remove drawbacks of the traditional design management approach, the lean
design reinforces the conversion perspective of traditional methods with value generation
and flow of information/processes. In a value generation perspective, the emphasis is
given in identifying the exact customer requirement. The main principle of this
perspective is to eliminate all non-value adding activities/requirements so that the final
product is made with the best possible value. Value is carefully analyzed at the very
outset by applying rigorous requirement analysis and systemized management of flow. The
correct and best possible value is then generated by frequent interactions between all the
stakeholders involved both in design and construction.
Lean Construction Journal 2020 page 181 www.leanconstructionjournal.org
http://creativecommons.org/licenses/by-nc-nd/4.0/
Aslam et al: Optimizing Construction Design Process Using the Lean Based Approach
Methodology
This research will be conducted by employing the extensive literature review in
identifying the best lean practices that should be incorporated into the design. The best
practices are further mapped with the existing design anomalies to establish the efficacy
of each practice in bringing the improvement within the design. The complete schematic
description of the research methodology is given in Figure 1. Based on the lean design
concepts and principles, improvement zones will be identified for improving the design
management processes in construction. For implementing the lean design, lean design
practices would then be explored and grouped within their respective zones of
improvement. The efficacy of individual design practices is judged based on its capability
of combatting the events leading to the design changes.
The final outcome in the form of metrics, indicating the lean design practices
applicable for mitigating the respective cause of design changes, will be established. The
factual causes of design changes as determined by Aslam et al. (2019) are retained in this
study for testing with lean design practices to reduce their effect.
The forums of lean construction institute (LCI) like the international group of lean
construction (IGLC) and lean construction journals (LCJ) are considered as the primary
resource for selecting the quality journal and conference papers. Apart from LCI, the data
banks of Science Direct, American Society of Civil Engineers online (ASCE), and google
scholar are also searched for the extraction of papers. Only the quality papers are retained
for further analysis based on the three-stage filtration approach proposed by Mok et al.,
(2015). Out of 183 papers initially selected, only 128 papers fulfilled the final criteria for
retention in this study.
Literature Review
Lean Design
improvement zones
skills or resources available within the construction region. Many researchers have also
highlighted the disintegration of design and construction as another important area causing
the design changes (Austin et al., 2002; Sha'aret al., 2017; Lopez et al., 2010). Based on
the above-mentioned literature facts, our research team has further summarized the
essentials of the complete lean design process in the form of improvement zones through
brainstorming and systematic literature review. These improvement zones contribute
towards achieving the principles of lean design and are discovered by many key
researchers in the past. All these improvement zones are connected and highly dependent
on each other to make efficient design. The summary of the improvement zones within the
framework of lean design is shown in Figure 2.
The productivity of lean design depends on the efficient working of all five
improvement zones throughout the design phase. This can be achieved by incorporating
different lean design practices specifically made to bringing improvements in the
respective zones. Different lean design practices identified from different studies and
grouped into the respective improvement zones are discussed in the subsequent
paragraphs.
Consistent
and accurate
Collaboration
flow (flow)
Lean
Focus on Design Integration of
design and
customer
construction
value (Value)
(IDC)
Continuos
Improvement
(CI)
guidance and supervision of architects, engineers, and contractors. This would decline the
design changes resulting from the ignorance of the client on technical issues. The Clients,
architects, engineers can be more focused on identifying and delivering the best product
through collaboration with each other. One of the major causes of design changes is the
lack of communication and coordination between various parties and the oblivious
relationships between engineers and contractors (Bibby, 2003; Yap and Skitmore, 2017;
Austin et al. 2002). Mutual collaboration can help in resolving such issues. To have a
collaborate environment in which all stakeholders are ready to help each other, few lean
design practices as recommended are given in table 2:
Table 2: Lean Design Practices
Improvement Zones Lean Design Practices References
Full Collaboration among Meetings, Conferences in a (Cousins, 2011; Ballard and Zabelle;
all the stakeholders big room by all stakeholders 2000, El. Reifi and Emmitt, 2013)
(Collaboration) (BR)
Last Planner System® (LPS®) (Ballard and Zabelle, 2000; Freire and
Alarcón, 2002)
Use of 5S
Focus on customer value Target Value Design (TVD) (Tauriainen et al., 2016; Gambetese
and Pestana 2014; Cousins, 2011;
(Value)
Franco and Picchi, 2016; Do, Chen,
Ballard and Tommelein, 2014)
Integration of design and Integrated project delivery (McGraw Hill, 2014; Cousins, 2011)
construction (IDC) (IDP)
activities are in progress, and the Client can better visualize the project, they order scope
changes to compensate for their initial lack of technical knowledge. In other cases,
Architects/Engineers have difficulties both in capturing clients’ needs and conveying
conceptual design options to them. Such types of design changes occur because of a lack
of collaboration and communication between Clients and Architects. If Clients are made
well aware of the technical requirements before the construction proceeds or if the
Architects/Engineers have fully captured the Client’s requirement before designing, such
events of design changes would not be happening. So the improvement zones identified for
mitigating these two causes of design changes are collaboration and value generation
respectively. To validate this, the literature review confirmed that through collaboration
and value generation exercises, such type of design changes can be reduced. In the same
way, improvement zones are identified for other causes of design changes. Due to limited
space, detailed literature references that how improvement zones are identified for every
cause of design change are not given in this study however example Table 3 is presented
that can show how some of the causes of design changes are categorized into improvement
zones.
Table 3: Examples for categorizing causes of design changes in improvement zones
Causes of Design Suggested Lean practices Relevant References
Changes improvement
zones
• lack of Client’s • Participation of clients in • Early • Herrera et al.,
technical knowledge the design phase involvement 2019
to comprehend and • Use of BIM to visualize and • Reifi et al., 2013
visualize the project • Improving communication collaboration • Knotten et al.
between different parties 2016
• Ballard, 2002
• Sacks et al. 2020
• Architects/Engineers • Participation of clients in • Collaboration • Herrera et al.,
have difficulties both the design phase • Customers 2019
in capturing clients’ • Early involvement of design value • Ballard, 2003
needs and conveying specialists for the project • Frieire 2002
conceptual design • Improving communication • Salgin et al., 2016
options to them between different parties
• Inadequate pre- • Involvement of • Collaboration • Ballard et al,
construction study builders/contractors during • Flow 2002
and review of design the early design stages of management • Formoso et al.,
documents by the project. • Integrated 1998
contractors • Managing flow of design and • Sodal et al., 2014
considering the information by involving construction • Ballard, 2002
exotic and complex contractors early (IDC)
nature of design • Simultaneously design of
the product and the
• Adversarial/Oblivious construction process
relationship between • Improving communication
consultant and between different parties
contractor
In the last step, the improvement zones are mapped against the best lean design
practices. From the systematic literature review, we have identified the respective lean
design practices that can target the respective improvement zones and are already shown
Lean Construction Journal 2020 page 189 www.leanconstructionjournal.org
http://creativecommons.org/licenses/by-nc-nd/4.0/
Aslam et al: Optimizing Construction Design Process Using the Lean Based Approach
in Table 2. In case the improvement zone is collaboration, tools like BR, KW, Freq comm,
IDC and VDC can be the lean tools that can be employed to increase collaboration. For the
sake of simplicity many practices that are sequential or having many common
characteristics have been grouped. Moreover, many practices can be an integral part of
another practice if applied in full spirit. For example, teamwork, reverse phase
scheduling, transparencies, and decision deferred until the last responsible moment are
inherent in the LPS®. Knot working and big rooms are combined because of the same
objective of achieving better collaboration. Since the SBD and TVD are interlinked, in
which design alternatives are checked against the targeted cost, hence kept in the same
group. Design workshop and quality functional deployment are grouped as both are used
for identifying the exact requirements of the clients.
Finally, we developed a matrix that can show how the construction industry can use
different lean design practices to eradicate the events leading to design changes in Table
4.
Perfection/CI
Collaboration
Supply chain
QFD/ Design
Freq Comm
Lean Audit
Workshop
in design
TVD/SBD
Cross FT
VDC-BIM
Training
BR/KW
Value
LPS®
Flow
DSM
VSM
Pull
IOT
IDC
IPD
CE
IIS
5S
Client Related
Lack of technical
knowledge to
* * * * *
comprehend and
visualize the project
Long-time taken by
the client for giving * * * * * * * *
decision
Clients changing
financial and business
* * * * * * * * * *
conditions necessitates
the scope changes
Inappropriate choice
of project contract
* * * * *
type (unit price, lump
sum, etc.)
Perfection/CI
Collaboration
Supply chain
QFD/ Design
Freq Comm
Lean Audit
Workshop
in design
TVD/SBD
Cross FT
VDC-BIM
Training
BR/KW
Value
LPS®
Flow
DSM
VSM
Pull
IOT
IDC
IPD
CE
IIS
5S
Unreasonable Client
and End User * * * * * * * * * * *
Expectations
Architect/Engineer Related
Lack of confidence in
preplanning for design * * * * * *
work
Designers have
difficulties both in
capturing clients’
* * * * * * * * * *
needs and conveying
conceptual design
options to them
Deficient resources in
quality or quantity
(e.g. tools, * * * * * * * * *
equipment, staff, or
financial)
Perfection/CI
Collaboration
Supply chain
QFD/ Design
Freq Comm
Lean Audit
Workshop
in design
TVD/SBD
Cross FT
VDC-BIM
Training
BR/KW
Value
LPS®
Flow
DSM
VSM
Pull
IOT
IDC
IPD
CE
IIS
5S
between Client and
designer as well as
designer and
contractor
Lack of information
* * * * * * * * * *
flow among parties
Unstructured Design
* * * * *
process
No Design checking or
2nd or 3rd party
* * * * * * * * *
reviews, No system of
design checking
Ineffective utilization
* * *
of automation
Time Constraints * * * * * * * * *
Designer
noninvolvement/unava
* * * * * * * *
ilability during the
construction phase
Inadequate
information provided * * * * * * * * * * * * * *
to Designer
Perfection/CI
Collaboration
Supply chain
QFD/ Design
Freq Comm
Lean Audit
Workshop
in design
TVD/SBD
Cross FT
VDC-BIM
Training
BR/KW
Value
LPS®
Flow
DSM
VSM
Pull
IOT
IDC
IPD
CE
IIS
5S
The short-term
conflict between
productivity * * * * * * * *
(production) and
quality.
Inadequate training/
inexperience, lack of
knowledge in ( building
bye-laws, codes etc,
constructability, * * * *
availability and
suitability of
materials, engineering
design techniques
Change of designers * * * * * * *
Lack of Design
* * *
Standards.
No involvement of
contractor during the * * * * * * * * * * * * * * * *
design phase
Lack of adequate
* * * * * *
documentation
Late approvals of
* * * * * * * * *
design
Perfection/CI
Collaboration
Supply chain
QFD/ Design
Freq Comm
Lean Audit
Workshop
in design
TVD/SBD
Cross FT
VDC-BIM
Training
BR/KW
Value
LPS®
Flow
DSM
VSM
Pull
IOT
IDC
IPD
CE
IIS
5S
Several groups visit
project late and give * * * * * * * *
their points too late
Discrepancies between
* * * * * * * * * *
contract documents
Contractor Related
Inadequate pre-
construction study and
review of design
documents by
* * * * * * * * * * * * * * *
contractors
considering the exotic
and complex nature of
design
Awarding contract to
the lowest price
* * * * *
regardless of the
quality of services
Lack of experience in
new construction * * * * * *
technologies
Lack of communication * * * * * * * * * *
and coordination
Perfection/CI
Collaboration
Supply chain
QFD/ Design
Freq Comm
Lean Audit
Workshop
in design
TVD/SBD
Cross FT
VDC-BIM
Training
BR/KW
Value
LPS®
Flow
DSM
VSM
Pull
IOT
IDC
IPD
CE
IIS
5S
between the various
project team
Information problems * * * * * * * * * * *
Adversarial/Oblivious
relationship between
* * * * * * * * *
consultant and
contractor
Shop drawings’
submission, approval * * * * * * *
and adequacy
Contractors request on
improving the
buildability by
* * * * * * * * * * * * * *
suggesting alternate
construction method
and material used
Strict quality
tolerances mentioned * * * * * * * * * * *
in the specification
lean design practices as mentioned in Table 4. We can say that it is the summation of
respective columns under the respective lean design practices.
Different lean design practices as mentioned in Figure 4 can provide a guideline for
construction firms, owners, or consultants to start with the lean design approach. Lean
philosophy never advocates on restricting to one or two practices rather it promotes a
culture of innovation and creativity in which best practices that best suit the prevailing
circumstances/environments, are selected.
30 27
Number of causes of design changes
25
20
20 17
15
9 9
10
0
Collaboration Flow IDC Value Perfection/CI
Improvement zones
35
Number of causes of design changes
29 29 28
30
26
25 22
20 18
16 16
15
10 10
10 8 8 7 7 6 6
5 3 3
Conclusions
Application of lean design practices during the design phase will eventually lead to
the reduction of design changes that normally occur at later stages in construction and
having detrimental effects on the cost, time, and productivity. Many events lead to design
changes like errors and omissions and result in rework or additional works. Lean literature
has suggested several lean design practices that can be used to target these causes of
design changes. A very elaborative study is carried out in determining the lean design
practices which are further mapped based on their role in targeting the respective causes
of design. This approach has provided a more distinct role of each practice in eliminating
the causes of design. Since the causes of design changes are summarized based on the
most commonly encountered causes of the design changes on construction projects as
documented in the existing literature, thereby making the findings of this study more
realistic and close to the construction project environments. The role of Clients,
architects, engineers, and contractors in eliminating the design changes can only be
effective if these stakeholders work together as a team in a mutually collaborative
environment which is the basic hallmark of lean construction philosophy. The inculcation
of flow and value views within the design processes leads towards a more structured
approach towards design with the reduction of inherent wastes within design processes and
information. The outcome of this study will provide a systematic approach to the
construction industry and new lean practitioners for making the design process as efficient
as possible by using lean design practices. Additionally, the developed matrix will be very
helpful to the new lean practitioners in finalizing their lean tools and techniques during
the design phase. In further continuation of this study, it would be a great assistant to the
construction industry if a complete framework is presented in future research for
implementing the lean design practices during different stages of design and validating the
results from its actual application in real-time construction projects.
References
Abdelhamid (2013). “Lean construction,” https://msu.edu/user/tariq/Learn_Lean.html
(March 21, 2013)
AGC, Lean Construction Education Program. https://www.agc.org/learn/education-
training/lean-construction-education-program
Ahmed, S. M., Sang, L. P., & Torbica, Ž. M. (2003). Use of quality function deployment in
civil engineering capital project planning. Journal of Construction Engineering and
Management, 129(4), 358-368. https://doi.org/10.1061/(ASCE)0733-
9364(2003)129:4(358)
Arroyo, P., and Long, D. (2018). “Collaborative Design Decisions” In: Proc. 26th Annual
Conference of the International. Group for Lean Construction (IGLC), González, V.A.
(ed.), Chennai, India, pp. 463–472. DOI: https://doi.org/10.24928/2018/0509.
Available at: www.iglc.net.
Aslam, M., Baffoe-Twum, E., & Saleem, F. (2019). Design Changes in Construction
Projects–Causes and Impact on the Cost. Civil Engineering Journal, 5(7), 1647-1655.
https://doi.org/10.28991/cej-2019-03091360
Austin, S. A., Baldwin, A. N., & Steele, J. L. (2002). Improving building design through
integrated planning and control. Engineering, Construction and Architectural
Management, 9(3), 249-258. https://doi.org/10.1108/eb021220
Lean Construction Journal 2020 page 199 www.leanconstructionjournal.org
http://creativecommons.org/licenses/by-nc-nd/4.0/
Aslam et al: Optimizing Construction Design Process Using the Lean Based Approach
Ballard, G. & Koskela, L. (1998), On the Agenda of Design Management Research In:, 6th
Annual Conference of the International Group for Lean Construction. Guarujá, Brazil,
13-15 Aug 1998. http://iglc.net/Papers/Details/38
Ballard, G. (2002). Managing work flow on design projects: a case study. Engineering
Construction and Architectural Management, 9(3), 284-291.
https://doi.org/10.1046/j.1365-232X.2002.00251.x
Ballard, G., & Howell, G. (2003). Lean project management. Building Research &
Information, 31(2), 119-133. https://doi.org/10.1080/09613210301997
Ballard, G., & Zabelle, T. (2000). “Lean Design: Process Tools & Techniques” White Paper#
10, Lean Construction Institute, USA. http://www.p2sl.berkeley.edu (accessed 12
Feb 2018)
Ballard, G., Kim, Y. W., Jang, J. W., & Liu, M. (2007). “Road Map for Lean Implementation
at the Project Level”, The Construction Industry Institute. Retrieved from
https://www.researchgate.net (accessed 05 Jan 2017)
Ballard, G.; Tommelein, I.D.; Koskela, L.; Howell, G. Lean Construction Tools and
Techniques. In Design and Construction: Bulding in Value; Best, R., de Valence, G.,
Eds.; Butterworth-Heinemann and Elsevier Ltd.: Amsterdam, The Netherlands, 2002;
pp. 227–255.
https://www.academia.edu/811476/Lean_construction_tools_and_techniques
Barth, K.B., Formoso, C.T., Sterzi, M.P., (2019). “Performance Measurement in Lean
Production Systems: an Exploration on Requirements and Taxonomies” In: Proc. 27th
Annual Conference of the International. Group for Lean Construction (IGLC), Pasquire
C. and Hamzeh F.R. (ed.), Dublin, Ireland, pp. 629-640. DOI:
https://doi.org/10.24928/2019/0266. Available at: www.iglc.net
Bibby, L. (2003). Improving design management techniques in construction. Doctoral
dissertation, Loughborough University. Retrieved from
https://repository.lboro.ac.uk/ Accessed 15 Jun 2018
Brookfield, E. , Emmitt, S. , Hill, R. & Scaysbrook, S. (2004, August) The Architectural
Technologist's Role in Linking Lean Design with Lean Construction' In 12th Annual
Conference of the International Group for Lean Construction. Helsingør, Denmark.
http://iglc.net/Papers/Details/30
Chang, A. S. T. (2002) Reasons for cost and schedule increase for engineering design
projects. Journal of Management in Engineering, 18(1), 29-36.
https://doi.org/10.1061/(ASCE)0742-597X(2002)18:1(29)
Cousins, B. 2011. Design Management – A Lean Approach.
https://network.aia.org/HigherLogic/System/DownloadDocumentFile.ashx?Document
FileKey=c89be6ec-b81c-4702-a1c2-ef86fc37ab5b. Accessed 25 June 2018
Dave, B., Kubler, S., Främling, K., & Koskela, L. (2016). Opportunities for enhanced lean
construction management using Internet of Things standards. Automation in
construction, 61, 86-97. https://doi.org/10.1016/j.autcon.2015.10.009
Delgado‐Hernandez, D. J., Bampton, K. E., & Aspinwall, E. (2007). Quality function
deployment in construction. Construction Management and Economics, 25(6), 597-
609. https://doi.org/10.1080/01446190601139917
Deshpande, A. S., Filson, L. E., Salem, O. M., & Miller, R. A. (2011). Lean techniques in the
management of the design of an industrial project. Journal of management in
engineering, 28(2), 221-223. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000065
Do, D. , Chen, C. , Ballard, G. & Tommelein, I. D. (2014, Jun) Target Value Design as a
Method for Controlling Project Cost Overruns. In 22nd Annual Conference of the
Howell, G. A. (1999), 'What Is Lean Construction – (1999) In:, 7th Annual Conference of
the International Group for Lean Construction. Berkeley, USA, 26-28.
http://iglc.net/Papers/Details/74
Ibbs, W. (2005). Impact of change’s timing on labor productivity. Journal of Construction
Engineering and Management, 131(11), 1219-1223.
https://doi.org/10.1061/(ASCE)0733-9364(2005)131:11(1219)
Jørgensen, B. (2006). Integrating lean design and lean construction: processes and
methods. Dissertation for PhD, Technical University of Denmark (DTU). Retrived from
https://orbit.dtu.dk/files/3141488/Jorgensen%202006%20thesis%20download%20versi
on.pdf Accessed 18 Jul 2018)
Kamara, J. M. (2003) Enablers for Concurrent Engineering in Construction. In:, 11th Annual
Conference of the International Group for Lean Construction. Virginia, USA.
http://iglc.net/Papers/Details/220
Karlsson, M., Lakka, A., Sulankivi, K., Hanna, A. S., & Thompson, B. P. (2008). Best
practices for integrating the concurrent engineering environment into multi partner
project management. Journal of construction engineering and management, 134(4),
289-299. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:4(289)
Khalife, S., Hamzeh, F. (2019). “A Framework for Understanding the Dynamic Nature of
Value in Design and Construction” In: Proc. 27 th Annual Conference of the
International. Group for Lean Construction (IGLC), Pasquire C. and Hamzeh F.R.
(ed.), Dublin, Ireland, pp. 617-628. DOI: https://doi.org/10.24928/2019/0254.
Available at: www.iglc.net
Knotten, V. , Svalestuen, F. , Lædre, O. & Hansen, G. (2016). Improving Design
Management With Mutual Assessment' In:, 24th Annual Conference of the
International Group for Lean Construction. Boston, Massachusetts, USA, 20-22 Jul
2016. http://iglc.net/Papers/Details/1303
Koskela, L. (1992). “Application of the new production philosophy to construction”, CIFE
Technical Report No. 72, Stanford, CA: Stanford university, September, 1992,
Retrieved from http://www.leanconstruction.org.uk/media/docs/Koskela-TR72.pdf
(accessed 25 Dec 2017)
Koskela, L. , Ballard, G. & Tanhuanpää, V. (1997, Jul) Towards Lean Design Management.
In 5th Annual Conference of the International Group for Lean Construction, Gold
Coast, Australia. http://iglc.net/Papers/Details/27
LAM, E. W., Chan, A. P., & Chan, D. W. (2003). Potential problems of running design-build
projects in construction. HKIE transactions, 10(3), 8-14.
https://doi.org/10.1080/1023697X.2003.10667915
Lean Construction Instituete (LCI). Lean Construction defined.
https://www.leanconstruction.org/wp-content/uploads/2016/02/TDC-CH04.pdf
Lopez, R., Love, P. E., Edwards, D. J., & Davis, P. R. (2010). Design error classification,
causation, and prevention in construction engineering. Journal of performance of
constructed facilities, 24(4), 399-408. https://doi.org/10.1061/(ASCE)CF.1943-
5509.0000116
Marzouk, M., Bakry, I., & El-Said, M. (2011). Application of lean principles to design
processes in construction consultancy firms. International Journal of Construction
Supply Chain Management, 1(1), 43-55.
http://www.ijcscm.com/sites/default/files/issue/nid-6/mmarzouk_1324337202.pdf
McGraw Hill Construction (2014) Managing Uncertainty and Expectations in Building Design
and Construction. Retrieved from https://dbia.org/wp-
content/uploads/2018/05/Research-McGrawHill-Managing-Uncertainty-Expectations-
2014.pdf Accessed 12 March 2018
Lean Construction Journal 2020 page 202 www.leanconstructionjournal.org
http://creativecommons.org/licenses/by-nc-nd/4.0/
Aslam et al: Optimizing Construction Design Process Using the Lean Based Approach
Tauriainen, M., Marttinen, P., Dave, B., & Koskela, L. (2016). The effects of BIM and lean
construction on design management practices. Procedia engineering, 164, 567-574.
https://doi.org/10.1016/j.proeng.2016.11.659
Thibelsky, E. & Sacks, R. 2010, 'The Relationship Between Information Flow and Project
Success in Multi-Disciplinary Civil Engineering Design' In:, Walsh, K. & Alves, T., 18th
Annual Conference of the International Group for Lean Construction. Haifa, Israel,
14-16 Jul 2010. pp 140-150. http://iglc.net/Papers/Details/722
Tzortzopoulos, P. & Formoso, C. T. (1999, July). Considerations on Application of Lean
Construction Principles to Design Management In 7th Annual Conference of the
International Group for Lean Construction. Berkeley, USA, pp 335-344.
http://iglc.net/Papers/Details/88
Tzortzopoulos, P., Sexton, M., & Cooper, R. (2005). Process models implementation in the
construction industry: a literature synthesis. Engineering, Construction and
Architectural Management, 12(5), 470-486.
https://doi.org/10.1108/09699980510627162
Yap, J. B. H., & Skitmore, M. (2018). Investigating design changes in Malaysian building
projects. Architectural Engineering and Design Management, 14(3), 218-238.
https://doi.org/10.1080/17452007.2017.1384714
yue Wang, L. (2015, December). Research on Construction Lean SCM in IOT Environment. In
2015 International Conference on Electrical, Electronics and Mechatronics. Atlantis
Press. https://www.atlantis-press.com/proceedings/iceem-15/25846357
Zaneldin, E. K. (2006). Construction claims in United Arab Emirates: Types, causes, and
frequency. International Journal of Project Management, 24(5), 453-459.
https://doi.org/10.1016/j.ijproman.2006.02.006