Final Internship Report
Final Internship Report
TECHNOLOGY
SCHOOL OF ENGINEERING
SEPTEMBER 2022
DECLARATION
I, KAWOOYA CHARLES declare that this report is my original work and has not been
submitted to any college university or institution for any academic award
Signed: _____________________________
Student Name:
Date: _______________________________
i
ABSTRACT
Here in this report is the work I did during my industrial training at SPAN
CONTRACTORS LIMITED.
This report covers the work done on Domestic installation on the arcade premises,
The first chapter of this report comprises a brief background of the industrial training
place, mission, address and objectives. The next two chapters comprise of a literature
review on domestic and industrial installation and detailed description of the practical
work done during the training.
This last chapter of this report includes observations made while training,
recommendations, conclusion, challenges and references.
ii
ACKNOWLEDGEMENT
First and foremost. I greatly thank the almighty God for the life and wisdom through I have
been able to successfully accomplish my industrial training
Furthermore, I thank span construction company for the industrial training placement
I also thank my supervisor Mr KAKOOZA STEVEN for his time and guidance during this
industrial training period.
iii
LIST OF FIGURES
FIGURE 1 SHOWING A 3 CORE CABLE.......................................................................................................................5
FIGURE 2 SHOWING A ONE WAY CIRCUIT WIRING....................................................................................................6
FIGURE 3 SHOWING A 3 WAY CIRCUIT WIRING.........................................................................................................7
FIGURE 4 SHOWING JOINT BOX WIRING METHOD......................................................................................................7
FIGURE 5 SHOWING THE RING CIRCUIT....................................................................................................................8
FIGURE 6 SHOWING A METALLIC MOULD BOX (MK)..............................................................................................11
FIGURE 7 SHOWING A JUNCTION BOX....................................................................................................................11
FIGURE 8 SHOWING A DRAWING TAPE..................................................................................................................11
FIGURE 9 SHOWING A CONSTRUCTED UNIT EARTH PIT..........................................................................................15
FIGURE 10 SHOWING THE EXCAVATION OF THE LOOP..........................................................................................16
FIGURE 11 SHOWING THE CONNECTION OF A REFERENCE EARTH POINT TO THE MEGGER TESTER.......................16
FIGURE 12 SHOWING THE FIRST TEST POINT HAMMERED IN THE GROUND CONNECTED TO THE MEGGER TESTER 17
FIGURE 13 SHOWING THE SECOND TEST POINT HAMMERED IN THE GROUND CONNECTED TO THE MEGGER
TESTER...........................................................................................................................................................17
FIGURE 14 SHOWING THE TEST RESULTS...............................................................................................................17
FIGURE 15 SHOWING A 4-POLE MCCB..................................................................................................................19
FIGURE 16 TESTING AFTER THE INSTALLATION OF THE 4-POLE MCCB................................................................20
FIGURE 17 SHOWING AN ALREADY INSTALLED 4-POLE MCCB.............................................................................21
FIGURE 18 ILLUSTRATION OF A 3-PHASE WIRING...................................................................................................22
FIGURE 19 A CONTROL PANEL...............................................................................................................................22
FIGURE 20 TIGHTENING SCREWS IN THE CONTROL PANEL.....................................................................................23
FIGURE 21 SHOWING A SUB DISTRIBUTION BOARD...............................................................................................23
FIGURE 22 SHOWING AN INSTALLED SUB DISTRIBUTION BOARD..........................................................................23
FIGURE 23 LOOPING SOCKETS AND LIGHT CABLES THROUGH THE JUNCTION BOXES..........................................24
FIGURE 24 INSTALLATION OF CEILING ROLLS........................................................................................................25
FIGURE 25 SHOWING A THREE GANG SWITCH COMPLETELY WIRED......................................................................26
FIGURE 26 SHOWING INSTALLED METERS ON THE SUB DISTRIBUTION BOARD.....................................................28
iv
LIST OF TABLES
v
LIST OF ACRONYMS
AC: Alternating Current
AI: Artificial Intelligence
CB: Circuit Breaker
CU: Consumer Unit
DAI: Distributed Artificial Intelligence
DB: Distribution Board
DC: Direct Current
DFB: Distribution Fuse Box
IEEE: Institute of Electrical and Electronics Engineering
IT: Industrial Training
MCB: Miniature Circuit Breaker
PVC: Polyvinyl Chloride
vi
Table of Contents
DECLARATION........................................................................................................................i
ABSTRACT...............................................................................................................................ii
ACKNOWLEDGEMENT........................................................................................................iii
LIST OF FIGURES..................................................................................................................iv
LIST OF TABLES.....................................................................................................................v
LIST OF ACRONYMS............................................................................................................vi
CHAPTER ONE........................................................................................................................1
1.0 INTRODUCTION............................................................................................................1
1.1 INDUSTRIAL TRAINING..............................................................................................1
1.1.1 Objectives of industrial training................................................................................1
1.2 ABOUT SPAN CONTRACTORS LIMITED.................................................................2
CHAPTER TWO.......................................................................................................................4
2.0 LITERATURE REVIEW.................................................................................................4
2.1 DOMESTIC INSTALLATION........................................................................................4
2.1.1 ELECTRICAL WIRING...........................................................................................4
2.1.2 MAINTENANCE....................................................................................................12
CHAPTER THREE..................................................................................................................14
3.1 EARTHING....................................................................................................................14
3.1.1 COMPONENTS OF EARTHING AND BONDING SYSTEM.............................14
Construction of a unit earth pit.........................................................................................14
3.1.2 EARTH TEST..........................................................................................................16
3.2 WALL CHASING ON THE LAST FLOOR.................................................................18
3.3 WIRING OF LIGHTS, SOCKETS, MCCB, AND DISTRIBUTION BOARDS..........18
3.3.1 CLEARING PATH WAYS.....................................................................................19
3.3.2 INSTALLATION OF 4-POLE MCCB...................................................................19
3.3.3 INSTALLATION OF THE CONTROL PANNEL AND SUB DISTRIBUTION
BOARDS..........................................................................................................................22
3.3.4 LOOPING IN WIRES.............................................................................................23
3.4 TERMINATIONS AND FITTINGS OF LIGHTS AND SOCKETS............................24
3.4.1 INSTALLATION OF LIGHTS...............................................................................24
3.4.2 INSTALLATION OF SOCKETS...........................................................................26
3.4.3 INSTALLATION OF METERS.............................................................................26
CHAPTER FOUR....................................................................................................................29
4.1 ENVIRONMENTAL HEALTH AND SAFETY POLICY AND PROCEDURES.......29
vii
4.1.1OBJECTIVE AND PURPOSE.................................................................................29
4.1.2 EHS PROCEDURES TAKEN AT THE SITE........................................................29
4.2 SKILLS ACQUIRED.....................................................................................................29
CHAPTER FIVE......................................................................................................................30
5.1 OBSERVATIONS AND CHALLENGES.....................................................................30
5.2 RECOMMENDATIONS...............................................................................................30
5.3 CONCLUSION..............................................................................................................30
REFERENCES.........................................................................................................................31
viii
CHAPTER ONE
1.0 INTRODUCTION
TO THE UNIVERSITY
To change the program in the light of company feedback
To build relationships with businesses and organisations for technical advancement,
especially in the fields of product design and construction
To know skill gaps and improve quality of training.
TO THE COMPANY
To be aware of potential skill availability and identify potential personnel
To enhance the training provided at training facilities for relevance to industry
To participate in the training of future employees.
To solidify the relationship between industrial organizations and the university.
To promote the products and services of the industrial institutions. (UBTEB, n.d.)
1
1.2 ABOUT SPAN CONTRACTORS LIMITED
Span Contractors Limited was registered in 2013 and has been in the field of construction for
the last eight years
“We Span Contractors Limited have a keen team player spirit and we pride ourselves on
quality work man-ship and the timely competition of projects”
Company address
Company name: SPAN CONTACTORS LIMITED
Location: MENGO
P.O. Box 74504 Kampala
Email: spancontractors@gmail.com
Company Mission
To strive for perfection in anticipation of exceeding our clients’ highest expectations,
building a good client relationship through leadership creative solutions and hard work.
Since construction can be a hazardous business, we are dedicated to education
implementation and self-monitory of all safety programmers to ensure the safest working
environment for all employees
Company Vision
To ensure that our operations safeguard the health, safety, environment and security of the
community where we work
Company Goals
Client contentment
Obtain rapid business growth
Employee and trainee empowerment through mentoring and skill development
2
COMPANY ORGANISATION CHART
STRUCTURAL ORGANISATION OF THE COMPANY
Client
Contractor Consultant’s team
Architect
Electrical
Site Engineer Structural
Quantity surveyor
Site supervisor
Clerk of works
Porters
3
CHAPTER TWO
Allowable wire and cable types and sizes are specified according to the circuit operating
voltage and electric environmental conditions such as ambient temperature range, moisture
levels and exposure to sunlight and chemicals (System of Electrical Wiring, n.d.)
Conduit wiring, Concealed wiring, Batten wiring, Cleat wiring, Casing wiring
ADVANTAGES OF CONDUIT WIRING
Safest wiring
Appearance is better
No risk of damage of cable insulation
Safe from humidity smoke, steam
No risk of shock (Britanicca, n.d.)
Electrical cable
This is a rally of one or more wires running side by side or bundled which is applied to
transfer electric current
4
Advantages:
Earth cable
Disadvantages:
5
Classification of electrical wires
Non-Metallic (sheathed cable)
Underground (feeder cables)
Metallic (sheathed cable)
Coaxial, Paired, Twisted pair multi-conductor cable, Twin, Twin axial (Classfication
of Electrical wires, n.d.)
It consists of a pair of wires from the mains terminals supplying a lamp. In this circuit there
must be a switch (if single pole) must be situated in the phase conductor.
In this circuit, the switches can have two positions, either of which can light the lamp.
Suppose switch A is in the upper position, and switch B in the lower position as illustrated,
there is no circuit, so the lamp is out
6
(Britanicca, n.d.)
Joint box showing phase, neutral and circuit protective conductor (c.p.c)
Switch connected showing switch feed and switch wire and c.p.c(or Earth)
Light connected showing switch wire and neutral and c.p.c (Earth)
7
Loop-in method
The most common system of wiring final sub-circuits is loop-in system where all connections
are made at the electrical accessories.
For simplicity all wiring diagrams have to show the basic circuit wiring necessary for the
circuit.
2.1.1.3 POWER CIRCUITS
SOCKET OUTLET CIRCUITS
Standard circuit arrangements
TYPES OF CIRCUITS
Ring circuits
Radial circuits
Applications
Limitations:
8
The floor area served by a single 30A ring circuit must not exceed 100 square meters
in domestic installations.
RADIAL CIRCUIT
Radial circuits also make use of 13A sockets but the circuit is not wired in the form of a ring.
Where immersion heaters are installed in storage tanks with a capacity in excess of 15litres or
a comprehensive space heating installation is to be installed, for example, electric fires or
storage radiators, separate circuits should be provided for each heater. (Bircham, 1994)
Limitations
The floor area served by the socket outlets may be limited to either 20 or 50 square meters.
The sum of the terms of cables which are to be run in the same enclosure is the compared
with the term given in the tables for different sizes and routes of conduit or trucking.
The minimum size of conduit or trucking to accommodate the cables can be determined from
the appropriate table.
CONDUIT WIRING
This refers to the conduit enclosed wiring.
In addition, conduits are installed in the ceiling. From the ceiling all final circuits are drawn.
Most junction boxes in such an installation are in the ceiling.
9
Few or no inspection boxes are found where half conduit wiring is used. In case of a fault in
the installation, the ceiling is one of the areas that are examined. It is a common and cheap
system of wiring.
Under this type of wiring all cables are drawn through conduits consumer unit to termination.
Conduits are also located in walls. Quite many inspection boxes are included. No wires are
exposed. (Bircham, Electrical Installation Notes, 1994)
Here drilling and installing wall clips is done to support the PVC conduits on the wall.
At corners flexible conduits are employed. The extra switches and sockets are mounted using
plastic mold boxes
Types of conduits.
Conduits are categorized according to the tasks they are to be used for and the materials from
which they are made.
They are usually used to terminate conduit electrical machinery, in situations where there is
likely to be movement or where high temperatures are likely to be experienced. Such
conduits are made from pressed steel spiral
Nonmetallic conduit.
Accessories are bends, adaptable boxes, saddles, base plates, circular boxes and couplers
Preparing a conduit.
To perform a clean job, conduits are carefully prepared in the following ways.
Measuring or estimating length: using measuring instruments such as a tape measure, correct
lengths required are determined.
Cutting: having measured or estimated desired length, using suitable tools conduits are cut to
these sizes. Cutting tools like the hacksaw with fine tooth blade are used.
10
Drawing cables into a conduit system
The steel or draw tape is commonly used. It consists of a spring steel with a ball point at one
end and a closed loop at the other end. It is used for actual draw-in wire
Wall plugs: These are electrical receptables in walls. They can be plastic or metallic
Junction boxes - These are used to provide open points in the ceiling for termination of lights.
Their size is specified using internal diameter of their arms, showing the sizes of conduits that
can fit inside them as in the case of bends and coupler
11
Figure 8 Showing a Drawing Tape
2.1.1.5 WALL CHASING.
This refers to the act of making grooves in the wall to provide for conduit passage during
conduit wiring. The grooves are cut following the drawing done by the qualified engineer.
Supervisors interpret these drawings and therefore give relevant instructions to ensure
accuracy.
Using hand cutting tools: in this method, a hammer and a chisel are used. With the hammer
hit on the head of the chisel grooves are created along the surface of the walls.
Using a drilling machine: this is specifically designed, electrically run machine whose
purpose is to make holes in surfaces like rocks, metal, concrete among others. The wall
chasing process is made less tedious and faster.
2.1.2 MAINTENANCE
This is the process of ensuring that electrical components/ equipment’s are
kept in good working order
12
Risk-based maintenance: Prioritizes maintenance resources towards assets that
carry the most risk if they were to fail
Condition-based maintenance (CBM): This is a maintenance strategy
that monitor the actual condition of an electrical component to decide what
maintenance must be done (scienceDirect, n.d.)
11 1
13 1.5
18 2.5
24 4
31 6
42 10
56 16
73 25
90 35
145 50
185 70
230 95
(images, n.d.)
Table 1: showing the cable sizes and their ratings
13
CHAPTER THREE
3.1 EARTHING
14
The main earth pit should be located as near to the equipotential earth bus bar in the
equipment room as possible
15
Figure 10 Showing the Excavation of the Loop
16
Figure 13 Showing the Second test point hammered in the ground Connected to the
megger tester
EXPLANATION
According to the IEEE standards the acceptable Earth resistance ranges from 1-10 ohms
For achieving this value more than one earth pits can be installed if necessary, depending
upon the soil resistivity
In places where space is not available to provide parallel earth pits then longer earth rods
maybe provided. These earth rods are connected with a suitable anticorrosive copper coupler
(Reasoned document, 2019)
IMPORTANCE OF MATERIALS USED
17
Sand: This adds porosity to the soil mixture around the earth rod
Sodium chloride (SALT): This lowers the soil’s resistance. It’s of importance that the earth’s
resistance that we make it as small as possible
Charcoal: this keeps the soil cold. It’s of importance that the earth’s pit remains cold
Each point of lightening arrestors was connected to two different earth pits
18
3.3.1 CLEARING PATH WAYS
PROCEDURE
Papers used for padding junction boxes and adapter boxes during conduit laying phase were
removed
The head of a wireman snake was inserted into the arm of the first JB connected to the
conduit and continuously pushed into concrete path ways at a suitable angle to the ceiling
In case of any blockages met, it was flushed with water using a horse pipe inserted at the
nearest JB entry until a water mark is seen at the ceiling. This point was chiselled open to
clear the path
If the passage was blocked from the junction box, it was chiselled to open and the padding
removed
The draw tape/ drawing tape was inserted to ensure continuity between the different junction
boxes and MKs
A binding wire was bound to the end of the drawing tape and pulled into the clear conduit
pathways continuously until the end of the given circuit
19
The green cables were connected to the earth bench fixed in the Box
20
It provides greater power density than a single circuit at the same amperage hence keeping
wiring size and costs lower
Three phase circuits make it easier to balance loads, minimising harmonic currents and the
need for the large neutral wires
Three phase transformers are light in weight and smaller in size than single-phase
transformers which means they use less space
Three phase systems provide constant power
21
Figure 19 a Control Panel
22
Figure 22 Showing an Installed Sub distribution Board
Figure 23 Looping Sockets and Light Cables through the Junction Boxes
23
3.4.1 INSTALLATION OF LIGHTS
Type of connection
The lights of the shops were connected in series controlled by one switch
ADVANTAGES OF SERIES CONNECTION
Series connection do not over heat easily
It minimises the amount of materials used
It makes components very dependent on other components
Procedure
A lamp holder (ceiling rolls) was placed on the ceiling with the junction box centrally located
and marks for fastening it made. These are drilled and plugged with wall plug
The lamp holder was then fastened in the place using screws
In the case of tubes, column width and tube holders are measured and marks made and drilled
at its start and end for fixing the holder such that it was perfectly centred between the walls
Using chalk line held at the start and end of the column a line is drawn on either side of the
line of the junction boxes to ease alignment of the tube.
Holes were drilled at the junction box points along the lines for fastening holders
Holes were drilled centrally in circular covers were black, red and green loops of wires are
passed through them at each junction box point. The holder was then fastened onto the ceiling
Red and black loops were partially stripped, fixed and fastened in the lamp holders
The live was terminated in common hole on the switch and load wire (phase) in the hole
marked L1 on the switch. Screw drivers were used to make these connections firm.
24
The earth wire was connected to the earthing point in the MK box.
Using screw drivers and screws, the switch was fixed on the wall.
Wires from the junction box to the MK box were stripped to a reasonable length using a wire
stripper or pliers.
The live (phase), neutral and earth wires were fixed in the points marked L, N, E respectively
on the socket.
Attach mounting clips to the underside of the energy meter by sliding them into the slots from
the inside
To prevent horizontal shifting across the DIN rail, we use two avo2 end stop clips
25
SCREW MOUNTING
Attach the mounting clips to the underside of the energy meter by sliding them into the slots
from the outside
Use tree screws to mount the energy meter to the inside of the enclosure
The environment: Outdoor meters need to be able to handle tougher conditions than indoor
meters
Meter size: The meter needs to align with size of the plumbing it will be installed on
Fixture unit demand: The amount of demand you’re asking of your lines. This will also affect
the meter size
PROCEDURE
With the circuit breakers switched off we located and recorded the CT number on the back of
the meter
Each sub metered room needed its own circuit connected from a separate circuit breaker on
the main distribution board
The sub meter was protected with an RCD and overload protection
We connected the live in and live out and neutral in and neutral out in their respective
positions
We made sure that connections are secure and replaced the anti-tamper cover
The main purpose of sub meter installation is to regulate power supply to the room’s sub
distribution. The sub distribution board powers the circuit in the apartment
26
Figure 26 Showing Installed meters on the Sub Distribution Board
3.4.3.3 BENEFITS OF SUBMETERING
Accurate billing based on usage; with sub metering the landlords are able to bill back utilities
to their residents based on their actual usage
27
CHAPTER FOUR
The responsibilities of contractors are to ensure that construction strategies are in place that
will minimize inconvenience, unnecessary disruption of work and unexpected costs
This policy applies to work performed in existing buildings, new constructions in existing
buildings or new constructions attached to existing buildings
The contractor roped off the areas of construction and signs to restrict access
How to use different kinds of tools used in electrical wiring and electrical Engineering
in general.
The important steps taken during maintenance and troubleshooting of circuits
Wiring the distribution board using the circuit breakers
Formation of circuits, drawing wires
The risk management skills
How to work with live circuits
28
CHAPTER FIVE
5.2 RECOMMENDATIONS
TO THE UNIVERSITY
To encourage students to fully and uninterruptedly dedicate themselves to IT, I would like to
suggest that industrial training should take place for a minimum of two months during the
semester holiday breaks
As preparation for industrial training, I also advise the university to go on the ground and
assist the students in obtaining internship placements by forming alliances with various
engineering firms
TO SPAN CONTRACTORS LIMITED
I would advise SPAN CONTRACTORS LIMITED to keep hiring interns from a variety of
academic backgrounds so that their business can continue to flourish as a result of the
knowledge that they impart to the young brains of the interns
5.3 CONCLUSION
A crucial component of an engineer’s professional development and career growth is
industrial training. IT has helped me in my quest to become an electrical engineer during the
4 weeks I had
The industrial training provided a platform for comparison and reverse engineering to
illustrate a point, which helped me to clear up a lot of doubts and ambiguities I had
concerning house hold and industrial installations
I have gained greater expertise in performing home and industrial installations.
Industrial training has taught me the true meaning of work which is practical work with a
flexible future
29
REFERENCES
i. BASIC ENGINEERING CIRCUIT ANALYSIS2008New York
ii. BASIC ENGINEERING CIRCUIT ANALYSIS2008New york
iii. Britanicca
iv. Britannica
v. britannicaBitannica
vi. Classfication of Electrical wires
vii. definition of industrial training
viii. Electrical Installation Notes1994UKConstruction Industry Training Board
ix. Electrical Installation Notes1994uk
x. Electrical Installation Notes1994UK
xi. Enviromental Health and Safety Policy and Procedure#20ehs20-contractors-minor3
xii. images
xiii. 2019Reasoned documentIndia
xiv. scienceDirect
xv. System of Electrical Wiring
xvi. The Spruce
xvii. UBTEBIndustrial training
30