PCC & Conc

This document provides a safe work method statement for a project involving PCC and concreting. It outlines the procedures, possible hazards, risk ratings, and control measures for preparatory works, manual handling of concrete materials, placing concrete mixture, and concrete mixing. Key hazards identified include slippery surfaces, sharp edges, heavy lifting, machinery fall, dust, and unguarded equipment. Control measures specify using personal protective equipment, barricading work areas, assessing safe lifting techniques, ensuring stable ground and machinery placement, trained operators, inspections, and equipment guarding. The project manager is responsible for ensuring these control measures are followed.

Uploaded by

prasanna ok
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
218 views4 pages

PCC & Conc

This document provides a safe work method statement for a project involving PCC and concreting. It outlines the procedures, possible hazards, risk ratings, and control measures for preparatory works, manual handling of concrete materials, placing concrete mixture, and concrete mixing. Key hazards identified include slippery surfaces, sharp edges, heavy lifting, machinery fall, dust, and unguarded equipment. Control measures specify using personal protective equipment, barricading work areas, assessing safe lifting techniques, ensuring stable ground and machinery placement, trained operators, inspections, and equipment guarding. The project manager is responsible for ensuring these control measures are followed.

Uploaded by

prasanna ok
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 4

Safe Work Method Statement

Project Name: OLA Cell technologies private limited DATE:16.07.2023  


Company Name

Address:

Office Contact No:

Project Manager Name Contact No:

ACIVITY : PCC & CONCRETING

The person who


Procedure (in steps) Possible Hazards Risk Control Measures will ensure this
Rating (Describe what action or procedure will be happens
(Break the job down into steps. Each step (Identify the hazards associated with (See taken to eliminate or minimize the risk of injury
should accomplish some major task and each step. Examine each to find below) or damage. Use the Hierarchy of Controls
be in logical sequence.) possibilities that could lead to an accident below as a guide
or potential harm arising.) 1. Eliminate the Hazard
2. Substitute the material or equipment
3. Isolate the hazard
4. Implement Engineering control
5. Implement Administrative control
6. PPE
 Preparatory works &  Use hand gloves while handling the
Manual handling of concrete  Slippery surface & tripping hazard. material.
material  Sharp edges/surfaces.  Barricade the working area.
 Length & weight of the material.  Assess the wait to be lifted.
 Loose grip, Slippery surface of material.  Clean up water, grease, oil or similar
substances of slippery surface of
material.Hold the material firmly while
handling

Document Name: Version Correct as at:


SWMS for brickwork and plastering 01 11.01.2023
Safe Work Method Statement
The person who
Procedure (in steps) Possible Hazards Risk Control Measures will ensure this
Rating (Describe what action or procedure will be happens
(Break the job down into steps. Each step (Identify the hazards associated with (See taken to eliminate or minimize the risk of injury
should accomplish some major task and each step. Examine each to find below) or damage. Use the Hierarchy of Controls
be in logical sequence.) possibilities that could lead to an accident below as a guide
or potential harm arising.) 1. Eliminate the Hazard
2. Substitute the material or equipment
3. Isolate the hazard
4. Implement Engineering control
5. Implement Administrative control
6. PPE
 Fall of machinery.  Ensured the levelled and firm ground.
 Fall of person. Collision or struck by  Ensure to place the machinery 2 Mtrs away
vehicle may cause injury. from work area.
 Provide safe access.
 Placing of concrete mixture
 Trained driver shall be engaged.
 PTW to be ensured before initiate the
work.

 Concrete Mixing  Person injury.  Ensure to cover the rotating parts with the
 Dust. guards.
 Unguarded gears, chains & rollers of  Ensure to stay away from self loading
mixtures. machine.
 Defective concrete bucket.  All gears ,chains & rollers of the mixtures
 Fall of material may cause injury. shall be properly guarded.
 Deflection in props or shuttering material.  Use mixture with hopper.
 Extreme weather condition.  Inspect the bucket prior to starting of
 Collapse of the form work may. Fall of concrete operation.
material  Ensure proper fastening & securing of
concrete pouring chute.
 Inspection of self loading machine.
 Ensure earthing of equipment’s and proper
functioning of electrical circuit before
commencement of work.

Document Name: Version Correct as at:


SWMS for brickwork and plastering 01 11.01.2023
Safe Work Method Statement
The person who
Procedure (in steps) Possible Hazards Risk Control Measures will ensure this
Rating (Describe what action or procedure will be happens
(Break the job down into steps. Each step (Identify the hazards associated with (See taken to eliminate or minimize the risk of injury
should accomplish some major task and each step. Examine each to find below) or damage. Use the Hierarchy of Controls
be in logical sequence.) possibilities that could lead to an accident below as a guide
or potential harm arising.) 1. Eliminate the Hazard
2. Substitute the material or equipment
3. Isolate the hazard
4. Implement Engineering control
5. Implement Administrative control
6. PPE
 Use of Vibrator  Vibration and noise.  Avoid prolonged exposure Insist on shift
 Splash of cement while use of vibrators. pattern.
 Discomfort, Hearing loss due to continues  Use hand gloves.
exposure. Contact with splash of cement  Use ear protection.
may lead to eye irritation.
 Curing & House keeping Slip and trip ,Fall of person due to wet surface &  Clean up water or other similar substances
fire hazard. to prevent slippery surface.
 Material to be stagnate at one place.
 Leakage of pipes is to be avoided.

 Concrete Pouring at Height.  Fall of person.  Area should be barricaded to prevent the
 Fall of material. manpower near to the workplace.
Columns Fall of personFall of material.  Ensure to use the all PPE's like helmet,
shoes, reflective jacket, hand gloves, nose
mask, goggles, safety full body harness,
etc.
 Scaffolding staging only used.

Document Name: Version Correct as at:


SWMS for brickwork and plastering 01 11.01.2023
Safe Work Method Statement

Personnel Summary
SUPERVISOR’S DETAILS
Supervisors Name & Qualifications: Name:
Experience:
Qualifications:

Prepared by: Signature: Date:


(Principle Contractor HSE Manager)

Reviewed by : Signature: Date:


(Principle Contractor Project Manager)

Reviewed by Signature Date:


(JLLSafety Manager)

Approved by
(JLL Project Manager) Signature Date:

Document Name: Version Correct as at:


SWMS for Brick work and plastering 01 11.01.2023