Pulang Bato 2nd Billing

Sundial Sustainable Solutions Inc. is requesting a 40% downpayment of 376,814.05 PHP from JE Hydro & Bio-Energy Corporation for work completed on the Pulang Bato Road Restoration project. Sundial has completed 70% of the project which had a total cost of 942,035.13 PHP according to their signed proposal. The letter provides billing details and notes terms regarding scheduling, cancellations, and changes that could impact the total project cost. Attached accomplishment reports provide additional details on progress.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
48 views2 pages

Pulang Bato 2nd Billing

Sundial Sustainable Solutions Inc. is requesting a 40% downpayment of 376,814.05 PHP from JE Hydro & Bio-Energy Corporation for work completed on the Pulang Bato Road Restoration project. Sundial has completed 70% of the project which had a total cost of 942,035.13 PHP according to their signed proposal. The letter provides billing details and notes terms regarding scheduling, cancellations, and changes that could impact the total project cost. Attached accomplishment reports provide additional details on progress.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

OP-137, One Paseo, Paseo Saturnino,

Banilad, Cebu City, Philippines


6000

Billing No: PBRR-0418-02

August 08, 2023

JOFFREY E. HAPITAN
Chairman
JE HYDRO & BIO-ENERGY CORPORATION
S. Diversion Road, Cagayan De Oro City, Misamis Oriental, Philippine 9000

Subject: Billing for Pulang Bato Road Restoration - 70% Completion

Dear Engr. Hapitan,

Please be informed that as of August 8, 2023, we are at 70% completed in Pulang Bato Road
Restoration, based on the signed proposal with a total project cost of (942,035.13) Nine Hundred Forty-Two
Thousand Thirty-Five & 13/100 pesos only. We would like to request a 40% Downpayment amounting to
(₱376,814.05) Three hundred seventy-six thousand eight hundred fourteen and 05/100 pesos only.

Pulang Bato Road Restoration 942,035.13


Progress Accomplishment 100%
Progress Billing 942,035.13
Less: 1st Billing (282,610.54)
Less: 2nd Billing (376,814.05)
THIS BILLING 376,814.05
Less: 1st Billing (282,610.54)

Attached are the pertinent accomplishment reports.


(Please note that project schedule is weather permitting and does not include non-working holidays. For abrupt cancellations, 20% of
project cost covering mobilization and planning will be non-refundable plus material cost already delivered on site. Sudden work schedule
changes made by client may incur additional labor costs. This project cost is subject to change if specifications are also changed pending
approval. )

Yours truly,

KARL ANDREW A. GAJUDO


President
SUNDIAL SUSTAINABLE SOLUTIONS INC.

APPROVED BY: _____________________


JOFFREY E. HAPITAN
JE HYDRO & BIO-ENERGY CORP.

August 08, 2023

Kindly prepare check payable to SUNDIAL SUSTAINABLE SOLUTIONS INC.


Thank you for your business!
OP-137, One Paseo, Paseo Saturnino,
Banilad, Cebu City, Philippines
6000

Accomplishment Report- Pulang Bato Road Restoration

Kindly prepare check payable to SUNDIAL SUSTAINABLE SOLUTIONS INC.


Thank you for your business!