OP-137, One Paseo, Paseo Saturnino,
Banilad, Cebu City, Philippines
6000
Billing No: PBRR-0418-02
August 08, 2023
JOFFREY E. HAPITAN
Chairman
JE HYDRO & BIO-ENERGY CORPORATION
S. Diversion Road, Cagayan De Oro City, Misamis Oriental, Philippine 9000
Subject: Billing for Pulang Bato Road Restoration - 70% Completion
Dear Engr. Hapitan,
Please be informed that as of August 8, 2023, we are at 70% completed in Pulang Bato Road
Restoration, based on the signed proposal with a total project cost of (942,035.13) Nine Hundred Forty-Two
Thousand Thirty-Five & 13/100 pesos only. We would like to request a 40% Downpayment amounting to
(₱376,814.05) Three hundred seventy-six thousand eight hundred fourteen and 05/100 pesos only.
Pulang Bato Road Restoration 942,035.13
Progress Accomplishment 100%
Progress Billing 942,035.13
Less: 1st Billing (282,610.54)
Less: 2nd Billing (376,814.05)
THIS BILLING 376,814.05
Less: 1st Billing (282,610.54)
Attached are the pertinent accomplishment reports.
(Please note that project schedule is weather permitting and does not include non-working holidays. For abrupt cancellations, 20% of
project cost covering mobilization and planning will be non-refundable plus material cost already delivered on site. Sudden work schedule
changes made by client may incur additional labor costs. This project cost is subject to change if specifications are also changed pending
approval. )
Yours truly,
KARL ANDREW A. GAJUDO
President
SUNDIAL SUSTAINABLE SOLUTIONS INC.
APPROVED BY: _____________________
JOFFREY E. HAPITAN
JE HYDRO & BIO-ENERGY CORP.
August 08, 2023
Kindly prepare check payable to SUNDIAL SUSTAINABLE SOLUTIONS INC.
Thank you for your business!
OP-137, One Paseo, Paseo Saturnino,
Banilad, Cebu City, Philippines
6000
Accomplishment Report- Pulang Bato Road Restoration
Kindly prepare check payable to SUNDIAL SUSTAINABLE SOLUTIONS INC.
Thank you for your business!