HGP Insulation Procedure
HGP Insulation Procedure
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
Technical Discipline 1 2 3 4
HSE Dept. 1 2 3 4
QA/QC Dept. 1 2 3 4
                     Designation
                                                                          QA/QC              QHSE/Projects
                                                      QC Engineer
                                                                         Manager               Manager
                                           Revision
    REV        Status          Date                    Issued By       Checked By             Approved by
                                            Memo
                                    PROJECT TITLE
                    HAWIYAH GAS PLAN (HGP) EXPANSION PROJECT
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
TABLE OF CONTENTS
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
        This specification covers the minimum mandatory requirement governing the design and
        insulation of industrial insulation activity for piping and equipment for HAWIYAH GAS
        PLANT EXPANSION PROJECT
  2.0        DEFINATION:
        Company           Saudi Aramco
        Contractor        The agreement entered between Saipem and RBH for the project
        Subcontractor     Altrad RB Hilton SA ltd
        IH        Hot Insulation
        PP        Personnel protection
        IC        Cold Insulation
        ET        Electrical Tracing
        ST        Steam Tracing
        SJ        Steam Jacketed
        AI        Acoustic Insulation
  3.0        REFERENCES:
        The following reference specifications and standards are to be regarded as integral part of this
        project specification:
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
PIP INSC 1000 Cold Service Insulation Materials and Installation Specification
PIP INSH 1000 Hot Service Insulation Materials and Installation Specification
      PIP INSR 1000 Installation of Flexible, Removable/Reusable Insulation Covers for Hot Insulation
      Service
ISO 15665 Acoustics – Acoustic Insulation for Pipes, Valves and Flanges (First Edition-2003)
      ASTM A167 Specification for Stainless and Heat Resisting Chromium Nickel Steel Plate, Sheet
      and Strip
ASTM B209 Specification for Aluminium and Aluminium-Alloy Sheet and Plate
ASTM C449 Specification for Mineral Fiber Hydraulic-Setting Thermal Insulating Cement
      ASTM C450 Fabrication of Thermal Insulating Fitting Covers for NPS Piping, and Vessel
                                       PROJECT TITLE
                      HAWIYAH GAS PLAN (HGP) EXPANSION PROJECT
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
Lagging
        ASTM C534 Specification for Preformed Flexible Elastomeric Cellular Thermal Insulation in
        Sheet and Tubular Form
ASTM C552 Specification of Cellular Glass Block and Pipe Thermal Insulation
ASTM C592 Specification for Mineral Fiber Block and Blanket-Type Pipe Insulation
ASTM C612 Specification for Mineral Fiber Block and Board Thermal Insulation
        ASTM C692 Method for Evaluating the Influence of Thermal Insulations on the External Stress
        Corrosion Cracking Tendency of Austenitic Stainless Steel
ASTM C764 Specification for Mineral Fiber Loose Fill Thermal Insulation
        ASTM C795 Specification for Thermal Insulation for Use in Contact with Austenitic Stainless
        Steel
        ASTM C871 Methods for Chemical Analysis of Thermal Insulation Materials for Leachable
        Chloride, Fluoride, Silicate and Sodium Ions
        ASTM C929 Practice for Handling, Transporting, Shipping, Storage, Receiving, and Application
        of Thermal Insulating Materials to be used over Austenitic Stainless Steel
ASTM E84 Test Method for Surface Burning Characteristics of Building Materials
4.0 DESIGN
        Insulation codes shall be used on P&ID, data sheets, piping isometrics, and other project
        documents the following codes shall apply
        Piping and equipment shall be insulated for energy conservation, in hot service, when the
        normal operating fluid temperature is above average annual temperature and heat loss
        limitation is required.
                                     PROJECT TITLE
                    HAWIYAH GAS PLAN (HGP) EXPANSION PROJECT
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
      Piping and equipment shall be insulated for cold conservation (CC) when the normal
      operating fluid temperature is below than yearly average daily max. temperature (99°F /
      37.2°C) and heat gain limitation is needed. Insulation systems that operate below the
      ambient dew-point temperature must be protected from the inward permeation of moisture.
      The symbols used on drawings and P&IDs to indicate the class of acoustic insulation
      required shall be comprehensive of the code AC (Acoustic Control) insulation followed by
      the second character to identify the class of sound absorption defined by ISO 15665:2003,
      namely AC1 (Acoustic Control Class A), AC2 (Acoustic Control Class B) or AC3 (Acoustic
      Control Class C). In case of class C, acoustic insulation shall cover all piping components
      (valve and flanges included).
      Acoustic insulation shall be comply with noise control level requirements mentioned in
      SAES-A-105 and SAEP-371.
      Acoustic insulation shall be designed in accordance with the criteria and material
      characteristics prescribed by ISO 15665:2003 reference standard.
      All accessible piping and equipment operating at temperature above 60°C / 140°F (PP) not
      provided with other type of insulation, shall be guarded for personnel protection purpose.
      Personnel Protection in hot service with service temperature between 60°C / 140°F and
      175°C / 347°F shall be covered by Guard Mesh and all details are described.
      Insulation (or guard mesh) for personnel protection shall extend within 910mm horizontally
      and to a height of 2133mm above any area that is routinely used as work space or access
      way by operational personnel.
      Personnel protection in hot service is provided by means of metal shields (or metal guards)
      and it shall be designated with the insulation code (class) MS. Metal shields (or guards) for
      personnel protection will be selected only for piping in intermittent service and designated
      equipment, when thermal or acoustic insulation would not otherwise be required.
      Metal shields (or guards) for personnel protection should be selected for piping and
      equipment in continuous service temperatures between 60 and 175°C, or in cyclic service
                                       PROJECT TITLE
                      HAWIYAH GAS PLAN (HGP) EXPANSION PROJECT
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
        crossing such service temperature range, on metal substrates subjected to high risk of CUI
        (Corrosion Under Insulation), when thermal or acoustic insulation would not be required.
        Metal shields (or guards) will be selected on items where personnel protection is to be
        provided but the items is designated to dissipate heat.
        Metal shields (or metal guards) for personnel protection purpose shall be provided to
        910mm horizontally and to a height of 2.13m above any area that is routinely used as
        workspace or access way (e.g. from periphery of platforms, walkways or ladders, etc.).
        Lines that are identified Electrical Traced (ET) or Steam Traced (ST) on drawings and on
        P&IDs shall be insulated to minimize heat loss and to avoid process disruption or
        solidification.
  5.0      REPONSIBILITIES
    5.1 Insulation Superintendent/Supervisor
        Ensure full compliance by all insulation foremen, insulation erectors, and labors regarding
        the execution of the work in accordance with manufacturer recommendation and project
        requirements and specifications. Confirm the availability of all material, tools, equipment and
        competent persons to perform the work. Ensure compliance by all labors, equipment
        operators and craftsmen associated with the execution of insulation works to the
        requirements of this procedure, project quality control procedure, relevant drawings, safety
        procedure, and project specifications Secure all necessary work permits.
        Conduct inspection in accordance with procedure and QCIP. Monitor daily insulating
        activities and verify strict compliance to the project requirements, specifications, and
        manufacturer recommendations. Prepare daily observation records and final acceptance
        documentation where required.
        Monitor the work areas of unsafe conditions. Ensure that all safety requirements are
        adequately addressed, and the work is being carried out safely in accordance with HSSE
        safety procedures. Ensure that material safety data sheets are available at site.
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
         manufacturer's instructions shall be brought to the attention of the Purchaser for resolution.
    6.2 Authorization to proceed with application of insulation shall be obtained in writing from the
        Purchaser.
    6.3 Unless otherwise specified, insulation shall not be applied until completion of the following
        has been verified:
           6.3.1 Required hydrostatic and/or pneumatic pressure testing
           6.3.2 Application of required substrate protective coating systems, including touch-up of
                 previously applied coatings
           6.3.3 Installation and testing of required tracing systems
           6.3.4 Cleaning of surfaces that are to receive insulation
    6.4 If required by the Purchaser, application of insulation may proceed before pressure testing
        is complete, provided that all welds and flanged and threaded connections are left
        exposed until the pressure testing is complete. Temporary terminations of installed
        insulation shall be adequately protected at all times.
    6.5 Where insulation has been specified on piping or equipment flanges that are to be hot
        bolted, the insulation shall not be installed until hot bolting has been accomplished and the
        flange determined to be leak-free.
    6.6 Unless otherwise specified, all insulation materials shall be installed in a single layer when
        the total thickness does not exceed 3 in. (75 mm).
    6.7 When applying single layer insulation, other than hinged pipe covering, the circumferential
        butt joints of each half section shall be staggered.
    6.8 Thicknesses 3-1/2 in. (90 mm) and greater shall be applied in multi-layers with staggered
        joints. Consideration shall be given to multi-layer insulation for operating temperatures
        over 600°F (316°C).
    6.9 When applying double or multi-layer insulation all longitudinal and circumferential joints
        shall be staggered.
    6.10 Each layer of double layer or multi-layer insulation shall be held in place separately.
    6.11 At final inspection, all insulation is smooth and free from cracks, voids, gaps and
       depression greater than 3mm should be refitted.
        • Mineral wool pipe section (ASTM C547), Density = 128 Kg/m3 and Mineral wool blanket
           with GI wire mesh (ASTM C592) type II or III, Density = 128 Kg/m3 shall be used for hot
           insulation.
        • Insulation thickness for piping and equipment in hot service shall be as specified in
           specification BE744722 or the applicable isometric drawing.
                                     PROJECT TITLE
                    HAWIYAH GAS PLAN (HGP) EXPANSION PROJECT
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
     • Insulation on piping up to NPS 6” shall be insulated with preformed pipe cover and piping
        with NPS > 6” shall be insulated with Mineral wool blanket with wire mesh.
     • Insulation layering, unless otherwise specified by the Purchaser, for piping and equipment
        shall be applied as a multiple layer for operating temperature above 300°C.
     • Circumferential butt joints of each half section shall be staggered in single layer insulation
        and all longitudinal and circumferential joints shall be staggered in multi-layer insulation.
     • Insulation on piping with 12” NPS shall be secured with 1.3mm Type SS304 tie wire, cut
        ends of tie wire shall be embedded into the insulation.
     • Insulation on piping and equipment diameter above 12” NPS and up to 24” NPS shall be
        secured with 13mm wide by 0.5mm thick 304 type stainless steel bands and wing seals.
     • Insulation for piping and equipment above 24” NPS shall be secured with 19mm wide by
        0.5mm thick 304 type stainless steel bands and wing seals.
     • Vertical pipe insulation shall be supported by a pipe insulation support located directly
        above all elbow, flanges or flanged valves
     • Maximum support ring spacing shall be 5m. for piping with temperatures below 315 deg C
        and 3.65m above 315 deg C.
• Flange and Valves shall be insulated with removable / reusable insulation covers.
     • Clearance (Bolt length + 25MM) must be made for removal of flange bolt without disturbing
        the fixed insulation.
       • Aluminum jacketing ASTM B209, ALLOY 3003M H-14 with polysurlyn moisture barrier
         should be used as jacketing material in non-fire hazardous area.
       • Except in Fire Classified Areas for which cladding shall be aluminized steel only.
                                    PROJECT TITLE
                    HAWIYAH GAS PLAN (HGP) EXPANSION PROJECT
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
       • 0.6mm thk stucco embossed sheet with 1 1/4" corrugation for vertical equipment 48" and
         larger diameter.
• 0.6mm thk stucco embossed sheet for horizontal equipment 48" and larger diameter.
• 0.5mm thk stucco embossed sheet for vessel less than 48" and all piping
• 0.5mm thk smooth and plain sheet for head segment, fittings and valve covers
       • Aluminized Steel jacketing ASTM A463 Type 1 should be used as jacketing material for Fire
         hazardous area.
       • 0.45mm thk Aluminised jacket shall be used for piping & equipment upto 36” and 0.6mm thk
         jacketing shall be used for equipment above 36”
       • Corrugated aluminised jacketing shall be used for vertical equipment’s with diameter 48”
         and above.
       • Metal jacketing for equipment shall be overlapped by 50mm both longitudinally and
         circumferentially.
       • Metal jacketing for outer diameter up to 24” NPS shall be secured with 13mm wide by
         0.5mm thick 304 type stainless steel bands and wing seals.
       • Metal jacketing above 24” NPS shall be secured with 19mm wide by 0.5mm thick 304 type
         stainless steel bands and wing seals.
       • Securement of insulation over the heads of horizontal equipment and top head heads of
         vertical equipment, using a floating ring made from 6mm diameter stainless steel rod. The
         floating ring shall be placed in the center of the head and the girth rings made from two
         bands shall be installed on the shell at approximately 150 mm from the tangent line of the
         head. Band shall be run radially from the floating ring to the girth rings. The bands shall be
         spaced at 300 mm maximum centers. Band shall be stainless steel type 304, 19 mm wide x
         0.5 mm thick with matching seals.
       • Metal jacketing over vertical pipe and vertical equipment shall be supported by S-clips
         spaced at approximately 24" (610mm) or minimum of two (2) S-clips per sheet. These S & J
         clips fabricated from 19 mm banding.
       • The metal jacketing shall be secured with stainless steel bands using J-clips at 6ft (1.8m)
         centers to prevent the bands from sliding down.
                                     PROJECT TITLE
                    HAWIYAH GAS PLAN (HGP) EXPANSION PROJECT
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
       • Bands securing equipment insulation weather jacketing shall incorporate 4-inch (100-mm)
         long, compression spring in accordance with Table 2 of PIP INSH 1000.
       • All metal joints and protrusion must be caulked and or sealed for possible ingress of
         moisture or water. For vertical vessel sealant, shall be applied only for longitudinal overlap
         of metal cladding.
• Exposed edges of metal jacketing shall be bent or rolled to eliminate sharp edges.
       • Piping and equipment, which is subject to either hydrostatic test or alternative tests shall not
         be insulated until such tests, have been successfully completed.
• Contractor shall identify the areas to be insulated by issuing work release document.
       • Insulation thickness for piping and equipment in cold service shall be as specified in
         specification BE-744722 or the applicable isometric drawing.
       • The insulation material on piping / equipment shall be applied in single layer for insulation
         thickness upto 75mm. insulation thickness greater than 90mm shall be in multi-layer.
• Single layer insulation, the circumferential butt joints of each section shall be staggered.
       • All insulation shall be smooth and free from cracks, voids, gaps and depressions greater
         than 3mm. all crack, voids, gaps and depression in the insulation greater than 3mm shall be
         refitted not filled.
       • The circumferential and longitudinal joints of each section when applying insulation shall be
         butted and staggered.
• Insulation on piping with 12” NPS shall be secured with 25mm filament tape.
       • Insulation on piping and equipment diameter above 12” NPS and upto 24” NPS shall be
         secured with 13mm wide by 0.5mm thick 304 type stainless steel bands and wing seals.
       • Insulation for piping and equipment above 24” NPS shall be secured with 19mm wide by
         0.5mm thick 304 type stainless steel bands and wing seals.
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
       • All circumferential and longitudinal insulation joints shall be sealed with sealant. Inner layer
         shall be installed without any joint sealer. All joints of single layer and only outer layer of
         multi-layer insulation shall be applied with joint sealer.
       • Vapor stops that seal the insulation to the pipe or equipment shall be installed at all
         insulation terminations. (applicable for Cold insulation CODE: CC)
       • Installed insulation shall be applied with temporary protection at the end of shift if rain or
         other forms of atmospheric moisture can damage the insulation.
       • Contraction joints shall also be provided in uninterrupted straight pipe insulation when the
         run length is equal to or greater than half of the following maximum allowed distance.
       • Insulation contraction joints shall be installed in all layers of multiple layer insulation and
         shall be staggered between layers. Outer contraction joint shall be covered with a flexible
         vapor seal / butyl tape.
       • Membrane type vapor barrier sheet shall be installed for strainght and shell sections without
         fish mouthing gaps or folds and shall have a minimum 50-mm (2-in) overlap at all joints.
       • Vapor barrier mastic and reinforcing fabric shall be applied as vapor barrier for compound
         shape (e.g. flanges, valves, head etc)
       • Aluminium jacketing ASTM B209, ALLOY 3003M H-14 with polysurlyn moisture barrier
         should be used as jacketing material in non-fire hazardous area.
                                    PROJECT TITLE
                    HAWIYAH GAS PLAN (HGP) EXPANSION PROJECT
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
• 0.6mm thk stucco embossed sheet for horizontal equipment 48" and larger diameter.
• 0.5mm thk stucco embossed sheet for vessel less than 48" and all piping
• 0.5mm thk smooth and plain sheet for head segment, fittings and valve covers
       • Aluminized Steel jacketing ASTM A463 Type 1 should be used as jacketing material for fire
         hazardous area.
       • 0.45mm thk Aluminised jacket shall be used for piping & equipment upto 36” and 0.6mm thk
         jacketing shall be used for equipment above 36”
• The weather proof jacketing shall be applied over the vapor barrier.
       • The jacketing on piping and equipment shall be applied with a minimum 50mm overlap on
         both longitudinally and circumferentially.
       • The weatherproof jacketing for OD up to 24” NPS shall be held in place with 13mm x 0.5mm
         thick SS 304 type bands. For OD larger than 24” NPS shall be held in place with 19mm x
         0.5mm thick band. The spacing between bands shall be 300mm.
       • Jacket bandings on vessels over 8ft (2.4m) in diameter shall have 4-inch (100mm) stainless
         steel compression spring. Spring shall be located every 30ft (9.1m) of band length.
• Exposed edges of metal jacketing shall be machine-bent or rolled to eliminate sharp edges.
       • Metal jacketing over vertical pipe and vertical equipment shall be supported by S-clips
         spaced at approximately 24" (610mm) or minimum of two (2) S-clips per sheet.
       • The metal jacketing shall be secured with stainless steel bands using J-clips at 6ft (1.8m)
         centers fastened to the jacket to prevent the bands from sliding down.
       • Securement of insulation over the heads of horizontal equipment and top head heads of
         vertical equipment, using a floating ring made from 6mm diameter stainless steel rod. The
         floating ring shall be placed in the center of the head and the girth rings made from two
         bands shall be installed on the shell at approximately 150 mm from the tangent line of the
         head. Band shall be run radially from the floating ring to the girth rings. The bands shall be
         spaced at 300 mm maximum centers. Band shall be stainless steel type 304, 19 mm wide x
         0.5 mm thick with matching seals.
       • Metal joints and protrusions shall be caulked with sealant wherever there is chance of water
         ingress.
                                    PROJECT TITLE
                    HAWIYAH GAS PLAN (HGP) EXPANSION PROJECT
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
       • All accessible piping and equipment operating at temperature above 60°C / 140°F (PP) not
         provided with other type of insulation, shall be guarded for personnel protection purpose.
       • Personnel Protection in hot service with service temperature between 60°C / 140°F and
         175°C / 347°F shall be covered by Guard Mesh.
       • Personnel protection shall be provided within normal working areas or access ways in an
         extent of 0.9m horizontally from periphery of platform, walkway or platforms and a height of
         2.1m above the grade or platform.
       • Removable plugs, collars and inspection windows shall be provided to permit “on-site”
         nondestructive ultrasonic thickness inspections. Number, location and dimensions for
         inspection windows shall comply with Company standard requirements.
                                     PROJECT TITLE
                    HAWIYAH GAS PLAN (HGP) EXPANSION PROJECT
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
       • Plugs, collars and windows shall be vapor tight, UV resistant and such that they can be
         operated and reclosed.
       • Plugs, collars and inspection windows shall not be located in flat areas subject to standing
         water.
                           Material                                       Layer
              Armacell Arma-check R                 Flexible polymeric barrier, 2mm thick
              Armacell Armafoam Barrier             Mass loaded vinyl acoustic barrier.
              Armacell Armafoam Sound 240           Open cell FEF insulation.
              Armacell LT/Armaflex                  Closed cell FEF insulation.
              Armacheck Mastic                      Sealant for armacheck R
              Armaflex HT 625                       Adhesive to bond FEF insulation
              Cellular glass                        ASTM C552
       • All joints in FEF insulation layers shall be adhesive bonded/sealed. Joints between layers
         shall be staggered.
       • Insulation termination, including those at flanges and valves, shall be sealed with a layer
         (disc) of closed cell (thermal) FEF between the pipe and inside surface of closed cell
         (thermal) FEF outer layer.
       • On all lines designated to receive sound and thermal control insulation, the piping
         expansion joints (bellows) if a part of the line, shall also be insulated for sound and thermal
         control.
• Sound and thermal control insulation shall completely cover Pipe trunnions.
       • Insulation layering shall be as indicated in Insulation thickness Table 5,6 & 7 of spec
         BE744722.
                                    PROJECT TITLE
                    HAWIYAH GAS PLAN (HGP) EXPANSION PROJECT
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
       • Client shall identify the areas to be insulated by issuing work release document with
         applicable drawings.
       • Piping erection drawings or assembly drawings will define the limit for extension of acoustic
         insulation.
• Valve and flanges installed online caded AC1 and AC2 are not to be insulated.
       • Pipe support clamps that extends outside the pipe insulation shall be fully insulated,
         including insulation terminated on the hanger rod.
       • Insulation shall be applied with tightly butted joints, using contact adhesive on all butt joint
         surfaces.
       • Projections through the jacketing shall be caulked with a liberal application of silicone
         sealant, jacketing shall not make direct contact with projections.
       • Jacketing and film barrier shall be retained by stainless steel bands. Screws shall not be
         used as jacketing securement.
       • Silicone sealant shall be applied between overlapped jacketing and film barrier surfaces to
         provide continuous seal between laps.
       • Example of minimum unitary mass (kg/m2) for jacketing to comply with class A, B or C shall
         be as indicated below.
                                    PROJECT TITLE
                    HAWIYAH GAS PLAN (HGP) EXPANSION PROJECT
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
        • The assistance of heavy equipment for loading and unloading of insulation material /
           accessories on site shall be taken care by Client.
        • Mineral Fibre preformed pipe sections in accordance with ASTM C547, type II, Density:
           128kg/m3.
        • Mineral Fibre blanket as per ASTM C592, type II, Density: 128kg/m3.
                                    PROJECT TITLE
                    HAWIYAH GAS PLAN (HGP) EXPANSION PROJECT
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
     • Metal sealant: All metal joints and protrusions must be caulked and sealed for possible
        ingress of moisture or water. RTV silicone sealant, aluminum or grey color to be used as
        metal sealant.
     • Weatherproof Jacketing (Applicable for Hot & Cold Insulation as ARAMCO standard
        drawing)
     • 0.6 mm thick stucco Embossed jacketing with 1 ¼” Corrugation ASTM B209, Alloy 3003
        H-14, with polysurlyn moisture barrier should be used as jacketing material for vertical
        equipment’s.
     • 0.6 mm thick stucco Embossed jacketing ASTM B209, Alloy 3003 H-14, with polysurlyn
        moisture barrier should be used as jacketing material for horizontal equipment’s.
     • 0.5 mm thick stucco Embossed jacketing ASTM B209, Alloy 3003 H-14, with polysurlyn
        moisture barrier should be used as jacketing material for Vessel less than 48” and all
        piping.
     • 0.5mm thk smooth and plain sheet ASTM B209, Alloy 3003 H-14, with polysurlyn moisture
        barrier for head segment, fittings and valve covers
     • 0.45mm thk Aluminised jacket ASTM A463 Type 1 shall be used for piping & equipment
        upto 36” and 0.6mm thk jacketing shall be used for equipment above 36”
• Expansion Springs on external jacketing shall be compression type spring, 100mm long.
• Float ring shall be made from 6mm diameter Carbon steel rod.
• Support ring shall be fabricated from 30x3mm thk GI & SS flat bar.
     • The main insulation materials Cellular glass to be used for cold insulation in accordance
        with ASTM C552 (Density 115 kg/m3).
                                     PROJECT TITLE
                      HAWIYAH GAS PLAN (HGP) EXPANSION PROJECT
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
• Joint Sealant
Properties:
• Vapor Stop
         Vapor stops that seal the insulation to the pipe or equipment shall be installed at all
         insulation terminations.
Properties:
• Glass cloth:
• Vapor barrier:
     • Metal sealant: All metal joints and protrusions must be caulked and sealed for possible
        ingress of moisture or water. RTV silicone sealant, aluminum or grey color to be used as
        metal sealant.
     • Expansion Springs: Flat spring for insulation & compression type spring for jacketing,
        100mm long.
• Float ring shall be made from 6mm diameter Carbon steel rod.
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
     • Handling & Storage of material shall be in accordance with the requirements of the project
        specification.
     • Materials shall be stored in a way that it is protected from exposure to extreme weather
        e.g. Heat, rain, dirt, etc.
     • All material shall also be protected from getting wet and getting in contact with chemicals
        or any other flammable substances during storage.
     • The insulation materials shall be kept on pallet / off the ground surface (direct contact of
        insulation material to ground surface shall be avoided).
CUSTOMER: SAUDI ARAMCO OIL COMPANY – SAUDI ARAMCO (IK) DOC NO. H99-ZA-E-0002711
   14.1 Unless otherwise specified, insulation that becomes wet shall be removed and replaced
        with dry insulation, and the wet insulation shall be discarded.
   14.2 Damaged insulation shall be replaced if the nature of the damage will adversely affect
        the thermal performance of the system. Any disputes regarding the need for replacement of
        insulation shall be referred to the Purchaser for resolution.
16.0 ATTACHMENTS