Detailed Inventory Survey: 3.1 General Information
Detailed Inventory Survey: 3.1 General Information
Selected National Highways in the Republic of the Philippines Inventory Survey and Risk Assessment
CHAPTER 3
The Detailed Inventory Survey (DIS) is used to inspect in detail the present condition of slopes
selected under the Preliminary Inventory Survey (PIS), and to plan the appropriate countermeasures.
The DIS is comprised of risk assessment, planning of countermeasures, and indicative feasibility
assessment, using the Inventory Format Sheets 3, 4 and 5. The outputs of the DIS are the detailed
record of the present condition of road slope disaster sites, the countermeasure plan for each disaster
site and indicative feasibility assessment of the proposed countermeasure.
Start
- Review of the PIS data
- Review of geological condition
Preparatory Works - Road Map of the DIS sections
Sheet 6
Collection of the disaster
records
Sketches
- Survey of cause(s) of disaster
Sheet 3 - Geometry Survey
Field Inspection - Prediction of magnitude of potential
disaster
District Engineer’s
- Basic design planning of countermeasure
comments
- Estimation of countermeasure work
quantities
Sheet 4 - Cost Estimation
Countermeasure Planning
- Input of disaster frequency and
magnitude
- Calculation of annual losses
Sheet 5 - Calculation of feasibility indicators of
Indicative Feasibility Assessment countermeasures
The required tools for each survey team are shown in Table 3.2.
The sketches on Sheet 3 are used as the basis for the countermeasure plan on Sheet 4, where an outline
of the present conditions of DIS slope. Sheet 3 sketches should be drawn clearly for scanning and
inserted as a digital image in Sheet 3 in Excel format. The key points, items required and methods of
sketches are as follows:
(a) The location of the disaster and the road, i.e. evaluate the influence of the disaster on the road;
(b) The original (before the current collapse/slide) surface line of the road slope and road structure;
(c) Water traces, geology of the road slopes, and any other factors that may trigger the disaster;
(e) The phenomena which may indicate the cause of the disaster;
(h) Existing structures to consider in the construction of countermeasure works (e.g. telephone
lines, etc.).
A legend for the sketch for Sheet 3 has been prepared for the inventory survey. Some of the
symbols were selected from the Design Guidelines Criteria and Standards Volume-I (DPWH),
while some have been created in consideration of actual conditions of the national highway. The
legend consists of structures, topography and geology. Geological symbols are limited to clay (or
clayey soil), sand (or sandy soil), gravel (or gravelly soil), weathered rock, fractured rock and
fresh rock to simplify the sketch.
The sketch is to be drawn clearly and highlighted by clearly visible black lines since it will be
shown as a monochrome image in the RSMS. If the sketch is drawn using pencil, it should be
retraced on a new sheet or the drawing highlighted using a black pen without any dirt on the sheet,
so that it can be scanned clearly. Scan the original sketch of Sheet 3 and paste it on the digital file
for Sheet 3. An example of a sketch is shown in Figures 3.5 and 3.6.
Start
Sheet 4
180m
60m
Clayey soil
60°
Spring water
Fresh rock
Phot-1
Phot-3 Phot-2
Grouted Rip Rap
Finish the sketch:
- Record dimensions of the objects.
Clayey soil
Weathered rock 17m 25m - Record information regarding the
0.8m 6m existing structures, geometry, geology
Fresh rock and the road slope conditions.
1.2m
1m - Record the location on photographs.
Drain
Structure
CL Traffic Lane
Center Line
Em.
Catch box Embankment Shoto Crete
Shotcret Slope Works
TELEPHONE
10m
Dimension Line Extension Line
70
o Natural slope 45
o Cutting Slope
Collapsed slope o
Callaped
/ Scarp
slope 30 Knick
Knickline/ point
line Overhang
/ Score 70o over
Shoreline Overflow 45
o
Gradient
Geology
Gravel Freshrock
R
Structure Structure of
30
o Sructure of
of bedding Figure Structure
30
o 4 Legend of crack
Sructure offor Use in Sheet30o3 Sructure of
fracture zone crack fracture zone
fracture zone
100m 80m
60m
40m
20m
0m
Step 1: Discuss and plan the countermeasures in the field in accordance with the concepts shown
in Table 3.5.
Step 2: Plan the countermeasures with the participation of the District Engineer, draw its basic
plan, and prepare a rough cost estimate in Sheet 4. The planning engineers determine the effect of
the countermeasure and encode the reduction ratio of RCDp on Sheet 5.
The engineer-in-charge of the DIS can select any type of countermeasure that he chooses. When
planning for countermeasures, traditional/common methods used in the Philippines are to be applied as
far as practicable. However, if road slope conditions are determined to be too difficult to prevent
disasters by using traditional methods, new methods should be considered and selected from the
countermeasure options shown in the following sections (Refer to the detailed information on
countermeasures in Guide III Design of Countermeasures). Proposed countermeasures for each
disaster type are shown in Appendix 2 with the typical/standard structures.
Attention should be paid to the target location of the drainage, configuration, diameter, angle,
length, outlet protection, and connection to surface drainage (channel).
The location of the causeway, where debris flow or surface water will be allowed to pass, is
important. If water is to be allowed to pass over the road surface, the surface should have thick
pavement that is resistant to scouring from the flow. In case of a culvert (under drain), attention
should be paid to length, gradient, structure and cross-section size. Large under-drains (2 to 3 m
deep) with collecting walls are suitable for ground with low permeability.
5 – 10m 1:1.5
Hard rock
5 – 10m 1:1.2
1:0.8 Weathered rock
Fractured rock
5 – 10m 1:1.0
Clayey/silty soil
1:1.5 Sandy soil
5 – 10m Gravelly soil
1:1.2
Gradient
Character of Soil or Bedrock Height(m)
(Vertical : Horizontal)
Hard rock 1:0.3 - 1:0.8
0 – 10m 1:0.6 - 1:0.8
Weathered rock 20 – 30m 1:1.0 - 1:1.2
Fractured rock
More than 30m 1:1.2 – 1:1.5
Less than 10m 1:0.8 - 1:1.0
Clayey/Silty soil Less than 5m 1:1.0 - 1:1.2
5 – 10m 1:1.2 - 1:1.5
Sandy soil
Less than 5m 1:1.0 - 1:1.2
Gravelly soil 5 - 10m 1:1.2 - 1:1.5
Note: Without slope stability works such as ground anchoring, the gradient is the same as shown in the
guideline on road earth works (Japan Road Association, supervised by the Ministry of Land Infrastructure
Transportation of Japan)
Figure 3.7 Appropriate Gradients for Cuts
(3) Fills
Counterweight filling should be planned at the toe of the target disaster area. It is important to use
permeable materials for filling. In general, under drains and drainage mats should be provided so
that no free groundwater (unconfined ground water) level forms in the fill.
Reinforced filling is a new technology for the mitigation of road slope disasters, particularly on a
steep and deep valley side with limited space for construction. This has the same function as a
retaining wall.
Sandbag walls are newly developed geo-textile reinforced earth walls in Japan. Sandbag walls are
generally designed as a retaining wall to retain soil mass on steep slopes or in a restricted
right-of-way situation. Its typical application includes the restoration and stabilization of road slips,
highway retaining walls on steep slopes, embankment walls for temporary or permanent road
widening, and so on.
(5) Structures
(a) Slope Works
Slope works mainly include pitching work, shotcrete and crib works. These works are primarily
used to protect against surface weathering and erosion, and in some cases, to control small-scale
rock falls.
Pitching works are commonly used on slopes gentler than 1V:1.0H. When the slope gradient is
greater than 1V:1.0H, the methods used are concrete retaining walls, stone masonry retaining walls
and block masonry retaining walls. Pitching works are applied to prevent surface weathering,
scouring, stripping and erosion and, in some cases, to prevent small-scale soil slope collapse.
Crib works are commonly used on steep slopes of highly weathered or heavily jointed rocks
accompanied with abundant springs, especially where falls cannot be fixed with shotcrete works.
Crib works are chiefly applied (a) to prevent surface weathering, scouring and erosion and, in
some cases, (b) to control both rock fall and small-scale slope failure.
In principle, retaining wall design includes the analysis of (a) sliding, (b) overturning, typically at
the toe of walls, (c) bearing capacity of the foundation ground, and (d) overall stability (Stability
analysis must not consider only the stability of the wall itself, but also of the overall slope of which
the wall may be a part of).
Catch fences are designed to protect road traffic from rock fall damage, but differ from rock nets in
that they are installed near the road to be protected. Rock nets are used to cover slopes that have a
potential for rock fall in order to protect road traffic from rock fall damage.
Compared with other countermeasures, ground anchors are costly but reliable. Recently, this
method has been applied increasingly to cut slopes at toe of landslides. Compared with rock bolts
and soil nailing, ground anchors have a relatively large resistance to sliding force and are therefore
used to stabilize relatively large-scale slope failures. Ground anchors are intended to prevent
landslides through the tensile strength of the high tensile strength steel wire or bars installed across
the slip surface.
Similar to ground anchors; steel pipe piles are costly but reliable. The work is recommended
especially when the ground is firm and has sufficient resistance against landslide mass. Moreover,
steel pipe piles are generally used when the slope of a landslide area or sliding surface is relatively
gentle or a potential landslide has a large scale. Steel pipe piles are intended to prevent landslides
through the doweling action between the landslide mass and stable ground by applying the shear
strength of the steep piles to the sliding surface or by using the wedge effect of steel piles.
Rock sheds are reinforced concrete or steel structures covering a road. They are very costly and
should only be planned and designed in areas of extreme rock fall hazard. It is applied to reduce
road disasters due to rock fall or rock mass failure by absorbing the impact force of a falling rock
mass or shifting the movement direction of the rock mass failure and rock fall.
Check dams are implemented (a) to prevent erosion and toe failure of potentially unstable slopes;
(b) to prevent and eliminate damage from the debris flow itself; and (c) to improve the stability of
a slope through sedimentation behind the dam.
Wave-absorbing works are a common countermeasure for coastal erosion in Japan. These works
are very costly and should only be planned and designed in areas where other works cannot meet
the degree of safety required.
Primary consideration in the procedure for the selection is the treatment of problems with water for the
DIS section. The major causative factors for a disaster are surface water and sub-surface water from
heavy rains. The next consideration is vegetation or earth works, which are generally simpler methods
than structures. The third consideration is choosing an appropriate structure that is compatible with the
permanent countermeasures for Alternative I. The final consideration is re-alignment, only this
requires different judgment criteria for re-opening or identifying of a detour/ practical route.
A flow chart for the selection of the different disaster types is shown in Appendix 3.
Start
Countermeasure
- Surface Water Drainage
- Sub-surface Blind Drainage
Would treatment of - Horizontal Drilling
surface or ground water be
YES - Flow Structure
effective?
Soil Works
- Pre-Splitting
NO - Rock Fall Foot Protection
- Banking (Embankment)
- Reinforced Embankment
- EPS Embankment
- Sand Packed in Cracks
YES Planting Work
Would soil works or planting - Coconut Fiber Nets
works be effective? - Vegetation Spraying
- Mangrove Planting
NO
- Rip Rap
- Gabions
- Grouted Rip Rap
- Gabion Walls
- Crib Walls
- Shotcrete
- Cast-in-Place Cribs
Would structures be - Concrete Retaining Walls
YES - Stone Masonry Retaining Walls
effective? - Gabion Retaining Walls
- Bolting
- Steel Piling
- Ground Anchoring
NO - Rock Nets
- Catch Fences (Rock fall Protection)
- Rock Sheds
- Concrete Check Dams
- Gabion Check Dams
- Wooden Stockades
- Grouted Rip Rap (Coastal)
- Reinforced Concrete Retaining Walls
(Coastal)
- Rock Armor Protection (Coastal)
YES
Is re-alignment the only Re-alignment
feasible solution?
Bypass
End
Figure 3.8 General Flow of Countermeasure Selection
Step 1
Trace the outline of the DIS section from Sheet 3 to Sheet 4. The outline will consist of the road
structure, dimensions of the disaster such as information related to the countermeasure plan.
Step 2 Draw the countermeasure plans on Sheet 4, that is a plan and a section for each
alternative countermeasure. The plans are to be drawn clearly and highlighted with highly visible
black lines since it will be shown as a monochrome image in the RSMS. If the sketch is drawn
using pencil, it should be highlighted using a black pen without any dirt on the sheet for scanning.
Step 3 Estimate the construction quantities of structure or potential collapse volume for the
unit cost estimation. Record the quantities on Sheet 4 with a pencil or a pen.
Step 5 Paste the scanned plans of the countermeasures on the digital file of Sheet 4 and
encode the countermeasure works, units, quantities and unit prices into the appropriate cells. The
costs of the countermeasures are calculated automatically.
If a countermeasure selected is not among the standard types, rough cost estimates should be done
for the plan by the inspectors.
Start
Paste the scanned plans and encode the costs on the digital file of Sheet 4
Sheet 5
Clayey soil
Weathered 17m 25m
0.8m6m
Fresh rock
1.2m
1m
Drain
170m
1.0m
(2) Pay attention at the origin and destination point side of the slope.
(4) Pay attention to both the valley and mountain side slopes.
(The possibility of construction should be evaluated.)
Calculate
automatically
Water gutter
SC3.2 Drainage Catch Basin ea 6,210 1 80 x 80 x 80 cm
SC4.1 Cast-in-Place Crib m2 2,270 1 Excluding riprap
SC4.2 Crib Vegetation m2 330 1
Spraying
SC5 Concrete Retaining Wall m 17,440 1
SC6 Stone Masonry Retaining m 13,000 1
Wall
SC7 Gabion Retaining Wall m 1,366 2 3 meter high wall
RC1 Pre-Splitting m3 1,570 1 Scaling & trimming of
rock
RC2 Rock Fall Foot Protection ea 5,720 1
RC3 Shotcrete m2 1,970 1 100 mm thick
Rock Slope Collapse
m3
River
Step 1
Step 2 Step 3
20.0m
Cutting
26.0m
Road(co)
Drainage
10.0m
Cast-In-Place
Crib
7.0m
Step 4
Cutting (1.63m2)
Road(co)
Drainage
Cast-In-Place Crib
Step 5
11.0m
70 °
Cutting(10.5m2)
4- 3 Cost estimates
0
0
0
Total Cost 6,081,450
Note
Numerical value or terms should be inputted.
Numerical value is automatically inputted.
Figure
Figure 3.13
3.13 Example
Example of of Sheet
Sheet 4CountermeasurePlan
4 Countermeasure Plan
(Wright-Taft
(Wright-Taft Road: 858
Road: 858 + 250:
+ 250: Alternative-I)
Alternative-II)
The indicative feasibility assessment, which is the preliminary estimate of the economic
viability of specific countermeasures identified to mitigate RCDs, is carried out in Inventory
Sheet 5 (Sheet 5).
3.4.1 General
In Sheet 5, the estimates of disaster frequency and magnitude, annual losses, risk reduction ratio
due to implementation of a specific countermeasure and cost/benefit analysis of the
countermeasures are undertaken.
The equations used for the indicative feasibility assessment differ per disaster type, which
requires a different sheet for each type and results in the preparation of seven different sheets
(Sheet 5-1 to Sheet 5-7).
1-2) Accumulation Volume on the Road per RCD/Length of Road Closure Site
(Accumulation Volume on the Road per RCD for Sheet 5-1: Disaster type - Soil Slope
Collapse and Sheet 5-2: Disaster type - Rock Slope Collapse)
The “accumulation volume on the road per RCD” is computed by multiplying the “ratio of
accumulation” to collapsible materials and the estimated volume of collapsible materials
per RCD”, as shown in the following equation:
where:
(Length of Road Closure Site for Sheet 5-3: Disaster type - Landslide and Sheet 5-4: Disaster
type - Road Slip; Sheet 5-5: Disaster type - Debris Flow; Sheet 5-6: Disaster type - River
Erosion; and Sheet 5-7: Disaster type - Coastal Erosion)
The ‘length of the road closure site’ is estimated based on the current range of slope
deformation, referencing to past closure examples in nearby areas and similar slope
conditions.
The method for estimating the dimensions of the collapsible material/area is selected from
the following and as shown in Figure 3.14
Max : The maximum dimensions of the collapsible material area are predicted.
Average: The average dimensions of the collapsible material area are predicted.
No input: In case the dimensions cannot be predicted such as for rock fall phenomena.
If ‘Max’ is selected: “a”, the coefficient for the volume estimation is empirically set at
a = 0.7
If ‘Average’ is selected: “a”, the coefficient for volume estimation is set at a = 1.0
Plan Profile
where
In case max values (for length, width, and depth) are used, a = 0.7
In case average values (for length, width, and depth) are used, a = 1.0
The length, width and depth dimensions are estimated based on the current range of slope
deformation and referring to past collapse examples in nearby areas and similar slope
conditions.
When these dimensions cannot be predicted, for example in the case of rock fall, the
‘volume of collapsible materials’ is estimated using Figure 3.15, which shows the
relationship between the collapsible volume and the slope gradient per slope height
category.
25
H > = 90m
Volume of Collapsible Material per road length (m3/ m)
H = Height of slope
20
15
10
5
60 m > H >=30 m
0 30m > H
G >= 60° 60° > 40° > 20° > G
G >= 40° G >= 20°
Category of Slope Gradient: G
This chart was formulated using the data from the PIS questionnaire results as of 2006 and
disaster observations in Benguet and Ifugao provinces in September 2006.
When the ratio of the accumulated volume of materials to the collapsible materials cannot
be calculated, it is estimated by using Figure 3.16. This was formulated based on
experience and is the relationship between the ratio of accumulated materials and
collapsible materials and the slope gradient category for each ‘distance from the road to
the toe of the mountainside slope.
1.0
1m<D
D : Distance from toe of
0.8 mountainside slope
Ratio of accumulation materials to collapsible materials
0.6
0.4 3m>=D>1m
0.2
5 m > = D >3 m
D> 5 m
0.0
G >= 60° 60° > 40° > 20° > G
G >= 40° G >= 20°
Category of Slope Gradient: G
This chart was formulated based on the PIS questionnaire results in 2006 and
disaster observations in Benguet and Ifugao provinces in September 2006.
Figure 3.16 Chart for Estimating the ‘Ratio of Accumulated Volume to Collapsible
Volume’
NIPPON KOEI CO., LTD. 3-31 June 2007
OYO INTERNATIONAL CORPORATION
The Study on Risk Management for Sediment-Related Disaster on Final Report Guide II
Selected National Highways in the Republic of the Philippines Inventory Survey and Risk Assessment
u= j + m + t (equation 3.3)
where:
The following equations have been formulated using data of reopening costs of a specific
Philippine national road and should be used for reference only.
(for Sheet 5-1: Disaster type - Soil Slope Collapse and Sheet 5-2: Disaster type - Rock Slope
Collapse)
where:
The value of ‘h’ and ‘i’ in equation 3.5 should be set by referring to local experience and
actual results obtained, though this assumes that the engineer of the DEO would be
responsible for preparing the estimate.
Just as a reference, a chart showing the relationship between accumulation volume and
reopening cost (data from questionnaire survey for RCDs on national highway in the
Philippines from 1996 to 2005) is shown in Figure 3.17. From the correlation analysis of
this data, ”h” of equation 3.5=540 pesos and ”i” =10,000 pesos.
1,000,000
RC: Reopening Cost per RCD
RC = 540 g + 10,000
Correlation Coefficient = 0.65
800,000
600,000
(
400,000
200,000
0
0 500 1,000 1,500
i = fixed cost for reopening per RCD (pesos per RCD) = 10,000
(for Sheet 5-3: Disaster type –Landslide; Sheet 5-4: Disaster type - Road Slip; Sheet 5-5:
Disaster type - Debris Flow; Sheet 5-6: Disaster type - River Erosion and Sheet 5-7: Disaster
type - Coastal Erosion)
where:
h = reopening cost per length of road closure site (excluding fixed cost) (pesos
per m)
The value of ‘h’ and ‘i’ in equation 3.7 should be set by referring to local experience and
actual results obtained, though this assumes that the engineer of the DEO would be
responsible for preparing the estimate.
Just for reference, a chart showing the relationship between the Length of the Road Closure
Site (LRC) and the Reopening cost per RCD (RC) on national highways in the Philippines
(data of questionnaire survey for RCDs from 1996 to 2005) is shown in Figure 3.18. From
the correlation analysis of this data, ”h” and ”i” of equation 3.7 are obtained and shown in
Table 3.8.
Disaster Type h= reopening cost per i = fixed cost for reopening per Correlation
length of road closure site RCD coefficient
(excluding fixed cost) [pesos per RCD]
[pesos per m]
LS: Landslide 4,800 8,800 0.22
Landslide
2000000
1500000
1000000
500000
RC = 4,800 x LRC + 88,000
Correlation coefficient = 0.22
0
0 50 100 150 200 250
Road Slip
1,000,000
800,000
600,000
400,000
200,000
RC = 4600 x LRC + 170,000
0 Correlation coefficient = 0.36
0 10 20 30 40 50 60 70 80 90 100
Debris Flow
150,000
RC = 1,200 x LRC + 12,000
Correlation coefficient = 0.36
100,000
50,000
0
0 10 20 30 40 50 60
5,000,000
RC = 1,600 x LRC + 890,000
4,000,000 Correlation coefficient = 0.25
3,000,000
2,000,000
1,000,000
0
0 200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000
Figure 3.18 Charts for Estimating Reopening Cost per Length of Road Closure
(Data from questionnaire survey for RCDs on national highway in the Philippines from 1996 to
2005)
where:
The estimate of the average number of deaths per RCD is given below:
1
ADB-ASEAN Regional Road Safety Program Accident Costing Report: The Cost of Road Traffic
Accidents in the Philippines, Manila, 2004.
When an alternative route to the closed survey road exists, the equation to estimate the annual
detour cost is as follows:
where:
n = Length of survey road (from entry to exit point of detour road to avoid the
road closure site on the survey road [see Figure 3.19]) (km)
o = Length of detour road (from entry to exit point of detour road to avoid road
closure site on survey road [see Figure 3.19])) (km)
Survey Road
Figure 3.19 Reference Points for Measuring Lengths of Survey and Detour Roads
2-3-1) Lengths of survey and detour roads are measured by the DEO
The reference points are the vehicle entry/exit points on the detour road to avoid the RCD
site.
Table 3.10 Example of AADT and Percent Share of Each Vehicle Type
(Baguio-Bontoc Rd)
2-3-3) Number of Predicted Closure Days of the Whole Width of the Road on the Survey
Site per RCD
The number of closure days of the whole width of the survey road due to a disaster is
predicted and the corresponding cell filled out. When traffic on one lane is open in the
prospective disaster site, the closure day is equal to 0.
Figures 3.20 to Figure 3.21 can be used as reference for the prediction of road closure days
due to disaster.
80
SC
70 RC
LS
RS
60 DF
RE
Number of RCD (full lane)
50 CE
40
30
20
10
0
0 days ~0.5d ~1d ~3d ~7d ~15d ~30d 30d~
LS
o : Nos. of closure days predicted of
the whole width of the road (days)
70
LS: Landslides
60
o = 0.0631*LRC
50
40
30
20
10
0
0 20 40 60 80 100 120 140 160
Length of road closure (LRC : m)
RS
DF
o : Nos. of closure days predicted of
the whole width of the road (days)
70
DF: Debris Flow
60
50
40
30
o = 0.0081*LRC + 2.3799
20
10
0
0 100 200 300 400 500 600
Length of road closure (LRC : m)
RE
o : Nos. of closure days predicted of
the whole width of the road (days)
70
RE: River Erosion
60
50
40
30
o = 0.1264*LRC
20
10
0
0 20 40 60 80 100 120
Length of road closure (LRC : m)
Figure 3.21 Charts for Estimating the Number of Road Closure Days by Length of
Road Closure Alignment for various RCDs
(Based on available data on RCDs on national highways from 1996-2006)
2-3-4) Average Vehicle Operating Cost per AADT unit/km on the Survey and Detour
Roads
The Average Vehicle Operating Cost (AVOC) per AADT unit/km on the Survey and Detour
Roads should be input based on the typical condition of the survey and detour roads, i.e., the
closed road is paved and in fair condition, while the detour road is unpaved and in poor
condition. The methodology for calculating the AVOC uses the data given in Tables 3.4.6 and
3.4.7.
The DPWH regularly updates its estimate of vehicle operating costs used in the evaluation of
road projects. This is applicable in the analysis of detour cost and the most recent estimate (as
of October 2006) given in Table 3.11
Table 3.11 Estimated Vehicle Operating Cost (VOC) per Road Surface Type and
Condition per km (VOC/km) (pesos)
SURFACE Vehicle Running Fixed Running Time VOC
Type Cost Cost + Fixed Cost Running +
Type Condition Fixed + Time
PAVED V.BAD CAR/VAN 10.99 0.53 11.52 1.73 13.25
JEEPNEY 7.58 2.60 10.18 2.56 12.74
BUS 14.21 4.76 18.97 14.76 33.73
TRUCK 18.28 5.59 23.87 0.00 23.87
MCYCLE 1.38 0.32 1.70 2.28 3.98
OTHERS 1.68 5.64 7.32 1.29 8.60
BAD CAR/VAN 9.62 0.40 10.02 1.30 11.31
JEEPNEY 6.64 1.95 8.58 1.92 10.51
BUS 11.97 3.57 15.54 11.07 26.61
TRUCK 15.39 4.19 19.58 0.00 19.58
MCYCLE 1.20 0.24 1.44 1.71 3.15
OTHERS 1.47 2.82 4.29 0.64 4.93
FAIR CAR/VAN 8.24 0.27 8.51 0.87 9.37
JEEPNEY 5.69 1.30 6.99 1.28 8.27
BUS 9.72 2.34 12.07 7.27 19.33
TRUCK 12.51 2.75 15.26 0.00 15.26
MCYCLE 1.03 0.10 1.13 0.65 1.81
OTHERS 1.26 1.61 2.87 0.37 3.24
(equation 3.15)
where:
(equation 3.16)
where:
It is the “discount rate r” where the present value of the benefit stream is equal to the
y=20
Σy=0[(xy-vy)/(1+r)y] = 0 (equation 3.17)
where:
x0= 0, x1, x2 ……….. x20 = x (x: decrease in annual loss due to countermeasure)
The proposed countermeasure is viable from the economic viewpoint if the estimated BCR >
1, ENPV > 0 at the 15% discount rate; and the computed EIRR > 15%.
Table 3.12 illustrates the estimation of the BCR, ENPV and EIRR.
Table 3.12 Estimates of BCR, ENPV and EIRR using Microsoft Excel
Assumptions:
Discount rate: Opportunity cost of capital =15%
V0 =Cost of countermeasure with 20 yeas maintenance = PHP 10 million
x =Annual benefits (reduction in losses due to RCD) = PHP 1,250,000
Economic life of countermeasure = 20 years
where: