Ufc 4 440 01 2014 c1
Ufc 4 440 01 2014 c1
1 April 2014
Change 1, 1 April 2019
WAREHOUSES AND
STORAGE FACILITIES
Any copyrighted material included in this UFC is identified at its point of use.
Use of the copyrighted material apart from this UFC must have the permission of the
copyright holder.
This UFC supersedes UFC 4-440-01A, dated March 1, 2005 and UFC 4-442-01N,
dated January 16, 2004.
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
FOREWORD
The Unified Facilities Criteria (UFC) system is prescribed by MIL-STD 3007 and provides
planning, design, construction, sustainment, restoration, and modernization criteria, and applies
to the Military Departments, the Defense Agencies, and the DoD Field Activities in accordance
with USD (AT&L) Memorandum dated 29 May 2002. UFC will be used for all DoD projects and
work for other customers where appropriate. All construction outside of the United States is
also governed by Status of Forces Agreements (SOFA), Host Nation Funded Construction
Agreements (HNFA), and in some instances, Bilateral Infrastructure Agreements (BIA.)
Therefore, the acquisition team must ensure compliance with the most stringent of the UFC, the
SOFA, the HNFA, and the BIA, as applicable.
UFC are living documents and will be periodically reviewed, updated, and made available to
users as part of the Services’ responsibility for providing technical criteria for military
construction. Headquarters, U.S. Army Corps of Engineers (HQUSACE), Naval Facilities
Engineering Command (NAVFAC), and the Air Force Civil Engineer Center (AFCEC) are
responsible for administration of the UFC system. Defense agencies should contact the
preparing service for document interpretation and improvements. Technical content of UFC is
the responsibility of the cognizant DoD working group. Recommended changes with supporting
rationale should be sent to the respective service proponent office by the following electronic
form: Criteria Change Request. The form is also accessible from the Internet sites listed below.
UFC are effective upon issuance and are distributed only in electronic media from the following
source:
• Whole Building Design Guide web site http://dod.wbdg.org/.
Hard copies of UFC printed from electronic media should be checked against the current
electronic version prior to use to ensure that they are current.
AUTHORIZED BY:
Superseding: UFC 4-440-01A Storage Depots and UFC 4-442-01N Design; Covered
Storage.
Impact:
• The result of these changes is a document which can more practically be used
as part of a construction contract and is more easily understood by the users,
more relevant to current practice and is properly coordinated with other
Government requirements documents.
Non-Unified Items:
• Differing policies for Navy and Marine Corps, Army, and Air Force appear in
paragraphs entitled “Controlled Humidity Warehouse”, “Flammable / Hazardous
Storage Within Other Storage Facilities”, and “Flammable / Hazardous Materials
Storage”.
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
TABLE OF CONTENTS
CHAPTER 1 INTRODUCTION ....................................................................................... 1
1-1 PURPOSE AND SCOPE. .......................................................................... 1
1-2 APPLICABILITY. ....................................................................................... 1
1-2.1 Conflicts in Criteria ................................................................................. 1
1-3 GENERAL BUILDING REQUIREMENTS ................................................. 1
1-4 TYPES OF STORAGE FACILITIES .......................................................... 2
1-4.1 General Purpose Warehouse ................................................................ 2
1-4.2 Humidity Controlled Warehouse ............................................................ 2
1-4.3 Shed Storage ......................................................................................... 3
1-4.4 Hazardous Materials Storage within Other Storage Facilities ................ 3
1-5 EXCLUSIONS ........................................................................................... 3
1-5.1 Cold Storage .......................................................................................... 3
1-5.2 Liquid Storage........................................................................................ 4
1-5.3 Ammunition Storage .............................................................................. 4
1-5.4 Open Storage ........................................................................................ 4
1-5.5 Hazardous Waste Storage ..................................................................... 4
1-6 APPENDICES ........................................................................................... 4
CHAPTER 2 PLANNING AND LAYOUT ........................................................................ 5
2-1 PROJECT INITIATION AND PLANNING.................................................. 5
2-1.1 Project Analysis and Engineering Phase ............................................... 5
2-2 GEOGRAPHIC PLANNING ....................................................................... 5
2-3 STORAGE / HANDLING SYSTEM ........................................................... 6
2-3.1 Design Parameters ................................................................................ 6
2-3.2 Procedures ............................................................................................ 6
2-3.3 Material Handling Equipment ............................................................... 11
2-3.4 Storage Equipment .............................................................................. 11
2-4 MATERIAL HANDLING SYSTEMS CONSIDERATIONS ....................... 13
2-4.1 Receiving Shipping Operations............................................................ 13
2-4.2 Order Picking Operations..................................................................... 13
2-5 SUPPORT AREAS .................................................................................. 14
2-5.1 Supervisory Offices.............................................................................. 15
2-5.2 Receiving Office................................................................................... 15
i
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
2-5.3 Shipping Office .................................................................................... 17
2-5.4 Rest Rooms ......................................................................................... 18
2-5.5 Employee Services .............................................................................. 18
2-5.6 Crating Operations ............................................................................... 18
2-5.7 Packing/Packaging Operations ............................................................ 18
2-5.8 Battery Charging Area ......................................................................... 18
2-6 PARKING ................................................................................................ 19
2-7 TRAFFIC FLOW ...................................................................................... 19
2-8 SAFETY................................................................................................... 19
CHAPTER 3 GENERAL DESIGN CRITERIA ............................................................... 21
3-1 GENERAL DESIGN FACTORS .............................................................. 21
3-1.1 Material Movement .............................................................................. 21
3-1.2 Expansion Capability ........................................................................... 21
3-1.3 Flexible Design .................................................................................... 21
3-1.4 Requirements of Specific Buildings ..................................................... 21
3-2 BUILDING SHAPE AND PROPORTIONS .............................................. 23
3-2.1 Travel Distance .................................................................................... 23
3-2.2 Irregular Shapes .................................................................................. 23
3-2.3 Height .................................................................................................. 23
3-2.4 Area ..................................................................................................... 23
3-3 BUILDING SPACING .............................................................................. 23
3-3.1 Rail Side .............................................................................................. 23
3-3.2 Truck Side............................................................................................ 23
3-3.3 Warehouses In-Line ............................................................................. 24
3-3.4 Hazardous Materials Facilities ............................................................. 24
3-4 DOCKING FACILITIES ........................................................................... 24
3-4.1 Truck Dock........................................................................................... 27
3-4.2 Rail Docks............................................................................................ 33
3-4.3 Ramp Access....................................................................................... 34
3-4.4 Dock Levelers ...................................................................................... 34
3-4.5 Dock and Platform Weather Protection ................................................ 35
3-4.6 Safety Equipment ................................................................................ 37
3-5 STRUCTURAL ........................................................................................ 39
ii
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-5.1 Ground Floors ...................................................................................... 39
3-5.2 Superstructure ..................................................................................... 39
3-6 EXTERIOR DESIGN ................................................................................ 43
3-6.1 Surface Treatment ............................................................................... 43
3-6.2 Roofing Systems.................................................................................. 43
3-6.3 Exterior Walls....................................................................................... 44
3-6.4 Dock Doors .......................................................................................... 44
3-6.5 Fire Doors ............................................................................................ 45
3-6.6 Windows .............................................................................................. 45
3-6.7 Doors and Hardware ............................................................................ 45
3-6.8 Signage................................................................................................ 45
3-7 INTERIOR DESIGN ................................................................................. 46
3-7.1 Interior Walls ........................................................................................ 46
3-7.2 Doors and Windows ............................................................................. 46
3-7.3 Signage................................................................................................ 47
3-7.4 Warehouse Storage Area .................................................................... 47
3-7.5 Shops and Storage Rooms .................................................................. 50
3-7.6 Administration and Office Spaces ........................................................ 50
3-7.7 Toilet and Locker Rooms ..................................................................... 51
3-7.8 Corridors and Stairs ............................................................................. 51
3-7.9 Support Spaces ................................................................................... 52
3-7.10 Battery Charging and Handling Operations ......................................... 52
3-7.11 Pallet Racks ......................................................................................... 57
3-7.12 Aisle Dimensions ................................................................................. 64
3-7.13 Building Bay Dimensions ..................................................................... 66
3-7.14 Telecommunication Systems ............................................................... 70
3-7.15 Alarm Systems..................................................................................... 70
3-7.16 Casework ............................................................................................. 70
3-7.17 Elevators and Lifts ............................................................................... 71
3-7.18 Furniture Considerations...................................................................... 71
3-7.19 Equipment Considerations ................................................................... 71
3-8 PEST CONTROL ..................................................................................... 71
3-9 ACCESSIBILITY FOR THE DISABLED.................................................. 72
iii
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-10 ACOUSTICS ............................................................................................ 72
3-11 CONVEYING SYSTEMS ......................................................................... 72
3-11.1 Overhead Bridge Cranes ..................................................................... 72
3-12 MOTOR AND CONTROLS...................................................................... 73
3-13 PLUMBING .............................................................................................. 73
3-13.1 General ................................................................................................ 73
3-13.2 Compressed Air ................................................................................... 73
3-14 ENVIRONMENTAL CONTROL ............................................................... 74
3-14.1 General ................................................................................................ 74
3-14.2 Heating ................................................................................................ 74
3-14.3 Ventilation ............................................................................................ 75
3-14.4 Humidity Control .................................................................................. 76
3-14.5 Air Conditioning ................................................................................... 76
3-14.6 Energy Conservation ........................................................................... 76
3-14.7 Insulation ............................................................................................. 76
3-14.8 Mechanical Equipment Requirements ................................................. 76
3-14.9 Noise and Vibration Control ................................................................. 77
3-15 FIRE PROTECTION ................................................................................ 77
3-15.1 Fire Protection Sprinkler Systems........................................................ 77
3-15.2 Fire Alarm Systems ............................................................................. 78
3-15.3 Smoke Detectors ................................................................................. 78
3-16 ELECTRICAL .......................................................................................... 80
3-16.1 Power................................................................................................... 80
3-16.2 Emergency Power ............................................................................... 80
3-16.3 Lighting ................................................................................................ 80
3-16.4 Receptacles ......................................................................................... 81
3-16.5 Battery Chargers.................................................................................. 81
3-16.6 Lightning Protection ............................................................................. 81
3-17 CIVIL........................................................................................................ 81
3-17.1 Siting .................................................................................................... 81
3-17.2 Utilities ................................................................................................. 82
3-17.3 Utility Metering ..................................................................................... 82
3-18 SUSTAINABLE DESIGN......................................................................... 82
iv
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
CHAPTER 4 HAZARDOUS MATERIALS STORAGE GENERAL DESIGN CRITERIA
...................................................................................................................................... 83
4-1 GENERAL ............................................................................................... 83
4-2 HAZARDOUS MATERIALS STORAGE ................................................. 83
4-2.1 Compliance Standards ........................................................................ 83
4-2.2 Hazardous Materials Storage .............................................................. 83
4-2.3 Design Criteria ..................................................................................... 84
4-2.4 Storage Requirements ......................................................................... 84
4-2.5 Material Handling Equipment ............................................................... 84
4-3 SEGREGATION OF MATERIALS .......................................................... 85
4-3.1 Categories of Materials ........................................................................ 85
4-3.2 Segregation Requirements .................................................................. 86
4-3.3 Combined Shed Storage...................................................................... 88
4-4 SPILL CONTAINMENT AND CONTROL ................................................ 88
4-4.1 Exterior Containment ........................................................................... 88
4-4.2 Interior Containment ............................................................................ 88
4-4.3 Dikes .................................................................................................... 89
4-4.4 Floor Trenches and Capture Systems ................................................. 89
4-4.5 Recessed Floor.................................................................................... 92
4-4.6 Containment ........................................................................................ 92
4-4.7 Drainage .............................................................................................. 92
APPENDIX A REFERENCES ....................................................................................... 93
APPENDIX B BEST PRACTICES ................................................................................ 99
B-1 GENERAL ............................................................................................... 99
B-2 WHOLE BUILDING DESIGN GUIDE ...................................................... 99
B-3 FACITILTY DESIGN ................................................................................ 99
APPENDIX C GLOSSARY ......................................................................................... 101
v
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
FIGURES
TABLES
Table 2-1 Administrative and Supervisory Offices and Support Area Space
Requirements ......................................................................................................... 14
Table 3-1 Special requirements for Warehouse Types.......................................... 22
Table 3-2 Truck and Rail Vehicle and Dock Heights ............................................. 28
Table 3-3 Dock Leveler Life (Years) Based on Impact Loading............................. 35
Table 3-4 Recommended Door and Portal Sizes .................................................. 44
Table 3-5 Building Bay Size Comparison .............................................................. 68
Table 3-6 Required Clear Building Heights ........................................................... 69
vi
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
CHAPTER 1 INTRODUCTION
This Unified Facilities Criteria (UFC), UFC 4-440-01, contains criteria for planners,
engineers, and architects on the planning, engineering, and design of Department of
Defense (DoD) storage facilities. The information in this UFC applies to the design of all
new construction projects, to include additions, alterations, and renovation projects in
the continental Unites States (CONUS) and outside the continental US (OCONUS).
Alteration and renovation projects must update existing facilities to meet the guidance
and criteria contained in this UFC within budgetary constraints. This is supplementary
guidance to be used in conjunction with Facility Requirements Documents (FRD),
Facility Requirements Supplements (FRS), Intrusion Detection Systems Engineering
Plans (IDSEP), Installation Appearance Plan (IAP), and other DoD material for the
planning and construction of DoD storage facilities and to support the preparation of DD
1391 project documentation.
1-2 APPLICABILITY.
This UFC will be used for planning individual projects, preparing engineering
documentation, and preparing contractual documents for construction. It is intended to
present the basis for standardization of practices and identify a common baseline to be
used during the planning of new facilities or the modification of existing facilities.
Where conflicts appear between the general criteria contained in the Whole Building
Design Guide (WBDG) website and the guidance in this document, the guidance in this
UFC governs.
Comply with UFC 1-200-01, General Building Requirements. UFC 1-200-01 provides
applicability of model building codes and government unique criteria for typical design
disciplines and building systems, as well as for accessibility, antiterrorism, security, high
performance and sustainability requirements, and safety. Use this FC in addition to UFC
1-200-01 and the UFCs and government criteria referenced therein.
1
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
1-4 TYPES OF STORAGE FACILITIES
The criteria in this UFC cover the design requirements for warehouse facilities; General
Purpose Warehouse, Controlled Humidity Warehouse, \1\ Hazardous Materials Storage,
/1/ and Shed Storage, or the combination of these storage facility types. These criteria
address the factors which affect the functional effectiveness of warehouse facilities.
Included in these factors are siting, system selection, facility layout, area, storage
height, life-cycle costs, energy efficiency, and internal details. Since modern storage
facilities are integrated operations in which the structure and materials handling/ storage
equipment function as a system, coordination and integration of equipment and
structure requirements is essential to proper operation of the system. The more
common facility types following:
2
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
1-4.3 Shed Storage
A shed is a roofed structure without complete side or end walls. Sheds are typically
used for storage of gas cylinders, drummed Petroleum/Oil/Lubricant (POL), vehicles,
unfinished lumber, and other construction material. In areas where it is impractical to
use shed space for the storage of materials because of weather conditions, storage
requirements must be included as warehouse space and complete justification must be
submitted. Sheds storing hazardous materials are subject to special design
requirements and must comply with criteria in Chapter 4 of this UFC.
Use DoD Real Property Classification System (RPCS); Category Codes 441-10 through
441-40 facility types.
1-5 EXCLUSIONS
Design of the following types of storage facilities is not covered by this UFC:
3
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
1-5.2 Liquid Storage
Bulk tanks and associated equipment for liquid fuel storage and storage of liquids other
than water, fuel tanks, and propellant tanks are not included. Refer to UFC 3-460-01,
Design: Petroleum Fuel Facilities.
Magazines, specialized warehouses, tanks, and open pads for storage of ammunition,
inert ammunition components, liquid propellants, and weapon related batteries are not
included.
Facilities which are used for storage of hazardous waste or are otherwise subjected to
the requirements of 40 Code of Federal Regulations (CFR) Protection of Environment,
Part 264 Standards for Owners and Operators of Hazardous Waste Treatment, Storage,
and Disposal Facilities \1\/1/are not included.
1-6 APPENDICES
Appendix A contains a list of references used in this document. The publication date of
the code or standard is not included in this document. In general, the latest available
issuance of the reference is used.
4
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
CHAPTER 2 PLANNING AND LAYOUT
This UFC provides information required for preparation of DD Form 1391, which initiates
project development. This includes information about functions, space allowances,
overall building size, site evaluation, and special factors to consider in developing
overall scope and cost estimates. It provides data and criteria needed at each stage of
planning, project engineering, and the design process.
After a project is initiated, it is analyzed and defined. During the Project Analysis stage,
the project team meets to define the project so as to have a clear understanding of the
project goals and objectives. The Customer, Design Agent, and Architect / Engineer
(A/E) team then develops the project documentation based on an analysis of unique
customer needs, requirements, established criteria, and site and environmental
constraints. Information gathered provides the basis for defining the preliminary design
and supports the project engineering phase, parametric cost estimating (PCE), and
programming process. Information required includes space planning, site design,
selection of the appropriate plan, water supply, and building design, elements and
concepts. Unique local requirements concerning building program and design criteria
are included in the PCE.
Functional concept planning for new facilities or modernization of existing facilities must
include guidance and information contained in this document and data from reference
documents identified in this publication.
2-1.1.1 Antiterrorism
Antiterrorism requirements are established as part of the design program and are
identified as a separate line item in the DD Form 1391 estimate.
Planning and design of warehouse facilities must address the specific climatic and
geographic conditions of the intended site. In all climate regions consider solar
orientation to maximize energy efficiency, passive solar and daylighting potential of the
building. Refer to UFC 1-200-02, High Performance and Sustainable Building
Requirements.
5
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
2-3 STORAGE / HANDLING SYSTEM
The following design parameters must be observed when collecting data and analyzing
requirements associated with the material storage and handling requirements of a
planned warehouse facility:
2-3.2 Procedures
The following steps should be followed in developing a facility concept. Figure 2-1
illustrates these steps in flowchart form. The Activity or Project Manager must
6
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
designate in the project scope the following factors, as well as any special requirements
for storage or handling.
Develop Define
Define Define Daily
Support Area Available
Inventory Transactions
Requirements Space
Perform
Preliminary
System
Selection for
Each Area
Determine
Relative Cost
for Each
System and
Select Best
Determine
Building Size
and
Configuration
Prepare
Manpower
and
Equipment
Requirements
Develop
Actual Cost
Estimate for
Layout
Prepare
DD1391 Form
7
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
2-3.2.1 Define Inventory
State inventory levels in terms of 0.80 measurement ton (m/t) (32 ft3 or 0.91 mm3)
pallet loads or 0.0095 m/t (0.38 cubic foot; 0.011 cu. M) shelf boxes. Separate
inventory into groups with similar storage, handling, or transaction characteristics. The
major inventory item attributes to be evaluated must include temperature sensitivity,
hazardous characteristics, stackability, dimension, volume, and weight. Examples are
pallet storage, bin storage, high and low activity material, pre-positioned war reserve
stocks, etc. Establish maximum/minimum inventory levels per group.
8
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 2-2 Standard Pallet Rack Elevation / Parameters
9
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
2-3.2.4 Compute Transaction/Inventory (T/I) Ratio
Compute the system T/I ratio based upon the defined inventory and transaction
quantities. Develop separate T/I ratios for each inventory or handling group identified
by the procedure in the paragraph entitled “Define Inventory”.
10
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
2-3.3 Material Handling Equipment
When gasoline, diesel or LPG/Propane fueled fork trucks are required by the user
activity the ventilation and/or climate control systems must be design to accommodate
the expected quantity of fork trucks and duration of indoor use. Refueling for these
types of fork trucks must be provided on the exterior of the building. Provide a spill
containment dike for gasoline and diesel fork trucks in accordance the paragraph
entitled “Dikes”.
11
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Storage equipment will be provided to store materials properly, off the floor. It will also
be securely fastened to the slab and/or other structural supports designed to support
the equipment per equipment manufacturer’s installation requirements. Storage
equipment will be protected by proper means from contact by material handling and
operational equipment.
2-3.4.2 Shelving/Bins
Shelving and bins are designed for storage of package type items in less than pallet
load quantities. Industrial grade steel shelving and storage bins are modular in nature
and are composed of front and rear upright posts, shelves, dividers. Bin storage units
are a sub-group of industrial shelving in which the storage shelves are divided into
smaller compartments. If a shelf is divided into two or more compartments, the
compartments are classified as bins.
2-3.4.2.1 Shelving
Shelving is used for economical storage of small hand stackable items which are not
suited to mechanized handling and storage due to their handling characteristics, activity,
or quantity. Shelving is most often used for small parts storage in order picking systems
and is suitable for either manual or mechanized operations.
2-3.4.2.2 Bins
Bin storage is, in most instances, identical in application to shelf storage but is generally
applied to smaller items which do not need the entire width of a conventional shelf
module. Bin storage represents a small part of the total storage system in terms of
physical space although it may represent a significant portion of the total storage in
terms of item positions.
12
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
2-3.4.3 Special
Special storage equipment consists of devices designed for specific purposes such as
cantilever rack, vertical sheet storage rack, pallet stacking frames, rigid and collapsible
metal bins, etc.
a. Plumbness of pallet racks and high rise shelving +/- 1/16 inch (+-1.6 mm)
over total height.
b. Pallet rack beam elevation +-1/4 inch (+-6.4 mm) between adjacent
beams.
c. Rail guide position +1/4, -0 inches (+6.4 mm, -0 mm) from specified rail
spacing.
d. Wire guide position +-1/4 inch (+-6.4 mm) from specified centerline.
e. Pallet rack aisle spacing +-1/4 inch (+-6.4 mm) from design aisle width.
f. Down-aisle rack offset +-1/4 inch (+-6.4 mm) from aisle centerline.
b. Documentation requirements.
13
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
c. Packing/packaging requirements.
Separate support areas from hazardous materials storage areas with a 2-hour fire wall
and from combustible or flammable storage areas with a 4-hour fire wall. Direct access
between support areas and hazardous materials storage areas is not permitted. Refer
to table 2-1 for space estimating criteria for administrative and supervisory offices.
Refer to UFC 2-000-05N (P80), Facilities Planning Criteria for Navy and Marine Corps
Shore Installations for criteria relating to other warehouse support functions.
Table 2-1 Administrative and Supervisory Offices and Support Area Space
Requirements
Provide offices for supervisory personnel such as foremen, crew leaders, etc. Offices
must accommodate two people and provide filing space, one desk, and two chairs per
person. Offices must be located near their associated activity areas. Offices may
consist of prefabricated partition-type enclosures or more permanent forms of
construction such as concrete block.
Separate shipping and receiving office areas may be required in larger facilities and
combined hazardous materials and general storage facilities for safe operation and to
expedite the flow of paperwork associated with the increased activity. A facility with few
employees may use a single multipurpose office located away from any hazardous
materials storage area. Office location and arrangement must provide separation of
work functions and maintain security by controlling access to the facility. Offices must
permit an unobstructed view of the inside and outside dock areas. Rest room facilities
for both truck drivers and employees may be integrated into the office design.
The typical functional area relationships for the Administration and Warehouse Facilities
provide space for a building and site security system and office space for receiving
personnel. The secured entrance, lobby and rest room for truck drivers provides
controlled entry into the facility. Separate rest rooms are provided for supervisory and
warehouse personnel. See figure 2-3.
15
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 2-3 Typical Receiving Office Layout - Functional Dimensions
16
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
2-5.3 Shipping Office
The typical shipping office provides a separate entrance, lobby, and rest room for truck
drivers. A central office area and separate rest room facilities are provided for shipping
department and supervisory personnel. See figure 2-4.
17
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
2-5.4 Rest Rooms
Separate rest room facilities may be provided for supervisory and general warehouse
personnel.
Employee service areas consist of break rooms, canteen and vending machine
facilities, and locker rooms. Size these areas to accommodate the expected number of
employees. Multiple installations may be required to place these facilities within
required distances from employee activity areas. Refer to UFC 3-101-01, Architecture
for Space Planning and Criteria and UFC 3-420-01, Plumbing Systems for specific
requirements.
General purpose storage facilities may require crating of large or odd shaped items prior
to storage or shipment. Variability in requirements for materials, product size, and tools
necessitates individual design of crating areas. Refer to DoD 4140.1-R, Supply Chain
Material Management Regulation, title 49 CFR Transportation for criteria.
Requirements for small item packaging may be met through use of multipurpose
packing table work stations. Small item packaging must support a supply of cartons,
filler material, tape, glue, labels, and scales. The design of small item packing
operations must be approached on an individual facility basis.
2-5.7.1 Design
The design of small package packing station depends upon the relationship between
package characteristics and throughput patterns. If the movement through the packing
operation is homogeneous in terms of product characteristics and packing
requirements, it is possible to install conveyor type equipment. If the packing operations
must accommodate a heterogeneous mixture, a customized work station must be
provided.
Refer to DoD 4140.1-R, Supply Chain Material Management Regulation, title 49 CFR
Transportation for criteria. Repackaging of damaged hazardous materials packages
must be performed in a designated safe area.
Provide an equipped and ventilated room or area for the charging of materials handling
vehicle batteries. For additional requirements see section titled “Battery Charging and
Handling Operations”.
18
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
2-6 PARKING
Provide parking space for \1\/1/facility employees. Parking areas must be separated
from truck docks and other activity areas. Site security must be enforced by separating
the storage facility from the remainder of the activity and further isolating parking from
receiving and shipping functions. Refer to UFC 3-201-01, Civil Engineering for parking
requirements.
Arrangement of the facility on the site and internal arrangement of the material handling
systems must be evaluated to reduce or eliminate areas of conflicting traffic. Consider
interaction with installation traffic flow.
2-8 SAFETY
All DoD facilities must comply with DoD Instruction 6055.1 and host services’
Occupational Safety and Health Requirements.\1\This includes but is not limited to the
following:/1/
19
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 2-5 Typical Safety Markings
Perspective Views
20
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
CHAPTER 3 GENERAL DESIGN CRITERIA
Providing easy and rapid materials handling and adequate clear storage space are the
prime considerations in warehouse design.
Transport paths and building layout must avoid discontinuities and elevation changes
which impede material movement. \1\ The transport path must be clear of structural
columns or beams. /1/
Locate warehouse facilities on a site to take advantage of highway and rail facilities.
Evaluate location of the facility on the site to reduce or eliminate areas of conflicting
traffic.
Consider present and future requirements in building construction and site location to
permit future expansion of facilities in an orderly, safe, and cost-efficient manner.
Where facility usage is uncertain or subject to change, building design must use the
universal bay dimension of 33 feet x 64 feet (10,060 mm x 19,510 mm).
Building requirements are dictated by the function of the facility. Refer to table 3-1 for
general requirements for specific types of buildings.
21
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Table 3-1 Special Requirements for Warehouse Types
22
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-2 BUILDING SHAPE AND PROPORTIONS
Arrange buildings or increments of buildings for minimum distance between high activity
operations. Square buildings minimize perimeter wall area for a given floor area.
Aspect ratios (ratio of length to width) of 1.25 or less are considered square. If possible,
avoid aspect ratios exceeding 3.00 for conventional warehousing operations.
3-2.3 Height
High-rise storage is preferred over low height buildings on a life-cycle cost basis since
storage costs per unit stored, over the life of the project, decrease as height is
increased. Coordinate building height parameters with storage system characteristics,
as illustrated in figure 2-2.
3-2.4 Area
Limit building size based on restrictions due to loss potential and fire and hazardous
chemicals safety and site restrictions. Fire protection separation between buildings;
Refer to UFC 3-600-01, Fire Protection Engineering for Facilities, for required building
separation based upon construction and exposure.
Required spacing between buildings to facilitate operations and aid in fire prevention,
protection, and hazardous chemical spills (liquid/gas) control, will vary according to the
type of construction and exposure classification. Refer to UFC 1-200-01, General
Building Requirements and UFC 3-600-01, Fire Protection Engineering for Facilities for
fire protection engineering requirements. Otherwise, observe the following:
23
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-3.3 Warehouses In-Line
Provide a buffer zone between the facility or portion of facility containing Hazardous
Materials and the nearest inhabited area, stream, or body of water in accordance with
UFC 1-200-01, General Building Requirements and UFC 3-600-01, Fire Protection
Engineering for Facilities.
24
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 3-1 Truck Apron Criteria (Functional Dimensions)
Plan View
25
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 3-2 Building Protection Devices
Plan View
26
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-4.1 Truck Dock
Truck dock height will vary between 44 and 52 inches (1120 mm and 1320 mm)
depending on the class of trucks served (see table 3-2). Use a 48-inch (1220 mm)
height for general highway tractor-trailer service. Configure truck docks to conform to
building, site, and traffic flow requirements (see figure 3-3). Figure 3-4 shows a typical
dock section. Slope dock apron areas away from the building, as illustrated in figure 3-5.
Provide doors of a size consistent with truck characteristics, as shown in figure 3-6.
Open uncovered exterior truck dock platforms are not recommended. Provide space to
load and unload flatbed and low-boy trucks and to move material in and out of the
warehouse using a rolling A-Frame hoist or similar material handling equipment. A dock
adjacent to the ramp of the building may be equipped with a 5-ton (4500 kilogram [kg])
monorail, interrupted at the door with a moveable (swing) section. A 12 x 12 foot (3660
mm x 3660 mm) door must be specified with this option. All outside supports must have
protective barriers.
27
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Table 3-2 Truck and Rail Vehicle and Dock Heights
Notes:
(1) Dock height range of 48”- 52” (1220-1320 mm).
(2) Dock height of 50” (1270 mm) if serving semis only.
(3) Dock height of 48”-50” (1220-1270 mm) recommended with exterior ramp to elevate
truck to provide nominal 30” (760 mm) dock height.
(4) Minimum dock leveler length determined by required clearance between rail car and
dock.
28
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 3-3 Truck Dock Configurations
29
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 3-4 Typical Truck Dock
30
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 3-5 Truck Apron Section
31
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 3-6 Door Size Characteristics
32
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-4.2 Rail Docks
If rail access is available include provisions for rail docks (see figure 3-7) as an option in
the design of all storage facilities exceeding 40,000 square feet (3716 sq. m). There are
three primary types of rail dock:
33
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-4.2.1 Outside Docks
Outside rail docks use through-the-wall access to rail cars without using an outside
platform. Use inflatable seals to seal the space between the rail car and the warehouse.
Include a wall-mounted dock board to provide access to the rail car.
3-4.2.3 Platforms
Platforms for rail service must extend the full length of the building and be 15 feet (4570
mm) wide. Platform height above rails must be 3 feet 8 inches (1118 mm) for general
use. Equip platforms with track-mounted dock boards. See the paragraph entitled,
“Dock and Platform Weather Protection”.
Provide ramps at the end of rail platforms and at one warehouse truck dock door for
vehicle access. Ramp slope must not exceed 10 percent.
For occupant accessibility requirements see the paragraph entitled, “Accessibility for the
Disabled”.
Provide dock levelers at all truck and rail dock positions. Dock leveler life is directly
affected by load weight, fork truck weight, and frequency of use. Specify dock leveler
capacity to provide a minimum 20 year life (see table 3-3).
34
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Table 3-3 Dock Leveler Life (Years) Based on Impact Loading
Notes:
Provide dock shelters or door seals in heated, air conditioned, and dehumidified
warehouses, to seal the space between the truck or railcar and the building (see figure
3-8). Full width canopies must be used to shield all docks and rail service platforms
from precipitation. Provide gutters and downspouts and connect to underground
stormwater drainage system.
35
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 3-8 Truck Dock Weather Seals
Perspective Views
3-4.5.3 Canopy
Provide a minimum 4 foot (1830 mm) full length canopy (figure 3-9) over outside docks
to protect the trailer and door interface and dock shelter or door seal from excessive
weather exposure. This requirement must be evaluated with the site solar angle to
alleviate solar loading in the cooling season and optimize solar gain in the heating
season.
36
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 3-9 Truck Dock Canopy
Section
Equip each truck dock with safety equipment consisting of wheel chocks and door-
mounted lights to illuminate the trailer interior. Dock levelers must be equipped with
manually or electrically operated trailer restraints with wheel chocks as a secondary
safety measure. Figure 3-10 illustrates a typical installation of a dock shelter, dock
leveler, and trailer restraint device.
37
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 3-10 Trailer Restraint System
Elevation View
Provide fall protection per requirements of 29 CFR 1910.23, Guarding Floor and Wall
Openings and Holes.
38
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Provide two safety posts for each personnel door on the warehouse storage side of the
door. See figure 2-3 and figure 2-4 for examples of safety posts applications.
3-5 STRUCTURAL
Slab-on-grade systems for the offices and shop spaces of the facility must be designed
in accordance with UFC 3-301-01, Structural Engineering. Fiber reinforced concrete
systems must not be used inside the building. Slab-on-grade must have adequate
thickness to support wall line loads. For slab-on-grade subject to forklift traffic, the
minimum compressive strength for the concrete must be 4,000 psi (27580 kPa).
3-5.1.1 Reinforcement
Provide crack control using reinforcement consisting of minimum number 6 welded wire
fabric in a 6- by 6-inch (150 mm x 150 mm) mesh or alternative non-reinforced methods.
3-5.1.2 Thickness
Floor thickness will be determined by a combination of live load, dead load, strength of
concrete, and subgrade conditions. Refer to UFC 1-200-01, General Building
Requirements, UFC 3-301-01, Structural Engineering and UFC 3-220-01, Geotechnical
Engineering, for structural engineering and geotechnical engineering procedures for
foundation design. Floors in warehouse facilities must be no less than 6 inches (150
mm) thick.
3-5.2 Superstructure
The superstructure of the warehouse must be a steel frame unless alternate structural
frame systems are determined to be better suited for the facility.
39
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-5.2.1 Structural Bracing
Structural bracing must be located so as not to impair functionality of storage areas.
Exposed structural bracing must not be permitted in any administrative spaces.
a. Availability of materials.
b. Speed of erection.
g. Criteria for design of structures in typhoon, hurricane, and other high wind
areas. Refer to UFC 3-301-01, Structural Engineering.
40
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-5.2.5.2 Hollow Structural Sections
HSS members must be sealed to keep water from entering the section and animals
from nesting inside. 1/4 inch (6.35 mm) diameter weep holes are allowed as necessary
to release any thermal pressure built-up from within the members.
All exposed structural steel must be coated with a high performance coating system
consisting of an epoxy primer, a high solids polyurethane intermediate coat and a high
solids polyurethane top coat. Refer to UFC 3-190-06, Protective Coatings and Paints.
The structural frame must be designed to accommodate 125% of the loading from
overhead bridge cranes. The designer must consider the effect of pattern loads
resulting from multiple loaded hooks. All crane hardware and lifted loads must be
treated as live loads in the load combinations defined in chapter 16 of the IBC, except
for patented tracks, tracks, supports, sway braces and similar elements which are
immobile and may be defined as dead loads.
41
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-5.2.7.2 Factored Load Combinations
If the dead load of any portion of the facility, including a structurally isolated
administration and shop structure sharing a common foundation, is used to resist uplift
forces, it must be factored by 0.9 in strength design analysis and by 0.6 in stress design
analysis if it favorably contributes to the performance of the system.
The design must also control deflections to within the limits imposed by section 1604 of
the IBC in compliance with UFC 3-301-01, Structural Engineering unless stricter control
is necessary to support equipment, fascia or other appurtenances. The warehouse roof
must meet the requirements of a structure “supporting a non-plaster ceiling” and the
walls must meet the requirements of a “partition with flexible finishes.” The
administrative area must meet the deflection requirements appropriate to finish type. If
the warehouse and administrative area framing is constructed as a single frame, the
combined structure must meet the most stringent requirements described above.
Exterior walls of the warehouse must be of a construction suitable to the building type,
be compatible with the design of the existing building / adjacent buildings with regards
to building form, height, materials selection, color and architectural detailing and be
protected from abuse, both interior and exterior. Exterior walls and building signage
must be compatible with the Installation Appearance Plan (IAP) or other written
documents. For Design/Build projects, coordinate any specific requirements for
materials prior to issuing the RFP.
Exterior design and architecture must comply with UFC 1-200-01, General Building
Requirements, UFC 3-101-01, Architecture and UFC 1-200-02, High Performance and
Sustainable Building Requirements.
The chemical properties of materials and finishes for exterior surfaces must have the
highest possible resistance to the effects of weather and salt-corrosive atmosphere.
Where metal panels are used for exterior wall and roof surfaces, provide a factory
applied finish system to resist corrosive climatic effects.
Low-slope roofs must be used to minimize potentially unusable space caused by the
roof rise associated with sloped roofs. Sloped roofs having a pitch exceeding 1 inch per
foot (83 mm per meter) must be avoided for warehouse facilities unless available
roofing materials require a greater pitch. When the roof slope exceeds 2 inch per foot
(166 mm per meter) the sprinkler operating area and sequence will be impacted. Sheds
may have a roof pitch of 2 inches per foot (166 mm per meter) or greater.
Refer to UFC 1-200-01, General Building Requirements and UFC 3-110-03, Roofing.
43
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
outlet on-grade splash blocks of adequate size for downspout capacity
must be provided.
e. Provide a drop ceiling in the warehouse when the roof slope is greater
than 2 inch per foot (166 mm per meter).
3-6.2.1 Low-Slope
Low-slope roofs must have a minimum pitch of 1/2 inch per foot (42 mm per meter).
Exterior walls may be of insulated metal siding, brick or concrete masonry, or tilt up
precast or cast-in-place concrete panels. When metal walls are used, the first 4 feet
(1220 mm) of wall above the floor must be of reinforced masonry construction to protect
the structure from fork truck impact and provide additional security. Walls located on
sides designated for future expansion must be removable.
Size dock doors consistent with the types of delivery vehicles expected to operate
around the facility.
Width Height
Description
inches mm inches mm
Standard Truck Door 9’-0” 2,743.2 mm 10’-0” 3,048.0 mm
Air Lines of Communication (ALOC) 2,743.2 mm 3,048.0 mm
10’-0” 10’-0”
Door
Transporter Door 10’-0” 3,048.0 mm 10’-0” 3,048.0 mm
Firewall Door (interior between bays) 15’-0” 4,572.0 mm 15’-0” 4,572.0 mm
Oversized Door 12’-0” 3,657.6 mm 10’-0” 3,048.0 mm
Forklift Ramp Door 15’-0” 4,572.0 mm 15’-0” 4,572.0 mm
Truck Well Door 12’-0” 3,657.6 mm 15’-0” 4,572.0 mm
44
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-6.4.1 Dock Door Height
Truck dock doors must be at least 9 feet (2745 mm) high.
3-6.6 Windows
Exterior doors with closers must be Level 4, physical performance Level A doors
complying with ANSI/SDI A250.8, Standard Steel Doors and Frames. Frames must
match door level. Exterior door frames must be welded type.
Provide Grade 1 hardware typical. Locksets must be mortise type, Series 1000 as
defined by ANSI/BHMA - A156.13, Mortise Locks and Latches for shop and
maintenance level doors. Hinges for doors with closers must be full mortise butt hinges
except where special types are required. Closers must be the best and highest grade
available from each manufacturer. Exterior doors must have overhead rain drips and
door drips.
3-6.8 Signage
45
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Provide exterior signage in accordance with UFC 3-120-01, Design: Sign Standards.
Durability is extremely important when specifying materials for interior construction and
finishes. Warehouses regularly handle heavy equipment throughout the facility. All
finishes and components must be selected based on the operations performed in the
warehouse, and shop spaces. These conditions will lead to greater interior damage
being incurred compared to many other facility types.
Refer to UFC 1-200-01, General Building Requirements and UFC 3-120-10, Interior
Design.
Interior wall construction will vary depending upon use, finish, and required fire and
corrosion resistance. Refer to UFC 1-200-01, General Building Requirements.
Windows must be provided for office and service structures when located on an exterior
wall. A continuous narrow band of high windows may be justified in large warehouses
by savings in electric lighting costs as determined by energy modeling.
3-7.2.1 Doors
Provide interior door openings and portals of sufficient height and width to permit
passage of materials handling equipment. Size doors and portals consistent with the
types of trucks expected to operate in the facility. These requirements do not apply to
personnel type exit doors.
46
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-7.2.1.3 Hardware
Provide Grade 1 hardware typical. Locksets must be mortise type, Series 1000 as
defined by ANSI/BHMA - A156.13, Mortise Locks and Latches. Locksets for
administrative spaces may be Series 4000 as defined by ANSI/BHMA - A156.2, Bored
and Preassembled Locks and Latches. Hinges for doors with closers must be full
mortise butt hinges.
Metal overhead doors must be chain hoist operated, except when frequent use
demands motorized operation.
3-7.3 Signage
Provide safety markings on walls and floors (figure 2-5.) Refer to Title 29 Code of
Federal Regulations (CFR) Part 1910, Occupational Safety and Health Standards.
Provide interior signage in accordance with the requirements of UFC 3-120-01, Design:
Sign Standards.
3-7.3.1 Identification
Provide identification signage to inform personnel of area identification, function,
services, safety, and storage locations.
3-7.3.2 Warning
Identify all hazards, hazardous equipment, and restricted areas with suitable warning
signage.
The warehouse must be provided with durable finishes. The exterior walls must have
as a minimum, a protective panel along the exterior walls that will prevent damage to
the exterior finish system. The minimum protection can be provided by a metal panel
attached to the wall panel girts. The protective panel must extend to at least 7 feet
(2.13 meters) above the warehouse floor. Alternatively, masonry may be provided.
3-7.4.1 Floors
Critical attention to floor design and construction is essential to proper operation of
narrow aisle high-rise storage systems. Provide a Class 5 floor in accordance with
American Concrete Institute (ACI) Guide for Concrete Floor Slab Construction, AC1
302.1R-04 and UFC 1-200-01, General Building Requirements, for areas not otherwise
specified.
47
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-7.4.1.1 Finishes
Floor hardeners, dressings, or toppings are required for durability in areas of
exceptionally high activity such as main aisles, towline paths, or industrial shop areas.
Sealers are required for dust control.
a. Clearly identify on the design drawings those areas of the warehouse floor
which must meet superflat tolerances.
e. Specify a concrete mix having a low water-cement ratio and low shrinkage
characteristics. Achieve concrete workability through use of plasticizers in
lieu of additional water.
f. During construction, pour concrete between rigid forms in lanes less than
20 feet (6100 mm) wide. Strike off concrete with a vibrating screed.
g. After initial floating, use a 10 foot (3050 mm) long transverse scraping
straightedge (highway straightedge) to remove high spots.
h. Check the surface of the plastic concrete frequently with a 10 foot (3050
mm) long straightedge placed both parallel and transverse to the
48
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
centerline. Correct any high spots and fill any low spots using the highway
straightedge.
3-7.4.2.2 Measurement
Refer to ACI 302.1R-04, Guide for Concrete Floor and Slab Construction for
measurement requirements for class 9 superflat floors and the following requirements:
3-7.4.3.1 Conduits
Avoid installing conduits in the floor.
3-7.4.3.2 Reinforcing
Reinforcing steel must be located at least 2 inches (50 mm) below the concrete surface.
Wire mesh must be tack-welded together wherever possible. Rebar and wire mesh
must be grounded.
49
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-7.4.3.3 Expansion Joints
Where possible, expansion joints must not be located under storage racks. When
expansion joints are located in the storage aisle, they must run parallel to the aisle and
not be within 3 inches (75 mm) of the centerline of the storage aisle or within materials
handling equipment wheel tracks. Expansion joint material used in hazardous materials
storage areas must be compatible with the contents of the materials being stored.
3-7.4.4 Walls
All unfinished items must be painted.
3-7.4.5 Ceilings
Paint all structural steel, deck and other non-prefinished items.
3-7.5.2 Floors
Floor finish must be an epoxy floor coating compliant with Master Painter’s Institute -
MPI 212, Floor Coating, Thin Film, for Aircraft Maintenance Facilities or sealed
concrete.
3-7.5.3 Ceilings
Shops must not have suspended ceilings. All exposed piping, structure, deck, ductwork,
etc. must be painted.
3-7.6.1 Partitions
Partitions separating administration spaces from the warehouse space must be
concrete masonry construction. Partitions separating administrative spaces may be
gypsum board construction. Partitions are not required to extend to above the ceiling
for similar office types and spaces where noise between offices is not an acoustical
issue or required for personnel counseling. Paint all unfinished materials.
50
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-7.6.2 Floors
Floor finishes must be standard type finishes based on the expected usage of the
spaces. Provide a wall base in all spaces.
3-7.6.3 Ceilings
Provide suspended acoustical ceilings in all administrative spaces.
3-7.7.1 Partitions
Provide CMU partitions around toilet and locker rooms. Partitions around perimeter of
space must extend to floor or roof construction above. Provide ceramic tile wainscot
and ceramic base. Provide ceramic tile wall finishes to the ceiling on all walls in
showers.
3-7.7.2 Floors
Floor finishes must be ceramic tile.
3-7.7.3 Ceilings
Ceilings in toilets must be gypsum wall board. Ceilings in locker rooms must be
suspended acoustical ceilings with a water resistant membrane. Ceilings in showers
must be water resistant gypsum board. Plaster is not allowed.
3-7.7.4 Lockers
Provide personnel lockers in dedicated locker rooms. The number of personnel lockers
must be identified in the RFP. Lockers are provided for personnel to keep personal
items or clothing during their work shift. Provide lockers with solid sides and louvered
doors.
Lockers must be 9” x 21” x 72” (229mm x 533mm x 1829mm) high and must be single
tier type. All lockers must be metal and must have capability to receive padlocks.
3-7.8.1 Partitions
Partitions in corridors and stairs must be painted masonry or painted gypsum board.
Gypsum board must be impact resistant type to 8 feet (2.44 meters) above the floor or
stair level. Corridor partitions and rooms without ceilings must extend to the deck
above.
51
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-7.8.2 Floors
Floor finishes for these spaces must be as determined by the designer but minimum
finish must be a resilient flooring system.
3-7.8.3 Ceilings
Corridors must have suspended acoustical ceilings, typical.
Support spaces such as mechanical, pump rooms, and electrical rooms must be
provided as required. These spaces must be as determined by the requirements of the
project.
Partitions in corridors, around mechanical, electrical, and similar type spaces must be
painted masonry. Corridor partitions and rooms without ceilings must extend to the
deck above. All exposed piping, structure, deck, ductwork, etc. must be painted.
Provide an equipped and ventilated area for the charging of materials handling vehicle
batteries. Figures 3-11, 3-12 and 3-13 illustrate typical battery charging layouts.
Hydrogen detectors must be provided at Battery Charging Areas.
52
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 3-11 Battery Charging Area (Open Locations)
Plan Views
53
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 3-12 Battery Charging Area (One-Entrance Room)
Plan Views
54
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-7.10.1 Containment Pit
Contact the local environmental office for regulations about handling contaminated
water.
Provide a spill containment pit with a floor grate to capture water and contaminants from
the safety shower/eyewash and accidental battery discharge. The pit must be equipped
with a shut off valve to allow for proper neutralization of contaminated water before
discharging. The pit must be large enough to hold the entire contents of the largest
battery serviced in the area as well as all the water from a 15 minute shower.
55
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 3-13 Typical Battery Charger Installation
Perspective View
\1\Note: Refer to paragraph Containment Pit for spill containment requirement. /1/.
56
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Provide specialized battery handling equipment in battery charging and work areas.
Equipment used must be selected based on the characteristics of the vehicle and
battery being serviced, the activity of the charging station, and the maintenance work
performed on the battery. Devices include handling beams, jib hoists, special charging
stations, and battery transporters.
3-7.10.4 Ventilation
Provide ventilation in accordance with UFC 3-410-04N, Industrial Ventilation.
Provide natural and mechanical exhaust ventilation to ensure diffusion of the gases
from the battery and to prevent the accumulation of an explosive mixture. Provide
ventilation to limit hydrogen gas buildup to no more than 1 percent by volume in room
air. If battery charging room air is air conditioned as part of a general building air
conditioning system, exhaust air directly to the outdoors and do not return it to the air
distribution system. Required air changes must be based on the expected activity in the
charging room, but must be no less than six air changes per hour. Activity must
consider the number of cells being charged at a given time and the charging current
being used. Provide an air velocity rate across battery charging shelves of at least 125
feet per minute (0.64 meters per second). Interlock the ventilation system with the
chargers to prevent charger operation unless the ventilation system is operating.
Selective pallet racks (see figure 3-14) consist of uprights, pallet beams, bracing, and
miscellaneous accessories. Minimum design load must be 3,000 pounds (1360 kg) per
pallet.
57
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 3-14 Pallet Rack Terminology
Perspective Views
58
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-7.11.1 Dimensions
Pallet racks must have a 40-inch (1020 mm) depth and accommodate standard 40- x
48-inch (1020 mm x 1220 mm) pallets without front or rear pallet overhang (see figure
3-15). Use of other sizes of pallet racks or pallets must be documented and justified.
Beam to beam vertical spacing averages 48 inches (1220 mm) (see figure 2-2).
59
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-7.11.2 Stability
Rack stability is influenced by loading conditions, attachment, and rack assembly.
Racks exceeding a 6:1 height to depth ratio must be securely anchored or braced
externally. For standard racks, this applies to racks exceeding 20 feet (6096 mm) in
height.
• In hazardous materials storage areas, provide 12-inch (300 mm) flues between
back-to-back racks. Flues of 8-12 inches (200-300 mm) must be provided
between backs of racks and walls.
• Standard pallet racks provide a minimum 4-inch (100 mm) transverse flue space.
60
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 3-16 Pallet Rack Fire Protection Terminology
Perspective View
61
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-7.11.4 Attachment
Securely attach all pallet racks to floors, walls, and each other, to ensure stability and
safety.
62
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 3-17 Pickup and Delivery (P&D) Stations
63
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
64
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-7.12.2 Wire Guidance
Coordinate guide wire locations with pallet rack and vehicle characteristics (see figure
3-19). Review guide wire location plan to provide a continuous loop and avoid
crossovers. Install loop driver and control panel in a protected location.
65
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-7.12.3 Transport Aisles
Width of transport aisles must be at least twice the vehicle width plus 18 inches (145
mm) to permit two-way traffic.
Plan View
66
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-7.13.1 Universal Bay Size
If a general purpose facility is required, or a specific materials handling system has not
been selected, maintain versatility in selecting the universal pattern subject to the
following considerations:
a. The universal pattern will not represent the optimum spacing for all
systems.
b. The facility may be costlier than necessary because of the inefficient use
of space. A smaller building can generally be constructed if the optimum
column spacing is used.
c. Use of the universal pattern will permit the building to fulfill a variety of
missions due to its ability to function with many materials handling
systems.
a. Use of the optimum bay size will reduce the size of the required building
due to more efficient use of the building cube.
67
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Table 3-5 Building Bay Size Comparison
SPACE
OPTIMUM BAY SIZE MODULAR BAY UTILIZATION
SYSTEM ft-in x ft-in EQUIVALENT BAY DIMENSION IN
(mm x mm) SIZE FOR FIT UNIVERSAL
ft-in x ft-in (mm x mm) ft-in (mm) BAY
%
Counterbalance Truck 39’-2” x 39’-2” (11,940 x 11,940) 39’-2” x 58’-4” (11,940 x 17,780) 64’-0” (19,510) 91.1%
33’-0” (10,060) 91.4%
Reach Truck 30’-2” x 44’-10” (9,190 x 13,670) 30’-2” x 44’-10” (9,190 x 13,670)
64’-0” (19,510) 92.9%
Front/Side-loader Truck
26’-2” x 38’-10” (7,980 x 11,840) 33’-0” (10,060) 79.3%
Turret Truck 26’-2” x 38’-10 (7,980 x 11,840)
26’-2” x 64’-2” (7,980 x 19,560) 64’-0” (19,510) 100.3%
Man-Up Turret Truck
Hybrid Truck 24’-2” x 35’-10” (7,370 x 10,920) 24’-2” x 59’-2” (7,370 x 18,030) 64’-0” (19,510) 92.4%
31’-0” x 61’-0” (9,450 X 18,590) 33’-0” (10,060) 93.9%
Manual Order Picker 31’-0” x 49’-0” (9,450 x 14,940)
31’-0” x 61’-0” (9,450 X 18,590) 64’-0” (19,510) 95.3%
33’-0” x 59’-0” (10,060 X 17,980) 33’-0” (10,060) 100.0%
Order Picking Truck 33’-0” x 49’-0” (10,060 x 14,940)
33’-0” x 59’-0” (10,060 X 17,980) 64’-0” (19,510) 92.2%
31’-0” x 61’-0” (9,450 X 18,590) 33’-0” (10,060) 93.9%
Manned S/R Machine 31’-0” x 49’-0” (9,450 x 14,940)
31’-0” x 61’-0” (9,450 X 18,590) 64’-0” (19,510) 95.3%
32’-6” x 45’-6” (9,910 x 13,870) 33’-0” (10,060) 98.5%
Carousel 32’-6” x 45’-6” (9,910 x 13,870)
32’-6” x 58’-6” (9,910 x 17,830) 64’-0” (19,510) 91.4%
26’-0” x 63’-6” (7,920 x 19,350) 33’-0” (10,060) 78.8%
Mini-S/R Machine 26’-0” x 51’-0” (7,920 x 15,540)
26’-0” x 63’-6” (7,920 x 19,350) 64’-0” (19,510) 99.2%
• Clearance from sprinkler deflectors to the top of storage load will affect sprinkler
requirements and water demand.
• Clear building height requirements for specific levels of storage, as well as three
modular clear heights covering a range of storage levels, are summarized in
table 3-6. Construction of a warehouse facility to a modular height greater than
that required for the desired system or level of storage will result in an unutilized
cube and extra construction and operating costs.
68
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Table 3-6 Required Clear Building Heights
Notes:
69
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-7.14 Telecommunication Systems
Provide telephones, service entrances, telephone cabinets, conduit runs, and telephone
outlets. Locate at least one telephone in each office. Provide in accordance with UFC
3-580-01 Telecommunications Building Cabling Systems Planning and Design.
3-7.14.2 Army
For Army projects, building telecommunications must be designed to satisfy Army
Installation Information Infrastructure Architecture (I3A) Policy.
Provide fire, hydrogen, ventilation failure, hazardous chemical spill, neutralizer tank and
security alarms.
3-7.16 Casework
70
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-7.17 Elevators and Lifts
Elevators may be needed if required for ADA/ABA compliance or the activity specifically
requests an elevator. See the section on Accessibility for further clarification.
Size elevator based on activity requirements. If elevators are required at least one
elevator must accommodate a 24 in. wide x 84 in. long (610 mm x 2,134 mm)
emergency stretcher.
Coordinate with the Comprehensive Interior Design package during the design process.
All case goods and hardware will be coordinated with the Structural Interior Design
package for the project to ensure matching woods, stains, and finishes as best possible.
Selection of materials and finishes for the main entry point area(s) will accommodate
heavy use.
Coordinate the use and location of recycling centers throughout the common areas to
complement the interior design while supporting sustainability guidance.
All appliance colors must be coordinated with the FF&E. The construction contractor or
design/build contractor will submit cut/datasheets of proposed equivalents/substitutions
appliances for review/approval. Purchase appliances meeting Energy Star program
standards and specifications as included in this guide. Qualifying products are listed on
the Energy Star website.
Incorporate pest control measures into building design to ensure the efficient control
and quarantine of insects, rodents, and other pests. Refer to Armed Forces Pest
Management Board Technical Guide No. 17, Military Handbook – Design of Pest
Management Facilities. Measures must include:
71
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-9 ACCESSIBILITY FOR THE DISABLED
Every facility must be designed to ensure access in accordance with UFC 1-200-01,
General Building Requirements.
3-10 ACOUSTICS
Use the “suggested design values” STC ratings in UFC 3-450-01, Noise and Vibration
Control, as the basis for the sound design of partition, door and window assemblies for
the facility. Utilize gypsum board wall “improvements” to increase the STC of gypsum
board “stud type” partitions to achieve the project sound requirements. Unless noted
otherwise extend partitions and seal to the structure above around rooms that have a
noise source such as but not limited to corridors, toilets, elevator machine rooms,
training rooms, maintenance rooms, activity rooms, and mechanical rooms. Unless
indicated in chapter 4, STC ratings do not need to be field verified. Do not provide any
special acoustical conditions in the project unless specifically recommended by an
acoustical study.
Conveying systems may not be required. For projects which require conveying
systems, provide them in accordance with the following:
Verify the crane capacity with the governing authority, but provide no less than a 5 ton
(4.5 metric ton) overhead bridge crane. All cranes must be Duty Service Class C. All
bridge cranes must be supported from patented track systems designed by the crane
manufacturer. All overhead bridge cranes must be under running, double girder electric
cranes.
Provide all cranes in accordance with Air Force Instruction 91-203, Air Force
Consolidated Occupational Safety Instruction; Navy Crane Center Instruction 11450.2,
Design of Navy Shore Weight Handling Equipment; title 29 CFR 1910.179(j),
Inspections; title 29 CFR 1910.179(k), Testing; and the American National Standards
Institute ANSI MH27.1, Specifications for Patented Track Underhung Cranes and
Monorail Systems; and relevant portions of the Crane Manufacturing Association of
America CMAA Specification 70, Top Running Bridge and Gantry Type Multiple Girder
Electric Overhead Traveling Cranes, and the Crane Manufacturing Association of
America CMAA Specification 74, Top Running and Under Running Single Girder
Electric Overhead Cranes Utilizing Under Running Trolley Hoist.
72
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-11.1.1 Hook Height
Hook height is to the saddle of the hook and must be determined by the overall height of
the facility. Hook height for any facility must be no less than 20 feet (6.10 m).
Bridge, trolley and hoist controls must provide for two-speed reversing of a two-speed,
squirrel-cage motor. The controls must be equipped with reduced voltage starting for
the motors. Controls must be operable from the floor.
Provide service catwalks or platforms to maintain overhead bridge cranes. Ensure all
safety requirements are met; see UFGS 01 35 26, Governmental Safety Requirements.
The access must be from inside the warehouse.
3-13 PLUMBING
3-13.1 General
73
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-14 ENVIRONMENTAL CONTROL
Provide heating in all offices in all heating zones. Provide air conditioning in offices.
Determine requirements for environmental control in storage space based on the
temperature requirements of material stored and the extent and activity level of
occupancy. Need for heating of storage spaces must be clearly demonstrated.
Warehouses for storage of materials not subject to freezing must not be heated. In
warehouses containing materials subject to freezing, design heating system to maintain
an inside winter temperature of 45°F (7°C). Maintain a temperature of 55°F (13°C) in
warehouse areas with active employment. Refer to UFC 3-410-01, Heating, Ventilating,
and Air Conditioning Systems.
The designer must consider a minimum of three HVAC systems that meet all the criteria
and perform a life cycle cost analysis for the basis of selection. Refer to UFC 1-200-02,
High Performance and Sustainable Building Requirements and UFC 3-410-01, Heating,
Ventilating, and Air Conditioning Systems.
3-14.1 General
Provide HVAC in accordance with UFC 1-200-01, General Building Requirements and
Unified Facilities Criteria series 3-400, Mechanical.
3-14.2 Heating
Provide heating in accordance with UFC 3-410-01, Heating, Ventilating, and Air
Conditioning Systems and as follows:
• The heating system must be a steam, hot water, gas fired hot air, or solar
system. Provide unit heaters or hot air registers at cargo doors and over aisles
between stored materials.
• Direct-fired hot air systems must not be used for hazardous materials
warehouses.
• Selection of unit heaters, spot heating systems, and design of total heating
systems, must be considered on energy and life-cycle cost basis.
a. Provide a wall with a 2-hour fire resistance rating between the heater room
and storage area.
b. All access to the heating area must be from the outside only.
74
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
c. When infrared unit heaters are used, provide safe clearances in
accordance with the manufacturer’s safety instructions.
Under floor heating systems must be 2 in. minimum and 3 in. maximum (50.8 mm and
76.2 mm) from the bottom of the floor slab. Depth of under floor heating system and
slab thickness must be coordinated with the rack / shelving fastener depth to avoid
conflict and damage to the heating system.
3-14.3 Ventilation
Provide ventilation in accordance with UFC 3-410-01, Heating, Ventilating, and Air
Conditioning Systems, and UFC 3-410-04N, Industrial Ventilation.
75
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Toxic fumes generated by gas powered fork trucks must be exhausted. It is
recommended that gas powered fork trucks not operate inside the warehouse area.
Provide humidity control in accordance with UFC 3-410-01, Heating, Ventilating, and Air
Conditioning Systems, and UFC 3-410-04N, Industrial Ventilation.
Provide air conditioning in accordance with UFC 3-410-01, Heating, Ventilating, and Air
Conditioning Systems.
Office areas in cooling zones must be air-conditioned by either high efficiency small
area units or a central system, as appropriate. Consider radiant floor cooling systems
for air conditioned storage areas.
3-14.7 Insulation
Warehousing facilities that require heating or cooling must be insulated. Determine the
amount and type of insulation by a life-cycle cost analysis.
76
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
• Consider using copper tube / copper fin with phenolic type coating for 100
percent outside air units.
Design mechanical systems and equipment to limit noise and vibration in accordance
with UFC 3-450-01, Noise and Vibration Control.
Provisions for fire protection and life safety will conform to National Fire Protection
Association (NFPA) Life Safety Code NFPA 101, UFC 1-200-01, General Building
Requirements and UFC 3-600-01, Fire Protection Engineering for Facilities.
For new construction and rehabilitation projects, install sprinkler systems in accordance
with National Fire Protection Association (NFPA) Standard for the Installation of
Sprinkler Systems NFPA 13 and UFC 3-600-01, Fire Protection Engineering for
Facilities.
• Aisle width
• Storage height
• Storage configuration
77
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
height will be designed to a maximum storage height of 22 ft regardless
of the defined storage height.
3-15.1.2 Storage System Sprinklers
In general purpose, controlled humidity, refrigerated and other type warehouses where
hazardous materials are not to be stored, provide \1\ /1/ face and flue sprinklers per
NFPA 13. Rack shelving must not be adjustable on rack levels where \1\ /1/ face and
flue sprinklers are provided. Additional flue sprinklers may be required depending upon
storage height and its relationship to the\1\ /1/ sprinklers. Face and flue sprinklers must
be placed at or below each 108-inch (2745 mm) open frame shelf at the required levels
in a manner which prevents sprinkler damage during storage operations, as illustrated
in figure 3-21. The sprinklers at all other shelf levels must be capable of vertical
adjustment using mechanically grooved fittings.
Install addressable building fire alarms systems that are compatible with the base
system and connect to the base reporting system.
Install smoke detectors in accordance with UFC 3-600-01, Fire Protection Engineering
for Facilities and NFPA 72, National Fire Alarm and Signaling Code.
78
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 3-21 Standard Face and Longitudinal Flue Sprinkler Mounting
79
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
3-16 ELECTRICAL
3-16.1 Power
Provide separate dedicated panel boards to serve each separate user area.
Serve shop spaces by distinct panels dedicated to shop and equipment loads only. Do
not supply office spaces from shop circuits or panels. Except as specifically noted
otherwise, feed loads located in each Shop space must be from panel boards located
within the Shop space.
3-16.3 Lighting
Design in accordance with UFC 3-530-01, Design: Interior and Exterior Lighting and
Controls.
Provide lighting at parking lots, maneuvering areas, outride storage, and, where
required, fence lighting.
3-16.4 Receptacles
Provide lightning protection in accordance with UFC 3-575-01 Lightning and Static
Electricity Protection Systems.
3-17 CIVIL
Refer to UFC 1-200-01, General Building Requirements and UFC 3-201-01, Civil
Engineering for physical security, antiterrorism, standoff distances, setbacks, Low
Impact Design (LID), storm drainage, geotechnical site investigation, vehicular and
pedestrian circulation, and other site related requirements.
3-17.1 Siting
When siting the Warehouse, place emphasis on operation, function, energy efficiency
and safety. Comply with the requirements of UFC 1-200-01, General Building
Requirements.
81
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
hazards, natural and man-made obstructions, adjacent land use and accessibility of
utilities. Vehicular parking, pedestrian access and traffic flow must also be given careful
consideration.
Truck traffic must be separated from other vehicular traffic. Truck delivery routes must
be planned so drivers are not backing up to the dock on their blind side. Truck arrival
route must be counterclockwise to the facility.
3-17.2 Utilities
Provide metering in accordance with UFC 1-200-02, High Performance and Sustainable
Building Requirements.
Refer to UFC 1-200-01, General Building Requirements and UFC 1-200-02, High
Performance and Sustainable Building Requirements for minimum requirements and
guidance to achieve high performance and sustainable facilities.
82
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
CHAPTER 4 HAZARDOUS MATERIALS STORAGE GENERAL DESIGN CRITERIA
4-1 GENERAL
Reference UFC 1-200-01; General Building Requirements for Use and Occupancy
requirements.
Space justified for hazardous materials storage must be considered a portion of the total
space allowed for the facility type. Use DoD Real Property Classification System
(RPCS); Category Codes 441-10 through 441-40 facility types. Such space must not
exceed 5 percent of the total space unless justified. Hazardous materials storage must
be designed and constructed in accordance with the standard references listed in the
paragraph in Chapter 4 entitled, “General” for storage of materials classified as
hazardous to health, environment, and property, i.e., flammables, acids, caustics,
oxidizers, water reactives, or others considered hazardous by the following Code of
Federal Regulations (CFR's): Title 29 CFR 1910, Occupational Safety and Health
Standards; 40CFR - Protection of Environment; 49CFR - Transportation - parts 171-
177, Hazardous Materials Safety; and FED-STD-313, Material Safety Data,
Transportation Data, and Disposal Data for Hazardous Materials Furnished to
Government Activities.
Comply with \1\NFPA 400, Hazardous Materials Code and /1/the following federal,
industry, and association standards.
83
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
4-2.3 Design Criteria
Facility design and layout must take into consideration the incompatibility of hazardous
materials and hazardous materials groups. Individual facility design and layout must be
based upon the specific types and categories of hazardous materials that are to be
handled and stored.
Electrically powered materials handling equipment is the only type of powered material
handling equipment rated for use in hazardous materials storage areas. Use vehicles
which have all electrical equipment completely enclosed in hazardous materials
warehouses. Type EX vehicles, which have all fittings and equipment, designed,
constructed, and assembled for use in atmospheres containing flammable vapors, dust;
and fibers, may be required for unique chemicals or applications. Verify the need for
any additional requirements which may be imposed by special storage conditions.
84
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
4-3 SEGREGATION OF MATERIALS
4-3.1.1.1 Flammable
Flammable liquids have a flash point below 100°F (38°C) and a vapor pressure not
exceeding 40 psi absolute (275 kPa) at 100°F (38°C). These liquids are also classified
as Class I liquids.
4-3.1.1.2 Combustible
Combustible liquids have a flash point of 100°F (38°C) or higher. Combustible liquids
are further classified as Class II for flash points at or above 100°F (38°C) and below
140°F (60°C), and Class III for flash points at or above 140°F (60°C).
4-3.1.2 Acids
Acids and acid mists and gases react with arsenides, borides, carbides, cyanides,
fluorides, phosphides, selenides, silicides, sulfides, sulfites, and tellurides to generate
toxic fumes. They also liberate hydrogen upon contact with metals and hydrides.
4-3.1.3 Oxidizers
Oxidizing materials are those chemicals which will decompose readily under certain
conditions to yield oxygen. They may cause a fire in contact with combustible materials,
may react violently with water, and when involved in a fire may react violently. Typical
oxidizers include: organic and inorganic peroxides, permanganates, chlorates,
perchlorates, persulfates, organic and inorganic nitrates, bromates, perbromates,
chromates, and dichromates.
4-3.1.4 Poisons
Poisons are materials that cause death by systemic poisoning rather than by corrosive
destruction of tissue. Under adverse conditions, such as a leak, spill, fire, or poor
85
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
ventilation, a common chemical or compound (e.g., ammonia) may be considered
poisonous.
4-3.1.6 Caustics
Caustics (alkalis) may liberate hydrogen upon contact with aluminum. They are not
compatible with acids and must be segregated from acids for safe and efficient
operations.
86
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 4-1 Hazardous Materials Storage Segregation Layouts
Plan Views
87
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
4-3.2.2 Drummed Petroleum/Oil/Lubricant (POL)
Drummed POL products with a flash point of more than 100°F (38°C) must be stored in
shed or open storage facilities with sealed pavements and berms/dikes to contain spills.
Outside storage for drummed POL may be used, provided the drums are of corrosion
resistant material or are hot-dipped galvanized for corrosion protection.
Means of providing containment and removal must be provided in the event of spills.
Refer to 29 CFR 1910.106 for additional information.
Exterior containment areas must be graded in a manner to divert possible spills away
from buildings or other exposures or be surrounded by a curb at least 6 inches high, see
paragraph in Chapter 4 entitled “Dikes”. When curbs are used, provisions must be
made for draining of accumulations of ground or rain water or spills of flammable liquids.
Drains are to terminate at a safe location and must be accessible to operation under fire
conditions.
Inside storage rooms must be constructed to meet the required fire-resistive rating for
their use. Such construction must comply with the test specifications set forth in
Standard Methods of Fire Tests of Building Construction and Materials, NFPA 251.
Openings to other rooms or buildings are to be provided with noncombustible liquid-tight
raised sills or ramps at least 4 inches in height or the floor in the storage area must be
at least 4 inches below the surrounding floor. Openings must be provided with
approved self-closing fire doors. The room must be liquid-tight where the walls join the
floor. A permissible alternate to the sill or ramp is an open-grated trench inside of the
room that drains to a safe location, see paragraph in Chapter 4 entitled “Floor Trenches
and Capture System”. Where other portions of the building or other properties are
88
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
exposed, windows must be protected as set forth in the Standard for Fire Doors and
Windows, NFPA No. 80.
4-4.3 Dikes
Dikes must be used for containment of spills for gasoline and/or diesel fork truck
refueling stations and commodities stored or handled outside of buildings. In
accordance with National Fire Protection Association (NFPA) Flammable and
Combustible Liquids Code, NFPA 30, their volume must be not less than 110% of liquid
that can be released from a fork truck or the largest storage container within the diked
area or a 10% minimum of all materials to be stored in the area, whichever is greater.
Where a continuous floor trench with grating is used in areas of hazardous materials
storage for the capture and control of hazardous chemical spills see figure 4-2. All spill
containment systems must provide separate containment as described in the paragraph
in Chapter 4 entitled, “Containment”. Secure grate frame support channels to concrete
floors. Grate design must provide for the ability to latch the removable grate sections at
aisle crossings and cargo doors to ensure that grates will remain firmly in place when
material handling equipment moves over them. The cross section of the grate frame
members must be "Z-", rather than "L-", shaped so that two legs of the "Z" form a pocket
for grates and the third leg is in the horizontal plane at floor level, as illustrated in figure
4-2. This protects the edges of concrete around grate frames from impact damage from
the wheels of materials handling equipment.
Where a trench passes in front of a personnel door use \1\concrete cover or solid
concrete plates sufficient /1/ to prevent a fire in the trench from blocking the exit door.
89
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 4-2 Spill Capture/Containment System
90
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
Figure 4-3 Electronic Guide Wire Crossing
91
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
When required for specific design or containment needs, interior storage floor surfaces
may be recessed 6 inches (150 mm) below the level of adjoining dock, office, and
support areas to prevent the flow of spilled hazardous liquids into these areas. Vehicle
access ramps must be provided at all doorways into such areas. The use of this
method is discouraged due to operational inefficiencies and the additional space
requirements caused by the ramps.
4-4.6 Containment
Use grate-covered interior 350 gallon (1323 l) sumps in conjunction with the trench
system to provide spill or leakage containment for the lesser of 1,000 gallons (3785 l) or
10 percent of the total free flowing liquid volume of all containers stored in each
segregated area. Provide a containment capacity of 1,000 gallons (3785 l) at the truck
apron adjacent to the shipping and receiving area. Include a controlled flow system to
prevent spilled or leaking materials from entering the environment.
4-4.7 Drainage
Install pallet racks and associated mechanical vehicle guidance systems so as to permit
the unimpeded flow of spilled liquids to collecting trenches. Maintain floor flatness
requirements. Floor drains connecting to the sanitary sewer are not permitted in
storage areas of hazardous materials.
92
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
APPENDIX A REFERENCES
http://www.aamanet.org/
http://www.concrete.org/
http://www.ansi.org/
ANSI MH27.1, Specifications for Patented Track Underhung Cranes and Monorail
Systems
http://www.astm.org/
Title 29 CFR 1910.23, Guarding Floor and Wall Openings and Holes
Title 29 CFR 1910.144, Safety Color Code for Marking Physical Hazards
Title 29 Code of Federal Regulations (CFR) Part 1910, Occupational Safety and Health
Standards
http://www.mhi.org/cmaa
CMAA Specification 70, Top Running Bridge and Gantry Type Multiple Girder Electric
Overhead Traveling Cranes
CMAA Specification 74, Top Running and Under Running Single Girder Electric
Overhead Cranes Utilizing Under Running Trolley Hoist
Air Force Instruction (AFI) 91-203, Air Force Consolidated Occupational Safety
Instruction
DoD Instruction 6055.1, DoD Safety and Occupational Health (SOH) Program,
http://www.dtic.mil/whs/directives/
FED-STD-313, Material Safety Data, Transportation Data, and Disposal Data for
Hazardous Materials Furnished to Government Activities,
http://www.wbdg.org/ccb/FEDMIL/fedstd313d.pdf
94
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
UNIFIED SERVICE BRANCH CRITERIA
Army TM 38-400/ Navy NAVSUP PUB 572/ Air Force AFJMAN 23-210/ Marine Corps
MCO 4450-14/ Defense Logistics Agency DLAM 4145.12, Joint Services Manual
(JSM) for Storage and Materials Handling
Armed Forces Pest Management Board Technical Guide No. 17, Military Handbook –
Design of Pest Management Facilities.
http://www.afpmb.org/sites/default/files/pubs/techguides/tg17.pdf
http://dod.wbdg.org/.
UFC 2-000-05N (P-80), Facilities Planning Criteria for Navy/Marine Corps Shore
Installations
95
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
UFC 3-450-01, Noise and Vibration Control
UFC 3-580-10 Navy and Marine Corps Intranet (NMCI) Standard Construction Practices
http:/www.iccsafe.org
http://www.paintinfo.com/
MPI 212, Floor Coating, Thin Film, for Aircraft Maintenance Facilities
96
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
NATIONAL FIRE PROTECTION ASSOCIATION
http://www.nfpa.org/
NFPA 430, Code for the Storage of Liquid and Solid Oxidizers
Interim Technical Design Guidance ITG FY05-02, NAVFAC Humid Area HVAC Design
Criteria, http://www.wbdg.org/ccb/NAVFAC/INTCRIT/fy05_02.pdf
Navy Crane Center Instruction 11450.2, Design of Navy Shore Weight Handling
Equipment,
https://portal.navfac.navy.mil/portal/page/portal/docs/doc_store_pub/navcranecen%2
0instruction%2011450.2.pdf
http://www.steeldoor.org/
UNDERWRITER’S LABORATORY
http://www.ul.com
UL325, Door, Drapery, Gate, Louver, and Window Operators and Systems
97
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
98
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
B-1 GENERAL
This appendix identifies background information and practices for accomplishing design
and engineering services. The Designer of Record (DOR) is expected to review and
interpret this guidance and apply the information according to the needs of the project.
If a Best Practices document has guidelines or requirements that differ from the UFGS
or UFC, the UFGS and the UFC must prevail. If a Best Practices document has
guidelines or requirements that are not discussed in the UFGS or UFC, the DOR must
submit a list of the guidelines or requirements being used for the project with sufficient
documentation to the Government Project Manager for review and approval prior to
completing design.
The WBDG provides access to Construction Criteria Base (CCB) criteria, standards and
codes for the DoD Military Departments, National Aeronautics and Space Administration
(NASA), and others. These include, UFC, UFGS, Performance Technical Specifications
(PTS), design manuals, and specifications. For approved Government employees, it
also provides access to non-government standards.
Comply with UFC (Latest Version), FC, and other related criteria as noted in UFC 1-
200-01, General Building Requirements under the heading “UNIFIED FACILITY
CRITERIA”.
99
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
100
UFC 4-440-01
1 April 2014
Change 1, 1 April 2019
APPENDIX C GLOSSARY
101