0. INTRODUCTION
This Engineering Standard covers the minimum requirements of all engineering aspects of instrumentation which are
common to various instruments. The Standard is contained in four parts as listed below:
Part Two: The Division of Responsibilities between Instrument and Engineering Disciplines
1
IPS-E-IN-100
PART I
AND
METHODS OF SAFEGUARDING
2
IPS-E-IN-100
1. SCOPE ..................................................................................................................................... 5
2. REFERENCES ......................................................................................................................... 5
3
IPS-E-IN-100
7. INTRINSIC SAFETY............................................................................................................... 16
8. FLAME-PROOF HOUSINGS.................................................................................................. 21
9. PURGING FOR REDUCTION OF HAZARDOUS AREA CLASSIFICATION...................... 21
9.1 Purging Classifications ................................................................................................. 21
APPENDICES:
4
IPS-E-IN-100
1. SCOPE
This Standard provides general guidance for the safe installation of electrical instruments using appropriate means to
prevent ignition of flammable gasses and vapors mixed with air under normal atmospheric conditions. It is intended to
be applied in petroleum industries of Iran.
2. REFERENCES
In preparation of this Standard, the following standards and publications have been considered:
IP (INSTITUTION OF PETROLEUM)
500 C "Classification of Areas for Electrical Installations at Petroleum & Gas Pipeline Transportation
Facilities"
5
IPS-E-IN-100
SECTION ONE
HAZARDOUS AREA CLASSIFICATION
3. GENERAL CONSIDERATIONS
3.1 Electrical equipment in petroleum industries require special precautions to prevent or contain safely any explosion
caused by ignition of vapors which have penetrated from outside into the equipment housing.
3.2 For electric instrumentation, the problem is aggravated because measuring elements containing flammable process
fluids are often located in the housing for the electric components, a typical example is a pressure switch. Failure of the
measuring element may mean an explosion, unless the electric components have been selected to prevent this.
3.3 Allowable techniques for coping with the above hazards, such as application of intrinsically safe circuits, flame-
proof housings etc., depend on the area classification, as will further detailed in the following chapters.
3.4 For recommendation on area classification in Petroleum Industries or applications, reference should be made to the
"Electrical Safety Code" Part I, "Model Code of Safe Practice in Petroleum Industry".
3.5 For determining the extent of the various types of dangerous area, such as distance in horizontal and vertical direc-
tion from potential sources of flammable gas and vapor, refer to the IP Code. The influence of future plant extensions on
adjacent plots shall be taken into account, when plans are known in sufficient detail.
3.6 For each project, an area classification drawing which is made by the relevant specialists, shall form the basis for
considering instrumentation-aspects.
3.7 The area classification drawing will only indicate the conditions around the instruments, but the situation inside
the instrument housing may be more dangerous in case of failure of the measuring element. The more onerous of the
two classifications should determine the appropriate execution.
The following section outlines the procedures for the classification of areas for the selection and installation of electrical
equipment. Unprotected electrical equipment would be a potential ignition hazard in certain areas of the installation. For
the selection of appropriate and safe electrical equipment, and its sitting in any oil facility, control is exercised by means
of ’Area Classification’, a procedure whereby the different zones of an installation or plant are set out in accordance
with the International Electrotechnical Commission nomenclature, IEC 79-10. The definition of hazardous area in this
context, and its converse, is as follows:
An area in which explosive flammable gas-air mixtures are, or may be expected to be, present in quantities such as to
require special precautions for the construction and use of electrical apparatus.
An area in which explosive/flammable gas-air mixtures are not expected to be present in quantities such as to require
special precautions for the construction and use of electrical apparatus.
6
IPS-E-IN-100
4.3.1 A flammable gas or vapor mixed with air in the proportions required to produce an explosive gas-air mixture.
Only means of ignition related to electrical apparatus are taken into consideration. These are arcs or sparks or surfaces at
a temperature sufficient to ignite the mixture. In order to facilitate the selection of appropriate electrical apparatus, haz-
ardous areas may be divided into classified Zones.
Hazardous areas are classified in zones based upon the frequency of the appearance and the duration of an explosive gas
atmosphere as follows:
5.1.1 Zone 0
An area in which an explosive flammable gas-air mixture is present continuously or is present for long periods.
The vapor space of a closed process vessel or storage tank or above an oil-water separator basin is an example of this
Zone.
5.1.2 Zone 1
The vicinity surrounding vents and gaging openings on a fixed-roof tank containing Class I petroleum products is an
example of this category.
5.1.3 Zone 2
An area in which an explosive gas-air mixture is not likely to occur in normal operation and if it does occur, it will only
exist for a short period.
An example is the whole area inside the bund wall of a fixed or floating-roof tank containing Class I petroleum prod-
ucts, and to the height of the bund wall.
Because of the lower probability of a Zone 2 occurrence, less stringent protection will be required for electrical equip-
ment suitable for Zone 2 installation.
A block diagram represents schematically the zone classification of hazardous areas, is shown in Appendix A.
7
IPS-E-IN-100
5.2.1 Division 1
The criterion for these locations is that; hazardous concentration of flammable gases or vapors continuously intermit-
tently or periodically present under normal operating conditions.
5.2.2 Division 2
The criterion for these locations is that; volatile flammable liquids or flammable gases present, but normally confined
within closed containers or system from which they can escape only under abnormal operating or fault conditions.
The Institute of Petroleum has revised its classification for petroleum products to be consistent with the system that is
adopted within the Europe.
The IP classification is based on closed-cup flash points which has been shown in the Table 1 below: Flash point is the
minimum liquid temperature at which, under certain standardized conditions, a liquid gives off sufficient vapors to form
an explosive vapor/air mixture.
TABLE 1 - IP CLASSIFICATION
IP CORRESPONDING UK AND
CLASSIFICATION RANGE OF LIMITS EEC LEGAL TERMINOLOGY
Class 0 Liquefied Petroleum Gas (LPG) Liquefied Petroleum Gas
Class I Liquids which have a flash point below 21°C Highly Flammable Liquid
Class II Liquids which have a flash point from 21°C up to Flammable Liquid
and including 55°C
Class III Liquids which have a flash point above 55°C up to Combustible
and including 100°C
Unclassified Liquids which have a flash point above 100°C (No designation, but will burn under
appropriate conditions.)
The extent of a hazardous area may increase with increase of temperature of process liquid provided the temperature is
above the flash-point. It should be noted that the liquid or vapor temperature after the release may be increased or de-
creased by the ambient temperature or other factors (e.g. a hot surface).
6.1.2 Subdivision of the classification for high ambient temperatures and for heated products
For locations where ambient temperatures are high enough for the normal handling of products to rise above 21°C, e.g.
in tankage, or in circumstances where products are handled artificially heated, it is necessary to introduce a further sub-
division of the classification. For example, kerosene with a flash point, say, of 38°C, would be classified as ’Class II’
petroleum for ambient handling in a temperate climate, since its vapor would be too lean to create a flammable atmos-
8
IPS-E-IN-100
phere; handled in a tropical location its temperature could rise to above the level of its flash point, creating a potential
flammable condition e.g. in the vapor space of a fixed-roof storage tank.
For this reason, in the IP Codes Class II and Class III categories of petroleum are further subdivided in accordance with
the circumstances as follows:
Class II (1) Liquids which have flash points from 21°C up to and including 55°C, handled below flash
point.
Class II (2) Liquids which have flash points from 21°C up to and including 55°C, handled at or above
flash point.
Class III (1) Liquids which have flash points above 55°C up to an including 100°C, handled below flash
point
Class III (2) Liquids which have flash points above 55°C up to and including 100°C, handled at or above
flash point.
This subdivision is used as follows in conjunction with the IP Codes of Safe Practice:
Where liquids to be handled are in the category Class II (1) or Class III (1), i.e. at temperatures below their flash point,
appropriately less stringent conditions of safety spacing and related precautions are given in the codes than are applica-
ble for Class I products i.e. highly flammable liquids.
When Class II or III products fall into the Class II (2) or III (2) category, they are treated as though they were in Class I.
This system of classification enables requisite guidance to be given, and readily understood and followed in the codes,
both for design and subsequent operation.
If the flash point is in excess of 100°C, then is called unclassified. "Unclassified" petroleum liquids should be consid-
ered as Class III (2) when handled under this condition.
Various factors must be taken into consideration when classifying an area. The main considerations are:
a) Source of hazard
b) Ventilation
c) Nature of hazard
The source of hazard is a point from which a flammable substance may be released into the atmosphere. There are three
basic grades of source of release as listed below in order of decreasing likelihood of the release occurring:
- Continuous grade
- Primary grade
- Secondary grade
A source of release may be one of the above three grades, or may be a combination of two or three, in which case it is
regarded as a multi-grade source of release.
9
IPS-E-IN-100
A source which will release continuously or is expected to release for long periods or for short periods which occur
frequently.
a) Machinery and plant which can release a flammable substance into the atmosphere during normal operation.
b) Equipment containing a flammable substance and constructed of material liable to easy breakage.
Machinery or plant which can release a flammable substance into the atmosphere during abnormal (leakage or bursting)
or infrequent operations for short periods. The source of releases are represented graphically as Figs. 1, 2 and 3.
The following is a schedule or examples of recognized sources of release but in no way is it claimed to be complete as
the design and development of new and modified equipment is a continuous process which frequently involves the use
of new materials etc. A constant review of all equipment used is therefore absolutely necessary.
When a tank is being filled vapor can be discharged-appropriate to the rate of filling-from any of the above referred to
openings which are not sealed at the time.
Discharge of vapor can also occur at other times due to a change in temperature or, if a dip hatch is opened when a tank
is above atmospheric pressure. Tank filling can occupy a relatively extended period of time and is a normal operation
that gives rise to a primary grade source of release of flammable vapor to atmosphere.
The roof-to-tank seal is normally vapor tight but vapor may accumulate above the roof within the tank shell when the
tank is being emptied. Since the roof, when traveling downward, leaves a wetted area of shell so giving rise to a primary
grade source of release. Normally there is sufficient wind to disperse such vapor but the source of release is nevertheless
classed as primary.
In plants and installation where products are handled below their boiling point the above do not normally give rise to
primary grade sources of release. A secondary grade source of release could occur where the valve stem or spindle
passes through the packing gland or seal or where a flange gasket fails.
The external surface of the immersed length of the arm will be wet as it is withdrawn from the vessel which has been
filled. The internal surface of the arm will also be wet. The wetted surfaces will drain so giving rise to other small wet-
ted areas as the arm is returned to the "rest" position.
Relief valves do not create sources of release unless they vent to atmosphere.
10
IPS-E-IN-100
6.2.2.6 Filters, sample points, air bleed points and pig traps
a) When filters are opened for cleaning, a wetted surface will be exposed and spillage may occur.
b) Sample points should be designed to prevent loss of constituents of the sample. The flow should, where prac-
tical, be restricted in order to limit the rate of loss if the sample point is accidentally left open. Samples should be
small and delivered if possible into a closed system. Release of flammable vapor should consequently be small
and infrequent.
c) Air bleed points are only fitted at high positions in piping systems and are normally in well-ventilated situ-
ations. Their use is infrequent, usually during commissioning and recommissioning and they should be plugged
or blanked off when not required.
Leakage can occur if a valve is not properly re-seated. Flow rate during operation of such valves should be re-
stricted but even so consideration should be given to the possible release of liquid and a consequent wetted area.
d) Pig traps give rise to three possible sources of release namely the air vent, the drain-line to a sump and the
exposed wetted area of the internal surface of the trap, when opened. This includes the pig and any discharged
debris. All the above are secondary grade sources of release.
In combination the above can form an oil/water effluent system and therefore require very careful consideration both
separately and jointly since spillage in one area can be transmitted through to other areas. Slop facilities usually com-
prise a tundish-type entry to a closed piped system, leading in turn to a storage tank. Spillage may occur which gives
rise to a secondary grade source of release.
The initial rate of evaporation from ground spillage will be high with low flash point material and will then decrease
assuming no replenishment by continued spillage. The area affected by the above secondary grade source of release will
extend above and beyond the total surface area of the spillage.
6.2.3 Ventilation
The dilution of a flammable gas with air will depend upon the degree of ventilation and upon the amount of ignitible
gas, or vapor available to replace the gas being diluted.
It follows from the above that there are two extreme conditions. A hazardous Zone 0 in which an explosive gas-air mix-
ture can be present either continuously or for an appreciable time in an enclosed space, hence a source of ignition must
be completely avoided; and a non-hazardous zone where a source of ignition is permissible because an explosive gas-air
mixture is not expected to be present.
a) Zone 1
In which an explosive gas-air mixture may be present under normal operating conditions (although every effort
would normally be made to minimize such a likelihood).
This situation requires the installation of protected-type electrical equipment which will not give rise to a source
of ignition (for a free flammable atmosphere) under normal or fault conditions.
b) Zone 2
In which an explosive gas-air mixture would only be present under abnormal conditions for a short time.
11
IPS-E-IN-100
This situation requires the installation of protected-type electrical equipment which will not give rise to a source
of ignition for a free flammable atmosphere in normal operation but which could do so in electrical fault condi-
tions despite precautions to minimize the likelihood. In this case the probability or a flammable atmosphere and
an electrical source of ignition being present simultaneously is very low.
Examination of the circumstances and total environment surrounding each possible source of release will indicate how
quickly the flammable vapor can be expected to disperse. For example if ventilation is good a hazardous situation may
remain for only the duration of the release and in this case a secondary grade source of release would give rise to a Zone
2 area, since the period of release would be short and infrequent.
A release of flammable substance may occur as gas, liquid, vapor or a combination of three. It is necessary to decide at
what distance from the source the vapor will have diffused in air to a mixture that cannot be ignited i.e., the distance at
which it passes the lower explosive limit. Consideration must therefore be given to:
a) The quantity of material released, if over a short period, or the rate of release.
b) The conditions of the release. Namely temperature and properties of the product, local ambient temperatures
and ventilation rate.
c) The rate of evaporation and the distance the vapor cloud will travel before dilution to below the lower explo-
sion limit.
An indication of the evaporation rate can be obtained from the vapor pressure of the product release as the evaporation
rate-including that for a mixture of hydrocarbons-depends upon its volatility. It will also depend upon the temperature of
the substance released and the temperature of the atmosphere into which it is released.
Dilution of the vapor from the flammable substance can occur due to:
All electrical equipment to be used in Zones 0, 1 and 2 must comply with the relevant standards for these Zones.
Whilst the classification described is for the selection of the correct electrical equipment and installation for each haz-
ardous zone, the same classification will apply when ignition sources arising from other than electrical equipment are
considered.
In Zone 0 and Zone 1 areas all items of equipment should be considered very carefully to establish if they could form an
ignition source and if so they must be omitted.
In Zone 2 areas it is recommended that no plant, equipment or facilities should be used giving rise to fire, capable of
producing sparks or generating temperatures higher than the auto-ignition temperature of the gas-air mixture present.
Full consideration must be given to all other factors which may influence the final classification for the purpose con-
cerned.
12
IPS-E-IN-100
The hazardous zones around all possible sources of release which could arise from the gantry equipment and slop facili-
ties in the absence of a tank vehicle, should be assessed and a practical envelope devised.
Then with vehicles present and manlids open the additional zones which arise whilst vehicles are being filled should be
determined. These zones are transient and will not exist when the manlids are closed and the loading arms have been
returned to the parked position.
Spillages which could arise during tank vehicle filling and from other operations such as filter cleaning etc., should be
considered and zones determined appropriate to the rate and duration when these could occur in practice, bearing in
mind the degree of manual participation involved.
It is self evident that the whole arrangement must permit the movement of vehicles to and from the loading positions
and this must take place with the loading gantry and vehicle in a hazard-free state.
A detailed analysis of each of the above stages is given below leading to the final classification of the loading area for
the purpose of selecting the correct type of electrical equipment and installation.
The loading arms are a primary grade source of release and consequently a hazardous zone will extend from the
island base to a level above the walkway; the criteria being the height of the open end of the loading arm in the
parked position.
b) Filling of vehicles
At all times whilst a vehicle is in service the internal spaces of the compartments should be classified Zone 0
(Division 1).
c) Spillage
Spillage, a secondary grade source of release, can occur from fillers during routine servicing, from the compo-
nents of pipework systems, and overfilling of vehicle compartments.
The total hazardous area should include that within the means of containment plus an area beyond it for a hori-
zontal distance equal to seventeenths (0.7) of that across the contained area, all to a height of 1 m, and a Zone 2
(Division 2) classification is recommended.
Where no means of containment exists around the area it is recommended that the extent of the hazardous area be
determined on the basis detailed above as an extension beyond the maximum distance a spillage could be ex-
pected to run.
Typical installation-final classification shows the various hazardous areas derived from, (a, b and c), com-
pounded to give a practical arrangement. The Zone 1 area around the vehicle has been extended to allow for
drainage from the loading arm after it has been removed from the vehicle compartment to the parked position.
13
IPS-E-IN-100
A primary grade source of release will occur during the filling operation and if overfilling occurs there could be a secon-
dary grade source of release. It is therefore recommended that the Zone 1 (Division 1) area around the vehicle be similar
to that for top loading.
A primary grade source of release occurs whilst the rail car is being loaded due to vapor emission from the open
or venting manlids.
Primary and secondary grade sources of release occur from the loading arms when being removed from the rail
car to the parked position, from spillages due to overfilling and from filters and other associated equipment.
Sealed couplings are normally used from which a secondary grade source of release may occur due to leakage.
Secondary grade sources of release can arise due to accidental spillage, when couplings are broken and from fil-
ters and associated equipment.
6.3.3 Tankage
The tanks covered by this example are either free venting or low pressure fitted with pressure/vacuum valves.
The ullage space should be classified Zone 0 (Division 1), irrespective of whether a floating or inert gas blanket
is present.
Primary grade source of release may occur above the tank roof and therefore the space above the roof and within
the tank shell should be classified Zone 1 (Division 1). When the roof travels upwards, vapor will be displaced
and diffusion will occur into the atmosphere above and around the tank. It is recommended therefore that an area
above the tank shell for a distance of 2 m, extending 2 m horizontally beyond the tank shell and down to ground
level should be classified Zone 2 (Division 2).
If the floating roof tank has a double wall, the outer wall acting as a bund, then the annular space between the
walls should be classified Zone 1 (Division 1). The Zone 2 (Division 2) area above the tank should be extended
horizontally to a point 2 m beyond the outer wall and then vertically downwards to the ground.
Pump platforms and open buildings are considered to be well ventilated situations. Any equipment installed usu-
ally gives rise to secondary grade sources of release.
A secondary grade source of release can occur from a flanged joint due to gasket failure. Flange joints most
likely to leak include those subject to sharp changes in temperature, mechanical stress due to pipe movement,
high pressure and those that are broken and remade at frequent intervals.
The extent of the hazardous area that can be expected from a flange gasket failure should be determined from a
knowledge of all the pertinent conditions.
Pump suction strainers which are opened for servicing may involve some spillage and the wetted surfaces of the
component parts and debris would give rise to secondary grade sources of release.
14
IPS-E-IN-100
Provided that the sources of release are those associated with the pump platform or open building then it is rec-
ommended that the whole area of the platform or building be classified Zone 2 to a height of 2 m above the
platform surface and, if an elevated platform, down to ground level irrespective of the type of flooring. The posi-
tion of flanges and valves relative to the extremities of the above area must be considered and the Zone 2 (Divi-
sion 2) area enlarged local to them.
The installation of pumps handling flammable materials within enclosed buildings is not recommended. How-
ever, when unavoidable the whole of the inside of the building should be classified Zone 1 (Division 1), since the
continuous dilution of any flammable vapor cannot be guaranteed. Openings in the building to the outside atmos-
phere should be considered as secondary grade sources of release and an area extending 3 m in all directions and
down to ground level from the edges of the opening should be classified Zone 2 (Division 2).
f) Manifolds
Manifolds in pipework systems such as those associated with pump platforms are usually in freely ventilated
situations.
Secondary grade sources of release only are likely to occur from valves, flanged joints, vents and drain valves.
Consequently a source of release can only be expected under abnormal conditions or under controlled conditions.
It is recommended that the manifold area, extended a distance of 2 m in all directions and down to ground level
when measured from the extreme outer possible sources of release, should be classified Zone 2 (Division 2).
Pits and trenches below ground level within the above area should be classified Zone 1 (Division 1) as they can-
not be considered freely ventilated and heavier than air vapors could accumulate within them.
If the manifold system contains line-pig or sphere reception facilities and has associated pit and open drainage
system as may be employed at pipeline-supplied terminals, then the above constitute primary grade sources of
release. It is recommended that the area extending 3 m horizontally from the open drainage system, 3 m upwards
from the highest source of release and down to ground level should be classified Zone 1 (Division 1).
15
IPS-E-IN-100
SECTION TWO
METHODS OF SAFEGUARDING
7. INTRINSIC SAFETY
7.1 An Intrinsically Safe (IS) instrument or circuit is an arrangement of instruments and wiring incapable (under nor-
mal or abnormal conditions) of releasing sufficient energy to cause ignition of a specific hazardous mixture in its most
easily ignited form at atmospheric pressure.
7.2 Only those instruments shall be used, which carry a certificate of intrinsic safety for the type of gas to be expected
in its intended location (refer to Appendix B). Moreover, it must be ensured that this certificate has been (or will be)
accepted by the Company regulations
7.3 For process instrumentation, the certificate of intrinsic safety shall be valid for field mounted instruments and the
related circuits extending to the control centers at safe areas.
7.4 When instruments, data loggers, computers, etc., without an IS certificate are to be connected to instrumentation in
hazardous areas, application of safety-barriers (with valid certificate) shall be considered to make the external circuit
intrinsically safe.
These safety-barriers restrict the maximum possible spark-energy, and consequently have more in-line resistance for
higher operating voltages.
Shunt-diode barriers are therefore only suitable for low-level signals, e.g., thermocouples, or electric signals in the milli-
amp, range for electronic instrumentation. Where switches mounted in hazardous areas are required to control higher
power, e.g., for operating relays in non-IS alarm and control systems, the use of other safety barriers, such as interposing
relays with IS, certificate shall be considered.
7.5 The housing of IS field-mounted instruments, components, and the associated cable gland(s) shall be weather-proof
and (where necessary) water-tight.
7.6 Some examples of the various configurations of intrinsically safe systems are given in Fig. 1.
16
IPS-E-IN-100
** Other enclosure may be shielded cable, metal-clad cable, or any mechanical or electrical protection that en-forces separa-
tion of intrinsically safe circuits from circuits that are not intrinsically safe.
17
IPS-E-IN-100
* IS Terminals.
7.7.1 A switching device is shown in Fig. 2. If a common fault voltage occurs at Terminals A, B, C, and D when all the
switch contacts are closed and if a simultaneous fault to ground occurs at point F, it is possible to get five times the
maximum current of any one barrier. Unless the barrier control drawing permits five barriers to be paralleled, this circuit
configuration is not acceptable.
18
IPS-E-IN-100
* IS Terminals.
7.8.1 Where intrinsically safe wiring may be exposed to disturbing magnetic or electric fields, it shall be twisted,
shielded, or other suitable methods implemented to prevent the energy level of the intrinsically safe wiring from becom-
ing ignition-capable.
7.8.2 When several devices having both intrinsically safe and nonintrinsically safe terminals are mounted in the same
enclosure, attention must be given to the separation of circuits. An acceptable method of separation is shown in Fig. 3.
Separate raceways are often used to provide greater assurance that separation of wiring will be maintained. Wire lacing,
wire ties, or equivalent fasteners are also acceptable methods of separating wiring.
19
IPS-E-IN-100
20
IPS-E-IN-100
8. FLAME-PROOF HOUSINGS
8.1 A flame-proof housing for electrical apparatus will withstand, without injury, any explosion of the prescribed flam-
mable gas or vapor that may occur within it, and will prevent the transmission of flame such as will ignite the prescribed
flammable gas or vapor which may be present in the surrounding atmosphere.
8.2 Flame-proof certificates are issued for separate groups of gases, according to the grade of risk. For segregation of
groups refer to Appendix B.
In general apparatus certified for the higher group will cover situations where gases from the lower groups are present.
8.3 Flame-proof housings have been carefully designed for pressure release and flame-quenching openings, and conse-
quently these housings are usually not weather-proof. Where weather-proofing is required for protection of the internals,
this shall not interfere with the basic features. The use of gaskets is permissible only where these are applied to a joint
additional to the flame-proof joint and do not interfere with its function.
The addition of air or inert gas (such as nitrogen) into the enclosure around the electrical equipment at sufficient flow to
remove any hazardous vapors present and sufficient pressure to prevent their re-entry, shall be considered for hazardous
area classification reduction.
This covers purging requirements adequate to reduce the classification within an enclosure from Division 2 (normally
non-hazardous-Zone 2) to non-hazardous.
This covers purging requirements adequate to reduce the classification within an enclosure from Division 1 (hazardous-
Zone 1) to Division 2 (normally non-hazardous).
This covers purging requirements adequate to reduce the classification within an enclosure from Division 1 (hazardous-
Zone 1) to non-hazardous.
All type of purging systems shall be engineered and made to prevent flammable material from entering the enclosure by
maintaining at least 2.5 mm of water, positive pressure inside the enclosure. All other requirements as specified in
ISA/S 12.4 shall be fulfilled in purged systems.
Note:
21
IPS-E-IN-100
9.2.1 This Standard applies to instrument enclosures not exceeding 0.3 cubic meter.
9.2.2 In like manner for purposes of this Standard the ratio of the maximum internal dimension to the minimum shall
not exceed 10 to 1.
9.2.3 An internal enclosure or an adjacent enclosure that is being considered as part of and purged with the main in-
strument enclosure must have nonrestricted top and bottom vents, common to the purged main enclosure, having a mini-
mum size for each vent of 645 mm² per 6555 mm³ of the volume of the internal or adjacent enclosure.
9.2.4 Enclosure shall be of non-combustible material and construction not likely to be broken under conditions to
which it may be subjected.
9.2.5 Any window in a purged enclosure shall be of a material that is resistant to breakage such as 6.35 mm tempered
glass or equivalent.
9.2.6 If hazardous gases or vapors have been collected within the enclosure, either because the door has been opened
or the purge has failed, then enclosure must be purged before power is applied. Once purged of hazardous concentration,
it is not obligatory to maintain any given flow rate. It is only necessary that positive pressure be maintained within the
case.
9.2.7 Since the intent is to purge an enclosure to reduce the concentration of hazardous gases or vapors to an accept-
ably safe level, enclosures within the instrument or adjacent enclosures connected to the instrument must be considered
separately.
9.2.8 If the enclosure is opened or if a failure occurs within the purging system, the purging system pressure may not
be adequate to exclude the entrance of flammable gases or vapors. Suitable precautions such as indicators, interlocks,
etc., must therefore be provided to safeguard the installation.
9.2.9 The purging supply shall be essentially clean and free of dust and liquids. It shall contain no more than trace
amounts of flammable vapors or gases.
9.2.10 Instrument air is acceptable as well as other suitable gas such as inert gas. Ordinary plant compressed air is
usually not suitable.
9.2.11 The compressor intake must be located in a non-hazardous area. The compressor suction line should preferably
not pass through any area having hazardous atmospheres.
For the use of purging to reduce the classification of the area within an instrument from Zone 2 (Division 2 normally
non-hazardous) to non-hazardous.
9.3.1.1 Before power is turned on, at least four enclosure volumes of purge gas must have passed through the enclo-
sure while maintaining an internal enclosure pressure of at least 2.5 mm of water.
Exception:
Power may be turned on immediately if a pressure of at least 2.5 mm of water exists and if the atmosphere in the enclo-
sure is known to be non-hazardous.
22
IPS-E-IN-100
9.3.1.2 The enclosure must be maintained under a positive pressure of not less than 2.5 mm of water when the power is
on.
9.3.1.3 Under normal operation and with 125 per cent of rated voltage applied to the instrument, the external enclosure
temperature or the temperature of the engress air shall not exceed 80 percent of the ignition temperature of the vapor or
gas involved.
9.3.1.4 Safety interlocks to remove power upon failure of purging supply are not required.
9.3.1.5 Acceptable installations are shown in Figs. 4.1, 4.2 and 4.3.
9.3.1.6 An alarm or indication of purge system failure must be provided. The audible or visual device may be me-
chanical, pneumatic or electric/electronic as follows:
b) To avoid plugging when a pneumatic device is used, any restrictions between the pneumatic device and the
enclosure shall have passages no smaller than the smallest passage before the pneumatic device.
c) No valve between the alarm or indicator and the enclosure shall be permitted.
d) The pressure or flow device must be capable of indicating (or actuating an alarm) when the purging pressure
or flow is inadequate to maintain a static pressure within the enclosure of 2.5 mm of water.
23
IPS-E-IN-100
Fig. 4.3
24
IPS-E-IN-100
9.3.1.7 A red warning nameplate must be mounted on the instrument. The name-plate shall be mounted in a prominent
location and be visible before the enclosure is opened. It shall state:
a) Enclosure shall not be opened unless area is known to be non-hazardous or unless the power has been re-
moved from all devices within the enclosure.
b) Power shall not be restored after enclosure has been opened until enclosure has been purged for x minutes.
(Period to be specified by manufacturer.)
9.3.1.8 The maximum operating temperature of any internal surface exposed to the atmosphere within the enclosure
shall not exceed 80 percent of the ignition temperature (°C) of the gases or vapors involved under normal operating
conditions and at 125 per cent of rated voltage. If any temperature exists over 80 per cent of the ignition temperature of
the gases or vapors involved, then:
a) The warning nameplate shall contain a statement that such conditions exist and that power must be removed
for x minutes (period to be determined and specified by the manufacturer to be sufficient to permit unit to cool to
safe limit) before the door is opened unless the area is demonstrated to be non-hazardous at the time, or
b) The hot component may be separately housed so that the temperature of its housing is below safe limits. This
housing shall be purged or sealed and provided with a warning name-plate that its cover may not be removed for
x minutes (period to be determined and specified by manufacturer), unless the area is demonstrated to be non-
hazardous at that time.
For the use of purging to reduce the classification of the area within an instrument from Zone 1 (Division 1-hazardous)
to Zone 2 (Division 2-normally non-hazardous).
9.3.2.2 Precautions must be taken to insure that a malfunction (short circuit) between the power wiring and the enclo-
sure walls shall not burn through the enclosure or otherwise raise the external surface temperature to 80 percent of the
ignition temperature in °C of the gas or vapor involve a combination of fuse type (i.e., quick blow and medium blow),
fuse rating and thickness of case wall. Conformance of aluminum or steel cases with this requirement can be determined
by reference to Fig. 4.7. Other materials meeting the requirements will be equally acceptable.
For the use of purging to reduce the classification of the area with an instrument from Zone 1 (Division 1-hazardous) to
non-hazardous.
9.3.3.1 A timing device must be incorporated to prevent power being applied until after the elapse of a time sufficient
to permit at least four enclosure volumes of purge gas to have passed through the enclosure while maintaining an inter-
nal pressure of at least 2.5 mm (0.1 in.) of water. Timing device must meet the requirements of its location (timing to be
specified by manufacturer).
9.3.3.2 The enclosure must be maintained under a positive pressure of not less than 2.5 mm of water when the power is
on.
9.3.3.3 A device must be incorporated to automatically remove potential from all circuits or equipment within the en-
closure not suitable for Zone 1 (Division 1), upon failure of the purging supply.
9.3.3.4 A door switch must be provided to remove potential automatically from all circuits, within the enclosure not
suitable for Zone 1 (Division 1), if the enclosure can be readily opened without the use of a key or tools. The door
switch, even though located within the enclosure must be suitable for Zone 1 (Division 1) locations.
25
IPS-E-IN-100
9.3.3.5 The maximum operating temperature of any surface exposed to the atmosphere within the enclosure shall not
exceed 80 percent of the ignition temperature in °C of the gases or vapors involved under normal operating conditions
and at 125 per cent of rated voltage.
If any temperature exists over 80 percent of the ignition temperature in °C of the gases or vapors involved, the surface
having this temperature shall be enclosed within a chamber hermetically sealed against the entrance of gases or vapors.
9.3.3.6 Precautions must be taken to insure that a malfunction (short circuit) between the power wiring and the enclo-
sure walls shall not burn through the enclosure or otherwise raise the external surface temperature to 80 percent of the
ignition temperature in °C of the gas or vapor involved. Precautions involve a combination of fuse type (i.e., quick
blow, and medium blow) fuse rating and thickness of case wall. Conformance of aluminum or steel cases with this re-
quirement can be determined by reference to Fig. 4.7. Other materials meeting the requirements will be equally accept-
able.
9.3.3.7 Acceptable installations are shown in Figs. 4.4, 4.5 and 4.6.
9.3.3.8 The power cut-off switch provided to remove power upon failure of the purging system shall be either flow or
pressure actuated, and;
b) the pressure of flow device must be capable of cutting off power when the purging pressure flow is inade-
quate to maintain a static pressure within the enclosure of 2.5 mm of water. If a pressure device (Fig. 4.6) is used,
it must be capable of cutting off power if pressure exceeds predetermined safe limits;
c) to avoid plugging when a pneumatic device is used, any restrictions between the device and the enclosure
shall have passages no smaller than the smallest passage before the device;
d) no valve between the alarm or indicator and the enclosure shall be permitted.
9.3.3.9 A red warning nameplate must be mounted on the instrument. The nameplate shall be mounted in a prominent
location and be visible before enclosure is opened. It shall state:
a) "Enclosure shall not be opened or any cover removed unless area is known to be non-hazardous or unless the
power has been removed from all devices within the enclosure".
b) "Power shall not be restored after enclosure has been opened until enclosure has been purged for x minutes"
(periods to be specified by manufacturer).
26
IPS-E-IN-100
PREFERRED ALTERNATE
Fig. 4.4 Fig. 4.5
ALTERNATE
Fig. 4.6
27
IPS-E-IN-100
APPENDICES
APPENDIX A
CLASSIFICATION OF HAZARDOUS AREAS
* This flow-chart is an extract from the leaflet by the Union o Chemical Industries is provided as a matter of interest only.
29
IPS-E-IN-100
APPENDIX B
COMPARISON OF APPARATUS GROUPS AND SUB-GROUPS
IN BS/EN/IEC AND ANSI/CSA STANDARDS
TYPICAL HAZARD GROUP/SUB-GROUP BS/EN/IEC DESIGNATION ANSI/CSA
METHANE I CLASS I GROUP D
AMMONIA IIA CLASS I GROUP D
PROPANE IIA CLASS I GROUP D
ETHYLENE IIB CLASS I GROUP C
HYDROGEN IIC CLASS I GROUP B
ACETYLENE IIC CLASS I GROUP A
30
IPS-E-IN-100
APPENDIX B.1
BRITISH CLASSIFICATION OF INTRINSICALLY SAFE APPARATUS AND CIRCUITS
Apparatus (and circuits) certified as being intrinsically safe are placed in one of two classes:
Class 2: Apparatus and circuits in Class 2 are subdivided according to the conditions of test for certifica-
tion. The following table shows the classifications appropriate to the different gases in which the
apparatus and circuits may be used.
Class 2e: Hydrogen, blue water gas, town gas, coke-oven gas.
31
IPS-E-IN-100
APPENDIX B.2
GERMAN SPECIFICATIONS FOR ELECTRIC EQUIPMENT IN HAZARDOUS AREA
Reference: Specifications for the Construction and Testing of Electrical Apparatus for use in Explosive
Gas Atmospheres for the Mining Industry (VDE 0170).
General
Type of Protection
d flameproof enclosure.
p plate protection (mining only).
o oil immersion.
f pressurized enclosure.
e increased safety.
I intrinsic safety.
s special protection.
Explosion Class
Note:
3 further subdivide 3a, 3b, etc. depending on type of gas used in test.
Ignition Group
Examples
32
IPS-E-IN-100
APPENDIX B.3
USA SPECIFICATIONS FOR ELECTRIC EQUIPMENT IN HAZARDOUS AREAS
Classification of Areas
a) Class I: Locations are those in which flammable gas or vapors are, or may be, present in the air in
quantities sufficient to produce explosive mixtures. Under Class I, the code specifies 4 Groups:
b) Class II: Locations are those which are hazardous because of the presence of combustible dust.
Group E: Metal dust, including aluminum, magnesium, and their commercial alloys.
c) Class III: Locations in which easily ignitable fibres or materials producing combustible flyings are present.
Group F: Carbon black, charcoal, cool or coke dusts which have more than 8% total volatile
material, or which have been sensitized by other materials.
Extent of Areas
Refer American Petroleum Institute Recommended Practice RP-500 A, RP-500 B, RP-500 C, or NFPA-497 A as may
be applicable.
33
IPS-E-IN-100
APPENDIX C
INTRINSIC SAFETY PRINCIPLES, COMPARISON OF IEC, USA & CANADA
IEC USA & CANADA
Intrinsic safety Technique that achieves safety by limiting the electrical-spark energy (and surface temperature) that can arise in hazardous areas to levels that are
(IS) insufficient to ignite an explosive atmosphere.
Categories Ex la: explosion protection maintained with up to two component or other faults. IS One category only: safety maintained with up to two
apparatus may be located in, and associated apparatus may be connected into Zone component or other faults. IS apparatus may be located in,
0, 1 and 2 hazardous areas (Germany requires galvanic isolation for Zone 0). and associated apparatus may be connected into Division 1
and 2 hazardous locations.
Ex lb: explosion protection maintained with up to one component or other fault. IS
apparatus may be located in, and associated apparatus may be connected into Zone
1 and 2 hazardous areas
Area Zone 0: explosive gas atmosphere is present continuously, or is present for Division 1: hazardous concentrations of flammable gases or
classification long periods vapors - or combustible dusts in suspension - continuously,
intermittently or periodically present under normal operating
Zone 1: explosive gas atmosphere is likely to occur in normal operation. conditions.
Zone 2: explosive gas atmosphere is not likely to occur in normal operation and, if Division 2: volatile flammable liquids or flammable gases
it does occur, it will exist for a short period only. present, but normally confined within closed containers or
systems from which they can escape only under abnormal
Zones Y & Z: being considered for dusts. operating or fault conditions. Combustible dusts not normally
in suspension nor likely to be thrown into suspension.
Gas Flammable gases, vapors and mists are classified according to the spark energy Flammable gases, vapors and mists and ignitable dusts,
classification required to ignite the most easily ignitable mixture with air. Apparatus is grouped fibres and flyings are classified according to the spark energy
according to the gases that it may be used with required to ignite the most easily-ignitable mixture with air.
T1 T2 T3 T4 T5 T6
450°C 300°C 200°C 135°C 100°C 85°C
Gas Details of the classification (C) and the ignition temperatures (T) of commonly used gases and vapors are
characteristics contained in:
IEC 79-12 1978 (C) NFPA 325M: 1984 (C)
EN 50014 March 1977 NFPA 497M: 1986 (includes dusts) (CT)
BS 5501: Part 1: 1977 (C) CSA C22.1: 1986 (CT)
VDE 0170/0171, Teil 1/05.78
BS 5345: Part 1: 1989 (CT)
VDE 0165: 1980 (CT)
Approval National certifying authorities issue certificates for approved equipment, defining FM and UL (USA) and CSA (Canada) issue reports and
how it may be used. publish listings of approved equipment defining how it may
be used.
Standards All countries in Western Europe work to CENELEC standards EN 50 020 FM and UL work to their own standards,
(apparatus) and EN 50 039 (systems) EEC member countries issue Certificates of FM 3610 based on the US national standard
Conformity to these standards and accept products and systems certified by other NFPA 493-1978, and UL 913, based on
members Other countries either work to their own standards based on IEC 79-11 ANSI/UL 913-1988
(e.g. Australia, Brazil, Japan, USSR) or accept products and systems certified to Canada works to CSA C22.2, No. 157.
European and/or North American standards.
34
IPS-E-IN-100
PART II
BETWEEN
35
IPS-E-IN-100
1. SCOPE ................................................................................................................................... 37
2. GENERAL .............................................................................................................................. 37
APPENDICES:
36
IPS-E-IN-100
1. SCOPE
This Standard defines the division of responsibilities between instrument and electrical engineering disciplines and
gives guidance for working at the interface between them.
2. GENERAL
In order to define the instrument and electrical interface clearly, the division of responsibilities should be based upon
identified areas of responsibility for each discipline.
A carefully defined division of responsibility for the instrument and the electrical disciplines is considered necessary in
order to:
2.1.6 Enable each engineering discipline to be directly and singularly for matters assigned where qualifications of com-
petance are required by authorities. Furthermore, the demarcation lines should be such that future developments can be
easily adapted on either side.
By its very nature, this Standard can never be so complete as to cover all possible situations. Those not covered should
be decided upon in line with the general objectives as stated above and with the principles as defined in the following
sections.
It is highly desirable that the division of responsibilities as defined in this Standard is adopted for use by users for all
instrument and electrical engineering activities.
In order to make areas of responsibility easily identifiable they are based upon a system division as opposed to an equip-
ment division, the guiding principles being:
2.3.1 Instrument engineering shall be responsible for measurement and control systems of the operating variables in
processing units, related utilities and facilities.
This shall include signal transmission systems, computer systems for process monitoring and control, and the related
peripherals, e.g. data-loggers. DCS, etc.
2.3.2 Electrical engineering will be responsible for electrical power systems and their rotating equipment systems. This
will include computers which monitor and control power generation equipment, power supply and distribution systems.
Note:
Rotating equipment systems in the context of this Standard refer only to electric-motor-driven equipment and to power gen-
eration equipment.
Typical examples of areas of responsibilities for instrument and electrical engineering are given in Appendix A.
37
IPS-E-IN-100
3.1 General
The interface between equipment forming part of instrument engineering (usually located in the plant control room) and
equipment forming part of electrical engineering (usually located in a switch house or in the plant) is normally a matter
of defining the demarcation lines for the interconnecting cabling.
In other situations, the demarcation lines are not so straightforward. For some typical cases demarcation lines have been
defined in more detail.
In order to achieve a well-defined interface in control and signal cabling between electrical and instrument engineering,
an interface box shall normally be provided. The box shall contain an interface terminal strip-for instrument cable con-
nections at one side and for electrical cable connections at the other side.
The interface box shall form part of instrument engineering, but shall be accessible to both instrument and electrical
engineering disciplines.
The interface box should normally be located adjacent to the relevant switch room, however, subject to the geographical
lay-out of the plant, it maybe located in other locations, e.g., control room basement, instrument auxiliary room, or close
to the relevant equipment as agreed between instrument and electrical engineering.
The area in which the interface box is located may contain instrument equipment/facilities for instrument signal conver-
sion and routing to and from the control center. The interposing relays which form part of instrument engineering may
be included in the interface box.
Terminals accommodating on-off signal/command lines, or analogue instrument signal lines shall be fitted with isolat-
ing facilities. For a typical example of a signal line interface, see Appendix B.
Note:
The interface termination between instrument and electrical signal lines is normally the only area where the two disciplines
shall work on the same item of equipment.
The interface with instrument engineering for e.g., remote control shall be as described in 3.2. For motor-operated
valves (see 3.8).
All measurements, protection and controls. including systems for speed control (up to speed governor) and machine
monitoring (bearing temperatures, vibration), etc., are part of instrument engineering.
Note:
For these facilities instrument engineering has an interface with mechanical engineering. However the subject of that inter-
face is not part of this Standard.
38
IPS-E-IN-100
3.5.1 General
- The filling of cans, bins, pails, bottles, drums, etc., with product (fluids, chemicals).
- The transportation of solid products (powder, nibs, flakes, lumps, bales) and associated filling of bags, drums,
etc.
- The transportation of solid products on conveyers with hoisting and lifting equipment, in packing machines,
palletizers, shrink wrapping machines, etc., including storage and dispatch.
Equipment for these systems is often supplied as an approved package unit complete with inherent controls. Remote
control with associated signal transmission to the control room is not normally required for this type of equipment.
Where remote monitoring and control is required the measuring and control signals shall be routed via an interface box
(see 3.2). The interface box should form part of the package.
The division of responsibilities between instrument and electrical engineering for these systems shall be as follows:
- All non-process-integrated individual power consumers for transport and handling, such as cranes, elevators,
’stand alone’ packaged units, etc.
- Electric consumers (e.g. electric motors, heaters), control gear but excluding small drives (e.g. control drives,
chart drives) for systems which are part of instrument engineering.
Where electrical AC parameters such as current, power or power factor have to be presented in the control room as a
process variable, these parameters shall be converted into a standard 4-20 mA DC transmission signal. These converters
should form part of electrical engineering responsibilities and shall be installed in the electrical switch room. Attention
shall be given to the provision of adequate isolation between input and output and to the arrangements for electricity
supply; some types require an AC supply (from switch room ) but others operate on a two-wire (24-V DC) system as is
usual for other transmitters and signal converters. To avoid complications in further data handling, cable screening, etc.,
preference should be given to converters operating from an external 24-V DC supply, which will then form part of in-
strument engineering and be supplied via the interface strip.
The interconnecting cabling between converters and the interface box shall form part of electrical engineering, see also
Appendix B.
39
IPS-E-IN-100
3.7.1 General
Instrument engineering shall specify the basic requirements for instrument electricity supply, such as:
Note:
The power requirements for air-conditioning systems to protect the instrument equipment, will be specified via air-
conditioning engineering.
The division of responsibilities between instrument and electrical engineering shall be as defined in 3.7.2 and 3.7.3.
Electrical engineering shall be responsible for the AC powering of instrument systems, including back-up and the AC
distribution network.
From take-off points of this network instrument engineering shall arrange for the connections to the various instrument
systems and racks located in a control room, basement or auxiliary room.
The AC supply for plant-mounted instruments or instrument racks form part of electrical engineering up to the AC ter-
mination point in the instrument or rack.
Instrument engineering shall be responsible for voltage inverters, conditioners and back-up arrangements as required for
the individual instrument systems and racks, which form an integral part of the instrument or instrument system.
For DC systems, including back-up, for powering the complete DC instrument systems of a plant, electrical engineering
shall be responsible up to and including the DC power distribution board. The instrument-electrical interface shall lie at
the DC terminal strip in the distribution board.
Instrument engineering shall be responsible for equipment, system, or rack-dedicated AC/DC systems (with battery
back-up as required).
The engineering of motor-operated valves (MOVs) requires an input from mechanical, instrument and electrical engi-
neering as follows:
3.8.1 Mechanical engineering shall have overall responsibility for the MOV and will specify the details for the valve.
3.8.2 Instrument engineering will decide in consultation with mechanical and electrical engineering whether the actua-
tor shall be electrically, pneumatically or hydraulically actuated.
Instrument engineering in cooperation with process engineering shall indicate the requirements for the associated meas-
uring and control features of the valve and actuator.
40
IPS-E-IN-100
3.8.3 Electrical engineering shall specify the actuator for electrically actuated MOVs. based on process design data
(closing time, size of the valve, etc.) and the required measuring and control features advised by instrument engineering.
In all other cases instrument engineering shall specify the actuator and the required measuring and control features.
The interface between instrument and electrical engineering for the electric-operated actuator shall lie in an interface
box, see 3.2, for the transfer of control signals to the actuator and valve status information from the actuator, see Appen-
dix C.
Instrument engineering shall be responsible for the flame rod amplifier; electrical engineering will specify, install and
maintain the HT transformer, if required.
Mechanical engineering shall be responsible for the ordering of the ignition burner package.
A schematic control arrangement with interface lines for a soot blower system is given in Appendix D.
41
IPS-E-IN-100
APPENDICES
APPENDIX A
TYPICAL ACTIVITIES OF INSTRUMENT AND ELECTRICAL ENGINEERING
Consists of activities necessary for the specification, design, construction, testing, inspection, quality control, installa-
tion and maintenance of equipment and systems for the measurement and control of operating variables in processing
units related utilities and facilities.
The equipment involved in instrument engineering activities comprises, but is not limited to:
- Measurement and control systems including analogue, digital, sequential, supervisory controls, DCS and PLC
systems.
- Machine monitoring systems (vibration, displacement, torque, speed) and associated actuation of machine pro-
tection systems.
- Detection systems and associated alarms for flammable and toxic gases, including those for buildings.
- Pollution detection systems and associated control systems including those for buildings.
- Instrument electricity supply and distribution systems as far as not forming part of electrical engineering.
- The selection of the type of actuator for control valves and remote operated on/off valves.
- Remote control and status signaling for pneumatically or hydraulically-operated valve actuators.
- Instrument air supply systems as far as not forming part of mechanical engineering.
Electrical engineering consists of activities necessary for the specification, design, construction, installation, mainte-
nance, measuring, protection and safeguarding, testing, inspection and quality control of electric power systems and ro-
tating equipment systems. Operation of electric power systems forms part of electrical engineering.
The equipment involved in electrical engineering activities comprises, but is not limited to:
(to be continued)
42
IPS-E-IN-100
APPENDIX A (continued)
- Electric-motor-operated valve actuators including remote control and status signaling up to the interface termi-
nal strip. Excluding torque and limit switches setting and maintenance.
- Instrument electricity supply systems up to the point where instrument engineering takes over.
- Safety circuits for personnel protection (e.g. emergency stops, pull chains, work safety switches).
- Earthing and bonding systems for electrical system earthing, protection against electrostatic charges, personnel
protection.
- Equipment for direct manual operation of above-mentioned items (e.g. remote control units, limit switches).
- Measurement and control systems, including inherent alarm annunciation and safeguarding systems for protec-
tion of electrical equipment, analogue, digital, sequential and supervisory controls for above-mentioned items.
43
IPS-E-IN-100
APPENDIX B
INSTRUMENT-ELECTRICAL SIGNAL LINE INTERFACE
(Typical Example)
44
IPS-E-IN-100
APPENDIX C
INSTRUMENT-ELECTRICAL INTERFACE FOR ELECTRIC MOVs
* The motor contactors may also be located in the electrical switch house.
** Status contacts to be potential free.
45
IPS-E-IN-100
APPENDIX D
INSTRUMENT-ELECTRICAL INTERFACE FOR A TYPICAL SOOT BLOWER SYSTEM
46
IPS-E-IN-100
PART III
INSTRUMENT ENGINEERING PROCEDURES
47
IPS-E-IN-100
1. SCOPE ................................................................................................................................... 49
2. GENERAL .............................................................................................................................. 49
6. FACTORY INSPECTION........................................................................................................ 53
6.1 Decision for Inspection ................................................................................................ 53
6.2 Inspection Procedures .................................................................................................. 54
6.3 Inspection Documents................................................................................................... 54
APPENDICES:
48
IPS-E-IN-100
1. SCOPE
This Standard describes project engineering procedures for the design, requisition, test and inspection of instruments.
The procedures are intended for use in Petroleum Industries of Iran.
2. GENERAL
Unless otherwise specified, Instrument Engineering shall be responsible for carrying out the activities as mentioned
hereafter. These activities comprise at least the following:
1) Planning and scheduling of the instrumentation work for the project within the overall project plan.
2) Checking of process engineering flow diagrams, utility engineering flow diagrams, functional logic diagrams
and flow charts (functional description).
5) Calculations for flow measuring instruments, control valves and safety/relief valves.
7) Evaluation of quotations, selection of suppliers from the list of approved manufacturers, checking copies of
orders and suppliers data/drawings/documents.
9) Advising and assisting in the lay-out of instrument panels, operator consoles, control rooms, auxiliary instru-
ment rooms, computer rooms and analyzer houses.
13) The preparation of detailed documents and drawings for the ordering and installation of the instruments, etc.
14) The checking of plant models, for instrument accessibility and location purposes.
15) Follow-up and progress control on all matters relating to instrument engineering.
16) The preparation and obtaining the necessary approvals of ’as-built’ drawings.
The Designer shall be responsible for all instrumentation and related activities, and for the satisfactory design and cor-
rect implementation of instruments and control systems in accordance with Company’s specifications.
For "split-phase" projects, responsibility shall be in accordance with the relevant section of the project specification.
The interface between Instrument and Electrical Engineering, is given in Part 2 of this Standard IPS-E-IN-100.
49
IPS-E-IN-100
Note:
The following items form part of mechanical engineering, for which the relevant engineering information shall be supplied by
instrument engineering:
- orifice flanges, orifice meter runs (made in accordance with Standard Drawings);
- level gage glasses, displacer chambers for level instruments;
- thermowells;
- safety/relief valves;
- instrument air compressors, coolers, dryers, buffer vessels and instrument air supply piping larger than ½ inches.
2.3.1 All instrument engineering shall be based on the design data given in Instrument data sheets and process and
utility engineering flow diagrams. Where necessary, additional information shall be provided in cooperation with rele-
vant disciplines to explain such plant operational requirements as:
2.3.2 The Designer shall continuously update the instrument data sheets if necessary and submit these at defined inter-
vals for the Company’s approval.
2.3.3 In addition to the instrumentation listed during the detailed engineering phase, all other instrumentation, such as
those for equipment packages, shall be included in the instrument data sheets and engineering flow diagrams. Where
these are not practicable, the additional instrumentation shall be shown on separate engineering flow diagrams and in-
strument data sheets.
Notes:
1) All process data shall be approved by the responsible process-control engineer before being used for instrument engineer-
ing.
2) The preliminary instrument data sheets as prepared in the basic design phase, shall normally only show the process data.
Hardware (engineering) data shall be stated in a later revision by the Designer.
2.4.1 All instrument engineering work shall be based on the requirements given in the design package and latest
amendments/revisions. In case of conflict between the referred to and the amendments, the latter shall over rule.
2.4.2 The Designer shall obtain the Company’s written agreement for all deviations from the Project Specification,
prior to carrying out the related engineering work.
2.4.3 Government and local authority requirements, laws and customs shall prevail if these are more stringent than
those specified in the Project Specifications.
2.4.4 It is the Designer’s responsibility that all the local legal obligations related to the scope of work and applicable to
the realization of the project are complied with.
2.4.5 The Designer shall inform the user immediately of any such local requirements which are not covered by the
specifications indicated above.
2.4.6 Should doubt arise in the interpretation of rules given in the design package referred to above, the Company shall
be consulted.
50
IPS-E-IN-100
2.4.7 Compliance with the requirements of this specification shall not relieve the Designer of his obligation to follow
sound and safe engineering practice throughout.
2.4.8 If changes in the design are considered necessary by the Designer tractor for economic, safety, ease of operation,
or other reasons they shall only be carried out after obtaining the Company’s approval in writing.
2.5.1 In general the instruments for equipment packages, such as boilers, incinerators, refrigeration equipment, com-
pressors, etc., should be of exactly the same make and type as those used for the process units as far as possible.
2.5.2 The Equipment Package supplier shall be informed of the selected types and manufacturer’s of the preferred in-
struments, in order that the instrument installation, including all materials, shall be in accordance with the overall re-
quirements for the total project. This requirement shall then be clearly stated on the inquiry for the unit, and the equip-
ment package supplier shall be provided with all pertinent documents and drawings.
3. TIME SCHEDULE
3.1 All phases of instrument engineering work shall be planned in detail and in accordance with the overall time sched-
ule for the project. Special attention shall be given to the timing of the following:
These summaries shall indicate all expected engineering documents, drawings and inquiries together with the expected
date of issue. The documents will then be used as the basis for the detailed instrument engineering planning.
- The finalization of computer input sheets for all calculations. This data shall be available at specified time be-
fore the planned date of plant commissioning.
4. PREPARATION OF INQUIRIES
4.1 General
4.1.1 The inquiries of all instruments, instrument and control systems, auxiliary equipment, installation materials etc.
shall be based on the relevant (process) data and on the makes and types specified by the Company.
4.1.2 When equipment or materials are free issue items to other suppliers, the Designer shall provide a clear descrip-
tion and all applicable cross references.
4.1.3 The Designer shall prepare separate inquiries for ’in line’ instruments which have a pressure rating of various
classes. They shall be segregated from inquiries which contain instruments of a lower pressure rating.
4.2.1 Inquiries shall be prepared for the purchase of all instruments shown in the Engineering P&IDs and listed in the
instrument data sheets, including all auxiliary equipment and installation materials. These inquiries shall clearly state all
the requirements and date necessary for the supply of correct equipment and materials.
51
IPS-E-IN-100
4.2.2 The types of equipment specified on any inquiries should. ‘preferably’ be limited to those which can all be sup-
plied by the same manufacturer.
4.3.1 The inquiries shall only carry the information necessary for ensuring the proper supply of the equipment and/or
services required.
4.3.2 When required, in addition to the operating conditions specified on the inquiry, the Designer shall also state re-
quirements such as vacuum service, high pressure, low and high temperature, oxygen service, strongly varying process
conditions, corrosive and abrasive conditions.
4.3.3 Furthermore, the specific requirements given in the Project Specification shall be stated on the inquiries and spe-
cial attention shall be given to the following:
- Material certification of instruments and related components for pressure retaining parts, including the bolting
of pressure retaining parts.
- Special testing and/or treatment of materials, e.g. leak, dye penetration, ultrasonic, magnetic particle, hardness,
heat treatment, stress relieving, annealing/pickling, etc., shall be in accordance with the requirements given for
the piping system or equipment in which the instruments are to be installed, and/or the Project Specification.
Note:
Pressure testing is mandatory for all pressure retaining instruments and/or installation materials.
- Requirements for the maximum allowable noise level, e.g. for control valves, control room equipment, etc.
- The ‘NACE Requirements’ for ’in line’ instruments used in sour service.
4.3.4 The Designer shall carefully check the supplier’s information to ensure the correct supply of equipment and/or
services.
4.3.5 Complete tag numbers shall be stated on the inquiry for identifying instruments and accessories during installa-
tion. This is not necessary for installation materials which are identified, stored and used by indent/item numbers.
4.4.1 When the Designer is requested by the Company to submit all inquiries for comments and/or approval, the rele-
vant up-to-date instrument data sheets and other relevant documents e.g. control valve calculation sheets shall be issued
prior to, or simultaneously with the inquiry.
4.4.2 Quotations for approval shall be submitted with all relevant documents included, such as catalogues, intermediate
correspondence and drawings, etc.
4.5.1 The inquiries, especially initial inquiries, should include an amount of certain extra equipment as ’project spares’
to allow for losses of installation materials, or for late changes at site.
4.5.2 The Designer shall propose for each of the (initial) inquiries an amount of project spares. The amount of these
spares requires the written approval of the Company.
If the inquiries for the main equipment contains free issue items, cross references shall be made between the inquiries
for main equipment and free issue items, giving the inquiry number, make and type of instrument/equipment and quanti-
ties.
52
IPS-E-IN-100
4.7.1 To ensure timely delivery, preliminary inquiries shall be issued for certain equipments at an early stage of the
detailed engineering, to allow the manufacturers to reserve manufacturing capacity and to order sub-assemblies and
parts.
- Control valves with components made from non-standard/special materials or Distributed Control Systems,
etc.;
- panel instruments and flow transmitters when required in large quantities (with estimated quantities).
4.7.2 Initial inquiries for installation materials and cables should be issued with estimated quantities and average
lengths of cable required for each instrument. The inquiries shall be revised and re-issued at a later date when final
quantities and lengths are known, together with and approved amount of project spares materials and cables.
Inquiries for equipment of ’Category B’ and ’Category C’, (see Clause 6), shall carry a note that the equipment will be
inspected after factory-testing and before shipment.
Inquiries for factory assembled systems and items of equipment in ’Category B’ Appendix A refers, shall specify
whether erection and/or commissioning assistance and/or a 6 months or 1 year maintenance contract is required from the
supplier, or as otherwise stated in the Project Specification.
5. COMPOSITE MANUALS
The Engineering Designer shall ensure that manufacturers/suppliers are instructed to supply to site, either by direct dis-
patch or via the Designer’s office in accordance with the Project specification, complete sets of all instrument installa-
tion, commissioning and maintenance manuals, applicable to each type of equipment in their supply. Where practicable,
these sets shall be assembled in loose-leaf binders.
For the larger systems, provided by the same supplier, the sets shall include all details of all the types of instruments
supplied, e.g. for Distributed Control System, blender, metering station, etc.
6. FACTORY INSPECTION
6.1.1 To facilitate the requirements for factory inspection, the instrumentation shall be separated into "Category A",
"Category B" or "Category C" Items as appropriate, see Appendix A Page 55.
Note:
53
IPS-E-IN-100
6.1.3 Material in Category A, which forms an integral part of the equipment of Category B, will be inspected against
the relevant requirements during the inspection of Category B material, e.g. controllers and recorders in a control desk
will be checked against the requisition in the panel shop, during the acceptance test of the control desk. The require-
ments for factory inspection shall be clearly indicated in the inquiry for the particular equipment.
6.2.1 Prior to factory inspection by or on behalf of company the manufacturer shall carry out tests and if necessary take
corrective measures, with the approval of company, in order to ensure that all equipment fulfills the requirements stated
in the inquiry. This shall include equipment which is supplied with equipment packages or as free issue items.
The factory inspection, by or on behalf of company, shall include full loop and function tests for which floor space,
simulation equipment and manpower assistance shall be provided by manufacturer. The inspection date shall be fixed at
least four weeks in advance.
6.2.2 One set of approved, up-to-date vendors drawings, including test procedures, shall be supplied to the Company
before the inspection is carried out.
For turnkey projects, the Designer shall establish, document and maintain, an effective quality assurance system to dem-
onstrate compliance with the requirements for services and manufactured products, in accordance with the relevant sec-
tion of the Project Specification.
For guidance as to which instruments and drawings should be made in the engineering stage, refer to IPS-E-IN-100/4
(Instrument Document and Drawings).
The engineering documents and drawings shall be processed and submitted to the Company in logical sequence for
comments, or released in accordance with the requirements of the Project Specification, to ensure proper coordination of
responsibilities and activities. If available, the Designer may use his own computerized system for handling documents
and drawings, having first obtained the Company’s approval in writing.
54
IPS-E-IN-100
APPENDICES
APPENDIX A
INSPECTION REQUIREMENTS
A.1.1 Category A
Comprising individual items of equipment and separately mounted instruments. Typical items in this category are:
- transmitters
- recorders
- controllers (including indicating controllers)
- pressure/drought/receiving/temperature gages
- installation materials (except for impulse lines containing valves)
- solenoid valves
- plant mounted terminal/junction boxes
- switches (manual/receiver and process)
- push buttons
- cables (except system cables)
- variable-area meters (except for process applications)
- indicators (including receiving indicators)
- diaphragm seals
- manual loading stations
- howlers
- integrators
- pulse counters
- alarm light units
- computing/selecting/limiting/boosting/time relays
- air filter-reducers
- TC assemblies
- resistance thermometer elements/RTD’s
- detectors
- tank gages
- gage glasses
- signal converters
- volume boosters
- load cells
- lock-up/quick exhaust devices
- control drives for dampers
- valve actuators/positioners.
A.1.2 Category B
Comprising instruments and equipment of a more complex nature, custom-built systems or equipment packages. Typi-
cal items of equipment in this category are:
- local panels
- metering station
- meter provers
55
IPS-E-IN-100
- receiver switches
- signal converters
- signal amplifiers
- miscellaneous/auxiliary components.
- control desks
- alarm systems/alarm service units
- safeguarding systems
- interlock systems
- sequential control systems
- relay systems
- binary logic systems (all types)
- distributed control systems
- multiplexers
- operator consoles
- programmable logic controllers
- graphic panels
- prefabricated (system) cables
- interface systems
- computer systems
- close circuit systems
- tank gaging systems
- interposing cabinets
- monitoring systems
- fire and smoke detection systems
- distribution frames or cabinets
- weighing systems
- dosing systems
- blending systems
- sequential event recorder
- printers (used in data gathering or DCS/PLC Systems)
- gas detection systems
- multi point temperature systems (only for 100 points and complex systems)
- batch control units or counters.
Notes:
1) If the Designer considers it to be necessary, or when required by the Company and stated in the project specification, the
more complicated instruments and equipment shall be commissioned by the manufacturer.
2) If doubt should arise regarding erection/commissioning assistance from the supplier, the Company shall be consulted.
56
IPS-E-IN-100
A.1.3 Category C
Comprising in-line mounted instruments and items for instrument impulse lines. Typical items of equipment in this
category are:
- manifold valves
Note:
All instruments installation materials in Category C which are to be inspected, shall be examined by a mechanical specialist
to ensure compliance with the piping specification.
57
IPS-E-IN-100
PART IV
58
IPS-E-IN-100
1. SCOPE ................................................................................................................................... 60
2. GENERAL REQUIREMENTS................................................................................................. 60
59
IPS-E-IN-100
1. SCOPE
This Part of IPS-E-IN-100 gives minimum requirements for instrumentation documents and drawings which shall be
prepared/completed during the basic design and detailed engineering stage of a project. In addition the requirements for
documents and drawings in the "As Built" condition are given in Clause 3.
It is intended for use in Petroleum Industries of Iran. Where cross-references are made, the numbers of the section of
sub-sections referred to, are shown in brackets.
2. GENERAL REQUIREMENTS
2.1 General
A set of instrumentation documents and drawings shall be prepared for each project, which shall include but not neces-
sarily be limited to those specified in this Part.
These documents and drawings shall be issued such that sufficient time is allowed for realizing the instrument installa-
tion, taking into account the procedures and the time required for review and comment by the user.
The extent of detailing of each document and drawing shall be such that it will facilitate the installation of all instrumen-
tation at the construction site and serve as a reference for future maintenance, changes and/or extension to the instru-
mentation.
The contents of these documents and drawings, the number of copies required, the need for additional documents and
the procedures for commenting and/or approval, shall be in accordance with requirements which will be stated by the
user.
The use of desk top computers, by the contractor, for document and drawing production requires the written approval of
the Company. If documents and drawings are provided through software system the application of program must also be
submitted.
Notes:
1) The release (date) of the above software packages shall be listed and submitted for approval by the Company.
2) The compatibility with computer equipment used on site should be verified by the Company if not compatible, the required
computer equipment should be ordered with the project.
All parts and sections of any form, sheet or other document which requires ’filling in’ shall be completed. Where a par-
ticular part of any document is not applicable it shall be so indicated.
2.2 Identification
All documents and drawings shall be provided with a registration number from the series of numbers allocated to the
project, together with a code number for classification and identification. The code number shall consist of a prefix,
project number, group number.
All documents and drawings shall bear proper references to related project construction drawings, and indent numbers
for the materials required, etc. The documents and drawings shall bear the titles as indicated in this part in addition, all
instrument related layout drawings of control rooms, auxiliary rooms and analyzer houses, etc., shall indicate the build-
ing and room number as appropriate.
Where multi-sheet drawings (Clause 2.4) consist of a large number of sheets, each sheet may be revised, if required. For
each revision, the cover sheet and the revision index sheet shall be re-issued together with the revised sheets. All the
revised sheets shall bear the same revision letter irrespective of the last revision letter on the individual sheets, i.e., all
revised sheets shall bear the same revision indicator as the cover sheet.
60
IPS-E-IN-100
For multi-sheet drawings where signatures are applied for approval or checking, these shall be indicated on the cover
sheet only. Where a full title block is applied this shall be used on the cover sheet only. Continuation sheets shall be
sufficiently titled to link them clearly to the cover sheet and include project title, drawing title, project, drawing number
and sheet number.
The drafting techniques, drawing sizes, preparation, and when applicable the micro filming, of technical drawings shall
be in accordance to the following instructions or company policy as instructed by the user. Drawings should be on A3
sized sheets. The basic format of each type of document produced by the Designer shall be submitted for review by the
Company prior to large scale application. The following order of preference shall apply:
A4 297 mm × 210 mm
A3 420 mm × 297 mm
A2 594 mm × 420 mm
A1 841 mm × 594 mm
A0 1189 mm × 841 mm
Drawing size A0 may be used for instrument documents and drawings on special cases. Special attention shall be paid
by the Designer to ensure a consistent drawing and documentation package, particularly for those documents which are
associated with equipment package unit, (Clause 2.8). It is not acceptable to deviate from an agreed format and stan-
dards, and it is the Designer’s responsibility to ensure rigid adherence to such procedures.
Copies of drawings issued for comments or information shall have a maximum size of A3. Consideration should be
given to reducing by copying to A4 size before dispatch. Drafting techniques should then take into account clear read-
ability of the reduced format.
Where it is anticipated that computer printouts will be employed, the dot matrix printers shall not be used for drawing
preparation purpose. For the mechanical, instrument and electrical symbols and identification systems to be used on
drawings, refer to the related symbols and legend drawings of these disciplines.
Certain ’documents’ shall be made in the format of a ’drawing’ with a large number of sheets, consisting typically of:
- A cover sheet.
- Index to sheets, giving the applicable revision indicator of the sheets contained in the set.
- Listing of symbols and abbreviations used.
- Listing (by item number) of materials required.
- Detail sheets (as indicated on the index sheet) giving the required information.
Note:
For a typical example, refer to the multi-sheet drawing for instrument impulse lines, given in IPS-D-IN-104.
For the preparation of such drawings, standard forms A4 and A3 size shall be used. To facilitate reproduction and filing
preference is given to the use of A4 size. All sheets of a multi-sheet drawing shall have the same size, mixing of A3 and
A4 sizes in one multi-sheet drawing set is not allowed.
Where the subject cannot be arranged entirely on one sheet, as may be the case with logic diagrams, relay diagrams or
instrument signal diagrams, the subject shall be continued on the following sheet(s) with proper cross references at the
demarcation points. The arrangement shall then be such that a continuous presentation of the subject is formed when the
separate sheets are laid side by side by the (ultimate) user.
61
IPS-E-IN-100
Where constructional details are required to ensure the proper supply of instrumentation equipment, such details shall
be shown on a separate construction drawing, to which references shall be made in the requisition.
For standard equipment, such drawings are available in the form of standard installation drawing. Where these standard
drawings are used in an unmodified form they can be used by referring to the standard number, revision indicator and
title. When, however, for a particular application, deviations from the standard drawing are necessary, the Designer shall
prepare an engineering drawing based on the standard drawing. Under no circumstances shall a standard drawing be
issued in a modified form.
For non-standard equipment, dedicated engineering drawings shall be prepared showing details and all requirements.
Where comprehensive descriptions, arrangement drawings and/or construction details are necessary for ensuring the
proper supply of equipment, these requirements shall take the form of a technical specification, to which references shall
be made in the requisition. For certain standard equipment, these specifications are available as an IPS publication (e.g.,
for control valves, control panels). Where this is not the case a dedicated technical specification shall be prepared in the
form of a multi-sheet specification.
Drawings received from manufacturer shall be identified as engineering drawings, see (2.2), and where applicable com-
mented upon and incorporated into the detailed engineering stage of the project.
Manufacturer’s drawings shall be fully integrated into the overall project documentation package and incorporated into
a dedicated ’Instrument Summary’, (see 3.2.1).
In addition to identification (2.2), manufacturer’s drawings shall carry a manufacturing schedule consisting of a table,
listing the tag and/or equipment numbers with special requirements such as material, range, type number, label-
ing/engraving adjacent to the tags.
This will serve both as an acknowledgment and check on the additional requirements specified in the requisition.
Standard manufacturer’s manuals/bulletins shall indicate or delete inapplicable items and details, and highlight those
which are applicable by underlining or arrowing, etc.
Note:
Where applicable, the above requirements shall be clearly stated under "Documentation" in each instrument equipment
requisition.
Manufacturer’s drawings shall only be used to assist in the production of a comprehensive installation drawing package
and shall not form a part of the installation package.
Drawings of an equipment package shall be identified in accordance with Sub-clause 2.2. The drawings shall be com-
mented upon and incorporated into the detailed engineering stage of the project. The drawings of an equipment package
shall be arranged in separate sets for each equipment package unit.
62
IPS-E-IN-100
The "As Built" preparation for the documents and drawings should be in accordance to the following table and catego-
ries:
- Category A Documents and drawings, should remain ’as built’ during the life time of the plant for main-
tenance and safety audit purposes.
After commissioning, particularly in the case of plant changes, however small, plant man-
agement is responsible for the updating of the ’category A’ documents and drawings con-
cerned, and this function shall be defined clearly within the plant organization.
- Category B ’As-Built’ documents and drawings, after construction shall include all changes/additions
which have been made during the construction/commissioning phase of the project.
(to be continued)
63
IPS-E-IN-100
64
IPS-E-IN-100
The following sub-sections indicate the type of documents and drawings generally applied and give guidance on how
they should be prepared.
The summary shall consists of an index sheet and separate sheets for listing engineering drawings and manufacturer’s
drawings respectively.
The first issue shall be prepared at specified time after award of the contract and shall contain, in numerical order, list-
ings of all instrumentation documents and engineering drawings, complete with the planned dates for the first issue indi-
cated in the relevant columns.
Revisions of the summary shall be issued monthly and shall then be up to date and contain all known information. Each
revision issued shall contain a complete set of sheets including non-revised sheet(s), the revision indicator used on the
index sheet shall also be used on the attached summary sheets and in the ’issue’ column of each revised item, irrespec-
tive of the previous revision indicator(s), if any, there-on. The revision shall include manufacturer’s drawings as soon as
these have been received.
This summary consists of an index sheet and a list(s) of inquiries for each group of instruments. The first issue shall be
prepared at specified time after award of the contract and shall contain, in numerical order, a listing of all instrumenta-
tion requisitions, complete with the planned dates for the first issue indicated in the relevant columns.
Normally one line should be used for each requisition but where the requisition covers materials which are expected to
have different delivery dates, one line should be used for each group of items which have the same delivery date. Revi-
sions of the summary shall be issued periodically and shall then be up to date and contain all known information.
For each processing unit and/or major equipment package unit in the project, the design and engineering information for
the instrumentation shall be listed on ’standard instrument engineering data sheets’. These sheets shall carry the process
data which is defined by process engineering.
Notes:
1) The Actual operating data for the processing unit and/or major equipment package unit shall be entered on the instrument
engineering data sheets. However, the values given for minimum/normal/maximum of flow/level/pressure/temperature etc.,
shall take into account the turn-down requirements and the operating/design limits of the processing and equipment package
unit.
2) In addition to the instrumentation entered by the process engineers, all other instrumentation data, such as for utilities,
etc., shall be included in the data sheets.
The tag numbers on the sheets shall be in numerical sequence ’Symbols and identification system instrumentation’.
These sheets shall comprise tag numbers in numerical sequence, the related process engineering (or utility) flow dia-
gram (PFD) drawing number, and the location co-ordinates of the instrument concerned on the (PFD). Where a line has
been revised the revision letter shall be placed in the left hand column.
Data sheets for each process unit and for each major equipment package shall be made up into separate sets and each set
shall be supplied with a dedicated cover sheet. The set(s) of sheets of equipment package(s) shall be combined with and
65
IPS-E-IN-100
immediately follow the set of sheets for its associated process unit. However, the cover sheets from each set shall be
placed at the front and the combined set shall be numbered accordingly. Tag numbers for a package unit shall be given
in sequence and in a group.
The first issue shall be prepared at an early stage of the detailed engineering phase and shall specify the components for
each instrument loop, with all additional information available at that time. During the detailed engineering period the
instrument engineering data sheets shall be further completed with engineering and purchasing data.
Revisions of the instrument engineering data sheets shall be issued periodically and shall then be up to date and contain
all known information.
The sequence of the data sheets as an engineering document and their numbering shall be as indicated on the cover
sheet. The cover sheet shall list all the sheets and give the latest revision letter.
Composite instrument manuals shall be compiled as follows, but not necessarily limited to the examples given:
- For all in-line instruments such as control valves, positive displacement/turbine meters including accessories,
level displacer instruments, etc.
The Composite instrument manuals shall incorporate all manufacturer’s documents for the instrumentation de-
signed/ordered against a particular project.
3.3 Diagrams
These diagrams shall be arranged as a multi-sheet ’drawing’ (2.4), in one complete set for the particular project.
The diagrams shall show overall signal routing between field devices and all systems and cabinets, including the type of
signal cabling, junction boxes, terminals, main distribution frame and system cabling, etc. For system cabinets, the type
of power supply and the arrangement of system cabinet alarms, etc., shall be indicated. These drawings shall be in the
form of block diagrams and, if applicable, detail all the battery limits delineating the scope of supply.
The diagrams shall be prepared at an early stage of the detailed engineering phase and shall be fully reviewed and ap-
proved by the Company before detailed design is started.
The instrumentation ’general’ drawings shall be revised throughout the project to incorporate further requirements as
they become apparent.
These diagrams shall show in detail all active instrument components complete with instrument ranges, set points, con-
troller settings, etc., for complicated systems such as HP/MP/LP steam systems, fuel gas systems and compressor surge
control systems.
66
IPS-E-IN-100
Loop diagrams shall be arranged as a multi-sheet ’drawing’ (2.4), in separate sets for each processing unit and for each
major equipment package unit.
Each set of instrument loop diagrams shall have a drawing number. Where more than one processing unit and/or major
equipment package unit is involved in the project, a group of consecutive drawing numbers shall be used for the various
sets of diagrams.
Logic diagrams shall be arranged as a multi-sheet ’drawing’ (2.4), in separate sets for each processing unit and for each
major equipment package unit.
For each system for binary logic functions (including those in package units), a functional logic diagram shall be pre-
pared by, or in close cooperation with, process design or process control engineering.
Each logic system as indicated on the process engineering, (or utility) engineering flow diagrams (P&IDs), shall have its
own sheet or it may consist of several sheets.
Where it has been decided by the user that the logic functions will be realized by electro-mechanical relays, the func-
tional logic diagrams shall be converted into relay diagrams. These conversions shall take into account system engineer-
ing aspects such as:
- Fail-safe provision.
- Provision for override, start-up, testing under operating conditions, etc.
- Identification of all components such as relays, circuit breakers, etc., terminals, sockets and pins, especially for
incoming and outgoing signals.
The resulting relay diagrams or engineering logic diagrams shall be in such detail that proper hardware execution by the
system supplier is ensured. The requisition for the system shall make reference to the applicable detailed hardware
drawings, showing the position of and the interconnections between the applied modules for easy identification during
installation, testing and maintenance. The format and layout of particular ’relay diagrams’ shall be to requirements
given by the user, and the proposed presentation shall be submitted for review and approval by the user.
Each set of logic diagrams, and relay diagrams (if applicable), shall have a drawing number. Where more than one proc-
essing unit and/or major equipment package unit is involved in the project, a group of consecutive drawing numbers
shall be used for the various sets of logic diagrams and relay diagrams.
Function descriptions, including basic logic diagrams and step charts, shall be made for sequence control or safeguard-
ing systems and other complicated control systems. Function descriptions shall include test procedures for testing under
operating conditions.
These diagrams and lists shall show all incoming and outgoing signals and control lines to computer equipment, opera-
tor consoles, interface equipment such as thermocouple selectors and signal line interconnections, junction boxes, cross
boards, etc., as far as not covered in the documents and drawings for the ’normal’ instrumentation.
67
IPS-E-IN-100
Alarm and trip setting details shall be arranged as a multi-sheet drawing (2.4), in sets for each system cabinet. Each
instrument having a binary logic function shall be listed on this ’drawing’. The ’drawings’ shall be prepared in such a
way that instruments forming part of a system are grouped together on one or more sheets.
The alarm and trip setting ’drawing’ shall be set out to requirements given by the user. The format and layout to show-
ing the intended presentation shall be submitted for review by the user.
Each set of listed alarm and trip settings shall have a drawing number. Where more than one set of listed alarm and trip
settings is involved in the project, a group of consecutive drawing numbers shall be used for the various sets.
- The arrangement of all equipment in the cabinet with their tag numbers.
- The arrangement of terminals and sockets for the outside cabling with their identification.
- Assignment of each terminal and socket pin for the outside cabling.
- Facilities for earthing, outside cable supporting, ventilation and hoisting.
- Cabinet, equipment and socket/terminal row nameplate details.
- Cabinet installation details.
For guidance in the arrangement of system/auxiliary cabinets, refer to IPS-E-IN-220 "Control Center".
This drawing shall show the construction and the layout of the interface cabinet, complete with the interface relays and
cable termination details for the signals forming part of instrument engineering, and those forming part of electrical en-
gineering. For the division of responsibilities between instrument and electrical engineering disciplines, refer to Part 2
of this Standard.
The calculation sheets shall be arranged as a multi-sheet ’drawing’ (2.4), in sets for each processing unit. The calcula-
tions of the different computing relays (functions) shall be given in detail.
Each set of computing relay calculations shall have a drawing number. When more than one processing unit is involved
in the project, a group of consecutive drawing numbers shall be used for the various sets of computing relay calcula-
tions.
The system shall be shown in a multi-sheet ’drawing’ (2.4), arranged in sets for the configuration of the selected DCS.
These sets of ’drawings’ shall give information on the layout of the console, cabinets and the software function block
configuration.
Software configuration information is not required for process multiplexer systems. For multiplexer systems, informa-
tion on the tag number location in a cabinet is sufficient.
The function block configuration diagrams shall provide detailed software information, including an overview of the
interrelations of the functional elements which constitute the controls and the interface with input/output circuitry,
man/machine interface and supervisory controls as appropriate.
68
IPS-E-IN-100
During the preparation of the DCS configuration drawings, care should be taken not to include "volatile" information in
the drawing, such as proportional band setting, group display layouts, pictorials, etc. The type of information tends to
change continuously during the lifetime of the plant, so that the drawing never reaches the "as built" status. This infor-
mation shall be depicted on a separate drawing, and not included in the composite instrument manuals.
The DCS configuration drawing package shall be completed in detail so that proper configuration execution by the sys-
tem supplier is ensured.
Certain parts of the DCS configuration, such as group display layout, pictorials, historical trend, alarm group listing,
etc., shall be prepared in close cooperation with, Company’s process design, process control and operation specialists.
Each set of DCS configuration drawing sheets shall have a drawing number. A group of consecutive drawing numbers
shall be used for the various sets of DCS configuration ’drawings’.
The calculation sheets shall be arranged as a multi-sheet ’drawing’ (2.4), and for each required instrument utility, give a
detailed calculation which shall include but not necessarily be limited to:
- Instrument air, which shall consider both the baseload and the maximum air consumption requirement and be
ultimately based on selected equipment manufacturer’s quoted consumption rates,
- Electrical power load requirements e.g., for Distributed Control System (DCS), Safeguarding Systems, Emer-
gency Shutdown Systems (ESD), etc.,
The calculation shall indicate the required and the installed capacity,
During the detailed engineering stage, the instrument utility consumption calculations shall be updated and is-
sued at regular intervals to ensure that the requirements can be met.
This ’drawing’ shall contain a detailed heat dissipation calculation for all electrically powered instrument equipment
which will be installed in the instrument auxiliary room and/or satellite house and control room, in view of total heat
load for the air-conditioning system(s).
During the detailed engineering stage, the heat dissipation calculation shall be updated and issued at regular intervals to
ensure that the requirements can be met.
This "drawing" shall contain a detailed noise calculation and/or spectrum for all instrument equipment which will be
installed in the control room and contribute to a noise level higher than the allowed limit. Typical examples are printers,
cooling fans of instrument equipment, etc.
Documents and drawings are concerned with the selection, specification and ordering of on-line process stream analyz-
ers, etc., and sundry instruments. For guidance on the preparation of such documents and drawings, refer to IPS-G-IN-
230 "Analytical Instruments".
69
IPS-E-IN-100
This Sub-section concerns the documents and drawings relating to the selection, specification and ordering of flow in-
struments. Typical examples are:
Flow meter and restriction orifice calculations shall be arranged as a multi-sheet ’drawing’ (2.4), in sets for each proc-
essing unit. Each set shall have a drawing number and, where more than one processing unit is involved in the project, a
group of consecutive drawing numbers shall be used for the various sets of flow meter and restriction orifice calcula-
tions.
This Section concerns documents and drawings relating to the selection, specification and ordering of level instruments.
Typical examples are:
Calculations for differential-pressure transmitters shall be arranged as a multi-sheet ’drawing’ (2.4), and show in detail
all the required data such as transmitter elevation, type of leg and sealing fluid (if applicable), calculations of tempera-
ture effect on the sealing medium (if applicable), calibrated range and zero elevation/suppression, etc., for each applica-
tion.
This Section comprises all documents and drawings relating to the selection, specification and ordering of pressure in-
struments. Typical examples are:
This Section comprises all documents and drawings relating to the selection, specification and ordering of temperature
instruments. Typical examples are:
This Section concerns documents and drawings relating to the selection, specification and ordering of final control ele-
ments. Typical examples are:
70
IPS-E-IN-100
ISA Forms to be used for this purpose. Each set of control valve sizing and noise calculations shall have a drawing
number. Where more than one processing unit is involved in the project, a group of consecutive drawing numbers shall
be used for the various sets of control valve sizing and noise calculations sheets.
The summary consists of an index sheet and separate summary sheets for electric signal and supply cables (which form
part of instrument engineering), thermocouple signal cables, system cables.
The summary shall contain a listing of all instrumentation cables (except single cables from individual plant instruments
to plant junction boxes). The relevant sheets shall be completed at a later date, with the manufacturer’s cable reel identi-
fication code.
The first issue of the summary shall be made as soon as possible after cable supplier selection, and henceforth it shall be
revised at regular intervals, with the final issue at such a time that the cable deliveries are not endangered.
The summary consists of a table of contents and an index sheet together with sheets listing standard materials, sheets for
specifying other materials and sheets for summarizing material quantities. The first issue of the summary shall be avail-
able two months after award of the contract.
Revisions of the summary shall be issued at regular intervals but at least once every two months. Each revision issued
shall consist of a revised index sheet with summary sheet(s) attached.
The summary ’sections’ consist of a cover sheet, an index sheet, sheets indicating abbreviations, together with separate
sheets for the different instrument groups, using Standard Forms.
During the detailed engineering stage, the summary of instrument process connections shall be updated and issued at
regular intervals to ensure that the requirements can be met.
Details of the type of tag numbers and nameplate and the description of the instrument service, etc., shall be arranged as
a multi-sheet ’drawing’ (2.4).
The control room drawing shall show in detail, true to scale (using the same scale as for the auxiliary room (3.12.1)), the
general arrangement and location of instrument consoles, computer consoles, supervision panels, printers, including
console/panel numbering as applicable. It shall also show openings in the wall or floor between control room and auxil-
iary room, etc.
For projects where the auxiliary room and control room will be on the same elevation, the drawing shall indicate the
grid of the cavity floor and openings required in this floor, for bottom entry into instrument consoles, etc.
71
IPS-E-IN-100
When the project includes a digital computer for process supervision (and control), all details of the computer system
shall be clearly covered in documents and drawings as follows:
These drawings shall show the arrangement of computer equipment, cabinets, desks, etc., in the computer room
and the computer auxiliary room respectively:
This drawing shall show the layout of the air distribution ducting and the direction of the air flow,
- A layout of the cavity floor in the computer and computer auxiliary rooms
This drawing shall show the construction of the cavity floor, with an indication of the openings therein.
The drawing of the auxiliary room shall show in detail, true to scale (using the same scale as for the control room
(3.11.1)), the arrangement and identification of all equipment such as system cabinets, auxiliary, distribution and riser
cabinets. For pneumatically controlled plants, the instrument air filter/reducer station(s), etc.
This drawing shall indicate the grid of the cavity floor and the openings required in this floor for bottom entry into cabi-
nets, etc.
- The arrangement of all cable supports under the ceiling and cavity floor of the auxiliary room.
- The plant instrument signal cable entries into the auxiliary room in the correct position together with the rele-
vant cable numbers.
- The position of the plant instrument signal cable termination facilities, with their identification, and the routing
of the plant instrument signal cables to these facilities.
- For pneumatically controlled plants, the routing of the instrument air supply piping complete with pipe sizes
and branch-off points.
- The openings in the wall or floor between control room and auxiliary room.
For pneumatically controlled plants, the drawing shall show, in detail and true to scale, the actual arrangement of fil-
ter/reducer station(s) complete with detailed identification of the required hardware, supporting structure, etc. For gen-
eral requirements see IPS-E-IN-200 "Instrument Air System".
72
IPS-E-IN-100
- The arrangement of the terminal rows for outdoor cables, complete with row/terminal identification.
- The arrangement of the system cable termination boards for indoor cables, complete with row/terminal and
socket identification.
- The facilities for earthing the armouring/lead sheathing of outdoor cables, if applicable.
Drawings required for thermocouple signal cables are similar to the above, but shall also include the arrangement of
cold junction compensation boxes and their identification. Drawings for pneumatic signal tubing shall show:
- The arrangement of the terminal rows for outdoor and indoor cables, complete with row/terminal identification.
- The facilities for earthing the lead sheathing of outdoor cables, if applicable.
- The arrangement of earth bars for instrument system earth and safety earth of instrument equipment, complete
with earth bar/terminal identification, choke and arrester.
This drawing shall show in diagrammatic form all signal cabling in the auxiliary room and its connection to equipment
in the auxiliary room, to the consoles in the control room and to the plant. The drawing shall indicate the exact signal
cabling routing, including cable crossing details, and generally follow the actual layout of equipment in the auxiliary
room, but need not necessarily be true to scale.
The cable terminations shall be coded such that a clear distinction is made between cables terminating on rail-mounted
terminals, plugs, and sockets, etc. The drawing shall also include the identification of the equipment, the cables, and the
system cable sockets mounted in the equipment.
Separate drawings shall be prepared for DCS earth, computer earth, instrument system earth and safety earth of instru-
ment equipment.
These drawings shall show in diagrammatic form all earth cabling from the system earth cabinet in the auxiliary room
and its connections to equipment in the auxiliary room and consoles in the control room. They shall also include the
identification of equipment and earth cables.
The drawing shall generally follow the actual layout of equipment in the auxiliary room, but need not necessarily be true
to scale.
73
IPS-E-IN-100
Drawings shall show the layout (to scale) of the main instrument console(s), the location of each instrument or group of
instruments and equipment in outline, with tag numbers(s) for each individual instrument or equipment such as visual
display units, keyboards, alarm annunciator panel, manual switches, etc. The main dimensions of the complete console
and the console sections shall be given and the console sections shall be numbered for identification.
Drawing(s) shall show the cut-out dimensions for all console sections. Drawings for prefabricated instrument consoles
shall be prepared by the console supplier based on the layout drawings and the detailed drawings for cut-out and bezel
dimensions for equipment not forming part of the supply of the console manufacturer.
Construction drawings shall give all information required for manufacturing and erecting the instrument consoles, in-
cluding the supporting details of the equipment mounted in the consoles. They should also indicate facilities to allow
maintenance personnel to reach from the rear of the console, equipment, installed in the front part.
Drawings shall show the layout (full scale) of the semi-graphic panels (mimic panels). The display shall consist of a
simplified plant flow diagrams with indication lights for valves states and controls if applicable.
For guidance in the preparation of the alarm annunciator panel, refer to IPS-E-IN-260 "Alarms and Shutdown Control
Circuits".
Drawing(s) shall show the layout (full scale) of the fire and gas detection display panel, giving main dimensions. The
display shall consist of a geographical plant representation for flammable gas, fire, smoke and hydrogen sulphide detec-
tion with indication lights for alarms, maintenance override status indication and manual call points.
For guidance in the preparation of the fire and gas detection display panel, refer to IPS-E-SF-260 "Automatic Fire and
Gas Detection Panel".
Drawings shall show the layout (to scale) of each local panel, with the instruments in outline and giving the tag number
for each instrument.
Construction drawings shall give all information required for manufacturing the local panels. Fully dimensioned cutouts
for all instruments shall be included, either on the same drawing or presented separately.
74
IPS-E-IN-100
The location of instruments shall be shown, superimposed on sections of a simplified plot plan as follows:
- All field mounted instruments, including local indicators and temperature indicators.
- All trunking for instrument cabling and its riser points from (underground) trenches, complete with sizes,
bends, branches and supporting points.
- All instrument air supply piping from its demarcation points with mechanical engineering to the relevant (group
of) consumers. Isolating valves, branch-off points and pipe sizes shall be clearly indicated.
Note:
In general, separate drawings shall be provided for the location of instruments relating to:
- Processing units.
- Flammable gas, fire and smoke detection and deluge systems.
- Toxic gas detection.
Each drawing shall contain a list of all instruments and junction boxes. Each list shall show, in sequence of tag number,
the (plant) coordinates for location of the equipment and its elevation above plant grade level.
Where instrumentation installation in structures is involved, preference shall be given to the preparation of layout draw-
ings for different levels, e.g., for each platform, and/or drawings showing such structures in sideview (elevation) con-
taining all the above information.
Where one drawing showing all the information would become too congested, consideration should be given to:
- Changing the scale of the drawing, or where necessary covering the processing unit on several drawings, on the
same scale.
- Splitting the information over two drawings, with one drawing showing instruments and junction boxes, and the
other showing junction boxes, cable trunking, conduits and air supply piping, this drawing shall then have the
title ’Location of Cable Trunking and Air Supply Piping’.
Complicated cable trunking shall also be shown in isometric form if plan/elevation drawings would not be sufficiently
clear for fabrication of trunking systems.
Where the cable trunking will be of fire resistant construction, it shall be shown on detailed construction drawings.
Where the cable trunking requires special supports, these shall be shown on detailed construction drawings, and a deci-
sion shall be taken whether they can form part of the installation activities or whether they should be requisitioned sepa-
rately for prefabrication.
75
IPS-E-IN-100
Drawings shall show the location of trenches for instrument cables complete with indication of size, branch-off points,
etc. Details of trench construction, methods of backfilling and trench closure shall also be indicated.
Note:
These drawings shall be prepared in close co-operation between instrument, electrical and civil engineering. the ultimate
drawing(s) may form part of civil engineering, provided detailed references are made on the instrumentation drawings.
Drawings shall show the aboveground and underground routing of all instrumentation cables from their termination
point in the plant to their termination point in the control building, complete with the laying pattern for cable segrega-
tion.
Cables for similar applications, such as for fire, gas and smoke detection and deluge systems shall also be indicated on
the drawings.
Special attention shall then be paid to the need for additional branches and riser points in these power cable trenches for
accommodating the instrument electricity supply cables.
All riser points for instruments power cables shall also be indicated on the drawings ’Layout of instrument cables in the
plant’, complete with the aboveground cable routing to the individual consumers. Cross references shall then be made
on both drawings.
The instrument power supply shall be shown diagrammatically, from the electrical distribution switchboards to the con-
sumers, and shall include:
For the division of responsibilities between instrument and electrical engineering disciplines, refer to Part 2, of this
Standard.
Drawing(s) shall show the layout of the instrument electricity supply cables, complete with the cable numbers, from the
distribution board(s) forming part of electrical engineering, under the cavity floor and up into the system and auxiliary
cabinets, and up through riser cabinets into the instrument panels of the control room, etc., and into the computer room.
The drawing shall show in detail, true to scale and on the same scale as ’Layout of an analyzer house’, the instrument
electricity supply connections for the individual consumers. Complete with de-energizing facilities for each consumer,
socket outlets for electrical tools and test equipment, and the cable routing from point of entry to the consumers.
76
IPS-E-IN-100
Instrument air lines shall be prepared as a multi-sheet ’drawing’ (2.4), showing in detail, the arrangement of the individ-
ual air supply for each pneumatically operated instrument, using the appropriate sheets of Standard form refer to IPS-C-
IN-200 "Installation Standard for Instrument Air System".
Dedicated instrument air line details shall be provided for instruments related to fire detection facilities and deluge sys-
tems.
- Cross sections of trenches showing the location and laying pattern of each group of cables.
- Procedures for laying cables in trunking, and methods for fixing the cables, etc.
- Details/procedures for laying cables entering the auxiliary room with respect to their termination point.
- Details for covering/sealing/fire proofing of cable entries into the auxiliary and control room.
- Details/procedures for stripping length and finishing touch of cables in particular with respect to cable glands.
- Procedures for termination of cables in thermocouple heads, transmitters, converters, solenoid valves, manual
switches junction boxes, distribution cabinets, etc.
The ’drawing’ shall also give dedicated earthing principles and details for instrument equipment such as:
- Instrument earthing, for signal cable screen continuity and earthing point, system cables, reference system earth
bar, etc.
- Safety earthing for signal cable armouring/lead sheathing, system cabinets, frames, instrument desks/consoles,
recessed floor(s), instrument cable trunking, junction boxes, local panels, power distribution boards, etc.
Instrument cable terminations in the form of a multi-sheet ’drawing’ (2.4) shall be prepared. These drawings shall be set
out to the requirements given by the user. The format and layout shall be submitted for review by the user prior to full
scale application. The multi-sheet ’drawing’ shall indicate the requirements of the following Sub-sections:
77
IPS-E-IN-100
- The (multi-element) signal cable(s) connected to these terminals with full identification by cable number(s),
pair/ quad number, color or number coding of wires, etc.
If more than one signal is related to a tag number, the following code shall be added:
- The terminal rows for plant and indoor tubing, complete with row and terminal identification and tubing num-
bers.
- The direct tubing between the terminal rows for indoor cables.
- The terminal rows and shunt diode safety barriers, if applicable, for plant cables, complete with row and termi-
nal or barrier identification and cable numbers.
- The terminal rows for indoor cables, complete with row/terminal identification.
- The cross wiring between the terminal row(s) for plant cables via the cold junction compensation boxes, com-
plete with row/terminal, box/terminal identification.
- The terminal rows for plant cables complete with row and terminal identification and cable numbers.
- Terminal rows for indoor cables complete with row/terminal identification.
- The cross wiring between the terminal rows.
- The direct wiring between the terminal rows for indoor cables.
Instrument impulse line details shall be prepared as a multi-sheet ’drawing’ (2.4), in sets for each processing unit, using
the appropriate ’Standard Forms’.
Each set of instrument impulse lines shall have a drawing number. Where more than one processing unit is involved in
the project, a group of consecutive drawing numbers shall be used for the various sets of instrument impulse lines.
Documents and drawings giving details of analyzer and sampling systems, etc., shall be prepared as follows, arranged in
sets for each on-line analyzer:
78
IPS-E-IN-100
- Calculations of the ratio of the sample line flow and the normal process line flow.
- Layout drawing(s) of analyzer sample transport system ’in isometric form’ showing the routing of the sample
transport lines from the sample take-off/return points in the plant, to the sample conditioning system at the ana-
lyzer house.
- Calculations of the conditions at the inlet and outlet of the sample conditioning system.
- Calculations of the percentage of normal flow in the process line which is vented (flared) or drained.
- The analyzer and related equipment such as programmers, peak pickers (peak holders), recorders, convertors,
etc.
- Calculations for auxiliary equipment such as heaters, coolers, pumps, tracing/lagging, etc., to obtain the re-
quired sample inlet conditions.
For guidance in the preparation of the above documents and drawings, refer to IPS-G-IN-230 "Analytical Instruments":
- Analyzer data sheet, using Standard Form for analyzer arrangements requiring a sample conditioning system.
Note:
The range of all instruments, in the above systems shall be specified in the requisition.
The range of the instruments shall also be specified on the appropriate documents and drawings. Each set of in-line
analyzer documents and drawings shall have a drawing number. Where more than one analyzer is involved in the pro-
ject, a group of consecutive drawing numbers shall be used for the various sets of documents and drawings.
A drawing, true to scale and on the same scale as the drawing ’Layout of instrument electricity supply in the analyzer
house’, shall show in detail the arrangement of all equipment in and around the analyzer house.
The equipment such as sample lines and conditioning systems, drain/vent systems, air conditioning, heating/ventilation
systems, analyzers and their related equipment, junction boxes, initiating elements of safeguarding systems, sink, work-
bench, etc., shall where applicable be identified with line and/or tag numbers, etc.
For guidance in the preparation of the layout of analyzer house(s), refer to IPS-G-IN-230 "Analytical Instruments".