CONSTRUCTION BAR CHART (WORK SCHEDULE)
DES NTH
MO
ONTH
M
NTH
MO
NTH
MO
NTH
MO
NTH
MO
NTH
MO
NTH
MO
CRIPTION/ WORKS 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Bldg. permit and other documents
Mobilization- material and workers
Site preparation: lot clearing, staking,
perimeter barricade
Excavation of footings and foundation
Concreting of footings and foundation
CHB laying- exterior/ divisions on ground floor
Slab concreting on fill
Formworks for second floor slab, stairs
Electrical and sanitary rough-ins
Concreting of second floor slab
CHB laying- exterior/ divisions on second floor
Installation of door jambs/ kitchen counter slab
Plastering- interior/exterior/moldings/stone
works
Paint works
Sanitary, Electrical, and Mechanical fixtures
Clean up-extraction of all debris