Part C
Part C
PART - C
SECTION – VI
TECHNICAL SPECIFICATION
FOR
(This document is meant for the exclusive purpose of bidding against this Package and shall not be
transferred, reproduced or otherwise used for purposes other than that for which it is specifically issued).
PART - C
GENERAL TECHNICAL REQUIREMENTS
TECHNICAL SPECIFICATION
RAGHUNATHPUR THERMAL POWER STATION SECTION-VI, PART-C
PHASE-II (2X660 MW) SEPARATOR
EPC PACKAGE ( EXCLUDING STG PKG.) BID DOC NO. CS-9586-001A-2
CLAUSE NO.
GENERAL TECHNICAL REQUIREMENTS
1.00.00 INTRODUCTION
This part covers technical requirements which will form an integral part of the
Contract. The following provisions shall supplement all the detailed technical
specifications and requirements brought out in Section-VI, the Technical
Specification and the Technical Data Sheets.
The Bidder's proposal shall be based upon the use of equipment and material
complying fully with the requirements specified herein. It is recognized that the
Contractor may have standardized on the use of certain components, materials,
processes or procedures different than those specified herein. Alternate proposals
offering similar equipment based on the manufacturer's standard practice will also be
considered, provided the base offer is in line with technical specifications and such
proposals meet the specified design standards and performance requirement and
are acceptable to the Employer. Sufficient amount of information for justifying such
proposals shall be furnished to Employer alongwith the bid to enable the Employer
to determine the acceptability of these proposals.
4.01.00 Bidders may note that this is an EPC Package contract. Each of the plant shall be
engineered and designed in accordance with the specification requirement. All
engineering and associated services are required to ensure a completely engineered
plant shall be provided.
4.02.00 All equipments furnished by the Contractor shall be complete in every respect, with
all mountings, fittings, fixtures and standard accessories normally provided with such
equipment and/or those needed for erection, completion and safe operation of the
equipment and for the safety of the operating personnel, as required by applicable
codes, though they may not have been specifically detailed in the respective
specifications, unless included in the list of exclusions.
4.03.00 For the C&I systems, the Contractor shall be required to provide regular information
about future upgrades and migration paths to the Employer.
5.01.00 In addition to the codes and standards specifically mentioned in the relevant
technical specifications for the equipment / plant / system, all equipment parts,
systems and works covered under this specification shall comply with all currently
applicable statutory regulations and safety codes of the Republic of India as well as
of the locality where they will be installed, including the following :
5.02.00 Unless covered otherwise in the specifications, the latest editions (as applicable as
on the date of bid opening), of the codes and standards given below shall also apply:
p) IEEE standard
q) JEC standard
5.03.00 Other International/ National standards such as DIN, VDI, BS, GOST etc. shall also
be accepted for only material codes and manufacturing standards, subject to the
Employer's approval, for which the Bidder shall furnish, adequate information to
justify that these standards are equivalent or superior to the standards mentioned
above. In all such cases the Bidder shall furnish specifically the variations and
deviations from the standards mentioned elsewhere in the specification together with
the complete word to word translation of the standard that is normally not published
in English.
5.05.00 In the event of any conflict between the codes and standards referred to in the
above clauses and the requirement of this specification, the requirement of
Technical Specification shall govern.
5.06.00 Two (2) English language copies of all national and international codes and/or
standards used in the design of the plant and equipment shall be provided by the
Contractor to the Employer within two calendar months from the date of the
Notification of Award.
5.07.00 In case of any change in codes, standards & regulations between the date of bid
opening and the date when vendors proceed with fabrication, the Employer shall
have the option to incorporate the changed requirements or to retain the original
standard. It shall be the responsibility of the Contractor to bring to the notice of the
Employer such changes and advise Employer of the resulting effect.
5.08.00 A detailed list of standards apart from those mentioned in the respective detailed
specifications in other parts of Section-VI to which all equipment/systems/civil works
should conform as indicated in this Part C and elsewhere in the specification.
6.01.00 The functional guarantees of the equipment under the scope of the Contract is given
in Section-VI Part - A & B of Technical Specifications. These guarantees shall
supplement the general functional guarantee provisions covered under Defect
liabilities Section-IV, General Conditions of Contract.
6.02.00 Liquidated damages for shortfall in meeting functional guarantee(s) during the
performance and guarantee tests shall be assessed and recovered from the
Contractor as specified elsewhere in this specification.
All the design procedures, systems and components proposed shall have already
been adequately developed and shall have demonstrated good reliability under
similar conditions elsewhere.
The Contractor shall be responsible for the selection and design of appropriate
equipments to provide the best co-ordinated performance of the entire system. The
basic requirements are detailed out in various clauses of the Technical
Specifications. The design of various components, assemblies and subassemblies
shall be done so that it facilitates easy field assembly and dismantling. All the
rotating components shall be so selected that the natural frequency of the complete
unit is not critical or close to the operating range of the unit.
Bidder shall state in his offer the various maintenance intervals, spare parts and
man-hour requirement during such operation. The intervals for each type of
maintenance namely inspection of the furnace, inspection of the entire hot gas path,
inspection of the steam path and the minor and major overhauls shall be specified in
terms of fired hours, clearly defining the spare parts and man-hour requirement for
each stage.
Lifting devices i.e. hoists and chain pulley jacks, etc. shall be provided by the
contractor for handling of any equipment or any of its part having weight in excess of
500 Kgs during erection and maintenance activities.
Lifting devices like lifting tackles, slings, etc. to be connected to hook of the hoist /
crane shall be provided by the contractor for lifting the equipment and accessories
covered under the specification.
8.01.00 Bidders may note that this is an EPC Package contract. Each of the plant and
equipment shall be fully integrated, engineered and designed to perform in
accordance with the technical specification. All engineering and technical services
required to ensure a completely engineered plant shall be provided in respect of
mechanical, electrical and power systems, control & instrumentation, civil &
structural works as per the scope.
Each main and auxiliary equipment/item of the plant including instruments shall be
assigned a unique tag number. The assignment of tag numbers shall be in
accordance with KKS system. In all drawings/documents/data sheet etc. KKS tag
number of the equipment/item/instrument etc. shall be indicated.
The Contractor shall furnish engineering data /drawings in accordance with the
schedule of information as specified in Technical Data Sheets and Technical
Specification.
8.03.00 The documentation that shall be provided by the Contractor is indicated in the
various sections of specification. This documentation shall include but not be limited
to the following:
vi) Schemes and Process & Instrumentation diagrams for the various
systems/ sub-system with functional write-ups.
viii) Operation Philosophy and the control philosophy of the Main Plant
and other plants.
ix) General Layout plan of the power station incorporating all facilities in
Bidder's as well as those in the Employer's scope. This drawing shall
also be furnished in the form of CD-ROMs to the Employer for
engineering of areas not included in bidder's scope.
x) Basic layouts and cross sections of the main plant building (various
floor elevations), boiler, fuel oil area, transformer yard, switchyard and
other areas included in the scope of the bidder.
The successful bidder shall furnish within three (3) weeks from the
date of Notification of Award, a list of contents of the Plant Definition
Manual (PDMs) including techno-economic studies, which shall then
be mutually discussed & finalised with the Employer.
iii) Flow diagram, Process and Instrumentation diagrams along with write
up and system description.
iv) Start-up curves for boiler and both turbines and boiler combined
together as a unit for various start-ups, viz. Cold, Warm and Hot start
up.
vii) Technical data sheets for all bought out and manufactured items.
Contractor shall use the Employer’s specifications as a base for
placement of orders on their sub vendors.
xiv) Power supply single line diagram, block logics, control schematics,
electrical schematics, etc.
xviii) Instrument schedule, measuring point list, I/O list, Interconnection &
wiring diagram, functional write-ups, installation drawings for field
mounted instruments, logic diagrams, control schematics, wiring and
tubing diagrams of panels and enclosures etc. Drawings for open
loop and close loop controls (both hardware and software). Motor list
and valve schedule including type of actuator etc.
xix) Alarm and annunciation/ Sequence of Event (SOE) list and alarms &
trip set points.
xxi) Type test reports, insulation co-ordination study report and power
system stability study report.
xxii) Control system configuration diagrams and card circuit diagrams and
maintenance details.
xxvi) Civil and Structural works drawings and documents for all structures,
facilities, architectural works, foundations underground and
overground works and super-structural works as included in the
scope of the bidder civil calculation sheets including structural
analysis and design alongwith output results.
xxxiii) Bidder shall submit all tabulated design calculations/ data (e.g. Pipe
schedule, valve schedule, etc.), in both EXCEL format as well as in
PDF format to enable DVC for fast review /approval.
The Contractor shall submit to the Employer, draft Instruction Manuals for all the
equipments covered under the Contract by the end of one year from the date of his
acceptance of the Letter of Award. The Instruction manuals shall contain full details
required for erection, commissioning, operation and maintenance of each
equipment. The manual shall be specifically compiled for this project. After
finalisation and approval of the Employer the Instruction Manuals shall be submitted
as indicated in Annexure-IV. The Contract shall not be considered to be completed
for purposes of taking over until the final Instructions manuals have been supplied to
the Employer. The Instruction Manuals shall comprise of the following.
A) ERECTION MANUALS
The erection manuals shall be submitted at least three (3) months prior to the
commencement of erection activities of a particular equipment/system. The
erection manual should contain the following as a minimum.
a) Erection strategy.
b) Sequence of erection.
c) Erection instructions.
f) Bill of Materials
a) The manual shall be a two rim PVC bound stiff sided binder able to
withstand constant usage or where a thicker type is required it shall
have locking steel pins, the size of the manual shall not be larger
than international size A3. The cover shall be printed with the Project
Name, Services covered and Volume / Book number Each section of
the manual shall be divided by a stiff divider of the same size as the
holder. The dividers shall clearly state the section number and title.
All written instructions within the manual not provided by the
manufacturers shall be typewritten with a margin on the left hand
side.
(e) Design data against which the plant performance will be compared.
(g) Identification system adopted for the various components, (it will be of
a simple process linked tagging system).
2) Chapter 2.0 - Plant Operation: To contain the following sections specific to the
equipment supplied
(d) Startup and shut down procedure for equipment alongwith the
associated systems in step mode.
(l) Change over schedule if more than one auxiliary for the same
purpose is given.
(b) Exploded view of the spare parts and critical components with
dimensional drawings (In case of Electronic cards, the circuit diagram
to be given) and spare parts catalogue for each equipment.
(k) Details of sub vendors with their part no. in case of bought out items.
(l) List of spare parts with their Part No, total population, life expediency
& their interchangeability with already supplied spares to DVC.
(n) Lead time required for ordering of spares from the equipment
supplier, instructions for storage and preservation of spares.
8.03.03 After finalization and approval of the Employer, the O & M Manuals shall be
submitted as indicated in Annexure-VI. The Contract shall not be considered to be
completed for purposes of taking over until the final Instructions manuals (both
erection and O & M manuals have been supplied to the Employer.
If after the commissioning and initial operation of the plant, the instruction manuals
(Erection and /or O &M manuals) require modifications/additions/ changes, the same
shall be incorporated and the updated final instruction manuals shall be submitted by
the Contractor to the Employer for records and number of copies shall be as
mentioned in Annexure-VI.
The Contractor shall submit to the Employer a preliminary plant hand book
preferably in A-4 size sheets which shall contain the design and performance data of
various plants, equipments and systems covering the complete project including
vii) General layout plan and layout of main plant building and auxiliary buildings
The plant handbook shall be submitted within twelve (12) months from the date of
award of contract. After the incorporation of Employer's comments, the final plant
handbook complete in all respects shall be submitted three (3) months before start-
up and commissioning activities.
iii) Final copies of the approved drawings along with requisite number of
hard copies shall be submitted as per Annexure-VI of Part-C.
iv) Contractor shall prepare the model of all the facilities located within
plant boundary covering facilities in Main Plant Block area and
Balance of plant (BOP) area in an integrated & intelligent 3D software
solution. Main Plant Block area shall include Transformer Yard, TG
building (including all facilities), Boiler area, ESP area, chimney area,
FGD area and any other facility located in main plant block. BOP area
shall include all facilities pertaining to AHP, CHP, LHP, GHP, DM PT
plant, pipe & cable racks and any other facility located within plant
boundary.
All piping layouts, equipment layouts, floor plans, ducting layout
(Air/flue gas, A/C, Ventilation etc.), General Arrangement drawings
and RCC layout of major buildings and structural arrangement
RAGHUNATHPUR THERMAL POWER
TECHNICAL SPECIFICATIONS
STATION PHASE-II (2X660 MW) GENERAL TECHNICAL PAGE
SECTION VI, PART-C
EPC PACKAGE ( EXCLUDING STG PKG.) REQUIREMENTS 15 OF 108
BID DOC NO CS-9586-001A-2
CLAUSE NO.
GENERAL TECHNICAL REQUIREMENTS
All input files of software used for design of Equipments / Piping like
CAESAR2 files, input files for Pressure vessel design, datasheets etc.,
shall be handed over to DVC as per DVC specifications for handover
of Engineering Information.
e) The drawings submitted by the Contractor (or their subvendors) shall bear
Employer's drawing number in addition to contractor's (their sub-vendor's)
own drawing number. Employer's drawing numbering system shall be made
available to the successful bidder to enable him to assign Employer's
drawing numbers to the drawings to be submitted by him during the course of
execution of the Contract.
Similarly, all the drawings/ documents submitted by the Contractor during
detailed engineering stage shall be marked "FOR APPROVAL" or "FOR
INFORMATION" prior to submission in line with suggestive MDL.
Further, space shall be identified on each drawing for Approval stamp and
electronic signature.
g) After the approval of the drawings, further work by the Contractor shall be in
strict accordance with these approved drawings and no deviation shall be
permitted without the written approval of the Employer.
i) Drawings shall include all installations and detailed piping layout drawings.
Layout drawings for all piping of 65 mm and larger diameter shall be
submitted for review/ approval of Employer prior to erection. Small diameter
pipes shall however be routed as per site conditions in consultation with site
authority/ representative of Employer based on requirements of such piping
indicated in approved/ finalised Flow Scheme/ Process & Instrumentation
Diagrams and/or the requirements cropping up for draining & venting of
larger diameter piping or otherwise after their erection as per actual physical
condition for the entire scope of work of this package.
Assessing & anticipating the requirement and supply of all piping and
equipment shall be done by the contractor well in advance so as not to
hinder the progress of piping & equipment erection, subsequent system
charging and its effective draining & venting arrangement as per site
suitability.
j) As Built Drawings
m) All engineering data submitted by the Contractor after final process including
review and approval by the Project Manager/ Employer shall form part of the
contract documents and the entire works covered under these specification
shall be performed in strict conformity with technical specifications unless
otherwise expressly requested by the Project Manager in writing.
8.03.05 NOT USED
All the Plant and equipments / Systems supplied under the contract shall be
designed following “Fail Safe” concept. In case of failure of Power supply like
Electric power, Hydraulic pressure, Pneumatic pressure, Vacuum etc. the system
should be designed in such a way that the equipment/Valves/dampers etc. shall
always move/remains (as applicable) to safest position as per system requirement to
ensure safety of Man and Machinery.
Name :
Designation :
Address :
a) Postal :
b) Telegraphic / e-Mail :
c) FAX : TELEPHONE :
Name :
Designation :
Address :
a) Postal :
b) Telegraphic / e-Mail :
c) FAX : TELEPHONE :
b) Not used
c) All drawings (including those of subvendor’s) shall bear at the right hand
bottom corner the ‘title plate’ with all relevant information duly filled in. The
Contractor shall furnish this format to his sub-vendor along with his purchase
order for sub-vendor’s compliance.
d) Not used
e) The contractor shall make a visit to site to see the existing facilities and
understand the layout completely and collect all necessary data / drawings at
site which are needed as an input to the engineering. The contractor shall do
the complete engineering including interfacing and integration of all his
equipment, systems & facilities within his scope of work as well as interface
engineering & integration of systems, facilities, equipment & works under
Employer’s scope and submit all necessary drawings/ documents for the
same.
g) The Contractor shall submit drawing / data / document for Employer’s review
and approval. The drawings submitted by the Contractor/vendor shall be
reviewed by DVC and their comments shall be forwarded within three (3)
weeks of receipt of drawings. Upon review of each drawing, depending on
the correctness and completeness of the drawing, the same will be
categorized and approval accorded in one of the following categories:
CATEGORY- I : Approved
h) After Rev 0 comments, the drawing will be locked in the system. Contractor
will review the Rev 0 comments within 7 days & furnish the Comment Reply
Sheet (CRS) to DVC as an agenda point for TCM. TCM shall be conducted
with Contractor on non-agreed comments of CRS. System will not allow
Contractor to submit approval category drawings before the scheduled
submission date. However, documents may be unlocked on case to case
basis. Based on resolution of all comments and agreements, the document
will be approved in TCM itself. The contractor will revise the document based
on the resolutions and certify that all the resolutions has been taken care of.
Based on this certification, the document will be opened and submitted by
contractor in the system for approval as Rev 01 within 10 days of TCM.
i) In case, the Contractor/ Vendor does not agree with any specific comment,
he shall furnish the explanation for the same to DVC for consideration. In all
such cases the Contractor shall necessarily enclose explanations along with
the revised drawing (taking care of balance comments) to avoid any delay
and/or duplication in review work.
l) These comments will be taken care by the contractor while submitting the
revised drawing.
The contractor shall use a single transmittal for drawings. Submission. This shall
include transmittal numbers and date, number of copies being sent, names of the
agencies to whom copies being sent, drawing number and titles, remarks or special
notes if any etc.
8.06.01 The Contractor shall submit every month an Engineering progress and Exception
Report giving the status of each engineering information including
8.06.02 The draft format for this report shall be furnished to the Employer within four (4)
weeks of the award of the contract, which shall then be discussed and finalised with
the Employer.
9.01.00 The Contractor shall be called upon to organise and attend monthly Design/
Technical Co-ordination Meetings (TCMs) with the Employer/Employer's
representatives and other Contractors of the Employer during the period of contract.
The Contractor shall attend such meetings at his own cost at KOLKATA or at
mutually agreed venue as and when required and fully co-operate with such persons
and agencies involved during the discussions.
9.02.00 The Contractor should note that Time is the essence of the contract. In order to
expedite the early completion of engineering activities, the comments of the
Employer shall be discussed across the table during the above Technical Co-
ordination Meeting (s) wherein best efforts shall be made by both sides to ensure the
approval of the drawing.
9.02.01 The Contractor shall ensure availability of the concerned experts / consultants/
personnel who are empowered to take necessary decisions during these meetings.
The Contractor shall be equipped with necessary tools and facilities so that the
drawings/documents can be resubmitted after incorporating necessary changes and
approved during the meeting itself.
9.02.02 Should any drawing remain unapproved for more than six (6) weeks after it's first
submission, this shall be brought out in the monthly Engineering Progress and
Exception Report with reasons thereof.
9.03.0 Any delays arising out of failure by the Contractor to incorporate Employer's
comments and resubmit the same during the TCM shall be considered as a default
and in no case shall entitle the Contractor to alter the Contract completion date.
The Employer or the Contractor may propose changes in the specification of the
equipment or quality thereof and if the parties agree upon any such changes the
specification shall be modified accordingly.
If any such agreed upon change is such that it affects the price and schedule of
completion, the parties shall agree in writing as to the extent of any changing the
price and/or schedule of completion before the Contractor proceeds with the change.
Following such agreement, the provision thereof, shall be deemed to have been
amended accordingly.
A cast iron or welded steel base plate shall be provided for all rotating equipment
which is to be installed on a concrete base, unless otherwise specifically agreed to
by the Employer. Each base plate shall support the unit and its drive assembly, shall
be of a neat design with pads for anchoring the units, shall have a raised lip all
around, and shall have threaded drain connections.
Suitable guards shall be provided for protection of personnel on all exposed rotating
and/or moving machine parts. All such guards shall be designed for easy installation
and removal for maintenance purpose.
13.01.00 All the first fill and one year’s topping requirement of consumables such as greases,
oils, lubricants, servo fluids / control fluids, gases etc. which will be required to put
the equipment covered under the scope of specifications into successful
commissioning/initial operation and to establish completion of facilities shall be
supplied by the contractor. Suitable standard lubricants as available in India are
desired. Efforts should be made to limit the variety of lubricants to minimum.
Bidder shall supply a quantity not less than 10% of the full charge or one (1) year
topping requirement mentioned above (Whichever is higher) of each variety of
lubricants, servo fluids, gases etc. (as detailed above) used which is expected to be
utilized during the first year of operation. This additional quantity shall be supplied in
separate containers.
13.02.00 As far as possible lubricants marketed by the Indian Oil Corporation shall be used.
The variety of lubricants shall be kept to a minimum possible.
Detailed specifications for the lubricating oil, grease, gases, servo fluids, control
fluids, chemicals etc. required for the complete plant covered herein shall be
furnished. On completion of erection, a complete list of bearings/ equipment giving
their location and identification marks shall be furnished to the Employer alongwith
lubrication requirements.
14.00.00 LUBRICATION
15.01.00 All materials used for the construction of the equipment shall be new and shall be in
accordance with the requirements of this specification. Materials utilised for various
components shall be those which have established themselves for use in such
applications.
16.01.00 Each main and auxiliary item of plant shall have permanently attached to it in a
conspicuous position, a rating plate of non-corrosive material upon which shall be
engraved manufacturer’s name, equipment, type or serial number together with
details of the ratings, service conditions under which the item of plant in question
has been designed to operate, and such diagram plates as may be required by the
Employer.
16.02.00 Each item of plant shall be provided with nameplate or label designating the service
of the particular equipment. The inscriptions shall be approved by the Employer or
as detailed in appropriate section of the technical specifications.
16.03.00 Such nameplates or labels shall be of white non-hygroscopic material with engraved
black lettering or alternately, in the case of indoor circuit breakers, starters, etc. of
transparent plastic material with suitably coloured lettering engraved on the back.
16.04.00 Items of plant such as valves, which are subject to handling, shall be provided with
an engraved chromium plated nameplate or label with engraving filled with enamel.
The name plates for valves shall be marked in accordance with MSS standard SP-
25 and ANSI B 16.34 as a minimum.
16.05.00 Hanger/ support numbers shall be marked on all pipe supports, anchors, hangers,
snubbers and restraint assemblies. Each constant and variable spring support shall
also have stamped upon it the designed hot and cold load which it is intended to
support.
16.06.00 Valves, steam traps and strainers shall be identified by Employer's tag number of a
metal tap permanently attached to non-pressure parts such as the yoke by a
stainless steel wire. The direction of flow shall also be marked on the body.
16.07.00 Safety and relief valves shall be provided with the following:
a) Manufacturer's identification.
16.08.00 All such plates, instruction plates, etc. shall be bilingual with Hindi inscription first,
followed by English. Alternatively, two separate plates one with Hindi and the other
with English inscriptions may be provided.
16.09.00 All segregated phases of conductors or bus ducts, indoor or outdoor, shall be
provided with coloured phase plates to clearly identify the phase of the system.
The Contractor shall supply with the equipment one complete set of all special tools
and tackles and other instruments required and other instruments for the erection,
RAGHUNATHPUR THERMAL POWER
TECHNICAL SPECIFICATIONS
STATION PHASE-II (2X660 MW) GENERAL TECHNICAL PAGE
SECTION VI, PART-C
EPC PACKAGE ( EXCLUDING STG PKG.) REQUIREMENTS 25 OF 108
BID DOC NO CS-9586-001A-2
CLAUSE NO.
GENERAL TECHNICAL REQUIREMENTS
assembly, disassembly and proper maintenance of the plant and equipment and
systems (including software). These special tools will also include special material
handling equipment, jigs and fixtures for maintenance and calibration / readjustment,
checking and measurement aids etc. A list of such tools and tackles shall be
submitted by the Bidder alongwith the offer.
The price of each tool / tackle shall be deemed to have been included in the total bid
price. These tools and tackles shall be separately packed and sent to site. The
Contractor shall also ensure that these tools and tackles are not used by him during
erection, commissioning and initial operation. For this period the Contractor should
bring his own tools and tackles. All the tools and tackles shall be of reputed make
acceptable to the Employer.
18.00.00 WELDING
18.01.00 If the manufacturer has special requirements relating to the welding procedures for
welds at the terminals of the equipments to be performed by others the requirements
shall be submitted to the Employer in advance of commencement of erection work.
19.01.00 All equipment/ piping/ pipe services are to be painted by the Contractor in
accordance with Employer's standard colour coding scheme, which will be furnished
to the Contractor during detailed engineering stage.
20.01.00 PROTECTION
All coated surfaces shall be protected against abrasion, impact, discoloration and
any other damages. All exposed threaded portions shall be suitably protected with
either metallic or a non-metallic protection device. All ends of all valves and piping
and conduit equipment connections shall be properly sealed with suitable devices to
protect them from damage. All primers/paints/coatings shall take into account the hot
humid, corrosive & alkaline, subsoil or over ground environment as the case may be.
The requirements for painting specification shall be complied with as detailed out in
Part-A & B of the Technical Specification.
painted as per the requirements covered in the relevant part of the Technical
Specification.
Transformers and other electrical equipments, if included shall be shop finished with
one or more coats of primer and two coats of high grade resistance enamel. The
finished colors shall be as per manufacturer's standards, to be selected and
specified by the Employer at a later date.
20.03.00 Shop primer for all steel surfaces which will be exposed to operating temperature
below 95 degrees Celsius shall be selected by the Contractor after obtaining specific
approval of the Employer regarding the quality of primer proposed to be applied.
Special high temperature primer shall be used on surfaces exposed to temperature
higher than 95 degrees Celsius and such primer shall also be subject to the approval
of the Employer.
20.04.00 All other steel surfaces which are not to be painted shall be coated with suitable dust
preventive compound subject to the approval of the Employer.
20.05.00 All piping shall be cleaned after shop assembly by shot blasting or other means
approved by the Employer. Lube oil piping or carbon steel shall be pickled.
20.06.00 Painting for Civil structures and equipment/system covered under this package shall
be done as specified under technical requirements on civil works in relevant part of
this specifications.
21.01.00 To ensure that the equipment and services under the scope of contract whether
manufactured or performed within the Contractor’s works or at his sub-contractor’s
premises or at the Employer’s site or at any other place of work are in accordance
with the specifications, the Contractor shall adopt suitable quality assurance
programme to control such activities at all points, as necessary. Such programmes
shall be outlined by the Contractor and shall be finally accepted by the
Employer/authorised representative after discussions before the award of the
contract. The QA programme shall be generally in line with ISO-9001/IS-14001. A
quality assurance programme of the contractor shall generally cover the following:
g) System for shop manufacturing and site erection control including process
controls and fabrication and assembly controls.
i) Inspection and test procedure both for manufacture and field activities.
p) Furnishing of quality plans for manufacturing and field activities detailing out the
specific quality control procedure adopted for controlling the quality
characteristics relevant to each item of equipment/component .Formats for the
same will be shared along with QA Coordination procedure.
22.01.00 All materials, components and equipment covered under this specification shall be
procured, manufactured, erected, commissioned and tested at all the stages, as per
a comprehensive Quality Assurance Programme. An indicative programme of
inspection/tests to be carried out by the contractor for some of the major items is
given in the respective technical specification. This is, however, not intended to form
a comprehensive programme as it is the contractor’s responsibility to draw up and
implement such programme duly approved by the Employer. The detailed Quality
Plans for manufacturing and field activities shall be drawn up by the Bidder and will
be submitted to Employer for approval. Schedule of finalisation of such quality plans
will be finalised before award on enclosed format No. QS-01-QAI-P-1/F3-R0.
Monthly progress reports shall be furnished.
22.02.00 Manufacturing Quality Plan will detail out for all the components and
equipment,various tests/inspection, to be carried out as per the requirements of this
specification and standards mentioned therein and quality practices and procedures
followed by Contractor’s/ Sub-contractor’s/ sub-supplier's Quality Control
Organisation, the relevant reference documents and standards, acceptance
norms,inspection documents raised etc., during all stages of materials
procurement,manufacture, assembly and final testing/performance testing. The
Quality Plan shall be submitted on electronic media through C-folders, a web based
system of DVC ERP, for review and approval.
22.03.00 Field Quality Plans will detail out for all the equipm ent, the quality practices and
procedures etc. to be followed by the Contractor’s "Site Quality Control
Organisation", during various stages of site activities starting from receipt of
materials/equipment at site.
22.04.00 The Bidder shall also furnish copies of the reference documents/plant
standards/acceptance norms/tests and inspection procedure etc., as referred in
Quality Plans along with Quality Plans. These Quality Plans and reference
documents/standards etc. will be subject to Employer’s approval without which
manufacturer shall not proceed. These approved documents shall form a part of the
contract. In these approved Quality Plans, Employer shall identify customer hold
points (CHP), i.e. test/checks which shall be carried out in presence of the
Employer’s Project Manager or his authorised representative and beyond which the
work will not proceed without consent of Employer in writing. All deviations to this
specification, approved quality plans and applicable standards must be documented
and referred to Employer along with technical justification for approval and
dispositioning.
22.05.00 The contractor shall submit to the Employer Field Welding Schedule for field welding
activities in the format enclosed at Annexure-V. The field welding schedule shall be
submitted to the Employer along with all supporting documents, like welding
procedures, heat treatment procedures, NDT procedures etc. at least ninety days
before schedule start of erection work at site.
22.06.00 The contractor shall have suitable Field Quality Organization with adequate
manpower at Employer's site, to effectively implement the Field Quality Plan (FQP)
and Field Quality Management System for site activities. The contractor shall submit
the details of proposed FQA setup (organizational structure and manpower) for
employer's approval. The FQA setup shall be in place at least one month before the
start of site activities.
22.07.00 No material shall be despatched from the manufacturer's works before the same is
accepted by Employer's Project Manager/Authorised representative and duly
authorised for despatch by issuance of Material Dispatch Clearance Certificate
(MDCC / CHP Clearance).
22.08.00 All material used for equipment manufacture including casting and forging etc. shall
be of tested quality as per relevant codes/standards. Details of results of the tests
22.10.00 All brazers, welders and welding operators employed on any part of the contract
either in Contractor’s/his sub-contractor’s works or at site or elsewhere shall be
qualified as per ASME Section-IX or BS-4871 or other equivalent International
Standards acceptable to the Employer. All welding / brazing procedures qualified /
used at shop, will be made available to DVC during audit / inspection. Procedures to
be qualified at site will be submitted to DVC for approval.
22.11.00 Not Used.
22.12.00 For all IBR pressure parts and high pressure piping welding, the latest applicable
requirements of the IBR (Indian Boiler Regulations) shall also be essentially
complied with. However, other piping shall be as per relevant code. Similarly, any
other statutory requirements for the equipment/systems shall also be complied with.
On all back-gauged welds MPI/LPI shall be carried before seal welding
22.13.00 All the heat treatment results shall be recorded on time temperature charts and
verified with recommended regimes.
22.14.00 No welding shall be carried out on cast iron components for repair.
22.15.00 Unless otherwise proven and specifically agreed with the Employer, welding of
dissimilar materials and high alloy materials shall be carried out at shop only.
In general all plates of thickness greater than 40mm & for pressure parts plates of
thickness equal to or greater than 25mm shall be ultrasonically tested otherwise as
specified in respective equipment specification. All bar stock/Forging of diameter
equal to or greater than 40 mm shall be Ultrasonically tested.
22.17.00 The Contractor shall list out all major items/ equipment/ components to be
manufactured in house as well as procured from sub-contractors (BOI).
All the sub-vendors proposed by the Main contractor for procurement of major
bought out items including castings, forgings, semi-finished and finished
components/equipment etc., list of which shall be drawn up by the Contractor and
finalised with the Employer, shall be subject to Employer's approval on enclosed
format as Annexure-III.
List of DVC approved sub vendors against similar Pkg/items is attached as Section-
VI, Part-B ,Chapter E-60 Indicative sub-vendor list.
The contractor’s proposal for any new sub vendor for any of the items identified in
indicative sub-vendor list shall necessarily be furnished in the sub vendor
questionnaire & main Contractor Evaluation report format attached as Annexure- VII
with all relevant documents and main contractor's own assessment report
assessed as per their quality management system for DVC review and acceptance .
New sub vendor proposal will only be considered for DVC review, provided the
proposal is received sufficiently in time: 90 days prior to ordering date of a Bought-
Out Items/Start of Manufacturing so as not to impede the progress of the contract.
22.19.00 Employer reserves the right to carry out quality audit and quality surveillance of the
systems and procedures of the Contractor’s or their sub-contractor’s quality
management and control activities. The contractor shall provide all necessary
assistance to enable the Employer carry out such audit and surveillance.
22.20.00 The contractor shall carry out an inspection and testing programme during
manufacture in his work and that of his subcontractor’s and at site to ensure the
mechanical accuracy of components, compliance with drawings, conformance to
22.21.00 Quality audit/surveillance/approval of the results of the tests and inspection will not,
however, prejudice the right of the Employer to reject the equipment if it does not
comply with the specification when erected or does not give complete satisfaction in
service and the above shall in no way limit the liabilities and responsibilities of the
Contractor in ensuring complete conformance of the materials/equipment supplied to
relevant specification, standard, data sheets, drawings, etc.
22.22.00 For all spares and replacement items, the quality requirements as agreed for the
main equipment supply shall be applicable.
22.25.00 The Contractor / Sub-contractor shall carry out routine test on 100% item at
contractor / sub-contractor's works. The quantum of check / test for routine &
acceptance test by employer shall be generally as per criteria / sampling plan
defined in referred standards. Wherever standards have not been mentioned
quantum of check / test for routine / acceptance test shall be as agreed during
detailed engineering stage.
Certification from OEM’s authorized signatory that software offered with DDCMIS,
PLC, CCTV, PA, CEMS, EQMS, BHMS etc. declaring that the all the offered
software(s) had gone through the established software quality test and offered
software is not of β-version and offered software is also free from all known bugs as
on date of approval of systems documents by DVC as a part of quality
documentation review and approval process during detail engineering.
identification number of equipment and including an index of its contents with page
control on each document.
(b.) Material mill test reports on components as specified by the specification and
approved Quality Plans.
(g.) CHP / Inspection reports duly signed by the Inspector of the Employer and
Contractor for the agreed Customer Hold Points.
(i.) MDCC
23.03.00 Similarly, the contractor shall be required to submit soft copies containing QA
Documentation pertaining to field activities as per Approved Field Quality Plans and
other agreed manuals/ procedures, prior to commissioning of individual system.
23.04.00 Before despatch / commissioning of any equipment, the Supplier shall make sure
that the corresponding quality document or in the case of protracted phased
deliveries, the applicable section of the quality document file is completed. The
supplier will then notify the Inspector regarding the readiness of the quality
document (or applicable section) for review.
(a.) If the result of the review carried out by the Inspector is satisfactory, the
Inspector shall stamp the quality document (or applicable section) for
release.
(c.) If a decision is made for despatch, whereas all outstanding actions cannot be
readily cleared for the release of the quality document by that time, the
supplier shall immediately, upon shipment of the equipment, send a copy of
the quality document Review Status signed by the Supplier Representative to
the Inspector and notify of the committed date for the completion of all
outstanding actions & submission. The Inspector shall stamp the quality
document for applicable section when it is effectively completed. The
submission of QA documentation package shall not be later than two (2)
weeks after the despatch of equipment.
For the particular case of phased deliveries, the complete quality document to the
Employer shall be issued not later than two (2) weeks after the date of the last
delivery of equipment.
24.01.00 To eliminate delays and avoid disputes and litigation, it is agreed between the
parties to the Contract that all matters and questions shall be referred to the Project
Manager and without prejudice to the provisions of ‘Arbitration’ clause in Section
GCC, the Contractor shall proceed to comply with the Project Manager's decision.
24.02.00 The work shall be performed under the supervision of the Project Manager.
The scope of the duties of the Project Manager pursuant to the Contract, will include
but not be limited to the following:
(a.) Interpretation of all the terms and conditions of these documents and
specifications
(b.) Review and interpretation of all the Contractor’s drawing, engineering data,
etc.
(c.) Witness or his authorised representative to witness tests and trials either at
the manufacturer’s works or at site, or at any place where work is performed
under the contract
(d.) Inspect, accept or reject any equipment, material and work under the
contract
25.01.00 The word ‘Inspector’ shall mean the Project Manager and/or his authorised
representative and/or an outside inspection agency acting on behalf of the Employer
to inspect and examine the materials and workmanship of the works during its
manufacture or erection.
25.02.00 The Project Manager or his duly authorised representative and/or an outside
inspection agency acting on behalf of the Employer shall have access at all
reasonable times to inspect and examine the materials and workmanship of the
works during its manufacture or erection and if part of the works is being
manufactured or assembled on other premises or works, the Contractor shall obtain
for the Project Manager and for his duly authorised representative permission to
inspect as if the works were manufactured or assembled on the Contractor’s own
premises or works.
25.03.00 The Contractor shall give the Project Manager/Inspector fifteen (15) days written
notice of any material being ready for testing. Such tests shall be to the Contractor’s
account except for the expenses of the Inspector’s. The Project Manager/Inspector,
unless the witnessing of the tests is virtually waived and confirmed in writing, will
attend such tests within fifteen (15) days of the date on which the equipment is
noticed as being ready for test/inspection failing which the contractor may proceed
with test which shall be deemed to have been made in the inspector’s presence and
he shall forthwith forward to the inspector duly certified copies of test reports in two
(2) copies.
25.04.00 The Project Manager or Inspector shall within fifteen (15) days from the date of
inspection as defined herein give notice in writing to the Contractor, or any objection
to any drawings and all or any equipment and workmanship which is in his opinion
not in accordance with the contract. The Contractor shall give due consideration to
such objections and shall either make modifications that may be necessary to meet
the said objections or shall inform in writing to the Project Manager/Inspector giving
reasons therein, that no modifications are necessary to comply with the contract.
25.05.00 When the factory tests have been completed at the Contractor’s or subcontractor’s
works, the Project Manager /Inspector shall issue a certificate to this effect fifteen
(15) days after completion of tests but if the tests are not witnessed by the Project
Manager /Inspectors, the certificate shall be issued within fifteen (15) days of the
receipt of the Contractor’s test certificate by the Project Manager /Inspector. Failure
on the part of Project Manager /Inspector to issue such a certificate shall not prevent
the Contractor from proceeding with the works. The completion of these tests or the
issue of the certificates shall not bind the Employer to accept the equipment should
it, on further tests after erection be found not to comply with the contract.
25.06.00 In all cases where the contract provides for tests whether at the premises or works
of the Contractor or any sub-contractor, the Contractor, except where otherwise
specified shall provide free of charge such items as labour, material, electricity, fuel,
water, stores, apparatus and instruments as may be reasonably demanded by the
Project Manager /Inspector or his authorised representatives to carry out effectively
such tests on the equipment in accordance with the Contractor and shall give
facilities to the Project Manager/Inspector or to his authorised representative to
accomplish testing.
25.07.00 The inspection by Project Manager / Inspector and issue of Inspection Certificate
thereon shall in no way limit the liabilities and responsibilities of the Contractor in
respect of the agreed Quality Assurance Programme forming a part of the contract.
25.09.00 All inspection, measuring and test equipment used by contractor shall be calibrated
periodically depending on its use and criticality of the test/measurement to be done.
The Contractor shall maintain all the relevant records of periodic calibration and
instrument identification, and shall produce the same for inspection by DVC.
Wherever asked specifically, the contractor shall re-calibrate the measuring/test
equipment in the presence of Project Manager / Inspector.
25.10.01 List of items requiring quality plan and sub supplier approval. Format No.: QS-01-
QAI-P-01/F3-R0 (Annexure-III).
25.10.02 Status of items requiring Quality Plan and sub supplier approval. Format enclosed
at Annexure-IV.
The major design features of the system shall be demonstrated by the Contractor at
the Contractor’s works or any other place mutually agreed within Six months from
the date of LOA. These are the system function tests, which have a major impact on
the detailed system design & finalization of important engineering documents like
configuration, functional grouping, BOM etc., but do not require a fully engineered
system for conductance. Bidder shall identify these features & include detailed test
procedures in the bid, which shall be finalized during discussions with the bidder
before award. The developments and any augmentation of standard features
undertaken by the Bidder to fulfill the various specification requirements, shall be
also be tested during these major design tests. This shall include but not be limited
to the following.
a) System accuracy tests of DDCMIS for the various type of inputs identified in
Part-B.
d) Server changeover.
The results of the above tests, after its acceptance by the Employer, shall be
properly documented and submitted to Employer.
If any of the envisaged tests have been carried out by Bidder in a previous
DVC project, then the same need not be specifically conducted by the Bidder
for this project, provided it is clearly established by the Bidder & accepted by
the Employer that there is no difference between the system offered for this
project & the previous DVC project with respect to the test. However, even in
such a case, test report of the previous project shall be submitted by the
Bidder as a part of MDFT (Major Design Feature Test) test report.
25.12.01 Contractor shall prepare and submit typical implemented scheme in their system
(Control system & HMI) on sample basis. The typical cases to be covered shall
include but not be limited to the following.
(i) Logics/Loops:
a) Drive logics implementation for each type of binary drive along with its
display in HMI.
a) LVS Annunciation.
b) Graphics.
c) HSR
d) Logs/Reports.
25.12.02 The above typical cases shall be finalized with the Employer through Technical Co-
ordination meetings.
After review and finalization of the typical cases, the implementation of each logic &
control loop shall be carried out by the Contractor. After implementation of these
logics & loops, the Contractor shall test each logic /loop and record the observations
and demonstrate to Employer at Employer premises during engineering finalization.
Any modifications as a result of the demonstration shall be done and documented as
part of the test report along with the final scheme. Similarly, HMI functions shall also
be demonstrated by the Contractor at Employer premises & the results shall be
documented as part of test report.
25.12.03 During the integrated testing at the Contractor’s works, only sample checks shall be
done by the Employer for the items covered in above application engineering
demonstration.
26.01.00 (a) As soon as the facilities or part thereof has been completed operationally and
structurally and before start-up, each item of the equipment and systems
forming part of facilities shall be thoroughly cleaned and then inspected
jointly by the Employer and the Contractor for correctness of and
completeness of facility or part thereof and acceptability for initial pre-
commissioning tests, commissioning and start-up at Site. The list of pre-
commissioning tests to be performed shall be as mutually agreed and
included in the Contractor’s quality assurance programme as well as those
included in Part-D, Section-VI and elsewhere in the Technical Specifications.
(c) All piping system shall be flushed, steam blown, air blown as required and
cleanliness demonstrated using acceptable industry standards. Procedures
to accomplish this work shall be submitted for approval to the Employer six
months prior to the respective implementations. The Employer will approve
final verification of cleanliness.
(d) The time consumed in the inspection and checking of the units shall be
considered as a part of the erection and installation period.
(e) The check outs during the pre-commissioning period should be programmed
to follow the construction completion schedule. Each equipment/system, as
it is completed in construction and turned over to Employer's commissioning
(start-up) Engineer(s), should be checked out and cleaned. The checking
and inspection of individual systems should then follow a prescribed
schedule to be agreed by Employer.
(f) The Contractor during initial operation and performance testing shall conduct
vibration testing to determine the ‘base line’ of performance of all plant
26.01.00 Contractor shall furnish the commissioning organization chart for review &
acceptance of employer at least eighteen months prior to the schedule date of
synchronization of 1st unit. The chart should contain:
(1.) Biodata including experience of the Commissioning Engineers.
(2.) Role and responsibilities of the Commissioning Organisation members.
(3.) Expected duration of posting of the above Commissioning Engineers at site.
26.02.00 Initial Operation
(b) The 'Initial Operation' of the complete facility as an integral unit shall be
conducted for 720 continuous hours. During the period of initial operation of
720 hours, the unit shall operate continuously at full rated load for a period
not less than 72 hours with demonstration of the capability of the machine to
raise load upto 105% of full rated load.
The Initial Operation shall be considered successful, provided that each item/
part of the facility can operate continuously at the specified operating
characteristics, for the period of Initial Operation with all operating
parameters within the specified limits and at or near the predicted
performance of the equipment/ facility.
(c) Any loss of generation due to constraints attributable to the Employer shall
be construed as Deemed Generation.
equipment, shall not be considered as reasons for with- holding the aforesaid
permission.
b) These tests shall be binding on both the parties of the Contract to determine
compliance of the equipment with the functional guarantee.
d) Any special equipment, tools and tackles required for the successful
completion of the Guarantee Tests shall be provided by the Contractor, free
of cost.
Upon successful completion of Initial Operations and all the tests conducted to the
Employer's satisfaction, the Employer shall issue to the Contractor a Taking over
Certificate as a proof of the final acceptance of the equipment. Such certificate shall
not unreasonably be withheld nor will the Employer delay the issuance thereof, on
account of minor omissions or defects which do not affect the commercial operation
and/or cause any serious risk to the equipment. Such certificate shall not relieve the
Contractor of any of his obligations which otherwise survive, by the terms and
conditions of the Contract after issuance of such certificate.
28.01.00 The scope of service under training of Employer’s engineers shall include a training
module covering the areas of Operation & Maintenance.
Such training should cover the following areas as a minimum in order to enable
these personnel to individually take the responsibility of operating and maintaining
the power station in a manner acceptable to the Employer:
(a) Training for Steam Generator & ESP Equipment and related equipment.
(b) Training for Electric Systems including VFD and Electric power supply
system.
(e) Training for various C&I systems/equipment supplied includes the following:
(g) Training for UPS systems Annunciation system, SWAS, PA system, flue gas
analyzers, CCTV and 24 VDC system.
(h) Training on following aspects of fieldbus (i) Hardware & Software features (ii)
System design, diagnostic and testing (iii) maintenance, troubleshooting and
fault analysis.
(k) Training for numerical relays & networking systems supplied under MV & LT
switchgear system.
(d.) Any other specialized training as required for system operation and
maintenance.
(m) Training for Ash Handling System & Coal Handling Plant Equipment and
Auxiliaries
Product design
- Basic design features
- Theory & principle of operation
- Latest technological trends in Coal handling
plant and design
Plant Visit
- Operational feedback
-Testing facilities
Operation & Maintenance of Plant
Plant Visit
-Operational feedback
-O&M history/problems related to RO
membranes
Visit to Manufacturer’s Work
Plant Visit
- Operational feedback
- O&M history/ problems related to VFD
- Familiarization with various equipment
functioning at reference plant
-Testing facilities
Plant Visit
- Operational feedback
- O&M history / problems
-Testing facilities
Operation & Maintenance (At site)
- O&M practices
Familiarization of special maintenance
techniques
- Special tool and tackles familiarization
Plant Visit
- Operational feedback
- O&M history / problems
(p) Training on Erection methodologies for all the Sub-packages, System and
Equipments associated with the EPC Package, including a visit to power plant
construction site.
The exact details, extent and schedule for training shall be as finalized during
detailed engineering and shall be subject to Employer's approval.
28.03.00 The scope of services under training shall also necessarily include training of
Employer’s Engineering personnel covering entire scope for the package. This shall
cover all disciplines viz, Mechanical, Electrical, C&I , QA etc. and shall include all the
related areas like Design familiarization, training on product design features and
product design software of major equipment and systems, engineering,
manufacturing, erection, commissioning, training on operating features of
equipment, quality assurance and testing, plant visits and visits to manufacturer’s
28.04.00 Contractor shall also arrange for training of Employer's personnel in respect of fire
detection and protection systems and other Balance of Plant equipments.
28.05.00 Contractor shall provide training on application of PAUT (Phased array ultrasonic
testing) and TOFD (Time of flight diffraction) techniques for two weeks (at least 80
Hours). The training shall be arranged at least six months prior to the start of
erection works of SG works.
28.06.00 Exact details, extent of training and the training schedule shall be finalized based on
the Bidder’s proposal within two (2) months from placement of award.
28.07.00 In all the above cases, the lodging and boarding of the Employer’s personnel shall
be at the cost of Bidder. The Bidder shall make all necessary arrangements towards
the same.
28.08.00 Take off prices (product wise) should be indicated by the Bidder in the Bid Proposal
Sheets. Employer reserves the right to include or exclude these item(s) during
placement of Award.
Note:
1. For training purposes, one (1) man month implies 30 working days (excluding all
intervening holidays) per person.
2. The total man months in each area shall be divided into suitable number of modules
which shall be discussed and finalized during post award stage.
3. Duration of each module shall not be less than 10 (ten) working days out of which 20
% shall be for plant/manufacturers’ works visits and 80% shall be classroom training.
Station C&I
(Control and 3.5 5.5 10
Instrumentation)
Ash Handling
Plant 2.0 3.0 5.0
Coal Handling
1.0 1.5 2.5
Plant
UF Membranes,
RO Membranes,
ZLD, Chlorine Di
Oxide (ClO2) 0.2 0.3 0.5
generation &
dosing system,
CW Treatment
System
Electrical systems
consisting of
generators,
Excitation
systems, VFD, 3.5 3.0 7
Motors, MV/LV
switchgears,
relays, SAS and
Switchyard
45.5
Total 14.7 21.3
ii) Ladders in accordance with Employer’s safety rules for construction and
erection shall be used. Rungs shall not be welded on columns. All the stairs
shall be provided with handrails immediately after its erection.
The equivalent 'A' weighted sound pressure level measured at a height of 1.5 m
above floor level in elevation and at a distance of one (1) meter horizontally from the
nearest surface of any equipment/machine, furnished and installed under these
specifications, expressed in decibels to a reference of 0.0002 microbar, shall not
exceed 85 dBA except for
i) Safety valves and associated vent pipes for which it shall not exceed 105
dBA-115 dBA.
ii) Regulating drain valves in which case it shall be limited to 90 dBA-115 dBA.
v) For intermittently operating control valves, the noise level shall be within the
limit of 90 dBA.
All the equipments shall be suitably protected, coated, covered or boxed and crated
to prevent damage or deterioration during transit, handling and storage at Site till the
time of erection. While packing all the materials, the limitation from the point of view
of the sizes of railway wagons available in India should be taken account of. The
Contractor shall be responsible for any loss or damage during transportation,
handling and storage at site due to improper packing and presevation. The
Contractor shall ascertain the availability of Railway wagon sizes from the Indian
Railways or any other agency concerned in India well before effecting despatch of
equipment. Before despatch it shall be ensured that complete processing and
manufacturing of the components is carried out at shop, only restricted by transport
limitation, in order to ensure that site works like grinding, welding, cutting &
preassembly to bare minimum. The Employer's Inspector shall have right to insist for
completion of works in shops before despatch of materials for transportation.
In addition to above, the contractor shall take all necessary measures for storage of
all electronic equipment / systems at site in a dust free Air conditioned space
ensuring proper temperature & humidity.
In addition to above, the contractor shall take all necessary measures for storage of all electronic
equipment / systems at site in a dust free environment ensuring proper temperature
& humidity inside the space. In case equipment/system are specifically
recommended for storage in airconditioned space by OEM, the same shall also be
provided by the contractor. 32.00.00 ELECTRICAL EQUIPMENTS/ENCLOSURES
32.01.00 All electrical equipments and devices, including insulation, heating and ventilation
devices shall be designed for ambient temperature and a maximum relative humidity
as specified elsewhere in the specifications.
33.01.00 All instrument scales and charts shall be calibrated and printed in metric units and
shall have linear graduation. The ranges shall be selected to have the normal
reading at 75% of full scale.
All scales and charts shall be calibrated and printed in Metric Units as follows:
33.02.00 All instruments and control devices provided on panels shall be of miniaturized
design, suitable for modular flush mounting on panels with front draw out facility and
flexible plan-in connection at rear.
effectively eliminating the noise problems shall be included in the proposal. The
equipment shall be protected against ESD as per IEC-61000-2. Radio Frequency
interference (RFI) and Electro Magnetic Interference (EMI) protection against
hardware damage and control system mal-operations/errors shall be provided for all
systems as per EN-50082-2 (1995).
All solid state systems /equipment shall be able to withstand the electrical noise and
surge as encountered in actual service conditions and inherent in a power plant and
shall meet the requirements of surge protection as defined in ANSI C37.90.1-1989
on its suitable equivalent class of IEC 254-4. Details of the features incorporated and
relevant tests carried out. The test certificates. etc. shall be submitted by the Bidder.
The instrument air supply system as supplied by the Bidder for various pneumatic
control & instrumentation devices like pneumatic actuators, power cylinders, E/P
converters, piping / tubing etc.
Each pneumatic instrument shall have an individual air shut - off valve. The pressure
regulating valve shall be equipped with an internal filter, a 50 mm pressure gauge
and a built-in filter housing blow down valve.
For direct temperature measurement of all working media, one stub with internal
threading of approved pattern shall be provided along with suitable plug and washer.
The Contractor will be intimated about thread standard to be adopted.
The following shall be provided on equipment by the Bidder. The standard which is
to be adopted, will be intimated to the Contractor.
The Bidder shall provide drawings, system overview & description, hardware/
software details, technical literature, functional & hardware schemes, bill of material,
parts list, interconnection diagrams, data sheets, erection/ installation/
commissioning procedures, instruction/ operating manuals, etc. for each of the C& I
The exact format, submission schedule and contents of various documents shall be
as finalised during detailed engineering stage.
38.01.00 Bill of material (instrument list) for all C&I equipment/ devices shall be furnished by
the bidder in standard formats as approved by the Employer.
The Contractor shall have to furnish two (2) sets of all maintenance manual of each
and every electronic card/module as employed on the various systems and
equipment including peripherals etc., offered by him. The Contractor will also have to
furnish the data regarding the expected failure rate of various modules and other
system components. Further, the contractor shall furnish a set of operating manuals
which should include block diagrams, make, model/type, details wiring and external
connection drawings etc. as required to do the testing and maintenance of the
electronic modules.
Backup & Restoration Procedures of DDCMIS, Station LAN & Advance Process
Control shall be provided.
c) The bidder/its sub vendor/supplier shall ensure supply of spares, materials and
technological support for the entire life of the project.
d) The bidder shall list out the products and components producing Toxic E-waste and
other waste as specified. It shall have an Extended Producers Responsibility (EPR)
so that after the completion of the lifecycle, the materials are safely recycled/
disposed of by the contractor and for this, the bidder has to establish
recycling/disposal unit as specified.
e) The equipment/ material sourced from foreign companies will be tested in accredited
labs in India before acceptance wherever such facilities are available. The testing
shall be carried out in accordance with MOP extant order/guidelines.
f) The bidder shall have to furnish a certificate regarding cyber security/safety of the
equipment/process to be supplied/services to be rendered as safe to connect.
g) All applicable safety requirements shall be met. Regular safety audit shall be carried
out by the manufacturer/ supplier.
h) Wherever required, the foreign supplier shall establish fully functional service centers
in India and shall keep spares/material locally for future needs of Employer.
Any violation w.r.t Make in India and minimum local content (MLC) requirements as
specified shall be sole responsibility of the Bidder.
Appendix-I
Appendix-II
ARI-410 Standard for forced circulation air cooling and air heating coils
BS:400 Low carbon steel cylinders for the storage & transport of
permanent gases.
BS:401 Low carbon steel cylinders for the storage & transport of
liquified gases.
CTI Code Acceptance test code for Water Cooling Tower.
ACT-105
IS: 10379 Code of practice for field control of moisture and compaction of
soils for embankment and sub-grade.
IS: 383 Specification for coarse and fine aggregates from natural sources
for concrete.
IS: 432 Specification for mild steel and (Parts 1&2) medium tensile steel
bars and hard-drawn steel wires for concrete reinforcement.
IS: 1363 Hexagon head Bolts, Screws and nuts of production grade C.
IS: 1364 Hexagon head Bolts, Screws and Nuts of Production grade A & B.
IS: 1566 Specification for hard-drawn steel wire fabric for concrete
reinforcement.
IS: 1786 Specification for high strength deformed bars for concrete
reinforcement.
IS: 3812 Specification for fly ash, for use as pozzolana and admixture.
IS: 280 Specification for mild steel wire for general engineering purposes.
IS: 457 Code of practice for general construction of plain & reinforced
concrete for dams & other massive structures.
IS: 2204 Code of practice for construction of reinforced concrete shell roof.
IS: 2210 Criteria for the design of reinforced concrete shell structures and
folded plates.
IS: 2502 Code of practice for bending and fixing of bars for concrete
reinforcement.
IS: 2506 General requirements for concrete vibrators, screed board type.
IS: 2722 Specification for portable swing weigh batches for concrete.
(single and double bucket type)
IS: 2751 Code of practice for welding of mild steel plain and deformed bars
for reinforced concrete construction.
IS: 3370 Code of practice for concrete structures for the storage of
(Part I to IV) liquids.
IS: 3414 Code of practice for design and installation of joints in buildings.
IS: 3550 Methods of test for routine control for water used in industry.
IS: 3558 Code of practice for use of immersion vibrators for consolidating
concrete.
IS: 4326 Code of practice for earthquake resistant design and construction
of buildings.
IS: 4461 Code of practice for joints in surface hydro-electric power stations.
IS: 4995 Criteria for design of reinforced concrete bins for the storage
(Parts I & II) of granular and powdery materials.
IS: 5256 Code or practice for sealing joints in concrete lining on canals.
IS: 7861 Code of practice for extreme weather concreting. (Parts I & II)
IS: 9417 Recommendations for welding cold worked steel bars for
reinforced concrete construction.
IS: 11384 Code of practice for composite construction in structural steel and
concrete.
IS: 11504 Criteria for structural design of reinforced concrete natural draught
cooling towers.
IS: 10297 Code of practice for design and construction of floors and roofs
using precast reinforced/prestressed concrete ribbed or cored
slab units.
IS: 10505 Code of practice for construction of floors and roofs using pre-cast
reinforced concrete units.
IS: 2250 Code of Practice for Preparation and use of Masonry Mortar.
Sheeting Works
IS: 730 Specification for fixing accessories for corrugated sheet roofing.
IS: 1626 Specification for Asbestos cement building pipes and pipe fittings,
gutters and gutter fittings and roofing fittings.
IS: 2527 Code of practice for fixing rain water gutters and down pipe for
roof drainage.
IS: 12093 Code of practice for laying and fixing of sloped roof covering using
plain and corrugated galvanised steel sheets.
IS: 814 Specification for covered Electrodes for Metal Arc Welding for
weld steel.
IS: 1852 Specification for Rolling and Cutting Tolerances for Hot rolled
steel products.
IS: 6911 Specification for stainless steel plate, sheet and strip.
IS: 800 Code of practice for use of structural steel in general building
construction.
IS: 816 Code of practice for use of Metal Arc Welding for General
Construction.
IS: 4000 Code of practice for assembly of structural joints using high
tensile friction grip fasteners.
IS: 9595 Code of procedure of Manual Metal Arc Welding of Mild Steel.
IS: 817 Code of practice for Training and Testing of Metal Arc Welders.
IS: 1811 Qualifying tests for Metal Arc Welders (engaged in welding
structures other than pipes).
IS: 9178 Criteria for Design of steel bins for storage of Bulk Materials.
IS: 4353 Recommendations for submerged arc welding of mild steel and
low alloy steels.
IS: 1608 Method of Tensile Testing of Steel products other than sheets,
strip, wire and tube.
IS: 1599 Method of Bend Tests for Steel products other than sheet, strip,
wire and tube
IS : 228 Methods of chemical Analysis of pig iron, cast iron and plain
carbon and low alloy steel.
IS : 3664 Code of practice for Ultra sonic Testing by pulse echo method.
IS : 3613 Acceptance tests for wire flux combination for submerged Arc
Welding.
IS : 1635 Code of practice for field slaking of Building lime and preparation
of putty.
IS : 2333 Plaster-of-paris.
IS : 158 Ready mixed paint, brushing, bituminous, black, lead free, acid,
alkali & heat resisting.
IS : 554 Dimensions for pipe threads, where pressure tight joints are made
on thread.
IS : 775 Cast iron brackets and supports for wash basins and sinks.
IS : 778 Copper alloy gate, globe and check valves for water works
purposes.
IS : 781 Cast copper alloy screw down bib taps and stop valves for water
services.
IS : 1239 Mild steel tubes, tubulars and other wrought steel fittings.
IS : 1536 Centrifugally cast (Spun) iron pressure pipes for water, gas and
sewage.
IS : 1537 Vertically cast iron pressure pipes for water, gas and sewage.
IS : 1538 Cast iron fittings for pressure pipe for water, gas and sewage.
IS : 1703 Ball valves (horizontal plunger type) including float for water
supply purposes.
IS : 1729 Sand cast iron spigot and socket, soil, water and ventilating pipes,
fittings and accessories.
IS : 3311 Waste plug and its accessories for sinks and wash basins.
IS : 3589 Electrically welded steel pipes for water, gas and sewage
(200mm to 2000mm nominal diameter).
IS : 3989 Centrifugally cast (Spun) iron spigot and socket soil, waste and
ventilating pipes, fittings and accessories.
IS : 5329 Code of practice for sanitary pipe work above ground for
buildings.
IS : 5382 Rubber sealing rings for gas mains, water mains and sewers.
IS : 5822 Code of practice for laying of welded steel pipes for water
supply.
IS : 8931 Cast copper alloy fancy bib taps and stop valves for water
services.
IS : 8934 Cast copper alloy fancy pillar taps for water services.
IS : 281 Mild steel sliding door bolts for use with padlocks.
IS : 1081 Code of practice for fixing and glazing of metal (steel and
aluminium) doors, windows and ventilators.
IS : 2202 Specification for wooden flush door shutters (solid core type);
(Part-II) particle board face panels and hard board face panels
IS : 3614 Fire check doors; plate, metal covered and rolling type.
IS:7452 Hot rolled steel sections for doors, windows and ventilators.
IS:1322 Specification for bitumen felts for water proofing and damp
proofing.
IS:1346 Code of practice for water proofing of roofs with bitumen felts.
IS:3067 Code of practice for general design details and preparatory work
for damp proofing and water proofing of buildings.
IS:3384 Specification for bitumen primer for use in water proofing and
damp proofing.
IS:5318 Code of practice for laying of flexible PVC sheet and tile flooring.
IS:162 Specification for fire resisting silicate type, brushing, for use on
wood, colour as required.
IS:2338 Code of practice for finishing of wood and wood based materials.
Part-I Operations and workmanship
Part-II Schedules
Part-I Pretreatment.
Part-II Painting.
Miscellaneous
IS:10430 Creteria for design of lined canals and liner for selection of type of
lining.
Publication
The design, manufacture, inspection, testing & installation of all equipment and
system covered under this specification shall conform to the latest editions of codes
and standards mentioned below and all other applicable VDE, IEEE, ANSI, ASME,
NEC, NEMA, ISA AND Indian Standards and their equivalents.
Temperature Measurements
Pressure Measurements
Flow Measurements
Instruments and apparatus for flow measurements - ASME PTC 19.5 (1972) Interim
supplement, Part-II.
7. General requirement and tests for printed wiring boards - IS 7405 (Part-I)
1973.
13. Information Processing Systems - Local Area Networks - Part 2 : Logical Link
Control - IEEE-802.2 - 1989.
14. Standard for Local Area Networks : Carrier Sense Multiple Access with
Collision Detection - IEEE-802.3 - 1985.
16. Standard for Local Area Networks : Token - Passing Bus Access Method -
IEEE-802.4 - 1985.
17. Standard for Local Area Networks : Token - Ring Access Method and
Physical Layer Specification - IEEE-802.5 - 1985.
21. Interface Between the Data Terminal Equipment and Data Circuit -
Terminating Equipment Employing Serial Binary Data Interchange - EIA-232-
D-1987.
1. Contact rating - AC services NEMA ICS 2 - 1978 (with revision through May
1983), Part - 2-125, A6000.
Enclosures
1. Type of Enclosures - NEMA ICS Part - 6 - 1978 (with Rev. 1 4/80) through
110.22 (Type 4 to 13).
3. Protection class for Enclosures, cabinets, control panels & desks - IS:2147 -
1962.
Sampling System
1. Stainless steel material of tubing and valves for sampling system - ASTMA
296-82, Grade 7 P 316.
2. Submerged helical coil heat exchangers for sample coolers ASTM D11 92-
1977.
Annunciators
1. Specifications and guides for the use of general purpose annunciators - ISA
S 19.1, 1979.
Protections
1. Relays and relay system associated with electric power apparatus. ANSI C
37.90, 1 - 1989.
2. General requirements & tests for switching devices for control and auxiliary
circuits including contactor relays - IS:6875 (Part-I) - 1973.
UPS System
2. Relays and relays system associated with electrical power apparatus - ANSI
C 3.90 - 1983.
5. Stationary cells & Batteries Lead Acid type (with tubular positive plates)
specification IS-1651-1991.
6. Recommended practice for sizing large lead storage batteries for generating
stations & sub-stations - IEEE-485-1985.
8. General Requirements & tests for printed wiring boards, IS:7405 (Part-I)
1973.
Control Valves
3. Forged & Rolled Alloy steel pipe flanges, forged fittings and valves and parts
- ASTM - A - 182.
6. Pipe fittings of wrought carbon steel and alloy steel - ASTM - A - 234.
Instrument Tubing
Cables
4. Insulation & Sheathing compounds for cables : VDE 0207 (Part-4, 5 & 6).
6. Rules for Testing insulated cables and flexible cables : VVDE - 0472
8. Standard specification for tinned soft or annealed copper wire for electrical
purpose - ASTM B-33-81.
15. PVC insulated electric cables for working voltage upto and including 1100 V -
IS:1554 (Part-I).
3. Zinc coating "hot dip" on assembled products for galvanising of carbon steel
cable trays - ASTMA - 386-78.
5. Code of practice for installation for indoor amplifying and sound distribution
system - IS:1881.
6. Basic environmental testing procedures for electronic and electrical items -
IS:9000.
7. Characteristics and methods of measurements for sound system equipment -
IS:9302
8. Code of practice of electrical wiring installations (System voltage not
exceeding 650 volts) - IS:732
9. Rigid steel conduits for electric wiring - IS:9537 (Part-I and II)
10. Fittings for rigid steel conduits for electrical wiring - IS:2667
11. Degree of protection provided by enclosure for low voltage switchgear and
control gear - IS:2147.
Vibration Monitoring System
2. BS : 4675 Part-2
LEG ENDS
SYSTEM SUPPLIER/SUB-SUPPLIER APPROVAL STATUS CATEGO RY (SHALL BE FILLED BY DVC)
A – For these items proposed vendor is acce ptable to DVC. To be indicate d with letter “A” in the list alongwith the condition of approval, if any.
DR – For these items “Detaile d re quire d” for DVC re view. To be identified with letter “DR” in the list.
NOTED – For these items vendors are approved by Main Supplier and accepted by DVC without specific vendor approval from DVC. To be identified with “NO TED.’
QP/INSPN CATEGORY:
CAT -I : For these items the Quality Plans are approve d by DVC and the final acce ptance will be on physical inspe ction witness by DVC.
CAT -II : For these items the Quality Plans approve d by DVC. Howe ver no physical inspection shall be done by DVC. The final acceptance by DVC shall be on the basis re view of documents as per approve d QP.
CAT -III : For these items Main Supplie r approves the Quality Plans. The final acce ptance by DVC shall be on the basis ce rtificate of conformance by the main supplier.
UNIT S/WORKS : Place of manufacturing Place of Main Supplie r of multi units/works.
RAGHUNATHPUR THERMAL POWER STATION TECHNICAL SPECIFICATION GENERAL TECHNICAL REQUIREMENT PAGE 104 OF 108
PHASE-II (2X660 MW) SECTION – VI, PART-C
EPC PACKAGE ( EXCLUDING STG PKG.) BID DOC NO.:CS-9586-001A-2
ANNEXURE-IV
Project : S tage :: S TATUS OF ITEM REQUIRING QP& DOC. NO.:
Package : S UB-S UPPLIER APPROVAL REV. NO.:
Contractor : DATE :
Contractor No. : PAGE : OF
Item / Service QP/ QP S ub. Date of Date of S tatus Proposed S ub-suppliers Place of Approval Sub- Remarks
S. N. Insp. S chedule sub- commt Code manufacturing works S tatus supplier
Cat. Approval mission Appl. C/II/I detail
schedule submission
schedule
RAGHUNATHPUR THERMAL POWER STATION TECHNICAL SPECIFICATION GENERAL TECHNICAL REQUIREMENT PAGE 105 OF 108
PHASE-II (2X660 MW) SECTION – VI, PART-C
EPC PACKAGE ( EXCLUDING STG PKG.) BID DOC NO.:CS-9586-001A-2
ANNEXURE-V
Project : S tage : FIELD WELDING S CHEDULE DOC. NO.:
Contractor : (To be raised by the contractor) REV. NO.:
Contractor No. : Welding Code: ……………………………………… DATE :
S ystem : PAGE : OF
DRG No. for Weld Descriptio Matl. Dimensions Process of Type of Electrode WPS . Min. Heat treatment NDT REF Remarks
Sl. Location and n of parts S pec. welding Weld filler spec. No. pre- method/
Temp. Holding S pec. No. ACC Norm
No. Identification mark to welded heat Quantum
time Ref.
NOTES:
SIGNATURE
RAGHUNATHPUR THERMAL POWER STATION TECHNICAL SPECIFICATION GENERAL TECHNICAL REQUIREMENT PAGE 106 OF 108
PHASE-II (2X660 MW) SECTION – VI, PART-C
EPC PACKAGE ( EXCLUDING STG PKG.) BID DOC NO.:CS-9586-001A-2
CLAUSE NO. GENERAL TECHNICAL REQUIREMENTS (Annexure-VI)
Other
Drawings/Documents (A0 3 -
& A1 sizes)
P&ID (All sizes) 3 -
a) Final drawings/documents 3 2
(Directly to site)
b) “As Built” 3 2
Drawing/Documents
(Directly to site)
c) Analysis reports of
Equipments / piping / 2 2
structures components/system
employing software packages
as detailed in the
specifications.
2 Erection Manual (Directly to site) 3 sets 2
viii. PO placement date/ Start of manufacturing (if self-manufactured) as per L2 network पीओ
िनयोजन क ितिथ / एल- 2 नेटवक के अनुसार िविनमाण (य द व-िन मत है) क शु आत
ix. Item Description Total quantity of Quantity proposed to be Timeline for quantity requirements
(Type/Size/Rating/Scope of proposed item procured from as per project schedule & whether the
Sub-Contracting) envisaged in this proposed sub-vendor proposed Sub-vendor equipped with
मद का िववरण ( कार / आकार / package (Nos/ (Nos/ Running Meters adequate capacity to supply proposed
रे टंग / उप-अनुबंध का दायरा) Running Meters/ /Kgs /Tons etc) order quantity in time /
Kgs/ Tons etc) इस तािवत उप-िव े ता (सं या / प रयोजना समय सूची के अनुसार मा ा
पैकेज म प रकि पत याशील मीटर / कलो ाम / आव यकता के िलए समय-सीमा और या
तािवत मद क कु ल टन आ द) से खरीदी जाने वाली तािवत उप-िव े ता समय पर तािवत मांग
मा ा (सं या / याशील मा ा क मा ा क आपू त करने म पूरी तरह से स म
मीटर / कलो ाम / टन है
आ द)
x. Supply experience of the proposed sub-vendor (including supplies to Main Contractor, if any) for similar item/scope of
sub-contracting, for last 3 years (Note:- Only relevant experience details w.r.t. proposed item/scope of subcontracting to
be brought out here) िपछले 3 वष के िलए उप-अनुबंध के समान मद / दायरे के िलए तािवत सब-वडर (मु य संिवदाकार हेतु
िववरण का उ लेख हो
Project/Package Customer Name Supplied Item PO ref Supplied Date of Supply
प रयोजना/पैकेज ाहक का नाम (Type/Rating/Model no/date Quantity आपूि की ितिथ
/Capacity/Size etc) पीओ संदभ आपू त क
आपूि त मद ( कार/रे िटं ग सं. /ितिथ मा ा
/मॉडल
/ मता/आकार आिद)
We confirm that as per our assessment, the proposed sub-vendor has requisite capabilities & supply experience and is suitable
for supplying the proposed item/scope of sub-contracting/हम अपने आकलन के अनुसार इस बात क पुि करते ह क, तािवत उप-
िव े ता के पास अपेि त मता और आपू त करने का अनुभव है और उप-अनुबंध के दायरे / तािवत मद क आपू त के िलए उपयु है।
Name: Desig: Contact No: Sign: Date: