Synch Instructions

This document provides instructions for synchronizing and load sharing multiple generators using DSE 5510 modules. It describes how to set up the modules, connect them to each other and the generators, and adjust settings like voltage droop and current transformer ratios. The key steps are: connecting the modules to the generators; setting the engine droop, voltage droop and frequency; connecting the modules together with a screened cable and 120ohm resistor; and setting the current transformer ratios in the modules.

Uploaded by

Ahmed Abdullah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
126 views11 pages

Synch Instructions

This document provides instructions for synchronizing and load sharing multiple generators using DSE 5510 modules. It describes how to set up the modules, connect them to each other and the generators, and adjust settings like voltage droop and current transformer ratios. The key steps are: connecting the modules to the generators; setting the engine droop, voltage droop and frequency; connecting the modules together with a screened cable and 120ohm resistor; and setting the current transformer ratios in the modules.

Uploaded by

Ahmed Abdullah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 11

Guide to Synchronising and load sharing with DSE 5510

modules

Deep Sea Electronics module


5510
Guide to synchronising and load sharing.

Deep Sea Module 5510 and stand.

04/07/2006 1 Prepared by A. Wormald


Guide to Synchronising and load sharing with DSE 5510
modules

Introduction
The information in this document will help you to synchronise and load share Scania 200 Kva 320kva and 350kva
sets using the DSE 5510 module.
The Panels come with a case for safe keeping while they are not been used.
Make sure they are returned to the case after the end of each hire.

Case for panel storage Panel inside the case


Setup

1. One DSE 5510 Synchronising panel is required per generator.

2. Before starting the generators the oil and water levels have to be checked also check for any other faults.

3. Check that the AVR droop pot is turned fully anti clockwise and the trim Pot is fully clockwise. Check that the links
on the AVR are set to the correct Frequency and correct size generator.

For example: - 200Kva. 320Kva and 350Kva will be set on B and C for the size of generator. The frequency selection
will be either 3 and 2 for 50Hz operation or 3 and 1 for 60Hz operation.

Trim pot

Droop pot

Volts pot

Frequency
tapping
Select correct link for
Size of generator.

04/07/2006 2 Prepared by A. Wormald


Guide to Synchronising and load sharing with DSE 5510
modules

4. Start the generator and check that the VOLTAGE, PHASE ROTATION and FREQUENCY are correct and set to
Client’s requirement.

5. The engine governor droop requires setting this is described below:-

350Kva.
On the 350Kva sets this is done by switching the ignition key to the local position and pressing the Stop/Reset button
and Information button at the same time on the DSE5310 module. This will take you to the configuration menu were you
need to enter the password which is 2000. This is done by pressing the + and – buttons, when the digit you require
appears press the auto button to save. When you have done this you can scroll through the menu until you come to a
screen which says DROOP. In the bottom left hand corner it will say disable press Auto and then + to enable the droop
and auto to save the setting. Now press the stop button to exit. The generator can now be started. Once the set is
running you will notice that the generator frequency has risen to 52Hz this can be adjusted to 50Hz by turning the speed
pot inside the control panel. The droop is now set.
If the set is required to run at 60Hz then you need to go into the configuration menu and scroll through the menus until
you find alternate frequency enable this by pressing auto and then + then auto to save the setting. When the set is now
started the frequency will go to 63Hz this can now be adjusted back to 60Hz using the speed pot inside the control
panel.

200kva.
To adjust the droop on these sets you need to open the control panel door you will then see a small panel. (See picture
below) Start the generator and check that the frequency is set to 50Hz you then need to turn the switch marked ISOCH /
DROOP to the right the engine speed will then increase to 52Hz if it does not then the pot marked droop requires
adjusting to bring the engine speed up to 52Hz the engine speed can then be lowered to 50Hz using the pot marked
speed.
If the 200 or 320Kva require to be operated at 60Hz then the dip switch on the DEC 2 module requires changing.
Switch 6. ON position for 50HZ
OFF position for 60Hz.
The generator can then be started and frequency checked and adjusted if required. Turn the ISOCH /DROOP switch to
the right the engine speed will go up to 63Hz. The speed can then be lowered to 60Hz by using the speed pot. The
droop is now set.

320Kva.
The 320Kva is adjusted in the same way as the 200Kva except you do not need to adjust the droop/engine speed via
the droop pot once the ISOCH/DROOP switch is turned to the right the engine speed will go to 52Hz you can then
lower the speed via the speed pot. See above for 60Hz operation.

Voltage adjustment pot.


Speed control
pot
ISOCH / DROOP SWITCH. Turn to
right for droop

Droop control
pot

On the earlier Scania sets fitted with the P522 module a small toggle switch requires switching from 50Hz to 60Hz if
you are changing frequencies this is at the rear of the 522 module.

6. Now the AVR droop has to be set this is done by using Resistive / Reactive load bank.

Voltage droop is normally set at 3% 0.8 pf.


Apply full load at 0.8pf check the voltage and adjust to client’s requirement. Adjust the droop pot so that the volts drop
by 3% i.e. 400volts off load apply full load @ 0.8pf and adjust the droop pot so you get a voltage reading of 388volts
remove load and re-adjust voltage to client’s requirement.

04/07/2006 3 Prepared by A. Wormald


Guide to Synchronising and load sharing with DSE 5510
modules

7. The 5510 modules require connecting via the 16 pin and 24pin plugs a show below:-

16 and 24 pin plugs on panel. 16 and 24 pin sockets on new Scania.

16 and 24 pin sockets on earlier Scania. Location of 16 and 24 pin socket on newer sets

8. Before the generators can be started a screened cable requires connecting between the panels the sockets for this is
shown below:-

Socket where the 120ohm resistor is fitted. Plug holding the 120ohm Resistor.

The screened cable supplied with each panel can be connected through the gland fitting to cable numbers K61
and K63. Other types of screened cable can cause the modules to display an MSC DATA ERROR this means
they are not communicating with each other.
A 120 ohm resistor has to fitted to the first and last panel i.e. If 2 sets are been synchronised then the resistor will be in
both panels. If 3 sets are been synchronised then the resistor would be in the 1st and 3rd panel. 4 sets then it will be in
the 1st and 4th panel. If the resistor is not being used place inside the panel

The screen cable supplied with the panels requires connecting to


terminals K61 and K63. Do not connect the MSC cable screen to earth
at any point. Protection from interference is provided within the module
and may be compromised by earthing the MSC cable screen.
K61

K63

Situated on the bottom right


hand corner of panel

04/07/2006 4 Prepared by A. Wormald


Guide to Synchronising and load sharing with DSE 5510
modules

9. Once the panels/modules are connected to the generator the CT ratios can be set in the 5510 module this is for two
main reasons one the metering display and the other is reverse power.
On the 350Kva and 320Kva the CT ratio is 1000A / 1A
On the 200kva the CT ratio is 600A / 1A

Adjustment is done in 2 different ways depending on which software version is installed in the modules if you have
panels with a plant number between XAMN034 and XAMN039 then this has to be done using a laptop. If the plant
numbers are between XAMN040 and XAMN049 this can be done via the module.

Via the laptop Computer.


a. Make sure the DSE program is installed on the computer to be used.
b. Check that the module has power to it.
c. Connect the DSE interface cable between the laptop and 5510 module.
d. Click on the icon below and this will open the DSE program.

Click here to
start program

e. You will then see a screen like the one on the left below. Click on the 55xx icon this will take you to the screen
in the centre click OK and then onto the below right screen.

Click here

f. Once you have got to the screen on the above right you need to click on read from controller this will then upload all
the parameters from the module. Next click on Edit config this will then take you to the screen below were you have to
click on Generator and then Current Power.

1st click here

2nd click here

04/07/2006 5 Prepared by A. Wormald


Guide to Synchronising and load sharing with DSE 5510
modules

g. Now you should see the screen below, you can now change the CT ratios.
Firstly click on the circle next to the 1amp icon a black dot should appear in the centre of the circle. Then click on the
CT primary (L1 L2 L3) by clicking on the arrows you can either increase or decrease the CT primary setting. When
you have the required figures i.e.:-
350Kva and 320Kva the CT ratio is 1000A / 1A
200kva the CT ratio is 600A / 1A
h. Now you also need to change the EARTH FAULT setting which is 10% 36A for 350kva / 320kva and 10% 25A for
200kva. (Also see drawings on page 9 + 10.)
i. You need to save the changes you have made to the program back to the 5510 module to this go to Config
Manager and click the box that says write to controller all the settings that you have made will be written to the 5510
module.

1 amp icon
CT
Config Manager primary
(L1 L2 L3)

Click here to write changes to controller

j.To check these setting you can click read from controller. Once all the data has been uploaded click on Edit config
then Generator and secondly Current/Power see if the figures you entered are present.

Via the 5510 module.


Once you have the panel/ modules connected to the generator and have supply to them you can change the CT
ratios.
a. Start by pressing the stop/reset button and information button at the same time.
b. This will bring you to the password screen were you need to enter the password which is 2000 this is done by
pressing the + and - buttons till the digit you require appears then press auto to save the digit.
c. Now you should see the configuration screen, scroll through the different menus till you come to the one that
says PRIMARY CT now press auto the digits in the bottom left hand corner will start to flash you can now use
the + and – buttons to adjust the CT ratio 1000/1A for 320kva and 350kva and for the 200kva 600/1A. Once
you have the required numbers you can press auto to save them.
d. Now go to the next menu by pressing the + and – buttons the menu you require is Secondary CT this has
only 2 settings 5A or 1A press auto and then + or – to adjust then auto to save the required setting.
e. Now press the STOP/RESET BUTTON.
04/07/2006 6 Prepared by A. Wormald
Guide to Synchronising and load sharing with DSE 5510
modules

10. To check the reverse power you can change over the C/T wires C50 and C90. Apply load to the generator it
should trip @ 35kw which is the default setting of the DSE 5510 module or you can set the value your self via the
laptop. IT IS VERY IMPORTANT THAT THIS FUNCTION WORKS.

11. Once the governor droop, voltage droop, frequency and phase rotation have been adjusted. Then the sets can be
Synchronized and checked to see if they are sharing load correctly

12. They now be need to be switched from local to remote by turning the key on the front panel see below:-

Requires switching Requires putting


into remote into Auto

13. The 5310 module now requires putting into the Auto mode this is done by pressing the auto button the 5310 (see
picture of module on page 9) the 5310 module will then display WAITING IN AUTO.
If the P522 module is fitted then this requires putting into the auto position see above:-
Now the set can be started from the DSE 5510 module by pressing the manual button and then the generator start
button. Once the set is up to running speed and the display on the generator module shows GENERATOR AVAILABLE
you will be able to close the circuit breaker by pushing the MCB close button shown below the green LED will then be lit.

Up and down
scroll buttons
LCD
Display

Information page
button Close generator
MCB
Open Pushbutton
generator CB
push button

Generator
CB closed
Stop / Reset on load
button

Manual button Auto button Mute / lamp Start button


test button

04/07/2006 7 Prepared by A. Wormald


Guide to Synchronising and load sharing with DSE 5510
modules

14. To synchronise the other sets press the information (page) button and scroll through the different pages till you
come the Synchronising page

At the start of synchronising the display will only show the


difference between the Bus and Generator output i.e. frequency
and voltage. The display is showing a mismatch of 2.9Hz this is
shown by the arrow. The generator frequency is high and
Arrow indicating the should be lowered by adjusting the speed pot slightly. The
Hz is too high voltage is also high but within limits set for synchronizing shown
by the Tick.

Moving bar

When the difference between the Bus and Generator


output has been reduced the synchroscope display will
become active this can be seen by the moving bar. The
area in the centre of the synchroscope indicates were
synchronizing will occur.

Tick mark indicating that the


Voltage and Frequency are in
acceptable limits

Once the voltage and frequency are within acceptable limits


shown by the tick marks then Synchronising can take place.

Press the MCB close button to start Auto


Synchronising. The 5510 module will then adjust the
Voltage and Hz if required. When the breaker has closed
the LED will be lit indicating that the set is synchronized
to the Bus and the bar will be locked in the centre of the
Synchroscope.

The moving bar is now locked in the


centre of the synchroscope.

THE SETS ARE NOW SYNCHRONISED!!


04/07/2006 8 Prepared by A. Wormald
Guide to Synchronising and load sharing with DSE 5510
modules

DSE module 5310.

Scroll down

Start

Stop

Next page Auto Mute / Lamp test


Manual

350kva and 320kva (1000/1A)

04/07/2006 9 Prepared by A. Wormald


Guide to Synchronising and load sharing with DSE 5510
modules

200kva (600/1A)

04/07/2006 10 Prepared by A. Wormald