RAJASTHAN’S ROAD
TO PROGRESS
Punjab
Haryana
Uttar Pradesh
RAJASTHAN
Gujarat Madhya Pradesh
Maharashtra
The rapid pace of National Highway development
in Rajasthan has ensured seamless connectivity
to Gujarat and Uttar Pradesh. Till 2014 the length of
National Highways in the State was 7,496 km. In 2018,
the length has been increased to 14,465 km. The
number of National Highways have been grown from
35 to 85 in just four years. Road development work
worth Rs 10,000 cr has been completed, and 1,959
km work has been fast-tracked with investments
worth Rs 12,000 Cr. In the coming years, projects
worth Rs 2 lakh cr have been planned for Rajasthan.
“When a network of good roads is
created, the economy of the country
also picks up pace. Roads are veins
and arteries of the nation, which help
to transform the pace of development
and ensure that prosperity reaches
the farthest corners of our nation.”
NARENDRA MODI
Prime Minister
“In the past four years, we have expanded the
length of Indian National Highways network to
1,26,350 km. The highway sector in the country has
seen a 20% growth between 2014 and 2018. Tourist
destinations have come closer. Border, tribal and
backward areas are being connected seamlessly.
Multimodal integration through road, rail and port
connectivity is creating socio economic growth
and new opportunities for the people.
In the coming years, we have planned projects with
investments worth over Rs 6 lakh crore, to further
expand the world’s second largest road network.”
NITIN GADKARI
Union Minister, Ministry of Road Transport &
Highways, Shipping and Water Resources,
River Development & Ganga Rejuvenation
Fast tracking National Highway
development in Rajasthan
NH + IN PRINCIPLE NH LENGTH
UPTO YEAR 2018
9,341 km
NH LENGTH
UPTO YEAR 2014
6,302 km
Adding new
National Highways
in Rajasthan
9,561 km
2,511 km
2014 - 2018
2010 - 2014
New NH New NH & In principle NH length
6
Construction of roads
in Rajasthan
3,263 km
1,207 km
2014 - 2018
2010 - 2014
Constructed Constructed
length length
3,263 km of National Highways have
been built in 4 years
7
Road Projects
awarded in Rajasthan
Yr 2010 - 2014 Yr 2014 - 2018
1,523 km 4,797 km
Total Cost Total Cost
Rs. 7,702 Cr Rs. 24,457 Cr
Growth of 214% in the awarded length
of road projects over last 4 years with
investments worth Rs. 24,457 Cr
8
Accelerated NH Development
under Central Road Fund (CRF)
in Rajasthan
Yr 2010 - 2014 Yr 2014 - 2018
81 84
Projects
Projects
Total Cost Total Cost
Rs. 734.03 Cr Rs. 2,848.72 Cr
Significant increase of 288% in cost
of CRF works sanctioned for the
upgradation & improvement of roads /
bridges in the State
9
Landmark Projects
in Rajasthan
10
Cable Stayed Bridge across River
Chambal on Kota Bypass along NH-76
on the East-West Corridor
Connecting the last mile of the Golden Quadrilateral
At a Glance
1.4 km length 40 months
Construction Period
Rs. 275 Cr total cost
11
Benefits
• Uninterrupted traffic flow from Porbandar
(Gujarat) to Silchar (Assam) on East-West
corridor NH-27
• Kota City Decongested
• Accidents and vehicle pollution lowered
• Reduced traffic over old Chambal Bridge at
Nayapura, Kota
• National Ghariyal Sanctuary protected
through zero construction on Chambal River
Salient Features
700 m long Cable stayed bridge
400 m Viaduct
300 m Approach Road
Dual 3 lane carriageway
40 m surface clearance from Chambal river
2.5 m Noise barrier
1.5 m side footpath
Bridge Behaviour Monitoring
Fully lit
12
Proposed Expressways passing
through Rajasthan
Sl. Name of Total Total Estimated Benefitted Districts
No. the Project Length in Length in Capital Cost
(km) Rajasthan (in Rs. Cr)
(km)
1 Bathinda- 626 489 24,500 Hanumangarh, Churu,
Ajmer Green Field Sikar, Nagaur, Ajmer
Expressway
2 Delhi- Vadodra 940 442 23,000 Alwar, Bharatpur,
Green Field Dausa, Swai
Expressway Madhopur, Bundi,
Kota, Jhalawar
3 Sangaria- 982 856 25,000 Hanumangarh, Sri
Sanchore- ganganagar, Bikaner,
Santhalpur Green Jodhpur, Barmer,
Field Expressway Jalore
Salient Features
13
14
6 laning of Jaipur Ring Road between
Agra Road and Ajmer Road section
under NHDP Phase-VII
1st Milestone scheduled on 18.05.2018;
delivered on 12.04.2018
At a Glance
46.4 km length Rs. 810 Cr total cost
Benefits
• Will ease heavy traffic from NH-11 Agra
road, NH-8 Ajmer road, NH-12 Tonk Road &
SH-12 Malpura Road
• Will ensure seamless connectivity to nearby
districts
• Will result in greater economic benefits by
saving travel time, fuel and cost
• Will enhance access to places of religious
importance such as Ajmer and Pushkar
• Will boost tourism in Rajasthan and Delhi
• Proposed Interchanges on the Ring Road at
vital crossings will result in uninterrupted,
smooth and safe flow of traffic
• Will create new opportunities for the people
Salient Features
2 Toll plazas 31 Underpasses
1 Major bridge 1 PUP
2 Minor bridges 36 Culverts
2 Flyovers Partially access
controlled
2 ROBs
15
4 Laning of
Kota-Darah section
At a Glance
34.33 km length 2 year Construction
Period
Rs. 396 Cr total cost
on EPC Mode
Benefits
• Boost industry and trade in Kota & Jhalawar
districts
• Improve connectivity between Rajasthan and
Madhya Pradesh with the rest of central India
Salient Features
34.33 km main 1 ROB
Carriageway with
7 Minor Bridges
concrete pavement
8 VUP
9.52 km Service
Road with concrete 21 Box culverts
pavement
35 HP culverts
16
Development and Operation of
Sikar-Bikaner section via Sikar
Bypass and Bikaner Bypass to
2-lane & PS
At a Glance
237.58 km length 2 year Construction
Period
Rs. 650.84 Cr
total cost
Benefits
• Improve connectivity of Sikar, which is
located in the heart of Rajasthan to Punjab.
• Provide better connectivity to Bikaner, a
major tourist destination in Rajasthan.
Salient Features
237.58 km main 17.24 km Bikaner
Carriageway with bypass
bituminous pavement
19.463 km Sikar
2 VUP bypass
2 CUP 4 Toll Plazas
17
Ongoing Projects of MoRTH in Rajasthan
Sl. Lok sabha Project Name NH No. Sanctioned Total Date of Likely
No. constituency (New) Cost/TPC Length Start date of
(Rs. Cr) in km completion
1 Ajmer, Ajmer-Nagaur 89 425.00 148.25 Mar-13 Mar-19
Nagaur section
2 laning with Paved
Shoulder under PPP
2 Chittorgarh 4 laning of 79 & 113 511.21 117.00 Jan-13 Mar-18
Chittorgarh-Neemach
& 2 laning with
Paved Shoulder
of Nimbahara
Pratapgarh under
PPP
3 Nagaur, 2 laning with Paved 11 378.07 108.26 Jan-14 Apr-19
Bikaner Shoulder of Nagaur-
Bikaner section under
PPP
4 Bikaner, Development & 15 501.08 172.38 Sep-13 Mar-19
Ganganagar operation of Bikaner-
Suratgarh section
under PPP
5 Ajmer, 4 laning of Beawar- 8 900.00 116.00 Oct-09 Oct-20
Rajashmand Gomti section under
PPP
6 Nagaur Construction of 58 & 62 155.76 19.23 Sep-16 Oct18
Nagaur bypass on
EPC mode
7 Barmer, Up-gradation to 325 179.32 24.71 Jul-17 Jul-19
Jalore 2 lane with paved
shoulder Balotra to
Sanderao via Jalore
section (Pkg-II)
8 Jalore, Pali Up-gradation to 325 163.54 34.42 Jul-17 Jul-19
2 lane with paved
shoulder Balotra to
Sanderao via Jalore
section (Pkg-III)
9 Sikar, Construction of 2 11 116.31 27.85 Apr-18 Oct-19
Jhunjhunu lane with paved
shoulder Fatehpur to
Jhunjhunu section
10 Tonk, Sawai Widening, 552E 187.82 33.90 Apr-18 Oct-19
Madhopur Strengthening and
Reconstruction of
Sawai Madhopur to
Sheopur section
11 Churu, Construction of 2 709E 163.95 54.67 May-18 Nov-19
Jhunjhunu lane with paved
shoulder of Rajgarh-
Hariyana Border
section.
12 Barmer Up-gradation to 325 131.28 31.25 May-18 Nov-19
2 lane with paved
shoulder of Balotra to
Sanderao via Jalore
section
13 Banswara Up-gradation to 927A 96.90 23.88 May-18 Nov-19
2 lane with paved
shoulderof Wajwana
– Banswara section
14 Udaipur Upgradation to 2 lane 58E 370.3 58.03 Nov-18 Dec-19
with paved shoulder
of Kundal-Jhadol
section
18
Ongoing Projects of MoRTH in Rajasthan
Sl. Lok sabha Project Name NH No. Sanctioned Total Date of Likely
No. constituency (New) Cost/TPC Length Start date of
(Rs. Cr) in km completion
15 Udaipur Upgradation to 2lane 58E 341.79 59.70 Nov-18 Nov-19
with paved shoulder
of Jhadol-Daiya
at Gujarat Border
section
16 Ajmer Construction of 79 12.59 1.8 Feb-17 Dec-18
service road on both
side of the existing
road on Ajmer-
Nasirabad road
17 Jhalawar Construction of 12 80.68 4.20 Feb-17 Sep-18
4 lane Cement
Concrete road in
Jhalawar City
18 Jhunjhunu Strengtheining of 11 44.9481 31.7 Feb-18 Jan-19
Jhunjhunu- Chirawa
section
19 Jaipur Strengthening of 148B 11.4927 5 Feb-18 Jan-19
Paniyala Mod to
Hariyana Border
section
20 Kota, Strengthening of 52 30.295 20 Feb-18 Jan-19
Jhalawar existing pavement on
NH-12
21 Ajmer Strengtheining of NH- 89 4.199 1.8 Mar-18 Oct-18
89 in Nagaur City
22 Nagaur, 4 Lanning of Netra 65 376.61 28.57 Jan-15 Jul-18
Jodhpur village to Mandore
section
23 Kota Construction of 76/12 78.58 10.3 Jun-15 Dec-18
Northern Kota bypass
with paved shoulder
Pkg 1
24 Nagaur ROB Level Crossing 65 29.23 1.173 LOA -
no. C-64 on Jodhpur May-18
Ajmer road
25 Churu ROB on NH-709E 709 24.79 0.5 LOA -
near Sadalpur railway Extn Apr-18
station
26 kota 4 laning by CC 12 621.43 Aug-16 Nov-18
pavement on Kota-
Darah section
19
Ongoing Projects of NHAI in Rajasthan
Sl. Lok sabha Project Name NH No Project Length Date of Likely
No. constituency (New) Cost in Km Start date of
(Rs Cr) completion
1 Barmer Barmer-Sanchore-Gu- 15 538.08 106.3 Aug-15 Jun-18
jarat Border section
upto Gandhav Bridge
2 Barmer Munabao (NH-25E)- 70 1158.35 273.87 Appoint- -
Sundra- Myajlar-Dha- ed Date
nana-Asutar -Ghota- pending
ru-Tanot
3 Barmer Jaisalmer (NH-11) Bha- 68 913.91 193.52 appoint- -
dasar-ramgarh-Tanot- ed Date
and Bhadesar-Sarkari- pending
tala (Pkg-BM/5)
4 Barmer & Gangaria (NH-25)- 925 & 1134 196.97 appoint- -
Jalore Baori Kalan-Serwa-Sa- 925A ed Date
ta-Bakhasar and sata pending
Gandhav (Pkg BM/8)
5 Bikaner, Jodh- Bikaner to Phalodi 15 844.08 159.243 Oct-15 Dec-18
pur section
6 Jodhpur, Phalodi to Jaisalmer 15 726.89 160.457 Sep-15 Nov-18
Barmer section
7 Bikaner Khajuwala-Poogal 911 874.25 212.11 appoint- -
- Dantour- Jaggasar- ed Date
Gokul- Goddu -Ran- pending
jeetpura- Charanwala-
Naukh-Bap section
8 Bikaner Raisinghnagar - NH not 1250 162.46 appoint- -
Anupgarh - Gharsa- de- ed Date
na - Rojri - Sattasar pending
clared
- Pugal- (Part-2) (Pkg-
BM/6)
9 Tonk-Sawai Tonk to Sawai Mad- 116 261.9 66.8 Jan-17 Jan-19
Madhopur hopur section
10 Bhilwwara, Gulabpura to Uniara 148D 717.25 203.977 Oct-15 Aug-18
Bundi-Kota
11 Bansawara & Padhi to Dahod 113 371.72 85.588 Nov-14 Sep-18
Dahod (Guj.) section
12 Bhilwara & Gulabpura to Chit- 79 1377.63 124.87 Nov-17 May-20
Chittorgarh torgarh
13 Bhilwara Kishangarh to Gulab- 79A & 1183.48 90 Feb-18 Aug-20
pura 79
14 Dausa, Tonk- Dausa - Lalsot - Ko- 11 A 881 83.453 May-17 Nov-19
Sawai Mad- thun section Extn.
hopur
15 Karauli- Karauli - Dholpur 11B 261 100.9 Sep-14 Dec-18
Dholpur section
16 Dholpur, Uncha Nagla - 123 265.79 75.008 Feb-16 Aug-18
Bharatpur & Dholpur Section
Fatehpur-Sikri
17 Dausa, Jaipur Manoharpur - Dausa 11A 249.04 62.318 Oct-16 Oct-18
(Rural) section
18 Jaipur (Rural), Gurgaon - Kotputli - 48 3269.6 225.6 Apr-09 Oct-18
Alwar & Gur- Jaipur section
gaon
19 Jaipur Balance works of Jai- - 1216.67 46.4 Jan-18 Oct-18
pur Ring Road from
Agra Road to Ajmer
Road section
20 Sojat, Jaitaran, Bar-Bilara-Jodhpur 112 1248.59 109.655 Mar-17 Sep-19
Bhopalgarh & section
Bilara
20
Ongoing Projects of NHAI in Rajasthan
Sl. Lok sabha Project Name NH No Project Length Date of Likely
No. constituency (New) Cost in Km Start date of
(Rs Cr) completion
21 Soorsagar, Jodhpur Ring Road - 1300.11 74.619 appoint- -
Luni, Bhopal- Package-I [4-laning of ed Date
garh, Bilara Dangiawas to Jajiwal pending
Nagaur road)
22 Kota-Bundi, Deoli to Jn. of NH-76 12 (New 593.38 82.81 Jan-11 Apr-18
Bhilwara on Kota Bypass NH-52)
23 Jhalawar- 4 Lane of Darah-Jhal- 12 (New 1316.83 48.88 appoint-
Baran awar-Teendhar NH-52) ed Date
section pending
24 Churu, Sikar, Rajasthan Border to 65 530.07 154.141 Feb-14 Nov-18
Jhunjhunu Salasar (New-
52 &
58)
25 Churu & Na- Salasar to Nagaur 65 832.43 119.594 Mar-17 Oct-19
gaur (New-
58)
26 Chittorgarh & Udaipur Bypass [Con- 48 990 23.883 Nov-17 Nov-19
Udaipur nection between NH-
76 at Debari to NH-8
at Kaya Village]
27 Chittorgarh Chittorgarh-Udaipur 76 1405 93.5 Jul-17 Dec-19
Section
28 Udaipur, Udaipur to Shamlaji 8 2088 113.8 Sep-17 Feb-20
Banswara &
Sabarkantha
(Guj.)
21
In-Principle declaration NH in Rajasthan
Sl. Stretch Tentative Length (km)
No. As on 30/11/2017
1 From Junction of NH-48 near Dadu connecting Naraina, Sambhar, 150.00
Nawan, Narayanpura, Kuchamancity, Budsu, Toshina and
terminating at Choti Khatu near NH 458.
2 From Mandsaur connecting Pratapgarh, Dhariyawad, Salumber 171.00
and terminating at junction of NH-927 A near Dungarpur (Length
in Rajasthan =171 km; Madhya Pradesh = 11km)
3 From junction of NH-11 near Phalaudi connecting Nagur, Trnau, 220.00
Chhoti and terminating at NH-458 near Khatu
4 From junction of NH-752 near Kawai connecting Chhabra and 45.00
terminating at NH-46 near Sada Colony (Length in Rajasthan
=45km; Madhya Pradesh = 17km)
5 Anoopgarh-Surathgarh 72.00
6 Jhirka Firojpur (Haryana)- Pahadi- Nagar- Mahuwa- Hindaun- 210.00
Karauli- Nandrayal- Muhana (in MP on NH-46) (Total length= 312
km; Haryana= 15 km; Rajasthan= 210 km; MP= 87 km)
7 Sirsa- Nohar- Taranagar- Churu (on NH-65) (Total length= 177 km; 143.00
Haryana= 34 km; Rajasthan= 143 km)
8 Jalore- Ramsin- Bhinmal- Karda- Sanchore (Ext. of NH-168) 136.00
9 Jodhpur Bypass 88.50
10 Stretch from Baran - Khanpur-Jhalawar 82.00
11 Stretch from Kota (NH-27)- Kethoon - Sangod-Bapaur -Kawai 90.00
(on NH-752)
12 Stretch from Deoli (on NH-52) to Nasirabad (on NH-48) via Kokri, 100.00
Sarwar
13 Stretch from Sikar – Jhunjhunu (via Nawalgarh) 60.00
14 Stretch from Chirawa – Loharu (via Surajgarh) (Length = 28 km, 25.00
25 km in Rajasthan, 3 km in Haryana)
15 Stretch from Kota-Rawatbhata-Singoli-Ratangarh-Morvan-Mnasa- 68.00
Naraingarh-Pipliamandi-Mandsaur (Rajasthan=68 kms, Madhya
Pradesh=115 kms)
16 Stretch from Lalsot (on NH-23) - Sawai Madhopur (on NH-148 D) 65.00
17 Stretch from Rohat(on NH-62)- Ahore (on NH-325) 94.00
18 Stretch from Kharia(on NH-25)-Ransi-Borunda- Gotan and 85.00
extended upto junction with NH-58 near Run
19 Stretch from Desuri(on NH-162) - Sadri- Lunawa- Bera - Kagdara- 90.00
Pindwara
20 Stretch from Mathura- Bharatpur- Bayana- Hindon (Uttar 101.00
Pradesh=24 kms, Rajasthan=101 kms)
21 Stretch from Gangapur- Sawai Madhopur 75.00
22 Stretch from Mathura- Govardhan- Dig- Nagar (Rajasthan=31 kms, 31.00
Uttar Pradesh= 31 kms)
23 Stretch from Dausa- Lowan- Chaksu- Phagi- Dudu 137.00
24 Baap-Shekhasar-Sihda-Ramdevra 50.00
25 Baap-Jambha-Motai-Padiyal-Renisar-Bhojasar-Aau 50.00
26 Pokharan-Sankda-Bhainsda-Fatehgarh 80.00
27 NH-15 - Kansingh ki Sid-Jambha-Shaitan singh Nagar-Lohawat- 106.60
Mega Highway
28 Marwar Junction-Kamlighat 50.00
22
In-Principle declaration NH in Rajasthan
Sl. Stretch Tentative Length (km)
No. As on 30/11/2017
29 Sojat-Siriyari-Desuri 93.00
30 Sanderao-Bali-Sadri 43.00
31 Charbhuja-Gomti Chouraha 9.00
32 Agra-Jagner-Masalpur (UP-60.00 and Rajasthan-33.00) 33.00
33 Kalwar to Jaipur Ring Road 14.00
34 Uniyara-Indragarh 27.00
35 Lakheri-Itawa-Mangrol 61.00
36 Nachna-Ramdevra-Falsund-Baytu 210.00
37 Nathusari-Bhadara-Sindhmukh-Sadulpur-Malsisar-Jhunjhunu- 200.00
Gudha-Udaipurwati (Haryana-13.00 and Rajasthan-200.00)
38 Jurhara-Palwal (Haryana- 66.00 and Rajasthan - 3.00) 3.00
39 Dungargarh-Sardarshahr-Taranagar-Rajgarh-Bahal-Ovara-Kairu- 180.00
Lohani (Haryana-46.00 and Rajasthan-180.00)
40 Soyla-Osian-Tinwari-Balesar 126.00
41 Suratgarh-Baropal-18SPD-Jhakharanwali-Bherusari-Rawatsar 57.00
42 NH-6 near Edlabad in Maharashtra – Burhanpur – Borgaon – 42.00
Chegaonmakhan – Deshgaon – Borwaha-Indore-Ujjain - Agar
& terminating at junction with NH-12 at Jhalawar in Rajasthan
(Length in MP=391 km; Maharashtra= 15 km; Rajasthan=42 km)
43 Baran- Mangrol - Sheopur (Total length= 80 km; MP= 37; 43.00
Rajasthan= 43)
44 Dhar-Nagda-Ratlam-Mandsaur-Nimach - junction with NH-156 42.00
near MP / Rajasthan border (Total length = 291 km; MP= 249 km;
Rajasthan= 42 km
45 MP/ Rajasthan border- Paron- Fatehgarh- Guna 22.00
(Total length = 98; MP= 76; Rajasthan= 22)
46 Jaipur Bypass 13.60
47 Sikar - Kuchaman City 68.40
48 Kuchaman City - Kishangarh 73.60
49 Tentawar - Singhana 42.00
50 Teentawar - Udaipurwati 24.00
51 Udaipurwati - Sikar 38.80
52 Ganganagar (NH-62)- Raisinghnagar- Anupgarh- Rojhri- Awa- 397.00
Poogal- Barsatpur- Ranjitpura- Charanwala- Naukh- Bap
53 Jaisalmer (NH-11)- Kanod- Ghantiali- Nachna- Chinnu- Naukh 169.00
54 Bhadasar – Sarkaritala – upto Pakisthan border 84.00
55 Nachna – Balan (Babla) 47.00
56 Nachna – Bharewala 40.00
58 Pagal – Aladin K Bera – Beriyanwala 60.00
59 Bap- Kanasar- Nachna 83.00
60 Ramdevra- Pokhran- Falsund- Undu- Kashmir- Bhadkha- NH 15- 210.00
Uttarlai air base
61 Abu Road (NH-27) – Mount Abu 10.00
23
Key Indian National Highways
SRINAGAR
Jammu
Jalandhar
DELHI
Gurgaon
Jaipur Agra Lucknow Gorakhpur
Ajmer Muzaffarpur
Gwalior Kanpur
Allahabad Guwahati
Jhansi Purnea
Shivpuri
Udaipur Varanasi SILCHAR
Barhi
Ahmedabad Panagarh
Rajkot Vadodara Lakhnadon Kharagpur KOLKATA
PORBANDAR Surat
Nagpur
Bhubaneshwar
MUMBAI
Pune
Satara Hyderabad Vishakhapatnam
Arabian Sea
Eluru Vijayawada
Belgaum LEGEND
Chilakaluripet
Golden Quadrilateral
Tumkur
Hosur CHENNAI
Bangalore Ranipet North South Corridor
Selam Krishnagiri
Bay of Bengal East West Corridor
COCHIN Madurai
Lakshadweep
KANYAKUMARI
Indian Ocean
24
National Highways - India Story
Fast tracking National Highway Development
Building National Highways
A new Pace of Progress
NH LENGTH
NH LENGTH
91,287 km 1,26,350 km
Yr 2010-2014 Yr 2014-2018
New National Highways being built
86,371.5 km of New and In-Principle National
Highways added in 4 years
New NH
34,391.5 km
+
In principle NH length
51,980 km
New NH
Total
20,353.2 km
86,371.5 km
Yr 2010 - 2014 Yr 2014 - 2018
25
National Highways - India Story
Adding more National Highways
per day
Enhancing efficiency by building 28 km National 28
Highways per day in 4 years, up from 3 km km
22.5
km
16.6 2017-2018
km
12 2015-2016
km
2016-2017
2 3 2 3
km km km km
2014-2015
2013-2014
2012-2013
2010-2011 2011-2012 Rate of Highway
construction per day
Construction of roads
Rs. 3 lakh Cr worth investments in the road sector in 4 years
Significant growth of 158%
Yr 2014 - 2018
Yr 2010 - 2014 28,532 km
19,444 km
Total Cost
Rs. 1.16 lakh Cr
Total Cost
Rs. 3 lakh Cr
26
National Highways - India Story
Road Projects Awarded
100% increase in projects awarded with investments
of over Rs. 4.68 lakh Cr
Yr 2010-2014
Road Length Total Cost
25,609 km Rs 1.62 lakh Cr
Yr 2014-2018
Road Length Total Cost
51,075.32 km Rs. 4.68 lakh Cr
Accelerated NH development
under Central Road Fund (CRF)
Significant increase of 207.6% in cost of CRF
works sanctioned for the upgradation & improvement
of roads /bridges in the Nation
2,876
Yr 2010 - 2014
Projects
935
Projects
Total Cost
Total Cost
Rs. 8,613.51 Cr Rs. 48,186.57 Cr
Yr 2014 - 2018
27
Transforming India’s Transport Sector
Key initiatives in 2014 -2018
Over the past four years, various smart initiatives on
Indian National Highways have resulted in transparent
processes, last mile connectivity, safer roads, upskilling,
new opportunities and employment for the people.
Motor Vehicle (Amendment) E Toll - FASTag to enhance
Bill 2017: To bring transparency, efficiency, and reduce long
reduce corruption queues at Toll plazas
E-Rickshaws for last mile Exemption from the
connectivity requirement of commercial
licence for LMV and LCV drivers
Driving training schools in every 0.2%-15% decrease in road
district for skill development accidents and fatalities till 2017
Road Safety Greater Compensation for Partnering with
Annual Plan accident victims of upto NGOs to ensure
Rs. 5 lakhs road safety
Green buses and electric vehicles have been introduced. Emission
standards have been upgraded for vehicles. BS VI norms along with
bio fuel B-100, flex-fuel E-85 or E-100 & ethanol ED-95, methanol
M-15 or M-100 and methanol MD-95 have been standardised
15% methanol blending can result in the replacement of around
31.9 million tons of crude oil. With crude oil prices at USD 54
per barrel, the use of clean energy biofuels will reduce fuel costs
resulting in significant savings. Compared to neat gasoline, M-15
reduces CO and HC emission by 40%. Biofuels will help in reducing
vehicle pollution levels in India
28
Anti Lock Braking System Model Automated
ensuring vehicle and Centres for checking
passenger safety fitness of vehicles
Vehicle Fleet modernization Simplified forms for
programme obtaining driving licences
Increasing Speed Limits from Taxi Policy Guidelines to
100 km/h to 120 km/h, at par ensure safe, secure and
with the global practices affordable journeys, while
reducing congestion
as well as pollution in cities
Indian Bridge Management System (IBMS), the world’s
largest inventory of bridges, has been created for proper
maintenance of these structures. Till date 1,72,519
bridges of all ages and structures have been inventoried
across India,and assigned GPS based Location Numbers,
Classification Numbers based on features, Structural Rating
& Socio-Economic Rating numbers
789 black spots have been identified and assigned unique
ID numbers. Guidelines have been prepared and notified for
investigation and rectification of these road accident-prone
black spots on National Highways. 265 spots have already
been rectified
Rectification measures at 318 spots have been sanctioned
and are in various stages of implementation. 139 spots are on
State Government roads or with other agencies. Remaining
67 spots would be taken up separately or rectified as part of
ongoing projects
29
Manzilen Abhi
Aur Bhi Hain
30
31