PGCIL Standard Sections
PGCIL Standard Sections
Table of contents
2 HV POWER CABLES 7
[ FOR WORKING VOLTAGES FROM
3.3KV AND INCLUDING 33KV]
4 CABLE DRUMS 9
5 TYPE TESTS 10
1.1.1. Aluminium conductor XLPE insulated armoured cables shall be used for
main power supply purpose from LT Aux. Transformers to control room,
between distribution boards, supply to oil filtration units, DG supply to
AC distribution board and for supply for colony lighting from control
room.
1.1.2 Aluminium conductor PVC insulated armoured power cables shall be used
for various other applications in switchyard area/control room except for
control/protection purposes.
1.1.4 POWERGRID has standardised the sizes of power cables for various
feeders. Bidders are to estimate the quantity of cables and quote
accordingly. The sizes of power cables to be used per feeder in different
application shall be as follows:
1.1.8 For different cores of CT & CVT separate cable shall be used
1.1.9 At least one (1) cores shall be kept as spare in each copper control cable
of 4C, 5C or 7C size whereas minimum no. of spare cores shall be two (2)
for control cables of 10 core or higher size.
1.1.10 For control cabling, including CT/VT circuits, 2.5 sq.mm. size copper
cables shall be used per connection. However, if required from voltage
drop/VA burden consideration, additional cores shall be used. Further for
potential circuits of energy meters, separate connections by 2 cores of 2.5
sq.mm. size shall be provided.
1.1.11 Standard technical data sheets for cable sizes up to and including 1100V
are enclosed at Annexure. Cable sizes shall be offered/manufactured in
accordance with parameters specified in standard technical data sheets.
Technical data sheet for any other cores/sizes required during detailed
engineering shall be separately offered for owner’s approval by the
contractor/supplier. Submission of standard technical data sheets for
these cable sizes are not required for approval. Contractor/supplier
shall intimate name of proposed approved cable manufacturer along
with cable sizes, its quantity required during detailed engineering for
purchaser’s information and acceptance.
1.2.1. General
1.2.1.1. The cables shall be suitable for laying in racks, ducts, trenches, conduits
and underground buried installation with uncontrolled back fill and
chances of flooding by water.
1.2.1.2. They shall be designed to withstand all mechanical, electrical and thermal
stresses under steady state and transient operating conditions. The XLPE
/PVC insulated L.T. power cables of sizes 240 sq. mm. and above shall
withstand without damage a 3 phase fault current of at least 45 kA for at
least 0.12 second, with an initial peak of 105 kA in one of the phases at
rated conductor temperature (70 degC for PVC insulated cables and 90
degC for XLPE insulated cables). The armour for these power cables
shall be capable of carrying 45 kA for at least 0.12 seconds without
exceeding the maximum allowable temperature of PVC outer sheath.
1.2.1.4. The Aluminium/Copper wires used for manufacturing the cables shall be
true circular in shape before stranding and shall be uniformly good quality,
free from defects. All Aluminium used in the cables for conductors shall be
of H2 grade. In case of single core cables armours shall be of H4 grade
Aluminium.
1.2.1.5. The fillers and inner sheath shall be of non-hygroscopic, fire retardant
material, shall be softer than insulation and outer sheath shall be suitable
for the operating temperature of the cable.
1.2.1.7. Strip wire armouring method (a) mentioned in Table 5, Page-6 of IS : 1554
(Part 1) – 1988 shall not be accepted for any of the cables. For control
cables only round wire armouring shall be used.
1.2.1.8. The cables shall have outer sheath of a material with an oxygen index of
not less than 29 and a temperature index of not less than 250°C.
1.2.1.9. All the cables shall pass fire resistance test as per IS:1554 (Part-I)
1.2.1.12. Allowable tolerance on the overall diameter of the cables shall be plus or
minus 2 mm.
1.2.3.1. The PVC (70°C) insulated power cables shall be of FR type, C1 category,
conforming to IS: 1554 (Part-I) and its amendments read alongwith this
specification and shall be suitable for a steady conductor temperature of
70°C. The conductor shall be stranded aluminium. The Insulation shall
be extruded PVC to type-A of IS: 5831. A distinct inner sheath shall be
provided in all multicore cables. All cables shall be of armoured type.
For multicore armoured cables, the inner sheath shall be of extruded
PVC. The outer sheath shall be extruded PVC to Type ST-1 of IS: 5831
for all cables.
1.2.4.1. The PVC (70°C) insulated control cables shall be of FR type C1 category
conforming to IS: 1554 (Part-1) and its amendments, read alongwith this
specification. The conductor shall be stranded copper. The insulation
shall be extruded PVC to type A of IS: 5831. A distinct inner sheath shall
be provided in all cables. All cables shall be of armoured type. The
over sheath shall be extruded PVC to type ST-1 of IS: 5831 and shall be
grey in colour.
1.2.4.2. Cores shall be identified as per IS: 1554 (Part-1) for the cables up to five
(5) cores and for cables with more than five (5) cores the identification of
2.2. Only overhead connection has been foreseen for interconnecting 630 kVA
and 800 kVA, LT transformer to the tertiary of the ICT. However, HV
cable connections in place of overhead connection, if necessary shall also
be in the scope of contractor. In this case contractor shall provide 1C x
185 mm2 (Aluminium Conductor) or 1Cx120mm2 (Copper Conductor),
38/66kV HV cable along with necessary terminating accessories. The
construction of XLPE insulated, armoured HV cable shall be generally
conforming to IS 7098 (Part-III). Terminating accessories shall conform to
IEC60840 1999.
2.3. Bidder may offer sizes other than the sizes specified in clause 2.1 and
2.2. In such case sizing of power cables shall be done keeping in view
continuous current, voltage drop & short-circuit consideration of the
system. Relevant calculations shall be submitted by bidder during
detailed engineering for purchaser’s approval.
2.6 The cables shall have outer sheath of a material with an Oxygen Index of
not less than 29 and a Temperature index of not less than 250°C.
2.7 Allowable tolerance on the overall diameter of the cables shall be plus or
minus 2 mm.
The XLPE insulated, EHV cable shall conform to the requirements of IEC
60502-2 (applicable clauses only) for construction and IEC 60840/
IEC62067 ( as applicable) for testing. The terminating accessories shall
conform to IEC 60840 / IEC62067 ( as applicable).
3.2 The cable shall be of specified EHV grade, single core, unarmoured,
stranded compacted Copper conductor, core screening by a layer of
semiconducting tape followed by a layer of semiconducting compound,
cross linked polyethylene (XLPE) dry cured insulation, insulation screening
with semiconducting compound extruded directly over the insulation,
longitudinal sealing by a layer of non woven tape with water swellable
absorbent over insulation screen, followed by radial sealing (Metal sheath
of Lead alloy ‘E’), metallic screening by concentric layer of plain copper
wire followed by an open helix of copper & overall HDPE sheathed &
graphite coated and conforming to the technical particulars of
specification.
3.5 They shall be designed to withstand all mechanical, electrical and thermal
stresses under steady state and transient operating conditions.
3.9 Allowable tolerance on the overall diameter of the cables shall be plus or
minus 2 mm.
4 CABLE DRUMS
4.1 Cables shall be supplied in returnable wooden or steel drums of heavy
construction. Wooden drum shall be properly seasoned sound and free
from defects. Wood preservative shall be applied to the entire drum.
Drums offered shall conform to relevant standards. Drum drawings
are not required to be submitted for approval.
4.2 Standard lengths for each size of power and control cables shall be
500/1000 meters. The cable length per drum shall be subject to a
tolerance of plus or minus 5% of the standard drum length. The owner
shall have the option of rejecting cable drums with shorter lengths.
Maximum, One (1) number non standard length of cable size(s) may be
supplied in drums for completion of project.
4.3 A layer of water proof paper shall be applied to the surface of the drums
and over the outer most cable layer.
4.4 A clear space of at least 40 mm shall be left between the cables and the
lagging.
4.5 Each drum shall carry the manufacturer's name, the purchaser's name,
address and contract number and type, size and length of the cable, net
and gross weight stencilled on both sides of drum. A tag containing the
same information shall be attached to the leading end of the cable. An
arrow and suitable accompanying wording shall be marked on one end of
the reel indicating the direction in which it should be rolled.
5 TYPE TESTS
5.1 All cables shall conform to all type, routine and acceptance tests listed in
the relevant IS.
5.2.1 Following type tests ( on one size in a contract) as per IS: 7098 (Part 1) –
1988 including its amendments shall be carried out as a part of
acceptance tests on XLPE insulated power cables for working voltages
up to and including 1100 V:
5.2.2 Contractor shall submit type test reports as per clause no. 9.2 of Technical
Specification, Section: GTR for the following tests-
5.3.2 Contractor shall submit type test reports as per clause no. 9.2 of Technical
Specification, Section: GTR for the following-
a) High voltage test (water immersion d.c. test as per clause no. 16.3.2
of IS: 1554 (Part 1) - 1988).
b) Ageing in air oven.
c) Loss of mass in air oven.
d) Short time current test on power cables of sizes 240 sqmm and
above on
i) Conductors.
ii) Armours.
e) Test for armouring wires/strips.
f) Oxygen and Temperature Index test.
g) Flammability test.
5.4.1 Contractor shall submit type test reports as per clause no. 9.2 of
Technical Specification, Section: GTR for XLPE insulated HV power
cables (as per IS 7098 Part-II including its amendment or as per IEC).
5.5 XLPE INSULATED EHV POWER CABLES ( For working voltages from
66kV up to and including 500 kV)-
5.5.1 Contractor shall submit type test reports as per clause no. 9.2 of Technical
Specification, Section: GTR for XLPE insulated EHV cables ( as per
IEC60840 for cables up to 150 kV & IEC 62067 for cables above 150 kV).
5.6.1 Contractor shall submit type test reports as per clause no. 9.2 of Technical
Specification, Section: GTR for Terminating/jointing accessories as per IS
17573:1992/ IEC 60840:1999/ IEC62067.
b) Maximum Conductor temp. allowed for the short circuit duty (deg
C.) as stated above. : --------------------------------------250 oC------------------------------------------------
9 Conductor
a) Material Stranded Aluminium as per Class 2 of IS : 8130
b) Grade : ------------------------------------- H 2 (Electrolytic grade) -------------------------
c) Cross Section area (Sq.mm.) : 630 300/150
d) Number of wires(No.)minimum : 53 30/15
e) Form of Conductor Stranded compacted
Stranded and compacted circular
circular/sector shaped
f) Direction of lay of stranded layers : -------- Outermost layer shall be R.H lay & opposite in successive layers --------
10 Conductor resistance (DC) at 20 oC per km-maximum 0.0469 0.1 / 0.206
11 Insulation
a) Composition of insulation : -------------------------------------Extruded XLPE as per IS-7098 Part(1)-----------------
b) Nominal thickness of insulation(mm) : 2.8 1.8/1.4
c) Minimum thickness of insulation : 2.42 1.52/1.16
12 Inner Sheath
a) Material : --------------------------------Extruded PVC type ST-2 as per IS-5831-84-----------------
b) Calculated diameter over the laid up cores,(mm) : NA 52
c) Thickness of Sheath (minimum)mm : N.A 0.6
d) Method of extrusion NA Pressure/Vacuum extrusion
13 Armour
a) Type and material of armour Al. Wire[ H4
: Gal. Steel wire
grade]
b) Direction of armouring : ----------------------------------left hand--------------------------------------------------
c) Calculated diameter of cable over inner sheath (under armour), mm
: 33.9 53.2
b) Non standard drum lengths : Maximum one(1) non standard lengths of each cable size may be
supplied in drums only over & above the standard lengths as specified
above.(if required for completion of project).
17 Whether progressive sequential marking on outer sheath provided at
1 meter interval : ----------------------------------------- YES -------------------------------------------------
18 Identification of cores
a) colour of cores As per IS 7098 Part(1)
b) Numbering : ----------------------------------------- N.A ---------------------------------------------------
19 Whether Cables offered are ISI marked : ----------------------------------------- YES ---------------------------------------------------
20 Whether Cables offered are suitable for laying as per IS 1255
: ----------------------------------------- YES -----------------------------------------------------
11 Insulation
a) Composition of insulation : -------------------------------------Extruded PVC type A as per IS-5831-84--------------------------
b) Nominal thickness of insulation(mm) : 2.1 1.4/1.2 1.2/1.0 1.0 1.0 1.0
c) Minimum thickness of insulation : 1.79 1.16/0.98 0.98/0.8 0.8 0.8 0.8
12 Inner Sheath
a) Material : --------------------------------Extruded PVC type ST-I as per IS-5831-84----------------------------------
b) Calculated diameter over the laid up cores,(mm) : N.A 27.6 20.4 15.7 11.6 9.6
c) Thickness of Sheath (minimum)mm : N.A 0.4 0.3 0.3 0.3 0.3
13 Armour : -------------------------- as per IS 3975/88 ---------------------------------------------------------------------
a) Type and material of armour Gal.steel Gal.steel Gal.steel
: Al. Wire[H4 grade] Gal. Steel wire Gal. Steel wire
strip strip strip
b) Direction of armouring : ----------------------------------left hand-----------------------------------------------------------------------
d) Nominal diameter of round armour wire/strip : 1.6 4 x 0.8 4 x 0.8 4 x 0.8 1.4 1.4
e) Number of armour wires/strips : -------------------Armouring shall be as close as practicable------------------------------------------
f) Short circuit capacity of the armour along for 1 sec-for info only
: --K x A√t (K Amp)(where A = total area of armour in mm 2& t = time in seconds), K=0.091 for Al & 0.05 for steel
b) Non standard drum lengths Maximum one(1) non standard lengths of each cable size may be supplied in drums only over & above the
: standard lengths as specified above.(if required for completion of project).
17 Whether progressive sequential marking on outer sheath provided : ----------------------------------------- YES -------------------------------------------------------------
18 Identification of cores
a) colour of cores Red R,Y,Bl &Bk R,Y,Bl &Bk R,Y,Bl &Bk R,Y,Bl &Bk Red & Bk
b) Numbering : ----------------------------------------- N.A -------------------------------------------------------------
19 Whether Cables offered are ISI marked : ----------------------------------------- YES -------------------------------------------------------------
20 Whether Cables offered are suitable for laying as per IS 1255
: ----------------------------------------- YES -------------------------------------------------------------
.
Annexure-I Bill of Quantity
Annexure-II Details of Lighting Fixture
Annexure-III Drawing of Portable Flood Light Panel (PFL)
Annexure-IV Drawing of Lighting Pole
Annexure-V Single Line Diagram(C/ENGG/TS/STD/ILLU/TOWNSHIP/01)
1. For Indoor Lighting, LED fixtures to be supplied as per Quantity specified in Technical
Specification.
2. For Outdoor Lighting & GIS Building, LED fixtures have been envisaged in place of
Conventional Sodium Vapor Lamps (Quantity to be supplied as per BPS).
3. Firewall mounted Flood Lights have been envisaged for Transformer & Reactors (to be
supplied as per BPS).
4. Portable Flood Light Panel for Maintenance purpose has been specified. Typical
Drawing is also enclosed (to be supplied as per BPS).
5. Bidder shall be required to submit LM-79 & LM-80 reports for LED Luminaries.
6. Roof top Solar Grid System with battery has been replaced by Roof Top Solar Grid
System of 50kW, 30kW & 20kW for 765kV, 400kV & 220kV Substation respectively
(without Battery) to be integrated in ACDB. (to be supplied as per BPS).
7. Considering maintenance issue of Pole mounted battery, Solar Panel along with battery
used for Street Lighting System has been deleted and Street Lighting using LED
Luminaries is retained.
8. AC Emergency Lighting in GIS building, SPR, DG Area and LT Transformer Area has
been specified.
9. Use of Occupancy Sensor has been deleted.
10. Lighting System for Township & Transit Camp included in line with Rev.05.
11. Stainless steel Panels/Junction Boxes of thickness 1.5 mm for Outdoor application has
been specified.
12. Indoor Lighting Panels Bus Bar has been changed from Copper to Copper/Aluminum
Alloy.
13. Technical Specification for Receptacle RQ-1 (250A) & RQ-2 (400A), 415V, 3-phase has
been included for Oil filtration purpose.
14. All concealed Conduit shall be PVC type and all surface mounted conduit shall be of
Galvanized steel.
15. Lighting Steel tubular Poles painting changed to hot deep galvanizing with PU
(Polyurethane) coating in Suzuki Silver color.
16. Fixtures Model and Vendor names have been deleted and general technical parameters of
LED fixtures have been included for Indoor as well as Outdoor Fixtures.
17. Bottom of Outdoor Lighting Panels mounting height shall be 1000mm from FGL.
Note : Above are major changes made in the Model TS, however Bidder is advised to refer
Technical Specification in detail for other changes in the specification.
Section -LIGHTING SYSTEM (Rev.07)
1 GENERAL
i) Indoor Lighting
Portable Flood Light Panel (PFLP): Portable Flood Light Panel along
with fixture is to be supplied as per BPS for maintenance purpose of
the Substation. The detailed drawing for the PFLP shall be as per the
drawing attached in the specification (Annexure-IV). Fixture shall be
FL-2 type on PFLP.
3.1 General
a) PV Modules (Crystalline)
b) Module Mounting Structure and frames
c) Array Terminal Box
d) Grid Interactive Inverters
e) Solar AC Panel
f) Cable & Wires
g) Earthing system
Technical Specification, Section: LS ENGG / SPEC / LS REV.NO: 07
Page 2 of 25
Section -LIGHTING SYSTEM (Rev.07)
The inverter shall be pure sine wave inverter of high efficiency. Inverters
shall have display to show its own parameters along with the parameters
of PV array connected to the Inverter. The inverter shall be compatible as
On Grid Connected Mode (Synchronization with grid). The inverter shall
include but not limited to the following:
• The inverter shall be highly efficient based on Maximum Power Point
Tracking (MPPT) control providing a fixed DC input voltage to inverter.
MPPT must be able to extract maximum energy from Solar array and
produce 415 V, 3-ph, 50Hz AC to synchronize with the grid through
Substation ACDB panel.
• The Inverter shall not produce Electromagnetic interference (EMI)
which may cause malfunctioning of electronic and electrical
Display
Voltage & Frequency
Power
Energy
Indications
DC Input Line Status
Inverter under voltage/ over voltage
Inverter over load
Protections
Over voltage both at input & output
Over current both at input & output
Over/ under grid frequency
Reverse Polarity Protection
Reverse current to PV array protection
Short circuit
Protection against lightning
Protection against Surge voltage induced at output due to
external source
For cleaning of the PV Modules, necessary plumbing & piping work shall
be done by tapping from the existing pipeline available at the roof top so
that water is easily available near the PV modules.
Corridors & Staircase so that the operating personnel can safely find their
way even during emergency of total AC failure.
The scope shall broadly consist of entire concealed conduit work, wiring
for lights/power/fans/telephones/cables & air-conditioners, supply and
fixing of metal boxes, plates, switches, sockets, call bells, buzzers,
Technical Specification, Section: LS ENGG / SPEC / LS REV.NO: 07
Page 7 of 25
Section -LIGHTING SYSTEM (Rev.07)
exhaust fans, ceiling fans, MCBs, MCCBs, light fittings, energy meters
boards & flat DBs etc. as per the requirements of various quarters,
recreation centers and transit camps.
LED Luminaries shall be used for the lighting of all the indoor and outdoor
areas. In false ceiling area, LED luminaries shall be recessed mounting
type & in non-false ceiling area, the LED luminaries shall be surface
mounting type.
ii) All Outdoor Lighting Panels shall be Stainless sheet steel of Grade 304
and shall be dust, weather and vermin proof. Panels shall be of
Technical Specification, Section: LS ENGG / SPEC / LS REV.NO: 07
Page 8 of 25
Section -LIGHTING SYSTEM (Rev.07)
thickness not less than 1.5 mm smoothly finished, leveled and free from
flaws. Stiffeners shall be provided wherever necessary.
iii) The panels shall be of front single door hinged construction, suitable for
either floor mounting on channels, sills or on walls/columns by suitable
M.S. brackets. Indoor Lighting panels shall be modular flush mounted
and wall embedded of slim depth.
iv) All panels shall have a dead front assembly provided with hinged
door(s) and with suitable locking arrangement.
v) All Outdoor panel’s removable covers and doors shall be gasketed all
around with neoprene/EPDM gaskets/ puff arrangement.
vi) The outdoor panels shall be suitable for cable/conduit entry from the
bottom. Suitable removable cable gland-plate shall be provided in the
bottom of panels. For indoor lighting panels the provision of
cable/conduit entry shall be from both top and bottom side with suitable
removable gland plate. The thickness of the gland plate shall be 3 mm.
Necessary number of double compression brass type cable gland shall
be supplied, fitted on to these gland plates.
ix) Each panel will be provided with laminated as built circuit diagram
suitably pasted in the panel.
xi) All Outdoor Lighting Panels shall be erected such that a minimum height
of 1000mm is maintained between FGL & bottom of the Lighting Panel.
Size of Outdoor Lighting panels shall be such that cables are properly
terminated and wires are dressed with provision of loops.
For indoor panels (ACP 1), 63A, 4pole 300 mA RCCB conforming IS
12640 will be provided along with incomer.
Technical Specification, Section: LS ENGG / SPEC / LS REV.NO: 07
Page 11 of 25
Section -LIGHTING SYSTEM (Rev.07)
b) The MCBs and MLDB panel MCCBs together shall be rated for full
fault level. In case the MCB rating is less than the specified fault level
the Contactor shall co-ordinate these breaker characteristics with the
backup MCCB in such a way that if fault current is higher than breaker
rating, the MCCB should blow earlier than the MCB. If the fault current
is less than MCB breaking capacity, MCB shall operate first and not
the incomer MCCB.
c) The MCBs shall be suitable for housing in the lighting panels and shall
be suitable for connection with stranded copper/Al wire connection at
both the incoming and outgoing side by copper/Al lugs or for bus bar
connection on the incoming side.
d) The terminals of the MCBs and the ‘open/trip’ and ‘close’ conditions
shall be clearly and indelibly marked.
(iv) CONTACTORS
Contactors shall be of the full voltage, direct-on line air break, single
throw, electro-magnetic type. They shall be provided with at least
2’NC’ and 2’NO’ auxiliary contacts. 3-Phase Contactor shall be
provided with the three elements, positive acting, ambient temperature
compensated time lagged, hand reset type thermal overload relay with
adjustable settings to suit the rated current. Hand reset button shall
be flush with the front of the cabinet and suitable for resetting with
starter compartment door closed. The Contactor shall check the
adequacy of the Contactors rating, wires with respect to lighting load.
All push buttons shall be of push to actuate type having 2 ‘NO’ and 2
‘NC’ self-reset contacts. They shall be provided with integral
escutcheon plates engraved with their functions. Push buttons shall
be of reputed make.
(vi) LABELS
Type RO : 20A, 240V, 3 pin type (third pin grounded) plug and socket
with body earthing arrangement with Single Pole MCB, metal clad with
gasket having cable gland entry suitable for 2Cx6 sq.mm.
PVC/aluminum armoured cable and a spring loaded cover suitable for
installation in moist outdoor location. Receptacles shall be housed in a
box made out of 1.5 mm thick Stainless Steel of Grade 304 with
hinged doors with suitable locking arrangements. Door shall be lined
with good quality gasketing.
a) The Indoor junction boxes shall be provided with 4 way knockouts suit-
able for two numbers 10 sq. mm. wire/ Cable. These junction boxes
shall be concealed type for indoor lighting.
b) Switch boards/boxes shall have conduit knock outs on all the sides.
c) The exact number of Switches including regulator for fans and layout
of the same in the switchboard shall be suitable as per the
requirement during installation.
a) The pull out boxes shall be concealed type for indoor lighting and
suitable for mounting on column, structures etc., for outdoor lighting.
b) The pull out boxes shall be circular of minimum 16 SWG sheet steel
and shall have cover with good quality gasket lining.
a) The Contactor shall supply and install 1400 mm sweep ceiling fans
complete with electronic regulator and board for mounting switch,
suspension rod, canopy and accessories. The electronic regulator for
Ceiling fans will be housed in common switchboard for lighting and
shall be of similar make and model as that of modular switches. The
wall mounted fans shall be of 400 mm sweep. Exhaust fans shall be of
300mm size.
c) The conductor sizes for wires used for point wiring shall be 1.5 sq.mm,
2.5 sq.mm, 4 sq.mm and 6 sq.mm stranded copper wire as required.
(i) The Contactor shall supply, store and install the following types of
galvanized steel tubular lighting poles required for street lighting and
decorative lighting, as per the attached drawing of poles.
(i) Type L1 Street Lighting Pole of 6 meter - for SL-L1 type fixture
(ii) Type D1 Post top lantern pole of 4 meter - for Sl-D1 type fixture
(ii) “L1” type poles shall be used for street lighting. “D1” type (Decorative
Technical Specification, Section: LS ENGG / SPEC / LS REV.NO: 07
Page 16 of 25
Section -LIGHTING SYSTEM (Rev.07)
post top lantern) poles and Bollards shall be installed In front of control
room building, Fire Fighting Buildings as finalized during detailed
engineering.
(iv) Poles and its Cable termination box shall be hot dip galvanized and
PU (Polyurethane) coated in Suzuki silver color and inside with
bituminous paint.
(v) Terminal strips provided in street - lighting poles shall be suitable for
terminating up to 2 nos. 4C x 16 sq. mm aluminum cables.
(vi) Wiring from junction box at the bottom of the pole to the fixture at the
top of the pole shall be done through 2.5 sq. mm Copper wire laid
inside the tubular pole.
8.1 General
(i) Contractor shall supply, store and install conduits required for the
lighting installation as specified. All accessories/fittings required for
making the installation complete, including but not limited to pull out
boxes (as specified in specification ordinary and inspection tees and
elbow, check nuts, male and female bushings (brass or galvanized
steel), caps, square headed make plugs, nipples, gland sealing
fittings, pull boxes, conduits terminal boxes, glands, gaskets and box
covers, saddle terminal boxes, and all steel supporting work shall be
supplied by the Contractor. In case of false ceiling surface conduiting
is permissible however all down run conduits will be concealed in wall
below the false ceiling. The conduit fittings shall be of the same
material as conduits. Separate Conduit should be laid for
Communication purpose .The contractor shall also supply & install 20
mm PVC conduit and accessories for telephone wiring and LAN
Cabling wherever feasible, telephone and LAN cabling can be laid in
the same conduit.
(iii) All unarmored cables/wires shall run within the conduits from lighting
panels to lighting fixtures, receptacles. etc.
(vii) For directly embedding in soil, the conduits shall be coated with an
asphalt-base compound. Concrete pier or anchor shall be provided
wherever necessary to support the conduit rigidly and to hold it in
place.
(viii) For long conduit run, pull boxes shall be provided at suitable intervals
to facilitate wiring.
(x) Conduits joints and connections shall be made through water-tight and
rust proof by application of a thread compound which insulates the
joints. White lead is suitable for application on embedded conduit and
red lead for exposed conduit.
(xi) The entire GI conduit system (if used) shall be embedded, electrically
continuous and thoroughly grounded. Where slip joints are used,
suitable bounding shall be provided around the joint to ensure a
continuous ground circuit.
8.3 Wiring
iii) Wires shall not be pulled through more than two equivalent 90 deg.
bends in a single conduit run. Where required, suitable junction boxes
shall be used.
vii) AC and DC wiring should run through the separate conduits. Similarly
Communication & LAN cables shall run in separate conduit than that
of AC & DC Conduits.
iii) The Sub lighting Panel shall be provided where independent switch of
fixtures are required.
i) Each cable run shall be tagged with number that appears in the cable
schedules. Cables shall be tagged at their entrance and/or exit from
any piece of equipment, junction or pull box, floor opening etc.
ii) The tag shall be made up of aluminum with the number punched on it
and securely attached to the cable by not less than two turns of G.I.
wire. Cable tags shall be rectangular in shape for power cables and
circular shape for control cables.
iii) Location of cables laid directly under ground shall be indicated clearly
by cable marker made of galvanized iron plate embedded in concrete
block.
i) Foundation for street lighting poles and panels shall be done by the
Technical Specification, Section: LS ENGG / SPEC / LS REV.NO: 07
Page 20 of 25
Section -LIGHTING SYSTEM (Rev.07)
Contractor.
ANNEXURE-I
SL-1 SC-I
RL-I Type RC-I
(Surface (Surface Type SSQ-1 Type RSQ-1
(Recessed (Recessed Type IHB
Sr. Technical Mounted Mounted (Surface (Recessed
Mounted 4 x Mounted Circular (LED Indoor
No Specification Linear LED Circular LED Mounted 2X2 Mounted 2x2
1 Feet LED LED Downlight High Bay)
Tube with Downlight LED Luminaire) LED Luminaire)
Panel) Luminaire)
Box ) Luminaire)
1 System Wattage ≤ 2 X 20 W ≤ 40 W ≤ 15 W ≤ 15 W ≤ 40 W ≤40 W ≤150W
2 System Lumen Output ≥ 3600 ≥ 3600 ≥ 1200 ≥ 1200 ≥ 3400 ≥ 3400 ≥14000
System efficacy
3 ≥ 100 ≥ 100 ≥ 80 ≥ 80 ≥ 85 ≥ 85 ≥ 100
(Lumens/Watt)
Pressure Die
CRCA CRCA Pressure Die Pressure Die Cast
4 Housing CRCA Housing CRCA Housing Cast Aluminum
Housing Housing Cast Housing Housing
Housing
5 Ingress Protection IP20 IP-20 IP20 IP-20 IP-20 IP-20 IP-65
4kV (Internal) &
6 Surge Protector 2kV 2kV 2kV 2kV 2kV 2kV
10kV (External)
Surface Hanging Type
7 Mounting False Ceiling Surface Mounted False Ceiling Surface Mounted False Ceiling
Mounted under Shed
System efficacy
3 ≥ 80 ≥ 100 ≥ 90 ≥ 100 ≥ 100
(Lumens/Watt)
TABLE OF CONTENTS
a. Hydrant System
1.00.01 It is not the intent to completely specify all details of design and
construction. Nevertheless, the system design and equipment shall
conform in all respects to high standard of engineering, design and
workmanship and shall be capable of performing in continuous
commercial operation in a manner acceptable to the Owner. The system
design shall also conform to TAC/ NFPA norms.
1.00.03 The equipment offered shall comply with the relevant Indian Standards
unless specified otherwise. The equipment conforming to any other
approved international standards shall meet the requirement called for in
the latest revision of relevant Indian Standard or shall be superior. The
Deluge valves, HVW spray nozzles & quartzoid bulb detectors shall
have the approval of any of the following agencies;
a. UL of USA.
b. F M of USA
c. LPCB of UK or
d. VDS of Germany,
1.00.05 The piping and instruments diagram for Hydrant and HVW spray system
for 765kV/400kV substations and for 220kV&132kV substation is
` The typical drawings for location of fire detectors and fire extinguishers
in control cum administrative building attached in Appendix-II with this
section shall be followed for execution.
1.00.06 Equipment under the fire protection system should be supplied from the
suppliers approved by POWERGRID (A list of approved vendors is
enclosed at Appendix-V). All equipment shall conform to the data sheets
attached in Appendix–IV and/or relevant subsections/clauses of this
specification. In case of contradiction between data specification sheets
and relevant subsections/clauses, then stipulations of the data sheets
will prevail.
d) Stores
e) Transformers
2.01.01 A warning plate shall be placed near the hydrant points for the
transformers and reactors substations to clearly indicate that water shall
be sprayed only after ensuring that the power to the transformer/ reactor
which is on fire is switched off and there are no live parts within
20metres of distance from the personnel using the hydrant.
The system shall be designed in such a way that the same can be
extended to protect additional Transformer/ Reactor to be installed in
future. However, for the purpose of design it shall be assumed that only
one Transformer/ Reactor will be on fire. The main header pipe size in
the yard shall be 250mmNB (for 400kV and above level substations)
and 200mmNB(for 220kV & 132kV substations). Branch to the
equipment (shall not be more than 20metres length) shall be of the
same size as of deluge valve.
2.02.01 The Electrical clearance between the Emulsifier system pipe work and
live parts of the protected equipment shall not be less than the values
given below :
5. 52 kV bushing 630 mm
6. 36 kV bushing 320 mm
Deluge Valve shall be water pressure operated manual reset type. The
Deluge valve shall be closed water tight when water pressure in the heat
detector pipe work is healthy and the entire pipe work shall be charged
with water under pressure upto the inlet of the Deluge valve. On fall of
water pressure due to opening of one or more heat detectors, the valve
shall open and water shall rush to the spray water network through the
open Deluge valve. The valves shall be manually reset to initial position
after completion of operation. Each Deluge Valve shall be provided with
a water motor gong which shall sound an alarm when water after
passing through the Deluge valve, is tapped through the water motor.
Each Deluge valve shall be provided with a local panel with provision of
opening of Deluge valve from local and remote from control room/
remote centre. In addition to this, each valve shall be provided with local
operation latch.
Test valves shall simulate the operation of Deluge valves and shall be of
quick opening type. The general construction shall conform to
requirements under clause no.7.00.00 for piping, valves and specialities.
This system shall be provided for control room building and Switchyard
panel rooms of substations.
2.03.01 Suitable fire detection system using smoke detectors and/or heat
detectors shall be provided for the entire building, including corridor and
toilets. Fire detectors shall be located at strategic locations in various
rooms of the building. Each Switchyard panel room shall be considered
a separate zone. Adequate number of extra zones shall be provided for
Switchyard panel rooms for future bays identified in Single line diagram
of the substation. The operation of any of the fire detectors/ manual call
point should result in the following;
2.03.02 Each zone shall be provided with two zone cards in the panel so that
system will remain healthy even if one of the cards becomes defective.
2.03.03 Coverage area of each smoke detector shall not be more than 80 m 2
and that of heat detectors shall not be more than 40 m2. Ionisation type
smoke detectors shall be provided in all areas except pantry room
where heat detectors shall be provided. If a detector is concealed, a
remote visual indication of its operation shall be provided. Manual call
points (Break glass Alarm Stations) shall be provided at strategic
locations in the control room building. All cabling shall be done through
concealed conduits.
2.03.04 Cables used should be exclusively for fire detection and alarm system
and shall be 2Cx1.5sq.mm Cu. cables. Un-armoured PVC insulated FR
cables conforming to IS 1554 (Part 1) shall be used.
For 400kV and above level substations water for hydrant & HVW system
shall be supplied by one electrical motor driven pump of rated capacity
410m3/hr. at 70MWC head & for 220kV and 132kV substations water
for hydrant & HVWS system shall be supplied by one electrical
motor driven pump of rated capacity 273m3/hr. at 70MWC head,
with another pump of same capacity , driven by diesel engine, shall be
used as standby. Water storage tank with two compartments of
adequate capacity shall be provided. Pumps shall work under positive
suction head. Annunciations of the hydrant & HVW spray systems shall
be provided in fire water pump house and repeated in control room.
Provision for sending data to remote control centre shall also be
available.
The outdoor piping for the system in general shall be laid above ground
on concrete pedestals with proper supporting arrangement. However, at
2.05.01 The general design of the fire fighting pump sets shall meet the
requirements under clauses no.5.00.00 for Horizontal centrifugal pumps,
no.6.00.00 for Diesel engines and no.12.00.00 for Electrical motors.
Power feeder for motors will be from switchgear board located in control
2. Start/Stop facility
15. Spare 10
-----------------------------------------------------------------------------------------
ii) Provision shall be made in the panel for a signal for spray ON for each
Transformer/Reactor for owner's use for event logger.
iii) Each Switchyard panel room shall be considered as separate zone for fire
detection and alarm system.
-----------------------------------------------------------------------------------------
Sl.No. Description Number
-----------------------------------------------------------------------------------------
d) Indication for fault in respective areas shall also be provided. Each zone
alarm module shall exhibit 'FIRE’ and 'FAULT' conditions separately.
e) Provision for sending data to Remote Control Unit for the following
(vii) High Speed Diesel tank level (low & very low)
(viii) AC Mains Supply Healthy/Fail for Main Pump & Jockey Pump
(ix) DC Control Supply Healthy/Fail for Main Pump & Jockey Pump
2.06.04 The control and interlock system for the fire protection system shall
meet the following requirements:
3. Jockey Pump
3.00.00 TESTS
3.01.01 Shop tests of all major equipment centrifugal pumps, diesel engines,
electrical drive motors, piping, valves and specialties, pressure and
storage vessels, MCC, electrical panels, controls, instrumentation etc.
shall be conducted as specified in various clauses and as per applicable
standards/codes.
3.01.02 Shop tests shall include all tests to be carried out at Contractor's works,
works of his sub-contractor and at works where raw materials supplied
for manufacture of equipment are fabricated. The tests to be carried out
shall include but not be limited to the tests described as follows :
3.01.05 All test certificates and reports shall be submitted to the Employer for
approval.
3.01.06 The Employer's representative shall be given full access to all tests.
The manufacturer shall inform the Employer allowing adequate time so
that, if the Employer so desires, his representatives can witness the test.
3.02.01 General
c) All pumps shall be run with the specified fluid from shut off condition
to valve wide open condition. Head developed will be checked from
the discharge pressure gauge reading. During the test, the pumps
and drives shall run smoothly without any undue vibration, leakage
through gland, temperature rise in the bearing parts, noise, flow
pulsation etc.
h) Automatic starting of all the fire pumps by operating the test valves.
3.02.02 After erection at site, the complete HVW spray protection and hydrant
system shall be subject to tests to show satisfactory performance for
which detailed procedure shall be submitted for Employer's approval.
Full flow tests with water shall be done for the system piping as a means
of checking the nozzle layout, discharge pattern and coverage, any
obstructions and determination of relation between design criteria and
actual performance, also to ensure against clogging of the smaller
piping and the discharge devices by foreign matter carried by the water.
Rigidity of pipe supports shall also be checked during the water flow.
3.02.03 All the detectors installed shall be tested for actuation by bringing a
suitable source of heat/smoke near the detector and creating a stream
of hot air/ smoke over the detector. The exact procedure of this test
shall be detailed out by the Employer to the successful Bidder.
The Contractor shall indicate in his scope of supply all the mandatory
spares in the relevant schedules. The list of mandatory spares is
indicated in ‘Section - Projects’.
5.01.00 The materials of the various components shall conform to the applicable
IS/BS/ASTM/DIN Standards.
5.01.01 In case of any contradiction with the aforesaid standards and the
stipulations as per the technical specification as specified hereinafter,
the stipulations of the technical specification shall prevail.
5.02.03 Pumps shall be capable of furnishing not less than 150% of rated
capacity at a head of not less than 65% of the rated head. The shut off
head shall not exceed 120% of rated head. Range of operation shall be
20% of rated flow to 150% of rated flow.
5.02.04 The pump-motor set shall be designed in such a way that there is no
damage due to the reverse flow through the pump which may occur due
to any mal-operation of the system.
The drive rating shall not be less than the maximum power requirement
at any point within the "Range of Operation" specified.
During starting under reverse flow condition, the motor shall be capable
of bringing the pump to rated speed at normal direction with 90% rated
voltage at motor terminals.
5.02.06 Pump set along with its drive shall run smooth without undue noise and
vibration. Acceptable peak to peak vibration limits shall generally be
guided by Hydraulic Institute Standards.
5.02.07 The Contractor under this specification shall assume full responsibility in
the operation of the pump and drive as one unit.
5.03.01 Pump casing may be axially or radially split. The casing shall be
designed to withstand the maximum pressure developed by the pump at
the pumping temperature.
5.03.02 Pump casing shall be provided with adequate number of vent and
priming connections with valves, unless the pump is made self-venting &
priming. Casing drain, as required, shall be provided complete with
drain valves.
5.03.03 Under certain conditions, the pump casing nozzles will be subjected to
reactions from external piping. Pump design must ensure that the
nozzles are capable of withstanding external reactions not less than
those specified in API-610.
5.03.05 Impeller
The impeller shall be secured to the shaft and shall be retained against
circumferential movement by keying, pinning or lock rings. On pumps
with overhung shaft impellers shall be secured to the shaft by an
additional locknut or cap screw. All screwed fasteners shall tighten in
the direction of normal rotation.
5.03.07 Shaft
Shaft size selected shall take into consideration the critical speed, which
shall be at least 20% away from the operating speed. The critical speed
shall also be atleast 10% away from runaway speed.
5.03.09 Shaft sleeves shall be securely fastened to the shaft to prevent any
leakage or loosening. Shaft and shaft sleeve assembly should ensure
concentric rotation.
5.03.10 Bearings
A common base plate mounting both for the pump and drive shall be
furnished.
5.03.15 Balancing
5.03.16 All the components of pumps of identical parameters supplied under this
specification shall be interchangeable.
5.04.01 The manufacturer shall conduct all routine tests required to ensure that
the equipment furnished conform to the requirements of this
specification and are in compliance with the requirements of applicable
Codes and Standards. The particulars of the proposed tests and the
procedures for the tests shall be submitted to the Employer/Engineer for
approval before conducting the tests.
5.04.05 Shaft shall be subjected to 100% ultrasonic test and machined portion of
the impeller shall be subject to 100% DP test. On finished shaft DP test
will also be carried out.
5.04.09 Tests shall preferably be conducted alongwith the actual drives being
supplied.
5.04.10 The Bidders shall submit in his proposal the facilities available at his
works to conduct performance testing. If because of limitations of
available facilities, a reduced speed test or model test has to be resorted
to establish pump performance, the same has to be highlighted in the
offer.
5.04.13 All rotating components of the pumps shall be subjected to static and
dynamic balancing tests.
5.04.14 The Employer or his authorised representative shall have full access to
all tests. Prior to performance tests, the Contractor shall intimate the
Employer allowing adequate time so that if the Employer so desires, his
representative can witness the test.
5.04.15 Report and test certificates of the above tests shall be submitted to the
Employer/Engineer for approval.
General
6.01.01 The diesel engine shall be of multicylinder type four-stroke cycle with
mechanical (airless) injection, cold starting type.
6.01.02 The continuous engine brake horse power rating (after accounting for all
auxiliary power consumption) at the site conditions shall be atleast 20%
greater than the requirement at the duty point of pump at rated RPM and
in no case, less than the maximum power requirement at any condition
of operation of pump.
6.01.06 Starting
The engine shall be capable of both automatic and manual start. The
normal mode of starting is automatic but in the event of failure of
automatic start or at the discretion of the operator, the engine can be
started manually from the LCP.
Since the fire pumping unit driven by the diesel engine is not required to
run continuously for long periods and the operation will not be frequent,
special features shall be built into the engine to allow it to start within a
very short period against full load even if it has remained idle for a
considerable period.
6.01.09 The batteries shall be used exclusively for starting the diesel engine and
be kept fully charged all the time in position. Arrangement for both
trickle and booster charge shall be provided.
Diesel engine shall be provided with two (2) battery charger units of air-
cooled design. The charger unit shall be capable of charging one (1) set
of battery at a time. Provision shall, however, be made so that any one
of the charger units can be utilised for charging either of the two (2)
batteries.
6.01.10 For detail design of battery and battery charger, sub- section Electrical
may be referred to.
The engine shall be fitted with a speed control device, which will control
the speed under all conditions of load.
6.01.13 The governor shall be suitable for operation without external power
supply.
6.01.15 The engine shall be provided with fuel oil tank of 250 litres capacity.
The fuel oil tank shall preferably be mounted near the engine. No fuel
oil tank will be provided by the Employer.
6.01.17 The fuel oil tank shall be designed in such a way that the sludge and
sediment settles down to the tank bottom and is not carried to the
injection pump. A small sump shall be provided and fitted with drain
plug to take out sludge/sediment and to drain oil. Adequate hand holes
(greater than 80 mm size) shall be provided to facilitate maintenance.
6.01.18 Pipeline carrying fuel oil shall be gradually sloped from the tank to the
injection pump. Any valve in the fuel feed pipe between the fuel tank
and the engine shall be placed adjacent to the tank and it shall be
locked in the open position. A filter shall be incorporated in this pipeline,
in addition to other filters in the fuel oil system. Pipe joints shall not be
soldered and plastic tubing shall not be used. Reinforced flexible pipes
may also be used.
6.01.19 The complete fuel oil system shall be designed to avoid any air pocket in
any part of the pipe work, fuel pump, sprayers/injectors, filter system etc.
No air relief cock is permitted. However, where air relief is essential,
plugs may be used.
6.01.20 A manual fuel pump shall be provided for priming and releasing of air
from the fuel pipelines.
6.02.01 The manufacturer shall conduct all tests required, to ensure that the
equipment furnished conforms to the requirement of this sub-section
6.02.02 At manufacturer's works, tests shall be carried out during and after
completion of manufacture of different component/parts and the
assembly as applicable. Following tests shall be conducted.
6.02.05 Static and dynamic balance tests of rotating parts at applicable over-
speed and determination of vibration level.
6.02.07 Ultrasonic testing of crankshaft and connecting rod after heat treatment.
6.02.09 Calibration tests of all fuel pumps, injectors, standard orifices, nozzles,
instruments etc.
6.02.12 Performance test of the diesel engine to determine its torque, power and
specific fuel consumption as function of shaft speed. Performance test
of the engine shall be carried for 12 hours out of which 1 hour at full load
and one hour at 110% overload.
The vibration shall be measured during full load test as well as during
the overload test and limit shall be 100 microns.
This clause covers the design, manufacture, shop testing, erection, test-
ing and commissioning of piping, valves and specialities.
7.02.00 Scope
The piping system which shall include but not be limited to the following:
7.02.01 Plain run of piping, bends, elbows, tees, branches, laterals, crosses,
reducing unions, couplings, caps, expansion joints, flanges, blank
flanges, thrust blocks, anchors, hangers, supports, saddles, shoes,
vibration dampeners, sampling connections, hume pipes etc.
7.02.02 Gaskets, ring joints, backing rings, jointing material etc. as required.
Also all welding electrodes and welding consumables including special
ones, if any.
7.02.04 Gate and globe valves to start/stop and regulate flow and swing check
valves for one directional flow.
7.02.06 Bolts, nuts, fasteners as required for interconnecting piping, valves and
fittings as well as for terminal points. For pipe connections into Owner's
R.C.C. works, Bidder will furnish all inserts.
7.03.00 Design
Mild steel black pipes as per IS:1239, Part-I medium grade (for
pipes of sizes 150 NB and below) or IS:3589, Fe 410 grade (for
pipes of sizes 200 NB and above) suitably lagged on the outside to
Mild steel black pipes as per IS:1239, Part-I medium grade (for
pipes for sizes 150 NB and below) or IS:3589, Fe 410 grade (for
pipes of sizes 200 NB and above).
(c) Overground pipes normally empty, but periodic charge of water and
for detector line for HVW System.
Mild steel galvanised pipes as per IS:1239, Part-I medium grade (for
pipes of sizes 150 NB and below) or IS:3589, Fe 410 grade (for pipes of
sizes 200 NB and above).
7.03.02 All fittings to be used in connection with steel pipe lines upto a size of 80
mm shall be as per IS:1239. Part-II Mild steel tubulars and other
wrought steel pipe fittings, Heavy grade. Fittings with sizes above 80
mm upto 150 mm shall be fabricated from IS:1239 Heavy grade pipes or
steel plates having thickness not less than those of IS:1239 Part-I Heavy
grade pipes. Fittings with sizes above 150 mm shall be fabricated from
IS:3589 Class-2 pipes. All fitting used in GI piping shall be threaded
type. Welding shall not be permitted on GI piping.
7.03.03 Pipe sizes shall not be less than the sizes indicated in the attached
drawings.
7.03.09 Gate/sluice valve shall be used for isolation of flow in pipe lines and
construction shall be as per IS:778 (for size up to 40 mm) and
IS:14846 (for sizes above 40 mm) except for valve spindle movement.
Valves shall be of rising spindle type and of PN 1.6 class
7.03.11 Gate valves shall be provided with back seating bush to facilitate gland
removal during full open condition.
7.03.13 Non-return valves shall be swing check type. Valves will have a
permanent "arrow" inscription on its body to indicate direction of flow of
the fluid. These valves shall generally conform to IS:5312.
7.03.15 Valves below 50 mm size shall have screwed ends while those of 50
mm and higher sizes shall have flanged connections.
d) Screen open area shall be at least 4 times pipe cross sectional area
at inlet.
b) Hydrant Valve
(c) Each hose shall be fitted with instantaneous spring lock type
couplings at both ends. Hose shall be fixed to the coupling ends by
copper rivets and the joint shall be reinforced by 1.5 mm galvanised
mild steel wires and leather bands.
(g) Hose pipes fitted with quick coupling ends, branch pipes, nozzles
spanner etc. will be kept in a hose box, which will be located near
point of use. The furnished design must meet the approval of Tariff
Advisory Committee.
7.04.01 The contractor shall fabricate all the pipe work strictly in accordance with
the related approved drawings.
(a) For steel pipes, end preparation for butt welding shall be done by
machining.
(c) For tees, laterals, mitre bends, and other irregular details cutting
templates shall be used for accurate cut.
(b) Coating and wrapping and holiday testing shall be in line with
IS:10221.
(c) Buried pipelines shall be laid with the top of pipe one meter below
ground level.
(d) At site, during erection, all coated and wrapped pipes shall be
tested with an approved Holiday detector equipment with a positive
signalling device to indicate any fault hole breaks or conductive
particle in the protective coating.
7.05.01 While erecting field run pipes, the contractor shall check, the
accessibility of valves, instrument tapping points, and maintain minimum
headroom requirement and other necessary clearance from the
adjoining work areas.
7.05.03 Welding
(v) As far as possible welding shall be carried out in flat position. If not
possible, welding shall be done in a position as close to flat
position as possible.
(viii) Tack welding for the alignment of pipe joints shall be done only by
qualified welders. Since tack welds form part of final welding, they
shall be executed carefully and shall be free from defects.
Defective welds shall be removed prior to the welding of joints.
(x) Root run shall be made with respective electrodes/filler wires. The
size of the electrodes/filler wires. The size of the electrodes shall
not be greater than 3.25 mm (10 SWG) and should preferably be
2.3 mm (12 SWG). Welding shall be done with direct current
values recommended by the electrode manufacturers.
7.06.01 Pipes
7.06.02 Valves
(ii) All valves shall be tested hydrostatically for the seat as well as
required in the code/standards for a period of ten minutes.
(iv) Visual check on the valve and simple operational test in which the
valve will be operated thrice from full open to full close condition.
7.06.03 Strainers
(i) The stand post assembly along with the hydrant valve (valve being
open and outlet closed) shall be pressure tested at a hydrostatic
pressure of 21 kg/cm2g to detect any leakage through defects of
casting.
b) Internal diameter
8.01.00 Air vessels shall be designed and fabricated of mild steel as class-II
vessels as per IS:2825 for a pressure of 14kg/cm2 and shall be minimum
3 m3 capacity.
8.03.00 Outside surfaces of the vessels shall be provided with one (1) coat of
red lead primer with two (2) coats of synthetic enamel paint of approved
colour and characteristics.
8.04.01 Air vessels shall be hydraulically tested at 21kg/cm2 for a period not
less than one (1) hour.
8.04.02 All materials used for fabrication shall be of tested quality and test
8.04.03 Welding procedure and Welder's qualification tests will be carried out as
per relevant IS Standard.
8.04.04 NDE tests, which will include 100% Radiography on longitudinal seams
and spot Radiography for circumferential seams, for pressure vessel will
be carried out.
9.01.00 Heat Detectors, Quartzoid bulb type. (Used in HVW spray system)
9.03.02 Both smoke and heat type fire detectors shall be used. Bidder shall
clearly indicate the mode of operation of detectors in his proposal.
9.03.03 The set point shall be selected after giving due consideration for
ventilating air velocity and cable insulation.
9.03.04 Fire detectors shall be equipped with an integral L.E.D. so that it shall be
possible to know which of the detectors has been operated. The
detectors, which are to be placed in the space above the false ceiling or
in the floor void shall not have the response indicators on the body but
shall be provided with remote response indicators.
10.00.01 This specification lays down the requirement regarding fire extinguishers
of following types :
10.00.02 All the extinguishers offered by the Bidder shall be of reputed make and
shall be ISI marked.
10.01.01 All the portable extinguishers shall be of freestanding type and shall be
capable of discharging freely and completely in upright position.
10.01.02 Each extinguisher shall have the instructions for operating the
extinguishers on its body itself.
10.01.03 All extinguishers shall be supplied with initial charge and accessories as
required.
10.01.04 Portable type extinguishers shall be provided with suitable clamps for
mounting on walls or columns.
10.01.05 All extinguishers shall be painted with durable enamel paint of fire red
colour conforming to relevant Indian Standards.
10.02.01 A performance demonstration test at site of five (5) percent or one (1)
number whichever is higher, of the extinguishers shall be carried out by
the Contractor. All consumable and replaceable items require for this
test would be supplied by the Contractor without any extra cost to
Employer.
10.03.00 Painting
Each fire extinguisher shall be painted with durable enamel paint of fire
red colour conforming to relevant Indian Standards.
11.00.02 All field mounted instruments shall be weather and dust tight, suitable
for use under ambient conditions prevalent in the subject plant. All field
mounted instruments shall be mounted in suitable locations where
maximum accessibility for maintenance can be achieved.
11.01.01 The pressure sensing elements shall be continuous 'C' bourdon type.
11.01.02 The sensing elements for all gauges/switches shall be properly aged
and factory tested to remove all residual stresses. They shall be able to
withstand atleast twice the full scale pressure/vacuum without any
damage or permanent deformation.
11.01.03 For all instruments, connection between the pressure sensing element
and socket shall be braced or hard soldered.
11.01.05 All gauges shall be with stainless steel bourdon having rotary geared
stainless steel movements.
11.01.06 Weatherproof type construction shall be provided for all gauges. This
type of construction shall be fully dust tight, drip tight, weather resistant
and splash proof with anti-corrosive painting conforming to NEMA- 4.
11.01.09 Scales shall be concentric, white with black lettering and shall be in
metric units.
11.01.12 All gauges shall have 1/2 inch NPT bottom connection.
11.01.14 All instruments shall be provided with 3 way gauge isolation valve or
cock. Union nut, nipple and tail pipe shall be provided wherever
required.
11.01.15 Switch element contact shall have two (2) NO and two (2) NC contacts
rated for 240 Volts, 10 Amperes A.C. or 220 Volts, 5 Amperes D.C.
Actuation set point shall be adjustable throughout the range. ON-OFF
differential (difference between switch actuation and de-actuation
pressures) shall be adjustable. Adjustable range shall be suitable for
switch application.
11.01.16 Switches shall be sealed diaphragm, piston actuated type with snap
action switch element. Diaphragm shall be of 316 SS.
11.02.00 Timers
11.02.02 Each timer shall have two pairs of contacts in required combination of
NO and NC.
ii) Gauge glasses, in general, shall be flag glass type with bolted
cover. Body and cover material shall be of carbon steel with rubber
lining.
iv) Reflex type gauge glasses shall be used for colourless liquids and
i) Float type mechanical level gauges with linear scale type indicator
shall be offered for measuring level of tanks wherever shown in the
flow diagram.
ii) AISI-316 stainless steel float, guide rope and tape shall be used.
Housing shall be of mild steel painted with anti-corrosive painting.
iii) The scale indicator shall be provided at a suitable height for ease of
reading.
11.04.01 The body of the valves shall be Forged brass or stainless steel.
11.04.02 The coil shall be continuous duty, epoxy moulded type Class-F, suitable
for high temperature operation.
12.01.00 General
12.01.01 This clause covers the requirements of three phase squirrel cage
induction motors and single-phase induction motors.
12.01.03 The motor supplied under this specification shall conform to the
standards specified in GTR.
12.01.04 Terminal point for all motors supplied under this specification shall be at
the respective terminal boxes.
12.01.05 Materials and components not specifically stated in this specification but
are necessary for satisfactory operation of the motor shall be deemed to
be included in the scope of supply of this specification.
12.02.23 National Electrical code for hazardous location and relevant NEMA
standard shall also be applicable for motors located in hazardous
location.
(i) The induction motors shall be of squirrel cage type unless specified
otherwise.
(ii) The motors shall be suitable for continuous duty in the specified
ambient temperature.
(iii) The MCR KW rating of the motors for 50oC ambient shall not be
less than the power requirement imposed at the motor shaft by the
driven equipment under the most onerous operation conditions as
defined elsewhere, when the supply frequency is 51.5 Hz (and the
motor is running at 103% of its rated speed).
b) Frequency 50 Hz + 3%.
12.03.02 Enclosure
a) All induction motors shall be suitable for full voltage direct on-line
starting. These shall be capable of starting and accelerating to
the rated speed alongwith the driven equipment without
exceeding the acceptable winding temperature even when the
supply voltage drops down to 80% of the rated voltage.
(i) When the motors are operating at extreme condition of voltage and
frequency given under clause no.12.03.01 (iv) the maximum
permissible temperature rise over the ambient temperature of 50 oC
shall be within the limits specified in IS : 325 after adjustment due
(ii) The double amplitude of motor vibration shall be within the limits
specified in IS: 4729. Vibration shall also be within the limits
specified by the relevant standard for the driven equipment when
measured at the motor bearings.
(iii) All the induction motors shall be capable of running at 80% of rated
voltage for a period of 5 minutes with rated load commencing from
hot condition.
(v) Motors shall be capable of developing the rated full load torque
even when the supply voltage drops to 70% of rated voltage. Such
operation is envisaged for a period of one second. The pull out
torque of the induction motors to meet this requirement shall not be
less than 205% of full load torque.
12.04.01 Stator
The stator frames and all external parts of the motors shall be rigid
fabricated steel or of casting. They shall be suitably annealed to
eliminate any residual stresses introduced during the process of
fabrication and machining.
12.04.02 Rotor
(i) For motors of 415 Volts and below a single terminal box may be
provided for power and accessories leads.
(iii) Terminal box shall be suitable for top and bottom entry of cables.
(vi) Suitable tinned brass compression type cable glands and cable
lugs shall be supplied by the Contractor to match Employer's
cable.
(vii) Terminal box for single core cable shall be of non- magnetic
material.
(i) Rating plates shall be provided for all motors giving the details as
called for in IS:325 (for three phase squirrel cage induction
(ii) In addition to above, the rating plate shall indicate the following :
(ii) Motor weighing more than 25 kg. shall be provided with eyebolts,
lugs or other means to facilitate lifting.
12.05.01 Motor external parts shall be finished and painted to produce a neat and
durable surface, which would prevent rusting and corrosion. The
equipment shall be thoroughly degreased, all sharp edges and scales
removed and treated with one coat of primer and two coats of grey
enamel paint.
12.05.03 All fasteners used in the construction of the equipment shall be either of
corrosion resistant material or heavy cadmium plated.
12.06.01 Motors shall be subject to routine tests in accordance with IS : 325 & IS :
4029 standards.
b) Measurement of vibration.
13.01.01 The equipment specified hereinafter are required for starting the diesel
engines and other operation of the plant as required.
13.01.02 For each diesel engine there shall be two (2) sets of Battery and two (2)
sets of Battery Charger.
13.01.03 The D.C. voltage shall be obtained normally after necessary rectification
by battery charger. The Battery Charging system shall be capable of
meeting the following requirements :
13.01.06 The battery shall be large enough to crank the engine 3 times without
charging in between and without getting drained to an extent which will
affect its life.
13.01.07 The Bidder shall indicate the battery voltage and battery capacity in
Ampere- Hour at ten (10) hour discharge rate. The battery voltage at
any time during operation shall not be less than the minimum voltage
required for operation of the D.C. loads.
13.02.01 Battery
(i) The cells shall be lead-acid type. The Battery shall be automotive
type.
(ii) The cells shall be sealed in type with anti-splash type vent plug.
(iii) The cell terminal posts shall be provided with connector bolts and
nuts, effectively coated with lead to prevent corrosion. Lead or
lead coated copper connectors shall be furnished to connect up
cells of battery set.
(iv) Positive and Negative terminal posts shall be clearly and indelibly
marked for easy identification.
(i) The Bidder shall furnish the battery charging scheme complete with
all necessary accessories such as transformers, switches, fuses,
starters, contactors, diodes, ammeters, voltmeters and other
devices as required for trouble free operation. All devices and
equipment shall conform to relevant Indian Standard or shall be
Superior to it.
(ii) The scheme of the battery charger shall be such that the battery
can be charged automatically as well as manually.
(iii) The boost charger shall have sufficient capacity to restore a fully
discharged Battery to a state of full charge in eight (8) hours with
some spare margin over maximum charging rate. Suitable
provision shall be kept so that, for a particular engine, any of the
two (2) charger units can be used for charging any of the two (2)
batteries.
(v) The panel shall be complete with internal wiring and input-output
terminal block. Terminal blocks shall be clip on type of suitable
rating. All equipment and wire terminals shall be identified by
symbols corresponding to applicable schematic/wiring diagram.
13.03.00 Testing
13.03.01 The Battery Charger shall also be subjected to the following tests at
manufacturer's works as per IS - 4540
b) Verification of dimensions
Battery and battery charger shall be checked for auto charging and
providing sufficient power for three consecutive starting kicks to diesel
engine within five minutes with A.C. supply switched off.
14.02.01 The equipment specified herein are required for controlling, metering,
monitoring and indication of electrical systems of the plant offered.
14.02.03 The reference ambient temperature outside the panel shall be taken as
50oC and relative humidity 100%.
14.04.01 The panel frames shall be fabricated using suitable mild steel structural
sections or pressed and shaped cold-rolled sheet steel of thickness not
less than 2.5 mm. Frames shall be enclosed in cold-rolled sheet steel of
thickness not less than 1.6 mm. Stiffeners shall be provided wherever
necessary.
14.04.02 Panels shall be of free standing type and shall be provided with hinged
door with locking arrangement. The access doors, cutest and covers
shall be equipped with neoprene/synthetic rubber gaskets (conforming
to IS 11149-1984) all around and the latches sufficiently strong to hold
them in alignment when closed. The panels to be installed outdoor or
semi outdoor shall have a degree of protection of IP:55 and those
installed indoor shall have a degree of protection of IP:52 as per
IS:13947 Part-1.
14.04.04 Removable eye bolt or lifting lugs shall be provided on all panels to
facilitate easy lifting.
14.04.05 The heights of all operating equipment on the panel shall be between
800 mm to 1600 mm from the finished floor level. The proper supporting
arrangement shall be provided by the Contractor.
14.04.06 Cable entries to the panel may be from bottom or top. The cable entry
required will be intimated to the successful Bidder. A suitable
removable gland plate of 3 mm thick shall be mounted not less than 200
mm above the floor level.
14.04.07 All equipment mounted on the front face of the panels shall be flush or
semi-flush type. All equipment shall be so located that their terminal
14.05.02 All name plates shall be of non-rusting metal or 3 ply lamicold, with
white engraved lettering on black background. Inscription and lettering
sizes shall be subjected to Employer's approval.
14.05.03 Suitable plastic sticker labels shall be provided for easy identification of
all equipment located inside the panel. These labels shall be positioned
so as to be clearly visible and shall give the device number, as
mentioned in the wiring drawings.
14.06.02 The Employer will provide one feeder each for AC and DC to the panel.
The Contractor shall make for his own arrangements for providing these
power supplies to different panels.
14.06.02 The Contractor shall provide suitable isolating switch fuse unit in the
control panel for receiving the above incoming AC and DC supplies.
Fuse and link shall be provided for isolating of individual circuit without
disturbing other circuits.
14.07.00 Wiring
14.07.01 All inter panel wiring and connections between panels (if there is group
of panels) including all bus wiring for AC & DC supplies shall be
provided by the Contractor.
14.07.02 All internal wiring shall be carried out with 1100 V grade, single core, 1.5
square mm or larger stranded copper wires having colour-coded PVC
insulation. CT circuits shall be wired with 2.5 square mm copper wires,
otherwise similar to the above.
14.07.04 Spare contacts of auxiliary relays, timers and switches shall be wired out
to the terminal blocks as required by the Employer/Engineer at the time
of detailed engineering.
14.08.01 Terminal Blocks shall be of 650V grade, rated for 10 Amps and in one-
piece moulding. It shall be complete with insulating barriers, clip-on-
type terminals, and identification strips. Marking on terminal strip shall
correspond to the terminal numbering on wiring diagrams. It shall be
similar to 'Elmex-Standard' type terminals.
14.08.03 The terminal blocks shall have at least 20% spare terminals.
14.09.00 Grounding
14.10.01 Space heaters shall be provided in the panels for preventing harmful
moisture condensation.
14.10.02 The space heaters shall be suitable for continuous operation on 240V
AC, 50 Hz, single phase supply and shall be automatically controlled by
thermostat. Necessary isolating switches and fuses shall also be
provided.
14.10.03 Free standing panel shall have a 240V AC, plug point and a fluorescent
light operated by door switch.
14.11.01 Control and selector switches shall be of rotary type, with escutcheon
plates clearly marked to show the function and positions.
14.11.02 Control/selector switches shall be spring return or stay put type as per
the requirements. Handles of control/selector switches shall be black in
colour. Shape and type of handles shall be to the approval of the
Employer.
14.12.01 Push buttons shall be spring return, push to actuate type and rated to
continuously carry and break 10A at 240V AC and 0.5A (Inductive) at
220V DC. The push buttons shall have at least 1 NO and 1 NC contact.
All contact faces shall be of silver or silver alloy.
14.12.02 All push buttons shall be provided with integral escutcheon plates
marked with its function.
14.12.04 Red push buttons shall always be located to the left of green push
buttons. In case of clinker grinder etc. the push buttons would be black-
red-green from left to right.
14.13.01 Indicating lamps shall be of the panel mounting, filament type and of
low-watt consumption. Lamps shall be provided with series resistors
preferably built-in- the lamps assembly. The lamps shall have
escutcheon plates marked with its function, wherever necessary.
14.13.02 Lamp shall have translucent lamp covers of the following colours :
Blue for all healthy conditions (e.g. control supply, lub oil pressure
and also for spring charged).
Amber for all ALARM conditions (e.g. pressure low, over load and also
for 'service' and 'Test' position indication).
14.13.03 Bulbs and lamps covers shall be easily replaceable from the front of the
panel.
14.13.04 Indicating lamps should be located directly above the associated push
14.14.00 Fuses
14.14.01 All fuses shall be of HRC cartridge plug-in-type and shall be of suitable
rating, depending upon circuit requirements.
14.14.02 All fuses shall be mounted on fuse carriers, which shall be mounted on
fuse-bases.
14.15.00 Contactors
14.15.03 DC contactors shall have a coil voltage of 220V DC and shall be suitable
for satisfactory continuous operation at 80% to 110% of the rated
voltage.
14.16.01 All auxiliary relays & timers shall be of proven design and of reputed
make. Contacts of relays and timers shall be of solid silver or silver
cadmium oxide or solid silver faced. Timers shall have the provision to
adjust the delay on pick-up or reset as required.
14.16.02 All relays and timers shall have at least two NO and two NC contacts.
14.16.03 All relays and timers shall be suitable for 240V AC and 220V DC as
required. DC relays shall operate satisfactorily between 70% to 110%
and AC relays shall be suitable for voltage variation between 80% to
110%.
14.17.01 All indicating and integrating meters shall be flush mounted on panel
front. The instruments shall be of at least 96 mm square size with 90
degree scales and shall have an accuracy class of 2.0 or better. The
covers and cases of instruments and meters shall provide a dust and
vermin proof construction.
14.17.02 All instruments shall be compensated for temperature errors and factory
14.17.03 All instruments shall have white dials with black numerals and lettering.
Black knife edge pointer with parallax free dials will be preferred.
14.18.01 The annunciation system shall be complete with all necessary relays,
flashers and other accessories required for the proper operation of the
equipment and shall be completely solid state. The control circuit shall
be mounted on plug-in type glass epoxy printed circuit boards. Audible
alarms for the system shall be mounted inside the panel. One set of
acknowledge, test and reset push buttons shall be mounted on the
panel.
14.18.03 Audible hooter shall sound when a trouble contact operates and shall
continue to sound until the acknowledge button is pressed. In addition to
the hooters provided on annunciation panels, a hooter shall be provided
outside FFPH which shall sound in any fire alarm condition.
14.18.04 Indication lamps shall flash when trouble contact operates and shall
continue flashing until acknowledge button is pressed.
14.18.05 After acknowledge button is pressed, the hooter and flashing shall stop
but the indication lamp shall remain lighted.
14.18.06 After trouble is cleared indication lamps shall be ready and shall go off
only when reset.
14.18.07 Silencing the hooter in conjunction with one trouble contact shall not
stop and hooter sounding if another trouble contact operates.
14.18.08 When test button is pressed, all lamps shall flash and hooter shall
sound.
14.18.10 The annunciation system shall include alarm for AC control system
failure (working on DC supply), DC supply failure (working on AC
supply) and test facilities for these alarms.
14.18.11 List of annunciations required on the panels has been listed elsewhere.
14.19.00 Painting
14.20.00 Tests
5. HV test
2. HV Test
3. Functional Testing.
(C)
WI
A 0
0 0 0
ACDB/DCDB ROOM
14840 X 9770
- CD
0 0
U.
0
BATTERY ROOM BILL OF QUANTITY FOR FIRE EXTINGUISHERS.
4800 X 6620 SYMBOL TYPE QUANTITY
TROL ROOM
)0 X 4770 A 4.5 KG CO2 08+1•
ELECTRICAL LAB
0 • 9 LITRE WATER 04
0 IONIZATION DETECTORS 24
0 HEAT DETECTOR 01
E REMOTE RESPONSE
011
INDICATOR
[Z3 MANUAL CALL POINT 04
DI HOOTER 02.If
0 FOR FIRE WATER PUMP HOUSE.
NOTES
ALL DIMENSIONS ARE IN MM. UNLESS OTHERWISE SPECIFIED.
ADMINISTRATIVE
OFFICE AREA
14840 X 9720
0 0
PROJECT
800/400/220 ICV SUB-STATION
OF REDIATOR
PSI 11144 14145 11146
-500 062
trig 575 575
D827
r -111 • -tom
)
18
11143
OF N.G.R.
600 2465
N142
1.---.4=mazzaziabgimc „ 111
14129 PSI 1•24
I • I_.=.= 47)) 4
I (1)
N141 111
MIN
0 dal OF
16326
REACTOR
- -00923
8 PS17
0131 41,
tPS16 I NT39
600 2985H 900
VU
2
1
OF REDIATOR
013
P510 14128 2265 600
1
OF SHUNT REACTOR
N725 /WIM
".1H
111111WilAr
immimo
NT24 1 U 017 D76
D1316? 1)815 .4- N112
PS9 1 1:
• D15
D814
14123 PS00 NT22 N119 1411434"36
8 13- P47 L.100
P LA\ VIEW
TYPICAL SPRAY SYST- V DRAW! F3R REACTC
APPENDIX-III (SHEET 2 OF 4)
TO TECHNICAL SPEOFICATION
FOR FIRE PROTECTION SYSTEM REV.-if
.111.111111.
O
O
LC)
ILEVAT \
TYR CAL SPRAY SYSTEM DRAW \C FOR REACTOR
APPENDIX-III (SHEET 3 OF 4)
TO TECHNICAL SPECIFICATION
FOR FIRE PROTECTION SYSTEM REV.-6
.44134
143312:
431 24 4.
72' 42342
*4 3 43
4529411)1
t .
0134
411251.
44 '13231.
4211 223644
45122
14247
101 1 4
PLAN VIEW
4_21 3, 92
4
.11135
• 42390 14199
0437 4t9116 4015 *1 14
----- • ..._,..,....--
4e----- "-*
4-
,414 1,
ari
1
1
40'",,6 4:i.,2,
4 4
2,
C. 4+ -41,_ _ —) -----.)
ELEVATION
TYPICAL SPRAY SYSTEM DRAWING FOR ICT
•
Appendix-IV
Sheet 1 of 13
1.6.1 Body 24
1.6.2 Seat 16
1. Pumps KBL/M&P/B&C
(Horizontal Centrifugal)
5 Batteries EXIDE/AMCO/AMARA
6. M.S./G.I Pipes JINDAL/PRAKASH/
SAIL/ LLOYD METALS &
ENGINEERS LTD.
7. C. I. Valves H. Sarkar/Venus/Kalpana
(Gate & Check)
TABLE OF CONTENTS
1 General 1
2 Air Conditioning System for Control Room Building 1
3 Air conditioning system for switchyard panel rooms. 6
1 GENERAL
1.2 Air conditioning units for control room building shall be set to
maintain the inside DBT at 24 o C ± 2oC and the air conditioning
system for switch-yard panel rooms shall be set to maintain DBT
inside switch-yard panel rooms below 24oC.
1.3 Controllers shall be provided in Control room and Battery room for
controlling and monitoring the AC units in these rooms as detailed in
clause no.2.3.4.
2.2 Scope
2.2.3 Required number of High wall type split AC units of 2TR capacity
each complete with air cooled outdoor condensing unit having
hermetically sealed compressor and high wall type indoor evaporator
unit with cordless remote controller.
2.2.5 First charge of refrigerant and oil shall be supplied with the unit.
2.2.7 Local start/stop facility for local starting/ stopping of all electrical
equipment/ drives.
2.2.8 All instruments and local control panels alongwith controls and
interlock arrangements and accessories as required for safe and
trouble free operation of the units.
2.2.9 PVC drain piping from the indoor units upto the nearest drain point.
2.2.10 Supply and erection of Power and control cable and earthing.
2.3.1.2 Cabinet
The cabinets housing the components of indoor units & outdoor units
shall be of heavy gauge sheet steel and suitable for floor
mounting/mounting from ceiling. The access panels shall be of easily
removable type. The entire casing shall be lined with 25mm thick
insulation of totally flame proof type. Suitable drain connection shall
be provided for removal of condensate collected inside a tray under
cooling coil.
2.3.1.3 Compressor
2.3.1.4 Condenser
The air handling fan shall be centrifugal type complete with belt drive
and electric motor.
2.3.1.6 Filter
2.3.1.12 Cooling capacity of 8.5TR unit shall not be less than 102000 btu/hr.
2.3.2.2 Indoor units shall be of 4-way, ceiling mounted cassette type. The
indoor unit shall be compact and shall have elegant appearance.
They shall have low noise centrifugal blowers driven by suitable
motors and copper tube aluminium finned cooling coils. Removable
and washable polypropylene filters shall be provided. They shall be
complete with multi function cordless remote control unit with special
features like programmable timer, sleep mode etc.
2.3.2.3 Cooling capacity of 3TR AC units shall not be less than 36000btu/hr.
2.3.3.1 The split AC units shall be complete with indoor evaporator unit,
outdoor condensing units and cordless remote control units.
2.3.3.3 The indoor units shall be high wall type. The indoor unit shall be
compact and shall have elegant appearance. They shall have low
noise centrifugal blowers driven by suitable motors and copper tube
aluminium finned cooling coils. Removable and washable
polypropylene filters shall be provided. They shall be complete with
multi function cordless remote control unit with special features like
programmable timer, sleep mode and soft dry mode etc.
2.3.3.4 Cooling capacity of 2TR AC units shall not be less than 22000btu/hr.
and shall have energy efficiency rating of 3star or above.
2.3.4 Controllers shall be provided in Control room and Battery room, one
controller for each room, to control and monitoring of AC units and
shall have the following facilities;
2.4 The Split AC units shall be of Carrier, Voltas, Blue Star, Hitachi,
Daikin, LG, National, O’General or Samsung make.
2.5 Warranty
All compressors shall have minimum 5 years Warranty from the date
3.3 Number and rating of the units for each panel room shall be as
follows:
3.4.1 Each AC unit shall be complete with air cooled condensing unit with
scroll compressor, direct expansion type evapourating unit and
microprocessor controller. AC units shall be provided with free
cooling arrangement. In free cooling mode, the refrigerant cycle of
AC unit shall be switched off and outside air (after filtration) shall be
circulated inside the conditioned space through the operation of
dampers provided with suitable sensors. This mode shall come into
operation in the following conditions;
3.4.3 Packaged AC units with free cooling shall be designed for high
sensitive cooling with sensible heat factor of 90% or above.
3.4.5 The AC units shall be mounted on the wall and the maintenance of
unit shall be possible from outside the Switchyard panel room.
The compressor shall be very reliable, trouble free and long life i.e.
hermetically sealed Scroll type of reputed make suitable for
continuous operation. Compressor should be installed on vibration
isolated mountings or manufacturer’s recommended approved
mounting. Valve shall be provided for charging/topping up of
refrigerant. The bidder shall furnish details of their compressor
indicating the MTBF, life of compressor and continuous run time of
compressor without failure. The contractor shall also furnish details of
all accessories i.e. refrigeration system, evaporator coil, condenser
coil, evaporator blower, filter, cabinet, indoor supply and return grill
etc. during detailed engineering.
3.5 Warranty
All compressors shall have minimum 5 years Warranty from the date
of commissioning
CONTENTS
1.0 GENERAL
- Aluminium Tube
- Spacers
- Cabling material
- Other items
The insulators for suspension and tension strings shall conform to IEC-60383
and long rod insulators shall conform to IEC-60433. Insulator hardware shall
conform to IS:2486. Composite long rod polymer insulator shall conform to
IEC:61109. Further, the contractor shall supply insulators as per details
mentioned below:
a) Suspension and tension insulators shall be wet process porcelain with ball
and socket connection. Insulators shall be interchangeable and shall be
suitable for forming either suspension or tension strings. Each insulator
shall have rated strength, manufacturer‘s logo, month & year of
manufacturing markings on porcelain printed and applied before firing.
c) Glazing of the porcelain shall be of uniform brown colour, free from blisters,
burrs and other similar defects.
It shall be made of toughened glass. Glass used for the shells shall be sound,
free from defects, flows bubbles, inclusions, etc and be of uniform toughness
over its entire surface. All exposed glass surfaces shall be smooth.
2.1.2.1 When operating at normal rated voltage, there shall be no electric discharge
between conductor and insulator which would cause corrosion or damage to
conductors or insulators by the formation of substances due to chemical action.
2.1.2.2 The design of the insulator shall be such that stresses due to expansion and
contraction in any part of the insulator shall not lead to deterioration. All ferrous
parts shall be hot dip galvanized in accordance with the latest edition of IS: 2629.
The zinc used for galvanizing shall be of grade Zn-99.95 as per IS-209. The zinc
coating shall be uniform, adherent, smooth, reasonably bright, continuous and
free from imperfections such as flux, ash, rust stains bulky white deposits and
blisters.
2.1.2.3 Contractor shall make available data on all the essential features of design
including the method of assembly of discs and metal parts, number of discs per
insulator string, the manner in which mechanical stresses are transmitted through
discs to adjacent parts, provision for meeting expansion stresses, results of
corona and thermal shock tests, recommended working strength and any special
design or arrangement employed to increase life under service conditions.
2.1.3.1 Clamps for insulator strings and Corona Control rings shall be of aluminium alloy
as stipulated for clamps and connectors.
2.1.3.2 Insulator hardware shall be of forged steel. Malleable cast iron shall not be
accepted except for insulator disc cap. The surface of hardware must be clean,
smooth, without cuts, abrasion or projections. No part shall be subjected to
excessive localized pressure. The metal parts shall not produce any noise
generating corona under operating conditions.
2.1.3.3 The tension Insulator hardware assembly shall be designed for minimum 21000
kg tensile load for 765kV and minimum 12000 kg tensile load for hardware
assembly below 765kV. Earth wire tension clamp shall be designed for minimum
1000 kg tensile load with a factor of safety of two (2).
2.1.3.4 The tension string assemblies shall be supplied alongwith suitable turn buckle.
Sag compensation springs if required may also be provided.
2.2 Tests
In accordance with the stipulations of the specification, the suspension and
tension strings, insulator and hardware shall be subjected to the following type
tests, acceptance tests and routine tests:
2.2.1 Type Tests on Insulator Strings: The test reports for following type tests shall
be submitted for approval as per clause 9.0 of Section - GTR.
a) Power frequency voltage withstand test with corona control rings (if
applicable) under wet condition as per IEC- 60383.
b) Switching surge voltage withstand test [400 kV and above class only]
under wet condition as per IEC-60383.
c) Lightning Impulse voltage withstand test with corona control rings under
dry condition as per IEC-60383
d) Voltage distribution test (Dry) [applicable for disc insulator string only]
The voltage across each insulator unit shall be measured by sphere gap
method. The result obtained shall be converted into percentage. The
voltage across any disc shall not exceed 6.5% for 765 kV suspension and
tension insulator strings, 9% and 10% for 400KV suspension string and
tension insulator string respectively, 13% for 220KV suspension and
tension insulator strings, 20% and 22% for 132KV suspension and
tension insulator strings respectively.
e) Corona Extinction Voltage test (Dry) [220kV and above class only]
Under the conditions as specified under (e) above the insulator string
alongwith complete hardware fittings shall have a radio interference
voltage as specified in clause 2.3.2 of this section. The test procedure
shall be in accordance with IS 8263/IEC 60437.
g) Mechanical strength test: The test shall be carried out as per following
procedure.
Type test report for Thermal Mechanical Performance tests (applicable for
porcelain type insulators) as per IEC-60575, Clause 3 shall be submitted for
approval as per clause 9.2 of Section - GTR.
g) Test on locking device for ball and socket coupling as per IEC-60372(2).
h) Porosity test as per IEC- 60383 (Applicable only for porcelain insulators).
The load shall be so applied that the component is stressed in the same
way as it would be in actual service and the procedure as given in
2.2.1.(g) above should be followed.
g) Test on locking devices for ball and socket coupling as per IEC -60372(2).
a) Chemical analysis of zinc used for galvanising: Samples taken from the
zinc ingot shall be chemically analyzed as per IS: 209. The purity of zinc
shall not be less than 99.95%.
Samples taken from the zinc ingot shall be chemically analyzed as per
IS:209. The purity of zinc shall not be less than 99.95%
Double insulator strings for 765kV, 400kV, 220kV and single insulator strings for
132 kV systems shall be used.
V-type polymer insulator string shall be used for 765kV system and single
suspension polymer insulator string shall be used for 400kV, 220kV & 132 kV
systems.
Bidder shall offer composite long rod polymer insulators with suitable hardware
fittings.
2.4.1.1 Insulators shall have sheds of the ―open aerodynamic profile without any under
ribs‖ with good self-cleaning properties. Insulator shed profile, spacing projection
etc. shall be strictly in accordance with the recommendation of IEC-60815.
2.4.1.2 Ball and socket shall be 20mm designation for 120kN & 24mm designation for
210kN Insulators in accordance with the standard dimensions stated in
IEC:60120/ IS:2486 (Part-II). Insulators shall be interchangeable and shall be
suitable for forming either suspension or tension strings. Each insulator shall
have laser markings on housings for manufacturer‘s name, month & year of
manufacturing, rated strength markings on each composite insulator rod unit. No
negative tolerance shall be applicable to creepage distance of composite
insulators
2.4.1.3 All ferrous parts shall be hot dip galvanized as per Section-GTR with
minimum weight of zinc coating as 610 gm/sq.m for normal area and 900
gm/sq.m for coastal area as specified in Section-Project.
2.4.2 Material
2.4.2.1 Core
It shall be a glass-fiber reinforced (FRP) epoxy resin rod of high strength. The rod
shall be resistant to hydrolysis. The rod shall be of electrical grade corrosion
resistant (ECR), boron free glass and shall exhibit both high electrical integrity
and high resistance to acid corrosion.
End fittings transmit the mechanical load to the core. They shall be made of
malleable cast iron/ spheroidal graphite or forged steel. They shall be connected
to the rod by means of a controlled compression technique. The manufacturer
shall have in-process Acoustic emission arrangement or some other
arrangement to ensure that there is no damage to the core during crimping. This
verification shall be in-process and done on each insulator. The system of
attachment of end fitting to the rod shall provide superior sealing performance
between housing and metal connection. The gap between fitting and sheath shall
be sealed by a flexible silicone rubber compound. The sealing shall stick to both
housing and metal end fitting. The sealing must be humidity proof and durable
with time.
End fittings shall have suitable provisions for fixing grading rings at the correct
position as per design requirements.
Grading rings shall be used at both ends of each composite insulator unit for
reducing the voltage gradient on and within the insulator and to reduce TV noise
to acceptable levels. The size and placement of the metallic grading rings shall
be designed to eliminate dry band arcing/corona cutting/ exceeding of
permissible electrical stress of material. The insulator supplier shall furnish
design calculations using appropriate electric field software showing electric field
at surface of housing, inside housing & core and at the interface of housing and
metal fittings with the proposed placement and design of corona rings. Grading
rings shall be capable of installation and removal with hot line tools without
disassembling any other part of the insulator assembly.
The design & supply of grading rings shall be in the scope of the composite
insulator supplier.
2.4.3 Tests
The test reports for following type tests on long rod units, components, materials
or complete strings shall be submitted for approval as per clause 9.2 of Section -
GTR.
2.4.3.1.1 On the complete composite Long Rod Polymer Insulator String with
Hardware Fittings:-
a) Power frequency voltage withstand test with corona control rings/grading ring
and arcing horns (if provided) under wet condition as per IEC:60383-1993.
b) Switching surge voltage withstand test under wet condition as per IEC:60383-
1993.
d) Corona and RIV test under dry condition. [132kV and above class only]
The sample assembly when subjected to power frequency voltage shall have
a corona extinction voltage as specified in clause 2.3.2 of this section There
shall be no evidence of Corona on any part of the sample. The atmospheric
condition during testing shall be recorded and the test results shall be
accordingly corrected with suitable correction factor as stipulated in IEC
60383.
e) Mechanical Strength test: The test shall be carried out as per following
procedure.
The complete insulator string alongwith its hardware fitting excluding arcing
horn, corona control ring, grading ring, tension/suspension clamps shall be
subjected to a load equal to 50% of the specified minimum ultimate tensile
strength (UTS) which shall be increased at a steady rate to 67% of the
minimum UTS specified. The load shall be held for five minutes and then
removed. After removal of the load, the string components shall not show any
visual deformation and it shall be possible to dismantle them by hand. Hand
tools may be used to remove cotter pins and loosen the nuts initially. The
string shall then be reassembled and loaded to 50% of UTS and the load
shall be further increased at a steady rate till the specified minimum UTS and
held for one minute. No fracture should occur during this period. The applied
load shall then be increased until the failing load is reached and the value
recorded.
f) Salt-fog pollution withstand test as per IEC: 60507. The salinity level for
composite long rod insulators shall be 160 Kg/m3 NaCl.
c) Damage limit proof test and test of tightness of interface between end firings
and insulator housing as per IEC: 61109-2008
The test arrangement shall be according to Damage limit proof test with
simultaneous application of 1N-HNO3 acid directly in contact with naked FRP
rod. The contact length of acid shall not be less than 40mm and thickness
around the core not less than 10mm.The rod shall withstand 80% of SML for
96 hours.
Minimum content of silicone shall be 30% and the same shall be verified
through FT-IR spectroscopy & TGA analysis or any other approved/
acceptable method.
3. Immediately after the corona treatment, spray the surface with water and
record the HC classification. The surface should be hydrophilic, with an HC
value of 6 or 7. If not, dry the surface and repeat the corona treatment for a
longer time until an HC of 6 or 7 is obtained. Dry the sample surface.
n) Torsion test
In the event of failure of the sample to satisfy the acceptance test(s) specified in
2.4.3.2 above, the re-test procedure shall be as per IEC 61109.
3.1.1 The Conductor shall conform to IEC: 61089/IS: 398 (Part V) - 1992 except where
otherwise specified herein.
The contractor shall supply the conductor as per the standard guaranteed technical
particulars enclosed in Annexure-E of the technical specification, Section –
Switchyard Erection and separate approval for guaranteed technical particulars is
not required during detailed engineering.
3.2.1 The Conductor shall conform to IEC: 61089/IS: 398 (Part V) - 1992 except where
otherwise specified herein.
3.2.2 The details of the ACSR Bersimis, ACSR Moose, ACSR Zebra and ACSR Panther
conductors shall be as per the standard guaranteed technical particulars enclosed in
Annexure-E of the technical specification, Section – Switchyard Erection and
separate approval for guaranteed technical particulars is not required during
detailed engineering.
3.3 Workmanship
3.3.1 The finished conductor shall be smooth, compact, uniform and free from all
imperfections including kinks (protrusion of wires), wire cross over, over riding,
looseness (wire being dislocated by finger/hand pressure and/or unusual bangle
noise on tapping), material inclusions, white rust, powder formation or black spot (on
account of reaction with trapped rain water etc.), dirt, grit etc.
3.3.2 All the Aluminium and steel strands shall be smooth, uniform and free from all
imperfections, such as spills and splits, diemarks, scratches, abrasions, etc., after
drawing.
3.3.3 The steel strands shall be hot dip galvanised and shall have a minimum zinc coating
as indicated in the guaranteed technical particulars. The zinc coating shall be
smooth, continuous and of uniform thickness, free from imperfections and shall
withstand minimum three dips in standard Preece test. The steel wire rods shall be of
such quality and purity that, when drawn to the size of the strands specified and
coated with zinc, the finished strands and the individual wires shall be of uniform
quality and have the same properties and characteristics as prescribed in IEC:
60888.
3.3.4 The steel strands shall be preformed and post formed in order to prevent spreading
of strands in the event of cutting of composite core wire. Care shall be taken to
avoid, damages to galvanisation during pre-forming and post-forming operation.
3.4.1.1 During stranding, no aluminium wire welds shall be made for the purpose of
achieving the required conductor length.
3.4.1.2 No joints shall be permitted in the individual wires in the outer most layer of the
finished conductor. However joints are permitted in the inner layer of the conductor
unavoidably broken during stranding, provided such breaks are not associated with
either inherently defective wire or with the use of short lengths of aluminium wires.
Such joints shall not be more than four (4) per conductor length and shall not be
closer than 15 meters from joint in the same wire or in any other aluminium wire of
the completed conductor.
3.4.1.3 Joints shall be made by cold pressure butt welding and shall withstand a stress of
not less than the breaking strength of individual strand guaranteed.
3.5 Tolerances
3.6 Materials
3.6.1 Aluminium
The aluminium strands shall be hard drawn from electrolytic aluminium rods having
purity not less than 99.5% and a copper content not exceeding 0.04%. They shall
have the same properties and characteristics as prescribed in IEC:60889.
3.6.2 Steel
The steel wire strands shall be drawn from high carbon steel wire rods produced by
either the acid or the basic open-hearth process, the electric furnace process, or the
basic oxygen process and shall conform to the chemical composition indicated in the
guaranteed technical particulars.
The Steel wire strands shall have the same properties and characteristics as
prescribed for regular strength steel wire in IEC: 60888.
3.6.3 Zinc
The zinc used for galvanising shall be electrolytic High Grade Zinc of 99.95% purity.
It shall conform to and satisfy all the requirements of IS:209 -1979.
3.7.1 The conductor shall be supplied as required. No joint shall be allowed within a single
span of stringing, jumpers and equipment interconnection.
3.8 Tests:
3.8.1 The following type, acceptance & routine tests and tests during manufacturing shall
be carried out on the conductor.
In accordance with the stipulation of specification, the following type tests reports of
the conductor shall be submitted for approval as per clause 9.2 of Section -GTR.
b) Dimensional check on )
steel and aluminium )
strands )
)
c) Check for lay ratios ) -do-
of various layers )
)
d) Galvanising test on steel )
strands )
)
e) Torsion and Elongation )
test on steel strands )
All the above tests except test mentioned at (a) shall be carried out on aluminium
and steel strands after stranding only.
a) Chemical analysis of )
zinc used for galvanising )
)
b) Chemical analysis of )
aluminium used for ) As per Annexure - A
making aluminium strands )
)
c) Chemical analysis of )
steel used for making )
steel strands )
4.2 Workmanship
4.2.1 All steel strands shall be smooth, uniform and free from all imperfections, such as
spills and splits, die marks, scratches, abrasions and kinks after drawing and also
after stranding.
4.2.2 The finished material shall have minimum brittleness as it will be subjected to
appreciable vibration while in use.
4.2.3 The steel strands shall be hot dip qalvanised and shall have minimum Zinc coating
after stranding, as stipulated in guaranteed technical particulars attached with. The
zinc coating shall be smooth, continuous, of uniform thickness, free from
imperfections. The steel wire rod shall be of such quality and purity that, when drawn
to the size of the strands specified and coated with zinc, the finished strands shall be
of uniform quality and have the same properties and characteristics as prescribed in
ASTM designation B498-74.
4.2.4 The steel strands shall be preformed and post formed in order to prevent spreading
of strands while cutting of composite earth wire. Care shall be taken to avoid damage
to galvanisation during preforming and postforming operation.
4.2.5 To avoid susceptibility towards wet storage stains (white rust), the finished material
shall be provided with a protective coating of boiled linseed oil.
4.8.1 The following type, routine & acceptance tests and tests during manufacturing shall
be carried out on the earthwire.
In accordance with the stipulation of specification, the following type tests reports
of the earthwire shall be submitted for approval as per clause 9.2 of Section -
GTR.
a) UTS test )
) As per Annexure - B
b) DC resistance test )
e) Torsion test )
f) Elongation test )
)
g) Wrap test )
h) DC resistance test )
) IS:398 (Part-III) - 1976
i) Breaking load test )
)
j) Chemical Analysis of )
steel
5.1 General
The contractor shall supply the aluminium tubes as per the standard guaranteed
technical particulars enclosed in Annexure-E of this section and separate
approval for guaranteed technical particulars is not required during detailed
engineering.
5.2.1 For outer diameter (OD) & thickness of the tube there shall not be any negative
tolerance, other requirements being as per IS: 2678 and IS: 2673.
5.2.2 The welding of aluminium tube shall be done by the qualified welders duly
approved by the Employer.
5.3 Tests
6.1 General
All conductors burried in earth and concrete shall be of mild steel. All conductors
above ground level and earthing leads shall be of galvanised steel, except for
cable trench earthing. The minimum sizes of earthing conductor to be used are
as indicated in clause 9.4 of this Section.
b) The minimum weight of the zinc coating shall be 610 gm/sq.m for normal
area and 900 gm/sq.m for coastal area as specified in Section-
Project and minimum thickness shall be 85 microns.
6.3 Tests
7.0 SPACERS
7.1 General
Spacers shall conform to IS: 10162. The spacers are to be located at a suitable
spacing to limit the short circuit forces as per IEC -60865. Wherever Employer‘s
765kV, 400 kV, 220kV & 132kV standard gantry structures are being used, the
spacer span(s) for different conductor / span configurations and corresponding
short circuit forces shall be as per Annexure-D. For strung buses, flexible type
spacers shall be used whereas for jumpers and other connections rigid type
spacers shall be used. All quad/twin conductors between equipments/ bus shall
be provided with at least one spacer.
Wherever Employer‘s 765kV, 400 kV, 220kV & 132kV standard gantry structures
are not being used, necessary spacer span calculation shall be provided by the
contractor during detailed engineering for the approval of Employer.
7.2.1 No magnetic material shall be used in the fabrication of spacers except for GI
bolts and nuts.
7.2.2 Spacer design shall be made to take care of fixing and removing during
installation and maintenance.
7.2.3 The design of the spacers shall be such that the conductor does not come in
contact with any sharp edge.
7.3 Tests
Each type of spacers shall be subjected to the following type tests, acceptance
tests and routine tests:
7.3.1 Type Tests: Following type test reports shall be submitted for approval as
per clause 9.2 of Section - GTR.
The sample shall be installed on test span of twin conductor bundle string
or quadruple conductor bundle string (as applicable) at a tension of 44.2
kN. One of the clamps of the sample when subjected to a longitudinal
pull of 2.5 kN parallel to the axis of the conductor shall not slip on the
conductor. The permanent displacement between the conductor and the
clamp of sample measured after removal of the load shall not exceed 1.0
mm. Similar tests shall be performed on the other clamps of the same
sample.
b) Fault current test as per Cl 5.14.2 of IS: 10162. Alternately, the same can
be carried by simulated short circuit method for which compressive forces
shall be based on IEC-60865.
This test shall be performed on 765 kV, 400 kV and 220 kV spacers as
per procedure mentioned at Annexure - C, Minimum Corona Extinction
voltage shall be as per clause 2.3.2.
f) Tension Test
h) Compression test
i) Galvanising test
a) Visual examination
b) Dimensional verification
c) Movement test
g) Compression test
h) Tension test
i) Galvanising test
The UTS of the retaining rods shall be measured. It shall not be less than
35 kg/Sq. mm.
a) Visual examination
b) Dimensional verification
The post insulators shall conform in general to latest IS: 2544, IEC-60168, IEC
60273 and IEC-60815.
8.1.1 Bus Post insulators shall consist of a porcelain part permanently secured in a
metal base to be mounted on the supporting structures. They shall be capable of
being mounted upright. They shall be designed to withstand any shocks to which
they may be subjected to by the operation of the associated equipment. Only
solid core insulators will be acceptable.
8.1.2 Porcelain used shall be homogeneous, free from lamination, cavities and other
flaws or imperfections that might affect the mechanical or dielectric quality and
shall be thoroughly vitrified, tough and impervious to moisture.
8.1.3 Glazing of the porcelain shall be of uniform brown in colour, free from blisters,
burrs and other similar defects.
8.1.4 The insulator shall have alternate long and short sheds with aerodynamic profile,
The shed profile shall also meet the requirements of IEC-60815 for the specified
pollution level.
8.1.5 When operating at normal rated voltage there shall be no electric discharge
between conductor and insulators which would cause corrosion or damage to
conductors or insulators by the formation of substance produced by chemical
action.
8.1.6 The design of the insulators shall be such that stresses due to expansion and
contraction in any part of the insulator shall not lead to deterioration.
8.1.7 All ferrous parts shall be hot dip galvanised in accordance with the latest edition
of IS: 2633, & IS: 2629. The zinc used for galvanising shall be grade Zn 99.95 as
per IS: 209. The zinc coating shall be uniform, adherent, smooth, reasonably
bright, continuous and free from imperfections such as flux ash, rust stains, bulky
white deposits and blisters. The metal parts shall not produce any noise
generating corona under the operating conditions.
8.1.8 a) Every bolt shall be provided with a hop dip galvanised steel washer under
the nut so that part of the threaded portion of the bolts is within the
thickness of the parts bolted together.
b) Flat washer shall be circular of a diameter 2.5 times that of bolt and of
suitable thickness. Where bolt heads/nuts bear upon the beveled
surfaces they shall be provided with square tapered washers of suitable
thickness to afford a seating square with the axis of the bolt.
c) All bolts and nuts shall be of steel with well formed hexagonal heads
forged from the solid and shall be hot dip galvanised. The nuts shall be
good fit on the bolts and two clear threads shall show through the nut
when it has been finally tightened up.
8.1.9 Bidder shall furnish drawings for the essential design features of assembly of
shells and metal parts, and number of shells per insulator.
8.2 Tests
In accordance with the stipulations of the specification, the post insulators shall
be subjected to type, acceptance, sample and routine tests as per IEC-60168.
8.2.1 In accordance with the stipulation of specification, the following type tests
reports of the post insulators shall be submitted for approval as per clause 9.2 of
Section - GTR.
c) Switching impulse test (wet) (For 420 kV and above class Insulator only)
c) The bending test shall be carried out at 50% minimum cantilever strength
load in four directions as a routine test and at 100% minimum cantilever
strength load in four directions as an acceptance test.
d) Acceptance norms for visual defects allowed at site and also at works
shall be agreed in the Quality plan.
h) Cantilever Strength
(i) Total minimum cantilever 800 800 800 600
strength (Kg)
i) Minimum torsional As per As per As per As per
moment IEC- IEC- IEC- IEC-
60273 60273 60273 60273
j) Total height of insulator 5700 3650 2300 1500
(mm)
k) P.C.D Top (mm) 225 127 127 127
Bottom (mm) 325 300 254 254
l) No. of bolts
Top 4 4 4 4
Bottom 8 8 8 8
m) Diameter of bolt/holes
(mm)
Top M16 M16 M16 M16
Bottom dia 18 18 18 18
n) Pollution level as per Heavy(III) Heavy(III) Heavy(III) Heavy(III)
IEC-60815
o) Minimum total creepage 20000 10500 6125 3165
distance for Heavy
Pollution (mm)
8.3.1 If corona extinction voltage is to be achieved with the help of corona ring or any
other similar device, the same shall be deemed to be included in the scope of the
Contractor. Aluminium used for corona ring shall be of grade 63401 or 19501
conforming to IS:5082.
9.0 EARTHING
9.1 The earthing shall be done in accordance with requirements given hereunder and
drawing titled ‗Earthing Details‘ enclosed with the specification. The spacing for
the main earthmat shall be provided by the Employer and the earthmat layout
drawings shall be prepared by the contractor based on the spacing provided by
the Employer. The resistivity of the stone for spreading over the ground shall be
considered as 3000 ohm-m under wet condition. The resistivity measurement of
stone (to be used for stone spreading) shall also be done by the Contractor to
confirm the minimum resistivity value of stone considered in earth mat design.
For measurement purpose, one sample of stones from each source (in case
stones are supplied from more than one source) shall be used. The main
earthmat shall be laid in the switchyard area in accordance with the approved
earthmat layout.
9.2 Neutral points of systems of different voltages, metallic enclosures and frame
works associated with all current carrying equipments and extraneous metal
works associated with electric system shall be connected to a single earthing
system unless stipulated otherwise.
9.3 Earthing and lightning protection system installation shall be in strict accordance
with the latest editions of Indian Electricity Rules, relevant Indian Standards and
Codes of practice and Regulations existing in the locality where the system is
installed.
c) CEA Safety Regulations 2010 & Indian Electricity Act 2003 with latest
amendments.
9.5.4 Earthing conductors or leads along their run on cable trench, ladder, walls etc.
shall be supported by suitable welding/cleating at intervals of 750 mm. Wherever
it passes through walls, floors etc., PVC sleeves shall be provided for the
passage of the conductor and both ends of the sleeve shall be sealed to prevent
the passage of water through the sleeves.
9.5.5 Earthing conductor around the building shall be buried in earth at a minimum
distance of 1500 mm from the outer boundary of the building.
9.5.6 Earthing conductors crossing the road shall be laid 300mm below road or at
greater depth to suit the site conditions.
9.5.7 Earthing conductors embeded in the concrete shall have approximately 50mm
concrete cover.
The contractor shall provide galvanised steel earth wire at 8m level in the
area where three interconnection levels (equipment interconnection, bus &
jack bus interconnection) are present at 765kV switchyard to limit electric
and magnetic field within permissible limit.
9.7.2 Whether specifically shown in drawings or not, steel/RCC columns, metallic stairs
etc. shall be connected to the nearby earthing grid conductor by two earthing
leads. Electrical continuity shall be ensured by bonding different sections of
hand-rails and metallic stairs.
9.7.3 Metallic pipes, conduits and cable tray sections for cable installation shall be
bonded to ensure electrical continuity and connected to earthing conductors at
regular interval. Apart from intermediate connections, beginning points shall also
be connected to earthing system.
9.7.5 Wherever earthing conductor crosses or runs along metallic structures such as
gas, water, steam conduits, etc. and steel reinforcement in concrete it shall be
bonded to the same.
9.7.6 Light poles, junction boxes on the poles, cable and cable boxes/glands, lockout
switches etc. shall be connected to the earthing conductor running alongwith the
supply cable which in turn shall be connected to earthing grid conductor at a
minimum two points whether specifically shown or not.
9.7.7 Railway tracks within switchyard area shall be earthed at a spacing of 30m and
also at both ends.
9.7.8 Earthing conductor shall be buried 2000 mm outside the switchyard fence. All the
gates and every alternate post of the fence shall be connected to earthing grid.
The stone spreading shall also be done 2000 mm outside switchyard fence. The
criterian for stone spreading shall be followed in line with requirement specified
elsewhere in the specification
9.7.9 Flexible earthing connectors shall be provided for the moving parts.
9.7.10 All lighting panels, junction boxes, receptacles fixtures, conduits etc. shall be
grounded in compliance with the provision of I.E. rules
9.7.11 A continuous ground conductor of 16 SWG GI wire shall be run all along each
conduit run. The conductor shall be connected to each panel ground bus. All
junction boxes, receptacles, switches, lighting fixtures etc. shall be connected to
this 16 SWG ground conductor.
9.7.12 50mm x 6mm MS flat shall run on the top tier and all along the cable trenches
and the same shall be welded to each of the racks. Further this flat shall be
earthed at both ends and at an interval of 30 mtrs. The M.S. flat shall be finally
painted with two coats of Red oxide primer and two coats of Zinc riched enamel
paint.
9.7.13 One number 40 mm dia, 3000 mm long MS earth electrode with test link, CI
frame and cover shall be provided to connect each down conductor of surge
arresters, capacitive voltage transformers, lightning masts and towers with peak.
9.8 Jointing
9.8.1 Earthing connections with equipment earthing pads shall be bolted type. Contact
surfaces shall be free from scale, paint, enamel, grease, rust or dirt. Two bolts
shall be provided for making each connection. Equipment bolted connections,
after being checked and tested, shall be painted with anti corrosive
paint/compound.
9.8.2 Connection between equipment earthing lead and main earthing conductors and
between main earthing conductors shall be welded type. For rust protections, the
welds should be treated with red oxide primer and afterwards coated with two
layers bitumen compound to prevent corrosion.
9.8.3 Steel to copper connections shall be brazed type and shall be treated to prevent
moisture ingression.
9.8.4 Resistance of the joint shall not be more than the resistance of the equivalent
length of the conductor.
9.8.5 All ground connections shall be made by electric arc welding. All welded joints
shall be allowed to cool down gradually to atmospheric temperature before put-
ting any load on it. Artificial cooling shall not be allowed.
9.8.6 All arc welding with large dia. conductors shall be done with low hydrogen
content electrodes.
9.8.7 The 75x12mm GS flat shall be clamped with the equipment support structures at
1000mm interval.
Metallic sheaths and armour of all multi core power cables shall be earthed at
both equipment and switchgear end. Sheath and armour of single core power
cables shall be earthed at switchgear end only.
9.10.1 Each earthing lead from the neutral of the power transformer/Reactor shall be
directly connected to two numbers pipe electrodes in treated earth pit (as per IS)
which in turn, shall be buried in Cement Concrete pit with a ISI marked cast iron
cover hinged to a cast iron frame to have an access to the joints. All accessories
associated with transformer/reactor like cooling banks, radiators etc. shall be
connected to the earthing grid at minimum two points.
9.10.2 Earthing terminal of each lightning arrester & capacitor voltage transformer shall
be directly connected to rod earth electrode which in turn, shall be connected to
station earthing grid.
9.10.3 Auxiliary earthing mat comprising of 40mm dia M.S. rods closely spaced (300
mm x 300 mm) conductors shall be provided at depth of 300mm from ground
level below the operating handles of the M.O.M. Box of the isolators. M.O.M.
boxes shall be directly connected to the auxiliary earthing mat. Flexible copper
braid connection to be provided between MOM box and GI flat to take care of soil
sagging. The size of auxiliary earthing mat shall be of 1500mmx1500mm size for
220kV and above voltage class isolators and 900mmx900mm size for 132kV and
below voltage class isolators. Factory welded auxiliary earthmat is preferable.
9.11.1 The scope covers supply and laying of insulating mats of ―class A‖ conforming to
IS: 15652-2006.
9.11.2 These insulating mats shall be laid in front of all floor mounted AC and DC
switchboards and control & relay panels located in control room building/
Switchyard panel room.
9.11.3 The insulating mats shall be made of elastomer material free from any insertions
leading to deterioration of insulating properties. It shall be resistant to acid, oil
and low temperature.
9.11.4 Upper surface of the insulating mats shall have small aberration (rough surface
without edges) to avoid slippery effects while the lower surface shall be plain or
could be finished slip resistant without affecting adversely the dielectric property
of the mat.
9.11.6 Width of insulating mats shall generally be of 1.5 meters or as per site
requirements. Length shall be supplied as per site requirements.
The brief description of the bus switching scheme, bus bar layout and equipment
connection to be adopted are indicated elsewhere in the specification. The bus
bar arrangements are shown in electrical layout drawings enclosed with the bid
documents.
10.1 The Contractor shall furnish supporting calculations where the design is to be
done by the contractor for the bus bars/conductors to show adequacy of design
parameters for:
e) Short circuit forces in bundle conductor and spacer location for each span
of ACSR conductor stringing as per layout drawings.
10.1.1 The welds in the aluminium tubes shall be kept to the minimum and there shall
not be more than one weld per span. The procedure and details of welding shall
be subject to Employer‘s approval. Material for welding sleeve shall be same as
that of Aluminium tube. Welding sleeve shall be of 600mm length
10.1.2 Corona bells shall be provided wherever the bus extends beyond the clamps and
on free ends, for sealing the ends of the tubular conductor against rain and
moisture and to reduce the electrostatic discharge loss at the end points. There
shall be a small drain hole in the corona bell. The material of Corona bell shall be
Aluminium alloy similar to that of clamps & connectors.
10.1.3 To minimise the vibrations in the aluminium tubes, damping conductor shall be
provided inside the aluminium tubes. For this purpose, the cut pieces of ACSR
conductor which otherwise are considered wastages, shall be used as damping
conductor.
10.1.4 Details of past experience of the persons proposed to be employed for
Aluminium tube welding and the test reports of the welded pieces to prove the
electrical and mechanical characteristics shall also be furnished to Employer.
Welding at site shall be done by adopting a qualified procedure and employing
qualified welders as per ASME-Section IX.
10.1.5 Joints shall be avoided in strung bus to avoid joint failure / hot spots and
hardwares to be designed accordingly.
11.1 The disposition of various bay equipments shall be as per single line diagrams
and layout drawings.
11.2 Bay Marshalling Kiosk:-
Bay marshalling kiosk shall be fabricated from 304 grade stainless steel of
minimum thickness of 1.6mm. For other constructional details, technical
specification of section-GTR shall be referred. Further, for stainless steel
type bay marshaling kiosk, no painting is envisaged.
One no. of bay marshalling kiosk shall be provided for each 765 kV, 400 kV, 220
kV and 132 kV bay under present scope. For one and half breaker scheme, one
number bay marshalling kiosk shall be provided for each controlling feeder (Line/
transformer/ bus reactor etc) of the diameter and no bay marshalling kiosks are
required to be provided for the tie bays. In addition to the requirements specified
elsewhere in the specification, the bay marshalling kiosk shall have two distinct
compartments for the following purpose:-
(i) To receive two incoming 415V, 3 phase, 63Amps, AC supply with auto
changeover and MCB unit and distribute minimum nine (9) numbers
outgoing 415V, 3 phase, 16 Amps AC supplies controlled by MCB.
(ii) To distribute minimum two numbers outgoing 415V, 63Amps three phase
supplies to be controlled by MCB to be drawn from above 3 phase
incomers for supply to switchyard panel rooms.
(iv) Necessary Terminal Blocks for terminating cables from ACDB and
necessary heating circuits.
(i) To receive two incoming 415V, 3 phase, 63Amps, AC supply with auto
changeover and MCB unit and distribute minimum four (4) number
outgoing 415V, 3 phase, 16 Amps AC supplies controlled by MCB.
(ii) To distribute minimum six (6) numbers outgoing 240V, 10 Amps single
phase supplies to be controlled by MCB to be drawn from above 3 phase
incomers.
(iii) 100 nos. terminal blocks in vertical formation for interlocking facilities for
substations without automation system.
(iv) Necessary Terminal Blocks for terminating cables from ACDB and
necessary heating circuits.
11.3 Further, all Bay Marshalling Kiosks shall be erected such that a minimum height
of 1000mm is maintained between FGL & bottom of the marshalling box. Size of
Marshalling box shall be such that cables are properly terminated and wires are
dressed with provision of loop.
11.4.1 The name plate for the bays shall be provided by the contractor as per standard
drawing (Drawing no. C/ENG/STD/BAY NAME PLATE) enclosed in this technical
specification.
11.4.2 All the phases are to be identified by painting the structures Red, Yellow and
Blue by reflecting colour as per as built condition. Phase identification colour is to
be provided around the top of the structure with colour band of 100 mm width at
a height of approximately 2000mm from the finished ground level.
12.6 Lightning conductors shall not pass through or run inside G.I. conduits.
12.7 Lightning protection shall also be provided for various buildings like control
building, FFPH, Township buildings as per relevant standard.
13.1 All circuit breaker and isolator erection shall be done under the supervision of
equipment manufacturer and erection of all switchyard equipments shall be done
as per POWERGRID approved Field Quality Plan (FQP) and as per provision of
Technical Specification.
13.3 Muslin or leather cloth shall be used for cleaning the inside and outside of hollow
insulators.
13.4 All support insulators, circuit breaker interrupters and other fragile equipment
shall preferably be handled with cranes having suitable booms and handling
capacity.
13.5 Bending of Aluminium tube and compressed air piping if any should be done by a
bending machine and through cold bending only. Bending shall be such that
inner diameter of pipe is not reduced.
All welding done at site for equipment and structures, shall be painted with zinc
rich paint immediately to avoid corrosion.
13.6 Cutting of the pipes wherever required shall be such as to avoid flaring of the
ends. Hence only a proper pipe cutting tool shall be used. Hack saw shall not be
used.
instructions/instruction manual.
13.8 Handling equipment, sling ropes etc. should be tested periodically before
erection for strength.
13.9 The slings shall be of sufficient length to avoid any damage to insulator due to
excessive swing, scratching by sling ropes etc.
14.0 STORAGE
14.1 The Contractor shall provide and construct adequate storage shed as per the
Filed Quality Plan for proper storage of equipments, where sensitive equipments
shall be stored indoors. All equipments during storage shall be protected against
damage due to acts of nature or accidents. The storage instructions of the
equipment manufacturer/Employer shall be strictly adhered to. POWERGRID
approved Field Quality Plan shall be followed alongwith the provision of
Technical Specification for storage.
15.1.1 Each cable and conduit run shall be tagged with numbers that appear in the
cable and conduit schedule.
15.1.2 The tag shall be of aluminium with the number punched on it and securely
attached to the cable conduit by not less than two turns of 20 SWG GI wire
conforming to IS:280. Cable tags shall be of rectangular shape for power cables
and of circular shape for control cables.
15.1.3 Location of cables laid directly underground shall be clearly indicated with cable
route marker made of galvanised iron plate.
15.1.4 Location of underground cable joints shall be indicated with cable route marker
with an additional inscription ―Cable joints‖.
15.1.5 The cable route marker shall project 150 mm above ground and shall be spaced
at an interval of 30 meters and at every change in direction. They shall be
located on both sides of road and drain crossings as per relevant standard.
15.1.6 Cable tags shall be provided on all cables at each end (just before entering the
equipment enclosure), on both sides of a wall or floor crossing, on each
duct/conduit entry and at each end & turning point in cable tray/trench runs.
Cable tags shall be provided inside the switchgear, motor control centres, control
and relay panels etc., wherever required for cable identification, where a number
of cables enter together through a gland plate.
15.2.1 The Contractor shall provide embedded steel inserts on concrete floors/walls to
secure supports by welding to these inserts or available building steel structures.
15.2.2 The supports shall be fabricated from standard structural steel members.
15.2.3 Insert plates will be provided at an interval of 750 mm wherever cables are to be
supported without the use of cable trays, such as in trenches, while at all other
15.3.1 The termination and connection of cables shall be done strictly in accordance
with cable and termination kit manufacturer‘s instructions, drawing and/or as
directed by the Employer.
15.3.2 The work shall include all clamping, fittings, fixing, plumbing, soldering, drilling,
cutting, taping, heat shrinking (where applicable), connecting to cable terminal,
shorting and grounding as required to complete the job.
15.3.4 The equipment will be generally provided with undrilled gland plates for
cables/conduit entry. The Contractor shall be responsible for drilling of gland
plates, painting and touching up. Holes shall not be made by gas cutting.
15.3.6 The Contractor shall use printed ferrules for control cable cores at all
terminations, as instructed by the Employer. Each cable wire shall be identified
with a number and detailed cable schedule may be prepared indicating the wire
numbers.
15.3.7 Spare cores shall be similarly encaped & tagged with cable numbers and coiled
up with end cap.
15.3.8 All cable entry points shall be sealed and made vermin and dust proof. Unused
openings shall be effectively closed.
15.3.9 Double compression type nickel plated (coating thickness not less than 10
microns) brass cable glands shall be provided by the Contractor for all power and
control cables to provide dust and weather proof terminations.
15.3.10 The cable glands shall conform to BIS:6121. They shall comprise of heavy duty
brass casting, machine finished and nickel plated, to avoid corrosion and oxida-
tion. Rubber components used in cable glands shall be neoprene and of tested
quality. Cable glands shall be of approved make.
15.3.11 The cable glands shall also be suitable for dust proof and weather proof
termination.
15.3.12 If the cable-end box or terminal enclosure provided on the equipment is found
unsuitable and requires modification, the same shall be carried out by the
Contractor, as directed by the Employer.
15.3.14 Control Cable lugs shall be tinned copper solderless crimping type conforming to
IS-8309 & 8394. Aluminium Bimetallic lugs for power cables as required shall be
used depending upon type of cables and terminations.
15.4.1 Cable drums shall be unloaded, handled and stored in an approved manner and
rolling of drums shall be avoided as far as possible. For short distances, the
drums may be rolled provided they are rolled slowly and in proper direction as
marked on the drum.
16.1 The Contractor shall construct the cable trenches required for directly buried
cables. The scope of work shall include excavation, preparation of sand bedding,
soil cover, supply and installation of brick or concrete protective covers, back
filling and ramming, supply and installation of route markers and joint markers.
16.2 The cable (power and control) between LT station, DG set location and fire
lighting pump house and control room shall be laid in the burried cable trenches.
In addition to the above, for lighting purpose also, buried cable trench can be
used in outdoor area.
16.3 Power cables from Main Switchboard to colony shall be laid in burried cable
trench. Location of cable termination point at colony shall be as per site condition
and shall be decided in consultation with Employer‘s site-in-charge. Power
Cables for oil filtration plant shall be laid in open cable trench or burried trench
upto transformer/reactor area and can be looped from adjacent receptacles
provided for power supply of oil filtration plant.
16.4 Cable route and joint markers and RCC warning covers shall be provided
wherever required. The voltage grade of cables shall be engraved on the marker.
Cable markers shall be grounded in a concrete base.
17.1 Cabling in the control room shall be done on ladder type cable trays for vertical
runs while cabling in switchyard area shall be done on angles in the trench.
17.2 All cables from bay cable trench to equipments including and all interpole cables
(both power and control) for all equipment, shall be laid in PVC pipes of minimum
50 mm nominal outside diameter of class 4 as per IS 4985 which shall be buried
in the ground at a depth of 250mm below finish formation level. Separate PVC
pipes shall be laid for control and power cables. Cable pull boxes of adequate
size shall be provided if required. For vertical runs on equipments, perforated
cable trays shall be provided for all equipments under scope of the
contract or any equipment to be provided by the owner (including for
owner supplied circuit breakers).
17.3 Cables shall be generally located adjoining the electrical equipment through the
pipe insert embedded in the floor. In the case of equipments located away from
cable trench either pipe inserts shall be embedded in the floor connecting the
cable trench and the equipment or in case the distance is small, notch/opening
on the wall shall be provided. In all these cases necessary bending radius as
17.4 Cable racks and supports shall be painted after installation with two coats of
metal primer (comprising of red oxide and zinc chromate in a synthetic medium)
followed by two finishing coats of aluminium paint. The red oxide and zinc
chromate shall conform to IS:2074.
17.5 Suitable arrangement should be used between fixed pipe/cable trays and
equipment terminal boxes, where vibration is anticipated.
17.6 Power and control cables in the cable trench shall be laid in separate tiers. The
order of laying of various cables shall be as follows, for cables other than directly
buried.
a) Power cables preferably on top tiers.
b) Control instrumentation and other service cables in bottom tiers.
c) For cabling from control room to switchyard in main cable trench, cable
shall be laid such that bottom tiers are preferably filled first and top tiers
are kept for filling future cables as per the instructions of Engineer-In-
Charge.
17.7 For Single core cables in trefoil formation shall be laid with a distance of three
times the diameter of cable between trefoil centre lines. Further, for horizontal
cables a minimum centre to centre distance equal to twice the diameter of the
cable of higher size of cables shall be maintained.
17.8 Trefoil clamps for single core cables shall be of pressure die cast aluminium (LM-
6), Nylon-6 or fibre glass and shall include necessary fixing GI nuts, bolts,
washer etc. These are required at every 2 metre of cable runs.
17.9 Power and control cables shall be securely fixed to the trays/supports with self
locking type nylon ties with de-interlocking facility at every 5 metre interval for
horizontal run. Vertical and inclined cable runs shall be secured with 25 mm
wide and 2 mm thick aluminium strip clamps at every 2m.
17.10 Cables shall not be bent below the minimum permissible limit. The permissible
limits are as follows:
Power cable 12 D
Control cable 10 D
D is overall diameter of cable
17.11 Where cables cross roads, drains and rail tracks, these shall be laid in reinforced
spun concrete or steel pipes buried at not less than one metre depth. The size of
hume/steel pipe shall be such that approximately 70% area is only occupied. For
meeting future requirement, additional hume/steel pipe shall be laid for future bay
provision.
17.12 In each cable run some extra length shall be kept at a suitable point to enable
one (for LT cables)/ two (for H.T. cables) straight through joints to be made in
case the cable develop fault at a later date.
17.13 Selection of cable drums for each run shall be so planned as to avoid using
straight through joints. Cable splices will not be permitted except where called for
17.14 Control cable terminations inside equipment enclosures shall have sufficient
lengths so that changing of termination in terminal blocks can be done without
requiring any splicing.
17.15 Metal screen and armour of the cable shall be bonded to the earthing system of
the station, wherever required by the Employer.
17.16 Rollers shall be used at intervals of about two metres while pulling cables to
avoid damage.
17.17 All due care shall be taken during unreeling, laying and termination of cable to
avoid damage due to twist, kinks, sharp bends, etc.
17.18 Cable ends shall be kept sealed to prevent damage. In cable vault, fire resistant
seal shall be provided underneath the panels.
17.20 Wherever cable pass through floor or through wall openings or other partitions,
GI/PVC wall sleeves with bushes having a smooth curved internal surface so as
not to damage the cable, shall be supplied, installed and properly sealed by the
Contractor at no extra charges.
17.21 In case the outer sheath of a cable is damaged during handling/installation, the
Contractor shall repair it at his own cost to the satisfaction of the Employer. In
case any other part of a cable is damaged, the same shall be replaced by a
healthy cable at no extra cost to the Employer, i.e. the Contractor shall not be
paid for installation and removal of the damaged cable.
17.22 All cable terminations shall be appropriately tightened to ensure secure and
reliable connections. The Contractor shall cover the exposed part of all cable
lugs whether supplied by him or not with insulating tape, sleeve or paint.
i) The cable trays shall be of G.S Sheet and minimum thickness of sheet
shall be 2mm.
ii) The Contractor shall perform all tests and inspection to ensure that
material and workmanship are according to the relevant standards.
Contractor shall have to demonstrate all tests as per specification and
equipment shall comply with all requirements of the specification.
17.24.1 Contractor shall supply and install all rigid conduits, mild steel pipes, flexible
conduits, hume pipes etc. including all necessary sundry materials such as tees,
elbows, check nuts, bushing, reducers, enlargers, coupling cap, nipples, gland
sealing fittings, pull boxes etc as required. The size of the conduit/pipe shall be
selected on the basis of 40% fill criterion.
17.24.2 Contractor shall have his own facility for bending, cutting and threading the
conduits at site. Cold bending should be used. All cuts & threaded ends shall be
made smooth without leaving any sharp edges. Anticorrosive paint shall be
applied at all field threaded portions.
17.24.3 All conduit/pipes shall be extended on both sides of wall/floor openings. The
fabrication and installation of supports and the clamping shall be included in the
scope of work by Contractor.
GI pipe (light grade) of suitable size (minimum 25 mm) along with required
bends, joints etc. shall be used for special cables such as cables for visual
monitoring system (VMS), substation automation system (SAS). Further,
single pipe can be used for laying multiple cables.
17.24.5 All conduits/pipes shall have their ends closed by caps until cables are pulled.
After cables are pulled, the ends of conduits/pipes shall be sealed in an approved
manner to prevent damage to threaded portions and entrance of moisture and
foreign material.
17.24.6 All unarmoured cables shall run within the conduits from lighting panels to
lighting fixtures, receptacles etc.
17.24.7 Size of conduit for lighting shall be selected by the Contractor during detailed
engineering.
17.24.8 Exposed conduits shall be run in straight lines parallel to building columns,
beams and walls. Unnecessary bends and crossings shall be avoided to present
a neat appearance.
17.24.9 Conduit supports shall be provided at an interval of 750mm for horizontal runs
and 1000mm for vertical runs.
17.24.10 Conduit supports shall be clamped on the approved type spacer plates or
brackets by saddles or U- bolts. The spacer plates or brackets in turn, shall be
securely fixed to the building steel by welding and to concrete or brick work by
grouting or by nylon rawl plugs. Wooden plug inserted in the masonary or
concrete for conduit support is not acceptable.
17.24.13 Where conduits are placed alongwith cable trays, they shall be clamped to
supporting steel at an interval of 600mm.
17.24.14 For directly embedding in soil, the conduits shall be coated with an asphalt-base
compound. Concrete pier or anchor shall be provided wherever necessary to
support the conduit rigidly and to hold it in place.
17.24.15 Conduit shall be installed in such a way as to ensure against trouble from
trapped condensation.
17.24.16 Conduits shall be kept, wherever possible, at least 300mm away from hot pipes,
heating devices etc. when it is evident that such proximity may reduce the
service life of cables.
17.24.17 Slip joints shall be provided when conduits cross structural expansion joints or
where long run of exposed conduits are installed, so that temperature change will
cause no distortion due to expansion or contraction of conduit run.
17.24.18 For long conduit run, pull boxes shall be provided at suitable intervals to facilitate
wiring.
17.24.19 Conduit shall be securely fastened to junction boxes or cabinets, each with a lock
nut inside and outside the box.
17.24.20 Conduits joints and connections shall be made thoroughly water-tight and rust
proof by application of a thread compound which insulates the joints. White lead
is suitable for application on embedded conduit and red lead for exposed conduit.
17.24.21 Field bends shall have a minimum radius of four (4) times the conduit diameter.
All bends shall be free of kinks, indentations of flattened surfaces. Heat shall not
be applied in making any conduit bend. Separate bends may be used for this
purpose.
17.24.22 The entire metallic conduit system, whether embedded or exposed, shall be
electrically continuous and thoroughly grounded. Where slip joints are used,
suitable bounding shall be provided around the joint to ensure a continuous
ground circuit.
17.24.23 After installation, the conduits shall be thoroughly cleaned by compressed air
before pulling in the wire.
17.24.24 Lighting fixtures shall not be suspended directly from the junction box in the main
conduit run.
Cable sealing system having earthing strip can alternately be used in place
of cable gland arrangement for indoor panels such as LCC, C&R, PLCC
panels etc.
The Contractor shall supply and install ISI marked junction boxes complete with
terminals as required. The brackets, bolts, nuts, screws etc required for erection
are also included in the scope of the Contractor.
19.1 All pre/commissioning activities and works work for substation equipment
shall be carried out in accordance with Employer's ''Pre- Commissioning
procedures for Switchyard Equipments (Doc. No. D-2-01-03-01-03)" by the
contractor. This document shall be provided to the successful contractor
during detailed engineering stage. Test results in the prescribed formats
shall be duly filled by the contractor and shall be submitted to the Owner in
soft form (CD or Pen Drive)
The Contractor shall arrange all equipments instruments and auxiliaries required
for testing and commissioning of equipments alongwith calibration certificates.
(c) Check from name plate that all items are as per order/specification.
(d) Check tightness of all bolts, clamps and connecting terminals using
torque wrenches.
(e) For oil filled equipment, check for oil leakage, if any. Also check oil level
and top up wherever necessary.
(f) Check ground connections for quality of weld and application of zinc rich
paint over weld joint of galvanised surfaces.
(h) All checks and tests specified by the manufacturers in their drawings and
manuals as well as all tests specified in the relevant code of erection.
(i) Check for surface finish of grading rings (Corona control ring).
c) Check earth resistance of the entire grid as well as various sections of the
same.
d) Check for weld joint and application of zinc rich paint on galvanised
surfaces.
a) Physical check
c) Dye penetration test & Radiography test on 10% sample basis on weld
joints.
19.6 INSULATOR
ANNEXURE “A”
Circles perpendicular to the axis of the conductor shall be marked at two places
on a sample of conductor of minimum 5m length suitably compressed with dead
end clamps at either end. The load shall be increased at a steady rate upto 50%
of minimum specified UTS and held for one minute. The circles drawn shall not
be distorted due to Relative movement of strands. Thereafter the load shall be
increased at a steady rate to 100% of minimum specified UTS and held for one
minute. The conductor sample shall not fail during this period. The applied load
shall then be increased until the failing load is reached and the value recorded.
Under the conditions as specified under (2.0) above, the conductor samples shall
have radio interference voltage as indicated in the guaranteed technical
particulars enclosed with. This test may be carried out with corona control rings
and arcing horns. The test procedure shall be in accordance with IEC-60437.
inspector shall visually check for scratches, joints, etc. and that the conductor
generally conform to the requirements of this specification. The length of
conductor wound on the drum shall be measured with the help of counter meter
during rewinding.
The lay-ratios of various layers shall be checked to ensure that they conform to
the requirements of this Specification.
The test procedure shall be as specified in IEC:60888. The material shall conform
to the requirements of this Specification. The adherence of zinc shall be checked
by wrapping around a mandrel four times the diameter of steel wire.
The test procedures shall be as per clause No. 10.3 of IEC:60888. In torsion test,
the number of complete twists before fracture shall not be less than that indicated
in the GTP. In case test sample length is less or more than 100 times the
stranded diameter of the strand, the minimum number of twists will be
proportioned to the length and if number comes in the fraction then it will be
rounded off to next higher whole number. In elongation test, the elongation of the
strand shall not be less than 4% for a gauge length of 250 mm.
Two Aluminium wires shall be welded as per the approved quality plan and shall
be subjected to tensile load. The breaking strength of the welded joint of the wire
shall not be less than the breaking strength of individual strands.
ANNEXURE “B”
1. UTS TEST
Circles perpendicular to the axis of the earthwire shall be marked at two places
on a sample of earthwire of minimum 5m length suitably compressed with dead
end clamps at either end. The load shall be increased at steady rate upto 50% of
UTS and held for one minute. The circles drawn shall not be distorted due to
relative movement of strands. Thereafter, the load shall be increased at a steady
rate to 100% of UTS and held for one minute. The earthwire sample shall not fail
during this period. The applied load shall then be increased until the failing load
is reached and value recorded.
4. TORSION TEST
The minimum number of twists which a single steel strand shall withstand during
torsion test shall be eighteen for a length equal to 100 times the standard
diameter of the strand. In case the test sample length is less or more than 100
times the standard diameter of the strand, the minimum number of twists will be
proportionate to the length and if number comes in the fraction then it will be
rounded off to next higher whole number.
5. DIMENSIONAL CHECK
The lay length shall be checked to ensure that they conform to the requirements
of this specification.
7. GALVANISING TEST
checked by wrapping around a mandrel four times the diameter of steel wire.
ANNEXURE-C
CORONA AND RADIO INTERFERENCE VOLTAGE (RIV) TEST
1. General
Unless otherwise stipulated, all equipment together with its associated connectors,
where applicable, shall be tested for external corona both by observing the voltage
level for the extinction of visible corona under falling power frequency voltage and by
measurement of radio interference voltage (RIV).
2. Test Levels:
The test voltage levels for measurement of external RIV and for corona extinction
voltage are listed under the relevant clauses of the specification.
3. Test Methods for RIV:
3.1 RIV tests shall be made according to measuring circuit as per International Special-
Committee on Radio Interference (CISPR) Publication 16-1(1993) Part -1. The
measuring circuit shall preferably be tuned to frequency with 10% of 0.5 Mhz but
other frequencies in the range of 0.5 MHz to 2 MHz may be used, the measuring
frequency being recorded. The results shall be in microvolts.
3.2 Alternatively, RIV tests shall be in accordance with NEMA standard Publication No.
107-1964, except otherwise noted herein.
3.3 In measurement of, RIV, temporary additional external corona shielding may be
provided. In measurements of RIV only standard fittings of identical type supplied
with the equipment and a simulation of the connections as used in the actual
installation will be permitted in the vicinity within 3.5 meters of terminals.
3.4 Ambient noise shall be measured before and after each series of tests to ensure
that there is no variation in ambient noise level. If variation is present, the lowest
ambient noise level will form basis for the measurements. RIV levels shall be
measured at increasing and decreasing voltages of 85%, 100% and 110% of the
specified RIV test voltage for all equipment unless otherwise specified. The
specified RIV test voltage for 765kV, 400kV, 220kV is listed in the detailed
specification together with maximum permissible RIV level in microvolts.
3.5 The metering instruments shall be as per CISPR recommendation or equivalent
device so long as it has been used by other testing authorities.
3.6 The RIV measurement may be made with a noise meter. A calibration procedure of
the frequency to which noise meter shall be tuned shall establish the ratio of voltage
at the high voltage terminal to voltage read by noisel meter.
4. Test Methods for Visible Corona [applicable for 400kV and above]
The purpose of this test is to determine the corona extinction voltage of apparatus,
connectors etc. The test shall be carried out in the same manner as RIV test
described above with the exception that RIV measurements are not required during
test and a search technique shall be used near the onset and extinction voltage,
when the test voltage is raised and lowered to determine their precise values. The
test voltage shall be raised to 110% of RIV test voltage and maintained there for five
minutes. In case corona inception does not take place at 110%, test shall be
stopped, otherwise test shall be continued and the voltage will then be decreased
slowly until all visible corona disappears. The procedure shall be repeated at least 4
times with corona inception and extinction voltage recorded each time. The corona
extinction voltage for purposes of determining compliance with the specification shall
be the lowest of the four values at which visible corona (negative or positive polarity)
disappears. Photographs with laboratory in complete darkness shall be taken under
test conditions, at all voltage steps i.e. 85%, 100%, and 110%. Additional
photographs shall be taken at corona inception and extinction voltages. At least two
views shall be photographed in each case using Panchromatic film with an ASA
daylight rating of 400 with an exposure of two minutes at a lens aperture of f/5.6 or
equivalent. The photographic process shall be such that prints are available for
inspection and comparison with conditions as determined from direct observation.
Photographs shall be taken from above and below the level of connector so as to
show corona on bushing, insulators and all parts of energised connectors. The
photographs shall be framed such that test object essentially, fills the frame with no
cut-off.
In case corona inception does not take place at 110%, voltage shall not be
increased further and corona extinction voltage shall be considered adequate.
4.1 The test shall be recorded on each photograph. Additional photograph shall be
taken from each camera position with lights on to show the relative position of test
object to facilitate precise corona location from the photographic evidence.
4.2 In addition to photographs of the test object preferably four photographs shall be
taken of the complete test assembly showing relative positions of all the test
equipment and test objects. These four photographs shall be taken from four points
equally spaced around the test arrangement to show its features from all sides.
Drawings of the laboratory and test set up locations shall be provided to indicate
camera positions and angles. The precise location of camera shall be approved by
Purchaser‘s inspector, after determining the best camera locations by trial
energisation of test object at a voltage which results in corona.
4.3 The test to determine the visible corona extinction voltage need not be carried out
simultaneously with test to determine RIV levels.
4.4 However, both test shall be carried out with the same test set up and as little time
duration between tests as possible. No modification on treatment of the sample
between tests will be allowed. Simultaneous RIV and visible corona extinction
voltage testing may be permitted at the discretion of Purchaser‘s inspector if, in his
opinion, it will not prejudice other test.
5. Test Records:
In addition to the information previously mentioned and the requirements specified
as per CISPR or NEMA 107-1964 the following data shall be included in test report:
a) Background noise before and after test.
b) Detailed procedure of application of test voltage.
c) Measurements of RIV levels expressed in micro volts at each level.
d) Results and observations with regard to location and type of interference
sources detected at each step.
e) Test voltage shall be recorded when measured RIV passes through 100
microvolts in each direction.
f) Onset and extinction of visual corona for each of the four tests required shall
be recorded.
ANNEXURE – D
A. SHORT CIRCUIT FORCES AND SPACER SPAN FOR 765kV GANTRY STRUCTURE
1. 54.0 mtr QUAD AAC BULL 15 mtr 3.96 T 5.98 T 3.5 mtr
2. 56.0 mtr QUAD AAC BULL 15 mtr 4.52 T 6.77 T 4.0 mtr
3. 87.9 mtr QUAD AAC BULL 15 mtr 8.35 T 11.22 T 6.5 mtr
4. 104.0 mtr QUAD AAC BULL 15 mtr 9.00 T 12.72 T 7.5 mtr
5. 108.61 mtr QUAD AAC BULL 15 mtr 9.00 T 12.72 T 8.0 mtr
B. SHORT CIRCUIT FORCES AND SPACER SPAN FOR 400kV GANTRY STRUCTURE
ANNEXURE – D
C. SHORT CIRCUIT FORCES AND SPACER SPAN FOR 220 kV GANTRY STRUCTURE
NOTE: ACSR conductor as mentioned above indicates that it is suitable for both ACSR
MOOSE as well as ACSR BERSIMIS conductor.
D. SHORT CIRCUIT FORCES AND SPACER SPAN FOR 132 kV GANTRY STRUCTURE
1.0 GENERAL
Employer has stardardised the guaranteed technical particulars for the following
AAC/ACSR conductors, Galvanised steel earthwire and aluminum tube. The
contractor shall supply the conductors as per the standard GTP mentioned below.
Any deviation to the following GTP shall be clearly brought out by the bidder in
their bid.
b) 12 wire Aluminium mm 16 10 16 10
layer
c) 18 wire Aluminium mm 16 10 14 10
layer
d) 24 wire Aluminium mm 14 10 - -
layer
4.8 DC resistance of the ohm/ 0.03340 0.03628
conductor at 20°C km
4.9 Standard length of the m 1000 1000
conductor
4.10 Tolerance on Standard % (+/-) 5 (+/-) 5
length
4.11 Direction of lay of Right Hand Right Hand
outer layer
4.12 Linear mass of the conductor
a) Standard kg/ 2400 2192
km
b) Minimum kg/ 2355 2150
km
c) Maximum kg/ 2445 2234
km
4.13 Modulus of Elasticity Kg/sq 4709 (Initial) 4709 (Initial)
.mm 5869 (Final) 5869 (Final)
4.14 Co-efficient of Linear Per 23.0x10-6 23.0x10-6
Expansion Deg.
C
4.15 Minimum Corona KV 508 320
Extinction Voltage (rms)
4.16 RIV at 1 Mhz Micro Less than 1000 Less than 1000 at
volts at 508 kV (rms) 320 kV (rms)
5.0 Drum Dimensions Generally conforms to IS:1778
b) 12 wire Aluminium mm 17 10 16 10
layer
c) 18 wire Aluminium mm 16 10 14 10
layer
d) 24 wire Aluminium mm 14 10 NA
layer NA
5.8 DC resistance of the ohm/ 0.06868 0.140
conductor at 20°C km
5.9 Standard length of the m 1800 1800
conductor
5.10 Tolerance on Standard % (+/-) 5 (+/-) 5
length
5.11 Direction of lay of Right Hand Right Hand
outer layer
5.12 Linear mass of the conductor
a) Standard kg/ 1621 974
km
b) Minimum kg/ 1589 954
mm
18. Thermal Conductivity at 100 0.43 Calories/sec/sq.mm/cm/deg.C
Deg.C
19. Minimum 0.2% proof stress 17.34 Kg/sq.mm
20 Minimum Yield point 14.50 Kg/sq.mm 17.50 Kg/sq.mm
21 Minimum Breaking Strength 17.50 Kg/sq.mm 20.42 Kg/sq.mm
450 mm
2 mm thick MS Plate
1000 mm
40 mm dia pipe
GROUND LEVEL
600 mm
Table of contents
1.0 GENERAL 1
2.0 DESIGN REQUIREMENTS FOR STRUCTURES NOT 2
COVERED IN STANDARDISED LIST
3.0 DESIGN DRAWINGS, BILL OF MATETRIALS AND 4
DOCUMENTS
4.0 FABRICATION AND ERECTION 5
5.0 BOLTING 5
6.0 WELDING 5
7.0 FOUNDATION BOLTS 6
8.0 STABILITY OF STRUCTURE 6
9.0 GROUTING 6
10.0 GALVANISING 6
11.0 TOUCH-UP PAINTING 6
12.0 INSPECTION BEFORE DISPATCH 7
13.0 TEST CERTIFICATE 7
14.0 SAFETY PRECAUTIONS 7
SECTION: STRUCTURES
1.0 GENERAL
Equipment support structure standardization has been carried out by the employer
with the provision of stool to facilitate interchangeability of equipments at a later
stage. Stools shall be provided by the Contractor between the equipment and its
support structure to match the bus bar height. The top of stool shall be connected
to the equipment and the bottom of the stool shall be connected to the Base
support structure.
The scope shall include supply and erection of all types of structures including
bolts, nuts, washers, step bolts, inserts in concrete, gusset plates, equipment
mounting bolts, structure earthing bolts, foundation bolts, spring washers, fixing
plates and any other items as required to complete the job.
The connection of all structures to their foundations shall be with base plates and
embedded anchor/foundation bolts. All steel structures including
anchor/foundation bolts shall be fully galvanized. The weight of the zinc coating
shall be at least 610 gm/sq.m. Zinc coating for costal areas, if defined in section –
Project shall not be less than 900gm/sq.m
2.1 For design of steel structures loads such as dead loads, live loads, wind loads
etc. shall be based on IS:875,Parts I to V.
2.2 For materials and permissible stresses IS: 802, Part-I, Section-2 shall be
followed in general. However, additional requirements given in following
paragraphs shall also be considered.
Other members 4
Redundant members 4
Size and thickness of gusset plate, pack washer and pack plate shall be as per
requirement.
2.4 Maximum slenderness ratios for leg members, other stressed members and
redundant members for compression force shall be as per IS-802.
2.5 Minimum distance from hole center to edge shall be 1.5 x bolt diameter.
Minimum distance between center to center of holes shall be 2.5 x bolt
diameter.
b) Switchyard gantry structures shall be designed for the two conditions i.e.
normal condition and short circuit condition. In both conditions the design of
all structures shall be based on the assumption that stringing is done only on
one side i.e. all the three (phase) conductors broken on the other side.
Factor of safety of 2.0 under normal conditions and 1.5 under short circuit
condition shall be considered for the design of switchyard structures.
c) Vertical load of half the span of conductors/string and the earth wires on
either side of the beam shall be taken into account for the purpose of design.
Weight of man with tools shall be considered as 150 kgs. for the design of
structures.
f) All Pipe support structures used for supporting equipments shall be designed
for the worst combination of dead loads, erection load. Wind load/seismic
forces, short circuit forces and operating forces acting on the equipment and
associated bus bars as per IS:806. The material specification shall be as per IS:
1161 read in conjunction with IS: 806.
g) If luminaries are proposed to be fixed on gantries, then the proper loading for
the same shall be considered while designing. Also holes for fixing the
brackets for luminaries should be provided wherever required.
h) Foundation bolts shall be designed for the loads for which the structures are
designed.
3.1 Structures, for which line diagram has already been provided along with
tender documents, fabrication drawings (structure assembly drawing) along
with Bill of Material shall be provided to the successful bidder after award
based on which structures shall be supplied. Fabrication drawings issued to
the contractor for any project shall be valid for other projects also if wind
speed of the area is same. These drawings are also available on the
POWERGRID web site and can be downloaded from the web site. Hard
copies, if needed, can be obtained from employer. These drawings shall be
good for fabrication and inspection of steel structures for any substation.
Release for construction stamp for particular substation is not required.
Replacing MS section with higher section or replacing MS section with HT
section of same size due to non availability of particular section shall not
require employer’s approval and this can be done without any additional
financial implication to the employer.
3.2.1 In case deisign of structure is to be done by employer, only line diagram of the
structure shall be provided to the contractor and fabrication drawing shall be prepared
by contractor based on line diagram and submitted for approval.
3.2.2 In case design of structure is covered in the scope of contract , the contractor shall
submit design alongwith line diagram for approval and based on approved line
diagram, fabrication drawing shall be prepared and submitted for
employers’approval. The line diagram should indicate not only profile, but
section, numbers and sizes of bolts and details of typical joints.
3.2.3 The fabrication drawings to be prepared and furnished by the Contractor shall
be based on line diagram provided by employer or the design approved by the
employer. These fabrication drawings shall indicate complete details of
fabrication and erection including all erection splicing details and typical
fabrication splicing details, lacing details, weld sizes and lengths. Bolt details
and all customary details in accordance with standard structural engineering
practice whether or not given by the employer. The fabrication drawings and
bill of material based on fabrication drawing shall be submitted to the
employer for approval. Approved bill of material prepared based on
fabrication drawing shall be the basis for payment.
4.1 The fabrication and erection works shall be carried out generally in
accordance with IS 802. A reference however may be made to IS 800 in case
of non-stipulation of some particular provisions in IS 802. All materials shall
be completely shop fabricated and finished with proper connection material
and erection marks for ready assembly in the field.
4.2 The component parts shall be assembled in such a manner that they are neither
twisted nor otherwise damaged and shall be so prepared that the specified
camber, if any, is provided. In order to minimize distortion in member the
component parts shall be positioned by using the clamps, clips, dogs, jigs and
other suitable means and fasteners (bolts and welds) shall be placed in a
balanced pattern. If the individual components are to be bolted, paralleled and
tapered drifts shall be used to align the part so that the bolts can be accurately
positioned.
4.3 Sample towers, beams, lightning masts and equipment support structures may
be trial assembled in fabrication shop in order to ensure fitment of various
members and to avoid problems during erection.
4.4 The Contractor should arrange on his own all plant and equipment, welding
set, tools and tackles, scaffolding, trestles equipments and all other accessories
and ancillaries required for carrying out erection without causing any stresses
in the members which may cause deformation and permanent damage. Minor
modification, if any, required during erection shall be done at site with the
approval of Engineer – in- charge.
5.0 BOLTING
i) Every bolt shall be provided with a washer under the nut so that no part of the
threaded portion of the bolt is within the thickness of the parts bolted together.
ii) In case of fasteners, the galvanizing shall confirm to IS-1367(Part 13). The
spring washer shall be electro galvanized as per Grade IV of IS-1573.
6.0 WELDING
The work shall be done as per approved fabrication drawings which shall
clearly indicate various details of joints to be welded, type of weld, length and
size of weld, Symbols for welding on erection and shop drawings shall be
7.1 Foundation bolts for the towers and equipment supporting structures shall be
embedded in first stage concrete while the foundation is cast. The Contractor
shall ensure the proper alignment of these bolts to match the holes in the base
plate.
7.2 The Contractor shall be responsible for the correct alignment and leveling of
all steel work on site to ensure that the towers/structures are plumb.
7.3 All foundation bolts for lattice structure, pipe structure are to be supplied by
the Contractor.
7.4 All foundation bolts shall be provided with two no. standard nuts of class 5
confirming to IS:1363/1367/6639, one check nut of class 4 confirming to IS:1364,
one anchore plate at the bottom of foundation bolt and one plain washer.
7.5 All foundation bolts shall conform to IS 5624, however, the material, shall be
MS conforming to IS:2062/ SAE:1018.
The Contractor shall be responsible for the stability of the structure at all
stages of its erection at site and shall take all necessary measures by the
additions of temporary bracings and guying to ensure adequate resistance to
wind and also to loads due to erection equipment and their operations.
9.0 GROUTING
10.0 GALVANISING
All structural steel works, equipment support structures and foundation bolts
shall be galvanized after fabrication. The galvanization shall be done as per
requirement of IS 4579. Purity of zinc to be used shall be 99.95% as per
IS:209.
Each part of the fabricated steel work shall be inspected as per approved
quality plans and certified by the employer or his authorized representative as
satisfactory before it is dispatched to the erection site. Such certification shall
not relieve the Contractor of his responsibility regarding adequacy and
completeness of fabrication.
15.0 All tests mentioned in standard field quality plans shall have to be carried out
and conformity of materials and workmanship shall be ascertained.
Insertion of order of precedence for Technical Specification, BIS code & CPWD
specification
2 2.9.2.5 Signing and stamping of soil report by qualified Geotechnical engineer/ consultant
6 5.6 (a) Supervision and safety of existing structures during dismantling works
12 10.3.18 “working stress method” replaced by “limit state method” for PEB design
13 10.3.16 All design and detailing (including ductile) as per latest BIS standards
3 3.6 Specification of RCC frame brick masonry wall & stone masonry wall
4 3.6.4 structural steel angle supporting barbed wire/concertina coil over boundary wall shall
be painted with epoxy paint
10 10.1.1 CRB shall be RCC structure at both AIS and GIS substations.
20 11.3.2 Min. value of Zn-Al coating in roof and wall sheeting changed to 150 gm/sqm
22 20.12.2 & Payment of miscellaneous structural steel for GIS equipment in GIS hall
20.12.3
1.0 GENERAL
1.1 All civil works shall be carried out as per design/drawings provided by the Employer/
Contractor and as per these specification provided by the Employer. In case
design/drawings are prepared by the contractor then these shall be approved by the
employer before execution. In case any item is not covered under specification then the
same shall be carried out as per CPWD specification /applicable BIS Standards and Codes.
Any item for which specification is not provided herein and is not covered under CPWD
specification/ BIS Standards, the same shall be executed as per manufacturer guidelines
with the approval of employer. All materials shall be of best quality conforming to relevant
Indian Standards and Codes. In case of any conflict between Standards/ Code and
Technical Specification, the order of precedence shall be as under:
1.1.1 Technical specification,
1.1.2 BIS codes
1.1.3 CPWD specification.
The decision of engineer in charge in this regard shall be final and binding.
1.2 Wherever reference to CPWD/BIS Codes is made, it shall be to the latest edition/revision
of the same, issued up to 7 days prior to the date of opening of this tender.
1.3 The Contractor shall arrange all labour, tools, equipment, materials, temporary works,
constructional plant & machinery, fuel supply, transportation and all other incidental items
not shown or specified but as may be required for complete performance of the Works in
accordance with drawings, specifications and direction of Employer.
1.4 All materials including cement, reinforcement steel, structural steel etc. shall be arranged
by the Contractor.
1.5 The Contractor shall execute the work as per the Field Quality Plan (FQP) which is available
on POWERGRID website. All testing required shall be arranged by the Contractor at his
own cost.
1.6 The bidder shall fully apprise himself of the prevailing conditions at the proposed site,
Climatic conditions including monsoon patterns, local conditions and site specific
parameters, soil parameters, availability of construction material and shall include for all
such conditions and contingent measures in the bid, including those which may not have
been specifically brought out in the specifications.
1.7 Unless leveling is in the scope of the bidder, fairly leveled site with single level/terraces
with different levels/ gradual slope shall be handed over to the Contractor, in a phased
1.8 Employer has standardized its technical specification for various items/ works.
Specification for items which are covered in the scope and as defined in Section project &
BPS shall only be referred.
1.9 The material specification, workmanship and acceptance criteria shall be as per approved
standard Field Quality Plan. In case certain item is not covered in FQP, it shall be
constructed as per CPWD specification/ relevant BIS.
2.1 SCOPE:
This specification covers all the work required for detailed soil investigation and
preparation of a detailed report. The work shall include mobilization of necessary
equipment, providing necessary engineering supervision and technical personnel, skilled
and unskilled labour etc. as required to carry out field investigation as well as,
laboratory investigation, analysis and interpretation of data and results, preparation of
detailed Geo-technical report including specific recommendations for the type of
foundations and the allowable safe bearing capacity for different sizes of foundations at
different founding strata starting from 0.5M from existing ground level for the various
structures of the substation. The Contractor shall make his own arrangement for
locating the co-ordinates and various test positions in field as per the information
supplied to him and also for determining the reduced level of these locations with
respect to the benchmark indicated by the Employer.
In the selected test point and chosen direction, four electrodes with insulated connecting
wires shall be driven into the earth along a straight line of equal intervals (a). The depth of
the electrodes in the earth shall be of the order of 15 cm to 20 cm. The megger shall be
placed on a steady and approximately level base, the link between terminals P1 and C1
shall be opened and the four electrodes connected to the instrument terminals. An
appropriate range on the instrument shall be selected to obtain clear readings avoiding the
two ends of the scale as far as possible.
Resistivity shall be calculated by substituting the value of R in the above equation. The test
shall be repeated in a chosen direction with a number of different electrode spacing,
increasing from 2m to 50m preferably in the steps of 2, 5, 10, 15, 25 and 50m. When the
spacing is increased gradually from low values, at a stage, it may be found that the
resistivity reading is more or less constant irrespective of the increase in the electrode
spacing. The resistivity for this spacing is noted and taken as the resistivity for that
direction. In a similar manner, resistivity for at least eight equally spaced directions from
the centre of the test points shall be measured. These measurements shall be repeated for
all test points.
Technical Specification, Section: Civil Works Page 9 of 80
C/ENGG/SPEC/CIVIL/ Rev-11A/Jun’18
NOTES:-
i. Soil resistivity points shall preferably be one number in each 100mx100m grid and
number of test points shall be such that the entire substation including the future area
is covered.
ii. Average resistivity value of all eight directions shall be considered for design of
earthing system.
iii. Soil resistivity measurement may be done in dry season. Small amount of water may
be applied at electrodes for making proper contact between the electrodes and soil.
Plate load test shall be conducted to determine the bearing capacity, modulus of sub grade
reaction and load/settlement characteristics of soil at shallow depths by loading a plane
and level steel plate kept at the desired depth and measuring the settlement under
different loads, until a desired settlement takes place or failure occurs. The specification
for the equipment and accessories required for conducting the test, the test procedure,
field observations and reporting of results shall conform to IS: 1888. Modulus of sub grade
reaction shall be conducted as per IS: 9214. Plate load test shall be conducted at two
locations to be decided during detailed engineering at the proposed foundation depth
below finished ground level for determining the bearing capacity.
Undisturbed tube samples shall be collected at 0.5 m and 2.5m depths from natural
ground level for carrying out laboratory tests
The size of the pit in plate load test shall not be less than five times the plate size and
shall be taken up to the specified depth. All provisions regarding excavation and visual
examination of pit shall apply here.
Unless otherwise specified the reaction method of loading shall be adopted. Settlement
shall be recorded from dial gauges placed at four diametrically opposite ends of the test
plate.
The load shall be increased in stages. Under each loading stage, record of Time v/s
Settlement shall be kept as specified in IS: 1888.
Backfilling of the pit shall be carried out as per the directions of the Employer. Unless
otherwise specified the excavated soil shall be used for this purpose. In cases of
gravel-boulder or rocky strata, respective relevant codes shall be followed for tests.
On completion of each hole, the Contractor shall backfill all bore holes as directed by
the Employer. The backfill material can be the excavated material.
2.8.1. The laboratory tests shall be carried out progressively during the field work after
sufficient number of samples has reached the laboratory in order that the test results
of the initial bore holes can be made use of in planning the later stages of the field
investigation and quantum of laboratory tests.
2.8.2. All samples brought from field, whether disturbed or undisturbed shall be
extracted/prepared and examined by competent technical personnel, and the test shall
be carried out as per the procedures laid down in the relevant I.S. Codes.
2.9.1 The Contractor shall submit the detailed report in four (4) copies wherein information
regarding the geological detail of the site, summarised observations and test data, bore
logs, and conclusions and recommendations on the type of foundations with
supporting calculations for the recommendations. Initially the Contractor shall submit
2.9.2 The report shall include, but not limited to the following:-
2.9.2.1 A plan showing the locations of the exploration work i.e. bore holes, trial pits, Plate load
test etc.
2.9.2.2 Bore Logs: Bore logs of each bore holes clearly identifying the stratification and the type
of soil stratum with depth. The values of Standard Penetration Test (SPT) at the depths
where the tests were conducted on the samples collected at various depths shall be
clearly shown against that particular stratum.
2.9.2.3 Test results of field and laboratory tests shall be summarized strata wise as well a s in
combined tabular form. All relevant graphs, charts tables, diagrams and photographs, if
any, shall be submitted along with report. Sample illustrative reference calculations for
settlement, bearing capacity, pile capacity shall be enclosed.
2.9.2.4 The report should contain specific recommendations for the type of foundation for the
various structures envisaged at site. The Contractor shall acquaint himself about the
type of structures and their functions from the Employer. The observations and
recommendations shall include but not limited to the following:
i) Standard drawings have been developed for Control Room Building, Switchyard Panel
Room, Fire Fighting Pump House & Water Tank, Towers & Equipments Foundations,
Transit Camp, Septic Tank & Soak Pit, Roads, Road Culverts & Rail Cum Road, Drains, Chain
Link Fence & Switchyard Gate, Rain Water Harvesting by the Employer and are enclosed
with the tender documents.
ii) These drawings are good for construction and are also available on POWERGRID website.
Additional prints if any required, can be downloaded from the website.
iii) All tender drawings shall be read in conjunction with this specification. Discrepancy if any
shall be brought to the notice of Employer prior to quote.
iv) All foundation drawings including foundations for buildings, towers, equipments etc shall
be released to the Contractor after award in a phased manner, after receiving the
geotechnical investigation report.
v) Drawings for transformer, reactor foundations and fire walls are not enclosed and shall be
made available to the successful bidders by the Employer during detailed engineering.
vi) In case the site conditions warrant any special type of foundations to be used, the same
shall be designed and issued by the Employer to the Contractor during detailed
engineering unless otherwise mentioned in section project.
vii) Drawings for any non-standard tower or equipment and their foundation, if required, shall
be designed by the Employer and made available to the Contractor during detailed
Engineering unless otherwise mentioned in section project.
viii) Drawings that have been mentioned and to be issued by the Employer to the Contractor
during detailed Engineering shall be made available to the Contractor as per the agreed
work schedule finalized after award.
ix) Items/ components of buildings not explicitly covered in the specification but required for
completion of the project shall be deemed to be included in the scope.
3.1.1 The construction drawings showing section detail for road, culverts as well as rail cum road
are enclosed with the tender documents. The layout of roads shall be as per approved
general arrangement drawing. Types of the roads in the scope of contract shall be either of
RCC or bituminous road as indicated in the GA drawing or in Bid Price Schedule.
3.1.2 The width of the road shall be either 5.5m wide or 3.75m as indicated in the GA drawing.
Type of pavement either rigid pavement (RCC Road) or flexible pavement(Bituminous
Road) shall be as per tender documents.
3.1.3 The type & location of culverts i.e. the number and diameter of Hume pipes shall be as
decided during detailed engineering. The invert level of Hume pipes of culverts shall match
with the invert level of drain meeting the culvert.
3.1.4 100mm diameter RCC Hume pipe (NP-3) shall be provided across the road at every 100M
interval along the road. In case NP3 pipe is not available, vendor may provide 100 dia
UPVC pipe encased with 75 mm thk. concrete 1:2:4 alround without any financial
implication to POWERGRID.
3.1.5 Road within the switchyard area should have shoulder of 600mm wide on either sides of
road. Shoulder shall be smooth finished with well compacted 75mm thick PCC 1:4:8. The
road leading to control room building and the roads outside switchyard fence area shall be
provided with kerb stone and interlocking tiles on shoulder. Width of shoulder shall be
1.75m in case of 5.5m wide road and 1.3m in case of 3.75m wide road.
3.1.6 The shoulder of the road in case of substation extension shall match with the shoulder of
the existing road in all respect.
3.1.7 Road leading towards the area of Autotransformer/Reactor shall be as short as possible.
Road layouts shall be prepared with adequate turning radius, so that easy movement of
vehicles is possible. Roads which are to be used for carrying transformers / reactors shall
be provided with turning radius preferably 19.5M or more but not less than 16.5M.
Turning radius of other roads may be decided at site depending on layout constraints
3.1.8 Contractor may use WMM instead of WBM with prior approval of employer without any
additional financial implication to POWERGRID. Guidelines of IRC: 109-1997 shall be
followed for Wet Mix Macadam (WMM) only. However, measurement of road shall be
done as specified elsewhere in this specification.
3.1.9 In case of rigid pavements, RCC shall be laid and finished with screed board, vibration,
vacuum dewatering process etc.
3.2.1 The construction drawing for the section of drain is enclosed with the tender documents.
3.2.2 The Contractor shall propose an overall drainage layout for the new sub-station or
extension of substation during detailed engineering considering the site conditions which
is to be approved by POWERGRID before execution. The type of drains used shall be of the
sections standardized and indicated in the drawings enclosed with the tender documents.
3.3.1 Fencing and Gate shall be constructed as per drawing attached with tender documents
and are also available on POWERGRID website.
3.3.2 Fencing and Gate shall be provided at the locations shown in approved general
arrangement drawing. Separate gate shall be provided for men and equipment. Fence shall
also be provided for the various equipments (if) mounted on ground or a height lower than
2.5m. Necessary gates shall be provided for each area so surrounded.
3.3.3 Chain link of galvanized fence fabric with 3.15mm dia wire and 75mm mesh size
conforming to IS: 2721 shall be used. MS tube used shall be of grade YST210 and conform
to IS: 1161. All other structural steel shall conform to IS: 2062.
3.3.4 The whole assembly of tubular post and frame of panels shall be hot dip galvanized. The
zinc coating shall be minimum 610 gram per square meter. In case the substation is
located within 30km from sea coast, the zinc coating shall be 900gm per square meter. The
purity of zinc shall be 99.95% as per IS: 209.
3.3.5 The gate shall be made of medium duty M.S. pipe of grade YST210 and conform to IS: 1161
with welded joints. The main frame (outer frame) of the gate shall be made of 40mm
nominal bore pipe and vertical pipes of 15mm nominal bore @ 125mm spacing (maximum)
shall be welded with the main frame. Gate shall be painted with one coat of approved
steel primmer and two or more coats of synthetic enamel paint to give an even shade.
3.4.1 In addition to drainage of rainwater, the Contractor shall make arrangement for rainwater
harvesting also. A drawing showing details of recharge structure for rainwater harvesting is
enclosed with tender document and is also available on POWERGRID website.
3.5.2 The layout should show type of cable trench, longitudinal slope and invert level calculated
considering future extensions also. The types of cable trench shall be of the section
indicated in the drawings enclosed with the tender documents and are also available on
POWERGRID website.
Boundary wall shall consist of frame of RCC column and foundation at regular intervals
connected through plinth beam and supporting 230 thick brick masonry. Details such as
height, column spacing, structural details, fencing/grating works, plastering/ painting, etc.
shall be as per tender/construction drawing.
3.6.2 Stone masonry wall:
Boundary wall shall be Random Rubble masonry wall and coursed rubble masonry (for
front portion). The wall thickness shall be 350 thk and foundation, height, fencing shall be
as per tender/construction drawing.
3.6.3.1 Pre-cast reinforced concrete units such as columns, posts, wall panels etc. shall be of grade
M-25 Design Mix. Mix design concrete should be well proportioned, mixed, placed and
thoroughly compacted by mechanical/platform/form vibrators to give a dense concrete
free from voids and honey combing. Fly ash conforming to grade-I of IS: 3812 (Part-1) may
be used as part replacement of OPC as per IS: 456. Uniform blending with cement to be
Technical Specification, Section: Civil Works Page 16 of 80
C/ENGG/SPEC/CIVIL/ Rev-11A/Jun’18
ensured in accordance with clauses 5.2 and 5.2.1 of IS: 456 -2000. Admixtures may be used
with the approval of the engineer-in-charge. However use of any admixture containing
chlorides in any form is prohibited. No admixtures shall be accepted for use in concrete
unless these are tested in accordance with IS: 9103 and the test results are approved by
the Engineer-in-Charge.
3.6.3.2 The forms/ moulds shall be of fiber glass or of steel sections for better finish. Provision
shall be made in the forms and moulds to accommodate fixing devices such as angle for
concertina coils, hooks and forming of notches and holes.
3.6.3.3 The contractor may pre-cast the units on cement or steel platform which shall be
adequately oiled provided the surface finish is of the same standard as obtained in form.
Each unit shall be cast in one operation.
3.6.3.4 Pre-cast articles shall have a dense surface finish showing no coarse aggregate and shall
not have cracks or crevices likely to assist in disintegration of concrete or rusting of steel
or other defects that would interfere with the proper placing of the units. All angles of the
pre-cast units with the exception of the angles resulting from the splayed or chamfered
faces shall be true right angles. Arises shall be clean and sharp except those specified or
shown to be rounded. Gaps if any noticed during installation shall be finished with
1:3cement Mortar. The wearing surface shall be true to the lines. On being fractured, the
interior of the units should present a clean homogeneous appearance.
3.6.3.5 The pre-cast articles shall be matured for 28 days before erection or being built in so that
the concrete shall have sufficient strength to prevent damage to units when first handled.
Date of casting shall be marked on the surface which should not be visible after
installation.
3.6.3.6 The exposed surfaces of walls & columns shall be painted with water proofing cement
paint of approved shade to give an even shade as per BOQ item.
3.6.3.7 Reinforcement as per approved design drawing shall be placed inside the mould in such a
way as to fulfill the minimum cover requirement or as per the drawing. Concrete shall
then be poured in middle and the sides and compacted with a plate vibrator
(platform/table/surface vibrator).
3.6.3.8 Each Pre-cast unit shall have marking like; date of manufacturing and identification
number. Units without marking shall not be accepted.
3.6.3.9 The mould sizes shall satisfy the following dimensional tolerances:
1 Length ±4 mm
2 Width ±2 mm
3.6.3.10 Contractor shall make his own arrangement for curing by making suitable size pond for
curing as directed by Engineer-in-charge. After having been cast in the mould or form the
concrete shall be adequately protected during setting in the first stages of hardening
from shocks and from harmful effects of frost, sunshine, drying winds and cold. The
concrete shall be cured at least for 7 days from the date of placing of concrete in case of
OPC and at least 10 days where mineral admixtures or blended cements are used. In hot
& arid regions, the minimum curing period shall be 14 days.
OR
Pre-cast units shall be stacked against a vertical support in nearly vertical position and
cured for at least two weeks by sprinkling water. If necessary, low pressure steam curing
may be employed. It shall further be air cured for another two weeks before it can be used
for construction. During initial stages of hardening, the Pre-cast units shall be adequately
protected from shocks as well as harmful effects of frost, sunshine, drying winds and cold.
3.6.3.11 SAMPLING
All Pre-cast units (viz. planks and columns) of the same size, manufactured from similar
materials and under similar conditions of production shall be grouped together to
constitute a lot.
Five units shall be selected at random out of a lot consisting of 300 units or less. For lots
bigger than 300 units, 5 units shall be selected for every additional 300 units or part
thereof.
The units shall be selected from the lot at random. In order to ensure randomness of
selection, procedure given in IS: 4905-1968 may be followed. The sampling procedure may
be modified, if the Engineer-In-Charge desires so.
1 Length ±5 mm
2 Width ±3 mm
3 Thickness ±2 mm
If four out of the five samples satisfy the shape (as per the drawing) and dimensional
requirements as tabulated above, the lot represented by the sample shall be deemed to
have passed the dimensional requirements.
Pre-cast units shall be stored, transported and placed in position in such as manner that
they will not be overstressed or damaged.
Pre-cast units shall be transported to the site by suitable means as approved by the
Engineer-In-Charge. Care shall be taken to ensure that no damage occurs during
transportation.
In case the units are to be transported in trolleys, the overhang of the units from the
trolley shall not be more than one-fifth of length of the Pre-cast unit.
For lifting/handling the units, rope slings shall be used at locations where lifting hooks have
been provided. The units shall be lifted manually or with the help of chain pulley blocks or
mechanically with a hoist or a crane. The Pre-cast units shall be handled and transported in
nearly vertical position as far as possible and these should be supported only near the
edges.
Any defect/breakage arising during transportation, due to mishandling or due to faulty
storage practice shall be the sole responsibility of the Manufacturer/Supplier/Agency.
3.6.3.15 ERECTION
Precast concrete columns and wall panel shall be placed in truly vertical position with the
aid of a compatible light crane/manually/by suitable means.
For erection, panels are handled by means of lifting devices/manually to set into columns
wedge. Panels may be carefully placed in successive horizontal position by means of
temporary wooden wedges placed at the junction of the two adjacent panels during
construction and which shall be removed after proper placement of panels.
After placement of wall panels, gaps if any between the wall panels shall be filled with 1:3
cement mortar and shall b finished before taking up of painting. No extra payment shall be
made for filling of joints with cement mortar.
Pre-cast units shall be erected in such a manner that no part is overstressed or damaged
due to faulty erection.
Any defect/breakage occurred during erection shall be the sole responsibility of the
Agency/Manufacturer/Supplier and such units shall not be accepted for use in
construction.
3.6.3.16 MISCELLANEOUS
The work to be performed under this specification shall include providing all labour,
supervision, materials, storages, inventories, all enabling works like scaffolding, watch and
ward for the works, power, fuel, construction equipment, water, tools and plants,
transportation, all taxes and duties, all labour welfare and safety measures, complete and
Technical Specification, Section: Civil Works Page 19 of 80
C/ENGG/SPEC/CIVIL/ Rev-11A/Jun’18
all other incidental items not shown or specified, but reasonably implied or necessary for
successful completion of the work including Contractor’s supervision and in strict
accordance with the drawings and specifications, inspection and testing standards and
field quality control and testing as given in the tender documents and the complete
execution of the works.
Employer reserves the right to inspect all the material before dispatch.
3.6.4 All structural steel angle for supporting barbed wire/concertina coil shall be painted with
epoxy paint of approved brand and colour shade.
4.1 The layout of the area, where anti-weed treatment and stone spreading is to be done,
shall be developed by the Contractor during detailed engineering and the same shall be
submitted to the employer for approval. The Contractor shall arrange all labour,
equipment and materials required for complete performance of the work in accordance
with the drawings, specification and direction of the Employer.
4.2 Stone spreading over cement concrete layer shall be done in the areas of the switchyard
under present scope of work. The cement concrete layer shall also be provided in future
areas within the fenced area. However the stone spreading in future areas shall be
provided in case step potential without stone layer is not well within safe limits.
4.3 The material required for site surfacing/stone filling shall be free from all types of organic
materials and shall be of standard quality, and as approved by the Employer.
4.4 The material to be used for stone filling/site surfacing shall be stone aggregate of 40mm
nominal size (ungraded single size) conforming to Table 2 of IS:383 – 1970. Hardness,
flakiness shall be as required for wearing courses are given below:
i) Sieve Analysis limits (Gradation) (IS : 383 – Table – 2)
Sieve Size % passing by weight
63mm 100
40mm 85-100
20mm 0-20
10mm 0-5
ii) Hardness : Abrasion value (IS:2386 Part-IV) – not more than 40% Impact value (IS:
2386 Part-IV) – not more than 30%.
iii) Flakiness Index : As per IS: 2386 Part – I maximum value is 25%.
4.5 After all the structures/equipments are erected, antiweed treatment shall be applied in
the switchyard where ever cement concrete is to be done and the area shall be thoroughly
de-weeded including removal of roots. The recommendation of local agriculture or
horticulture department may be sought where ever feasible while choosing the type of
chemical to be used.
4.6 The antiweed chemical shall be procured from reputed manufacturers. The doses and
application of chemical shall be strictly done as per manufacturer’s recommendation.
Nevertheless the effectiveness of the chemical shall be demonstrated by the Contractor in
a test area of 10MX10M (appx) and shall be sprinkled with water at least once in the
afternoon every day after forty eight hours of application of chemical. The treated area
shall be monitored over a period of two to three weeks for any growth of weeds by the
Engineer – in- charge. The final approval shall be given by Engineer – in –charge based on
the results.
4.7 Engineer-in-charge shall decide final formation level so as to ensure that the site appears
uniform devoid of undulations. The final formation level shall however be very close to
the formation level indicated in the approved drawing.
4.8 After antiweed treatment is complete, the surface of the switchyard area shall be
maintained, rolled/compacted to the lines and grades as decided by Engineer-in-charge.
The sub grade shall be consolidated by using half ton roller/surface vibrator with suitable
water sprinkling arrangement to form a smooth and compact surface. The roller shall run
over the sub grade till the soil is evenly and densely consolidated and behaves as an elastic
mass.
4.9 In areas that are considered by the Engineer-in-Charge to be too congested with
foundations and structures for proper rolling of the site surfacing material by normal
rolling equipments, the material shall be compacted by hand rammer, if necessary. Due
care shall be exercised so as not to damage any foundation structures or equipment during
rolling / compaction.
4.10 The sub grade shall be in moist condition at the time the cement concrete is placed. If
necessary, it should be saturated with water for not less than 6 hours but not exceeding 20
hours before placing of cement concrete. If it becomes dry prior to the actual placing of
cement concrete, it shall be sprinkled with water and it shall be ensured that no pools of
water or soft patches are formed on the surface.
4.11 Over the prepared sub grade, 75mm thick base layer of cement concrete in 1:5:10 (1
cement: 5 fine aggregate: 10 burnt brick aggregate 40mm nominal size) shall be provided
4.12 The ridge shall be suitably located at the centre of the area between the nearest drains.
The above slope shall be provided at the top of base layer of cement concrete in 1:5:10. A
layer of cement slurry of mix 1:6 (1cement: 6 fine aggregate) shall be laid uniformly over
cement concrete layer. The cement consumption for cement slurry shall not be less than
150 kg for every 100 sq.m.
4.13 A final layer of 100mm thickness of stone aggregate of 40mm nominal size (conforming to
clause 5.2.1) shall be spread uniformly over cement concrete layer after curing is
complete.
Excavation for foundations shall be in accordance with CPWD Specification/ the relevant
BIS code. Excavation shall include removal of all materials of whatever nature at all depth
and whether wet or dry necessary for the construction of foundations. The bottom of
excavation shall be leveled both longitudinally and transversely unless otherwise
mentioned in the drawings or as directed by Engineer-in-charge. Excavation shall be
measured as classified under:-
a) Excavation in all kind of soil including soft/ disintegrated rock, PCC, WBM, Brickwork/
stone masonry etc (excluding hard rock).
5.1 If required the sides of excavations should be supported in such a way as is necessary to
secure these from falling in, and the shoring, if required, shall be provided and maintained
in position as long as necessary. No extra payment shall be made for shoring.
5.2 Whenever water table is met during the excavation, it shall be dewatered and water table
shall be maintained below the bottom of the excavation level during excavation, The
excavation shall be kept free from water:-
When concrete and/or masonry works are in progress and till they come above the
natural water level
Till the Employer considers that the concrete/ mortar is sufficiently set.
5.3 Material unsuitable for foundations shall be removed and replaced by suitable fill material
as per specification and to be approved by the Employer.
Technical Specification, Section: Civil Works Page 22 of 80
C/ENGG/SPEC/CIVIL/ Rev-11A/Jun’18
5.4 Backfill material around foundations or other works shall be suitable for the purpose for
which it is used and compacted. Requirements regarding density / tests of backfilled earth
shall be as specified in Field Quality Plan. The sub-grade for the roads and embankment
filling shall be compacted to minimum 95% of the Standard Proctor’s density at OMC
(optimum moisture content). Cohesion less material sub-grade shall be compacted to 70%
relative density (minimum).
5.5 If, excavated material is not suitable or not required for backfill, it shall be disposed off in
areas as directed by Employer up to a maximum lead of 2 km from the substation
boundary.
5.7.1 The thickness of fill material under the foundations shall be such that the maximum
pressure from the footing, transferred through the fill material and distributed onto the
original undisturbed soil will not exceed the allowable soil bearing pressure of the original
undisturbed soil.
5.7.2 The filling shall be done in accordance with clause 4.10 of IS: 1080. For expansive soils the
fill materials and other protections etc. to be used under the foundation is to be got
approved by the Employer.
5.7.3 Cohesive Non Swelling (CNS) soil, if required, for filling under / around the foundations,
cable trenches, drains, roads etc shall confirm to IS: 9451: 1994 reaffirmed 2004
6.0 CEMENT:
6.1 The type of cements which can be used are Portland Pozzolana cement (conforming to
IS:1489), Ordinary Portland cement (conforming to IS:269 or IS:8112 or IS:12269), and
Portland Slag cement. (Conforming to IS: 455). Cement shall be arranged by contractor.
6.3 Extra care for curing shall be taken for concrete made with OPC 53 grade & PPC.
6.4 Extra care for removing form work shall be taken, when PPC is used.
6.5 Portland Slag Cement has low heat of hydration and is relatively better resistant to soils
and water containing excessive amount of sulphates of alkali metals, alumina and iron, as
well as to acidic waters. Hence it can be specifically allowed for above conditions with prior
approval of EIC.
7.1 Use of chemical admixtures shall be permitted in accordance, with the provisions of
IS 456 and IS 9103.
7.2 It shall be the responsibility of the producer to establish compatibility and suitability
of any admixture with the other ingredients of the mix and to determine the dosage
required to give the desired effect. The amount of admixture added to mix shall be
recorded in the production record by the producer.
7.3 Admixtures should be stored in a manner that prevents degradation of the product
and consumed within the time period indicated by the admixture supplier. Any
vessel containing an admixture in the plant or taken to site by the producer shall be
clearly marked as to its content.
7.4 When offering or delivering a mix to a purchaser it should be indicated if such a mix
contains an admixture or combination of admixtures or not. The admixtures may be
identified generically and should be declared on the delivery ticket.
All RCC work including material properties, proportioning, batching, mixing, transporting,
pouring, compacting, finishing, curing, sampling, testing, acceptance criterion etc. shall be
as per IS : 456-2000 (or latest)
8.1.1 For new substations and extensions except minor works, Reinforced cement concrete shall
be M-25 design mix conforming to IS: 456. IS: 10262 shall be followed for mix
8.1.2 Design mix concrete may be procured from approved RMC plant as per latest IS: 4926 or
may be prepared by using a portable/mini/compact weigh batch plant conforming to latest
IS: 4925
8.1.3 As per provisions of IS: 456, fly ash conforming to grade I of IS: 3812 (part-1) may be used
as part replacement of cement, when OPC cement is used for concrete works. Uniform
blending with cement is to be ensured.
8.2.1 Use of volumetric mix concrete shall be restricted to minor works only (as per clause 8.1.1)
with approval of engineer incharge. In such cases reinforced cement concrete shall be of
volumetric mix 1:1.5:3 (1 cement: 1.5 coarse sand: 3 well graded stone aggregate 20mm
nominal size) conforming to CPWD specifications. Volumetric mix 1:1.5:3 shall be
considered equivalent to M-20.
8.2.2 In case of volumetric mixes, Standard measuring boxes of 35cmX40cmX25cm (35 liters
capacity as per CPWD) shall be used for measuring fine and coarse aggregates.
8.2.3 However, full 50 kg of OPC/PPC/Slag cement shall be directly unloaded into the mixer
hopper to ensure that cement consumption is 400kg per cum of 1:1.5:3 concrete
irrespective of different types of cements with different densities.
8.2.4 The cement consumption shall be as per DSR (CPWD) for other grades of concretes
provided as volumetric concrete in the BPS.
8.2.5 For volumetric mix concretes, the cement used may be generally PPC type, however
concrete may be prepared with OPC also, without any financial implication to
POWERGRID.
The following clauses are applicable for the design and drawings which are to be
developed during detailed engineering either by contractor/ vendor or by employer as per
section project.
10.1.1 For AIS Substations: Control room building shall be of RCC framed structure & brickwork
(Conventional).
For GIS Substations: Control room building shall be of RCC framed structure with
brickwork; however its alignment shall be in line with GIS hall & may/may not be
attached to GIS hall as per detail engineering.
10.1.2 In case of extension of Control room building, the same shall be matched with existing
building, whether it is PEB or Conventional.
10.1.3 All walls shall be of non-load bearing Minimum wall thickness of full brick with 1:6
cement sand mortar. Partition walls in toilets and pantry can be half brick walls with 1:4
cement sand mortar and two nos. 6mm dia MS bars at every third course. CPWD
specifications shall be followed for brick masonry work.
10.1.4 Partitions, if any required shall be made of powder coated aluminium frame (minimum
thickness of powder coating is 50 micron) provided with minimum 5.5mm thick clear
glass or pre-laminated board depending upon the location of partition.
10.1.5 The details of doors and windows of the control room building shall be as per finish
schedule Table-1.
10.1.6 IS approved or ISI Marked PVC electrical conduits of shall be provided as per the
requirement of electrical installations including its accessories, junction boxes/surfaces
boxes, fan boxes etc. Areas where false ceiling is provided electrical conduit may be laid
on exposed surfaces of walls or ceiling, above false ceiling area. In rest areas conduits &
junction boxes, fan boxes etc. shall be concealed.
10.1.7 Contractor shall develop conduit layout drawing based on electrical illumination &
Electrical installation drawings approved by POWERGRID. For control Room conference
Hall/Admin Hall conduits are also to be provided below floor tiles for extending power
supply/internet cables to Conference table users/ Admin Cubicles.
10.1.9 The area for above provisions shall be suitably decided by bidder during detailed
engineering stage in consultation with employer.
10.1.10 Control room building shall be so designed that most of the area of switchyard is visible
from control room.
10.1.11 Open cable trenches in the building shall be covered with minimum 6mm thick steel
chequered plate with suitable stiffeners. Chequered plate shall be painted with two or
more coats of epoxy paint as per item 13.52 of DSR’ 2014 over a coat of steel primer.
10.1.12 The isometric view of the CRB with local aesthetic and best industry practices shall be
submitted by vendors for approval of POWERGRID. Three alternatives of colored
isometric views with different color shades shall be submitted for approval.
10.1.13 All flooring area other than foundations shall be designed as industrial floor with
minimum 100 mm thick RCC floor slab, laid over well compacted stone soiling of
minimum 200 mm thick using stone of size 150 mm & below with interstices filled with
sand over well compacted earth.
10.2.1 The New GIS building shall be of pre-engineered steel structure. GIS building consist of
GIS hall, Room for control, protection & communication panels and AHU room. Provision
for service bay and future extension of the building shall be made. During extension
works in GIS hall, to keep the existing part of the building dust free, a temporary partition
sheet of suitable material and strength shall be provided without any additional cost to
POWERGRID. The same shall be removed after completion of work and taken back by
contractor. Suitable space shall be provided to facilitate maintenance of GIS equipments.
Panels shall be kept in an air-conditioned enclosure. The building shall be designed for
future expansion also. Building shall be designed in such a manner that the same crane
shall be extended in future expansion. Loads, structural design, fabrication & erection,
material etc. of PEB structure shall be as per BIS standards
10.2.3 Size of the building shall be as per requirement of GIS modules, panel, O&M needs and
housekeeping considerations. Any clearance required as per Electricity Act or any other
Standard shall also be kept. Separate fire escape doors shall also be provided in the GIS
Building
10.2.4 A Glazed partition made of aluminum extruded sections powder coated frame (min. 50
micron powder coating) and 5.5 mm (min) thick glass shall be provided between GIS hall
and panel room. The total height of glazed partition shall 3000 mm above FFL include sill
level of 900mm. Up to sill level full brick masonry wall to be provided and finished with
Non-VOC acrylic emulsion paint to give an even shade on plastered surface over 2mm
POP putty.
10.2.5 Over all Width of crane walk way shall not be less than 1.0m and shall be provided at
gantry girder level on the two longer side of GIS hall along with climbing arrangement to
facilitate maintenance of crane. Suitable arrangement shall be made on top of the crane,
to facilitate maintenance of lighting fixtures. Structural steel of walkway shall be finished
with priming coat of standard steel primmer followed by one coat of epoxy paint and
final coating of PU (Minimum 100 Micron). The minimum clear height of the building
shall be kept 1800 mm from the top of walk way or 600 mm above the top most point of
crane, whichever is higher.
10.2.6 The base plate of steel columns shall be mounted on the RCC foundation by means of hot
dip galvanized foundation bolts (The zinc coating shall be minimum 610 gram per square
meter. In case the substation is located within 30km from sea coast, the zinc coating
shall be 900gm per square meter. The purity of zinc shall be 99.95% as per IS: 209). The
RCC pedestal shall not protrude above floor level to avoid obstruction in the movement.
10.2.7 PVC electrical conduits of ISI marked or IS approved shall be provided as per the
requirement of electrical installations its accessories, junction boxes/surfaces boxes, fan
boxes etc. Areas where false ceiling is provided and on puff panels, electrical conduit may
be laid on exposed surfaces of walls or ceiling, above false ceiling area. In rest area
conduit & junction boxes, fan boxes etc. shall be concealed wherever brick wall/RCC is
provided.
10.2.8 The walls of GIS building and the attached relay room shall be of full brick and up to a
height of 150mm above false ceiling level of relay room. Rest portion shall be provided
with puff sandwiched panels as mentioned elsewhere in TS.
10.2.10 Colour Scheme matching with local aesthetic and best industry practices shall be
submitted by vendors for approval of POWERGRID. Three alternatives of coloured
isometric views with colour codes shall be submitted for approval. The monotony of
external colour of sheet shall be avoided by providing vertical bands of different coloured
sheet. The colour of roof sheet shall be light coloured to minimize heat absorption.
External and internal masonry walls shall be painted with suitable approved colour in
consultation with Employer.
10.2.11 All external openings for duct entries shall be provided with all round sunshade/chajjas to
ensure that no rain water shall directly splashes on the sealant.
10.2.12 All flooring area other than foundations shall be designed as industrial floor with
minimum 100 mm thick RCC floor slab, laid over well compacted stone soiling of
minimum 200 mm thick using stone of size 150 mm & below with interstices filled with
sand over well compacted earth and with floor finish as per table - 1.
10.3.1 To the requirements of the National Building Code of India, and the standards quoted
therein.
10.3.2 For the specified climatic & loading conditions.
10.3.3 To adequately suit the requirements of the equipment and apparatus contained in the
buildings and in all respects to be compatible with the intended use and occupancy.
10.3.5 To be aesthetically pleasing. Different buildings shall show a uniformity and consistency
in architectural design.
10.3.6 To allow for easy access to equipment and maintenance of the equipment.
10.3.7 With wherever required, fire retarding materials for walls, ceilings and doors, which
would prevent supporting or spreading of fire.
10.3.10 With anti-termite treatment, plinth protection, DPC, peripheral drain, sanitary, water
supply, electrification etc.
10.3.11 With the building lighting, in accordance with the requirements of relevant section.
10.3.12 With the building auxiliary services like air conditioning and ventilation systems, fire
protection and detection systems and all other miscellaneous services, in accordance
with the requirements specified in relevant section or elsewhere in this Specification.
10.3.13 Most critical combinations of dead loads, super- imposed loads, equipment loads, crane
load, wind loads, Snow load, seismic loads, any other load etc whichever is applicable
shall be considered.
10.3.14 The individual members of the buildings frame shall be designed for the worst
combination of forces such as bending moment, axial force, shear force, torsion
deflection etc.
10.3.15 The permissible stresses for different load combinations shall be taken as per relevant
BIS Codes.
10.3.16 All structures and its components must be designed and detailed as per latest BIS
standards incorporating ductile detailing. List of reference codes e.g IS 456-2000 (latest),
IS 875 all parts, IS 1893 all parts, IS 4326, IS 13920,SP34 etc.
10.3.17 RCC columns shall be provided with rigid connection at the base.
10.3.18 The design of steel structures for the Pre-engineered buildings shall be done in
accordance with IS: 800-2007 with limit state method or elsewhere mentioned in section
project.
10.3.19 Limit state method of Concrete design shall be adopted unless specified otherwise in the
specification.
10.3.21 Expansion joints wherever necessary with provision of twin columns shall be as per the
provisions of relevant IS or National building codes.
10.3.22 Any sub-soil water encountered at founding level, same shall be considered in the
i) Dead loads shall include the self-weight of all structures complete with finishes, fixtures
and partitions.
ii) In addition, RCC beams shall be designed for any incidental point loads to be applied at any
point along the beams if applicable.
i) Super-imposed loads in different areas shall include live loads, minor equipment loads,
cable trays, small pipe racks/hangers and erection, operation and maintenance loads
wherever these loads are expected. Equipment loads shall constitute, if applicable, all load
of equipments to be supported on the building frame.
ii) Floors/slabs shall be designed to carry loads imposed by equipment, cables and other
loads associated with building. Cable load shall also be considered additionally for floors
where these loads are expected.
iii) The floor loads shall be subject to Employer’s approval. Floors shall be designed for live
loads as per relevant IS 875 part 2 (latest), however, for Buildings, the following loads may
be considered.
Toilets 2 kN/m2
Chequered plate 4 kN/m2
floor
Walkways 3 kN/m2
iv) For crane loads an impact factor of 30% and lateral crane surge of 10% (lifted weight +
trolley) shall be considered in the analysis of frame according to provisions of IS:875. The
horizontal surge shall be 5% of the static wheel load. Crane load shall be applied as per the
requirement of building.
i) The wind loads shall be computed as per IS 875 part 3 (latest), the class of structure for
design, k1 factor, shall be considered under the category as ‘important buildings and
structures like hospitals, communication buildings/towers, power plant structures’ for
Control Room building, GIS hall, Towers, Gantries, equipment structure. For other
buildings/structures wind loads shall be computed as per IS 875 part 3 (latest).
ii) Wind and Seismic forces shall not be considered to act simultaneously.
i) Seismic Coefficient method/Response Spectrum method shall be used for the seismic
analysis as per IS: 1893: Part 1 with importance factor 1.5.
ii) Wind and Seismic forces shall not be considered to act simultaneously.
i) The critical load combinations for design of RCC structures shall be computed or generated
by using IS: 875 Part-5 (latest), IS: 456 (latest), IS: 1893- part 1 (latest).
ii) The critical load combinations for design of Steel structures shall be computed or
generated by using IS: 875 Part-5 (latest), IS: 800, IS: 1893- part 1 (latest).
10.5.1 All foundation shall be of reinforced cement concrete. The design and construction of RCC
structures shall be carried out as per IS: 456. Minimum 75mm thick lean concrete (1:4:8)
shall be provided below all underground structures, foundations, trenches etc. to provide
a base for construction
10.5.2 The switchyard foundation’s plinths shall be minimum 300mm and buildings plinth shall be
minimum 600 mm above finished ground level respectively. If the site is sloping, the
foundation height will be adjusted to maintain the exact level of the top of structures to
compensate such slopes.
10.5.3 The tower and equipment foundations shall be checked for a partial factor of safety of 2.2
for normal condition and 1.65 for short circuit condition.
10.5.4 The design and detailing of foundations shall be done based on the approved soil data and
sub-soil conditions as well as for all possible critical loads and the combinations thereof.
The Isolated/ Combined/ Strip footings / Raft or pile foundation as may be required based
on soil/sub-soil conditions and superimposed loads shall be provided
10.5.5 The procedure used for the design of the foundations shall be the most critical loading
combination of the steel structure and or equipment and/or superstructure and other
conditions which produces the maximum stresses in the foundation or the foundation
component and as per the relevant BIS Codes of foundation design. Detailed design
calculations shall be submitted by the bidder showing complete details.
10.5.6 Necessary protection to the foundation work, if required shall be provided to take care of
any special requirements for aggressive alkaline soil, black cotton soil or any other type of
soil which is detrimental/harmful to the concrete foundations.
10.5.7 If pile foundations are adopted, the same shall be cast-in-situ bored or pre-cast or under
reamed type as per relevant parts of IS: 2911. Only RCC piles shall be provided. Necessary
initial load test shall be carried out by the Contractor to establish the pile design capacity.
Only after the design capacity of pile has been established, the Contractor shall take up the
job of piling. Routine tests for the pile shall also be conducted as per IS: 2911/IS :10262. All
the testing work shall be planned in such a way that these shall not cause any delay in
project completion. RCC for pile works shall be Design Mix of minimum grade M-25 and
also minimum cement content shall be 400Kg/ cu.m as per IS:2911 (Latest revision). In
case extra cement is required to meet the provisions of IS: 2911, it will be paid extra.
10.6.1 The foundations of Transformer & Reactor shall be of block type foundation. Minimum
reinforcement shall be governed by IS: 2974 and IS: 456. In case of Reactor Plan
dimension of block should not be less than size of base of reactor.
10.6.2 The Contractor shall provide a RCC Rail cum road system integrated with the
Autotransformer / Reactor foundation to enable installation and the replacement of any
failed unit. The transfer track system shall be suitable to permit the movement of any
failed unit fully assembled (including OLTC, bushings) with oil.
10.6.3 This system shall enable the removal of any failed unit from its foundation to the
nearest road. If trench/drain crossings are required then suitable R.C.C. culverts shall be
provided in accordance with I.R.C. standard / relevant IS.
10.6.4 The Contractor shall provide a pylon support system for supporting the firefighting
system.
10.6.5 Each Autotransformer/Reactor including oil conservator tank and cooler banks etc. shall
be placed in a self-sufficient pit surrounded by retaining walls (Pit walls). The clear
distance of the retaining wall of the pit from the Autotransformer/Reactor shall be 20%
of the Autotransformer/Reactor/ cooler bank height or 0.8m whichever is higher. The
oil collection pit thus formed shall have a void volume equal to 200% volume of total oil
in the Autotransformer/Reactor. In case of transformers of 132kV and below, where
hydrant system for firefighting is not provided, volume of pit may be reduced to 130%
of total oil volume. However, in case common oil pit is envisaged during detailed
engineering, the individual oil collection pit thus formed shall have a void volume equal
to 33% volume of total oil in the Autotransformer/Reactor. The common oil collection
pit shall have a void volume equal to 200% volume of maximum total oil of either
Autotransformer or Reactor.
10.6.6 The minimum height of the retaining walls of pit shall be 20 cm above the finished level
of the ground to avoid outside water pouring inside the pit. The bottom of the pit shall
have a uniform slope towards the sump pit. While designing the oil collection pit, the
movement of the autotransformer / reactor must be taken into account.
10.6.7 The grating shall be made of MS flat of size 30mm x 5mm placed at 30mm centre to
centre and 6mm dia MS bar at spacing of 150mm at right angle to each other.
10.6.8 Each oil collection pit shall be drained towards a sump pit of size 1000X750mm and
500mm deep below the floor level within the collection pit whose role is to drain water
and oil due to leakage within the collection pit so that collection pit remains dry.
10.7.1 The construction of fire walls shall be cast in situ type or pre cast RCC as per drawings and
meeting the technical specification.
10.7.2 The firewall shall have a minimum fire resistance of 4 hours. The walls of the building,
which are to be used as firewalls, shall have also a minimum fire resistance of 4 hours. The
firewall shall be designed to protect against the effect of radiant heat and flying debris
from an adjacent fire.
10.7.3 The firewall shall extend 600 mm on each side of the Autotransformer or Reactors and 600
mm above the conservator tank or safety vent. A minimum of 2.0 meter clearance shall be
provided between the equipment’s e.g. Autotransformer or Reactors and firewalls. In case
of space constraints, these dimensions can be reduced as per the approval of Employer.
10.7.4 The building walls, which act as firewalls, shall extend at least 1 m above the roof or 600
mm above the conservator tank or safety vent, whichever is maximum, in order to protect
it.
10.7.5 The firewall will be made of reinforced cement concrete with smooth surfaces devoid of
honey comb, undulations etc. and shall be finished with water proofing cement paint of
approved colour.
10.8 DESIGN OF WATER TANKS, CHANNELS, SUMPS, TRENCHES AND OTHER UNDER-GROUND
STRUCTURES:
10.8.1 RCC water retaining structures like storage tanks, etc. shall be designed as un-cracked
section in accordance with IS: 3370 (Part I to IV) by working stress method. In case of
10.8.2 All sub-structures shall be checked for sliding and overturning stability during both
construction and operating conditions for various combinations of loads. Factors of safety
for these cases shall be taken as mentioned in relevant BIS Codes or as stipulated
elsewhere in the Specifications. For checking against overturning, weight of soil vertically
above footing shall be taken and inverted frustum of pyramid of earth on the foundation
should not be considered.
10.8.3 Earth pressure for all underground RCC structures like cable trenches, underground water
tanks, Oil collection pits, Septic tanks, basements etc. shall be calculated using co-efficient
of earth pressure at rest, co-efficient of active or passive earth pressure (whichever is
applicable). However, for the design of substructures of any underground enclosures,
earth pressure at rest shall be considered.
10.8.4 In addition to earth pressure and ground water pressure etc., a surcharge load of 2T/Sq.m
shall also be considered for the design of all underground structures for the vehicular
traffic in the vicinity of the structure.
10.8.5 Underground tanks shall be checked for full water pressure from inside and no earth
pressure & ground water pressure & surcharge pressure from outside (application only to
structures which are liable to be filled up with water or any other liquid). They shall also be
checked for full earth pressure, surcharge pressure and ground water pressure from
outside and no water pressure from inside.
10.8.6 Design shall also be checked against buoyancy due to the ground water during
construction and maintenance stages. Minimum factor of safety of 1.5 against buoyancy
shall be ensured ignoring the superimposed loadings. Base slab of any underground
enclosure shall also be designed for empty condition during construction and maintenance
stages with maximum ground water table (GWT). Minimum factor of safety of 1.5 against
buoyancy shall be ensured ignoring the super-imposed loadings.
10.8.7 Base slab of any underground enclosure like water storage tank shall also be designed for
the condition of different combination of pump sumps being empty during maintenance
stages with maximum GWT. Intermediate dividing piers of such enclosures shall be
designed considering water in one pump sump only and the other pumps sump being
empty for maintenance.
10.9 INTERNAL FINISH SCHEDULE FOR BUILDING & GIS HALL EITHER RCC/ PEB:
10.9.1 Internal finishing Schedule for control room building and GIS hall is given in Table - 1
below: The Locations, which are not specified in finish schedule, shall be provided with
Table-1
Sr. FLOORING WALL CEILING DOOR, WINDOWS &
No & SKIRTING (INTERNAL) VENTILATOR
LOCATION
. 150MM
HIGH
1 Control Vitrified Non VOC False ceiling Windows shall be of min.
Room tiles size acrylic painted with 10mm thick laminated
600 x emulsion paint Non VOC acrylic float safety glass
600mm over 2mm POP emulsion paint conforms to IS: 2553
(DSR Item putty upto to give an even (Part-I) by using suitable
11.46) false ceiling shade. powder coated
over approved aluminum extruded
primer coat sections peripheral
frame. The glazed
window shall be provided
between column to
column horizontally and
vertically from sill level of
0.75 m to bottom false
ceiling. In a window 2 to
3 vertical pieces may be
provided depending
upon the availability of
glass and the vertical
joint shall be sealed with
silicon sealant. All doors
shall be glazed powder
coated aluminium doors
with minimum 5.5 mm
thk. glass
2 Confer- Vitrified Non VOC False ceiling All doors, windows,
ence tiles size acrylic painted with ventilators shall be of
Room 600 x emulsion paint Non VOC acrylic uPVC with minimum
600mm over 2mm POP emulsion paint 5.5.mm thk. Glazing.
(DSR Item putty upto to give an even
11.46) false ceiling shade.
8 Lobby 18mm thick Non VOC False ceiling All doors, windows,
granite acrylic painted with ventilators shall be of
flooring ( emulsion paint Non VOC acrylic uPVC with minimum
DSR Item ove r2mm POP emulsion paint 5.5.mm thk. Glazing.
8.12) putty upto to give an even
false ceiling shade.
over approved
primer coat
9 Corridor Vitrified Non VOC False ceiling All doors, windows,
tiles size acrylic painted with ventilators shall be of
600 x emulsion paint Non VOC acrylic uPVC with minimum
600mm over 2mm POP emulsion paint 5.5.mm thk. Glazing.
(DSR Item putty upto to give an even
11.46) false ceiling shade.
over approved
primer coat
10 Portico for 18mm thick Granite Non VOC acrylic All doors, windows,
RCC granite cladding emulsion paint ventilators shall be of
Building flooring( over approved uPVC with minimum
DSR Item primer coat 5.5.mm thk. Glazing.
8.12)
11 Toilet Ceramic DADO glazed Non VOC acrylic All windows, ventilators
tiles (DSR tile 2100mm emulsion paint shall be of uPVC with
item 11.38) high, above over approved minimum 5.5.mm thk.
that non VOC primer coat for Glazing.
acrylic RCC building / All doors shall be flush
emulsion paint False ceiling door shutters made of
over 2 mm shall be pre-laminated particle
thick POP provided in-case board (DSR 9.131 &
putty along of PEB building. 9.132) with powder
with primer coated aluminum frame.
coat.
12 Janitor Ceramic DADO glazed Non VOC acrylic All windows, ventilators
room tiles (DSR tile 2100mm emulsion paint shall be of uPVC with
item 11.38) high, above over approved minimum 5.5.mm thk.
that non VOC primer coat for Glazing.
acrylic RCC building / All doors shall be flush
emulsion paint False ceiling door shutters made of
Technical Specification, Section: Civil Works Page 39 of 80
C/ENGG/SPEC/CIVIL/ Rev-11A/Jun’18
over 2mm thk. shall be pre-laminated particle
POP putty provided in-case board (DSR 9.131 &
along with of PEB building. 9.132) with powder
primer coat. coated aluminium frame.
13 GIS 62mm thick Non VOC In case of RCC All doors, windows,
Hall cement acrylic roof, ceiling ventilators shall be of
concrete emulsion paint shall be finished uPVC with minimum
flooring over 2mm POP with Non VOC 5.5.mm thk. Glazing.
with putty upto acrylic emulsion
hardener. false ceiling paint over
Two coats over approved approved
of PU primer coat primer coat.
coating over plastered
over the surface
floor shall
be
provided.
over the
total area
(Present +
Future).
The final
coat of PU
shall be
applied
after
Installation
of
equipments
. Total
thickness of
PU coats
shall be
minimum
300
microns.
uPVC doors, windows, ventilators shall be sliding or openable or partially openable/partially fixed
or fixed type of factory made uPVC doors, windows (casement/sliding), ventilators, fixed glazing
and partitions as per DSR ’16 item no. 9.147A to 9.147F.
10.10.1 For the locations of false ceiling refer table -1 above, unless otherwise specified
elsewhere in tender documents.
10.10.2 15mm thick densified tegular edged eco friendly light weight calcium silicate false ceiling
tiles of approved texture spintone/cosmos/ Hexa or equivalent of size 595x595 mm in
true horizontal level, suspended on inter locking metal grid of hot dipped galvanised
steel sections (galvanising @ 120 grams per sqm. Including both side).
Consisting of main ‘T’ runner suitably spaced at joints to get required length and of size
24x38 mm made from 0.33 mm thick (minimum) sheet, spaced 1200 mm centre to
centre, and cross ‘T’ of size 24x28 mm made out of 0,33 mm (minimum) sheet, 1200 mm
long spaced between main ‘T’ at 600 mm centre to centre to form a grid of 1200x600
mm and secondary cross ‘T’ of length 600 mm and size of 24x28 mm made of 0.33 mm
thick (minimum) sheet to be interlocked at middle of the 1200x600 mm panel to form
grid of size 600x600 mm, resting on periphery walls/partitions on a perimeter wall angle
precoated steel of size (24x24x300 mm made of 0.40 mm thick (minimum) sheet with
Main ‘T’ runners to be suspended from, ceiling using G.I. slotted cleats of size 25x35x1.6
mm fixed to ceiling with 12.5 mm dia and 50 mm long dash fasteners, 4 mm G.I.
adjustable rods with galvanised steel level clips of size 85x30x0.8 mm, spaced at 1200
mm centre to centre along main ‘T’, bottom exposed with 24 mm of all T-section shall be
pre-painted with polyester baked paint, for all heights, as per specifications, drawings
and as directed by engineer- in-charge.
10.11.1 Integral cement based water proofing treatment including preparation of surface as
required for treatment of roofs, balconies, terraces etc consisting of following operations:
a) Applying a slurry coat of neat cement using 2.75 kg/sqm. of cement admixed with water
proofing compound conforming to IS. 2645 and approved by Engineer-in-charge over the
RCC slab including adjoining walls upto 300mm height including cleaning the surface
before treatment.
b) Laying brick bats with mortar using broken bricks/brick bats 25 mm to 115 mm size with
50% of cement mortar 1:5 (1 cement : 5 coarse sand) admixed with water proofing
compound conforming to IS : 2645 and approved by Engineer-in-charge over 20 mm thick
layer of cement mortar of mix 1:5 (1 cement :5 coarse sand ) admixed with water proofing
compound conforming to IS : 2645 and approved by Engineer-in-charge to required slope
and treating similarly the adjoining walls upto 300 mm height including rounding of
junctions of walls and slabs
c) After two days of proper curing applying a second coat of cement slurry using 2.75 kg/ sqm
of cement admixed with water proofing compound conforming to IS : 2645 and approved
by Engineer-in-charge.
d) Finishing the surface with 20 mm thick joint less cement mortar of mix 1:4 (1 cement :4
coarse sand) admixed with water proofing compound conforming to IS : 2645 and
approved by Engineer-in-charge including laying glass fibre cloth of approved quality in top
layer of plaster and finally finishing the surface with trowel with neat cement slurry and
making pattern of 300x300 mm square 3 mm deep.
e) The whole terrace so finished shall be flooded with water for a minimum period of two
weeks for curing and for final test. All above operations to be done in order and as
directed and specified by the Engineer-in-Charge
10.11.2 Alternatively in case of non- availability of good quality of brick bats, the water proofing
treatment can also be done in the following manner:
The water proofing membrane shall be laid on the RCC slab without any break. The grading
concrete (1:2:4) of average thickness of 50 mm with water proofing compound as per
manufacturer’s specification shall be laid over the membrane. Cement concrete flooring of
40mm thick with (1cement: 2 fine aggregate: 4 stone aggregate 20mm graded stone
aggregate) finished with a floating coat of neat cement including cement slurry complete
shall be laid over grading concrete and checkered pattern in the grid of 300mm x 300mm
shall be made .
Water proofing treatment shall be done in sunken portion of WCs, bathroom etc. by
applying cement slurry mixed with water proofing cement compound consisting of:
a) First layer of slurry of cement @ 0.488 kg/sqm mixed with water proofing cement
compound @ 0.253 kg/ sqm. This layer will be allowed to air cure for 4 hours.
b) Second layer of slurry of cement @ 0.242 kg/sqm mixed with water proofing cement
compound @ 0.126 kg/sqm. This layer will be allowed to air cure for 4 hours followed with
water curing for 48 hours.
Treatment and sealing of joints, corners, junction of pipes and masonary with polymer
mixed slurry shall be carried out as per CPWD specifications.
10.12.1 All plumbing and sanitation shall be executed to comply with the requirements of the
appropriate bye-laws, rules and regulations of the Local Authority having jurisdiction
over such matters. The Contractor shall arrange for all necessary formalities to be met in
regard to inspection, testing, obtaining approval and giving notices etc.
10.12.3 Each toilet shall be provided with Water Closet, Wash hand basin, health faucet, Mirror,
Towel Rail, Paper Holder, Liquid soap dispenser, twin coat holder.
10.12.4 In addition to general requirements of each toilets, 2 nos. Sensor based urinals shall be
provided for common Gents toilet.
10.12.7 The specification of different items, which are to be used for plumbing, sanitation &
water supply etc. in are given below, the same shall be used during detailed engineering,
unless otherwise mentioned else-where in the tender.
S.No. Items Description
1 Wall hung Coloured vitreous china extended wall mounting water closet of
Water Closet approved size and shape including providing & fixing white vitreous
china cistern with dual flush fitting, of flushing capacity 3 litre/6 litre
(adjustable to 4 litre/8 litres), including seat cover, and cistern
fittings, nuts, bolts and gasket etc complete.
2 Squatting Pan (Indian type W.C. pan ) (white vitreous china Orissa pattern W.C. pan
of size 580x440mm with integral type foot rests) shall be with
100mm sand cast iron P or S trap. 10 litre low level white P.V.C
flushing cistern with manually controlled device (handle lever)
conforming to IS:7231, with all fittings and fixtures complete
including cutting and making good the walls and floors wherever
required.
3 Wash Basin Providing and fixing coloured wash basin counter type of
(approximate size 630x450mm size under counter or over counter
type), in case flat bash hand is required the approximate size shall be
550x400mm and shall be provided with C.P. close basin mixer (ISI
approved) with CI. Brackets taps with battery based infrared
sensor, 32mm C.P. brass waste and bottle trap of standard pattern,
including painting of fittings and brackets, cutting and making good
the walls wherever required. Other details shall be as per the
drawings.
4 Urinal White vitreous china battery based infrared sensor operated urinal
of approx. size 610 x 390 x 370 mm having pre & post flushing with
water ( 250 ml & 500 ml consumption), having water inlet from back
side, including fixing to wall with suitable brackets all as per
manufacturers specification and direction of Engineer-in-charge.
5 Urinal 10mm thk toughened glass partition with frosted film to be fixed in
partition position for urinals on appropriate stainless steel patch fittings of
desired shape and size
6 Kitchen sink Stainless steel AISI 304 (18/8) Kitchen sink of 510x1040 mm bowl
with depth of 178mm with drain board shall be provided and fixed
as per IS 13983 with C.I brackets, and stainless steel plug 40mm with
provision of 2 nos. CP brass long body bib cock conforming to IS
Standard and weighing not less than 650 gm for CP bottle trap etc.
Technical Specification, Section: Civil Works Page 44 of 80
C/ENGG/SPEC/CIVIL/ Rev-11A/Jun’18
including painting of fittings and brackets, cutting and making good
the wall.
7 Bib cock C.P. brass short body and long body bib cock 15mm nominal bore
shall be of approved quality conforming to IS: 8931.
8 Angle valve C.P. brass angle valve of 15mm nominal bore provided and fixed in
position for basin and cistern points of approved quality conforming
IS :8931.
9 Towel rail C.P. brass towel rail of approved make of 600mm length, 25mm dia
with a pair of brackets or flanges provided and fixed to wall beside
each wash basin/set of wash basin with necessary screws, plugs, etc.
11 Hooks Double type coat & hat hooks with flanges, fixed to wall / shutter,
etc. with necessary screws, washers & plugs.
12 Liquid soap C.P. brass liquid soap holder of approved make fixed with each wash
holder basin to the wall with necessary CP brackets, CP screws, washers,
plugs etc.
13 C.P. Brass or Approved C.P. Brass cockroach trap shall be provided in the Kitchen,
S.S. cockroach Toilets and pantry
trap
14 Floor traps PVC floor traps of self cleansing design shall be provided & fixed in
position with 100 mm dia. inlet and 75mm dia. outlet of approved
make, including making connection with PVC soil/waste pipes using
rubber gaskets, embedding the trap in 150 mm thick PCC 1:2:4.
15 Internal Soil, Unplasticised rigid PVC pipes of 75mm for waste & 110mm dia for
waste and soil shall be provided conforming to IS:13592 type B and all its
vent pipe fittings like bends, sockets, door bend, Y-tee etc. as per requirement
with seal ring conforming to IS: 5382 including jointing with cement
solvent conforms to IS:14182. All underground or under floor pipes
shall be encased with 1:3:6 concrete. Minimum concrete cover shall
be 75 mm thk.
20 External Glazed stoneware pipes of 100 & 150mm diameter grade 'A' shall be
Sewerage provided, laid and jointed with stiff mixture of cement mortar in the
proportion of 1:1 (1cement :1 fine sand ) including testing of joints
etc. complete. SW pipes shall be encased with Cement concrete
1:5:10 (1 cement: 5 coarse sand: 10 graded stone aggregate 40 mm
nominal size) including bed concrete as per CPWD standard design
and CPWD specifications. In case of non-availability of SW Pipe,
contractor may use UPVC Pipe of similar dia with the prior approval
of EIC without any financial implication to POWERGRID.
21 Gully trap 100x100 mm or 150x100 mm size P type Square-mouth S.W. gully
trap class SP-1 complete with C.I. grating brick masonry chamber
and water tight C.I. cover frame o f 300 x300 mm size (inside), the
weight of cover to be not less than 4.50 kg and frame to be not less
than 2.70 kg as per standard design. FPS Bricks class designation 75
shall be provided for brick masonry chamber.
22 Manholes FPS brick masonry manhole shall be constructed in cement mortar
1:4 (1 cement :4 coarse sand ) RCC top slab with 1:2:4 mix ( 1
cement : 2 fine aggregate : 4 graded stone aggregate 20 mm
nominal size ) foundation concrete 1:4:8 mix ( 1cement : 4 coarse
sand :8 graded stone aggregate 40 mm nominal size ) inside
plastering 12 mm thick with cement mortar 1:3 (1 cement : 3 coarse
sand ) finished with floating coat of neat cement and making
channels in cement concrete 1:2:4 ( 1 cement: 2 coarse sand :4
graded stone aggregate 20 mm nominal size ) finished with a floating
coat of neat cement complete as per standard design. The size and
depth of manhole shall be suitably decided based on requirement of
layout in line with CPWD specification.
a) Inside size shall be 90 x 80 cm and 60 cm deep including CI
cover with frame (light duty) 455 x 610 mm internal
dimensions total weight of cover and frame shall not be less
than 38 kg (weight of cover 23 kg and weight of frame 15 kg)
and shall be constructed with F.P.S. bricks with class
designation 75.
b) Inside size shall be 120 x 90 cm and 90 cm or more deep
including CI cover with frame (medium duty) 500mm internal
diameter total weight of cover and frame to be not less than
116 kg (weight of cover 58 kg and weight of frame 58 kg) with
FPS Bricks class designation 75.
24 Road Gully Brick Masonry road gully chamber of 50x45x60cm shall be provided
Chamber with FPS brick with cement mortar 1:4 including 500x450mm pre
cast RCC Horizontal/vertical grating with frame complete.
11.1.1 Primary structural framing shall include the transverse rigid frames, columns, corner
columns, end wall wind columns and crane gantry girders and Frames at Door openings.
11.1.2 Primary members are fabricated from plates and sections with minimum yield strength of
340 Mpa to suit design by continuous double side welding.
11.1.3 All miscellaneous structural members, rod bracings, angle bracings, pipe bracings, wind
bracings, sag rods, etc. shall conform to the physical specification of IS: 2062 with a
minimum 245Mpa Yield Strength.
11.1.4 All welded structural steel members shall be provided with suitable treatment of shot
blasting before application of steel primer.
11.1.5 All structural steel members including walk way structural steel members shall be painted
with a steel priming coat followed by one coat of epoxy paint and final coating of PU
(Minimum 100 Micron).
11.1.6 The structural steel members of cage ladder shall be galvanized with 610 gm/sqm.
11.2.1 Purlins, girts, necessary clips and other cold rolled structural members shall conform to
the physical specification of ASTM A570 (Grade 50) or equivalent IS Standards having a
minimum yield strength of 340 MPa and shall be of Pre galvanised having a total coating
thickness of 275 gm/sqm. inclusive of both sides.
11.3.1 Factory assembled 50mm thick puff (overall average density 40kg/cu.m. +/- 2 Kg/cu m as
per IS: 11239 Part-2) sandwiched panels shall be provided. These panels shall be made of
puff insulation sandwiched between two high tensile steel sheets each of 0.5 mm thickness.
The material of sheets shall confirm to ASTM 792 M with minimum yield strength of 340
Mpa. However, higher grades of steel sheet may be supplied without any further cost
implication.
11.3.2 The steel sheets shall be provided with hot dip coating of Zinc aluminium alloy
(approximately 55% Al, 43.5% Zn and 1.5 % silicon).Total mass of zinc aluminium alloy
coating shall be minimum 150 gm/Sq. m inclusive of both sides. The tolerance of base metal
thickness (BMT) of steel sheet shall be as per IS 16163. After hot dip coating of Zinc
aluminium alloy, the sheet shall be provided with steel primer and silicon modified
polyester (SMP) paint. The total thickness of primer and paint shall be 40 microns inclusive
of both sides (TCT) comprising of 20 microns of SMP paint on top surface and 10 microns of
backer coat (polyester coat) on back surface over 5 microns thick primer each on both
surfaces with inorganic pigments coated free from heavy metals. Painting shall conform to
IS: 15965. In case SMP paint is not available, Super Durable Polyester paint (SDP) can also
be used by the bidder without cost implication to POWERGRID.
Standard fasteners shall be self tapping zinc plated metal screws with EPDM bonded zinc
plated washers. All screws shall be colour coated to match roof and wall sheeting.
11.5 SEALER:
This is to be applied at all side laps and end laps of roof panels and around self
flashing windows. Sealer shall be pressure sensitive elastomeric Butyl tapes. The
sealer shall be non-asphaltic, non-shrinking and non toxic and shall be superior
adhesive metals, plastics and painted at temperatures from 51°C to +104°C.
Solid or closed cell closures matching the profiles of the panel shall be installed
along the eaves, rake and other locations. It should be specifically specified on drawings.
The steel sheets shall be provided with hot dip coating of Zinc aluminium alloy
(approximately 55% Al, 43.5% Zn and 1.5 % silicon).Total mass of zinc aluminium alloy
coating shall be minimum 200 gm/Sq. m inclusive of both sides. The tolerance of base metal
thickness (BMT) of steel sheet shall be as per IS 16163. After hot dip coating of Zinc
aluminium alloy, the sheet shall be provided with steel primer and silicon modified
polyester (SMP) paint. The total thickness of primer and paint shall be 40 microns inclusive
of both sides (TCT) comprising of 20 microns of SMP paint on top surface and 10 microns of
backer coat (polyester coat) on back surface over 5 microns thick primer each on both
surfaces with inorganic pigments coated free from heavy metals. Painting shall conform to
IS: 15965. In case SMP paint is not available, Super Durable Polyester paint (SDP) can also
be used by the bidder without cost implication to POWERGRID.
Flashing and / or trim shall be furnished at the rake, corners, eaves, and framed openings
and wherever necessary to provide weather tightness and finished appearance. Colour
shall be matching with the colour of wall. The steel sheets shall be provided with hot dip
coating of Zinc aluminium alloy (approximately 55% Al, 43.5% Zn and 1.5 % silicon).Total
mass of zinc aluminium alloy coating shall be minimum 200 gm/Sq. m inclusive of both
sides. The tolerance of base metal thickness (BMT) of steel sheet shall be as per IS 16163.
After hot dip coating of Zinc aluminium alloy, the sheet shall be provided with steel primer
and silicon modified polyester (SMP) paint. The total thickness of primer and paint shall be
40 microns inclusive of both sides (TCT) comprising of 20 microns of SMP paint on top
surface and 10 microns of backer coat (polyester coat) on back surface over 5 microns thick
primer each on both surfaces with inorganic pigments coated free from heavy metals.
Painting shall conform to IS: 15965. In case SMP paint is not available, Super Durable
Polyester paint (SDP) can also be used by the bidder without cost implication to
POWERGRID.
For day lighting purpose of GIS hall, minimum 2 mm thick approved translucent
polycarbonate sheet shall be provided for wall lighting in addition to windows for at least
10% of wall area on upper portion of both long walls. The polycarbonate sheet shall be
fixed with necessary EPDM/rubber gasket, Silicon Sealant, cold forged fastener, aluminum
profile etc. including MS supporting structural steel (conforming to IS:1161/4923) frame to
ensure water tight arrangement.
ii) All secondary bolted connections shall be furnished with bolts, nuts, washers
conforming to the specifications of grade 4.6 of IS 1367 or ASTM-A307.
All shop connections shall be welded with appropriate arc welding process and welding
shall be in accordance with IS: 816, IS -818 ,IS1024, IS:1261, IS1323, IS-9595, AWSD 1.1.
as appropriate. The Webs should be welded on to the flanges at both the faces at top
and bottom for columns, beams and crane girders. Weld material should have strength
more than the parent metal.
Gutters and downspouts shall be adequately designed to ensure proper roof drainage
system. The steel sheets shall be provided with hot dip coating of Zinc aluminium alloy
(approximately 55% Al, 43.5% Zn and 1.5 % silicon).Total mass of zinc aluminium alloy
coating shall be minimum 200 gm/Sq. m inclusive of both sides. The tolerance of base metal
thickness (BMT) of steel sheet shall be as per IS 16163. After hot dip coating of Zinc
aluminium alloy, the sheet shall be provided with steel primer and silicon modified
polyester (SMP) paint. The total thickness of primer and paint shall be 40 microns inclusive
of both sides (TCT) comprising of 20 microns of SMP paint on top surface and 10 microns of
backer coat (polyester coat) on back surface over 5 microns thick primer each on both
surfaces with inorganic pigments coated free from heavy metals. Painting shall conform to
IS: 15965. In case SMP paint is not available, Super Durable Polyester paint (SDP) can also
be used by the bidder without cost implication to POWERGRID.
12.1 All the material required for Pre-engineered (steel) building shall be procured from
approved vendors as per list of compendium of vendors available on POWERGRID web site
or any other reputed manufacturer for which prior approval shall be obtained from
POWERGRID.
12.3 Shop/fabrication showing each and every detail along with bill of material for all members
of structures, joints, nuts & Bolts, welding shall be prepared and approved by venders as
per standard practice of fabrication based on POWERGRID approved design and structural
drawings.
12.4 Complete material shall be offered for inspection by CC (Corporate Centre) QA&I
department before dispatch. Inspection of Material by POWERGRID CC QA &I deptt. shall
be carried out based on Shop/fabrication drawing and BOM as approved by Vendors.
Approval of BOM and shop/fabrication drawings from Employer is not required.
These clauses are applicable for Buildings, which are to be constructed as per drawings provided
by employer such as CRB, transit camp, residential buildings, switch yard panel room and fire
water pump house with fire water tank. Architectural drawings of buildings covered in the scope
are enclosed with the tender documents and are also available on website. These drawings are
good for construction except for foundation drawings of the buildings which will be issued to the
successful bidder after award of work and after receipt of soil investigation report depending
upon soil parameters.
This shall also be applicable for vendor designed buildings wherever applicable.
In case of CRB and GIS halls, most of the finishing items are explained in previous clauses, if any of
items are missed or may be required for completion of the same, the below mentioned clauses
may also be referred.
13.1 The material specification, workmanship and acceptance criteria shall be as per approved
standard Field Quality Plan attached with this document which is available on POWERGRID
web site. In case certain item is not covered in FQP, it shall be constructed as per CPWD
specification.
13.2 Post constructional Anti termite treatment shall be carried out for all buildings as per DSR
item no. 2.34 & 2.35. Anti termite chemical treatment shall be given to column pits, wall
trenches, foundations of buildings, filling below the floors etc. as per IS: 6313 and other
relevant Indian Standards.
13.4 FPS or Modular clay/fly ash based Bricks having minimum 75 kg/cm2 compressive strength
can only be used for masonry work. Contractor shall ascertain himself at site regarding the
availability of bricks of minimum 75 kg/cm2 compressive strength before submitting his
offer. However, Contractor can propose to use aerated concrete block or solid concrete
blocks of compressive strength not less than 75kg/cm2 without any cost implication to
POWERGRID.
13.5 Full brickwork shall be provided with cement mortar 1:6 (1cement: 6 coarse sand). Half
brick work masonry shall be provided with cement mortar 1:4 (1cement: 4coarse sand)
and two no 6mm dia ms bar at every third course.
13.6 12mm cement plaster of mix 1:6 (1cement: 6 fine sand) shall be provided on the smooth
side of internal walls. However rough side of walls shall be provided with 15mm cement
plaster of mix 1:6 (1cement: 6 fine sand).
13.7 External plaster in two coats - 18mm Cement plaster in two coats under layer 12mm thick
cement plaster 1:5 (1 cement: 5coarse sand) finished with a top layer 6mm thick cement
plaster (1cement : 6 fine sand). External plastered surface shall be finished with white
cement based putty of average thickness 1 mm, of approved brand and manufacturer to
prepare the surface even and smooth. After putty the walls shall be finished with Premium
Acrylic Smooth exterior paint of approved brand and manufacturer with Silicone additives
of required shade (Two or more coats applied @ 1.43 ltr/ 10 sqm. over and including
priming coat of exterior primer applied @ 2.20 kg/ 10 sqm).
13.8 6 mm thk. Cement plaster of mix 1:3 (1 cement: 3 fine sand) to RCC ceiling shall be done
except areas where false ceiling are provided.
13.9 Internal walls shall be finished with Plaster of Paris putty of average thickness 2 mm, of
approved brand and manufacture, over the plaster surface to prepare the surface even
and smooth complete. In case plastered surface of buildings are covered under wall
paneling, dado work, skirting etc. no putty and painting are required.
13.10 Internal walls shall be painted with minimum two coats of premium acrylic emulsion paint
having VOC (volatile organic compound) content less than 50gm per litre of approved
brand and manufacture including applying additional coats wherever required, to achieve
even shade and colour over priming coat as per manufacturer specification/
recommendation.
13.12 Painting with synthetic enamel paint of approved brand and manufacture of required
colour to give an even shade shall be provided on the steel doors, flush doors and rolling
shutters in various buildings or as specified in the drawings. Two or more coats over an
under coat of suitable shade with primer paint of approved brand and manufacture.
13.13 Two or more coats of French spirit polishing with a coat of wood filler shall be provided on
the wooden doors and frames.
13.14 Polished vitrified tiles in 60x60 cm size (thickness to be specified by the manufacturer) in
flooring and skirting, with water absorption’s less than 0.08% and conforming to IS: 15622
of approved make in all colours and shades, laid on cement mortar 20mm thick min. for
flooring & 12mm thick for skirting 1:4 (1 cement: 4coarse sand) including grouting the
joints with white cement and matching pigments etc., complete.
13.15 Glazed Ceramic floor tiles 300x300mm (thickness to be specified by the manufacturer) of
1st quality conforming to IS:15622 of approved make in colours as approved by Engineer-
in-charge in toilet and pantries area on 20mm thick min. cement mortar 1:4 (1 cement :
4coarsesand) including grouting the joints with white cement and matching pigments etc.,
complete.
13.16 62 mm thick cement concrete flooring with concrete hardener topping, under layer 50 mm
thick cement concrete 1:2:4 (1 cement: 2 fine aggregate : 4 graded stone aggregate 20mm
nominal size) and top layer 12mm thick cement hardener consisting of mix 1:2 (1 cement
hardener mix: 2 graded stone aggregate, 6mm nominal size) by volume, hardening
compound mixed @ 2 litre per 50 kg of cement or as per manufacturer’s specifications.
13.17 Cement plaster skirting (up to 15 cm height) with cement mortar 1:3 (1 cement: 3 coarse
sand) mixed with metallic concrete hardener in same ratio as for floor finished with a
floating coat of neat cement. 21 mm thick in ACDB/DCDB room.
13.18 Granite stone of 18mm thick gang saw cut mirror polished pre-molded and pre-polished,
machine cut for of required size of approved shade, colour and texture laid over 20mm
thick base cement mortar 1:4 (1 Cement: 4 coarse sand) with joints treated with white
cement, mixed with matching pigment, epoxy touch ups, including rubbing, curing molding
and polishing to edge to give high gloss finish etc. complete for staircase.
13.19 Granite stone of flooring with 18mm thick gang saw cut mirror polished premoulded and
prepolished, machine cut for of required size of approved shade, colour and texture laid
over 20mm thick cement mortar 1:4. The joints are filled with jointing compound matching
13.20 Granite counter of approved shade shall be provided and fixed with 18mm thick gang saw
cut, mirror polished, premoulded and pre-polished, machine cut for pantry & kitchen
platform facias and similar locations of required size, approved shade, colour & texture
laid over 20mm thick base cement mortar 1:4 ( 1cement : 4 Coarse sand) joints treated
with white cement, mixed with matching pigment, epoxy touch ups, including rubbing,
curing moulding and polishing to edges to give high gloss finish etc complete at all levels.
13.21 Ceramic glazed wall tiles of 1st quality conforming to IS: 15622 (thickness to be specified
by the manufacture) of approved make in all colours, shades as approved by Engineer-in-
Charge in dados over 12mm thick bed of cement Mortar 1:3 (1 Cement: 3 Coarse sand)
and jointing with grey cement slurry @ 3.3kg per sqm including pointing in white cement
mixed with pigment of matching shade complete. Height of dado shall be 2.1m high in
toilets, kitchen and pantry or elsewhere specified in the drawings or TS.
13.22 Rolling shutters shall be seamless galvalume motorized rolling shutters, with inclusion of
features as under:
Roller shaft Roller shaft shall be heavy duty mild steel strong
suspension tubular shaft without springs.
13.22 Circular/hexagonal M.S. sheet ceiling fan box shall be provided in the ceiling with clamp of
internal dia. 140 mm, 73 mm height, 3 mm thick rim, top and bottom lid of 1.5 mm M.S.
Sheet. Lids shall be screwed in to M. S. box by means of 3 mm round headed screws,
clamps shall be made of 12 mm dia. M. S. bar bent to shape as per standard drawing with
overall length as 80 cm.
13.23 Powder Coated (minimum thickness 50 micron) aluminium work for doors, windows,
ventilators and partitions shall be provided and fixed in building with extruded built up
standard tubular and other sections of approved make conforming to IS:733 and IS : 1285,
fixed with rawl plugs and screws or with fixing clips, or with expansion hold fasteners
including necessary filling up of gaps at junctions at top, bottom and sides with required
PVC/neoprene felt etc and joined mechanically wherever required including cleat angle,
Aluminium snap beading for glazing / panelling, C.P. brass/ stainless steel screws including
glazing and fittings as specified.
13.24 All doors except for toilet shall have 100mm 6 lever CP Brass mortice lock . Anodized
aluminum handles of ISI marked and approved size shall be provided for all doors and
windows as per requirement and instruction of E.I.C.
13.25 Cylindrical keyless lock of 25 mm diameter and 50mm diameter knob on both sides (ISI
marked) shall be provided for toilets.
13.26 Kitchen door shall have 250x16mm C.P. brass sliding door bolt.
13.27 Door shall be provided with anodized aluminum tower bolt (barrel type) 250x10mm
wherever door closers are not provided.
13.28 All windows shall have aluminum tower bolt (barrel type) 150x10mm as per requirement.
13.29 Double action hydraulic floor spring of approved brand and manufacture confirming to IS:
6315 having brand logo embossed on the body/plate with double spring mechanism and
door weight upto 125 kg, for doors shall be provided and fixed at the following door
including cost of cutting floors as required, embedding in floors and cover plates with brass
pivot and single piece MS sheet outer box with slide plate etc. as per the direction of
Engineer-in-charge. With stainless steel cover plate minimum 1.25 mm thickness.
13.31 Plinth protection 50 mm thick of cement concrete 1:2:4 (1 cement : 2 fine aggregate : 4
graded stone) aggregate 20 mm nominal size) shall be laid over 75 mm bed of dry brick
ballast 40 mm nominal size well rammed and consolidated and shall be grouted with fine
sand including finishing the top smooth. Minimum width of plinth protection shall be 1000
mm.
13.32 G.S. corrugated sheets of 0.80 mm thick with zinc coating not less than 275 gm/m²
roofing shall be provided and fixed with G, I, J or L hooks, bolts and nuts 8mm diameter G, I
plain and bitumen washers complete excluding the cost of purlins, rafters and trusses for
water tank.
13.33 Cement Jali of (1:2:4) ( 1 Cement: 2 fine aggregate : 4 coarse aggregate ) 50mm thick, shall
be reinforced with 1.6mm dia with Mild steel wire including centering and shuttering
cleaning fixing and furnishing with cement mortar 1:3).
13.34 Ward Robes of required height and about 600 mm deep shall be made out of 18 mm. thk
anti termite treated commercial board ISI marked at end verticals, top and bottom,
shutters, partition etc complete. The rear side of the unit shall be made with 6mm thk
commercial ply ISI marked, which shall have French spirit polish on the exterior face. Inner
surface of the storage cabinet shall be finished with 0.8mm thk approved laminate. The
horizontal partition shall be of removable type fixed with necessary SS fittings and
hardware. All external surfaces shall be finished with 4.0 mm thk approved veneer with
melamine including making necessary grooves, teak wood moulding as per approved
drawings. Each shutter shall have piano type stainless steel hinges and C.P. Brass or SS
125mm long handle. The unit shall have necessary fittings such as tower bolts, 4 lever CB
locks etc complete.
13.35 Angles 50x50x6 mm (minimum) with lugs shall be provided for edge protection all round
cut outs/openings in floor slab.
14.0 EXTERNAL WATER SUPPLY FROM BORE-WELL TO FIRE WATER TANK/CONTROL BUILDING
AND / OR TRANSIT CAMP:
14.1 The drawing for the water supply from bore-well to fire water tank shall be developed by
the Contractor. Water supply will be made available to the Contractor from a bore-well by
the Employer at any one location within the sub-station. 80 mm dia CPVC pipe shall be
provided by the Contractor from the bore-well to the fire water tank. The underground
pipe line shall be laid as per CPWD Specification. The ball valve, NRV etc. shall be provided
as per requirement. From this pipe line a 25 mm dia tap off shall be connected by the
Contractor to the roof water tank provided for the control room building & transit camp.
14.2 The Contractor shall carry out all the external plumbing/erection works required for supply
of water to the control room building, firewater tank and/ or transit camp beyond the
single point as given at 14.1.
14.3 A scheme shall be prepared by the Contractor indicating the layout and details of water
supply which shall be got approved from the Employer before actual start of work
including all other incidental items not shown or specified but as may be required for
complete performance of the works.
15.0 SUBMISSION:
The following information shall be submitted for review and approval to the Employer:
15.1 Editable Soft as well as hard copies of structural design calculations and structural
drawings (including construction/fabrication) for all reinforced concrete and structural
steel structures.
15.2 Fully, dimensioned concept plan including floor plans, cross sections, longitudinal sections,
elevations and perspective view of each building. These drawings shall identify the major
building components. Auto cad drawings shall also be submitted.
15.3 Fully dimensioned drawings showing details and sections drawn to scales of sufficient size
to clearly show sizes and configuration of the building components and the relationship
15.4 Product information of building components and materials, including walls partition
flooring ceiling, roofing, door and windows and building finishes to be submitted to EIC.
15.5 A door & window schedule showing door types and locations, door lock sets and latch sets
and other door hardware. Approval of the above information shall be obtained before
ordering materials or starting fabrication or construction as applicable.
16.1 All joints including construction and expansion joints for the water retaining structures
(RCC tank for Fire Fighting and underground water tank) shall be made water tight by using
PVC ribbed water stops with central bulb. The minimum thickness of PVC water stops shall
be 5 mm and minimum width shall be 230 mm.
16.2 All mild steel parts used in the firefighting water tank and underground water tank shall be
hot-double dip galvanised. The minimum coating of the zinc shall be 750 gm/sq. m. for
galvanised structures and shall comply with IS:2628 and IS:2633. Galvanizing shall be
checked and tested in accordance with IS: 2633. The galvanizing shall be followed by the
application of an etching primer and dipping in black bitumen in accordance with BS: 3416.
The structural steel provided for roofing shall have enamel paint of approved shade two or
more coat to give even shade over steel primer.
16.3 Angles 50x50x6 mm (minimum) with lugs shall be provided for edge protection all round
cut outs/openings in floor slab.
16.4 For sump pit of switch yard Horizontal type submersible type pump as per BOQ rating
having level switch shall be provided.
16.5 The material specification, workmanship and acceptance criteria shall be as per approved
standard Field Quality Plan attached with this document which is available on POWERGRID
web site. In case certain item is not covered in FQP, it shall be constructed as per CPWD
specification.
16.6 Items/ components of buildings not explicitly covered in the specification but required for
completion of the project shall be deemed to be included in the scope.
16.8 For communication Room GI Pipe of 40 mm dia shall be laid below floor to extend
communication cable coming from switchyard via ACDB/DCDB Room.
17.0 INTERFACING:
The proper coordination & execution of all interfacing civil works activities like fixing of
conduits in roofs/walls/floors, fixing of foundation bolts, fixing of lighting fixtures, fixing of
supports/embedment, provision of cut outs etc. shall be the sole responsibility of the
Contractor. He shall plan all such activities in advance and execute in such a manner that
interfacing activities do not become bottlenecks and dismantling, breakage etc. is reduced
to minimum.
18.1 Contractor shall comply with all the applicable statutory rules pertaining to factories act
(as applicable for the State), Fire Safety Rules of Tariff Advisory Committee, Water Act for
pollution control etc.
18.2 Statutory clearance and norms of State Pollution Control Board shall be followed as per
Water Act for effluent quality from plant.
18.3 Requirement of sulphate resistant cement (SRC) for sub structural works shall be decided
in accordance with the Indian Standards based on the findings of the detailed soil
investigation. In case sulphate resistant cement is used as per requirement, differential
cost between sulphate resistant cement and PPC cement shall be payable as an extra item.
18.4 All building/construction materials shall conform to the best quality specified in CPWD
specifications if not otherwise mentioned in this specification.
18.5 All tests as required in the standard field quality plans have to be carried out without any
financial implication to employer.
This specification shall apply to site levelling works as are required to be executed under
the Contract or otherwise directed by the Engineer-in-Charge. All testing shall be carried
out as per standard field quality plan of POWERGRID.
Site levelling work shall consist of clearance of site, excavation in all kinds of soils,
soft/disintegrated rock, hard rock, dewatering, transporting of excavated earth, filling,
consolidation of earth, levelling benching, giving slopes and making formations, levelling
operations, removal and satisfactory disposal of unsuitable materials necessary for
achieving desired formation level, if required, in accordance with the requirements of the
specifications and the lines, grades and cross-sections shown in the drawings or indicated
by the Engineer-in-Charge. The work shall include the hauling and stacking of or the
hauling to levelling site, of suitable materials as required, as also the disposal of unsuitable
materials in specified manner; and the trimming and finishing of works.
This work also includes cutting of diversion channel to prevent the area from flooding and
construction of kuchcha surface drains for drainage of the area.
The quality of work and materials shall comply with the requirements set forth in the
succeeding sections. Where the drawings and Specifications describe a portion of the
work only in general terms, and not in complete details, it shall be understood that only
the best general practice is to prevail, materials and workmanship of the best quality are
to be employed and the instructions of the Engineer-in-Charge are to be fully complied
with.
The work to be performed under this specifications consists of providing all labour,
supervision, materials, planking and strutting, power, fuel, construction equipments, tools
and plants, supplies, transportation, blasting materials if required, storage, insurance,
royalty and all incidental items not shown or specified by reasonably implied or necessary
for successful completion of work including contractor's supervision and in strict
accordance with drawing and specifications.
The scope may however vary based on the specific requirement of various works/site,
which shall be specified by the Owner.
The work shall be executed according to "Released for Construction", drawings with
additions, alterations and modifications made from time to time as required or approved
by the Engineer-in-Charge and also according to any other drawings that would be
supplied to the Contractor progressively during the execution of the Contract.
The words like Contract, Contractor, Engineer-in-Charge, Drawings, Owner, works, site
used in this Specifications shall be considered to have the meaning as understood from the
definition of these terms included in the General Conditions of Contract.
The Contractor shall undertake all reasonable precautions for the protection and
preservation of Trees, shrubs, any other plants, pole lines, fences, signs, monuments,
buildings, pipelines, sewers or other subsurface drains, pipes, conduits and any other
structures under or above ground, which may be affected by construction operations and
which in the opinion of the Engineer-in-Charge shall be continued in use without any
change.
The Contractor shall provide and install at his own expenses, suitable safeguards approved
by the Engineer-in-Charge for this purpose. However, if any of these objects is damaged by
reason of the Contractor's negligence, it shall be replaced or restored to the original
condition without any financial implication to POWERGRID.
All materials arising from jungle clearing, grubbing operation, all type of excavation etc.
shall be the property of Power Grid and shall be disposed of by the Contractor as
hereinafter provided or directed by the Engineer-in-Charge within a lead of 2000 m
beyond the periphery of substation area. Also boulders, stones and other materials usable
shall be neatly stacked.
All products of clearing and grubbing which in the opinion of the Engineer-in-Charge
cannot be used or auctioned shall be cleared away to waste areas and burnt, if so desired,
at locations away to a lead mentioned above in a manner as directed. Care shall be taken
to see that unsuitable waste materials are disposed of in such a manner that there is no
likelihood of these getting mixed up with the materials meant for filling.
Where the excavated material is directed to be used in the filling area, it shall be directly
deposited at the required location complying with the total requirements. All disposed
material other than hard material shall be spread in layers at the places within specified
leads.
Unsuitable and surplus materials not intended for use in any part of the works shall be
disposed off.
The work shall consist of numbering of trees, removing and disposing of all materials such
as trees, bushes, woods, shrubs, grass, stumps, rubbish, rank vegetation, roots, foreign
materials, etc., which in the opinion of the Engineer-in-Charge are unsuitable for
incorporation in the works, from within the limits and areas as may be specified by the
Engineer-in-Charge.
All trees up to a girth (perimeter) of 30 cm measured at one metre above the ground level
shall also be cut and useful portion of the trees so cut shall be stacked at a suitable place
as directed by the Engineer-in-Charge and shall be considered incidental to clearing and
grubbing operations.
The roots of trees shall be dug up to 60 cm below the ground level or 15 cm below
formation level whichever is deeper and after removal of all vegetable and organic matter
from the holes so formed by removal of the roots, holes and hollows shall be filled with
good earth in layer of 20 cm, well rammed, consolidated and levelled.
The serviceable and unserviceable materials obtained from the site clearance shall be
removed from the area and disposed of to a place as per the directions of the Engineer-in-
Charge. All unserviceable and serviceable materials obtained from the site clearance shall
be the property of POWERGRID.
Clearing and grubbing item is not payable and the same shall be deemed to be included in
the earth work in excavation and filling.
All kind of soils includes various types of soils, plain concrete, shingle and river or nallah
bed boulders, soling of road, paths and hard core, macadam surface of any description,
stone masonry below the ground level, soft conglomerate and laterite stone which can be
detached from the matrix with picks and shovel.
Soft/disintegrated Rock (Not requiring blasting): Rock and boulders which may be quarried
and split with crow bars and other mechanical implements etc. It includes lime stone, sand
stone, hard conglomerate.
All kind of rocks which can be excavated by machines and requires blasting chiselling in
edging or in another agreed method. This can be classified under the following categories:
a) Hard Rock (Requiring Blasting)-This shall comprise:
i) Any rock for the excavation of which the use of mechanical plant or blasting is
required;
ii) Reinforced cement concrete (reinforcement cut through but not separated from
the concrete) below ground; and
iii) Boulder requiring blasting.
Hard rock requiring blasting as described under (a) above but where blasting is prohibited
for any reason and excavation has to be carried out by chiselling, wedging or any other
agreed method.
The classification of excavation shall be decided by the Engineer-in-Charge and his decision
shall be final and binding on the Contractor. Merely the use of explosives in excavation
will not be considered as a reason for higher classification unless blasting is clearly
necessary in the opinion of the Engineer-in-Charge. All the excavated material shall be the
property of the POWERGRID.
After the site has been cleared, the limits of site levelling shall be set out true to lines,
curves, slopes, grades and sections as shown on the drawings or as directed by the
Masonry pillars shall be erected at suitable places in the area to serve as bench marks for
the execution of the work. These bench marks shall be connected with G.T.S. of any other
permanent bench mark approved by the Engineer-in-Charge. Necessary profiles with pegs,
bamboos and strings or "Burgeis" shall be made to show the correct formation levels
before the work is started and the same shall be approved by the Engineer-in-Charge. The
contractor shall supply all labour, tools, equipment, materials, safeguards and incidentals
necessary for setting out and making profiles and burgeis & pillars for the work at his own
cost. The profiles and burgeis shall be maintained during the execution of the work.
Marks/pillars shall invariably be diagonal unless otherwise directed, and should be such
that their average height is representative of average depths. Payments will be made on
the basis of volume measurement after with-holding the amount corresponding to 5% of
the volume of earth work on account of non-removal of marks/pillars.
The Contractor shall have to remove the marks/pillars and utilise the earth spoils as per
the directions of the Engineer-in-Charge. The withheld amount as stated in the above
paragraph may be paid after certification of the Engineer-in-Charge; regarding his full
satisfaction and to the effect that the mark/pillars, etc. have been removed and soils/earth
thereof has been utilised as directed by him.
If the contractor fails to remove, partly or fully the marks/pillars in the manner and within
the period as aforesaid double the amount spent by the owner for removal of
marks/pillars will be recovered from dues payable to the contractor.
All excavations shall be carried out in conformity with the directions laid herein under and
in a manner approved by the Engineer-in-Charge. The work shall be so done that the
suitable materials available from excavation are satisfactorily utilised as decided upon
before disposal.
While planning or executing excavation, the Contractor shall take all adequate precautions
against soil erosion, water pollution, air pollution etc.
All debris and loose material on the slopes of cuttings shall be removed.
If cutting be taken deeper, it shall be brought to the required level as per the instructions,
by filling it with the earth and duly consolidating at the Contractor's cost.
Filling shall be done in regular horizontal layers not exceeding 20 cm. in depth. The earth
shall be free from all roots, grass, rubbish and humps and clods exceeding 80mm in any
direction shall be broken. Each layer shall be consolidated by breaking clods and
Compacting each layer with wooden /steel rammer or movement of dozers, trucks or 8/10
tonne power road rollers, sheep foot roller and vibratory compactors etc. so that
compaction of 95% of the maximum dry density is achieved at optimum moisture content.
The surface finished shall be neatly dressed to the required formation levels with tolerance
of (±) 100 mm.
Tests for Compaction are to be performed as per the procedures laid down in the relevant
I.S. Codes of practice and Standard Field Quality Plan of POWERGRID. In cases of
compaction below the stipulated percentage, the contractor shall adopt proper techniques
as directed by the Engineer in-Charge and to his satisfaction to ensure the specified degree
of compaction. The cost of tests to be performed shall be borne by the Contractor.
During the execution of work, natural drainage of the area shall be maintained by the
contractor.
Hard Rock, when encountered during excavation, shall be removed up to the finished
ground level or as indicated on the drawings. In all cases, the excavation operations shall
be so carried out that at no point on cut formation the rock protrudes above the specified
levels, provided, however, that a negative tolerance of 150 mm shall be permissible.
Blasting shall be carried out as per relevant clause mentioned elsewhere in this
specification and all precautions indicated therein to be observed.
19.6.4 DEWATERING
If water is met with in the excavation due to stream flows, springs, seepage, rain or other
causes, it shall be removed by suitable diversions, pumping or bailing out and other
excavation kept dry whenever so required or directed by the Engineer-in-Charge, Care
shall be taken to so discharge the drained water as not to cause damage to the works,
crops or any other property. No extra payment shall be admissible to the contractor on
this account.
Finishing operations shall include the work of properly shaping and dressing all excavated
surfaces. When completed, no point on the slopes shall vary from the designated slopes by
more than 150 mm measured at right angles to the slope, except where excavation is in
rock where no point shall vary more than 600 mm from the designated slope. In no case
shall any portion of the slope encroach on the road way.
19.7 EARTH FILL MATERIAL:
The borrowed earth used in filling shall be free from all roots, grass, shrubs, rank
vegetation, brush wood, tree sapling and rubbish.
Unsuitable material shall mean materials unsuitable for placing as fill in the works and shall
comprise:
a) Material from swamps, marshes and bogs;
b) Peat, logs, stumps and perishable materials;
c) Material susceptible to spontaneous combustion;
d) Any natural material or industrial and domestic produce which will adversely affect
other materials in the work;
e) Clay with liquid limit exceeding 80% and/or plasticity index exceeding 55%.
For the earth works contractor shall satisfy the Engineer-in-Charge that the entire specified
requirement regarding compaction can be achieved. Testing shall be carried out as per
standard field quality plan of POWERGRID.
The Final formation shall be correct in level and profile after compaction.
In the case of earth work consolidated under optimum moisture conditions, each layer of
earth shall be carefully moistened to give field moisture content of about + 1% to - 2% of
the optimum moisture content (OMC). The OMC shall be determined according to IS:
2720 (Pt.VII &VIII) Methods of Tests for Soils.
Each layer shall then be compacted by rolling with wooden/ steel rammer or movement
of dozers, trucks, 8/10 tonnes power road roller, sheep foot roller and vibratory
compactors/roller. The required amount of water shall be added during consolidation to
keep the moisture content of the soil at the optimum as per test. The density to be
achieved for each layer of the material shall not be less than 95% of the density obtained
in the laboratory (Proctor Method).
Control on compaction in the field shall be exercised through frequent moisture content
and density determinations. A systematic record of these shall be maintained. At all times
during construction the top of the embankment shall be maintained at such cross fall as
will shed water and prevent pounding.
19.8 BLASTING OPERATIONS.
19.8.1 GENERAL
Blasting shall be carried out only with the written permission of the Engineer-in-Charge.
All the statutory laws, regulations, rules, Indian Standards, etc., pertaining to the
acquisition, transport, storage, handling and use of explosives shall be strictly followed.
The Contractor may adopt any method or methods of blasting consistent with the safety
and job requirements, after approval from the Engineer-in-Charge and shall muffle the
blasting adequately to the satisfaction of the Engineer-in-Charge. Blasting should be
carried out as far as possible with the help of Ammonium Nitrate mixed with proper
proportions of fuel oil which is a safer method. However, in the event of its non-
availability the convenient practice of using gelatine with detonators can be resorted to.
The magazine for the storage of explosives shall be built to the designs and specifications
of the Explosives Department concerned and located at the approved site. No
unauthorised person shall be admitted into the magazine which when not in use shall be
kept securely locked. No matches or inflammable material shall be allowed in the
In addition to these, the Contractor shall also observe the instructions in following clauses
and any further additional instructions which may be given by the Engineer-in-Charge and
shall be responsible for damage to property and any accident which may occur to
workmen or the public or the materials on account of any operations and blasting. The
Engineer-in-Charge shall frequently check the Contractor's compliance with these
precautions.
All the materials, tools and equipment used for blasting operations shall be of approved
type and shall be arranged by the contractor from any authorised dealer of such approved
material. Necessary assistance in the form of approval for procurement of the material
shall be given by the Corporation. The contractor shall be fully responsible for entering
into the agreement with any authorised magazine contractor in respect of rates, regularity
of supply, etc. the Engineer-in-Charge may specify the type of explosives to be allowed in
special cases. The fuse to be used in wet locations shall be sufficiently water-resistant as
to be unaffected when immersed in water for 30 minutes. The rate of burning of the fuse
shall be uniform and definitely known to permit such a safe length being cut as will permit
sufficient time to the firer to reach safety before explosion takes place. Detonators shall
be capable of giving effective blasting of the explosives. The blasting powder, explosives,
detonators fuses, etc., shall be fresh and not damaged due to damp, moisture or any other
cause. They shall be inspected before use and damaged articles shall be discarded totally
and removed immediately.
19.8.3 PERSONNEL
The blasting operation shall remain in the charge of competent and experienced
supervisor and workmen who are thoroughly acquainted with the details of handling
explosives and blasting operations.
The blasting shall be carried out during fixed hours of the day preferably during the mid-
day lunch hour or at the close of the work as ordered in writing by the Engineer-in-Charge.
The hours shall be made known to the people in the vicinity. All the charges shall be
Technical Specification, Section: Civil Works Page 69 of 80
C/ENGG/SPEC/CIVIL/ Rev-11A/Jun’18
prepared by the man in charge only. Proper precautions for safety of persons and
property shall be taken.
Red danger flags shall be displayed prominently in all directions during the blasting
operations. People, except those who actually light the fuse shall be prohibited from
entering this area. The flags shall be planted 200 metres from the blasting site in all
directions and all persons including workmen shall be excluded from the flagged area at
least 10 minutes before the firing, a warning whistle being sounded for the purpose.
The charge holes shall be drilled to required depths and in suitable places. Blasting should
be as light as possible consistent with thorough breakage of the material necessary for
economic loading and hauling. Any method of blasting which leads to overshooting shall
be discontinued.
When blasting is done with powder, the fuse cut to the required length shall be inserted
into the hole and the powder dropped in. The powder shall be gently tamped with copper
rods with rounded ends. The explosive powder shall then be covered with tamping
material which shall be tamped lightly but firmly.
At a time, not more than 10 such charges will be prepared and fired. The man in charge
shall blow a whistle in a recognised manner for cautioning the people. All the people shall
then be required to move to safe distances. The charges shall be lighted by the man in
charge only. The man in charge shall count the number of explosions. He shall satisfy
himself that all the charges have been exploded before allowing the workmen to go back
to the work site.
When blasting is to be carried out in the proximity of other existing structures, sand/earth
bags, etc. shall be used on the top of the blast holes to prevent the rock fragment from
causing damage to the structures.
However, when blasting is prohibited for any reasons the excavation shall be carried out
by chiselling, wedging or any other agreed method.
19.8.5 MISFIRE
19.8.6 ACCOUNT.
A careful and day to day account of the explosives shall be maintained by the Contractor in
an approved register and manner which shall be open to inspection by the Engineer-in-
Charge at all times.
The ground levels shall be taken at every 5 metres distance and at closer distances where
pits, undulations, etc. are met with. The ground level shall be recorded in field book,
plotted on plans and shall be signed by contractor and the Engineer-in-Charge before the
earth work is started.
The levels of the area after excavation shall be recorded in the field book duly signed by
the Engineer-in-Charge and contractor. The labour, materials, tools, equipment,
safeguards and incidentals required for taking levels shall be supplied by the contractor at
his own cost.
All measurements shall be made in the metric system. Different items of work shall be
measured in accordance with the procedures set forth in the relevant sections.
All measurements and computations, unless otherwise indicated, shall be carried nearest
to the following limits:
a) Length and breadth -- 10 mm
b) Height, depth or thickness of work -- 5 mm
c) Area -- two places of decimal
d) Cubical qty. -- two places of decimal
Providing and laying Plain Cement Concrete of all types and at all locations including all
leads and lifts. The quantity shall be measured in cubic meters as per lines and levels
indicated in the drawings.
20.2.1 PCC 1:2:4 (1 cement : 2 fine aggregate : 4 coarse aggregate 20 mm nominal size) shall be
measured in flooring of buildings, plinth protection, fencing, transformer foundation,
reactor foundation, rail track, drain, culverts, septic tank, chain link fencing, gate etc. as
indicated in the drawings.
20.2.2 PCC 1:3:6 (1 cement : 3 fine aggregate : 6 stone aggregate, 40mm nominal size) shall be
measured below all foundations including buildings, underground water tanks, covered
car parking cable trench, roads, under flooring, rail-cum-road, transformer foundation,
reactor foundation, drain, water tank, culverts, gate, tower/equipment etc. as indicated in
the drawings.
20.2.3 PCC 1:4:8 (1 cement : 4 fine aggregate : 8 stone aggregate, 40mm nominal size) shall be
measured below all foundations including buildings, underground water tanks, covered
car parking cable trench, roads, under flooring, rail-cum-road, transformer foundation,
reactor foundation, drain, water tank, culverts, gate, tower/equipment etc. as indicated in
the drawings.
20.2.4 PCC 1:5:10 (1 cement: 5 fine aggregate: 10 brick aggregate/ stone aggregate 40mm
nominal size) shall be provided for site surfacing in switchyard. This shall include providing
and laying cement slurry in case of site surfacing in switchyard.
Technical Specification, Section: Civil Works Page 72 of 80
C/ENGG/SPEC/CIVIL/ Rev-11A/Jun’18
All other PCC required for the completion of the work including hold fasts of
doors/windows/rolling shutters, fixing of plumbing pipes, bedding concrete for sewer lines,
embedment of electrical conduits, water proofing of roof etc. shall not be measured and
deemed to be included in the composite rates quoted by the bidder for respective works.
Water proofing compound wherever specified shall be added without any extra cost.
20.3 RCC
Measurement of reinforced cement concrete at all locations shall be made and shall
include all leads, lifts, formwork, grouting of pockets and underpinning. This shall also
include pre-cast RCC work and addition of water proofing compound & admixtures
wherever required for which no additional payment shall be made. The quantity shall be
measured in cubic meters as per lines and levels indicated in the drawings. No deduction
shall be made for volume occupied by reinforcement/inserts/sleeves and for openings
having cross-sectional area up to 0.1 sq.m.
20.7 ROADS
20.7.1 The measurement for the concrete road shall be made on the basis of area in square
meter (M2) of top concrete completed surface of the road and shall be deemed to include
all items such as earth work (excavation, disposal etc.), compaction, rolling, watering,
WBM, Kerb stone, grating, shoulder, 100mm dia RCC Hume pipe to be provided at every
100M etc where ever indicated complete as per drawing. Concreting all type and
reinforcement shall be measured and paid separately under relevant items mentioned else
where in this specification. Usage of WMM in place of WBM shall be done with approval of
employer without any additional financial implication.
20.7.2 The measurement of bituminous road shall be made on the basis of area in square meter
(M2), of the top bituminous completed surface of the road and shall include all items such
as earth work (excavation, disposal etc.), compaction, rolling, watering, WBM, Kerb stone,
grating, shoulder, 100mm dia RCC Hume pipe to be provided at every 100M etc where
ever indicated complete as per drawing including premix carpet etc complete .Usage of
WMM in place of WBM shall be done with approval of employer without any additional
financial implication.
20.7.3 Interlocking concrete tiles required to be provided on the shoulders of the road shall be
measured in square meter (M2) and paid separately under relevant item.
The measurement shall be done for the actual area in square metres of antiweed
treatment which will include supplying required chemicals and doing the treatment
complete in all respect as per the specification for the specified area.
20.11 CABLE TRENCH CROSSING AND ROAD CULVERTS THROUGH HUME PIPES
Cable trench crossings and road culverts shall be measured by length (in running meters)
of individual Hume pipe which will be laid as per the drawings. The item shall be inclusive
of earth work (excavation, backfilling, disposal etc.), laying, back filling, jointing, brickwork,
plastering etc complete in all respect but excluding concrete (all type)which will be
measured and paid separately under respective items.
20.12 BUILDINGS:
a) GIS HALL
b) AHU & RELAY ROOM
The quantity of earth work (excavation, backfilling, disposal etc.), concrete (all type),
reinforcement steel shall be measured & paid separately as per relevant clauses as
described above. Plinth area shall be calculated based on IS 3861-2002. However,
payment for remaining finishing items a), b) & c) shall be made on plinth area basis for
each building including internal foundations, cable trenches, internal & external finishes,
stone soling for flooring, plinth protection, drain along plinth protection, electrical
conduit & junction boxes, fan boxes, cable transit system, miscellaneous structural steel
required for seating of GIS equipments, cable supports in cable trenches, chequered
plates etc inside GIS building. complete in all respect.
The quantity of earth work (excavation, backfilling, disposal etc.), concrete (all type),
reinforcement shall be measured and paid as per relevant clauses as described above.
Plinth area shall be calculated based on IS 3861-2002. However, payment for above items
a), b) & c) shall be made on plinth area basis for each building including internal
foundations, cable trenches, internal & external finishes, stone soling for flooring, plinth
protection, drain along plinth protection, electrical conduit & junction boxes, fan boxes,
cable transit system wall dismantling works, miscellaneous structural steel required for
seating of GIS equipments, cable supports in cable trenches, chequered plates etc inside
GIS building complete in all respect.
Payment for internal electrification as well as internal firefighting works is not included in
items covered in clauses above and shall be paid as per relevant clauses and BPS.
However, conduit, junction boxes, surface boxes for electrification, cable transit system is
deemed to be included in the building items.
This is a lump sum item. The Contractor shall be required to complete the work in all
respect as per drawings furnished by the Employer. All the items including earth work
(excavation, backfilling, disposal etc.), miscellaneous steel, brick work, fillings of boulders,
gravel, sand, pipes etc. shall be deemed to be included in this lump sum rate. However,
the concrete (all types) and the reinforcement shall be measured and paid under the
relevant clauses as mentioned above.
The measurement for the rail cum road shall be made in square metres of top concrete
completed surface of the rail cum road and shall include all items such as earth work
(excavation, backfilling, disposal etc.), compaction, rolling, watering, WBM etc. complete
as per drawing but excluding concrete (all type), reinforcement, structural steel and rails.
Usage of WMM in place of WBM shall be done with approval of employer without any
additional financial implication.
This is a lump sum item. The Contractor shall be required to complete the work in all
respect as per drawings furnished by the Employer. All the items including, compaction,
brick work, roof truss, purlins, roofing, all types of miscellaneous steel, internal and
external plastering, painting etc. shall be deemed to be included in this lump sum cost.
However, concrete (all types) and reinforcement shall be measured and paid under the
relevant clauses as mentioned above.
20.17 EXTERNAL WATER SUPPLY FROM BORE-WELL TO FIRE WATER TANK, CONTROL ROOM
BUILDING AND TRANSIT CAMP:
The external water supply from Bore-well shall be measured in running meters of pipe of
various diameters. It shall include all the items such as earth work (excavation,
backfilling, disposal etc.), piping, pipe fittings, painting, brickwork, sand filling, concrete,
valves, chambers cutting chases in walls, openings in RCC and repairs, etc. required to
complete the job.
Sewage System of the shall be measured diameter wise in running meters. It shall
include all the items such as earth work (excavation, backfilling, disposal etc.), piping,
pipe fittings, manholes, gully trap, gully chamber, encasing in concrete and repairs etc
required to complete the job. Any modification in the existing sewage system, if required,
shall be done by the Contractor without any financial implication to Employer.
Various items like earth work (excavation, backfilling, disposal etc.), concrete (all type),
reinforcement steel and miscellaneous steel required for construction of cable trenches
shall be measured and paid under respective clauses mentioned above.
20.20 DRAINS:
The item Concrete (all type) & Reinforcement for drains shall be measured under
relevant clauses as mentioned above. All other items required for completion of drains
CNS or sand filling or boulder packing with interstices filled with sand under or sides of
the foundations, roads, cable trenches, drains etc shall be measured in cubic meters.
20.22.1 For payment purpose pile of different diameter shall be measured separately in length
(running meter) from bottom of pile cap to the lowest point of pile. The rate shall include
boring, providing and installation including temporary casing as applicable etc. complete
in all respect except for concrete and reinforcement steel which will be paid separately
under relevant items of BPS. Initial and routine test for vertical load and lateral load shall
be payable under respective items of BPS.
20.22.2 In case pile foundation is not envisaged originally in the LOA then concrete and
reinforcement steel shall be measured and paid as per items mentioned under relevant
clauses as mentioned above. Boring installation including temporary casing, bentonite
treatment, initial and routine tests etc of pile will be paid as an extra item. In case extra
quantity of cement is required to meet the provisions of IS: 2911, it will be paid as an
extra item.
20.24 Billing break up of Lump sum items for payment purpose shall be decided at site by
Engineer in charge for the work.
20.25 Civil works for Pipe supports and deluge valve housing for firefighting shall be deemed to
be included in the items for firefighting and shall not be paid under civil works.
In case hard rock is encountered during excavation, the level of rock surface before start
and completion of rock excavation shall be recorded for calculating the quantity of
excavation of hard rock. The volume of hard rock shall be computed on the basis of stacks
of excavated rubble after making 50 % deduction for voids. The item of excavation in hard
rock shall be payable separately.
The quantity of earth work in excavation in all kinds of soil & soft/disintegrated rock shall
be arrived by reducing quantity of hard rock from the gross excavated quantity.
The unit rate shall include all lifts and all leads within levelling boundary. It also includes
disposal of surplus earth and stacking of unusable material up the lead of2000 meters
beyond the levelling boundary. Rate of item shall include all operations specified in the
respective clause of technical specification.
20.27.2 EARTH WORKS IN EXCAVATION IN ALL TYPES OF SOILS AND SOFT /DISINTEGRATED
ROCKS, HARD ROCKS AND DISPOSAL.
Quantity of excavation in all type of soils and soft/disintegrated rocks shall be worked out
based on initial level before start of excavation and final levels after excavation. No void
deduction shall be made to calculate net quantity of earth work in excavation. The
excavated soil and soft/disintegrated rock shall be used for filling in lower areas of the
substation. The unit rate shall include disposal of excavated material for leads up to 1000
meters beyond the levelling boundary.
For hard rock excavation, the volume of hard rock shall be computed on the basis of stacks
of excavated rubble after making 50% deduction for voids. The unit of measurement shall
be in cubic meter. The unit rate shall include stacking, disposal of excavated material for
leads up to 2000 meters beyond the levelling boundary.
Where soil, soft/disintegrated rock and hard rock are mixed, the quantity of earth work in
excavation in all kinds of soil & soft/disintegrated rock shall be arrived by reducing
quantity of hard rock from the gross excavated quantity. Rate of item shall include all
operations specified in the respective clause of technical specification.
For borrowed earth, the measurement shall be based on levels of area under filling only.
The quantity of earth shall be worked out based on initial and final levels of levelling area.
No void deduction shall be made to calculate net quantity of earth work. The unit of
measurement shall be in cubic meter. The rate shall include arrangement of borrow area,
payment of royalty, transportation, laying compaction, all leads and lifts etc. Rate of item
shall include all operations specified in the respective clause of technical specification.
1. TYPE OF PANELS
1.1 Simplex Panel
Simplex panel shall consist of a vertical front panel with equipment
mounted thereon and having wiring access from rear for control panels &
front for relay/protection/Interface panels. In case of panel having width
more than 800mm, double leaf-doors shall be provided. Doors shall have
handles with built-in locking facility.
1.2 Duplex Panel
Duplex panel shall be walk-in tunnel type comprising two vertical front and
rear panel sections connected back-on-back by formed sheet steel roof tie
members and a central corridor in between. The corridor shall facilitate
access to internal wiring and external cable connections. In case of
number of duplex panels located in a row side by side, the central corridor
shall be aligned to form a continuous passage. Both ends of the corridor
shall be provided with double leaf doors with lift off hinges. Doors shall
have handles with built-in locking facility. Separate cable entries shall be
provided for the front and rear panels. However, inter-connections
between front and back panels shall be by means of inter panel wiring at
the top of the panel.
2. CONSTRUCTIONAL FEATURES
2.1. Control and Relay Board shall be simplex type unless otherwise
indicated in section-project / bill of quantity as duplex type. It is the
responsibility of the Contractor to ensure that the equipment specified and
such unspecified complementary equipment required for completeness of
the protective/control schemes be properly accommodated in the panels
without congestion and if necessary, either more number of panels or
panels with larger dimensions shall be provided (as per panel layout
requirement). No price increase at a later date on this account shall be
allowed. However, the width of panels that are being offered to be placed
in existing switchyard control rooms, should be in conformity with the
space availability in the control room.
2.2. Panels shall be completely metal enclosed and shall be dust, moisture and
vermin proof. The enclosure shall provide a degree of protection not less
than IP-31 in accordance with IS: 2147.
2.3. Panels shall be free standing, floor mounting type and shall comprise
structural frames completely enclosed with specially selected smooth
finished, cold rolled sheet steel of thickness not less than 3 mm for weight
bearing members of the panels such as base frame, front sheet and door
frames, and 2.0mm for sides, door, top and bottom portions. There shall
be sufficient reinforcement to provide level transportation and installation.
2.4. All doors, removable covers of panels shall be gasketed all around with
synthetic gaskets Neoprene/EPDM generally conforming with provision of
5. TERMINAL BLOCKS
5.1. All internal wiring to be connected to external equipment shall terminate on
terminal blocks. Terminal blocks shall be 650 V grade and have 10 Amps.
Continuous rating, moulded piece, complete with insulated barriers, stud
type terminals, washers, nuts and lock nuts. Markings on the terminal
blocks shall correspond to wire number and terminal numbers on the
wiring diagrams. All terminal blocks shall have shrouding with transparent
6. PAINTING
The painting shall be carried out as detailed in Section–GTR.
7. MIMIC DIAGRAM (FOR CONTROL PANELS)
7.1. Coloured mimic diagram and symbols showing the exact representation of
the system shall be provided in the front of control panels.
7.2. Mimic diagram shall be made preferably of anodised aluminium or plastic
of approved fast colour material, which shall be screwed on to the panel
and can be easily cleaned. The mimic bus shall be 2mm thick. The width
of the mimic bus shall be 10mm for bus bars and 7mm for other
13. SWITCHES
13.1. Control and instrument switches shall be rotary operated type with
escutcheon plates clearly marked to show operating position and circuit
designation plates and suitable for flush mounting with only switch front
plate and operating handle projecting out.
13.2. The selection of operating handles for the different types of switches
shall be as follows :
17. RELAYS
17.1. All relays shall conform to the requirements of IS: 3231/IEC-60255/IEC
61000 or other applicable standards. Relays shall be suitable for flush or
semi-flush mounting on the front with connections from the rear.
17.2. All protective relays shall be of numerical type and communication
protocol shall be as per IEC 61850. Protective relays shall also fulfil
the requirements specified for Protection IEDs in Section-
Substation automation system
17.3. All protective relays shall be in draw out or plug-in type/modular cases
with proper testing facilities. Necessary test plugs/test handles shall be
supplied loose and shall be included in contractor's scope of supply.
17.4. All AC operated relays shall be suitable for operation at 50 Hz. AC
Voltage operated relays shall be suitable for 110 Volts VT secondary and
current operated relays for 1 amp CT secondary. All DC operated relays
and timers shall be designed for the DC voltage specified, and shall
operate satisfactorily between 80% and 110% of rated voltage. Voltage
For 132KV
Main: Distance protection scheme
Back up: Directional Over Current and Earth fault Protection
The detailed description of line protections is given here under.
21.4. Back-up Over Current and Earth fault protection scheme with high
set feature
(a) Shall have three over current and one earth fault element(s)
which shall be either independent or composite unit(s).
(b) The scheme shall include necessary VT fuse failure relays for
alarm purposes
(c) Over current relay shall
• have directional IDMT characteristic with a definite
minimum time of 3.0 seconds at 10 times setting and have
a variable setting range of 50-200% of rated current
• have low transient, over reach high set instantaneous unit
of continuously variable setting range 500-2000 % of rated
current
• have a characteristic angle of 30/45 degree lead
• include hand reset flag indicators or LEDs.
(d) Earth fault relay shall
• have directional IDMT characteristic with a definite
minimum time of 3.0 seconds at 10 times setting and have
a variable setting range of 20-80% of rated current
• have low transient, over reach high set instantaneous unit
of continuously variable setting range 200-800 % of rated
current
• have a characteristic angle of 45/60 degree lag
• include hand reset flag indicators or LEDs
• include necessary separate interposing voltage
Tech Specification, Section: CRP Page 25 of 49
C/ENGG/SPEC/CRP REV NO: 09
transformers or have internal feature in the relay for open
delta voltage to the relay
21.5. Transformer Overload Protection Relay shall
(a) be of single pole type
(b) be of definite time over-current type
(c) have one set of over-current relay element, with continuously
adjustable setting range of 50-200% of rated current
(d) have one adjustable time delay relay for alarm having setting
range of 1 to 10.0 seconds, continuously.
(e) have a drop-off/pick-up ratio greater than 95%.
v. have minimum 02 nos. binary input per line for line protection trip
input. Binary input shall be rated for 220V DC and it shall be
possible to set the de-bounce time of the binary input.
vii. have facility to transmit the fault record to the Central unit by dialing
mode, IEC60870-5-103 or IEC60870-5-104 or TCP/IP net protocol
etc. Scope shall include dialup modem, if required with each
Acquisition unit.
ii. have all necessary hardware & software for data download from
Acquisition units, storage, processing, device (acquisition unit)
creation and configuration, and comprehensive viewer for manual
analysis of waveform. It will also have diagnostic feature to check
the healthiness of connected devices & communication link.
iii. calculate & report the fault location based on the traveling wave
data acquired from acquisition units of both end of the line.
However, Central data processing unit shall have the facility to
calculate the fault location even with only one end acquisition unit
data of the line.
III) REACTOR PROTECTION PANEL: The protection panel for Reactor shall
consist of the following features/schemes:
VI) CONTROL PANEL WITH BAY CONTROL UNIT (BCU): Various types of
control panels shall consist of the following:
General Comments:
1. These test cases are evolved from the report of working group 04 of study committee 34
(Protection) on evaluation of characteristics and performance of power system protection
relays and protective systems. For any further guidelines required for carrying out the tests,
reference may be made to the above document.
2. The test shall be carried out using network configuration and system parameters as shown
in the figure-1
3. All denotations regarding fault location, breakers etc are referred in figure –1
4. The fault inception angles are referred to R- N voltage for all types of faults
5. The fault inception angle is zero degree unless otherwise specified
6. Where not stated specifically, the fault resistance (Rf) shall be zero or minimum as possible
in simulator
7. Single pole circuit breakers are to be used
8. The power flow in double source test is 500 MW
System parameters
System voltage =400KV
CTR= 1000/1
PTR = 400000/110 (with CVT, the parameters of CVT model are shown in figure –2)
RELAY
C1 CVT C3
CT CT
XSA
XSB
C2 C4
SOURCE 1
BUS 1 S OURCE 2
BUS 2
FIGURE 1
Line parameters/km
Positive Sequence Resistance, (r1) = 0. 02897 Ω
Positive Sequence Reactance (x1) = 0.3072 Ω
Zero Sequence Resistance (r0) = 0.2597 Ω
Zero Sequence Reactance (x1) = 1.0223 Ω
Zero Sequence Mutual Resistance (rm) = 0.2281 Ω
Zero Sequence Mutual Reactance (xm) = 0.6221 Ω
Zero Sequence succeptance (bo) = 2.347 µ mho
Positive Sequence succeptance (b1) =3.630 µ mho
* Alternatively, the tests can be done with 10 Ω secondary impedance and source impedance
may accordingly be modified
CVT Model
C1
TUNING CIRCUIT ( Rl , Ll) DAMPING CIRCUIT (Ra ,La)
C2
LOAD(Rc)
CAPACITIVE DIVIDER
INTERMEDIATE TRANSFORMER
Figure-2
1. GENERAL
1.1 All the PLCC equipment covered under the package shall conform to the
requirements of the latest edition of the relevant IEC/IS Specifications or
equivalent National Standards,
3. Location of Equipment
3.1 The PLCC Equipment and Line traps as specified shall be installed at the respec-
tive ends of the transmission lines. The Contractor shall be responsible for
coordinating the equipment supplied by him with the already existing carrier
equipment at the respective sub-stations. Contractor shall also be responsible for
collecting all the necessary information/data from the respective sub-
stations/concerned State Electricity Boards for the installation of the equipment.
4. Frequency Planning
4.1 For planning frequency and output power of carrier terminals Bidders may plan
for a minimum receive signal to noise ratio of 25 dB for the speech channels
without companders. The noise power in 2.1 kHz band (300-2400 Hz) may be
taken as -13 dBm referred to the coupling point of the H.T. line. An additional
minus two and a half dB may be assumed for psophometric factor. As far as
coupling loss (phase to phase) is concerned the Bidders may assume the same as
6dB at one coupling end for evaluating SNR. For protection channels the
minimum SNR shall not be less than 15 dB under adverse weather. A safety
margin of 9 dB shall be taken over and above these SNR values in order to cater
for variations in line attenuation from the computed value as inhand reserve.
Frequency and output power of PLC terminals for protection shall be planned
such that the protection signal is received with full reliability even when one of
the phase is earthed or is on open circuit on the line side causing an additional
minimum loss of 6 dB.
The Bidder shall indicate the noise power in the bandwidth used for protection
signaling and shall submit the SNR calculations for speech as well as protection
channels on all the line section given in at the proposed frequencies. Sample
calculations for SNR requirement and power allocation over different channels
4.2 Successful Bidder shall be fully responsible for the coordination required with
concerned State Electricity Boards for finalising the frequency plan.
4.3 The frequency plan will be referred to wireless Adviser/DOP Department for
clearance and in case any change in the Contractor’s recommended carrier
frequency and power output is proposed by these authorities, the Contractor shall
have to modify his proposal accordingly. Change of power output shall, however,
not involve repeater stations.
5. Proposed Arrangement
5.1 The power line carrier communication equipment required by the OWNER is to
provide primarily efficient, secure and reliable information link for carrier aided
distance protection and direct tripping of remote-end breaker and also for speech
communication between 765/400/220 kV sub-stations. It shall include separate
carrier terminals of multipurpose type for speech and protection purposes. All
carrier terminals including those for protection shall be suitable for point to point
speech communication also.
5.2 For security reasons each 765/400/220kV transmission line shall be protected by
Main-I and Main-II protections as given below :
132kV transmission lines shall have Main I protection same as above alongwith
backup overcurrent and earth fault protections.
5.3 The requirement of carrier information on each link covered under this
specification is as below :
a) One protection channel for Main-I and another for Main-II distance
protection schemes. Further these channels will also be used as main and
back-up channel for direct circuit breaker inter-tripping for 765kV/ 400kV
lines.
5.4 The equipment for protection signals shall have high degree of reliability and
speed. It shall be guaranteed to function reliably in the presence of noise impulse
caused by isolator or breaker operation. The equipment shall be suitable for direct
tripping of remote end breaker for fault in unswitched 765kV/400 kV Shunt
Reactor & Operation of Buchholz relays of reactor etc. It shall also be possible to
effect direct tripping of breaker at one end when the other end breaker opens out
either manually or by relays such as Bus fault relay etc.
5.5 The time intervals between receipt of a trip command on the transmit side, its
transmission over the carrier link, reception at the far end and giving command to
the trip relays at the distant end shall not exceed 20 mS. for permissive inter-
tripping and 30 m sec. for direct inter-tripping even for the longest line section.
The above timings are inclusive of operating time for auxiliary relays and
interposing relays, if any, included in the PLCC equipment.
5.6 The requirement of protection signaling channel is such that security against
incorrect signals being received shall be at least two to three orders higher than
reliability against a signal not being received.
5.7 For reasons of security and reliability, phase to phase coupling for 765kV/400 kV
S/C , D/C & 220kV S/C lines shall be employed. Inter-circuit coupling shall be
used for 220/132kV D/C lines and phase to ground coupling shall be used for
132 KV S/C lines. Double differential coupling shall also be considered for
double circuit lines. Bidders must furnish detailed write-up on methods of
coupling and recommend suitable coupling mode for double-circuit lines along-
with the bids. Coupling mode shall, however, be fully confirmed by Contractor
after conducting detailed computer study taking into account the transpositions of
765kV/400 kV lines for optimum coupling mode over these line sections. The
coupling arrangement shall be fully optimized by the Contractor after conducting
detailed study of every line section individually, taking into account the
temperature variations, transpositions, earth resistivity, conductor configuration,
carrier channels requirements, security and reliability criteria and other relevant
details. The line attenuation shall be calculated for complete range of frequencies.
The earth resistivity data, existing frequency networks and other relevant details
of each line will be furnished to the Contractor for carrying out the computer
studies and frequency planning. The Contractor shall complete the computer
Tech Specification, Section : PLCC Page 3 of 23
C/ENGG/SPEC/ PLCC REV NO:05
studies wherever required and submit the frequency plan and optimum coupling
details within a period of one month from the date of receipt of above data.
5.9 The parameters of the equipment quoted shall be such that the mode of wave
propagation on 765kV/400 kV power line (with transpositions indicated) shall not
impose any limitation on the efficient and reliable performance of information
link from protection or communication point of view.
5.10 The Contractor shall have to check and prove through the results of his computer
studies that attenuation due to transpositions in the EHV lines is within limits
and the offered equipment will perform satisfactorily.
5.11 The Bidder shall submit curves illustrating ‘incorrect tripping’ and “Failure to
trip” probability plotted against corona noise level, in the presence of impulse
noise due to switching of isolator and circuit breaker etc. Details of field tests and
laboratory tests for successful operation of his equipment, under such adverse
conditions shall be furnished by the Bidder. These are to be related to end-to-end
signaling and shall take into account the type of communication link e.g. account
shall be taken of transpositions in the phase to phase coupled H.T. line. Details of
field tests and laboratory tests for successful operation of the equipment under the
above circumstances shall be submitted by the Bidder illustrating the above
parameters.
6. LINE TRAP
6.1 Line trap shall be broad band tuned for its entire carrier frequency range.
Resistive component of impedance of the line trap within its carrier frequency
blocking range shall not be less than 450 ohms for 765kV/400 kV system and 570
ohms for 220kV and 132 kV systems..
6.2 Line trap shall be provided with a protective device in the form of surge arrestors
which shall be designed and arranged such that neither significant alteration in its
protective function nor physical damage shall result from either temperature rise
or the magnetic field of the main coil at continuous rated current or rated short
time current. The protective device shall neither enter into operation nor remain in
operation, following transient actuation by the power frequency voltage
developed across the line trap by the rated short time current.
6.3 The lightning arrestor provided with the line trap of each rating shall fully comply
with the requirements of IS:3070 Part-I/IEC-60099-I Part-I. It shall conform to
type tests as applicable and type test certificate for the same shall be submitted by
the Bidder.
6.4 The lightning arrestor provided with the line trap shall be subject to routine and
acceptance tests as per IEC-60099-1 (Part-I).
6.5 The line trap on 765kV & 400 kV lines shall show no visual corona discharge at a
voltage of 508kV(rms) and 320 KV (rms) power frequency falling voltage.
Suitable corona rings may be incorporated in the line trap. Radio interference
voltage for 420/245/132 kV shall not exceed 500 micro volts at 280/163/97 kV
(rms) respectively. For 765kV, RIV shall not exceed 1000 micro volts at
508kV(rms).
6.7 Line trap shall conform to IEC 60353 (latest) fulfilling all the technical
requirements. The rated short time current for 1 Second shall be 31.5/40/50/63 kA
as per requirement. The mH. rating shall be 0.25/0.5/1.0 mH depending on
frequency plan.
6.8 The Bidder shall indicate continuous current rating of the line trap at 65 deg. C
ambient.
6.9 Reports for the following type tests on each type of line trap shall be submitted
as per clause 9.2 of GTR .
6.11 Welding
All the welding included in the manufacture of line traps shall be performed by
personnel and procedure qualified in accordance with ASME-IX and all the
critical welds shall be subject to NDT as applicable.
6.12.1 The Line Trap shall be suitable for outdoor pedestal or suspension mounting and
shall be mechanically strong enough to withstand the stresses due to maximum
wind pressure of 260 kg/square meter.
6.12.2 For pedestal mounting, each line trap shall be mounted on a tripod structure
formed by three insulator stacks arranged in a triangular form. All the accessories
and hardware, mounting stool including bolts for fixing the line trap on insulators
shall be of non-magnetic material and shall be supplied by the Contractor.
6.12.3 For suspension mounting, Contractor shall be required to coordinate the mounting
arrangement with the existing arrangement. Non-magnetic suspension hook/link
of adequate length and tensile strength to provide necessary magnetic clearance
between the line trap and suspension hardware shall be supplied by the
Contractor.
6.13.1 The line traps shall be suitable for connecting to 4" IPS Aluminium tube or 3"
IPS Al. tube or ACSR single/twin/Quad bundle conductor with horizontal or
vertical take off. Necessary connector shall be supplied by the Contractor.
6.13.4 Clamps and connectors shall be designed corona controlled. Visual Corona
extinction voltage shall not be less than 508kV(rms) & 320kV(rms) for 765kV
and 420kV respectively. All nuts and bolts shall be suitably shrouded.
6.13.5 Radio interference Voltage for 420/245/132 kV shall not exceed 500 microvolts
at 280/163/97 kV (rms) respectively. For 765kV, RIV shall not exceed 1000
micro volts at 508kV(rms).
6.13.7 Clamps/connectors shall conform to type test as per IS:5561. Type Test reports
shall also be submitted for following additional type tests :
6.13.8 Bidders are required to submit alongwith their bid typical drawings clearly
indicating the above mentioned features of the line traps, line trap mounting
arrangement and terminal connectors. For suspension mounted line traps, Bidder
shall submit drawings showing single point as well as multipoint (normally 3
point) suspension arrangements.
7. COUPLING DEVICE
7.1 The coupling devices shall be interposed between the capacitor voltage
transformer and coaxial line to the PLC transmitter/receiver, and in conjunction
with the capacitor voltage transformer shall ensure :
7.2 The coupling device, in conjunction with the CVT shall from an electric filter of
band pass type :
c) Power frequency currents derived by the CVT may be drained to the earth
by a separate inductance termed drain coil of suitable rating.
d) Voltage surges coming from the power line at the terminals of the
coupling device shall be limited by a non-linear surge arrestor of suitable
rating in the primary side. Requirement of a gas type voltage arrestor in
secondary side of the coupling device shall have to be fully justified, but
7.3 Two numbers ‘phase to earth’ type coupling filters shall be used to achieve
‘phase to phase’/ ‘inter-circuit coupling’. Connection between secondaries of the
two phase to earth type coupling device shall be through a balancing
transformer/hybrid such that reliable communication shall be ensured even when
one of the coupled phase is earthed or open circuited on the line side.
7.4 Coupling device shall conform to IEC-60481 and shall have the following carrier
frequency characteristics as applicable to a phase to earth type coupling device:
a) Nominal line side i) 240 ohms for 765kV and 400 kV Quad/triple
impedance bundle conductor line.
ii) 320 ohms for 400kV twin bundle conductor line.
iii) 400 ohms for 220/132 kV line
b) Nominal equipment 75 ohms (unbalanced)
side impedance
c) Composite loss Not more than 2 dB
7.5 The coupling device shall be suitable for outdoor mounting. Temperature of
metallic equipment mounted outdoor is expected to rise upto 65 deg. C during the
maximum ambient temperature of 50 deg. C specified. The equipment offered by
the Bidder shall operate satisfactorily under these conditions.
7.7 Coupling device shall have at least two terminals for carrier equipment
connection. Bidder shall confirm that such a parallel connection to coupling
device directly will not result in any additional attenuation.
7.8 The coupling device including the drainage coil, surge arrester and earthing
switch shall conform to type tests and shall be subject to routine tests as per IEC-
60481/IS:8998.
ii) Turns ratio test and insulation tests on the balancing transformer.
iii) Milli volt drop test, power frequency voltage test and mechanical
operation test on earthing switch.
iv) Power frequency spark over test for lightning arrester as per relevant
IS/IEC.
7.9 Reports for the following type tests on coupling device shall be submitted as per
clause 9.2 of GTR .
5)Tests on Arrestors
Bidder shall furnish, alongwith his bid copies of all type and routine test
conducted earlier on similar coupling device in accordance with relevant
standards.
8.1 High frequency cable shall connect the coupling device installed in the switchyard
to the PLC terminal installed indoor.
Bidder must enclose in his bid a detailed construction drawing of the cable being
offered, with mechanical and electrical parameters.
8.3 Impedance of the cable shall be such as to match the impedance of the PLC
terminal on one side and to that of the coupling device on the other side over the
entire carrier frequency range of 40-500 kHz.
8.4 Conductor resistance of cable shall not exceed 16 ohms per Km at 20°C.
8.5 The cable shall be designed to withstand test voltage of 4 kV between conductor
and outer sheath for one minute.
8.6 Bidder shall specify attenuation per Km of the cable at various carrier frequencies
in the range of 40 to 500 kHz. The typical attenuation figures for H.F. cable shall
be in the range of 1 to 5 dB/km in the frequency range of 40-500 kHz.
8.7 The H.F. cable shall conform to type tests and be subjected to routine tests as per
IS 11967(Part 2/Sec 1): 1989/IS 5026:1987.
8.8 All HF cables within the scope of this specification shall be laid and termination
shall be carried out by the Contractor.
8.9 The cables shall be supplied wound on drums containing nominal length of 500
meters each. However, exact requirement of drum lengths shall be finalised
during detailed engineering to avoid joint in HF cable and its wastage.
9.1 As already indicated the information link shall be provided for speech, protection,
telex and data services.
9.2 PLC terminal shall use Amplitude Modulation and shall have single side band
transmission mode. These shall be equipped for fixed frequency duplex working.
Characteristic input and output parameters of the SSB PLC terminals shall be as
per IEC-60495, unless otherwise specified.
9.4 All the PLC terminals shall be of multipurpose type. The Bidder shall confirm
that the total transmission time for teleprotection shall not exceed 20 ms for
permissive and 30 ms for direct tripping signals. Speech and teleprotection
channels shall independently fulfill the SNR requirements out of the power
allocated to its channel from the total power of the PLC terminals.
Detailed calculation for SNR requirement and power allocation over different
channels should be furnished alongwith the bid.
9.5 In the input circuit of the PLC terminal protective devices shall be provided in the
form of zener diodes or surge suppressers in order to eliminate any surge transfer
through the coupling device or the surge induced in the connecting path of H.F.
cable.
9.7 Sudden changes in input level to the receiver shall not cause false tripping. The
Bidder shall clearly indicate in his offer the methods adopted to ensure above
phenomenon. The receiver design shall also provide protection against false
tripping from random noise.
9.9 The PLC set shall be designed to give guaranteed performance from 0 deg. C to
50 deg. C ambient temperature. The thermal capability of the equipment shall be
so designed that the equipment remains operational successfully upto 60 deg. C
ambient temperature. Any ventilation fans provided for circulation of air inside
the cabinets shall conform to relevant Indian Standards.
9.10 The terminals shall be provided with built-in indicating instrument to facilitate
checking of important voltages and current values and signal levels in different
parts of the PLC Terminals. Protection fuses shall be provided in all important
circuits and fuses shall be so mounted as allow their easy inspection and
replacement. All test points shall be easily accessible.
The carrier set shall be provided with suitable supervision and alarm facilities.
Individual parts of the carrier set should be accessible from front, making it
possible to place the carrier cabinets side-by-side. All components and parts of the
carrier set shall be suitably tropicalised.
9.11 PLC terminals shall be housed in floor mounting sheet metal cabinets, suitable for
mounting on concrete plinth as well as channel frame by means of nuts and bolts
or welding. All the panels shall be properly earthed to the OWNER’s earthing
grid by the Contractor. Contractor shall submit detailed drawings for earthing
connections.
9.12 All the panels shall be protected against moisture ingress and corrosion during
storage. Panels shall be properly dried before they are installed and energized.
9.13 All cabinets having PLC terminals shall be provided with lamps of sufficient
wattage for interior illumination with switch. Each panel shall be provided with
240 V AC single phase socket with switch to accept 5 & 15A standard Indian
plugs.
9.14 A name plate shall be provided on the front door of each cabinet indicating
channel function, transmitter frequency and direction etc.
9.15 Reports for the following type tests for PLC Terminals shall be submitted as per
clause 9.2 of GTR .
Tests to determine various characteristics of PLC terminals as per IEC –60495.
a)Voltage variation
c)Frequency accuracy
f)Harmonic distortion
g) Selectivity
j)Balance to ground
k)Limiter action
l)Spurious emission
n)Attenuation distortion
r)Conducted noise
t)Speech levels
v)Insulation test
All solid state equipment shall be burn-in for minimum of 120 hours
continuously under operation condition. During the last 48 hours of testing, the
ambient temperature of the test chamber shall be 50°C. Each PLC panel shall be
complete with all associated sub-systems and the same shall be in operation
during the above test. During the last 48 hours of the above test, the temperature
inside the panel shall be monitored with all the doors closed. The temperature of
the panel interior shall not exceed 65°C.
10.1 PLC equipment offered shall provide telephone communication between the
stations where the transmission lines are terminating. The equipment shall be
suitable for providing the following facilities :
b) The equipment shall contain all normal facilities like ring back tone, dial
tone, engage tone & priority tone, and suitable pulses to establish and
disconnect communication between subscribers.
c) The equipment shall be provided with necessary alarm circuits and fuses
etc.
g) All the carrier telephone conversations shall be secret and it should not be
possible for anybody to over hear the conversation going on between any
two parties excepting those provided with over-riding facilities.
h) The necessary cables for connecting all the telephone instruments ordered
for at each sub-station (including wiring and termination) shall be
provided by the Contractor. These telephone instruments shall be located
within control room building at respective sub-station.
i) The cabinets housing the equipment for EPAX, four wire E/M interface &
remote subscriber units (four wire) shall have mounting arrangement
similar to that for PLC terminals.
j) All the terminals for speech shall be with Transit Band Pass Filter suitable
for tuning at site and shall be wired for addition of VFTs in future.
l) Terminals for protection shall be suitable for speech between two ends of
each transmission line or on tandem operation basis with back to back
connection at the intermediate stations.
10.2.1 The 24 line Electronic Private Automatic Exchange (EPAX) wherever specified
shall be connected to minimum six trunk routes thorough PLCC channels (speech
panel) with Four-wire E/M’ interface unit. This 4-wire interface unit either shall
form an integral part of the ‘EPAX’ system or be suitable for mounting/housing in
the carrier panel. The exchange will have its own ringing current and tone
generator etc. The exchange shall be suitable for working on 48 V DC Power
Supply (positive pole earthed).
The exchange shall be fully automatic, solid state, and of modular construction
and shall have multiple switching routes (minimum 4-routes).
10.2.2 ‘EPAX’ shall also be provided with two (2) additional interface units and operate
exclusively with OWNER’s leased subscriber lines, of Department of
Telecommunication (DOT) and compatible with 2 wire full duplex, voice grade
mode of operation.
The details of communication protocol, for interfacing of the ‘DOT’ leased lines,
shall be coordinated by the Contractor, with the licensing authority (DOT).
10.3 Remote End Four Wire ‘E/M’ Interface & Subscriber Unit or Equivalent
EPAX (4x4)
10.3.1 The remote end four wire ‘E/M’ interface & subscriber units, wherever specified,
shall be of electronic type and be suitable for working on fixed frequency power
line carrier systems with E & M signaling. This shall be housed in the carrier set
and be fully wired to the power line carrier terminal equipment.
10.3.2 This unit shall receive and register various signals, on PLCC Channels, from
remote end exchanges or other remote end subscriber units and associated four
wire interface unit.
10.3.3 The four wire interface unit shall be equipped for routing transit calls and shall be
supplied pre-wired to handle calls for minimum eight directions, in a form
suitable for transmission over PLCC.
10.3.4 The bidder shall also indicate the total number of trunk-line capacity, available
with each four-wire interface unit.
10.4.1 The Bidder shall offer voice frequency transmission equipment which shall work
on frequency shift or coded signal principle for transmission/reception of
protection signals as single purpose channel. The equipment shall be suitable for
connection to the power line carrier terminal.
10.4.2 The voice frequency transmission equipment shall not only be insensitive to
corona noise but shall also remain unaffected by impulse type noise which are
generated by electrical discharge and by the opening and closing of circuit
breakers, isolators, earthing switches etc. The equipment shall also be made
immune to a field strength of 10V/m expected to be caused by portable radio
transmitters in the range of 20-1000 MHz. In his offer, bidder shall clearly explain
as to what measures have been taken to make the equipment insensitive to corona
noise, white noise and to impulse noise of an amplitude larger than the wanted
signal and submit full field test and laboratory test reports. The guarantee on
design data shall not be acceptable.
10.4.3 The equipment shall be unaffected by spurious tripping signals. The Bidder shall
submit proof as to how this is achieved satisfactorily.
10.4.4 The equipment shall be suitable for transmission of direct and permissive trip
signal as well as blocking signals for protective gear of power system. The
equipment shall be operated in the audio frequency range in speech band or
above speech band as superimposed channel in 4 kHz band of SSB carrier. The
equipment shall operate with full duplex frequency shift mode of operation or by
switching between two frequencies in case of coded signals . The protection
signaling equipment shall be of solid state design, modular in construction and
have a proven operating record in similar application over EHV systems. Details
regarding application of the equipment over 765kV/400kV/220kV systems shall
be submitted along with the bid. Each protection signaling equipment shall
provide:
10.4.5 The equipment shall be designed for remote tripping/ blocking on permissive
basis and direct tripping for reactor fault and others. The overall time of PLC,
Operating time lower than specified above may be preferred provided they fulfill
the requirements of security and reliability as mentioned below :
False - trip probability 10-5
(Noise burst of any amplitude)
10.4.6 It may be emphasized that specified time, as mentioned above is composed of the
following :
a) Transmit side
Contact Rating:
Contact Rating:
c) Alarm
10.4.8 The Contractor shall submit drawings showing inter-connection between PLCC
and protection panels for approval by the OWNER.
10.4.9 It has to be ensured that under no circumstances protection channel should share
the power. Each protection channel shall be able to transmit power for which
system is designed. For example, a 40 W PLC terminal shall transmit 40 Watt
(max.) for protection channel alone in the event of fault. Speech and super-
imposed data channels, in the same protection terminal must get disconnected
momentarily during the operation of protection channels.
10.4.10 The equipment shall be constructed such that in permissive line protection system,
operational reliability of the protection channel may be checked over the carrier
link by means of a loop test. It shall be possible to carry out the above test from
either end of the carrier link. During healthy condition of the transmission line,
the loop test shall not initiate a tripping command. In the event of a system fault,
while loop test is in progress, protection signal shall over-ride the test signal.
10.4.12 Reports for the following tests as per clause 9.2 of GTR shall be submitted for
approval for protection coupler and the relays associated with PLCC equipment
for network protection signaling equipment and interface unit with protective
relay units if any :
c)Reflected noise
d)Reverse polarity
f)Transmission time
h)Alarm function
g)Security
h)Dependability
j)Insulation test.
Print testing kit for PLCC terminal, E/M interface & subscriber unit, Protection
coupler & EPAX —
2. Nose pliers
3. Cutting pliers
4. Ordinary Pliers
5. Adjustable wrench
b) 35 Watts - 1 No
c) 10 watts - 1 No.
8. Print extender
9. Print puller
12. Large selection of plugs, jacks & pistol probes compatible with equipment
supplied
1. Composite loss and return loss on coupling device using dummy load.
5. If end to end return loss for optimum coupling mode is not satisfactory,
same shall be measured for other coupling modes also.
7. AF frequency response (end to end) for the entire 4 kHz Bandwidth for
speech and teleoperation channels.
11. Observation of Tx/Rx levels (test-tone) for each channel at both ends by
sequential switching on/off parallel channels using dummy load and also
with the transmission line.
Notes
1. All measurements for link attenuation, composite loss and return loss shall
be carried out for the entire range of carrier frequencies with specific
attention to the frequencies.
3. Necessary test instruments required for all the above tests shall be brought
by commissioning engineers of the contractor.
SECTION: LT SWITCHGEAR
1.1.2. All board frames, shall be fabricated using suitable mild steel structural sections or
pressed and shaped cold-rolled sheet steel of thickness not less than 2.0 mm. Frames
shall be enclosed in cold-rolled sheet steel of thickness not less than 1.6 mm. Doors and
covers shall also be of cold rolled sheet steel of thickness not less than 1.6 mm.
Stiffeners shall be provided wherever necessary. Gland plate shall be cold rolled sheet
steel having thickness not less than 3 mm in all cases. However, in case of termination
of single core power cables, gland plate shall be of non-magnetic material of at least
4mm thickness.
1.1.3. All panel edges and cover/door edges shall be reinforced against distortion by rolling,
bending or by the addition of welded reinforcement members.
1.1.4. The complete structures shall be rigid, self-supporting, and free from flaws, twists and
bends. All cut-outs shall be true in shape and devoid of sharp edges.
1.1.5. All boards shall be of dust and vermin proof construction and shall be provided with a
degree of protection of IP: 52, for category I enclosure as per IS 13947 (Part-1).
However, the busbar chambers having a degree of protection of IP: 42, in accordance
with IS 13947 (Part-1), are also acceptable where continuous busbar rating exceeds 1000
Amp. Provision shall be made in all draw out Air Circuit Breaker compartments for
providing IP: 52 degree of protection, when Circuit breaker trolley, has been removed.
Panels with lighting transformers shall have IP 31 degree of protection in accordance
with IS 13947 (Part-1). Door frame of panels, meters, relays, Breaker cut-outs shall be
provided with neoprene rubber gaskets generally conforming to Type-II, Class 2A as
per IS: 11149.
1.1.6. Provision of louvers on boards would not be preferred. However, louvers backed with
metal screen are acceptable on the busbar chambers where continuous busbar rating
exceeds 1000 Amps. Panels with lighting transformers in lighting distribution boards
shall have louvers.
1.1.7. All boards shall be of uniform height not exceeding 2450 mm.
1.1.8. Boards shall be easily extendible on both sides, by the addition of the vertical sections
after removing the end covers of bus bar chambers.
1.1.10. a) All boards shall be of double front construction and shall have :
(i) A completely enclosed busbar compartment for running horizontal busbars and
vertical busbars. Busbar chambers shall be completely enclosed with metallic
portions. Bolted covers shall be provided for access to horizontal and Vertical
busbars for repair and maintenance, which shall be feasible without disturbing
feeder compartment. Vertical bus bar chambers shall be accessible from front as
well as back side of the panel and shall be of at least 350 mm width. One set of
vertical busbars shall be used in between two adjacent sections for switchgear
connections. In case of ACB feeders, the panel shall have single front without
any vertical busbar chamber, however vertical busbars associated with ACBs
shall be located in rear side and shall be additionally covered with metallic
perforated/ transparent acrylic or polyvinyl bolted sheets to avoid direct access
after opening rear door of chamber.
(ii) Completely enclosed switchgear compartment(s) one for each circuit for housing
circuit breaker or MCCB or motor starter.
(iii) A distinct compartment or alley for power and control cables on each side of
panel. Cable alley compartment shall have a through metallic partition for
segregating cables on both sides. Cable alley door shall preferably be hinged.
Cable alley shall have no exposed live parts. Any live terminals shall be fully
shrouded/insulated from safety aspects. However, it shall be of atleast 350mm
width.
(iv) A compartment for relays and other control devices associated with a circuit
breaker.
1.1.11. Sheet steel barriers shall be provided between two adjacent vertical panels running to the
full height of the switchboard, except for the horizontal busbar compartment. Each
shipping section shall have full metal sheets at both ends for transport and storage.
1.1.12. All equipments associated with a single circuit except MCB circuits shall be housed in a
separate compartment of the vertical section. The Compartment shall be sheet steel
enclosed on all sides with the withdrawal units in position or removed. The front of the
compartment shall be provided with the hinged single leaf door, with locking facilities.
In case of circuits controlled by MCBs, group of MCB feeders can be offered in common
compartment. In such case number of MCB feeder to be used in a common compartment
shall not exceed 4 (four) and front of MCB compartment, shall have a viewing port of
1.1.13. After isolation of power and control circuit connections it shall be possible to safely
carryout maintenance in a compartment with the busbar and adjacent circuit live. Neces-
sary shrouding arrangement shall be provided for this purpose over the cable terminations
located in cable alley.
1.1.14. The minimum clearance in air between phases and between phase and earth for the entire
run of horizontal and vertical busbars, shall be 25 mm. For all other components, the
clearance between "two live parts", " A live part and an earthed part" and isolating
distance shall be atleast ten (10) mm throughout. Wherever it is not possible to maintain
these clearances, insulation shall be provided by sleeving or barriers. However, for
horizontal run of busbar minimum clearance of 25 mm should be maintained even if they
are sleeved.
1.1.15. The temperature rise of horizontal & vertical busbars when carrying rated current along
its full run shall in no case exceed 55°C, with silver plated joints and 40°C with all other
type of joints over an outside ambient temperature of 50°C.
1.1.16. All busbar chambers shall be provided with removable bolted covers . The covers shall
be provided with danger labels.
1.1.17. All identical circuit breakers and module chassis of same test size shall be fully
interchangeable without having to carryout modifications.
1.1.18. All Circuit breaker boards shall be of Single Front type, with fully drawout circuit
breakers, which can be drawn out without having to unscrew any connections. The circuit
breakers shall be mounted on rollers and guides for smooth movement between
SERVICE, TEST and ISOLATED positions and for withdrawal from the Switchboard.
Testing of the breaker shall be possible in the TEST position.
1.1.19. Wherever two breaker compartments are provided in the same vertical section, insulating
barriers and shrouds shall be provided in the rear cable compartment to avoid accidental
touch with the live parts of one circuit when working on the other circuit.
1.1.20. All disconnecting contacts for power circuits shall be of robust design and fully self
aligning. Fixed and moving contacts of the power drawout contact system shall be silver
plated. Both fixed and moving contacts shall be replaceable.
1.1.22. All module shall be fixed type except air circuit breaker module, which shall be drawout
type.
1.1.23. The connections from busbars to the main switch shall be fully insulated/shrouded, and
securely bolted. The partition between the feeder compartment and cable alley may be
non-metallic and shall be of such construction as to allow cable cores with lugs to be
easily inserted in the feeder compartment for termination.
1.1.24. All equipment and components shall be neatly arranged and shall be easily accessible for
operation and maintenance. The internal layout of all modules shall be subject to
PURCHASER approval. Bidder shall submit dimensional drawings showing complete
internal details of Busbars and module components, for each type and rating for approval.
Technical Specification, Section: LT Switchgear . Page:3 of 26
C/ENGG/SPEC/LTSWGR Rev. No: 5
1.1.25. The tentative power and control cable entries shall be from bottom. However, Purchaser
reserves the right to alter the cable entries, if required, during detailed engineering,
without any additional commercial implication.
1.1.26. Adopter panels and dummy panels required to meet the various busbar arrangements and
layouts required shall be included in Bidder's scope of work.
1.3.1. All AC Distribution Boards shall be provided with three phase buses and a neutral bus
bars and the DC Distribution Boards shall be provided with two busbars.
1.3.2. All busbars and jumper connections shall be of high conductivity aluminium/copper of
adequate size.
1.3.3. The Cross-Section of the busbars shall be uniform through out the length of Switchgear
and shall be adequately supported and braced to withstand the stresses due to the
specified short circuit currents.
1.3.4. All busbars shall be adequately supported by adequate numbers of high strength type
Polyester fibre glass Moulded Insulators to withstand short circuit withstand capability
of panel. Separate supports shall be provided for each phase and neutral busbar. If a
common support is provided anti-tracking barriers shall be provided between the
supports.
1.3.5. All busbars joints shall be provided with high tensile steel bolts. Belleville/spring
washers and nuts, so as to ensure good contacts at the joints. Non-silver plated Busbars
joints shall be thoroughly cleaned at the joint locations and a suitable contact grease shall
be applied just before making a joint.
1.3.6. All busbars shall be colour coded as per IS: 11353-1985: Guide for Uniform System of
Marking and Identification of Conductors and Apparatus Terminals.
1.3.7. The Bidder shall furnish calculations, establishing the adequacy of busbar sizes for
specified current ratings, On the basis of short circuit current and temperature rise
consideration at specified ambient temp.
1.4.1. A galvanised steel earthing shall be provided at the bottom of each panel and shall extend
throughout the length of each switchboard. It shall be welded/bolted to the frame work
of each panel and breaker earthing contact bar vertical bus shall be provided in each
vertical section which shall in turn be bolted/welded to main horizontal ground bus.
1.4.2. The earth bus shall have sufficient cross-section to carry the momentary short circuit and
short time fault currents to earth without exceeding the allowable temperature rise.
Technical Specification, Section: LT Switchgear . Page:4 of 26
C/ENGG/SPEC/LTSWGR Rev. No: 5
1.4.3. Suitable arrangements shall be provided at each end of the horizontal earth bus for
bolting to Purchaser's earthing conductors. The horizontal earth bus shall project out the
switchboard ends and shall have predrilled holes for this connection. A joint spaced and
taps to earth bus shall be made through at least two bolts.
1.4.4. All non-current metal work of the Switchboard shall be effectively bonded to the earth
bus. Electrical conductivity of the whole switchgear enclosures frame work and the truck
shall be maintained even after painting.
1.4.5. The truck and breaker frame shall get earthed while the truck is being inserted in the
panel and positive earthing of the truck and breaker frame shall be maintained in all
positions. SERVICES & ISOLATED, as well as through out the intermediate travel.
1.4.6. Air Circuit Breaker (ACB) module frame shall get engaged to the vertical earth bus,
before the disconnecting contacts on these module are engaged to the vertical busbar.
1.4.7. All metallic cases of relays, instruments and other panel mounted equipments shall be
connected to earth by independent stranded copper wires of size not less than 2.5 mm2.
Insulation colour code of earthing wires shall be green. Earthing wires shall be
connected to terminals with suitable clamp connectors and soldering is not acceptable.
Looping of earth Connection which would result in loss of earth connection to the
devices when a device is removed is not acceptable. However, looping of earth
connections between equipment to provide alternative paths or earth bus is acceptable.
1.4.8. VT and CT secondary neutral point earthing shall be at one place only, on the terminal
block. Such earthing shall be made through links so that earthing of one secondary
circuit shall be removed without disturbing the earthing of other circuit.
1.4.9. All hinged doors shall be earthed through flexible earthing braid.
1.4.10. Caution nameplate `Caution-Live Terminals' shall be provided at all points where the
terminals are like to remain live and isolation is possible only at remote end.
1.5.1. Circuit breakers shall be three-pole air break horizontal drawout type and shall have
inherent fault making and breaking capacities as specified in "Technical Parameters".
The circuit breakers which meet specified parameter only after provision of releases or
any other devices shall not be acceptable.
1.5.2. Circuit breakers shall be mounted along with it operating mechanism on a wheeled
carriage. Suitable guides shall be provided to minimise misalignment of the breaker.
1.5.3. There shall be `Service', `Test' and `Fully withdrawn positions for the breakers. In `Test'
position the circuit breaker shall be capable of being tested for operation without
energising the power circuits i.e. the power Contacts shall be disconnected while the
Control circuits shall remain undisturbed. Locking facilities shall be provided so as to
prevent movement of the circuit breaker from the `SERVICE', `TEST' OR FULLY
WITHDRAWN' position. It shall be possible to close the door in TEST position.
1.5.4. All circuit breakers shall be provided with 4 NO and 4 NC potentially free auxiliary
contacts. These contacts shall be in addition to those required for internal mechanism of
the breaker. Separate limit switches each having required number of contacts shall be
Technical Specification, Section: LT Switchgear . Page:5 of 26
C/ENGG/SPEC/LTSWGR Rev. No: 5
provided in both `SERVICE' & `TEST' position of the breaker. All contacts shall be
rated for making continuously carrying and breaking 10 Amps at 240V AC and 1 Amp
(Inductive) at 220V DC.
1.5.5. Suitable mechanical indications shall be provided on all circuit breakers to show `OPEN'.
`CLOSE', `SERVICE', `TEST' and `SPRING CHARGED' positions.
1.5.6. Main poles of the circuit breakers shall operate simultaneously in such a way that the
maximum difference between the instants of contacts touching during closing shall not
exceed half cycle of rated frequency.
1.5.7. All circuit breakers shall be provided with the interlocks as explained in further clauses.
1.5.8. Movement of a circuit breaker between SERVICE AND TEST positions shall not be
possible unless it is in OPEN position. Attempted with drawl of a closed circuit breaker
shall trip the circuit breaker.
1.5.9. Closing of a circuit breaker shall not be possible unless it is in SERVICE, TEST
POSITION or in FULLY WITHDRAWN POSITION.
1.5.10. Circuit breaker cubicles shall be provided with safety shutters operated automatically by
the movement of the circuit breaker carriage to cover the stationary isolated contacts
when the breaker is withdrawn. It shall however, be possible to open the shutters
intentionally, against spring pressure for testing purpose.
1.5.11. A breaker of particular rating shall be prevented from insertion in a cubicle of a different
rating.
1.5.12. Circuit breakers shall be provided with electrical anti-pumping and trip free feature, even
if mechanical antipumping feature is provided.
1.5.13. Mechanical tripping shall be possible by means of front mounted RED `Trip' push-
button. In case of electrically operated breakers these push buttons shall be shrouded to
prevent accidental operation.
1.5.14. Breaker controlled motors shall operate satisfactorily under the following conditions:
(i) Direct on-line starting of Induction Motors rated 110 kW to 220 kW with a locked
rotor current of seven times the rated current, and starting time of up to 30
seconds.
(ii) Breaking on-load, full load and locked rotor currents of Induction Motors for
rated 100 kW to 220 kW.
1.5.15. Means shall be provided to slowly close the circuit breaker in withdrawn position. If
required for inspection and setting of Contacts, in service position slow closing shall not
be possible.
1.5.16. Power operated mechanism shall be provided with a universal motor suitable for
operation 220V DC Control supply with voltage variation from 90% to 110% rated
voltage. Motor insulation shall be class `E' or better.
1.5.17. The motor shall be such that it requires not more than 30 seconds for fully charging the
closing spring.
Technical Specification, Section: LT Switchgear . Page:6 of 26
C/ENGG/SPEC/LTSWGR Rev. No: 5
1.5.18. Once the closing springs are discharged, after the one closing operation of circuit
breaker, it shall automatically initiate, recharging of the spring.
1.5.19. The mechanism shall be such that as long as power is available to the motor, a continuous
sequence of closing and opening operations shall be possible. After failure of power
supply at least one open-close-open operation shall be possible.
1.5.20. Provision shall be made for emergency manual charging and as soon as this manual
charging handle is coupled, the motor shall automatically get mechanically decoupled.
1.5.21. All circuit breakers shall be provided with closing and trip coils. The closing coils shall
operate correctly at all values of Voltage between 85% to 110% at rated control voltage.
The trip coil shall operate satisfactorily under all values of supply voltage between 70%
to 110% of rated control voltage.
1.5.22. Provision for mechanical closing of the breaker only in `TEST' and `WITHDRAWN'
positions shall be made.
1.5.23.1. It shall be the responsibility of the Contractor to fully co-ordinate the overload and short
circuit tripping of the circuit breakers with the upstream and down stream circuit
breakers/fuses/motor starters, to provide satisfactory discrimination.
1.6.2. MCCB shall be flush mounted on the AC/DC distribution boards and shall have
extended handle.
1.6.3 MCCBs shall be provided with thermo-magnetic type release for over current and short
circuit protection. The setting of the thermal release shall be adjustable between 80% to
100% of the rated current. The MCCB shall have breaking capacity not less than 20kA.
1.6.4 MCCBs used for ACDB incomers and Bus coupler shall be equipped with stored energy
mechanism for electrical closing and tripping. All other MCCBs shall be manually
operated. The operating handle should give a clear trip indication.
1.6.5 Miniature circuit breaker (MCB) shall conform to IEC: 898-1987 and IS: 8828.
1.7 RELAYS
1.7.1 All relays and timers in protective circuits shall be flush mounted on panel front with
connections from the inside. They shall have transparent dust tight covers removable
from the front. All protective relays shall have a drawout construction for easy
replacement from the front. They shall either have built-in test facilities, or shall be
provided with necessary test blocks and test switches located immediately below each
relay. The auxiliary relays and timers may be furnished in non-drawout cases.
1.7.3 All protective relays and timers shall have at least two potentially free output contacts.
Relays shall have contacts as required for protection schemes. Contacts of relays and
timers shall be silver faced and shall have a spring action. Adequate number of terminals
shall be available on the relay cases for applicable relaying schemes.
1.7.4 All protective relays auxiliary relays and timers shall be provided with hand reset
operation indicators (Flags) for analysing the cause of operation.
1.7.5 All relays shall withstand a test voltage of 2 KV (rms) for one minute.
1.7.6 Motor starters shall be provided with three element, ambient temperature compensated,
time lagged, hand reset type overload relays with adjustable settings. The setting ranges
shall be properly selected to suit the motor ratings. These relays shall have a separate
black coloured hand reset push button mounted on compartment door and shall have at
least one changeover contact.
1.7.7 All fuse-protected contactor-controlled motors shall have single phasing protection,
either as a distinct feature in the overload relays (by differential movement of bimetallic
strips), or as a separate device. The single phasing protection shall operate even with
80% of the set current flowing in two of the phases.
1.8 CONTACTORS
1.8.1 Motor starter contactors shall be of air break, electromagnetic type rated for
uninterrupted duty as per IS:13947 (Part 4).
1.8.2 Contactors shall be double break, non-gravity type and their main contacts shall be silver
faced.
1.8.3 Direct on line starter contactors shall be of utilisation category AC2. These contactors
shall be as per IS:13947 (Part 4).
1.8.4 Each contactor shall be provided with two (2) normally open (NO) and two (2) normally
close (NC) auxiliary contacts.
1.8.5 Operating coils of contactors shall be of 240V AC Unless otherwise specified elsewhere.
The Contactors shall operate satisfactorily between 85% to 110% of the rated voltage.
The Contactor shall drop out at 70% of the rated voltage.
1.9.1 All current and voltage transformers shall be completely encapsulated cast resin insulated
type suitable for continuous operation at the temperature prevailing inside the switchgear
enclosure, when the switchboard is operating at its rated condition and the outside
ambient temperature is 50°C.
1.9.2 All instrument transformers shall be able to withstand the thermal and mechanical
stresses resulting from the maximum short circuit and momentary current ratings of the
associated switchgear.
1.9.4 Current transformers may be multi or single core type. All voltage transformers shall be
single phase type. The Bus VTs shall be housed in a separate compartment.
1.9.5 All VTs shall have readily accessible MCBs on both primary and secondary sides.
1.10.1 All indicating and integrating meters shall be flush mounted on panel front. The
instruments shall be of at least 96 mm square size with 90 degree scales, and shall have
an accuracy class of 2.5 or better. The covers and cases of instruments and meters shall
provide a dust and vermin proof construction.
1.10.2 All instruments shall be compensated for temperature errors and factory calibrated to
directly read the primary quantities. Means shall be provided for zero adjustment without
removing or dismantling the instruments.
1.10.3 All instruments shall have white dials with black numerals and lettering. Black knife
edge pointer with parallax free dials will be preferred.
1.10.4 Ammeters provided on Motor feeders shall have a compressed scale at the upper current
region to cover the starting current.
1.10.5 Watt-hour meters shall be of 3 phase three element type, Maximum demand indicators
need not be provided.
1.11.1 Control & Selector switches shall be of rotary type with escutcheon plates clearly marked
to show the function and positions. The switches shall be of sturdy construction suitable
for mounting on panel front. Switches with shrouding of live parts and sealing of
contacts against dust ingress shall be preferred.
1.11.2 Circuit breaker selector switches for breaker Controlled motor shall have three stay put
positions marked `Switchgear', `Normal' and `Trial' respectively. They shall have two
contacts of each of the three positions and shall have black shade handles.
1.11.3 Ammeter and voltmeter selector switches shall have four stayput position with adequate
number of contacts for three phase 4 wire system. These shall have oval handles
Ammeter selector switches shall have make before break type contacts to prevent open
circuiting of CT secondaries.
1.11.4 Contacts of the switches shall be spring assisted and shall be of suitable material to give a
long trouble free service.
1.12.1 Air breaker switch shall be of the heavy duty, single throw group operated, load break,
fault make type complying with IS:13947,Part-3.
1.12.2 The Bidder shall ensure that all switches are adequately rated so as to be fully protected
by the associated fuses during all abnormal operating conditions such as overload, locked
motor, short circuit etc.
1.12.3 Switch operating handles shall be provided with padlocking facilities to lock them in
`OFF' position.
1.12.4 Interlocks shall be provided such that it is possible to open the cubicle door only when
the switch is in `OFF' position and to close the switch only when the door is closed.
However suitable means shall be provided to intentionally defeat the interlocks explained
above.
1.12.5 Switches and fuses for AC/DC control supply and heater supply wherever required shall
be mounted inside and cubicles.
1.13.1 Push-buttons shall be of spring return, push to actuate type. Their contacts shall be rated
to make, continuously carry and break 10A at 240V and 0.5A (inductive) at 220V DC.
1.13.2 All push-buttons shall have one normally open and one normally closed contact, unless
specified otherwise. The contact faces shall be of silver or silver alloy.
1.13.3 All push-buttons shall be provided with integral escutcheon plates marked with its
function.
1.13.5 All push-buttons on panels shall be located in such a way that Red-push-buttons shall
always be to the left of green push-buttons.
1.14.1 Indicating lamps shall be of the panel mounting cluster LED type. The lamps shall have
escutcheon plates marked with its function, wherever necessary.
1.14.2 Lamps shall have translucent lamp-covers of the following colours, as warranted by the
application :
1.14.3 Lamps shall be easily replaceable from the front of the cubicle.
1.14.4 Indication lamps should be located just above the associated push buttons/control
switches. Red lamps shall invariable be located to the right of green lamps. In case a
white lamp is also provided, it shall be placed between the red and green lamps along
with the centre line of control switch/push button pair. Blue and Amber lamps should
normally be located above the Red and Green lamps.
1.14.5 When associated with push-buttons, red lamps shall be directly above the green push
button, and green lamps shall be directly above the red push-button. All indicating lamps
shall be suitable for continuous operation at 90 to 110% of their rated voltage.
1.15 FUSES
1.15.1 All fuses shall be of HRC cartridge fuse link type. Screw type fuses shall not be
accepted. Fuses for AC Circuits shall be of class 2 type, 20 kA (RMS) breaking current
at 415 AC, and for DC circuits Class 1 type 4 kA breaking current.
1.15.3 Fuses shall be mounted on fuses carriers, which are mounted on fuse bases, wherever it is
not possible to mount fuses on carriers fuses shall be directly mounted on plug in type of
bases. In such cases one set of insulated fuse pulling handles shall be supplied with each
switchgear.
1.15.4 Fuse rating shall be chosen by the Bidder depending upon the circuit requirements and
these shall be subject to approval of PURCHASER.
1.16.1 Terminal blocks shall be of 750 volts grade and have continuous rating to carry the
maximum expected current on the terminals. It shall be complete with insulating barriers,
clip-on-type/stud type terminals for Control Cables and identification strips. Marking on
terminal strip shall correspond to the terminal numbering on wiring on diagrams. It shall
be similar to `ELEMEX' standard type terminals, cage clamp type of Phoenix or WAGO
or equivalent
1.16.2 Terminal blocks for CT and VT secondary leads shall be provided with test links and
isolating facilities. CT secondary leads shall be provided with short circuiting and
earthing facilities. It shall be similar to `Elem.' `CATD' - Type.
1.16.3 In all circuit breaker panels at least 10% spare terminals for external connections shall be
provided and these spare terminals shall be uniformly distributed on all terminal blocks.
Space for adding another 10% spare terminals shall also be available.
1.16.4 All terminal blocks shall be suitable for terminating on each side, two (2) Nos. of 2.5 mm
square size standard copper conductors.
1.16.5 All terminals shall be numbered for identification and grouped according to the function.
Engraved white-on-black labels shall be provided on the terminal blocks.
Technical Specification, Section: LT Switchgear . Page:11 of 26
C/ENGG/SPEC/LTSWGR Rev. No: 5
1.16.6 Wherever duplication of a terminal block is necessary it shall be achieved by solid
bonding links.
1.16.7 Terminal blocks shall be arranged with at least 100 mm clearance between two sets of
terminal block. The minimum clearance between the first row of terminal block and the
associated cable gland plate shall be 250 mm.
1.17.1 All switchgears, AC/DC distribution boards, shall be provided with prominent, engraved
identification plates. The module identification plate shall clearly give the feeder number
and feeder designation. For single front switchboards, similar panel and board
identification labels shall be provided at the rear also.
1.17.2 All name plates shall be of non-rusting metal or 3-ply lamicoid with white engraved
lettering on black back ground. Inscriptions and lettering sizes shall be subject to
PURCHASER approval.
1.17.3 Suitable plastic sticker labels shall be provided for easy identification of all equipments,
located inside the panel/module. These labels shall be positioned so as to be clearly
visible and shall give the device number as mentioned in the module wiring drawings.
1.18.1 Space heater shall be provided in all the boards for preventing harmful moisture
condensation.
1.18.2 The space heaters shall be suitable for continuous operation on 240V AC, 50 Hz, single
phase supply, and shall be automatically controlled by thermostats. Necessary isolating
switches and fuses shall also be provided.
1.19.1 All switchboards shall be supplied completely wired internally upto the terminal blocks
ready to receive Purchaser's control cables.
1.19.2 All inter cubicle and inter panel wiring and connections between panels of same
switchboard including all bus wiring for AC and DC supplies shall be provided by the
bidder.
1.19.3 All internal wiring shall be carried out with 1100 V grade, single core, 1.5 square mm or
larger stranded copper wires having colour coded, PVC insulation. CT circuits shall be
wired with 2.5 square mm copper wires. Voltage grade and insulation shall be same as
above.
1.19.4 Extra-flexible wires shall be used for wiring to device mounted on moving parts such as
hinged doors.
1.19.5 All wiring shall be properly supported, neatly arranged, readily accessible and securely
connected to equipment terminals and terminals blocks.
1.20.2 All necessary cable terminating accessories such as Gland plates, supporting clamps and
brackets, power cable lugs, hardware etc. shall be provided by the successful bidder, to
suit the final cable sizes which would be advised later.
1.20.3 The gland plate shall be of removable type and shall cover the entire cable alley. Bidder
shall also ensure that sufficient space is provided for all cable glands. For all single core
cables, gland plates shall be of non-magnetic Material.
1.21.1 Type tests reports on Panels (Switchgear and Control gear assemblies) as per IS 8623
Part-I shall be submitted for the following tests in line with clause 9.0 of Section GTR :
1.21.2 Contractor shall submit type test reports for the following Switchgear and Control gears
before the fabrication of switchgear is started:
1. Circuit breakers/MCCB as per IS 13947 Part-II
2. Protective Relays as per IEC: 60255.
3. Lighting transformers as per IS:2026
For above equipments, test conducted once are acceptable (i.e. The requirement of test
conducted within last ten years shall not be applicable)
1.22.1 The Contractor shall unload, erect, install, test and put into commercial use all electrical
equipment included in this specification.
1.22.2 Equipment shall be installed in a neat, workman like manner so that it is level, plumb,
square and properly aligned and oriented. Tolerance shall be as established in
Contractor's drawings or as stipulated by purchaser. No equipment shall be permanently
bolted down to foundations until the alignment has been checked and found acceptable
by the purchaser.
1.22.3 Contractor shall furnish all supervision, labour tools equipment rigging materials, bolts,
wedges, anchors, concrete inserts etc. in proper time required to completely install, test
and commission the equipment.
1.22.6 All boards shall be installed in accordance with relevant code of practices and at
Purchaser's instructions. All boards shall be installed on finished surfaces, concrete or
steel stills. Contractor shall be required to install and align any channel sills which form
part of foundations. In joining shipping sections of switchboards together adjacent
housing of panel sections or flanged throat sections shall be bolted together after
alignment has been completed. Power bus, enclosures ground and control splices of
conventional nature shall be cleaned and bolted together being drawn up with torque
spanner of proper size or by other approved means.
1.22.8 Contractor shall take utmost care in holding instruments, relaying and other delicate
mechanism wherever the instruments and relays are supplied separately they shall be
mentioned only after the associated panels have been erected and aligned. The
packing materials employed for safe transit of instrument and relays shall be removed
after ensuring that panel have been completely installed and to further movement of the
same should be necessary. Any damage shall be immediately reported to Purchaser.
1.22.9 Equipment furnished with finished coats of paint shall be touched by up Contractor if
their surface is specified or marred while handling.
1.22.10 After installation of panels, power and control wiring and connections, Contractor shall
perform operational tests on all switchboards, to verify proper operation of switch-
boards/panels and correctness of all equipment in each and every respect. The cable
opening and cables entries for cables terminating to the panels shall be sealed with fire
sealing materials.
The Contractor shall carry out the following commissioning checks, in addition to the
other checks and tests recommended by the manufacturers.
1.23.1 General
1.23.2.3 Check control wiring for correctness of connections, continuity and IR values.
1.23.2.12 Check on spring charging motor, correct operation of limit switches, and time of
charging.
1.23.3.3 Ratio identification checking of all ratios on all cores by primary injection of current.
1.23.5.2 Each wire shall be traced by continuity tests and it should be made sure that the wiring
is as per relevant drawing. All interconnections between panels/equipment shall
be similarly checked.
Technical Specification, Section: LT Switchgear . Page:15 of 26
C/ENGG/SPEC/LTSWGR Rev. No: 5
1.23.5.3 All the wires shall be meggered to earth.
1.23.5.4 Functional checking of all control circuit e.g. closing, tripping control, interlock,
supervision and alarm circuit.
1.23.6 Relays
1.23.6.8 Check CT and VT connections with particular reference to their polarities for directional
relays, wherever required.
1.23.7 Meters
1.23.7.3 Check CT and VT connections with particular reference to their polarities for power
type meters.
1.24.1 The Bidder shall include in his proposal any special tools and tackles required for
erection, testing commissioning and maintenance of the equipments offered.
1.24.2 The list of these special tools and tackles shall be given in the bid proposal sheets
alongwith their respective prices.
1.24.3 The total price of the special tools and tackles shall be included in proposal sheets.
1.25.1 The Bidder shall quote for various AC/DC distribution boards in accordance with this
specification.
1.25.3 The Bill of Materials for each type of module shall be as under. These are minimum
indicative requirement of the system. The necessary auxiliary relays, push buttons and
indicating lamps shall be provided as per scheme requirement. Any other
item/component required with in a module for efficient and reliable operation shall be
deemed to be included in bidder's scope.
1.25.4 Module Type AE (Electrically controlled circuit breaker for incoming and Bus Coupler
Circuit).
(i) One (1) Triple pole air circuit breaker complete with all accessories and
power operated mechanism as specified.
(vi) One (1) Triple pole instantaneous over-current relay having the
setting range of 200-800% or 500-2000% of CT secondary
and adjustable definite minimum time.
(vii) One (1) Instantaneous earth fault relay having an adjustable setting range
of 10-40% or 20 - 80% of CT secondary current and adjustable
definite minimum time. The earth fault relay shall be provided
with a stabilising resistor.
(i) One (1) Triple pole Air Circuit Breaker complete with accessories,
and power operated mechanism as specified.
(vi) One (1) Triple pole instantaneous over-current relay for providing
positive sequence current protection in all the three phases.
The relay setting range shall be continuously adjustable
between 200-800% or 400-1600% of CT secondary rated
current as required.
Technical Specification, Section: LT Switchgear . Page:17 of 26
C/ENGG/SPEC/LTSWGR Rev. No: 5
(vii) One (1) Double pole inverse definite minimum time over current
relays connected in R & B phases for over current protection
of motor rated 110 kW - 200 kW. The relay shall have an
adjustable setting range of 50% - 200% of CT Secondary
current and time setting range of 0-30 Second. The relay
shall be CDGM-22 of EE or equivalent.
(viii) One (1) Single pole adjustable definite time delay relay for motor
overload alarm connected in Y-phase only. The relay shall
have resetting ratio of not less than 90%. The relay shall have
continuously adjustable time delay range of 2.5 to 25 Sec.
(ix) One (1) Instantaneous earth fault relay having an adjustable setting
range of 10-40% or 20-80% of CT secondary current. The
earth fault relay shall be provided with a stabilising resistor.
(i) Three (3) 415 / 110 volts single phase voltage transformer star/star
√3 √3
connect with star point solidly earthed mounted on common
draw out chassis. Accuracy Class 0.5 for protection and
metering with 50VA Burden.
(v) One (1) Double pole instantaneous under voltage relays with
continuous variable setting range of 40-80% of 110 Volts.
(vi) One (1) Time delay pick up relay having a time setting range of 0.5
to 3 secs. with 3 `NO'. Self reset contacts, suitable for 220V
DC.
(vii) One (1) Auxiliary relay 220V DC with 2 NO. self reset contacts.
(viii) Three (3) Indicating lamps with series resistor and colour lenses (Red,
Blue & Yellow).
(iii) One (1) Voltmeter selector switch four position (R-Y, Y-B, B-R
OFF).
1.25.9 Module Type H & H (BC) (Isolating Switch Controlled Incoming Circuit)
(ii) One (1) Red Indicating lamp to indicate isolating switch closed
position.
(iii) One (1) Instantaneous under voltage relay with 95% of 220V DC.
The resetting ratio of relay of relay should not be more than
1.25. The relay shall be provided with a series resistor and
a push button across if for resetting (pick up) the relay at
about 105% of the drop out voltage.
(iv) One (1) Instantaneous over voltage relay with setting range of 110%
of 220V DC. The resetting ratio of relay should not be less
than 0.8. The relay shall have a push button in series of
resetting the relay at about 95% of the operating voltage.
(v) One (1) Earth leakage relay only for 220V DC system having
adjustable pick up range between 3 to 7 milliamps the relay
shall be suitable for 220V DC/240V AC Auxiliary supply.
(i) One (1) Double pole 250V DC MCCB for incomer from Battery.
(ii) One (1) DC ammeter with shunt and range of 90-0-400 Amps. For
220V DC DB and 90-0-200 Amp for 50V DC DB.
(iv) One (1) Double pole single throw 250V DC air break switch
connecting battery & charger sections to DC DB.
Technical Specification, Section: LT Switchgear . Page:19 of 26
C/ENGG/SPEC/LTSWGR Rev. No: 5
(v) One(1) set Voltage and Current Transducers
1.25.13 Module Type DG-1 (Electrically Controlled Circuit Breaker for Incomer from DG
Set)
a) One (1) Triple pole circuit breaker complete with all accessories
and power operated mechanism as specified.
k) One (1) Three pole voltage controlled definite time delay relay
having current setting range of 50-200% of CT secondary
current and adjustable time delay 0.3 to 3 secs.
l) One (1) Watt hour meter with six (6) digits and minimum count of
one (1) kwh.
m) One (1) Single pole definite time over current relay having a
continuous setting range of 50-200% of CT secondary current
and a time delay of 2.5-25 secs connected in CT of Y phase
for overload alarm. The relay shall have a setting ratio of
not less than 90%.
o) Two (2) Push buttons for Remote starting & stopping of DG Set (Red,
Green).
One (1) Double pole DC Switch with pad locking facility in off position.
(iii) Electronic Timer suitable for continuous operation, push button and selector
switch be as per scheme requirement
1.26 PARAMETERS
b) Frequency 50 Hz ± 5%
b) Fault Level 4 kA
c) System 48 V ± 10%
Voltage
d) Fault Level --
c) Momentary (kA) 45 kA
PEAK
b) No. of poles 3
j) Short Circuit
breaking current
I. AC Component 20 kA (RMS)
a) No. of poles 4 2
I. Current 20 kA (RMS)
b) Rated Voltage
Primary 415/√3 V
Secondary 110/√3 V
c) Method of connection
Primary Star
Secondary Star
1.26.9 Relay
1.27.1 EL-type module of 415V Main lighting distribution board and Emergency lighting
distribution board and shall be controlled by timer and contactor module to facilitate its
operation automatically.
(i) Under normal conditions i.e. when supply is available in both the incomers, incomers
I&II of 415 V Main switchboard, ACDB shall be in closed condition and Bus
couplers and DG set breaker shall be in open condition.
(ii) In case of failure of either of the sources, the incomer of that source shall trip and Bus
coupler shall get closed. On restoration of supply, normal conditions described above
are to be established automatically.
iii) In case of failure of supply in both the sources, both incomers, incomers of ACDBs
and ACDB Bus coupler shall trip and DG set breaker switched on.
On restoration of one or both sources, DG set breaker shall trip, DG set stopped and
conditions described in paragraph (i) /(ii) shall be restored.
LT System shall have provision of following analogue inputs for owner’s substation
automation purpose. These analogue inputs shall be generated by distinct transducers
to be provided in respective modules. These inputs shall be wired up to respective
terminal blocks.
ANALOGUE INPUTS:
LT System shall have provision of following digital inputs for owner’s substation
automation purpose. These digital inputs shall be made available in the form of
potential free contacts to be provided in respective modules. These potential free
contacts shall be wired up to respective terminal blocks.
FOR
&
LOCAL DATA MONITORING SYSTEM (LDMS)
Page 1 of 33 Rev.3
Model Technical Specification For RTU and LDMS
INDEX
1. GENERAL INFORMATION 4
2. REMOTE TERMINAL UNIT REQUIREMENTS 5
2.1. Redundancy in CPU and Power supply 6
2.2. Communication Interface 6
2.2.1. Master Station Communication Interface 7
2.2.2. Modems (Applicable in case of RTU communicating on PLCC) 7
2.2.1. Portable Configuration & Maintenance terminal Interface 8
2.3. Master Station Communication Protocol 8
2.3.1. Communication Channel Control 9
2.3.2. Exception Reporting 9
2.3.3. Message Security 9
2.3.4. Control Security 9
2.3.5. Data Concentrator Communication Protocol 10
2.4. Communication interface between RTU & MFT/Energy Meters 10
2.5. Communication Protocol between RTU & IEDs 10
2.6. Analog Inputs 11
2.7. Digital Status Inputs 11
2.7.1. Two-State Devices 12
2.7.2. Momentary Change Detection 12
2.7.3. Digital Telemetry 12
2.7.4. RTU Sequence of Events (SOE) Collection 12
2.8. Digital Control Outputs 13
2.8.1. Two-State Control 13
2.8.2. Raise/Lower Pulse Outputs 13
2.8.3. Control Output Relays 14
2.8.4. RTU Control Security and Safety Requirements 14
2.8.5. Control Disable 14
2.8.6. Dummy breaker relay 15
2.9. Analog Outputs 15
2.10. Time Synchronization 15
2.11. Spare Parts 15
Page 2 of 33 Rev.3
Model Technical Specification For RTU and LDMS
Page 3 of 33 Rev.3
Model Technical Specification For RTU and LDMS
1. GENERAL INFORMATION
This document contains the specifications for the Remote Terminal unit (RTU),
Local Data Monitoring System (LDMS) and associated equipment. The Bidder
shall provide the complete RTU and LDMS under the scope of supply.
The dual output type transducers/MFTs/Energy Meters are included in the Control
and Relay panels and Remote Tap Changer Control (RTCC) Panels. One of the
output from these transducers shall be used for wiring to the RTU. Similarly
potential free contacts for status signal from control and relay panels are to be
used for further wiring to RTU. The Bidder shall be responsible for supplying all
hardware, software, installation, cabling and field implementation for RTU and
LDMS as defined in this Specification. The Bidder shall also provide complete
documentation, training and testing to fully support the hardware and software
provided.
Owner may not initially procure all capabilities specified in this document for RTU.
Regardless of the RTU configuration purchased, the RTU shall be capable of
providing all functions specified herein with the addition of the necessary hardware
and software modules in the field when required by Owner.
The RTU shall be used for real-time supervision and control of substation/ power
plant through owner’s Control centres.
See Exhibit 1-1 for a block diagram of the RTU its interface.
It is Owner's intent that the Bidder uses as much standard hardware and software
as possible; however, all of the functional requirements of this Specification must
be satisfied. The use of the Bidder's standard hardware and software may cause
the Bidder to conclude that there is a need for additional items not specifically
mentioned in this Specification. The Bidder shall supply all such items and provide
a complete RTU and LDMS design that meets all of the Owner's functional
requirements defined in this Specification.
Page 4 of 33 Rev.3
Model Technical Specification For RTU and LDMS
Exhibit 1.1
Remote operation Back
Printer IEC 60870-5- up
IEC 60870-5- 101/104 RLDC
101/104
P P I/ I/ I/ I/ I/ I/ I/ I/ C
P
C
P
Maintenanace
S S O O O O O O O O U
/
U
/
port
C C
O O
C C C C C C C C C C M
M
M
M
A A A A A A A A A A C C
R R R R R R R R R R A
R
A
R
D D D D D D D D D D D D
IEC 60870-5-
101/104
IEC 60870-5-104
Main
RLDC
LDMS
Printer
* Note:- No. of Ports as required.
Page 5 of 33 Rev.3
Model Technical Specification For RTU and LDMS
The RTU shall be provided with redundant CPUs and Power Supply Unit so that
the RTU can communicate with all masters even when one of the redundant units
fails. A failover process shall cause the assignment of all the functions of the failed
unit to the healthy unit. The failover between the two redundant units shall be
transparent and shall not require any manual intervention.
The failover process of the Power Supply Units shall not cause any interruption in
the functioning of the RTU.
The failover of process of the CPU shall be completed within 30 seconds of the
failure of the primary CPU. All the functions in the RTU shall be operational within
30 seconds of the failover operation i.e. one minute from the time of failure
The typical communication ports has been shown in the Exhibit 1.1.
The communication interface to the master stations shall allow scanning and
control of defined points within the RTU independently for each master station.
The RTU shall respond to independent scans and commands from Owner's
master stations, RTU Maintenance and Configuration Terminal and LDMS/RCC.
The RTU shall support the use of a different communication data exchange rate
(bits per second), scanning cycle, and/or communication protocol to each master
station.
Page 6 of 33 Rev.3
Model Technical Specification For RTU and LDMS
Also, each master station's data scan may be different for different data points
within the RTU's database.
All ports shall be accessible to Owner to attach the interface equipment and to
provide access for the maintenance, test and monitoring equipment.
Owner will supply communication channels between the RTU and the SCADA
system master stations. The communication channels are not part of RTU and
LDMS/RCC scope of supply. The communication channels provided will consist
of power line carrier, microwave, optical fibre, VSAT and cable communication
using modems specified below.
The Bidder shall supply two (2) number modems along with each RTU (at RTU
end) for communicating with the master station. The corresponding two number
modems shall also be supplied by the Bidder for remote end. The remote end
modems shall be of standalone type (with power supply unit ) and can be located
either at the Control centre or at wideband communication node. A single modem
combining all of the characteristics defined below is preferred such that changing
the communication data rate shall only require reconfiguration of the RTU modem.
The modems shall not require manual equalization and shall include self-test
features such as manual mark/space keying, analog loop-back, and digital loop-
back. The modems shall provide for convenient adjustment of output level and
receive sensitivity. The configuration of tones and speed shall be programmable
and maintained in non-volatile memory in the modem.
(a) Use CCITT Standards including V.24, V.28, V.52, and V.54.
(b) Communicate data rates of 300, 600 and 1200 bits per second.
(c) Use CCITT V.23, R35, R.37, R.38a, and R.38b standard tones for the
selected RTU data rate.
Page 7 of 33 Rev.3
Model Technical Specification For RTU and LDMS
(i) PLCC modem shall use bandwidth upto 4khz and shall accommodate
multiple data channels over and above voice channels. It shall conform to CCITT-
38 standards.
The interface shall provide easy access to allow Owner to use the maintenance
terminal at the RTU installed in the field. The contractor shall provide the RTU
configuration and maintenance software and its associated license for using it
on window based PCs. The software shall be provided on CD /electronic media.
The desktop/laptop PC at control centre end , shall be used for RTU configuration
and maintenance purpose. The RTU configuration and maintenance software
shall include the following features:
RTU shall be provided with IEC 60870-5-101 as well as IEC 60870-5-104 protocol
a communication protocol for communicating with Owner's master stations The
communication protocol shall support all the requirements of this standard. The
communication protocol shall be non-proprietary and the Bidder shall provide
complete description and documentation of the protocol to Owner. The
interoperatibility profile for RTU as implemented at RLDC master is given at
Appendix-C of this document. The bidder’s scope shall include implementation of
RTU protocol exactly in-line with the protocol implemented for RLDC SCADA
system and integration of this RTU communication port with RLDC. The Bidder
has to define RTU database as per the requirements of RLDC. Necessary
information in this regard shall be provided by Owner during detailed engineering.
The communication interface to the master station(s) shall allow scanning and
control of defined points within the RTU independently for each master station
using a logical database in the RTU. It shall be possible to pick points from the
RTU database randomly and assign it for reporting to a Master station. Further,
the RTU shall support the use of a different communication data exchange rate
(bits per second), scanning cycle, and/or communication protocol to each master
station.
Page 8 of 33 Rev.3
Model Technical Specification For RTU and LDMS
The RTU communication protocol shall report status changes by exception. The
communication protocol shall also support an integrity scan of all status data by
master stations regardless of the lack of any change data.
Each RTU communication message shall include an error code, the use of which
shall result in a very low probability of an erroneous message being accepted as
valid. The error code shall be determined and appended to the message for all
messages transmitted by the RTU and verified by the RTU for all messages
addressed and received by the RTU. Cyclic error detection codes such as CRC
are required.
High data integrity and consistency is required of the RTU protocols. The
protocols used shall provide an adequately low Residual Error Rate (RER),
depending on the Bit Error Rate (BER) of the line in use. The minimum required
RER is as specified for the IEC 870-5-101 protocol with the T-101 profile. This
requires the following integrity:
BER RER
10-5 10-14
-4
10 10-10
-3
10 10-6
The implemented protocol shall ensure satisfactory performance at Bit Error Rate of
1x10 -4.
RTU shall operate in remote control mode i.e. Supervisory Control shall be
exercised through one of the master station and the remaining Master Station
shall be used for display of information only. The operation of control outputs shall
use a true select-check-before-execute command sequence between the RTU
and the Master Station. The sequence shall include, as a minimum, the following
functional capabilities:
Page 9 of 33 Rev.3
Model Technical Specification For RTU and LDMS
The RTU shall initialize its control logic, reassemble the control
selection message received , and transmit the reassembled
message to the Master Station. The information in the
message sent to the Master Station shall be generated by the
RTU point-selection logic indicating that the point and control
function have been selected. It shall not be a simple repeat of
the Master Station message transmission.
The Master Station will verify the returned message with the
message sent and, if valid, shall issue an execute control
message to the RTU.
The RTU shall only operate the control point selected after the
check-before-execute sequence above has been performed
without error or interruption by any other messages. The RTU
shall reset its control logic upon any error in the sequence or if
the execute message is not received within a set time (user
adjustable from 2 - 20 seconds) after the command message
is received at the RTU.
The RTU shall act as a IEC 60870-5-104 protocol master and collect data and
also allow control on the existing RTUs on IEC 60870-5-101 protocol (if provided
by the Employer) and communicate it to the SCADA system at Master control
centre.
The RTU shall acquire data from the MFTs / Energy meters using the MODBUS
protocol. The MFTs / energy meters will act as slave to the RTU. The RTU shall
have the ability of issuing retry scan to acquire data from the MFTs / Energy
Meters in case of communication failure between RTU and MFTs/energy meters.
The RTU shall use the IEC 61850 protocol for communication with IEDs over Sub-
station LAN. The RTU shall act as a Client and collect data from the IEDs.
Page 10 of 33 Rev.3
Model Technical Specification For RTU and LDMS
The RTU shall store data acquired from the MFTs & IEDs in its database and do
processing like change detection/deadband processing on the data for optimizing
its transmission to the Master station (SCADA Control Centre). The processing
shall include necessary mapping of information to the protocol requirement for
communication with Control Center.
The RTU shall accommodate analog current inputs which are isolated, uni-polar
or bipolar, 2-wire ungrounded differential signals with full resolution as follows:
(a) +4 to +20 mA
(b) 0 to +10 mA
Each input shall have surge protection and filtering to provide protection against
voltage spikes and residual current at 50 Hz, 0.1 ma (peak-to-peak). Overload of
up to 50% of the input shall not sustain any failures to the input.
The RTU shall make all appropriate signal level conversion and conditioning to
allow full utilization of analog inputs and meaningful reasonability checking.
Including signal conditioning components, the input impedance shall not be
greater than 250Ω. Input scaling shall allow for 20% over range.
The digital status input interface shall be capable of accepting isolated wet or dry
contact status inputs. The Bidder shall supply necessary sensing voltage, current
limiting, optical isolation, and debounce filtering independently for each digital
status input. The Bidder sensing voltage shall not exceed 48 Vdc. The sensing
voltage source shall be isolated from that of the RTU logic power such that any
noise or a short circuit across the sensing supply's output terminals would not
disrupt the RTU operation other than the shorted digital status input.
The RTU shall store all status changes detected for retrieval by the master
stations. For communication delays or short-term failure of communications with a
master station, the RTU shall store a minimum of 300 status change events The
RTU shall report any overflow of this status change buffer to the master stations.
Page 11 of 33 Rev.3
Model Technical Specification For RTU and LDMS
Two-state status input points with momentary change detection shall be used by
Owner for points where multiple operations (changes of state) can occur between
RTU scans (e.g., breakers with reclosing devices that operate faster than the scan
rate). The RTU shall capture and maintain all of the momentary changes, up to 4
per MCD digital status point. The MCD status input points shall be set to capture
operations of greater than 20 ms duration. Operation of less than 20 ms shall be
considered no change (contact bounce). The capture duration shall be adjustable
between 4 and 25 ms in increments of 1 ms.
Digital telemetry input points shall be provided for sixteen-bit inputs from Owner
telemetry contacts. The digital telemetry may use BCD (4-bit decimal characters
without sign) and/or binary (16 bit) codes.
The RTU shall collect digital status input data and time-of-operation from fast-
acting power system devices. The RTU shall maintain a clock and shall time-
stamp the data with a time resolution of one millisecond. The time resolution will
enable Owner's operating and engineering personnel to determine the sequential
operation device state changes throughout the power system.
Any digital status input data point in the RTU shall be assignable by Owner as an
SOE point. The SOE buffer shall be sized for at least 1000 events.
Page 12 of 33 Rev.3
Model Technical Specification For RTU and LDMS
Each time a SOE status indication point changes state, the RTU shall time-tag the
change and store the change (open, close) and the time-tag of the event in SOE
buffers within the RTU. Separate and independent SOE data storage buffers shall
be provided in the RTU for each master station. The RTU shall transfer all Status
points with time tag to master station by exception and within resolution of 1 ms.
When requested from a SCADA system master station, the RTU shall transmit the
SOE data stored in its buffer corresponding to that master station. An
acknowledgement of receipt by the master station shall be made prior to the
deletion of any data in the RTU SOE buffer.
The RTU shall provide the capability for a master station to select and change the
state of digital output points. Device control will be used by Owner to control
power system devices including:
The RTU shall have the capability for control outputs as described in the following
Sub-sections
A pair of outputs shall be supplied for each two-state (open/close) control output
point that drive control relays. One output shall be supplied for open, the other for
close. Upon command from a master station using the check-before-execute
sequence, the appropriate control output shall be operated for a preset
(momentary) time period. The operation period shall be adjustable for each point
from 0.1 to 2 seconds.
The RTU shall provide the capability to output Automatic Generation Control
signals to generation equipment upon command from a SCADA system. The
raise/lower output controls will also be used for transformer tap position settings.
A pair of outputs shall be supplied for each (raise/lower) control output point that
drive control relays. One output shall be supplied for raise, the other for lower.
When commanded from the master station, the appropriate raise or lower output
shall be operated for the selected time interval. The closure time interval for
raise/lower pulse output points shall be specified in the operate command from the
Page 13 of 33 Rev.3
Model Technical Specification For RTU and LDMS
master station. The raise/lower output for each point shall operate over a range of
0.1 to 4 seconds in a minimum of eight equal increments.
Control output interposing relays shall be supplied by the Bidder for each control
output described above. Each control relay shall consist of three isolated contacts.
The output contacts shall be rated 10 amps at 220 Vdc, and shall provide arc
suppression to permit interruptions of an inductive load. Relay coils shall be
shunted with diodes to suppress inductive transients associated with energizing
and de-energizing of the relay coils. The relays shall conform to the IEC 255-1-00
and IEC 255-5 requirements.
The RTU shall include the following security and safety features as a minimum:
(b) No more than one control point shall be selected at any given time. A
detection and lockout method shall be provided that prevents a control operation if
more than one control point has been selected.
(c) The control selection shall be automatically cancelled if after receiving the
"control selection" message, the "operate" command is not received within the set
time period.
(d) No false output shall result during power up or power down. No false output
shall result from inadvertent connections to a circuit card.
(e) All connections with a voltage of fifty (50) volts or more shall have a
protective cover.
A manual Local/Remote switch shall be provided for each RTU to disable all
control output interposing relays by breaking the power supply connection to the
control output interposing relays. When in the "Local" position, the Local/Remote
switch shall allow testing of the control outputs without activating the interposing
control relays.
A status input indication shall be provided for the Local/Remote switch to allow the
SCADA system to monitor the position of the switch.
Page 14 of 33 Rev.3
Model Technical Specification For RTU and LDMS
The Bidder shall provide a latching relay to be used to simulate and test
supervisory control from the RTU. The simulation relay shall accept the control
signals to open and close from the RTU and shall provide the correct indication
response through a single contact indication input point.
The RTU shall be capable of driving Analog outputs as setpoint control for AGC
(future implementation) or other setpoint devices. The analog outputs shall have
an accuracy of 99.8% of full scale at an ambient temperature of 25 deg. C. Mean
accuracy shall drift no more than 0.01% per deg. C over a temperature range of -5
to +50 deg. C. The Digital-to analog converter shall have a minimum resolution of
2048 counts (sign plus 11 data bits).
The RTU shall accommodate analog outputs which are isolated, unipolar or bipo-
lar, 2-wire ungrounded differential signals with full resolution as follows:
The RTU shall maintain real-time clock and shall have an internal RTU time base
with a stability of 1 ppm i.e. 3.6 milliseconds per hour or better. The RTU shall
maintain the real-time clock information even when the auxiliary power to the RTU
is switched OFF.
The accuracy of the internal clock for shall be maintained by protocol messages
from the master station. The RTU time will be set from time synchronization
messages received from master station at every 10 minutes when using the IEC
60870-5-101 communication protocol over dedicated lines.
The RTU shall be provided with suitable hardware and software for accepting time
synchronisation from a GPS using IRIG –B/ASCII time messages/1 pps signals
also. This shall be preferred means of time synchronisation wherever the RTU can
not be directly synchronised from a master stations (e.g. reporting through Data
concentrator, reporting on TCP/IP connection etc.). Any hardware required for
multiplication of the ports of the GPS shall also be supplied by the Contractor.
Page 15 of 33 Rev.3
Model Technical Specification For RTU and LDMS
The Bidder shall provide spare parts for the RTU supplied. The minimum essen-
tial spare parts to be provided are defined in the Annexure B
The RTU shall accept power from the DC system with the following character-
istics:
The Bidder shall supply any hardware required to convert RTU input voltage to the
required internal voltages for the RTU hardware. The RTU shall operate with
grounded input power from Owner. The RTU shall not place a ground on the input
power.
Each RTU shall have the capability of automatic start-up and initialisation following
restoration of power after an outage without need of master station intervention.
All restarts shall be reported to the connected master stations.
Secondary power shall be provided to the RTU at 230 Vac, 50 Hz, single-phase
for non-critical auxiliary equipment including heaters, internal lighting, and internal
maintenance outlets.
Over voltage and under voltage protection shall be provided to the input and
output of the power supply in addition to output over current protection to
safeguard the RTU internal logic from being damaged as a result of a component
failure in the power supply and to prevent the RTU internal logic from becoming
unstable and causing mal-operation as a result of voltage fluctuations.
The RTU shall have a status point which shall be set if the power to the RTU's has
been cycled (off-on) for any reason (including maintenance). The master station
shall reset the power fail status point.
The Bidder shall provide simplex type panel for the RTU . The constructional
features of the panel shall be similar to the construction features defined of
Control and Relay Panels specifications.
Page 16 of 33 Rev.3
Model Technical Specification For RTU and LDMS
2.14. Interconnections
The bidder shall supply, install, terminate at both ends, test and commission all
interconnection cables (power, control and signal cables) as follows:
All power and control cables shall be as per owners technical specifications for the
same. The signals cables for communication, I/O points shall be shielded type to
provide suitable protection against noise and electromagnetic interference. All
the cables shall be suitably sized to meet the functional requirements.
Terminal blocks shall be screw-type/ stud type/ cage clamp type/ self
stripping/spring type having provision for disconnection(isolation), with full-depth
insulating barriers made from moulded self-extinguishing material. Rust-proofing
of metallic components shall be provided by means of the metal used or a suitable
coating. Terminal blocks shall be appropriately sized and rated for the electrical
capacity of the circuit and wire used.
Each assembly (to the level of printed circuit cards) shall be clearly marked with
the manufacturer's part number, serial number, and the revision level of the
component. Changes to assemblies shall be indicated by an unambiguous change
to the marked revision level.
All electronic parts (such as capacitors, resistors, and integrated circuits) shall be
marked either with the characteristics of the part or with an industry standard part
number. Where custom parts are provided (such as read-only memories), the part
shall be marked such as to specifically identify the part when similar parts may
exist.
Page 17 of 33 Rev.3
Model Technical Specification For RTU and LDMS
All printed circuit card cages and all slots within the cages shall be clearly labelled.
Printed-circuit cards shall be keyed for proper insertion. It is desirable that printed-
circuit cards be keyed to prevent insertion into incorrect locations.
The audible noise generated by the RTU equipment shall not exceed 50 dbA one
meter from the enclosure.
2.20. Availability
The RTU will perform data acquisition and control of important equipment
necessary for the operation of Owner's power system. Any failure of an RTU to
perform its functions will adversely affect power system operations. An availability
of 99.9% is required exclusive of communication channel availability. An RTU
shall be considered unavailable when:
The RTU shall be supplied for the sizing as per Annexure A. The RTU delivered
shall have further capability to add additional I/O modules to expand the overall
point count of the RTU by a minimum of fifty percent (50%) of the actual RTU
count as defined in Annexure A. Expansion shall be accomplished in the field by
Owner by only adding additional distributed input/output modules within the main
unit.
2.22. Maintainability
Page 18 of 33 Rev.3
Model Technical Specification For RTU and LDMS
The RTU design shall facilitate isolation and correction of all failures. The following
features which promote rapid problem isolation and replacement of failed
components shall be provided:
(b) On-line error detection capabilities within the RTU and detailed
reporting to the connected master stations of detected errors
Page 19 of 33 Rev.3
Model Technical Specification For RTU and LDMS
The LDMS shall be used for local data acquisition, monitoring and control of
substation parameters through RTU.
The scope of LDMS shall include installation and integration of LDMS software on
a Personal computer. The bidder has the option to use personal computer and
printer being supplied as part of C & R panel specification for disturbance
recorder/event logger for LDMS purpose as well. However if bidder feels that
Disturbance/event logger PC and printer are not adequate to meet LDMS
requirement, then separate PC and/or printer shall be provided for LDMS at no
additional cost to owner.
The LDMS shall be a mini SCADA system providing MMI capability for use in the
sub-station control room building. The LDMS software shall include following
functions:
(i) data acquisition for analog, digital and pulse accumulator type data
(ii) data processing – Conversion to engineering units , limit monitoring,
data validity test, calculated data
(iii) Calculated data (such as maximum, minimum, average values with
associated time-stamping etc.) of all the station parameters.
(iv) Time Synchronization
(v) Sequence of Events Processing
(vi) Supervisory control
(vii) Alarm, tagging, trending, quality codes etc.
(viii) Single Line Diagrams, Trends, daily, weekly, monthly reports etc. shall
be prepared by the bidder and integrated on LDMS system. The
LDMS shall also have capability to generate additional displays,
single line diagrams, reports , and trends.
The LDMS shall store all real-time telemetered & calculated data every 5 minutes
(adjustable to 15,30,45,60 minutes). The software and hardware shall be sized for
storage of all above data at every 5 minutes for at least six months duration. All
alarms, events, SOE etc. shall also be stored on regular basis. It shall be possible
to define daily, weekly, monthly Substation reports on LDMS. It shall be possible to
generate reports highlighting the maximum, minimum, average with associated
time-stamping etc. of all the station parameters. The historical data stored on the
storage medium shall be in standard format and necessary tools for its conversion
to standard spreadsheet programs (Calc, Excel) shall be provided.
The LDMS shall update analog data from RTU every ten seconds (programmable)
and status data by exception. The SOE status data shall be recoded with
resolution of 1 ms timestamp.
Page 20 of 33 Rev.3
Model Technical Specification For RTU and LDMS
The software provided to support the functions of the RTU/LDMS shall meet the
characteristics described in this Sub-section. The term "software" is used
throughout this Specification to mean either software or software implemented in
firmware.
The software and the database shall be sized to accommodate growth within the
sizing parameters defined for the RTU without requiring software or database
regeneration. The design of the software and the database shall not restrict future
expansion beyond the sizing parameters. Expansion beyond the original design
parameters may require software or database regeneration.
At the time the RTU is accepted, all software delivered must be up to date and in
final form, including all standard software changes and field changes initiated by
the Bidder or the sub-contractor prior to acceptance. The software documentation
must reflect these changes.
The Bidder shall use a non-proprietary operating system capable of managing the
distributed applications of the RTU. If a proprietary operating system is offered
then Bidder shall provide the corresponding source code. The operating system
shall support multi-tasking and multi-programming. The minimum real-time facili-
ties to be provided shall include process, job, database, and memory manage-
ment, process synchronizing, message services for communication between jobs,
and device and interrupt handling. Industry Standard operating system shall be
provided for LDMS.
Software shall provide automatic restart of the RTU upon power restoration,
memory parity errors, hardware failures, and upon manual request. The software
shall initialize the RTU and begin execution of the RTU functions without
intervention by master station. All restarts shall be reported to the connected
master stations.
Page 21 of 33 Rev.3
Model Technical Specification For RTU and LDMS
The Bidder shall supply a database compiler which will enable to configure and
document each RTU's database. A compiler shall be provided to completely
generate or modify the database of the RTU. The database compiler shall provide
error detection services and shall produce a printed listing of the input data and
the resulting RTU configuration. It shall be possible to maintain the RTU database
locally and from a master station.
RTU shall have diagnostic software which monitors and individually test each of
the modules of RTU. The diagnostics shall provide comprehensive user
interaction and printout capabilities.
Page 22 of 33 Rev.3
Model Technical Specification For RTU and LDMS
All materials, hardware, and software to be furnished and all work to be performed
under this Specification shall be subject to inspections and tests. No equipment
shall be shipped until all required inspections and tests have been made,
demonstrating that the equipment conforms to the Specification and that the
hardware and software have been approved for shipment by Owner
5.1 Inspection
Representatives of Owner shall have free entry into the shops of the manufac-
turer at any time while design, fabrication, or testing of the equipment is taking
place and into any mill, shop, or factory where the hardware or software described
in this specification is being produced.
The Bidder shall provide to Owner's representatives, free of cost, all reasonable
facilities, equipment, and documentation necessary to satisfy Owner's represen-
tatives that the hardware is being fabricated in accordance with the Specification.
The inspection rights described above shall apply to the facilities of the Bidder or
the Bidder's sub-Bidder where the hardware is being manufactured. The inspec-
tion rights shall not apply to the facilities of sub-Bidders supplying unit components
to the manufacturer. Such items will be inspected and tested by Owner's repre-
sentatives at the manufacturing site.
Page 23 of 33 Rev.3
Model Technical Specification For RTU and LDMS
The Bidder shall submit the test procedures for approval twelve weeks prior to the
start of factory tests. Fully approved test procedures shall be submitted to Owner
at least four weeks prior to the commencement of the tests. Owner will approve
test procedures if they are inclusive, thoroughly testing each of the equipment.
The Bidder shall use IEC standards as a guide in preparing the test procedures.
The test procedures shall include the following:
(a) The test schedule, including provision for eight hours of unstructured
tests to be performed by Owner
(f) The test setup, equipment, and conditions for each part of the test
(l) A procedure for handling the variances that are identified during
testing.
The Bidder shall maintain a complete record of the results of all tests. This record
shall be keyed to the steps enumerated in the previously approved test proce-
dures. The record shall include the following items:
Page 24 of 33 Rev.3
Model Technical Specification For RTU and LDMS
A copy of the test records shall be delivered to Owner at the conclusion of the
tests.
The RTU, and cabling elements of the RTU procurement shall be tested in
two parts i.e. type test and routine test as described below
A minimum of one of each major complete integrated units shall be fully tested to
assure full compliance with the functional and technical requirements of the Speci-
fication. The type test reports for the RTU shall be submitted by the bidder which
shall include the tests listed in Table-1 & Table -2 below.
Test
DESCRIPTION OF THE TEST
Nos.
EMI/EMC IMMUNITY TESTS FOR RTU
1. Surge Immunity Test as per IEC 60870-2-1
2. Electrical Fast Transient Burst Test as per IEC-60870-2-1
3. Damped Oscillatory Wave Test as per IEC 60870-2-1
4. Electrostatic Discharge test as per IEC 60870-2-1
5. Radiated Electromagnetic Field Test as per IEC 60870-2-1
6. Damped Oscillatory magnetic Field Test as per IEC-60870-2-1
7. Power Frequency magnetic Field Test as per IEC-60870-2-1
INSULATION TEST FOR RTU
8. Power frequency voltage withstand Test as per IEC 60870-2-1
9. 1.2/50 µs Impulse voltage withstand Test as per IEC 60870-2-1
10. Insulation resistance test
ENVIRONMENTAL TEST FOR RTU
11. Dry heat test as per IEC60068-2-2
12. Damp heat test as per IEC60068-2-3
Page 25 of 33 Rev.3
Model Technical Specification For RTU and LDMS
Note: -
EUT - Equipment Under Test
CM - Common Mode; DM - Differential mode
I/O points do not include communication ports
Passing Criteria
0 - no failure: normal performance within the specified limits
A: minor failure : temporary degradation or loss of function or performance which is
self-recoverable, however issuance of control output command is not allowed.
Page 26 of 33 Rev.3
Model Technical Specification For RTU and LDMS
( 2) Routine testing :
(c) Test operation and accuracy of all RTU analogue inputs over entire
range.
The Bidder shall be responsible for providing field installation and testing. All
hardware will be installed, aligned, and adjusted, interfaces to all field inputs and
outputs established, operation verified and all test readings recorded. Upon
completion, a field performance test shall be performed to exercise all functions of
the RTU and duplicate selected routine tests to the extent possible. The SCADA
database and displays at regional SCADA master station shall be developed by
Owner, however for this purpose all necessary information shall be provided by
the bidder. This testing will include, but not be limited to, the following tests:
RTU initialization.
Page 27 of 33 Rev.3
Model Technical Specification For RTU and LDMS
Test time synchronization and accuracy of the RTU from the master
station.
Page 28 of 33 Rev.3
Model Technical Specification For RTU and LDMS
The Bidder shall provide training and support services to create Owner's in-house
maintenance and support capabilities for the hardware and software. The training
program shall be comprehensive and provide for interdisciplinary training
hardware and software. The required training of Owner's personnel shall be
conducted by the Bidder in English.
The Bidder shall provide RTU and LDMS hardware, software, and operation &
maintenance training. The courses shall familiarize Owner's course participants
with RTU installation, card/circuit board level troubleshooting and repair
procedures, and the recommended preventive maintenance procedures for the
RTU equipment. Courses shall include use of the RTU configuration and
maintenance terminal and shall demonstrate all facets of its operation. Courses
shall also include hands-on trouble-shooting experience with the RTU supplied by
the Bidder and shall cover any special equipment required for maintenance.
Actual RTU to be supplied under this procurement shall be used for training.
The Bidder shall also provide RTU software training in the following areas:
The Bidder shall also provide LDMS software training in the following areas:
6.1.1 Attendance
The training schedule shall coincide with the delivery of the RTU to Owner. The
training course shall be a optimum mix of class-room and laboratory training, the
duration of training shall be 5 days.
The RTU maintenance courses shall be given at the site/ Bidder's facility in India,
or optionally, at Owner's facility. Adequate training manuals shall be provided to
the trainees.
Page 29 of 33 Rev.3
Model Technical Specification For RTU and LDMS
7.0 DOCUMENTATION
The Bidder shall submit hardware and software documentation for RTUs and
LDMS to Owner for review and approval. After approval four set of all the
documents shall be submitted as final documentation. Any changes observed
during field implementation shall be incorporated in the as-build drawing and four
sets of same shall be submitted to owner. In addition to paper copies all the
documents shall also be provided on electronic media in two copies.
7. 1 Hardware Documentation
The Bidder shall provide documentation for all hardware supplied to Owner.
Documentation describing the circuitry, operation of the circuitry, and
troubleshooting and maintenance procedures shall indicate the revision level of
the hardware to which the documentation applies. Generic manuals are not
acceptable unless they clearly show what is supplied and what is not supplied.
This documentation shall satisfy the following requirements:
The Bidder shall supply documentation for all software provided with the RTU and
LDMS. This documentation shall include the following documentation as a
minimum:
Software Inventory.
Functional Design specification of RTU software and LDMS software.
Software maintenance manuals for RTU configuration and maintenance
software, LDMS software, RTU softwares.
RTU and LDMS database documents.
Implemented Protocol detailed document.
Page 30 of 33 Rev.3
Model Technical Specification For RTU and LDMS
Annexure A
Note:
1. Cabling with control and relay panels shall be carried out for current bays as per
single line diagram of the substation, however all analog and digital points shall
be wired to terminal blocks in the RTU for external interface.
Page 31 of 33 Rev.3
Model Technical Specification For RTU and LDMS
Annexure B
Page 32 of 33 Rev.3
Model Technical Specification For RTU and LDMS
Annexure C
Page 33 of 33 Rev.3
TECHNICAL SPECIFICATION
SECTION-GENERAL TECHNICAL REQUIREMENTS
Followings are the major changes made in the Technical Specification, Section-GTR (Rev.- 14)
NOTES:-
1. The above is the list of major changes w.r.t. the previous revision (Rev.-13). However, Bidders
are advised to read the entire section-GTR for other changes and quote accordingly.
SECTION- GENERAL TECHNICAL REQUIRMENT (GTR)
INDEX
1.0 FOREWORD
The provisions under this section are intended to supplement requirements for the
materials, equipments and services covered under other sections of tender documents
and are not exclusive.
2.0 GENERAL REQUIREMENT
2.1 The contractor shall furnish catalogues, engineering data, technical information, design
documents, drawings etc., fully in conformity with the technical specification during
detailed engineering.
2.2 It is recognised that the Contractor may have standardised on the use of certain
components, materials, processes or procedures different from those specified herein.
Alternate proposals offering similar equipment based on the manufacturer’s standard
practice will also be considered provided such proposals meet the specified designs,
standard and performance requirements and are acceptable to Employer.
2.3 Wherever a material or article is specified or defined by the name of a particular brand,
Manufacturer or Vendor, the specific name mentioned shall be understood as
establishing type, function and quality and not as limiting competition.
2.4 Equipment furnished shall be complete in every respect with all mountings, fittings,
fixtures and standard accessories normally provided with such equipment and/or
needed for erection, completion and safe operation of the equipment as required by
applicable codes though they may not have been specifically detailed in the Technical
Specifications unless included in the list of exclusions. Materials and components
which are minor in nature and incidental to the requirement but not specifically stated
in the specification and bid price schedule, which are necessary for commissioning and
satisfactory operation of the switchyard/ substation unless specifically excluded shall
be deemed to be included in the scope of the specification and shall be supplied
without any extra cost. All similar standard components/parts of similar standard
equipment provided, shall be inter-changeable with one another.
2.5 The Contractor shall also be responsible for the overall co-ordination with internal
/external agencies; Supplier of Employer’s supplied equipments, project management,
training of Employer’s manpower, loading, unloading, handling, insurance, moving to
final destination for successful erection, testing and commissioning of the substation
/switchyard.
2.6 The bidder shall be responsible for safety of human and equipment during the working.
It will be the responsibility of the Contractor to co-ordinate and obtain Electrical
Inspector's clearance before commissioning. Any additional items, modification due to
observation of such statutory authorities shall be provided by the Contractor at no
extra cost to the Employer.
3.0 STANDARDS
3.1 The works covered by the specification shall be designed, engineered, manufactured,
built, tested and commissioned in accordance with the Acts, Rules, Laws and
Regulations of India.
3.2 The equipment to be furnished under this specification shall conform to latest issue
with all amendments (as on the originally scheduled date of bid opening) of standard
specified under Annexure-C of this section, unless specifically mentioned in the
specification.
3.3 The Bidder shall note that standards mentioned in the specification are not mutually
exclusive or complete in themselves, but intended to compliment each other.
____________________________________________________________________________
Technical Specification: GTR Page 1 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
3.4 The Contractor shall also note that list of standards presented in this specification is
not complete. Whenever necessary the list of standards shall be considered in
conjunction with specific IS/IEC.
3.5 When the specific requirements stipulated in the specifications exceed or differ than
those required by the applicable standards, the stipulation of the specification shall
take precedence.
3.6 Other internationally accepted standards which ensure equivalent or better
performance than that specified in the standards specified under Annexure-C/
individual sections for various equipments shall also, be accepted, however the salient
points of difference shall be clearly brought out during detailed engineering along with
English language version of such standard. The equipment conforming to standards
other than specified under Annexure-C/individual sections for various equipments
shall be subject to Employer’s approval.
4.1 The 800kV and 420kV system is being designed to limit the switching surge over
voltage of 1.9 p.u. and 2.5 p.u., respectively and the power frequency over voltage of 1.4
p.u. and 1.5 p.u., respectively. In case of the 420kV system, the initial value of the
temporary overvoltages could be 2.0 p.u. for 1-2 cycles. The equipment furnished
under this specification shall perform all its functions and operate satisfactorily
without showing undue strain, restrike etc under such over voltage conditions.
4.2 All equipments shall also perform satisfactorily under various other electrical,
electromechanical and meteorological conditions of the site of installation.
4.3 All equipment shall be able to withstand all external and internal mechanical, thermal
and electromechanical forces due to various factors like wind load, temperature
variation, ice & snow, (wherever applicable) short circuit etc for the equipment.
4.4 The bidder shall design terminal connectors of the equipment taking into account
various forces that are required to withstand.
4.5 The equipment shall also comply to the following:
a) To facilitate erection of equipment, all items to be assembled at site shall be
“match marked”.
b) All piping, if any between equipment control cabinet/operating mechanism to
marshalling box of the equipment, shall bear proper identification to facilitate
the connection at site.
4.6 System Parameter
____________________________________________________________________________
Technical Specification: GTR Page 2 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
____________________________________________________________________________
Technical Specification: GTR Page 3 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
8. Min. clearances
i. Phase to phase 1300 mm 750 mm 320 mm 280 mm
Notes:
1. The above parameters are applicable for installations up to an altitude of 1000m above
mean sea level. For altitude exceeding 1000m, necessary altitude correction factor shall
be applicable as per relevant IEC.
2. The insulation and RIV levels of the equipments shall be as per values given in the
Technical Specification of respective equipment.
3. Corona and radio interference voltage test and seismic withstand test procedures for
equipments shall be in line with the procedure given at Annexure-A and Annexure-B
respectively.
____________________________________________________________________________
Technical Specification: GTR Page 4 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
5.8 The list of major drawings/documents to be approved to qualify for second advance as
per Section SCC, shall be as per Annexure–D.
6.0 MATERIAL/ WORKMANSHIP
6.1 General Requirement
6.1.1 Where the specification does not contain references to workmanship, equipment,
materials and components of the covered equipment, it is essential that the same must
be new, of highest grade of the best quality of their kind, conforming to best
engineering practice and suitable for the purpose for which they are intended.
6.1.2 In case where the equipment, materials or components are indicated in the
specification as “similar” to any special standard, the Employer shall decide upon the
question of similarity. When required by the specification or when required by the
Employer the Contractor shall submit, for approval, all the information concerning the
materials or components to be used in manufacture. Machinery, equipment, materials
and components supplied, installed or used without such approval shall run the risk of
subsequent rejection, it is to be understood that the cost as well as the time delay
associated with the rejection shall be borne by the Contractor.
6.1.3 The design of the Works shall be such that installation, future expansions,
replacements and general maintenance may be undertaken with a minimum of time
and expenses. Each component shall be designed to be consistent with its duty and
suitable factors of safety, subject to mutual agreements. All joints and fastenings shall
be devised, constructed and documented so that the component parts shall be
accurately positioned and restrained to fulfill their required function. In general, screw
threads shall be standard metric threads. The use of other thread forms will only be
permitted when prior approval has been obtained from the Employer.
6.1.4 Whenever possible, all similar part of the Works shall be made to gauge and shall also
be made interchangeable with similar parts. All spare parts shall also be
interchangeable and shall be made of the same materials and workmanship as the
corresponding parts of the Equipment supplied under the Specification. Where
feasible, common component units shall be employed in different pieces of equipment
in order to minimize spare parts stocking requirements. All equipment of the same
type and rating shall be physically and electrically interchangeable.
6.1.5 All materials and equipment shall be installed in strict accordance with the
manufacturer’s recommendation(s). Only first-class work in accordance with the best
modern practices will be accepted. Installation shall be considered as being the
erection of equipment at its permanent location. This, unless otherwise specified, shall
include unpacking, cleaning and lifting into position, grouting, levelling, aligning,
coupling of or bolting down to previously installed equipment bases/foundations,
performing the alignment check and final adjustment prior to initial operation, testing
and commissioning in accordance with the manufacturer’s tolerances, instructions and
the Specification. All factory assembled rotating machinery shall be checked for
alignment and adjustments made as necessary to re-establish the manufacturer’s limits
suitable guards shall be provided for the protection of personnel on all exposed
rotating and / or moving machine parts and shall be designed for easy installation and
removal for maintenance purposes. The spare equipment(s) shall be installed at
designated locations and tested for healthiness.
6.1.6 The Contractor shall apply oil and grease of the proper specification to suit the
machinery, as is necessary for the installation of the equipment. Lubricants used for
installation purposes shall be drained out and the system flushed through where
necessary for applying the lubricant required for operation. The Contractor shall apply
all operational lubricants to the equipment installed by him.
____________________________________________________________________________
Technical Specification: GTR Page 7 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
6.1.7 All oil, grease and other consumables used in the Works/Equipment shall be purchased
in India unless the Contractor has any special requirement for the specific application
of a type of oil or grease not available in India. If such is the case, he shall declare in the
proposal, where such oil or grease is available. He shall help Employer in establishing
equivalent Indian make and Indian Contractor. The same shall be applicable to other
consumables too.
6.2 Provisions For Exposure to Hot and Humid climate
Outdoor equipment supplied under the specification shall be suitable for service and
storage under tropical conditions of high temperature, high humidity, heavy rainfall
and environment favourable to the growth of fungi and mildew. The indoor
equipments located in non-air conditioned areas shall also be of same type.
6.2.1 Space Heaters
6.2.1.1 The heaters shall be suitable for continuous operation at 240V as supply voltage. On-
off switch and fuse shall be provided.
6.2.1.2 One or more adequately rated thermostatically connected heaters shall be supplied to
prevent condensation in any compartment. The heaters shall be installed in the
compartment and electrical connections shall be made sufficiently away from below
the heaters to minimize deterioration of supply wire insulation. The heaters shall be
suitable to maintain the compartment temperature to prevent condensation.
6.2.2 FUNGI STATIC VARNISH
Besides the space heaters, special moisture and fungus resistant varnish shall be
applied on parts which may be subjected or predisposed to the formation of fungi due
to the presence or deposit of nutrient substances. The varnish shall not be applied to
any surface of part where the treatment will interfere with the operation or
performance of the equipment. Such surfaces or parts shall be protected against the
application of the varnish.
6.2.3 Ventilation opening
Wherever ventilation is provided, the compartments shall have ventilation openings
with fine wire mesh of brass to prevent the entry of insects and to reduce to a
minimum the entry of dirt and dust.
6.2.4 Degree of Protection
The enclosures of the Control Cabinets, Junction boxes and Marshalling Boxes, panels
etc. to be installed shall comply with following degree of protection as detailed here
under:
a) Installed out door: IP- 55
b) Installed indoor in air conditioned area: IP-31
c) Installed in covered area: IP-52
d) Installed indoor in non-air conditioned area where possibility of entry of water is
limited: IP-41.
e) For LT Switchgear (AC & DC distribution Boards): IP-52
number together with details of the loading conditions under which the item of
substation in question has been designed to operate, and such diagram plates as may
be required by the Employer. The rating plate of each equipment shall be according to
IEC requirement.
6.3.2 All such nameplates, instruction plates, rating plates of transformers, reactors, CB, CT,
CVT, SA, Isolators, C & R panels and PLCC equipments shall be bilingual with Hindi
inscription first followed by English. Alternatively two separate plates one with Hindi
and the other with English inscriptions may be provided.
6.4 FIRST FILL OF CONSUMABLES, OIL AND LUBRICANTS
All the first fill of consumables such as oils, lubricants, filling compounds, touch up
paints, soldering/brazing material for all copper piping of circuit breakers and
essential chemicals etc. which will be required to put the equipment covered under the
scope of the specifications, into operation, shall be furnished by the Contractor unless
specifically excluded under the exclusions in these specifications and documents.
7.0 DESIGN IMPROVEMENTS / COORDINATION
7.1 The bidder shall offer the equipment meeting the requirement of the technical
specification. However, the Employer or the Contractor may propose changes in the
specification of the equipment or quality thereof and if the contractor & Employer
agree upon any such changes, the specification shall be modified accordingly.
7.2 If any such agreed upon change is such that it affects the price and schedule of
completion, the parties shall agree in writing as to the extent of any change in the price
and/or schedule of completion before the Contractor proceeds with the change.
Following such agreement, the provision thereof, shall be deemed to have been
amended accordingly.
7.3 The Contractor shall be responsible for the selection and design of appropriate
equipments to provide the best co-ordinated performance of the entire system. The
basic design requirements are detailed out in this Specification. The design of various
components, sub-assemblies and assemblies shall be so done that it facilitates easy
field assembly and maintenance.
7.4 The Contractor has to coordinate designs and terminations with the agencies (if any)
who are Consultants/Contractor for the Employer. The names of agencies shall be
intimated to the successful bidders.
7.5 The Contractor will be called upon to attend design co-ordination meetings with the
Engineer, other Contractor’s and the Consultants of the Employer (if any) during the
period of Contract. The Contractor shall attend such meetings at his own cost at
POWERGRID Corporate Centre, Gurgaon (Haryana) or at mutually agreed venue as and
when required and fully cooperate with such persons and agencies involved during
those discussions.
8.0 QUALITY ASSURANCE PROGRAMME
8.1 To ensure that the equipment and services under the scope of this Contract, whether
manufactured or performed within the Contractor’s Works or at his Sub-Contractor’s
premises or at the Employer’s site or at any other place of Work as applicable, are in
accordance with the specifications, the Contractor shall ensure suitable quality
assurance programme to control such activities at all points necessary. A quality
assurance programme of the Contractor shall be in line with ISO requirements & shall
generally cover the following:
a) The organisation structure for the management and implementation of the
proposed quality assurance programme.
____________________________________________________________________________
Technical Specification: GTR Page 9 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
____________________________________________________________________________
Technical Specification: GTR Page 10 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
Items not covered under MQP/ITP/FAT shall be offered for inspection as per
POWERGRID LOA/technical Specifications/POWERGRID approved data sheets/
POWERGRID approved drawings and relevant Indian/International standards.
Inspection Levels: For implementation of projects in a time bound manner and to avoid
any delay in deputation of POWERGRID or its authorized representative, involvement
of POWERGRID for inspection of various items / equipment will be based on the level
below:
Level –I: Contractor to raise all inspection calls and review the report of tests
carried out by the manufacturer, on his own, as per applicable standards/
POWERGRID specification, and submit to concerned POWERGRID
inspection office/Inspection Engineer. CIP/MICC will be issued by
POWERGRID based on review of test reports/certificates of
manufacturers.
____________________________________________________________________________
Technical Specification: GTR Page 11 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
Level – II: Contractor to raise all inspection calls and carry out the inspection on
behalf of POWERGRID on the proposed date of inspection as per
applicable standards/specification. However, in case POWERGRID wishes
to associate itself during inspection, the same would be intimated to
Contractor and CIP/MICC will be issued by POWERGRID. Else, Contractor
would submit their test reports/certificates to POWERGRID. CIP/MICC
will be issued by POWERGRID based on review of test reports/
certificates.
Level - III: Contractor to raise inspection calls for both, stage (as applicable) & final
inspection and carry out the stage inspections (if applicable) on behalf of
POWERGRID on the proposed date of inspection as per applicable
standards/specification. However, in case POWERGRID wishes to
associate itself during stage inspection, the same would be intimated to
Contractor and CIP will be issued by POWERGRID. Else, Contractor would
submit the test reports / certificates of stage inspection after their own
review and CIP will be issued by POWERGRID based on review of test
reports / certificates. Final inspection will be carried out by POWERGRID
and CIP/MICC will be issued by POWERGRID.
Level – IV: Contractor to raise inspection calls for both, stage (as applicable) & final
inspections. POWERGRID will carry out the inspection for both stage &
final inspection as per applicable standards/specification and CIP/MICC
will be issued by POWERGRID.
8.3.2 Contractor shall ensure that to implement the above inspection levels, particularly for
the quality control and inspection at sub-vendor’s works, they would depute sufficient
qualified & experienced manpower in their Quality Control and Inspection department.
Further, to assure quality of construction, Contractor shall have a separate workforce
having appropriate qualification & experience and deploy suitable tools and plant for
maintaining quality requirement during construction in line with applicable Field
Quality Plan (FQP).
8.3.3 The Employer, his duly authorised representative and/or outside inspection agency
acting on behalf of the Employer shall have at all reasonable times access to the
Contractor’s premises or Works and shall have the power at all reasonable times to
ensure that proper Quality Management practices / norms are adhered to, inspect and
examine the materials & workmanship of the Works, to carry out Quality/Surveillance
Audit during manufacture or erection and if part of the Works is being manufactured
or assembled at other premises or works. The Contractor shall obtain for the Employer
and for his duly authorised representative permission to inspect as if the works were
manufactured or assembled on the Contractor’s own premises or works. The
item/equipment, if found unsatisfactory with respect to workmanship or material is
liable to be rejected. The observations for improvements during product/ process
inspection by POWERGRID shall be recorded in Quality Improvement Register
(available & maintained at works) for review & timely compliance of observations.
8.3.4 Contractor shall submit inspection calls over internet through POWERGRID website.
The required vendor code and password to enable raising inspection call will be
furnished to the main Contractor within 30 days of award of contract on submission of
documents by Contractor. After raising the inspection calls, Contractor shall then
proceed as per the message of that particular call which is available on the message
board.
8.3.5 The Employer reserves the right to witness any or all type, acceptance and routine
tests specified for which the Contractor shall give the Employer/Inspector Twenty
one (21) days written notice of any material being ready for testing for each stage of
____________________________________________________________________________
Technical Specification: GTR Page 12 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
reports within Ten (10) days to POWERGRID IE. Failure of the Employer/IE to issue
such a certificate shall not prevent the Contractor from proceeding with the Works.
The completion of these tests or the issue of the certificate shall not bind the Employer
to accept the equipment should, it, on further tests after erection, be found not to
comply with the Contract.
8.3.13 In all cases, where the Contract provides for tests whether at the premises or works
of the Contractor or of any Sub- Contractor, the Contractor, except where otherwise
specified, shall provide free of charge such items as labour, materials, electricity, fuel,
water, stores, apparatus and instruments as may be reasonably demanded by the
Employer/Inspector or his authorised representative to carry out effectively such tests
of the equipment in accordance with the Contract and shall give facilities to the
Employer/Inspection Engineer or to his authorised representative to accomplish
testing.
8.3.14 The inspection and acceptance by Employer and issue of Inspection Certificate thereon
shall in no way limit the liabilities and responsibilities of the Contractor in respect of
the agreed quality assurance programme forming a part of the Contract, or if such
equipment is found to be defective at a later stage.
8.3.15 The Employer will have the right of having at his own expenses any other test(s) of
reasonable nature carried out at Contractor’s premises or at site or in any other place
in addition of aforesaid type and routine tests, to satisfy that the material comply with
the specification.
8.3.16 The Employer reserves the right for getting any additional field tests conducted on the
completely assembled equipment at site to satisfy that material complies with
specifications.
8.3.17 Rework/ Re-engineering, if any, on any item/equipment shall be carried out only after
mutual discussions and in accordance with mutually agreed procedure. Contractor
shall submit Joint Inspection Report of equipments under Re-Work/Re-Engineering
alongwith procedure for the same to POWERGRID for approval, before taking up the
Re-Work/Re-Engineering, failing which POWERGRID reserves the right to reject the
equipment.
8.3.18 Contractor may establish a field test Laboratory to execute Civil Construction testing
requirements at site with the condition that all testing equipment shall be calibrated
from POWERGRID approved accredited Testing laboratories, with calibration
certificates kept available at site and all testing personnel employed in the Field
Testing Laboratories to be qualified and experienced Engineers or testing to be carried
out at POWERGRID approved Third Party Laboratories.
8.3.19 Contractor shall ensure that all possible steps are taken to avoid damages to the
equipment during transport, storage and erection.
8.3.20 Contractor shall implement additional stringent quality checks and preparation during
installation of GIS at site (if applicable) as per POWERGRID approved
guidelines/Technical specifications.
8.3.21 Contractor shall ensure commissioning of all CSDs along with Circuit Breakers
wherever applicable.
8.3.22 For EHV transformers/reactors:
Insulation oil shall be as per POWERGRID Technical specifications and same grade
shall be used for impregnation of the active part & testing at the works of
Transformer/Reactor Manufacturer and as well as for filling the Transformer/Reactors
at site. Contractor to ensure that windings for Transformer/Reactors are made in air-
conditioned environment. Core-coil assembly shall be performed in positive
____________________________________________________________________________
Technical Specification: GTR Page 14 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
8.3.23 The Employer reserves the right to increase or decrease their involvement in
inspections at Contractor’s Works or at his Sub-Contractor’s premises or at the
Employer’s site or at any other place of Work based on performance of
Contractor/sub-Contractor.
9.1 All equipment being supplied shall conform to type tests as per technical specification
and shall be subject to routine tests in accordance with requirements stipulated under
respective sections.
9.2 The reports for all type tests as per technical specification shall be furnished by the
Contractor alongwith equipment / material drawings. However, type test reports of
similar equipments/ material already accepted in POWERGRID shall be applicable for
all projects with similar requirement. The type tests conducted earlier should have
either been conducted in accredited laboratory (accredited based on ISO / IEC Guide
25 / 17025 or EN 45001 by the national accreditation body of the country where
laboratory is located) or witnessed by POWERGRID or representative authorized by
POWERGRID or Utility or representative of accredited test lab.
Unless otherwise specified elsewhere, the type test reports submitted shall be of the
tests conducted within last 10 (ten) years from the date of NOA. In case the test reports
are of the test conducted earlier than 10 (ten) years from the date of NOA, the
contractor shall repeat these test(s) at no extra cost to the Employer.
Further, in the event of any discrepancy in the test reports i.e. any test report not
acceptable due to any design/manufacturing changes or due to non-compliance with
the requirement stipulated in the Technical Specification or any/all type tests not
carried out, same shall be carried out without any additional cost implication to the
Employer.
The Contractor shall intimate the Employer the detailed program about the type tests
atleast two (2) weeks in advance in case of domestic supplies & six (6) weeks in
advance in case of foreign supplies.
9.3 The Employer intends to repeat those type tests which are indicated in the price
schedule and the same shall be payable as per provision of contract. The price of
conducting type tests shall be included in Bid price and break up of these shall be given
in the relevant schedule of Bid Proposal Sheets. These Type test charges would be
considered in bid evaluation. In case Bidder does not indicate charges for any of the
type tests or does not mention the name of any test in the price schedules, it will be
presumed that the particular test has been offered free of charge. Further, in case any
Bidder indicates that he shall not carry out a particular test, his offer shall be
considered incomplete and shall be liable to be rejected. The Employer reserves the
right to waive the repeating of type tests partly or fully and in case of waival, test
charges for the same shall not be payable.
____________________________________________________________________________
Technical Specification: GTR Page 15 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
9.4 The Employer reserves the right to witness any or all the type tests. The Employer
shall bear all expenses for deputation of Employer’s representative(s) for witnessing
the type tests.
9.5 The list of makes of various items, for which Type test reports are not required to
be submitted are specified in Compendium of Vendors (COV).
10.0 TESTS
10.1 Pre-commissioning Tests
On completion of erection of the equipment and before charging, each item of the
equipment shall be thoroughly cleaned and then inspected jointly by the Employer and
the Contractor for correctness and completeness of installation and acceptability for
charging, leading to initial pre-commissioning tests at Site. The list of pre-
commissioning tests to be performed are given in respective chapters and shall be
included in the Contractor’s quality assurance programme.
10.2 Commissioning Tests
10.2.1 The available instrumentation and control equipment will to be used during such tests
and the Employer will calibrate, all such measuring equipment and devices as far as
practicable.
10.2.2 Any special equipment, tools and tackles required for the successful completion of the
Commissioning Tests shall be arranged by the Contractor at his own cost.
10.2.3 The specific tests requirement on equipment have been brought out in the respective
chapters of the technical specification.
10.3.4 PRECOMMISSIONING, COMMISSIONING, TRIAL-RUN & COMPLETION
As soon as the Facilities covered by these specifications are physically completed in all
respects, the Pre commissioning, Commissioning, Trial-run and Completion of the
Facilities, as mentioned below, shall be attained in accordance with the procedure given
in the Conditions of Contract, Vol.-I of the Bidding Documents.
(i) Pre commissioning : As per relevant Sections
(ii) Commissioning : Charging of the Facilities at rated voltage.
‘Guarantee Test(s)’ and/or ‘Functional Guarantees’ are applicable only for Substation
Automation System as specified in Section-‘Substation Automation System.’
10.3. The Contractor shall be responsible for obtaining statutory clearances from the
concerned authorities for commissioning the equipment and the switchyard. However
necessary fee shall be reimbursed by POWERGRID on production of requisite
documents.
____________________________________________________________________________
Technical Specification: GTR Page 16 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
- Adhesion test
- Mass of zinc coating
12.2.6 Galvanised material must be transported properly to ensure that galvanised surfaces
are not damaged during transit. Application of touch-up zinc rich paint at site shall be
allowed with approval of Engineer Incharge.
12.3 PAINTING
12.3.1 All sheet steel work shall be degreased, pickled, phosphated in accordance with the IS-
6005 “Code of practice for phosphating iron and sheet”. All surfaces, which will not be
easily accessible after shop assembly, shall beforehand be treated and protected for the
life of the equipment. The surfaces, which are to be finished painted after installation
or require corrosion protection until installation, shall be shop painted with at least
two coats of primer. Oil, grease, dirt and swaf shall be thoroughly removed by emulsion
cleaning. Rust and scale shall be removed by pickling with dilute acid followed by
washing with running water, rinsing with slightly alkaline hot water and drying.
12.3.2 After phosphating, thorough rinsing shall be carried out with clean water followed by
final rinsing with dilute dichromate solution and oven drying. The phosphate coating
shall be sealed with application of two coats of ready mixed, stoving type zinc
chromate primer. The first coat may be “flash dried” while the second coat shall be
stoved.
12.3.3 After application of the primer, two coats of finishing synthetic enamel paint shall be
applied, each coat followed by stoving. The second finishing coat shall be applied after
inspection of first coat of painting.
12.3.4 The exterior and interior colour of the paint in case of new substations shall preferably
be RAL 7032 for all equipment, marshalling boxes, junction boxes, control cabinets,
panels etc. unless specifically mentioned under respective sections of the equipments.
Glossy white colour inside the equipments /boards /panels/junction boxes is also
acceptable. The exterior colour for panels shall be matching with the existing panels in
case of extension of a substation. Each coat of primer and finishing paint shall be of
slightly different shade to enable inspection of the painting. A small quantity of
finishing paint shall be supplied for minor touching up required at site after
installation of the equipments.
12.3.5 In case the contractor proposes to follow his own standard surface finish and
protection procedures or any other established painting procedures, like electrostatic
painting etc., the procedure shall be submitted during detailed engineering for
Employer’s review & approval.
12.3.6 The colour scheme as given below shall be followed for Fire Protection and Air
Conditioning systems
____________________________________________________________________________
Technical Specification: GTR Page 19 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
for proper operation of circuit breakers, isolators and their operating mechanisms. All
components shall be protected against damage during unloading, transportation,
storage, installation, testing and commissioning. Any equipment damaged due to
negligence or carelessness or otherwise shall be replaced by the Contractor at his own
expense.
13.6 Contractor shall be responsible for examining all the shipment and notify the Employer
immediately of any damage, shortage, discrepancy etc. for the purpose of Employer’s
information only. The Contractor shall submit to the Employer every week a report
detailing all the receipts during the weeks. However, the Contractor shall be solely
responsible for any shortages or damages in transit, handling and/or in storage and
erection of the equipment at Site. Any demurrage, wharfage and other such charges
claimed by the transporters, railways etc. shall be to the account of the Contractor.
13.7 The Contractor shall be fully responsible for the equipment/material until the same is
handed over to the Employer in an operating condition after commissioning.
Contractor shall be responsible for the maintenance of the equipment/material while
in storage as well as after erection until taken over by Employer, as well as protection
of the same against theft, element of nature, corrosion, damages etc.
13.8 Where material / equipment is unloaded by Employer before the Contractor arrives at
site or even when he is at site, Employer by right can hand over the same to Contractor
and there upon it will be the responsibility of Contractor to store the material in an
orderly and proper manner.
13.9 The Contractor shall be responsible for making suitable indoor storage facilities, to
store all equipment which requires indoor storage.
13.10 The words ‘erection’ and ‘installation’ used in the specification are synonymous.
13.11 Exposed live parts shall be placed high enough above ground to meet the requirements
of electrical and other statutory safety codes.
13.12 The design and workmanship shall be in accordance with the best engineering
practices to ensure satisfactory performance throughout the service life. If at any stage
during the execution of the Contract, it is observed that the erected equipment(s) do
not meet the above minimum clearances the Contractor shall immediately proceed to
correct the discrepancy at his risks and cost.
13.13 Equipment Bases
A cast iron or welded steel base plate shall be provided for all rotating equipment
which is to be installed on a concrete base unless otherwise agreed to by the Employer.
Each base plate shall support the unit and its drive assembly, shall be of a neat design
with pads for anchoring the units, shall have a raised lip all around, and shall have
threaded drain connections.
14.0 TOOLS
14.1 TOOLS & PLANTS (T&P)
The Contractor shall arrange all T&P (such as necessary supports, cranes, ladders,
platforms etc.) for erection, testing & commissioning of the system at his own cost.
Further, all consumables, wastage and damages shall be to the account of contractor.
All such T&P shall be taken back by the contractor after commissioning of the system.
are specifically required for the equipment offered and are proprietary in nature. The
list of special tools and tackles, if any, shall be finalized during detail engineering and
the same shall be supplied without any additional cost implication to the Employer.
____________________________________________________________________________
Technical Specification: GTR Page 21 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
17.1 All power clamps and connectors shall conform to IS:5561 or other equivalent
international standard and shall be made of materials listed below :
Sl. No. Description Materials
a) For connecting ACSR Aluminum alloy casting, conforming to
conductors/AAC conductors/ designation A6 of IS:617 and all test shall
Aluminium tube conform to IS:617
b) For connecting equipment Bimetallic connectors made from
terminals mad of copper with aluminum alloy casting, conforming to
ACSR conductors/AAC designation A6 of IS:617 with 2mm thick
conductors/ Aluminium tube bimetallic liner/strip and all test shall
conform to IS:617
c) For connecting G.I Galvanised mild steel shield wire
d) Bolts, nuts & plain washers Electro-galvanised for sizes below M12,
for others hot dip galvanised.
e) Spring washers Electro-galvanised mild steel suitable for
atleast service condition-3 as per IS:1573
17.2 Necessary clamps and connectors shall be supplied for all equipment and connections.
If corona rings are required to meet these requirements they shall be considered as
part of that equipment and included in the scope of work.
17.3 Where copper to aluminum connections are required, bi-metallic clamps shall be used,
which shall be properly designed to ensure that any deterioration of the connection is
kept to a minimum and restricted to parts which are not current carrying or subjected
to stress.
17.4 Low voltage connectors, grounding connectors and accessories for grounding all
equipment as specified in each particular case, are also included in the scope of Work.
17.5 No current carrying part of any clamp shall be less than 10 mm thick. All ferrous parts
shall be hot dip galvanised. Copper alloy liner/strip of minimum 2 mm thickness shall
be cast integral with aluminum body or 2 mm thick bi-metallic liner/strips shall be
provided for Bi-metallic clamps.
17.6 All casting shall be free from blow holes, surface blisters, cracks and cavities. All sharp
edges and corners shall be blurred and rounded off.
17.7 Flexible connectors, braids or laminated straps made for the terminal clamps for bus
posts shall be suitable for both expansion or through (fixed/sliding) type connection of
IPS AL tube as required. In both the cases the clamp height (top of the mounting pad to
centre line of the tube) should be same.
17.8 Current carrying parts (500A and above) of the clamp/connector shall be provided
with minimum four numbers of bolts preferably for 132kV & above.
17.9 All current carrying parts shall be designed and manufactured to have minimum
contact resistance.
17.10 Power Clamps and connectors shall be designed to control corona as per requirement.
17.11 Tests
Clamps and connectors should be type tested as per IS:5561 and shall also be subjected
to routine tests as per IS:5561. Following type test reports shall be submitted for
____________________________________________________________________________
Technical Specification: GTR Page 22 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
approval. Type test once conducted shall hold good. The requirement of test conducted
within last ten years, shall not be applicable.
i) Temperature rise test (maximum temperature rise allowed is 35°C over 50°C
ambient)
ii) Short time current test
iii) Corona (dry) [for 400kV and above] and RIV (dry) test [for 132kV and above
voltage level clamps]
iv) Resistance test and tensile test
18.0 CONTROL CABINETS, JUNCTION BOXES, TERMINAL BOXES & MARSHALLING
BOXES FOR OUTDOOR EQUIPMENT
18.1 All types of boxes, cabinets etc. shall generally conform to & be tested in accordance
with IS-5039/IS-8623, IEC-60439, as applicable, and the clauses given below:
18.2 Control cabinets, junction boxes, Marshalling boxes & terminal boxes shall be made of
stainless steel of atleast 1.5 mm thick or aluminum enclosure of atleast 1.6 mm thick
and shall be dust, water and vermin proof. Stainless steel used shall be of grade SS304
(SS316 for coastal area) or better. The box shall be properly braced to prevent
wobbling. There shall be sufficient reinforcement to provide level surfaces, resistance
to vibrations and rigidity during transportation and installation. In case of aluminum
enclosed box the thickness of aluminum shall be such that it provides adequate rigidity
and long life as comparable with sheet steel of specified thickness.
18.3 A canopy and sealing arrangements for operating rods shall be provided in marshalling
boxes / Control cabinets to prevent ingress of rain water.
18.4 Cabinet/boxes shall be provided with double hinged doors with padlocking
arrangements. The distance between two hinges shall be adequate to ensure uniform
sealing pressure against atmosphere.
18.5 All doors, removable covers and plates shall be gasketed all around with suitably
profiled EPDM/Neoprene/PU gaskets. The gasket shall be tested in accordance with
approved quality plan, IS:11149 and IS:3400. Ventilating Louvers, if provided, shall
have screen and filters. The screen shall be fine wire mesh made of brass.
Further, the gasketing arrangement shall be such that gaskets are pasted in slots (in
door fabrication/gasket itself) in order to prevent ingression of dust and moisture
inside the panels so that no internal rusting occurs in panels during the operation of
the equipment.
18.6 All boxes/cabinets shall be designed for the entry of cables by means of weather proof
and dust-proof connections. Boxes and cabinets shall be designed with generous
clearances to avoid interference between the wiring entering from below and any
terminal blocks or accessories mounted within the box or cabinet. Suitable cable gland
plate above the base of the marshalling kiosk/box shall be provided for this purpose
along with the proper blanking plates. Necessary number of cable glands shall be
supplied and fitted on this gland plate. Gland plate shall have provision for some future
glands to be provided later, if required. The Nickel plated glands shall be dust proof,
screw on & double compression type and made of brass. The gland shall have provision
for securing armour of the cable separately and shall be provided with earthing tag.
The glands shall conform to BS:6121.
18.7 A 240V, single phase, 50 Hz, 15 amp AC plug and socket shall be provided in the
cabinet with ON-OFF switch for connection of hand lamps. Plug and socket shall be of
industrial grade.
____________________________________________________________________________
Technical Specification: GTR Page 23 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
18.8 LED based illumination of minimum 9 watts shall be provided. The switching of the
fittings shall be controlled by the door switch.
For junction boxes of smaller sizes such as lighting junction box, manual operated
earth switch mechanism box etc., plug socket, heater and illumination is not required
to be provided.
18.9 All control switches shall be of MCB/rotary switch type and Toggle/piano switches
shall not be accepted.
18.10 Earthing of the cabinet shall be ensured by providing two separate earthing pads. The
earth wire shall be terminated on to the earthing pad and secured by the use of self
etching washer. Earthing of hinged door shall be done by using a separate earth wire.
18.11 The bay marshalling kiosks shall be provided with danger plate and a diagram showing
the numbering/connection/feruling by pasting the same on the inside of the door.
18.12 The following routine tests alongwith the routine tests as per IS:5039 shall also be
conducted:
i) Check for wiring
ii) Visual and dimension check
18.13 The enclosure of bay marshalling kiosk, junction box, terminal box and control cabinets
shall conform to IP-55 as per IS:13947 including application of 2KV rms for 1 (one)
minute, insulation resistance and functional test after IP-55 test.
19.0 DISPOSAL OF PACKING MATERIAL & WASTE FROM CONSTRUCTION SITE
After completion of the work, Contractor shall dispose-off all the packing & waste
materials including empty conductor drums, cable drums, wooden containers, oil
drums, gas cylinders and other waste/scrapped materials from construction site at his
own cost and shall make the substation area properly cleaned.
20.0 TERMINAL BLOCKS AND WIRING
20.1 Control and instrument leads from the switchboards or from other equipment will be
brought to terminal boxes or control cabinets in conduits. All interphase and external
connections to equipment or to control cubicles will be made through terminal blocks.
20.2 Terminal blocks shall be 650V grade and have continuous rating to carry the maximum
expected current on the terminals and non-breakable type. These shall be of moulded
piece, complete with insulated barriers, stud type terminals, washers, nuts and lock
nuts. Screw clamp, overall insulated, insertion type, rail mounted terminals can be used
in place of stud type terminals. But the terminal blocks shall be non-disconnecting stud
type except for the secondary junction boxes of Current Transformer and Voltage
Transformer.
20.3 Terminal blocks for current transformer and voltage transformer secondary leads shall
be provided with test links and isolating facilities. The current transformer secondary
leads shall also be provided with short circuiting and earthing facilities.
20.4 The terminal shall be such that maximum contact area is achieved when a cable is
terminated. The terminal shall have a locking characteristic to prevent cable from
escaping from the terminal clamp unless it is done intentionally.
20.5 The conducting part in contact with cable shall preferably be tinned or silver plated
however Nickel plated copper or zinc plated steel shall also be acceptable.
20.6 The terminal blocks shall be of extensible design, multilayer terminal arrangement is
not allowed in any junction box (Common MB, Individual MB, JB etc.). There should be
____________________________________________________________________________
Technical Specification: GTR Page 24 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
____________________________________________________________________________
Technical Specification: GTR Page 26 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
____________________________________________________________________________
Technical Specification: GTR Page 27 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
20% of the rated speed. The speed switch shall be capable of withstanding 120%
of the rated speed in either direction of rotation.
23.4 Running Requirements:
____________________________________________________________________________
Technical Specification: GTR Page 28 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
(ii) Alternatively, the manufacturer, who have established manufacturing and testing
facilities in India for the offered equipment and not meeting the requirement
stipulated in (i) above, can also be considered provided that
a) 715/345/220/132/110kV* or higher Voltage class equipment(s) must have
been manufactured in the above Indian works & type tested (as per IEC/IS
standard) and supplied as on the date of NOA.
(ii) Alternatively, the manufacturer, who have established manufacturing and testing
facilities in India and not meeting the requirement stipulated in (i) above, can
also be considered provided that
a) 715kV or higher voltage class one (1) number three phase Transformer of
atleast 500 MVA capacity (or equivalent capacity in a bank of three (3)
numbers single phase units) must have been manufactured in the above
Indian works based on technological support of collaborator, type tested (as
per IEC/IS standard) and supplied as on the date of NOA.
in a bank of three (3) numbers single phase units). These Reactors must have
been in satisfactory operation# for atleast two (2) years as on the date of NOA.
(ii) Alternatively, the manufacturer, who have established manufacturing and testing
facilities in India and not meeting the requirement stipulated in (i) above, can
also be considered provided that
a) 715kV or higher voltage class one (1) number three phase Reactor of atleast
240MVAR capacity (or equivalent capacity in a bank of three (3) numbers
single phase units) must have been manufactured in the above Indian works
based on technological support of collaborator, type tested (as per IEC/IS
standard) and supplied as on the date of NOA.
24.4 Technical Requirement for 400kV, 220kV, 132kV and 110kV class Transformer
(i) The manufacturer whose transformer(s) are offered must have designed,
manufactured, tested and supplied 400kV/220kV/132kV/110kV* or higher
voltage class transformers. These Transformer(s) must have been in satisfactory
operation# for atleast two (2) years as on the date of NOA.
(ii) Alternatively, the manufacturer, who have established manufacturing and testing
facilities in India and not meeting the requirement stipulated in (i) above, can
also be considered provided that
24.5 Technical Requirement for 400kV, 220kV and 132kV class Reactor
____________________________________________________________________________
Technical Specification: GTR Page 30 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
voltage class. These Reactor(s) must have been in satisfactory operation# for
atleast two (2) years as on the date of NOA.
(ii) Alternatively, the manufacturer, who have established manufacturing and testing
facilities in India and not meeting the requirement stipulated in (i) above, can
also be considered provided that
(ii) Alternatively, the manufacturer, who have established manufacturing and testing
facilities in India and not meeting the requirement stipulated in (i) above, can
also be considered provided that
(ii) Alternatively, the manufacturer, who have established manufacturing and testing
facilities in India and not meeting the requirement stipulated in (i) above, can
also be considered provided that
a) The manufacturer must have designed, manufactured, type tested and supplied
132KV/110kV/66kV* or higher grade XLPE insulated cable and which must be
in satisfactory operation# for atleast one (1) year as on the date of NOA.
24.9 Technical Requirement for 1.1 KV Grade PVC Control Cable
The manufacturer(s), whose PVC control cables are offered, must have designed,
manufactured, tested and supplied in a single contract atleast 100 Kms of 1.1kV grade
PVC insulated control cables as on the originally scheduled date of bid opening.
Further the manufacturer must also have designed, manufactured, tested and supplied
atleast 1 km of 27C x 2.5 Sq.mm or higher size as on the date of NOA.
24.10 Technical Requirement for 1.1 KV Grade PVC Power Cable
The manufacturer(s), whose PVC Power Cables are offered, must have designed,
manufactured, tested and supplied in a single contract atleast 100 Kms of 1.1kV or
higher grade PVC insulated power cables as on the date of NOA/award. Further the
manufacturer must also have designed, manufactured, tested and supplied atleast 1 km
of 1C x 150 Sq. mm or higher size as on the date of NOA.
24.11 Technical Requirement for 1.1 KV Grade XLPE Power Cables
The manufacturer(s), whose XLPE Power cables are offered, must have designed,
manufactured, tested and supplied in a single contract atleast 25 Kms of 1.1 KV or
higher grade XLPE insulated power cables as on the date of NOA/award. Further the
manufacturer must also have designed, manufactured, tested and supplied atleast 1 km
of 1C x 630 Sq. mm or higher size as on the date of NOA.
24.12 Technical Requirement for LT Switchgear
i) The manufacturer whose LT Switchgear(s) are offered, must be a manufacturer of
LT Switchboards of the type and rating being offered. He must have designed,
manufactured, tested and supplied atleast 50 nos. draw out circuit breaker panels,
out of which atleast 5 nos. should have been with relay and protection schemes
with current transformer. He must have also manufactured atleast 50 nos. MCC
panels comprising of MCCBs (ie Moulded Case Circuit Breakers) modules of the type
offered which must be in satisfactory operation# as on the date of NOA.
ii) The Switchgear items (such as circuit breakers, fuse switch units, contactors etc.),
may be of his own make or shall be procured from reputed manufacturers and of
proven design, atleast one hundred circuit breakers of the make and type being
offered must have been in satisfactory operation# as on the date of NOA.
____________________________________________________________________________
Technical Specification: GTR Page 32 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
(ii) Alternatively, the manufacturer, who have established manufacturing and testing
facilities in India and not meeting the requirement stipulated in (i) above, can
also be considered provided that
a) The manufacturer must have designed, manufactured, type tested and supplied
Composite Long rod Insulator of 120KN or above electro-mechanical strength
for 765kV/400kV* or higher voltage class and the same must have been in
satisfactory operation# as on the date of NOA.
b) Contractor shall furnish performance guarantee for an amount of 10% of the ex-
works cost of the equipments(s)* and this performance guarantee shall be in
addition to the contract performance guarantee to be submitted by the
contractor.
____________________________________________________________________________
Technical Specification: GTR Page 33 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
24.17 Technical Requirements for Control, Relay & Protection System and Sub-station
Automation System
The manufacturer whose Control, Relay & Protection System (Control & protection
Intelligent Electronic Devices (IEDs)), and Sub-station Automation System (as
applicable) are offered, must have designed, manufactured, tested, installed and
commissioned Control, Relay & Protection system along with Sub-station Automation
System which must have been in satisfactory operation# on (i) 400 kV system
[applicable for 765kV substation] & (ii) specified voltage level or above [applicable for
400kV & below substation] for atleast two (2) years as on the date of NOA.
AND
The Manufacturer or their joint venture or subsidiary company or parent company
must be a manufacturer of control and protection IEDs and must have established
repair, testing and integration (atleast for 4 bays) facilities for Control, Relay &
Protection System and Sub-station Automation System in India.
24.18 Technical Requirements for analog and digital PLCC panels (765kV, 400kV,
220kV & 132kV)
(i) The manufacturer whose PLCC panels are offered, must have designed,
manufactured, tested, supplied and commissioned PLCC panels for (i) 400kV
system or above [applicable for 765 kV & 400 kV substation], (ii) 220 kV
System or above [applicable for 220 kV Substation] & (iii) 132 kV system or
above [applicable for 132 kV substation] and the same must have been in
satisfactory operation# for atleast two (2) years as on the date of NOA.
(ii) Alternatively, the manufacturer, who have established manufacturing and
testing facilities in India and not meeting the requirement stipulated in (i)
above, can also be considered provided that
a) PLCC panels must have been manufactured in the above Indian works based
on technological support of collaborator, type tested (as per IEC/IS
standard) and supplied as on the date of NOA.
b) collaborator shall furnish performance guarantee for an amount of 10% of
the ex-works cost of such equipment(s) and this performance guarantee
shall be in addition to contract performance guarantee to be submitted by
the contractor.
c) The collaborator meets the requirements stipulated in (i) above. A valid
collaboration agreement for technology transfer/license to design,
manufacture, test and supply PLCC panels in India, shall be submitted.
24.19 Technical Requirement of Communication Equipment
The SDH equipment shall be offered from a manufacturer(s) who has been
manufacturing SDH equipments for the last three (3) years and SDH equipment
manufactured by such manufacturer(s) shall have been satisfactory operation in
110kV or higher voltage Power Substations for at least two (2) years as on the date of
NOA.
24.20 Technical Requirement of “Indian Associate” for execution of on shore supply
and services for 765 kV Transformer & Reactor package
Indian associate must have erected at least two (2) or more circuit breaker equipped
bays of 345 kV or above voltage level or at least two (2) nos. of 345 kV or above
voltage class transformer/reactor; during last seven (7) years and above
bays/transformer/reactors must be in satisfactory operation# as on the date of NOA.
____________________________________________________________________________
Technical Specification: GTR Page 34 of 34
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan 2017)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-A
CORONA AND RADIO INTERFERENCE VOLTAGE (RIV) TEST
1. General
Unless otherwise stipulated, all equipment together with its associated connectors,
where applicable, shall be tested for external corona (for 400kV & above) both by
observing the voltage level for the extinction of visible corona under falling power
frequency voltage and by measurement of radio interference voltage (RIV) for 132kV
and above.
2. Test Levels:
The test voltage levels for measurement of external RIV and for corona extinction
voltage are listed under the relevant clauses of the specification.
3. Test Methods for RIV:
3.1 RIV tests shall be made according to measuring circuit as per International Special-
Committee on Radio Interference (CISPR) Publication 16-1(1993) Part -1. The
measuring circuit shall preferably be tuned to frequency with 10% of 0.5 Mhz but
other frequencies in the range of 0.5 MHz to 2 MHz may be used, the measuring
frequency being recorded. The results shall be in microvolts.
3.2 Alternatively, RIV tests shall be carried out in accordance with relevant IEC of
respective equipment or NEMA standard Publication No. 107-1964.
3.3 In measurement of, RIV, temporary additional external corona shielding may be
provided. In measurements of RIV only standard fittings of identical type supplied
with the equipment and a simulation of the connections as used in the actual
installation will be permitted in the vicinity within 3.5 meters of terminals.
3.4 Ambient noise shall be measured before and after each series of tests to ensure that
there is no variation in ambient noise level. If variation is present, the lowest ambient
noise level will form basis for the measurements. RIV levels shall be measured at
increasing and decreasing voltages of 85%, 100%, and 110% of the specified RIV test
voltage for all equipment unless otherwise specified. The specified RIV test voltage for
765kV, 400 kV, 220 KV is listed in the detailed specification together with maximum
permissible RIV level in microvolts.
3.5 The metering instruments shall be as per CISPR recommendation or equivalent device
so long as it has been used by other testing authorities.
3.6 The RIV measurement may be made with a noise meter. A calibration procedure of the
frequency to which noise meter shall be tuned shall establish the ratio of voltage at the
high voltage terminal to voltage read by noise meter.
4. Test Methods for Visible Corona
The purpose of this test is to determine the corona extinction voltage of apparatus,
connectors etc. The test shall be carried out in the same manner as RIV test described
above with the exception that RIV measurements are not required during test and a
search technique shall be used near the onset and extinction voltage, when the test
voltage is raised and lowered to determine their precise values. The test voltage shall
be raised to 110% of specified corona extinction voltage and maintained there for five
minutes. In case corona inception does not take place at 110%, test shall be stopped,
otherwise test shall be continued and the voltage will then be decreased slowly until
____________________________________________________________________________
Technical Specification: GTR Page 1 of 2 (Annexure-A)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-A
all visible corona disappears. The procedure shall be repeated at least 4 times with
corona inception and extinction voltage recorded each time. The corona extinction
voltage for purposes of determining compliance with the specification shall be the
lowest of the four values at which visible corona (negative or positive polarity)
disappears. Photographs with laboratory in complete darkness shall be taken under
test conditions, at all voltage steps i.e. 85%, 100%, and 110%. Additional photographs
shall be taken at corona inception and extinction voltages. At least two views shall be
photographed in each case using Panchromatic film with an ASA daylight rating of 400
with an exposure of two minutes at a lens aperture of f/5.6 or equivalent. The
photographic process shall be such that prints are available for inspection and
comparison with conditions as determined from direct observation. Photographs shall
be taken from above and below the level of connector so as to show corona on
bushing, insulators and all parts of energised connectors. The photographs shall be
framed such that test object essentially, fills the frame with no cut-off.
For recording purpose, modern devices utilizing UV recording methods such as image
intensifier may also be used.
4.1 The test shall be recorded on each photograph. Additional photograph shall be taken
from each camera position with lights on to show the relative position of test object to
facilitate precise corona location from the photographic evidence.
4.2 In addition to photographs of the test object preferably four photographs shall be
taken of the complete test assembly showing relative positions of all the test
equipment and test objects. These four photographs shall be taken from four points
equally spaced around the test arrangement to show its features from all sides.
Drawings of the laboratory and test set up locations shall be provided to indicate
camera positions and angles. The precise location of camera shall be approved by
Employer’s inspector, after determining the best camera locations by trial energisation
of test object at a voltage which results in corona.
4.3 The test to determine the visible corona extinction voltage need not be carried out
simultaneously with test to determine RIV levels.
4.4 However, both test shall be carried out with the same test set up and as little time
duration between tests as possible. No modification on treatment of the sample
between tests will be allowed. Simultaneous RIV and visible corona extinction voltage
testing may be permitted at the discretion of Employer’s inspector if, in his opinion, it
will not prejudice other test.
5. Test Records:
In addition to the information previously mentioned and the requirements specified as
per CISPR or NEMA 107-1964 the following data shall be included in test report:
a) Background noise before and after test.
b) Detailed procedure of application of test voltage.
c) Measurements of RIV levels expressed in micro volts at each level.
d) Results and observations with regard to location and type of interference
sources detected at each step.
e) Test voltage shall be recorded when measured RIV passes through 100
microvolts in each direction.
f)Onset and extinction of visual corona for each of the four tests required shall be
recorded.
____________________________________________________________________________
Technical Specification: GTR Page 2 of 2 (Annexure-A)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-B
The seismic withstanding test on the complete equipment (for 132kV and above) shall be
carried out alongwith supporting structure.
The Bidder shall arrange to transport the structure from his Contractor’s premises/
POWERGRID sites for the purpose of seismic withstand test only.
The seismic level specified shall be applied at the base of the structure. The accelerometers
shall be provided at the Terminal Pad of the equipment and any other point as agreed by
the Employer. The seismic test shall be carried out in all possible combinations of the
equipment. The seismic test procedure shall be furnished for approval of the Employer.
The frequency range for the earthquake spectra shall be as per IEC–6227-300.
____________________________________________________________________________________________
Technical Specification: GTR Page 1 of 1 (Annexure-B)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
-- India Electricity Rules
-- Indian Electricity Act
-- Indian Electricity (Supply) Act
-- Indian Factories Act
IS-5 Colors for Ready Mixed Paints and Enamels
IS-335 New Insulating Oils
IS-617 Aluminium and Aluminium Alloy Ingots and Castings for General
Engineering Purposes
IS-1448 (P1 to P 145) Methods of Test for Petroleum and its Products
IS-2071 (P1 to P3) Methods of High Voltage Testing
IS-12063 Classification of degrees of protection provided by enclosures of
electrical equipment
IS-2165 ; P1:1997, Insulation Coordination
P2:1983
IS-3043 Code of Practice for Earthing
IS-6103 Method of Test for Specific Resistance (Resistivity) of Electrical
Insulating Liquids
IS-6104 Method of Test for Interfacial Tension of Oil against Water by the
Ring Method
IS-6262 Method of test for Power factor & Dielectric Constant of Electrical
Insulating Liquids
IS-6792 Method for determination of electric strength of insulating oils
IS-5578 Guide for marking of insulated conductors
IS-11353 Guide for uniform system of marking & identification of
conductors & apparatus terminals.
IS-8263 Methods for Radio Interference Test on High voltage Insulators
IS-9224 (Part 1,2&4) Low Voltage Fuses
IEC-60060 (Part 1 to P4) High Voltage Test Techniques
IEC 60068 Environmental Test
IEC-60117 Graphical Symbols
IEC-60156 Method for the Determination of the Electrical Strength of
Insulation Oils
IEC-60270 Partial Discharge Measurements
IEC-60376 Specification and Acceptance of New Sulphur Hexafloride
IEC-60437 Radio Interference Test on High Voltage Insulators
IEC-60507 Artificial Pollution Tests on High Voltage Insulators to be used on
AC Systems
IEC-62271-1 Common Specification for High Voltage Switchgear & Control
gear Standards
IEC-60815 Guide for the Selection of Insulators in respect of Polluted
Conditions
____________________________________________________________________________
Technical Specification: GTR Page 1 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
IEC-60865 (P1 & P2) Short Circuit Current - Calculation of effects
ANSI-C.1/NFPA.70 National Electrical Code
ANSI-C37.90A Guide for Surge Withstand Capability (SWC) Tests
ANSI-C63.21, C63.3 Specification for Electromagnetic Noise and Field Strength
Instrumentation 10 KHz to 1 GHZ
C36.4ANSI-C68.1 Techniquest for Dielectric Tests
ANSI-C76.1/EEE21 Standard General Requirements and Test Procedure for Outdoor
Apparatus Bushings
ANSI-SI-4 Specification for Sound Level Meters
ANSI-Y32-2/C337.2 Drawing Symbols
ANSI-Z55.11 Gray Finishes for Industrial Apparatus and Equipment No. 61
Light Gray
NEMA-107T Methods of Measurements of RIV of High Voltage Apparatus
NEMA-ICS-II General Standards for Industrial Control and Systems Part ICSI-
109
CISPR-1 Specification for CISPR Radio Interference Measuring Apparatus
for the frequency range 0.15 MHz to 30 MHz
CSA-Z299.1-1978h Quality Assurance Program Requirements
CSA-Z299.2-1979h Quality Control Program Requirements
CSA-Z299.3-1979h Quality Verification Program Requirements
CSA-Z299.4-1979h Inspection Program Requirements
TRANSFORMERS AND REACTORS
IS:10028 (Part 2 & 3) Code of practice for selection, installation & maintenance of
Transformers (P1:1993), (P2:1991), (P3:1991)
IS-2026 (P1 to P4) Power Transformers
IS-3347 (part 1 to Part 8) Dimensions for Porcelain transformer Bushings for use in lightly
polluted atmospheres
IS-3639 Fittings and Accessories for Power Transformers
IS-6600 Guide for Loading of oil immersed Transformers
IEC-60076 (Part 1 to 5) Power Transformers
IEC-60214 On-Load Tap-Changers
IEC-60289 Reactors
IEC- 60354 Loading Guide for Oil - Immersed power transformers
IEC-60076-10 Determination of Transformer and Reactor Sound Levels
ANSI-C571280 General requirements for Distribution, Power and Regulating
Transformers
ANSI-C571290 Test Code for Distribution, Power and Regulation Transformers
ANSI-C5716 Terminology & Test Code for Current Limiting Reactors
ANSI-C5721 Requirements, Terminology and Test Code for Shunt Reactors
Rated Over 500 KVA
ANSI-C5792 Guide for Loading Oil-Immersed Power Transformers upto and
including 100 MVA with 55 deg C or 65 deg C Winding Rise
____________________________________________________________________________
Technical Specification: GTR Page 2 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
ANSI-CG,1EEE-4 Standard Techniques for High Voltage Testing
IEC 60076 Power transformers
IEC 60076-1 Part 1: General
IEC 60076-2 Part 2: Temperature rise
IEC 60076-3 Part 3: Insulation levels, dielectric tests and external clearances
in air
IEC 60076-4 Part 4: Guide to the lightning impulse and switching impulse
testing - Power transformers and reactors
IEC 60076-3-1 Part 3-1: Insulation Levels and Dielectric Tests –External
Clearances in Air
IEC 60076-5 Part 5: Ability to withstand short circuit
IEC 60076-6 Part 6: Reactors
IEC 60076-7 Part 7: Loading guide for oil-immersed power transformers
IEC 60076-8 Part 8: Application guide
IEC 60076-10 Part 10: Determination of sound levels
IEC 60076-10-1 Part 10-1: Determination of sound levels - Application guide
IEC 60076-11 Part 11: Dry-type transformers
IEC 60076-12 Part 12: Loading guide for dry-type power transformers
IEC 60076-13 Part 13: Self-protected liquid-filled transformers
IEC 60076-14 Part 14: Design and application of liquid-immersed power
transformers using high-temperature insulation materials
IEC 60076-15 Part 15: Gas-filled power transformers
IEC 60076-16 Part 16: Transformers for wind turbine applications
IEC 60076-18 Part 18: Measurement of frequency response
IEC 60076-19 Part 19: Rules for the determination of uncertainties in the
measurement of losses in power transformers and reactors
IEC 60076-21 Part 21: Standard requirements, terminology, and test code for
step-voltage regulators
IEC 60044, BS 3938 Current transformers
IEC 60050 International Electrotechnical Vocabulary
IEC 60050(421) International Electrotechnical vocabulary- Chapter 421 : Power
Transformers and Reactors
IEC 60060 High Voltage test techniques
IEC 60060-1 General definitions and test requirements
IEC 60060-2 Measuring systems
IEC 60071 Insulation co-ordination
IEC 60071-1 Part 1: Definitions, principles and rules
IEC 60071-2 Part 2 : Application guide
IEC 60137 Bushing for alternating voltage above 1000V
IEC 60214 On-Load Tap changers
IEC 255-21-3 Relays vibration
____________________________________________________________________________
Technical Specification: GTR Page 3 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
IEC 60270 Partial discharge measurements
IEC 60296 Specification for Unused Mineral Oil for Transformers and
Switchgear
IEC 60422 Supervision and Maintenance guide for Mineral Insulating Oil in
Electrical Equipment
IEC 60475 Method of Sampling Liquid dielectrics
IEC 60529 Classification of Degrees of Protection provided by Enclosures
IEC 60542 Application Guide for On-Load Tap-Changers
IEC 60567 Guide for the Sampling of Gases and of Oil from Oil-filled
Electrical Equipment for the Analysis of Free and Dissolved Gases
IEC 60651 Sound Level Meters
IEC 61083 Digital Recorders and Software for High Voltage Impulse testing
IEC 61083-1 Part 1: Requirements for digital recorders in high voltage impulse
tests
IEC 61083-2 Part 2: Evaluation of software used for the determination of the
parameters of impulse waveforms
CISPR 16 Specification for radio disturbance and immunity measuring
apparatus
CISPR 16-1 Radio disturbance and immunity measuring apparatus
CISPR-18 Radio Interference Characteristics of Power Lines and High
Voltage Equipment
ISO 9001 Quality system-Model for Quality Assurance in Design
/development
Cigre Publication 202 Guidelines for conducting design reviews for transformers 100
MVA and 123 kV and above. August 2002-Cigre Working Group
12.22
WG 12-15 Guide for Customers Specifications for Transformers 100 MVA
and 123 kV and above
WG 12 19 Short Circuit Performance of Transformers.
BS-4360 Specification for weldable structural steel
BS-5135 Specification for arc welding of carbon and carbon manganese
steels
BS-5500 Specification for unfired fusion welded pressure vessels
IS-3618 Specification for phosphate treatment of iron & steel for
protection against corrosion
IS-6005 Code of practice for phosphating of Iron and Steel
ISO-8501 Preparation of steel surface before application of Paints and
related product
IEC-60599 Mineral oil impregnated electrical equipment in service – guide
to the interpretation of dissolved and free gases analysis
IS-10593 Method of evaluating the analysis of gases in oil filled electrical
equipment in service
IS-2099 Bushings for alternating voltages above 1000 volts
____________________________________________________________________________
Technical Specification: GTR Page 4 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
IS-3347 Part I to 8 Dimension for porcelain transformer bushing
DIN-42530 Bushing up to 1000kV from 250A-5000A for liquid filled
Transformer
IS-2026 Part 1 to 5 Power transformer
IS-4691 Degrees of protection provided by enclosure for rotating
electrical machinery
IEC-60034-5 Degrees of protection provided by integral design of rotating
electrical machines(IP Code) classification
IS:325 / IEC -60034 Performance of cooling fan / oil pump motor
IS-13947 part 1 to 5 Specification for low voltage switchgear and control gear
IS:3400 Methods of test for vulcanised rubber
IS:7016 part 1 to 14 Methods of test for coated and treated fabrics
IS:803 Code of practice for design, fabrication and erection of vertical
mild steel cylindrical welded oil storage tanks.
IS:3637 Gas operated Relays
IS:335 New Insulating oils – Specification
IEC-62271-203 Gas insulated metal enclosed switchgear for rated voltage above
52kV
IEC-61639 Direct connection between power transformers and gas-
insulated metal enclosed switchgear for rated voltages of 52.5 kV
and above.
IS:3400 / BS 903 / Air cell ( Flexible Air Separator)
IS:7016
IEC 60529 / IP : 55 Degree of protection for cooler control cabinet , MOLG, Cooling
fan , oil pump, Buchholz Relay
IEC 60529 / IP : 56 Degree of protection for Pressure Relief Device
IEC 60529 / IP : 43 Degree of protection for Remote tap Changer cubicle (RTCC)
CIRCUIT BREAKERS
IEC-62271-100 High-voltage switchgear and control gear - Part 100: Alternating
current circuit-breakers
IEC-62271-101 High-voltage switchgear and control gear - Part 101: Synthetic
testing
IEC-62155 Hollow pressurized and unpressurized ceramic and glass
insulators for use in electrical equipment with rated voltages
greater than 1000 V
IEC-62271-110 High-voltage switchgear and control gear - Part 110: Inductive
load switching
IEC-62271-109 High-voltage switchgear and control gear - Part 110: Inductive
load switching
CURRENT TRANSFORMERS, VOLTAGE TRANSFORMERS AND COUPLING CAPACITOR
VOLTAGE TRANSFORMERS
IS-2705- (P1 to P4) Current Transformers
____________________________________________________________________________
Technical Specification: GTR Page 5 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
IS:3156- (P1 to P4) Voltage Transformers
IS-4379 Identification of the Contents of Industrial Gas Cylinders
IEC-61869 (Part-1) Instrument transformers - Part 1: General requirements
IEC-61869 (Part-2) Instrument transformers - Part 2: Additional requirements for
current transformers
IEC-61869 (Part-3) Instrument transformers - Part 3: Additional requirements for
inductive voltage transformers
IEC-61869 (Part-4) Instrument transformers - Part 4: Additional requirements for
combined transformers
IEC-61869 (Part-5) Instrument transformers - Part 5: Additional requirements for
capacitor voltage transformers
IEC-61869 (Part-6) Instrument transformers - Part 6: Additional general
requirements for low-power instrument transformers
IEC-61869 (Part-9) Instrument transformers - Part 9: Digital interface for instrument
transformers
IEC-61869 (Part-102) Instrument transformers - Part 102: Ferroresonance oscillations
in substations with inductive voltage transformers
IEC-61869 (Part-103) Instrument transformers - The use of instrument transformers
for power quality measurement
BUSHING
IS-2099 Bushings for Alternating Voltages above 1000V
IEC-60137 Insulated Bushings for Alternating Voltages
above 1000V
SURGE ARRESTERS
IS-3070 (PART2) Lightning arresters for alternating current systems : Metal oxide
lightning arrestors without gaps
IEC-60099-4 Metal oxide surge arrestors without gaps
IEC-60099-5 Selection and application recommendation
ANSI-C62.1 IEE Standards for S A for AC Power Circuits
NEMA-LA 1 Surge Arresters
CUBICLES AND PANELS & OTHER RELATED EQUIPMENTS
IS-722, IS-1248 Electrical relays for power system
IS-3231, 3231 (P-3) Protection
IS:5039 Distributed pillars for Voltages not Exceeding 1000 Volts
IEC-60068.2.2 Basic environmental testing procedures Part 2: Test B: Dry heat
IEC-60529 Degree of Protection provided by enclosures
IEC-60947-4-1 Low voltage switchgear and control gear
IEC-61095 Electromechanical Contactors for household and similar
purposes
IEC-60439 (P1 & 2) Low Voltage Switchgear and control gear assemblies
ANSI-C37.20 Switchgear Assemblies, including metal enclosed bus
ANSI-C37.50 Test Procedures for Low Voltage Alternating Current Power
____________________________________________________________________________
Technical Specification: GTR Page 6 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
Circuit Breakers
ANSI-C39 Electric Measuring instrument
ANSI-C83 Components for Electric Equipment
IS: 8623: (Part I to 3) Specification for Switchgear & Control Assemblies
NEMA-AB Moulded Case Circuit and Systems
NEMA-CS Industrial Controls and Systems
NEMA-PB-1 Panel Boards
NEMA-SG-5 Low voltage Power Circuit breakers
NEMA-SG-3 Power Switchgear Assemblies
NEMA-SG-6 Power switching Equipment
NEMA-5E-3 Motor Control Centers
1248 (P1 to P9) Direct acting indicating analogue electrical measuring
instruments & their accessories
Disconnecting switches
IEC-62271-102 High-voltage switchgear and control gear - Part 102: Alternating
current disconnectors and earthing switches
IEC-60265 (Part 1 & 2) High Voltage switches
ANSI-C37.32 Schedule of preferred Ratings, Manufacturing Specifications and
Application Guide for high voltage Air Switches, Bus supports and
switch accessories
ANSI-C37.34 Test Code for high voltage air switches
NEMA-SG6 Power switching equipment
PLCC and line traps
IS-8792 Line traps for AC power system
IS-8793 Methods of tests for line traps
IS-8997 Coupling devices for PLC systems
IS-8998 Methods of test for coupling devices for PLC systems
IEC-60353 Line traps for A.C. power systems
IEC-60481 Coupling Devices for power line carrier systems
IEC-60495 Single sideboard power line carrier terminals
IEC-60683 Planning of (single Side-Band) power line carrier systems
CIGRE Teleprotection report by Committee 34 & 35
CIGRE Guide on power line carrier 1979
CCIR International Radio Consultative Committee
CCITT International Telegraph & Telephone Consultative Committee
EIA Electric Industries Association
Protection and control equipment
IEC-60051: (P1 to P9) Recommendations for Direct Acting indicating analogue electrical
measuring instruments and their accessories
IEC-60255 (Part 1 to 23) Electrical relays
IEC-60297 (P1 to P4) Dimensions of mechanical structures of the 482.6mm (19 inches)
____________________________________________________________________________
Technical Specification: GTR Page 7 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
series
IEC-60359 Expression of the performance of electrical & electronic
measuring equipment
IEC-60387 Symbols for Alternating-Current Electricity meters
IEC-60447 Man machine interface (MMI) - Actuating principles
IEC-60521 Class 0.5, 1 and 2 alternating current watt hour metres
IEC-60547 Modular plug-in Unit and standard 19-inch rack mounting unit
based on NIM Standard (for electronic nuclear instruments)
ANSI-81 Screw threads
ANSI-B18 Bolts and Nuts
ANSI-C37.1 Relays, Station Controls etc
ANSI-C37.2 Manual and automatic station control, supervisory and
associated telemetering equipment
ANSI-C37.2 Relays and relay systems associated with electric power
apparatus
ANSI-C39.1 Requirements for electrical analog indicating instruments
MOTORS
IS-325 Three phase induction motors
IS-4691 Degree of protection provided by enclosure for rotating electrical
machinery
IEC-60034 (P1 to P19:) Rotating electrical machines
IEC-Document 2 Three phase induction motors
(Central Office) Motors and Generators
NEMA-MGI
Electronic equipment and components
MIL-21B, MIL-833 Environmental testing
& MIL-2750
EC-60068 (P1 to P5) Printed boards
IEC-60326 (P1 to P2) Material and workmanship standards
IS-1363 (P1 to P3) Hexagon head bolts, screws and nuts of product grade C
IS-1364 (P1 to P5) Hexagon head bolts, screws and nuts of products grades A and B
IS-3138 Hexagonal Bolts and Nuts (M42 to M150)
ISO-898 Fasteners: Bolts, screws and studs
ASTM Specification and tests for materials
Clamps & connectors
IS-5561 Electric power connectors
NEMA-CC1 Electric Power connectors for sub station
NEMA-CC 3 Connectors for Use between aluminium or aluminum-Copper
Overhead Conductors
Bus hardware and insulators
IS: 2121 Fittings for Aluminum and steel cored Al conductors for overhead
____________________________________________________________________________
Technical Specification: GTR Page 8 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
power lines
IS-731 Porcelain insulators for overhead power lines with a nominal
voltage greater than 1000 V
IS-2486 (P1 to P4) Insulator fittings for overhead power lines with a nominal
voltage greater than 1000 V
IEC-60120 Dimensions of Ball and Socket Couplings of string insulator units
IEC-60137 Insulated bushings for alternating voltages above 1000 V
IEC-60168 Tests on indoor and outdoor post insulators of ceramic material
or glass for Systems with Nominal Voltages Greater than 1000 V
IEC-62155 Hollow pressurized and unpressurized ceramic and glass
insulators for use in electrical equipment with rated voltages
greater than 1 000 V
IEC-60273 Characteristics of indoor and outdoor post insulators for systems
with nominal voltages greater than 1000V
IEC-61462 Pressurized and un-pressurized insulator for use in electrical
equipment with rated voltage greater than 1000V – Definitions,
Test methods, acceptance criteria and design recommendations
IEC-60305 Insulators for overhead lines with nominal voltage above 1000V-
ceramic or glass insulator units for ac systems Characteristics of
String Insulator Units of the cap and pin type
IEC-60372 (1984) Locking devices for ball and socket couplings of string insulator
units : dimensions and tests
IEC-60383 (P1 and P2) Insulators for overhead lines with a nominal voltage above 1000
V
IEC-60433 Characteristics of string insulator units of the long rod type
IEC-60471 Dimensions of Clevis and tongue couplings of string insulator
units
ANSI-C29 Wet process porcelain insulators
ANSI-C29.1 Test methods for electrical power insulators
ANSI-C92.2 For insulators, wet-process porcelain and toughened glass
suspension type
ANSI-C29.8 For wet-process porcelain insulators apparatus, post-type
ANSI-G.8 Iron and steel hardware
CISPR-7B Recommendations of the CISPR, tolerances of form and of
Position, Part 1
ASTM A-153 Zinc Coating (Hot-Dip) on iron and steel hardware
____________________________________________________________________________
Technical Specification: GTR Page 9 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
ASTM-B 231-81 Concentric - lay - stranded, aluminum 1350 conductors
ASTM-B 221 Aluminum - Alloy extruded bar, road, wire, shape
ASTM-B 236-83 Aluminum bars for electrical purpose (Bus-bars)
ASTM-B 317-83 Aluminum-Alloy extruded bar, rod, pipe and structural shapes for
electrical purposes (Bus Conductors)
Batteries
IS:1651 Stationary Cells and Batteries, Lead-Acid Type (with Tubular
Positive Plates)
IS:1652 Stationary Cells and Batteries, Lead-Acid Type (with Plante
Positive Plates)
IS:1146 Rubber and Plastic Containers for Lead-Acid Storage Batteries
IS:6071 Synthetic Separators for Lead-Acid Batteries
IS:266 Specification for Sulphuric Acid
IS:1069 Specification for Water for Storage Batteries
IS:3116 Specification for Sealing Compound for Lead-Acid Batteries
IS:1248 Indicating Instruments
IS:10918 Vented type nickel Cadmium Batteries
IEC:60896-21&22 Lead Acid Batteries Valve Regulated types – Methods of Tests &
Requirements
IEC: 60623 Vented type nickel Cadmium Batteries
IEC:60622 Secondary Cells & Batteries – Sealed Ni-Cd rechargeable single
cell
IEC:60623 Secondary Cells & Batteries – Vented Ni-Cd rechargeable single
cell
IEC:60896-11 Stationary Lead Acid Batteries – Vented Type – General
requirements & method of tests
IEEE-485 Recommended practices for sizing of Lead Acid Batteries
IEEE-1115 Sizing of Ni-Cd Batteries
IEEE-1187 Recommended practices for design & installation of VRLA
Batteries
IEEE-1188 Recommended practices for design & installation of VRLA
Batteries
IEEE-1189 Guide for selection of VRLA Batteries
Battery Charger
IS:3895 Mono-crystalline Semiconductor Rectifier Cells and Stacks
IS:4540 Mono-crystalline Semiconductor Rectifier Assemblies and
Equipment
IS:6619 Safety Code for Semiconductor Rectifier Equipment
IS:2026 Power Transformers
IS:2959 AC Contactors for Voltages not Exceeding 1000 Volts
____________________________________________________________________________
Technical Specification: GTR Page 10 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
IS:1248 Indicating Instruments
IS:2208 HRC Fuses
IS:13947 (Part-3) Air break switches, air break disconnectors & fuse combination
units for voltage not exceeding 1000V AC or 1200V DC
IS:2147 Degree of protection provided by enclosures for low voltage
switchgear and control gear
IS:6005 Code of practice for phosphating of Iron and Steel
IS:3231 Electrical relays for power system protection
IS:3842 Electrical relay for AC Systems
IS:5 Colours for ready mix paint
IEEE-484 Recommended Design for installation design and installation of
large lead storage batteries for generating stations and
substations
IEEE-485 Sizing large lead storage batteries for generating stations and
substations
Wires and cables
ASTMD-2863 Measuring the minimum oxygen concentration to support candle
like combustion of plastics (oxygen index)
IS-694 PVC insulated cables for working voltages upto and including
1100 Volts
IS-1255 Code of practice for installation and maintenance of power
cables, upto and including 33 kV rating
IS-1554 (P1 and P2) PVC insulated (heavy duty) electric cables (part 1) for working
voltage upto and including 1100 V
Part (2) for working voltage from 3.3 kV upto and including 11kV
IS:1753 Aluminium conductor for insulated cables
IS:2982 Copper Conductor in insulated cables
IS-3961 (P1 to P5) Recommended current ratings for cables
IS-3975 Mild steel wires, formed wires and tapes for armouring of cables
IS-5831 PVC insulating and sheath of electric cables
IS-6380 Elastometric insulating and sheath of electric cables
IS-7098 Cross linked polyethylene insulated PVC sheathed cables for
working voltage upto and including 1100 volts
IS-7098 Cross-linked polyethyle insulated PVC sheathed cables for
working voltage from 3.3kV upto and including 33 kV
IS-8130 Conductors for insulated electrical cables and flexible cords
IS-1753 Aluminum Conductors for insulated cables
IS-10418 Specification for drums for electric cables
IEC-60096 (part 0 to p4) Radio Frequency cables
IEC-60183 Guide to the Selection of High Voltage Cables
IEC-60189 (P1 to P7) Low frequency cables and wires with PVC insulation and PVC
sheath
____________________________________________________________________________
Technical Specification: GTR Page 11 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
IEC-60227 (P1 to P7) Polyvinyl Chloride insulated cables of rated voltages up to and
including 450/750V
IEC-60228 Conductors of insulated cables
IEC-60230 Impulse tests on cables and their accessories
IEC-60287 (P1 to P3) Calculation of the continuous current rating of cables (100% load
factor)
IEC-60304 Standard colours for insulation for low-frequency cables and
wires
IEC-60331 Fire resisting characteristics of Electric cables
IEC-60332 (P1 to P3) Tests on electric cables under fire conditions
IEC-60502 Extruded solid dielectric insulated power cables for rated
voltages from 1 kV upto to 30 kV
IEC-754 (P1 and P2) Tests on gases evolved during combustion of electric cables
AIR conditioning and ventilation
IS-659 Safety code for air conditioning
IS-660 Safety code for Mechanical Refrigeration
ARI:520 Standard for Positive Displacement Refrigeration Compressor
and Condensing Units
IS:4503 Shell and tube type heat exchanger
ASHRAE-24 Method of testing for rating of liquid coolers
ANSI-B-31.5 Refrigeration Piping
IS:2062 Steel for general structural purposes
IS:655 Specification for Metal Air Dust
IS:277 Specification for Galvanised Steel Sheets
IS-737 Specification for Wrought Aluminium and Aluminium Sheet &
Strip
IS-1079 Hot rolled cast steel sheet & strip
IS-3588 Specification for Electrical Axial Flow Fans
IS-2312 Propeller Type AC Ventilation Fans
BS-848 Methods of Performance Test for Fans
BS-6540 Part-I Air Filters used in Air Conditioning and General Ventilation
BS-3928 Sodium Flame Test for Air Filters (Other than for Air Supply to
I.C. Engines and Compressors)
US-PED-2098 Method of cold DOP & hot DOP test
MIL-STD-282 DOP smoke penetration method
ASHRAE-52 Air cleaning device used in general ventilation for removing
particle matter
IS:3069 Glossary of Terms, Symbols and Units Relating to Thermal
Insulation Materials
IS:4671 Expanded Polystyrene for Thermal Insulation Purposes
IS:8183 Bonded Mineral Wool
IS:3346 Evaluation of Thermal Conductivity properties by means of
____________________________________________________________________________
Technical Specification: GTR Page 12 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
guarded hot plate method
ASTM-C-591-69 Standard specification for rigid preformed cellular urethane
thermal insulation
IS:4894 Centrifugal Fans
BS:848 Method of Performance Test for Centrifugal Fans
IS:325 Induction motors, three-phase
IS:4722 Rotating electrical machines
IS:1231 Three phase foot mounted Induction motors, dimensions of
IS:2233 Designations of types of construction and mounting
arrangements of rotating electrical machines
IS:2254 Vertical shaft motors for pumps, dimensions of
IS:7816 Guide for testing insulation resistance of rotating machines
IS:4029 Guide for testing three phase induction motors
IS: 4729 Rotating electrical machines, vibration of, Measurement and
evaluation of
IS:4691 Degree of protection provided by enclosures for rotating
electrical machinery
IS:7572 Guide for testing single-phase ac motors
IS:2148 Flame proof enclosure for electrical apparatus
BS:4999(Part-51) Noise levels
Galvanizing
IS-209 Zinc Ingot
IS-2629 Recommended Practice for Hot-Dip galvanizing on iron and steel
IS-2633 Methods for testing uniformity of coating of zinc coated articles
ASTM-A-123 Specification for zinc (Hot Galavanizing) Coatings, on products
Fabricated from rolled, pressed and forged steel shapes, plates,
bars and strips
ASTM-A-121-77 Zinc-coated (Galvanized) steel barbed wire
Painting
IS-6005 Code of practice for phosphating of iron and steel
ANSI-Z551 Gray finishes for industrial apparatus and equipment
SSPEC Steel structure painting council
Fire protection system
-- Fire protection manual issued by tariff advisory committee (TAC)
of India
HORIZONTAL CENTRIFUGAL PUMPS
IS:1520 Horizontal centrifugal pumps for clear, cold and fresh water
IS:9137 Code for acceptance test for centrifugal & axial pumps
IS:5120 Technical requirement – Rotodynamic special purpose pumps
API-610 Centrifugal pumps for general services
Hydraulic Institutes Standards
____________________________________________________________________________
Technical Specification: GTR Page 13 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
BS:599 Methods of testing pumps
PTC-8.2 Power Test Codes - Centrifugal pumps
DIESEL ENGINES
IS:10000 Methods of tests for internal combustion engines
IS:10002 Specification for performance requirements for constant speed
compression ignition engines for general purposes (above 20
kW)
BS:5514 The performance of reciprocating compression ignition (Diesel)
engines, utilizing liquid fuel only, for general purposes
ISO:3046 Reciprocating internal combustion engines performance
IS:554 Dimensions for pipe threads where pressure tight joints are
required on threads
ASME Power Test Code Internal combustion engine PTC-17
-- Codes of Diesel Engine Manufacturer’s Association, USA
PIPING VALVES & SPECIALITIES
IS:636 Non percolating flexible fire-fighting delivery hose
IS:638 Sheet rubber jointing and rubber inserting jointing
IS:778 Gun metal gate, globe and check valves for general purpose
IS:780 Sluice valves for water works purposes (50 to 300 mm)
IS:901 Couplings, double male and double female instantaneous pattern
for fire fighting
IS:902 Suction hose couplings for fire-fighting purposes
IS:903 Fire hose delivery couplings branch pipe nozzles and nozzle
spanner
IS:1538 Cast iron fittings for pressure pipes for water, gas and sewage
IS:1903 Ball valve (horizontal plunger type) including floats for water
supply purposes
IS:2062 SP for weldable structural steel
IS:2379 Colour Code for the identification of pipelines
IS:2643 Dimensions of pipe threads for fastening purposes
IS:2685 Code of Practice for selection, installation and maintenance of
sluice valves
IS:2906 Sluice valves for water-works purposes (350 to 1200 mm size)
IS:3582 Basket strainers for fire-fighting purposes (cylindrical type)
IS:3589 Electrically welded steel pipes for water, gas and sewage (150 to
2000 mm nominal diameter)
IS:4038 Foot valves for water works purposes
IS:4927 Unlined flax canvas hose for fire fighting
IS:5290 Landing valves (internal hydrant)
IS:5312 (Part-I) Swing check type reflex (non-return) valves
IS:5306 Code of practice for fire extinguishing installations and
equipment on premises
____________________________________________________________________________
Technical Specification: GTR Page 14 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
Part-I Hydrant systems, hose reels and foam inlets
Part-II Sprinkler systems
BS:5150 Specification for cast iron gate valves
MOTORS & ANNUNCIATION PANELS
IS:325 Three phase induction motors
IS:900 Code of practice for installation and maintenance of induction
motors
IS:996 Single phase small AC and universal electric motors
IS:1231 Dimensions of three phase foot mounted induction motors
IS:2148 Flame proof enclosure of electrical apparatus
IS:2223 Dimensions of flange mounted AC induction motors
IS:2253 Designations for types of construction and mounting
arrangements of rotating electrical machines
IS:2254 Dimensions of vertical shaft motors for pumps
IS:3202 Code of practice for climate proofing of electrical equipment
IS:4029 Guide for testing three phase induction motors
IS:4691 Degree of protection provided by enclosure for rotating electrical
machinery
IS:4722 Rotating electrical machines
IS:4729 Measurement and evaluation of vibration of rotating electrical
machines
IS:5572 Classification of hazardous areas for electrical
(Part-I) installations (Areas having gases and vapours)
IS:6362 Designation of methods of cooling for rotating electrical
machines
IS:6381 Construction and testing of electrical apparatus with type of
protection ‘e’
IS:7816 Guide for testing insulation for rotating machine
IS:4064 Air break switches
IEC DOCUMENT 2 Three Phase Induction Motor
(Control Office) 432
VDE 0530 Part I/66 Three Phase Induction Motor
IS:9224 (Part-II) HRC Fuses
IS:6875 Push Button and Control Switches
IS:694 PVC Insulated cables
IS:1248 Indicating instruments
IS:375 Auxiliary wiring & busbar markings
IS:2147 Degree of protection
IS:5 Colour Relay and timers
IS:2959 Contactors
PG Test Procedures
____________________________________________________________________________
Technical Specification: GTR Page 15 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
NFPA-13 Standard for the installation of sprinkler system
NFPA-15 Standard for water spray fixed system for the fire protection
NFPA-12A Standard for Halong 1301 Fire Extinguishing System
NFPA-72E Standard on Automatic Fire Detectors
-- Fire Protection Manual by TAC (Latest Edition)
NFPA-12 Standard on Carbon dioxide extinguisher systems
IS:3034 Fire of industrial building
-- Electrical generating and distributing stations code of practice
IS:2878 CO2 (Carbon dioxide) Type Extinguisher
IS:2171 DC (Dry Chemical Powder) type
IS:940 Pressurised Water Type
D.G. SET
IS:10002 Specification for performance requirements for constant speed
compression ignition (diesel engine) for general purposes
IS:10000 Method of tests for internal combustion engines
IS:4722 Rotating electrical machines-specification
IS:12063 Degree of protection provided by enclosures
IS:12065 Permissible limit of noise levels for rotating electrical machines
-- Indian Explosive Act 1932
Steel structures
IS-228 (1992) Method of Chemical Analysis of pig iron, cast iron and plain
carbon and low alloy steels.
IS-802 (P1 to 3) Code of practice for use of structural steel in overhead
transmission line towers
IS-806 Code of practice for use of steel tubes in general building
construction
IS-808 Dimensions for hot rolled steel beam, column channel and angle
sections
IS-814 Covered electrodes for manual arc welding of carbon of carbon
manganese steel
IS-816 Code of Practice for use of metal arc welding for general
construction in Mild steel
IS-817 Code of practice for training and testing of metal arc welders.
Part 1 : Manual Metal arc welding
IS-875 (P1 to P4) Code of practice for design loads (other than earthquake) for
buildings and structures
IS-1161 Steel tubes for structural purposes
IS-1182 Recommended practice for radiographic examination of fusion
welded butt joints in steel plates
IS-1363 (P1 to P3) Hexagonal head bolts, screws & nuts of products grade C
IS-1364 Hexagon head bolts, screws and nuts of product grades A and B
IS-1367 (P1 to P18) Technical supply condition for threaded steel fasteners
____________________________________________________________________________
Technical Specification: GTR Page 16 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
IS-1599 Methods for bend test
IS-1608 Method for tensile testing of steel products
IS-1893 Criteria for earthquake resistant design of structures
IS-1978 Line Pipe
IS-2062 Steel for general structural purposes
IS-2595 Code of practice for Radiographic testing
IS-3063 Single coil rectangular section spring washers for bolts, nuts and
screws
IS-3664 Code of practice for ultrasonic pulse echo testing by contact and
immersion methods
IS-7205 Safety code for erection of structural steel work
IS-9595 Recommendations for metal arc welding of carbon and carbon
manganese steels
ANSI-B18.2.1 Inch series square and Hexagonal bolts and screws
ANSI-B18.2.2 Square and hexagonal nuts
ANSI-G8.14 Round head bolts
ASTM-A6 Specification for General Requirements for rolled steel plates,
shapes, sheet piling and bars of structural use
ASTM-A36 Specifications of structural steel
ASTM-A47 Specification for malleable iron castings
ASTM-A143 Practice for safeguarding against embilement of Hot Galvanized
structural steel products and procedure for detaching
embrilement
ASTM-A242 Specification for high strength low alloy structural steel
ASTM-A283 Specification for low and intermediate tensile strength carbon
steel plates of structural quality
ASTM-A394 Specification for Galvanized steel transmission tower bolts and
nuts
ASTM-441 Specification for High strength low alloy structural manganese
vanadium steel
ASTM-A572 Specification for High strength low alloy colombium-Vanadium
steel of structural quality
AWS D1-0 Code for welding in building construction welding inspection
AWS D1-1 Structural welding code
AISC American institute of steel construction
NEMA-CG1 Manufactured graphite electrodes
Piping and pressure vessels
IS-1239 (Part 1 and 2) Mild steel tubes, tubulars and other wrought steel fittings
IS -3589 Seamless Electrically welded steel pipes for water, gas and
sewage
IS-6392 Steel pipe flanges
ASME Boiler and pressure vessel code
____________________________________________________________________________
Technical Specification: GTR Page 17 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
ASTM-A120 Specification for pipe steel, black and hot dipped, zinc-coated
(Galvanized) welded and seamless steel pipe for ordinary use
ASTM-A53 Specification for pipe, steel, black, and hot-dipped, zinc coated
welded and seamless
ASTM-A106 Seamless carbon steel pipe for high temperature service
ASTM-A284 Low and intermediate tensile strength carbon-silicon steel plates
for machine parts and general construction
ASTM-A234 Pipe fittings of wrought carbon steel and alloy steel for moderate
and elevated temperatures
ASTM-S181 Specification for forgings, carbon steel for general purpose piping
ASTM-A105 Forgings, carbon steel for piping components
ASTM-A307 Carbon steel externally threated standard fasteners
ASTM-A193 Alloy steel and stainless steel bolting materials for high
temperature service
ASTM-A345 Flat rolled electrical steel for magnetic applications
ASTM-A197 Cupola malleable iron
ANSI-B2.1 Pipe threads (Except dry seal)
ANSI-B16.1 Cast iron pipe flangesand glanged fitting. Class 25, 125, 250 and
800
ANSI-B16.1 Malleable iron threaded fittings, class 150 and 300
ANSI-B16.5 Pipe flanges and flanged fittings, steel nickel alloy and other
special alloys
ANSI-B16.9 Factory-made wrought steel butt welding fittings
ANSI-B16.11 Forged steel fittings, socket-welding and threaded
ANSI-B16.14 Ferrous pipe plug, bushings and locknuts with piple threads
ANSI-B16.25 Butt welding ends
ANSI-B18.1.1 Fire hose couplings screw thread
ANSI-B18.2.1 Inch series square and hexagonal bolts and screws
ANSI-B18.2.2 Square and hexagonal nuts
NSI-B18.21.1 Lock washers
ANSI-B18.21.2 Plain washers
ANSI-B31.1 Power piping
ANSI-B36.10 Welded and seamless wrought steel pipe
ANSI-B36.9 Stainless steel pipe
Other civil works standards
IS-269 33 grade ordinary portland cement
IS2721 Galvanized steel chain link fence fabric
IS-278 Galvanized steel barbed wire for fencing
IS-383 Coarse and fine aggregates from natural sources for concrete
IS-432 (P1 and P2) Mild steel and medium tensile steel bars and hard-dawn steel
wire for concrete reinforcement
____________________________________________________________________________
Technical Specification: GTR Page 18 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
IS-456 Code of practice for plain and reinforced concrete
IS-516 Method of test for strength of concrete
IS-800 Code of practice for general construction in steel
IS-806 Steel tubes for structural purposes
IS-1172 Basic requirements for water supply, drainage and sanitation
IS-1199 Methods of sampling and analysis of concrete
IS-1566 Hard-dawn steel wire fabric for concrete reinforcement
IS-1742 Code of Practice for Building drainage
IS-1785 Plain hard-drawn steel wire for pre-stressed concrete
IS-1786 High strength deformed Steel Bars and wires for concrete
reinforcement
IS-1811 Methods of sampling Foundry sands
IS-1893 Criteria for earthquake resistant design of structures
IS-2062 Steel for general structural purposes
IS-2064 Selection, installation and maintenance of sanitary appliances-
code of practices
IS-2065 Code of practice for water supply in buildings
IS-2090 High tension steel bars used in pre-stressed concrete
IS-2140 Standard Galvanized steel wire for fencing
IS-2470 (P1 & P2) Code of practice for installation of septic tanks
IS-2514 Concrete vibrating tables
IS-2645 Integral cement waterproofing compounds
IS-3025 (Part 1 to Methods of sampling and test (Physical and chemical) for water
Part 48) and waste water
IS-4091 Code of practice for design and construction of foundations for
transmission line towers and poles
IS-4111 (Part 1 to P5) Code of practice for ancillary structures in sewerage system
IS-4990 Plywood for concrete shuttering work
IS-5600 Sewage and drainage pumps
National building code of India 1970
USBR E12 Earth Manual by United States Department of the interior Bureau
of Reclamation
ASTM-A392-81 Zinc/Coated steel chain link fence fabric
ASTM-D1557-80 test for moisture-density relation of soils using 10-lb (4.5 kg)
rame land 18-in. (457 mm) Drop
ASTM-D1586(1967) Penetration Test and Split-Barrel Sampling of Soils
ASTM-D2049-69 Test Method for Relative Density of Cohesionless Soils
ASTM-D2435 Test method for Unconsolidated, (1982)
Undrained Strengths of Cohesive Soils in Triaxial Compression
BS-5075 Specification for accelerating Part I Admixtures, Retarding
Admixtures and Water Reducing Admixtures
____________________________________________________________________________
Technical Specification: GTR Page 19 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
CPWD Latest CPWD specifications
ACSR MOOSE CONDUCTOR
IS:6745 Methods for Determination of
BS:443-1969 Mass of zinc coating on zinc
coated Iron and Steel Articles
IS:8263 Methods for Radio Interference
IEC:437-1973 Test on High Voltage Insulators
NEMA:107-1964
CISPR
IS:209, BS:3436-1961 Zinc Ingot
IS:398 Part - V Aluminum Conductors for Overhead Transmission Purposes
IEC:209-1966
BS:215(Part-II), Aluminium Conductors galvanized steel reinforced extra high
IEC:209-1966 voltage (400 kV and above)
IS:1778, BS:1559-1949 Reels and Drums for Bare Conductors
IS:1521, ISO/R89-1959 Method for Tensile Testing of steel wire
IS:2629 Recommended practice for Hot dip Galvanising on Iron and Steel
IS:2633 Method for Testing Uniformity of coating of zinc Coated Articles
IS:4826/ Hot dip galvanised coatings on round steel wires
ASTMA-472-729
GALVANISED STEEL EARTHWIRE
IS:1521, ISO/R:89-1959 Method for Tensile Testing of Steel Wire
IS:1778 Reels and Drums for Bare Conductors
IS:2629 Recommended practice for Hot Dip Galvanising on Iron and Steel
IS:2633 Methods for testing Uniformity of Coating of Zinc Coated Articles
IS:4826/ ASTM: Hot dip Galvanised Coatings on Round Steel Wires
A 475-72a
BS:443-1969
IS:6745/ BS:443-1969 Method for Determination of mass of Zinc Coating on Zinc coated
Iron and Steel Articles.
IS:209/ BS:3463-1961 Zinc ingot
IS:398 (Pt. I to P5:1992)/ Aluminum Conductors for overhead transmission purposes
BS:215 (Part-II
Lighting Fixtures and Accessories
IS:1913 General and safety requirements for electric lighting fittings
IS:3528 Water proof electric lighting fittings
IS:4012 Dust proof electric lighting fittings
IS:4013 Dust tight proof electric lighting fittings
IS:10322 Industrial lighting fittings with metal reflectors
IS:10322 Industrial lighting fittings with plastic reflectors
IS:2206 Well glass lighting fittings for use under ground in mines (non-
____________________________________________________________________________
Technical Specification: GTR Page 20 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
flameproof type)
IS:10322 Specification for flood light
IS:10322 Specification for decorative lighting outfits
IS:10322 Luminaries for street lighting
IS:2418 Tubular fluorescent lamps
IS:9900 High pressure mercury vapour lamps
IS:1258 Specification for Bayonet lamp fluorescent lamp
IS:3323 Bi-pin lamp holder tubular fluorescent lamps
IS:1534 Ballasts for use in fluorescent lighting fittings.
(Part-I)
IS:1569 Capacitors for use in fluorescent lighting fittings
IS:2215 Starters for fluorescent lamps
IS:3324 Holders for starters for tubular fluorescent lamps
IS:418 GLS lamps
IS:3553 Water tight electric fittings
IS:2713 Tubular steel poles
IS:280 MS wire for general engg. Purposes
Conduits, Accessories and Junction Boxes
IS:9537 Rigid steel conduits for electrical wiring
IS:3480 Flexible steel conduits for electrical wiring
IS:2667 Fittings for rigid steel conduits for electrical wiring
IS:3837 Accessories for rigid steel conduits for electrical wiring
IS:4649 Adaptors for flexible steel conduits
IS:5133 Steel and Cast Iron Boxes
IS:2629 Hot dip galvanising of Iron & Steel
Lighting Panels
IS:13947 LV Switchgear and Control gear(Part 1 to 5)
IS:8828 Circuit breakers for over current protection for house hold and
similar installations
IS:5 Ready mix paints
IS:2551 Danger notice plates
IS:2705 Current transformers
IS:9224 HRC Cartridge fuse links for voltage above 650V(Part-2)
IS:5082 Wrought aluminium and Al. alloys, bars, rods, tubes and sections
for electrical purposes
IS:8623 Factory built Assemblies of Switchgear and Control Gear for
voltages upto and including 1000V AC and 1200V DC
IS:1248 Direct Acting electrical indicating instruments
Electrical Installation
IS:1293 3 pin plug
IS:371 Two to three ceiling roses
____________________________________________________________________________
Technical Specification: GTR Page 21 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
IS:3854 Switches for domestic and similar purposes
IS:5216 Guide for safety procedures and practices in electrical work
IS:732 Code of practice for electrical wiring installation (system voltage
not exceeding 650 Volts.)
IS:3043 Code of practice for earthing
IS:3646 Code of practice of interior illumination part II & III
IS:1944 Code of practice for lighting of public through fares
IS:5571 Guide for selection of electrical equipment for hazardous areas
IS:800 Code of practice for use of structural steel in general building
construction
IS:2633 Methods of Testing uniformity of coating on zinc coated articles
IS:6005 Code of practice for phosphating iron and steel
INDIAN ELECTRICITY ACT
INDIAN ELECTRICITY RULES
LT SWITCHGEAR
IS:8623 (Part-I) Specification for low voltage switchgear and control gear
assemblies
IS:13947 (Part-I) Specification for low voltage switchgear and control gear, Part 1
General Rules
IS:13947 (part-2) Specification for low voltage switchgear and control gear, Part 2
circuit breakers
IS:13947 (part-3) Specification for low voltage switchgear and control gear. Part 3
Switches, Disconnectors, Switch-disconnectors and fuse
combination units
IS:13947 (part-4) Specification for low voltage switchgear and control gear.
Part 4 Contactors and motors starters
IS:13947 (part-5) Specification for low voltage switchgear and control gear.
Part 5 Control-circuit devices and switching elements
IS:13947 (part-6) Specification for low voltage switchgear and control gear.
Part 6 Multiple function switching devices
IS:13947 (part-7) Specification for low voltage switchgear and control gear.
Part 7 Ancillary equipments
IS:12063 Degree of protection provided by enclosures
IS:2705 Current Transformers
IS:3156 Voltage Transformers
IS:3231 Electrical relays for power system protection
IS:1248 Electrical indicating instruments
IS:722 AC Electricity meters
IS:5578 Guide for Marking of insulated conductors of apparatus terminals
IS:13703 (part 1) Low voltage fuses for voltage not exceeding 1000V AC or 1500V
DC Part 1 General Requirements
IS:13703 (part 2) Low voltage fuses for voltage not exceeding 1000V AC or 1500V
DC Part 2 Fuses for use of authorized persons
____________________________________________________________________________
Technical Specification: GTR Page 22 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-C
CODES TITLE
IS:6005 Code of practice of phosphating iron and steel
IS:5082 Wrought Aluminum and Aluminum alloys for electrical purposes
IS:2633 Hot dip galvanising
____________________________________________________________________________
Technical Specification: GTR Page 23 of 23 (Annexure-C)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-D
B. CIVIL DRAWINGS/DOCUMENTS
C. DRAWINGS/DOCUMENTS OF EQUIPMENT
(1) Circuit Breaker, Isolator, CT, CVT, IVT, Surge Arrestor, Bus Post Insulator
- Drawing, GTP and Type test Reports
(2) Control and Relay Panels
- GTP and Type test Reports
(3) Substation Automation System (SAS)
- GTP and Type test Reports
____________________________________________________________________________
Technical Specification: GTR Page 1 of 2 (Annexure-D)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-D
E. DRAWINGS/DOCUMENTS OF REACTOR
NOTES:-
1. The list of drawings/ documents mentioned above is a standard list. Some of the items may
not be applicable and need not to be referred for a particular substation package.
2. In case type tests are to be repeated/conducted, then approval of type test reports is not
required at this stage.
3. Category-II approved drawings shall also be considered for release of second/engineering
advance.
____________________________________________________________________________
Technical Specification: GTR Page 2 of 2 (Annexure-D)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-E
4.00 AUTOTRANSFORMER
4.01 Design Review A
4.02 Guaranteed Technical Particulars A
4.03 Outline General Arrangement Drawing with Bill of material (OGA parts list) A
4.04 Foundation Plan A
4.05 Over Fluxing withstand duration curve R
4.06 Hysteresis Characteristics & specific loss vs flux density curve of iron core R
4.07 General Arrangement & Control Schematic of OLTC along with write-up A
4.08 General Arrangement & Control Schematic of Marshalling Box, Common A
Marshalling Box and Cooler control cubicle along with write-up
____________________________________________________________________________
Technical Specification: GTR Page 2 of 9 (Annexure-E)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-E
5.00 REACTOR
5.01 Design Review A
5.02 Guaranteed Technical Particulars A
5.03 Outline General Arrangement Drawing with Bill of material (OGA parts list) A
5.04 Foundation Plan A
5.05 General Arrangement & Control Schematic of Marshalling Box, Common A
Marshalling Box along with write-up
5.06 SCADA communication interface of online monitoring equipment A
5.07 Transport Drawing R
5.08 Technical Particulars of Online DGA, Drying system, FO system A
5.09 Outline and control schematic of NIFPS A
5.10 GA & GTP of bushings A
5.11 Earthing Arrangement Drawing (Internal & External) A
5.12 Drawing of Aircell, Conservator & Radiator R
5.13 Conservator & Tank Oil filling procedure plate R
5.14 Magnetization characteristics of Reactor Core and bushing CTs R
5.15 Hysteresis Characteristics & specific loss vs flux density curve of iron core R
5.16 Rating and diagram plate A
5.17 Voltage Ampere curve for Reactor R
5.18 Valve Schedule plate drawing A
5.19 GA of Twin bi-directional roller A
5.20 Instruction Manual R
5.21 Type test Report A
8.00 ISOLATOR
8.01 GA drawing of Isolator with/without earth switch A
8.02 GTP A
8.03 Contact blade assembly (main & earth switch) R
8.04 Terminal pad & hinge contacts R
8.05 GA of MOM – main switch R
8.06 Schematic & wiring drawing for main switch R
8.07 Name plate - details A
8.08 GA of terminal pad A
____________________________________________________________________________
Technical Specification: GTR Page 4 of 9 (Annexure-E)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-E
____________________________________________________________________________
Technical Specification: GTR Page 5 of 9 (Annexure-E)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-E
20.00 ILLUMINATION
20.01 GTP/Catalogue of fittings/fixtures A
20.02 GA drawing of lighting poles/posts A
20.03 GA drawing of Junction box A
20.04 GA drawing of street lighting panel/outdoor/indoor lighting panel A
20.05 GA drawing of Receptacles A
20.06 Schematic drawing of panel/LDBs to fixtures R
21.00 LT SWITCHGEAR
21.01 SLD, GA & Schematic drawings of MSB A
21.02 SLD, GA & Schematic drawings of ACDB A
21.03 SLD, GA & Schematic drawings of 220V DCDB A
21.04 SLD, GA & Schematic drawings of 48V DCDB A
21.05 SLD, GA & Schematic drawings of MLDB A
21.06 SLD, GA & Schematic drawings of ELDB A
21.07 Type Test Reports A
21.08 Instruction Manual R
____________________________________________________________________________
Technical Specification: GTR Page 6 of 9 (Annexure-E)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-E
26.00 DG SET
26.01 GTP A
26.02 Drawings/manuals A
28.00 LT TRANSFORMER
28.01 GTP A
28.02 Drawings A
28.03 Type Test Reports A
____________________________________________________________________________
Technical Specification: GTR Page 8 of 9 (Annexure-E)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-E
NOTES:-
1. In case any additional drawings/documents are required, the same shall also be
submitted during execution of the contract.
2. In case, some drawings as mentioned in the above list are not applicable for the
scope of work, the same shall not be referred to.
____________________________________________________________________________
Technical Specification: GTR Page 9 of 9 (Annexure-E)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
Annexure- F
Assessment report from Contractor for proposed sub-vendor along with following
enclosures (to the extent available):
____________________________________________________________________________
Technical Specification: GTR Page 1 of 1 (Annexure-F)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
Annexure-G
__________________________________________________________________________
Technical Specification: GTR Page 2 of 3 (Annexure-G)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
Annexure-G
Note:
* MICC for test and measuring equipment shall be issued only after actual
verification/demonstration of satisfactory performance at site.
** Though level-2 items, CIP can be issued also on review of TCs and visual
inspection of these items.
__________________________________________________________________________
Technical Specification: GTR Page 3 of 3 (Annexure-G)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-H
RTV Silicone high voltage insulation coating (HVIC)
1.0 General
The scope of work shall include supply, delivery and application of RTV silicone high
voltage insulation coating for Substations at coastal area.
a) The supplied virgin RTV coating material shall have sufficient margin before expiry
of its shelf life (Date of manufacturing shall not be older than two months from
date of delivery). Application of RTV coating material on the equipment after
expiry of its shelf life will not be permitted.
b) All the required materials, tools and tackles, testing equipment, consumables etc.
for application of HVIC coating shall be in the contractor’s scope.
c) Surface preparation: All insulation surfaces of the equipment to be coated shall be
made free from dust, grease, oil and any other foreign material without damaging
the surface. The surface of the equipment shall be made dry before application of
the RTV coating.
d) Preparation/mixing of the virgin RTV coating materials shall be done strictly as per
recommendations of the original manufacturer only.
e) The application of the properly prepared /mixed virgin RTV coating materials shall
be done by certified applicants of original manufacturer only.
f) The coating shall cover complete insulation surface of the equipment.
g) Coated insulation surface of the equipment after full cure shall be smooth and free
from any defect viz. scratches, uneven surface etc.
h) Following tests are to be carried out by the contractor after full care of coatings.
(i) Hydrophobic test on 1-2 coated equipment as per STRI guidelines and the
results shall be HC2 class or better.
(iii) Bonding/adherence test at site: The sample coated insulator shall be put in
water and boiled for 02 hours and removed. The coating shall not exhibit
water blisters at the interface between the insulator surface and the coating.
(iv) High pressure water withstand test at site: A high pressure water wash test
shall be performed on sample coated insulator. The RTV coating shall
withstand the pressure without any damage to it.
i) Any other item which is not specifically mentioned above but are required for
successful completion of the work shall be in this scope of work.
____________________________________________________________________________
Technical Specification: GTR Page 1 of 2 (Annexure-H)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
SECTION-GENERAL TECHNICAL REQUIREMENTS (GTR)
ANNEXURE-H
RTV Silicone high voltage insulation coating (HVIC)
2.0 Technical Requirements
Parameters Requirement
____________________________________________________________________________
Technical Specification: GTR Page 2 of 2 (Annexure-H)
C/ENGG/SPEC/GTR (Rev. No.:-14, Jan’17)
Technical Specification for RTV Silicone high voltage insulation coating (HVIC)
The scope of work shall include supply, transportation and application of RTV silicone rubber high
voltage insulator coating and cleaning/removal of waste from the equipment.
a) All the required materials, tools & tackles, testing equipments including man lift etc. are in the
scope of successful bidders/ contractor.
b) Surface preparation:
All equipment surfaces to be coated should be made free from dust, grease, oil etc. & other
foreign matter. Also the surface meant for application must be dry.
c) The RTV coating supplied for application should be properly mixed before application as per the
recommendations of manufacturer. The coating should cover complete surface and should be
applied in manner that prevents runs, sags, drips, spills etc. The application shall be done by
certified applicant of Manufacturer.
d) Successful bidder/ contractor shall submit the detailed field quality plan for approval. It is not the
intention of this specification to specify completely herein all details and design requirements.
However, the materials offered & work execution shall confirm in all respects to high standards
of engineering and workmanship and be capable of performing in continuous commercial
operation up to guarantee in a manner acceptable to purchaser.
2. CLIMATIC CONDITIONS:
The overall climate is moderate hot, humid, tropical, highly polluted and conducive to rust and fungus
growth. The climatic conditions are prone to wide range of outdoor service conditions.
The latest revision/amendments of the following Codes and Standards shall be applicable for the
equipment/material covered in this Technical Specification. In case of conflict, the
vendor/manufacturer may propose equipment/material conforming to one group of Industry Codes and
Standards quoted hereunder without jeopardizing the requirements of this Technical Specification.
IEC 60243-1 Electric strength of insulating materials - Test methods - Part 1: Tests at
power frequencies
IEC TR 62039 Selection guide for polymeric materials for outdoor use under HV stress
IEC 60250 Recommended methods for the determination of the permittivity and
dielectric dissipation factor of electrical materials at power, audio and radio
frequencies including meter wavelengths
IEC 60587 Electrical insulating materials used under severe ambient conditions - Test
methods for evaluating resistance to tracking and erosion
IEC TS 62073 Guidance on the measurement of hydrophobicity of insulator surfaces
IEC 61621 Dry, solid insulating materials-Resistance test to high - voltage, low -
current arc discharges
IEC 62217 Polymeric HV insulators for indoor and outdoor use-General definitions,
test methods and acceptance criteria
IEC 62631-3-2 Dielectric and resistive properties of solid insulating materials - Part 3-2:
Determination of resistive properties (DC methods) - Surface resistance and
surface resistivity
IEEE Std 957 IEEE Guide for Cleaning Insulators
IEEE Std 1523 IEEE Guide for the Application, Maintenance and Evaluation of Room
Temperature Vulcanizing (RTV) Silicone Rubber Coatings for Outdoor
Insulation Applications.
Technical Specification for RTV Silicone high voltage insulation coating (HVIC)
ASTM D149-09 Standard Test Method for Dielectric Breakdown Voltage and Dielectric
Strength of Solid Electrical Insulating Materials at Commercial Power
Frequencies
ASTM D150-11 Standard Test Methods for AC Loss Characteristics and Permittivity
(Dielectric Constant) of Solid Electrical Insulation
ASTM D257-14 Standard Test Methods for DC Resistance or Conductance of Insulating
Materials
ASTM D495-14 Standard Test Method for High - Voltage, Low - Current, Dry Arc
Resistance of Solid Electrical Insulation
CEA LWIWG-02 (1996) Line Post Composite Insulator for Overhead Distribution Lines
4. Technical Parameters
4.1 RTV Silicon compound in its liquid form shall have the following properties:
4.2 RTV Silicon coating after cured form shall have the following properties:
Parameters Requirement
Application Area Glass, Porcelain, station insulators, as well as
bushing, instrument transformers and related
devices
Full cure time ≥ 24 hours
Coating thickness 500 microns + 10% tolerance,
dry film thickness
Dielectric Strength ≥ 20 kV/mm
Volume Resistivity ≥ 1.0*10^12 ohm.m
Tracking and Erosion test 1000 Hours
Min. Salinity Level withstood during “Artificial >160 kg/m^3
Pollution Test using Salt Fog Method”
Hydrophobic Recovery Test HC2 or HC1
Method of Application Airless Spray
Dry Arc resistance Tract ≥ 140 seconds
Burn Out ≥ 420 seconds
Tracking and Erosion (IEC 60587, Method 1: Class 1A 4.5kV or better
Application of constant tracking voltage)
Primer Required No primer material shall be allowed
Resistant to Marine salt fog, Water, Industrial (cement dust, fly
ash, acid emission etc.), Rough Weather
Conditions
Other Properties Non Hazardous to environment, surface after full
cure shall be smooth
Technical Specification for RTV Silicone high voltage insulation coating (HVIC)
4.3 Materials
4.3.1 The RTV Silicone high voltage insulation coating shall be ultraviolet (UV) radiation exposure resistant.
The finished product shall withstand the adverse atmospheric conditions due to weather, proximity to
the coast, fumes, ozone, acids (particularly nitric acid in the coastal areas and sulphuric acid in the oil
field areas), bases/alkalis, and hydrocarbon components, dust or rapid changes to air temperature
(temperature extremes). There shall not be significant material degradation such as development of
surface cracks and unacceptable increase in surface hardness etc.
4.3.2 The RTV Silicone high voltage insulation coating shall be resistant to atmospheric and chemical
degradation. Salt air, airborne pollutants, industrial pollutants such as cement dust, sulphur, rain and
humidity shall not result in flashover on the coating.
4.3.3 The RTV Silicone high voltage insulation coating shall be resistant to arcing and corona. The Coating
shall exhibit high tracking resistance to reduce damage during salt-storms (storms arising from the sea)
or other severe contamination events. The track resistance of the RTV Silicone Rubber Insulator
Coating material shall meet the requirements of IEC 60587, Method 1, Class 1A 4.5kV.
4.3.5 The RTV Silicone high voltage insulation coating shall be a single component, ready-to-use after
simple mixing. It shall not require excessive mixing/shaking and thinning/dilution before use. The
Coating shall be moisture curable at room temperature.
4.3.6 The RTV Silicone high voltage insulation coating shall exhibit long-term water repellency and
hydrophobicity.
4.3.7 The RTV Silicone high voltage insulation coating shall not require use of any primer on the ceramic
insulators for adhesion purposes.
4.3.8 The RTV Silicone high voltage insulation coating shall be easy to be reapplied. The Coating shall have
excellent arc resistance, excellent unprimed adhesion, easy to apply and spray-able as well as paint-
able.
4.3.9 The RTV Silicone high voltage insulation coating shall have a minimum 12 months shelf life, which
shall effect from the date of manufacturing. The manufacturer shall submit the warranty to this effect.
The expiry date shall be marked on the containers. The remaining shelf life of the material shall be at
least six (6) months when delivered to site. The coating shall be supplied in cans weighing not more
than 25kg.
4.4.1 The RTV Silicone high voltage insulation coating shall be capable of withstanding high-pressure water
power washing. To prove this property, a power wash test shall be performed per requirements stated
hereafter in this standard.
4.4.2 The RTV Silicone high voltage insulation coating shall protect the ceramic insulators (porcelain and
glass) against flashovers caused by pollution.
4.4.3 The manufacturer shall advise/recommend suitable method of application and submit written
application instructions and shall suggest suitable equipment set-up (size of pump and compressors,
etc.) and the compatibility of his product to be reapplied on the RTV coating from other manufacturers.
4.4.4 The warranty for RTV coating on the equipments shall be for a period of 5 years.
Technical Specification for RTV Silicone high voltage insulation coating (HVIC)
4.5 Markings
The packing and expiry dates of coating shall be labeled on the coating cans. The expiry date shall be
considered from the packaging date and not from the date of shipment of the coating.
The cans shall be marked for “flammable” or “non-flammable” depending upon the type of solvent
used for the dispersion of the coating.
5.0 TESTS
All test results shall be provided for review and acceptance by customer.
5.1.1 Type tests as prescribed in relevant standards shall be performed on RTV coated sample tiles or RTV
coated insulators as applicable to verify the suitability of the design, materials and method of
manufacture. Testing shall include, but not limited to following. These tests shall be performed only on
the new design of RTV silicone high voltage insulation coating. The test reports shall be submitted
from tests done in a NABL/International accredited lab.
a) Tracking and erosion resistance test (IEC 60587, Method 1, Class 1A 4.5kV). Samples shall
consist of smooth porcelain plates of 6mm (± 0.5mm) thickness coated with the thickness of the
material as proposed by the manufacturer for the offered coating. Breaking of porcelain substrate
shall not be allowed.
c) Salt-fog tests
The 1000 hour Tracking and erosion test outlined in IEC-62217 shall be carried out.
Dry arc resistance test shall be carried out as per ASTM D495.
Receding contact angle measurement test shall be performed in accordance with IEC TS 62073.
The test shall be carried out as per IEC:60093. Sample thickness shall be 2mm which can be
obtained by using an open mould casting technique. The minimum volume resistivity as
specified shall be achieved.
h) Artificial Pollution Test in general with IEC 60507 without the pre-condition test.
Adhesion test shall be performed in accordance with Canadian Electric Association (CEA)
specification LWIWG-02 (96) or any other equivalent standard to verify the bonding
characteristics of the RTV Silicone Rubber Coating when applied to ceramic insulators. Three
(3) coated insulators shall be put in water having 0.1% by weight of NaCl and boiled for 100
hours (each sample separately). At the end of boiling, allow each insulator to remain in the water
until the water cools to about 50oC. The coating shall not exhibit any water blisters at the
interface between the insulator surface and the coating.
Technical Specification for RTV Silicone high voltage insulation coating (HVIC)
a) Thickness measurement:
Dry film thickness (DFT) of the coating shall be measured at site on all Equipments randomly at
least at one point of the Equipment.
Adhesion test shall be performed at site in accordance with CEA specification LWIWG-02 (96)
or any other equivalent standard to verify the bonding characteristics of the RTV Silicone
Rubber Coating when applied to ceramic insulators. Three (3) coated insulators shall be put in
water having 0.1% by weight of NaCl and boiled for 2 hours (each sample separately). At the
end of boiling, allow each insulator to remain in the water until the water cools to about 50oC.
The coating shall not exhibit any water blisters at the interface between the insulator surface and
the coating.
A power water wash test shall be performed at site on 5% sample in accordance with IEEE Std
957 to demonstrate that the RTV coated insulators can be power washed without any damage to
RTV coating. The test shall be a water spray of a solid stream through a 6mm diameter nozzle at
3800 kPa for a period of 10 (ten) minutes. The nozzle of the spray equipment shall be at a
distance of 3m from the insulator surface. There should not be any damage to the coating.
d) Hydrophobicity test :
Hydrophobicity test shall be carried out on virgin material at site on 5% sample on 1-2 coated
equipment as per STRI guidelines and the results shall be HC2 class or better. Hydrophobicity
test shall be carried out after completion of high pressure water withstand test.
TECHNICAL SPECIFICATION
SECTION: SWITCHGEAR-CB
REVISION-11
1) Technical specification, Section: Switchgear, Chapter 765kV CB, Rev.02 and Section:
Switchgear, Chapter CB, Rev.10A are merged to prepare this combined technical
specification section up to 765kV CB.
2) All 765kV & 400kV Circuit Breaker control schematics shall be finalized in such a
way, that it may operate with or without CSD (refer clause 1.6)
4) SF6 gas for main CBs shall be supplied in returnable cylinders (refer clause 5.0)
5) Insulators for Circuit breakers can be of Porcelain/polymer type (refer clause 6.0)
6) Included Indicative platform & ladder drawing for 400kV&765kV CB (refer clause
9.0)
7) Included Plug-in type arrangement for termination of inter pole cables (refer clause
11.0)
9) Some parameters like dielectric, creepage, seismic requirement etc w.r.t CBs are
included (refer clause 16.0)
10) Included Actions required for defects observed during defect liability period (refer
clause 18.0)
Note:
Changes made in this document are shown with bold letters, further major changes
are listed above; however for complete details of changes, please refer the complete
technical specification, Section: Switchgear-CB, REV.11
CONTENTS
1.0 General 4
6.0 Insulators 11
15.0 Tests 19
1.0 GENERAL
1.1 The circuit breakers and accessories shall conform to IEC: 62271-100, IEC:
62271-1 and other relevant IEC standards except to the extent explicitly
modified in the specification and shall also be in accordance with
requirements specified in Section-GTR.
1.3 The circuit breaker shall be complete with operating mechanism, common
marshalling box, piping, inter-pole cables, cable accessories like glands,
terminal blocks, marking ferrules, lugs, pressure gauges, density monitors
(with graduated scale), galvanised support structure, platform with ladder
for CB, their foundation bolts and all other accessories required for carrying
out all the functions of the CB.
1.4 Painting shall be done in line with Section – GTR. Paint shade RAL-7032 or
similar shades can be used for painting. The support structure, platform &
ladder of circuit breaker shall be hot dip galvanised. Exposed hardware items
shall be hot dip galvanised or Electro-galvanised.
1.5 The circuit breakers shall be designed for use in the geographic and
meteorological conditions as given in Section-Project.
1.6 All 765kV & 400kV Circuit Breaker control schematics shall be finalized
in such a way, that it may operate with or without CSD by using a
suitable selector switch irrespective of whether circuit breakers to be
supplied are envisaged along with CSD or not as per bid price schedules.
2.1 The circuit breakers shall be capable of performing their duties without
opening resistors.
2.2 The circuit breaker shall meet the duty requirements for any type of fault or
fault location and also for line switching when used on effectively grounded
system and perform make and break operations as per the stipulated duty
cycles satisfactorily.
800kV & 420kV circuit breakers shall be provided with single step pre-
insertion closing resistors (wherever the requirement of PIR is explicitly
specified in bid price schedules) to limit the switching surges. The
resistance value of pre-insertion resistor and the duration of pre-insertion time
is given in clause 16.0 of this section. The resistor shall have thermal rating
for the following duties:
i) TERMINAL FAULT
Close .... 1 Min .... Open Close Open…..2 min ..... Close ..... 1 Min ........
Open Close Open.
Duty shall be the same as under (i) above. The first, third and fourth closures
are to be on de - energised line while second closing is to be made with lines
against trapped charge of 1.2 p.u. of opposite polarity.
One closing operation under phase opposition, that is with twice the voltage
across the terminals.
iv) No allowance shall be made for heat dissipation of resistor during time
interval between successive closing operations. The resistors and resistor
supports shall perform all these duties without deterioration. Test reports of
resistors proving thermal rating for duties specified above shall be furnished
during detailed engineering. The calculations shall be provided to take care
of the effect of tolerances on resistance values and insertion time.
220/132kV 50 to 200
132/33kV 10 to 50
iii) Clearing short line fault (kilometric faults) with source impedance
behind the bus equivalent to symmetrical fault current specified.
iii) Breaking 25% of the rated fault current at twice rated voltage under
phase opposition condition.
v) Circuit breakers shall be able to switch in and out the shunt reactor
as detailed below:
245kV 25 to 50 2.3
vi) The breakers shall also withstand the voltages specified under clause
16.0 of this section.
a) The CSD shall be designed to operate correctly and satisfactorily with the
excursion of auxiliary A/C & DC voltages and frequency as specified in
section - GTR.
c) The CSD shall have functions for switching ON & OFF the circuit
breakers.
e) The CSD shall also have an adaptive control feature to consider the next
operating time of the breaker in calculation of optimum time of issuing the
switching command. In calculation of next operating time of the breaker,
the CSD must consider all factors that may affect the operating time of the
breaker such as, but not limited to, ambient temperature, control voltage
variation, SF6 gas density variations etc. Schematic drawing for this
purpose shall be provided by the contractor. The accuracy of the operating
time estimation by the controller shall be better than ± 0.5 ms.
f) The CSD should have display facility at the front for the display of
settings and measured values.
g) The CSD shall be PC compatible for the setting of various parameters and
down loading of the settings and measured values, date, time of switching
etc. Window based software for this purpose shall be supplied by the
contractor to be used on the owner’s PC.
h) The controller shall be suitable for current input of 1 ampere from the
secondary of the CTs. and 110 V (Ph to Ph) from the CVTs. The CSD
shall withstand transient and dynamic state values of the current from the
secondary of the CTs and CVTs.
k) The CSD shall also record and monitor the switching operations and
make adjustments to the switching instants to optimize the switching
behavior as necessary. It shall provide self-diagnostic facilities,
signaling of alarms and enable downloading of data captured from
the switching events.
3.1 The total break time as specified under this section shall not be exceeded
under any of the following duties:
i) Test duties T10, T30, T60, T100a, and T100s (with TRV as per IEC:
62271-100)
ii) Short line fault L75, L90 (with TRV as per IEC: 62271-100)
3.2 The total break time of the breaker shall not be exceeded under any duty
conditions specified such as with the combined variation of the trip coil
voltage (70-110%), arc extinguishing medium pressure etc. While furnishing
the proof of the total break time of complete circuit breaker, the effect of non-
simultaneity between contacts within a pole or between poles shall be
brought out to establish guaranteed total break time.
3.3 The values guaranteed shall be supported with the type test reports.
4.1 Contacts
4.1.1 The gap between the open contacts shall be such that it can withstand at least
the rated phase to ground voltage for 8 hours at zero gauge pressure of SF6
gas due to the leakage. The breaker should be able to withstand all dielectric
stresses imposed on it in open condition at lock out pressure continuously (i.e.
2 p.u. across the breaker continuously, for validation of which a power
frequency dielectric with stand test conducted for a duration of at least 15
minutes is acceptable).
4.2 If multi-break interrupters are used, these shall be so designed and augmented
that a uniform voltage distribution is developed across them. Calculations/
4.3 The SF6 Circuit Breaker shall meet the following additional requirements:
a) The circuit breaker shall be single pressure type. The design and
construction of the circuit breaker shall be such that there is a minimum
possibility of gas leakage and entry of moisture. There should not be
any condensation of SF6 gas on the internal insulating surfaces of the
circuit breaker.
d) Each pole shall form an enclosure filled with SF6 gas independent of
two other poles (for 800, 420 & 245 kV CBs) and the SF6 density of
each pole shall be monitored individually. For CBs of voltage class of
145 kV or less, a common SF6 scheme/density monitor shall be
acceptable.
4.5 The CO (Close-open) operation and its timing shall be such as to ensure
complete travel/insertion of the contact during closing operation and
then follow the opening operation.
a) The SF6 gas shall comply with IEC 60376 and shall be suitable in all
respects for use in the switchgear under the operating conditions.
b) The high pressure cylinders in which the SF6 gas is shipped and stored
at site shall comply with requirements of the relevant standards and
regulations. SF6 gas shall be supplied (in returnable cylinders) for
all circuit breakers. However, SF6 gas for spare circuit breakers
and mandatory spare quantity of SF6 gas shall be supplied in non-
returnable cylinders.
c) Test: SF6 gas shall be tested for purity, dew point, air, hydro-soluble
fluorides and water content as per IEC 60376 and test certificates shall
be furnished to Employer indicating all the tests as per IEC 60376 for
each lot of SF6 gas and Material safety datasheet shall be provided. Gas
bottles should be checked for leakage during receipt at site.
6.0 INSULATORS
8.1.2 The operating mechanism box shall be strong, rigid, rebound free and shall
be readily accessible for maintenance.
8.1.3 The mechanism shall be anti-pumping and trip free under every method of
closing.
8.1.4 The mechanism shall be such that the failure of any auxiliary spring will not
prevent tripping and will not cause unwanted trip or closing operation of the
Circuit Breaker
8.1.5 A mechanical indicator shall be provided to show open and close position of
the breaker. It shall be located in a position where it will be visible to a man
standing on the ground level with the mechanism housing closed. An
operation counter shall also be provided in the common marshalling box.
8.1.7 The contractor shall furnish detailed operation and maintenance manual of
the mechanism alongwith the operation manual for the circuit breaker. The
instruction manuals shall contain exploded diagrams with complete storage,
handling, erection, commissioning, troubleshooting, servicing and
overhauling instructions.
8.1.8 Size of common marshalling Box shall be such that adequate space is
available for working in the panel and all wiring shall be routed through
non-inflammable wire troughs with covers.
8.2.1 The close and trip circuits shall be designed to permit use of momentary
contact switches and push buttons.
8.2.2 Each breaker shall be provided with two (2) independent tripping circuits,
pressure switches and coils each to be fed from separate DC sources.
8.2.4 The trip coils shall be suitable for trip circuit supervision during both open
and close position of breaker.
8.2.5 Closing coil and associated circuits shall operate correctly at all values of
voltage between 85% and 110% of the rated voltage. Shunt trip coil and
associated circuits shall operate correctly under all operating conditions of the
circuit breaker up to the rated breaking capacity of the circuit breaker and at
all values of supply voltage between 70% and 110% of rated voltage.
However, even at 50% of rated voltage the breaker shall be able to open. If
additional elements are introduced in the trip coil circuit their successful
operation and reliability for similar applications on outdoor circuit breakers
shall be clearly brought out during detailed engineering.
8.2.6 The 765kV kV, 3-Phase circuit breakers suitable for single phase
switching shall be suitable for taking a spare pole into service in case of
any operational requirement and their marshalling box shall be suitable
for accommodating the additional relays etc. required for changeover
arrangement of all contacts, alarms, signals, indications, interlocks and
lockouts.
8.2.7 In trip and closing circuits, relays/relay contacts shall preferably be used
instead of contactors.
8.2.9 Density Monitor contacts and pressure switch contacts shall be preferably
suitable for direct use as permissive in closing and tripping circuits. The
devices shall provide continuous & automatic monitoring of the state of
the gas as follows:
The density monitor shall be placed suitably inclined in such a way so that the
readings are visible from ground level with or without using binoculars.
Separate contacts have to be used for each of tripping and closing circuits. If
contacts are not suitably rated and multiplying relays are used then fail safe
logic/schemes are to be employed. DC supplies for all auxiliary circuits shall
be monitored and provision shall be made for remote annunciations and
operation lockout in case of D.C. failures. Density monitors are to be so
mounted that the contacts do not change on vibration during operation of
circuit Breaker.
8.2.10 The auxiliary switch of the breaker shall be positively driven by the breaker
operating rod.
c) For 220kV, 132kV & 66kV circuit breakers a suitable platform cum
ladder shall be provided as per manufacturer design.
The circuit breaker terminal pads shall be made up of high quality electrolytic
copper or aluminium and shall be conforming to Australian Standard AS-
2935 or equivalent standard for rated current. The terminal pad shall have
protective covers which shall be removed before interconnections.
11.1 All cables to be used by contractor shall be armoured and shall be as per IS –
1554/ IEC-60502 (1100 Volts Grade). All cables within & between circuit
breaker poles and its marshaling box and up to the controlled switching
device is included in the scope of work. Special cables like screened cable if
required for Circuit Breaker, temperature Transducer/CB Status Signals
for CSD and its associated C&R panel shall be laid in 50mm diameter PVC
pipe. Suitable supports for PVC pipe shall be included in the scope of Supply.
11.2 Only stranded conductor shall be used. Minimum size of the conductor for
inter-pole control wiring shall be 1.5 sq.mm. Copper.
11.3 The cables shall be with oxygen index Minimum 29 and temperature index as
250oC as per relevant standards.
11.4 Separate cables shall be used for AC, DC-I, DC-II and selected DC.
11.6 Vertical run of cables to the operating mechanism box shall be properly
supported by providing the perforated closed type galvanized cable tray
(Cable tray also to be supplied along with the Circuit Breaker) to be
fixed as an integral part of the structures. The load of the cable shall not
be transferred to the mechanism box/plug-in type terminal arrangement
in any circumstances. Hanging or loose run of cable is not permitted.
The drawing of cable tray including fixing arrangement shall be
incorporated in the GA drawing of CB also.
11.7 Wiring shall be done with stud type terminals and ring type lugs. More than
two wires shall not be connected on each side of terminal.
12.1 Following is list of some of the major fittings and accessories to be furnished
by Contractor in the common marshalling box. Number and exact location
of these parts shall be indicated in the drawing.
v) Fuses/MCBs as required.
vi) The number of terminals provided shall be adequate enough to wire out
all contacts and control circuits plus 24 terminals spare for future use.
b) The temperature v/s pressure curves for each setting of density monitor
along with details of density monitor.
g) Details & type of filters used in interrupter assembly and also the
operating experience with such filters.
i) The test methods used in controlling the quality of gas used in the
circuit breakers particularly purity and moisture content.
ii) Proposed tests to assess the conditions of the SF6 within a circuit
breaker after a period of service particularly with regard to
moisture contents of the gas.
j) Shall furnish curves supported by test data indicating the opening time
under close open operation with combined variation of trip coil voltage.
14.2 The enclosure shall be made of either Al/Al Alloy or mild steel (suitably hot
dip galvanized). The enclosure shall be designed for the mechanical and
thermal loads to which it is subjected in service. The enclosure shall be
manufactured and tested according to the pressure vessel codes {i.e., latest
edition of the ASME code for pressure vessel - Section VIII of BS-5179,
IS4379, IS-7311 (as applicable) and also shall meet Indian Boiler
Regulations}.
14.3 The enclosure has to be tested as a routine test at 1.5 times the design
pressure for one minute. A bursting pressure test shall be carried out at 5
times the design pressure as type test on the enclosure.
15.0 TESTS
15.1 In accordance with the requirements stipulated under Section-GTR the circuit
breaker alongwith its operating mechanism shall conform to the type tests as
per IEC: 62271-100.
15.2 The type test reports as per IEC and the following additional type test reports
shall also be submitted for purchaser’s/employer’s review:
iii) Line charging interrupting current for proving parameters as per clause
no. 16.0 of this section.
i) Speed curves for each breaker shall be obtained with the help of a
suitable operation analyzer to determine the breaker contact movement
during opening, closing, auto reclosing and trip free operation under
normal as well as limiting operating control voltage conditions. The
tests shall show the speed of contacts directly at various stages of
operation, travel of contacts, opening time, closing time, shortest time
between separation and meeting of contacts at break make operation
etc. This test shall also be performed at site for which the necessary
operation analyzer along with necessary transducers, cables, console
etc. shall be arranged by the contractor at his own cost.
* The values indicated are for specific creepage of 25mm/kV. In case of specific
creepage of 31mm/kV specified, the Minimum Creepage distance values shall be
concidered proportionately.
17.1 An indicative list of tests is given below. All routine tests except power frequency
voltage dry withstand test on main circuit breaker shall be repeated on the
completely assembled breaker at site. For Pre-commissioning tests, procedures
and formats for circuit breakers, POWERGRID document no. CF/CB/03/R-4
dated 01/04/2013 of document no. D-2-01-03-01-04 dated 01-04-2013 will be the
reference document. This document will be available at respective sites and shall
be referred by the contractor. Contractor shall perform any additional test based
on specialties of the items as per the field Q.P./instructions of the equipment
Supplier or Employer without any extra cost to the Employer. The Contractor
(m) Operation check of pressure switches and gas density monitor during
gas filling.
17.2 The contractor shall ensure that erection, testing and commissioning of circuit
breaker shall be carried out under the supervision of the circuit breaker
manufacturer's representative. The commissioning report shall be signed by the
manufacturer’s representative.
The actions required to be taken by contractor in case of defects observed in AIS type
Circuit Breakers of ratings 132kV & above during the warranty period (defect liability
period) shall be as per following. Further, the replaced/repaired/ refurbished equipment
(or part of equipment) shall have warranty in line with the GCC clause 22 in SCC.
SECTION-SWITCHGEAR-INST
(INSTRUMENT TRANSFORMERS)
Note: The above is the list of major changes with respect to previous revision (Rev. 10).
However, the bidders are advised to read the entire section/chapter for other changes and
quote accordingly.
INSTRUMENT TRANSFORMERS
CONTENTS
Clause.No. Description Page No.
1.0 General 4
6.0 Tests 10
f) SF6 gas filled CT/IVT shall be provided with a suitable SF6 gas density
monitoring device, with NO/NC contacts to facilitate the remote
annunciation and tripping in case of SF6 gas leakage. Provisions shall
be made for online gas filling. Suitable rupture disc shall be provided to
prevent explosion.
g) The rated extended currents for 800kV and 420kV class Current
transformers shall be as given below:
j) For 800kV CTs, the instrument security factor at all ratios shall be less
than ten (10) for metering core. For 420/245/145/72.5kV CTs, the
instrument security factor at all ratios shall be less than five (5) for
metering core. If any auxiliary CTs/reactor are used in the current
transformers then all parameters specified shall have to be met treating
auxiliary CTs as an integral part of the current transformer. The
auxiliary CTs/reactor shall preferably be inbuilt construction of the
CTs. In case these are to be mounted separately these shall be mounted
in the central marshalling box suitably wired upto the terminal blocks.
k) The wiring diagram plate for the interconnections of the three single
phase CTs shall be provided inside the marshalling box. A typical
6.0 TESTS:
6.1 In accordance with the requirements in Section-GTR, Current Transformer
and Voltage Transformer should have been type tested and shall be subjected
to routine tests in accordance with relevant IEC.
6.2 The test reports of type tests, as applicable, as per IEC-61869-2 for CT,
IEC-61869-5/IEC-60358 for CVT, and IEC-61869-3 for IVT and
following additional tests shall be submitted for the Employer’s review. The
type tests for which the procedure is under consideration as per
abovesaid IEC is not required to be considered.
a) Current Transformers (CT):
i) Corona test as per Annexure-A of Section-GTR for 420kV and
above voltage rating.
ii) RIV test as per IEC-61869 or as per Annexure-A of Section-
GTR for 145kV and above voltage rating. However, RIV level
shall be as specified at Annexure-II of this specification.
iv) Transmitted over voltage test for 145kV and above voltage
rating
v) Mechanical test (with minimum Cantilever load as per clause
no. 2.1.c) for 72.5kV and above voltage rating
vi) Enclosure tightness test at low & high temperature for SF6
filled CT of 145kV and above voltage rating
vii) Gas dew point test for SF6 filled CT
a) CURRENT TRANSFORMERS:
ROUTINE TESTS:
For Oil filled CT:
i) Measurement of Capacitance.
ii) Oil leakage test.
iii) Measurement of tan delta at 0.3, 0.7, 1.0 and 1.1 Um/√3.
For SF6 filled CT:
i) Dew point measurement
ii) SF6 alarm/ lockout check.
iii) SF6 gas leakage test: Gas leakage rate shall be maintained
within 0.2% per annum.
b) VOLTAGE TRANSFORMERS:
Routine tests on CVT/IVT shall be done in line with IEC-61869-3/61869-5.
7.0 MANDATORY SPARES:
Bidder shall include in his proposal mandatory spares as mentioned in the
Bidding Documents.
Dissolved Gas Analysis (DGA) shall be carried out twice within the first
year of service, first within the first month of commissioning/charging
and second between six months to one year from the date of
commissioning/charging.
CTs/IVTs must have adequate provision for taking oil samples from the
bottom of the CT/IVT without exposure to atmosphere. Manufacturer shall
recommend the frequency at which oil samples should be taken and norms
for various gases in oil after being in operation for different durations.
Bidder/Manufacturer should also indicate the total quantity of oil which can
be withdrawn from CT for gas analysis before refilling or further treatment of
CT becomes necessary.
Bidder shall supply 2 nos. oil sampling device for every 20 nos. oil filled
CT supplied with a minimum of 2 nos. oil sampling device for each
substation.
9.3 Inductive Voltage Transformers/Capacitive Voltage Transformers
(a) Insulation Resistance test for primary (if applicable) and secondary
winding
(b) Polarity test
(c) Ratio test
(d) Dielectric test of oil (wherever applicable)
3. No. of secondaries 3
4. Rated voltage factor 1.2 continuous
1.5 - 30 seconds
5. Phase angle error + 10 minutes (For metering
core)
6. Capacitance (pf) (for CVT) 4400/8800* (+10% / - 5%)
7. Core details Core-1 Core-2 Core-3
a) Voltage Ratio 400/0.11 400/0.11 400/0.11
√3 √3 √3 √3 √3 √3
b) Application Protec- Protec- Meter-
tion tion ing
c) Accuracy 0.5&3P 0.5&3P 0.2
d) Min. Output burden (VA) 50 50 50
————————————————————————————————————
* Capacitance value shall be as specified in BPS.
c) Accuracy 3P 0.5
No. Core Application Ratio Output Accuracy Min. Max. CT Max. Excit.
of No. Burden Class Knee Pt. Sec. wdg. Current at
cores Voltage Resistance Vk (in mA)
(Vk) (in )
No.of Core Appli- Current Output Accuracy Min. knee Max. CT Max. Excit-
Cores No. cation ratio burden class pt.volt- sec.wdg. ation cur-
(VA) age Vk resist- rent at Vk
ance(ohms) (in mA)
5 1 BUS DIFF 600- - PX 600/ 6/3 30 on
CHECK 300/1 300 600/1
Tap;
60 on
300/1
Tap
________________________________________________________________________
*The values indicated are for specific creepage of 25mm/kV. In case of specific creepage
of 31mm/kV is specified, the Minimum Creepage distance values shall be considered
proportionately.
For other parameters, refer respective Table for the applicable voltage class of CTs.
5 Design ambient 50 50 50 50 50
temperature (°C)
6 System fault level 40kA/50kA (as 40kA/50kA/63kA 40kA/50kA (as
(kA) 31.5kA for 25kA for
applicable) for 1 (as applicable) for applicable) for 1
1sec 3sec
sec 1 sec sec
6 Standard reference 96% to 102% for protection and
range of frequencies 99% to 101% for measurement
for which the
accuracies are valid
7 High frequency Within 80% to 150% of rated capacitance -
capacitance for entire
carrier frequency
range (for CVT only)
8 Equivalent series
resistance over entire
Less than 40 Ohms -
carrier frequency
range (for CVT)
9 Stray capacitance and
stray conductance of
HF terminal over
As per IEC-60358 -
entire carrier
frequency range (for
CVT)
10 Temperature rise over
design ambient As per IEC
temperature
11 Rated Insulation levels
a) Full wave impulse withstand voltage (1.2/50 microsecond)
i) between line ±2100 ±1425 ±1050 ±650 ±325
terminals and ground
(kVpeak)
b) Switching impulse withstand voltage (250/2500 microsecond) (dry and wet)
Technical Specification, Section: Switchgear-INST
C/ENGG/SPEC/SWGR/R11, JAN 2017 Page 28 of 34
S. No. Description 765kV 400kV 220kV 132 kV 66 kV
system system system system System (for
tertiary
loading)
i) between line ± 1550 ± 1050 -NA- -NA- -NA-
terminals and ground
(kVpeak)
c) One minute power frequency dry withstand voltage (dry and wet)
i) between line 975 630 460 275 140
terminals and ground (dry only) (dry only)
(kVrms)
d) One minute power frequency withstand voltage between secondary terminals & earth
i) between LV (HF) 10kVrms for exposed terminals and 4kVrms for terminals enclosed in a weather
terminal and earth proof box
terminal (kVrms)
ii) For secondary 3kVrms
winding
*The values indicated are for specific creepage of 25mm/kV. In case of specific creepage
of 31mm/kV is specified, the Minimum Creepage distance values shall be considered
proportionately.
For other parameters, refer respective Table for the applicable voltage class of CVTs/IVTs.
SECTION-SWITCHGEAR - ISOLATOR
Notes: The above is the list of major changes with respect to previous revision (Rev.
11/11A). However, the bidders are advised to read the entire section for other changes
and quote accordingly.
CONTENTS
1.0 General 4
6.0 Operation 10
9.0 Tests 12
Annexure-I
1.0 GENERAL:
1.1 The Isolators and accessories shall conform in general to IEC: 62271-102/103
except to the extent explicitly modified in specification and shall be in
accordance with requirement of Section-GTR.
1.2 Complete isolator with all the necessary items for successful operation shall be
supplied including but not limited to the following:
1.2.1 Isolator with complete Support Insulators, operating rod insulator, base frame,
linkages, operating mechanism, control cabinet, interlock etc.
1.2.2 All necessary parts to provide a complete and operable isolator installation,
control parts and other devices whether specifically called for herein or not.
1.2.3 The isolator shall be designed for use in the geographic and meteorological
conditions as given in Section-GTR and Section-Project.
3.1 Contacts:
a) The contacts shall be self aligning and self cleaning type and shall be so
designed that binding cannot occur after remaining in closed position for
prolonged period in a heavily polluted atmosphere.
c) Contact springs shall not carry any current and shall not loose their
characteristics due to heating effects.
d) The moving contact of double break isolator shall have preferably turn-and-
twist type or other suitable type of locking arrangement to ensure adequate
contact pressure.
e) Flexible braided copper, where used, shall have corrosion resistant coating
such as tinning or silvering.
3.2 Base :
Each single pole of the isolator shall be provided with a complete galvanised
steel base provided with holes and designed for mounting on a standard
supporting structure. Common base frame shall be provided for 400/220/132kV
isolators suitable for mounting on pipe structures.
b) The live parts shall be designed to eliminate sharp joints, edges and other
corona producing surfaces, where this is impracticable, adequate corona
rings shall be provided. Corona shields are not acceptable. Corona rings
shall be made up of aluminum/aluminum alloy.
d) The isolator and earth switch shall be designed such that no lubrication of
any part is required except at very infrequent intervals. i.e. after every
1000 operations or after 5 years whichever is earlier.
3.4 Insulator :
a) The insulator shall conform to IS: 2544, IEC-60168 and IEC-60815. The
porcelain of the insulator shall conform to the requirements stipulated
under Section-GTR.
b) Pressure due to the contact shall not be transferred to the insulators after
the main blades are fully closed.
(i) Bending load test in four directions at 50% of minimum bending load
guaranteed on all insulators, as a routine test.
The name plate shall conform to the requirements of IEC incorporating year of
manufacture.
a) Where earthing switches are specified these shall include the complete
operating mechanism and auxiliary contacts.
b) The earthing switches shall form an integral part of the isolator and shall
be mounted on the base frame of the isolator.
e) The plane of movement and final position of the earth blades shall be
such that adequate electrical clearances are obtained from adjacent live
parts in the course of its movement between ON and OFF position.
f) The frame of each isolator and earthing switches shall be provided with
two reliable earth terminals for connection to the earth mat.
g) The earth switch should be able to carry the same fault current as the
main blades of the Isolators and shall withstand dynamic stresses.
h) 800kV, 420 kV & 245 kV earth switches shall also comply with the
requirements of IEC-62271-102, in respect of induced current switching
duty as defined for Class-B and short circuit making capability class E-0
for earthing switches.
i) Earth switch blade in open condition shall not project (from the centre line
of Insulator) by more than 4200mm for 400kV and 2810mm for 220kV
respectively.
a) The bidder shall offer motor operated Isolators and earth switches.
Isolators of 36 kV and below and earth switches of 72.5 kV and below
rating shall be manual operated.
f) Suitable reduction gearing shall be provided between the motor and the
drive shaft of the isolator. The mechanism shall stop immediately when
motor supply is switched off. If necessary a quick electro-mechanical
brake shall be fitted on the higher speed shaft to effect rapid braking.
j) Only stranded conductor shall be used for wiring. Minimum size of the
conductor for control circuit wiring shall be 1.5 sq.mm. (Copper).
l) Snap type limit/auxiliary switches shall be used with Factory set values.
No adjustment shall be required at site during commissioning.
a) The main Isolator and earth switches shall be individual pole operated for
800/420 kV and gang operated in case of 245 kV & 145 kV. However,
245 kV Tandem Isolators shall be individual-pole operated. The operating
mechanism of all the three poles shall be well synchronized and
interlocked.
e) All rotating parts shall be provided with grease packed roller or ball
bearings in sealed housings designed to prevent the ingress of moisture,
dirt or other foreign matter. Bearings pressure shall be kept low to ensure
long life and ease of operation. Locking pins wherever used shall be rust-
proof.
f) Signaling of closed position shall not take place unless it is certain that the
movable contacts, have reached a position in which rated normal current,
h) The contractor shall furnish the following details alongwith quality norms,
during detailed engineering stage:
800 kV/420 kV/245 kV/145 kV Isolators along with Earth switches shall be
suitable for mounting on standard support structures.
9.0 TESTS:
9.2 The test reports of the type tests as per IEC 62271-102 and the following
additional type tests (additional type tests are required for isolators rated above
72.5 kV only) shall also be submitted for the Employer’s review.
12.1 Contractor shall perform any additional test based on specialties of the items as
per the field Q.P./Instructions of the equipment manufacturer or Employer
without any extra cost to the Employer. The Contractor shall arrange all
instruments required for conducting these tests alongwith calibration certificates
at his own cost.
An indicative list of tests on isolator and earthswitch is given below. For pre-
commissioning procedures and formats for Isolators and Grounding switch,
Doc.No.: CF/ISO/07/R-4, dtd-01.04.2013 under POWERGRID Document no. D-
2-01-03-01-04 will be the reference document. This document will be available
at respective sites and shall be referred by the contractor.
(i) Functional check of the control schematic and electrical & mechanical
interlocks
12. 2 The Contractor shall ensure that erection, testing and commissioning of
Isolators above 72.5 kV class shall be carried out under the supervision of the
Isolator manufacturer's representative and the cost of the same shall be
included in the erection price of the respective equipment.
Sl. Description Unit 800kV ISO 420kV ISO 245kV ISO 145kV ISO
No.
1 Rated voltage kVrms 800 420 245 145
2 Rated frequency Hz 50 50 50 50
3 No. of poles Nos. 3 3 3 3
4 Design ambient °C 50 50 50 50
temperature
5 Type Outdoor Outdoor Outdoor Outdoor
6 Rated current at A 3150 3150 1600A / 1250
50oC ambient 2500 A (as
temperature applicable)
7 Rated short time kA 40 / 50 for 1 40 /50 /63 40 / 50 for 1 31.5 for 1
withstand current of sec (as for 1 sec (as sec (as sec
isolator and earth applicable) applicable) applicable)
switch
8 Rated dynamic short kAp 102kAp 100 kAp / 100 kAp / 80kAp
time withstand 125 kAp / 125 kAp (as
current of isolator 157.5 kAp applicable)
and earth switch (as
applicable)
9 Temperature rise As per Table-3 of IEC-62271-1
over design ambient
temperature
10 Rated mechanical N As per table III of IEC-62271-102 or as per value
terminal load calculated in Section-GTR whichever is higher
11 Mechanical Isolator-M2
Endurance Class E/S-M0
12 Operating A.C. Motor operated
mechanism of
isolator/erathswitch
13 No. of auxiliary Besides requirement of this spec., 5 NO + 5 NC contacts wired on
contacts on each each isolator to terminal block exclusively for Employer’s use in
isolator future.
14 No. of auxiliary Besides requirement of this spec., 3 NO + 3 NC contacts wired on
contacts on each each isolator to terminal block exclusively for Employer’s use in
earthing switch future.
Note: The above insulation levels are applicable for altitude up to 1000 meters
above M.S.L. For higher altitudes, suitable correction factor as per relevant IEC
shall be applied.
Note: The above insulation levels are applicable for altitude up to 1000 meters
above M.S.L. For higher altitudes, suitable correction factor as per relevant IEC shall
be applied.
Notes: The above is the list of major changes with respect to previous revision
(Rev. 10). However, the bidders are advised to read the entire section for other
changes and quote accordingly.
CONTENTS
1.0 General 4
5.0 Tests 8
Annexure-I
1.0 GENERAL:
1.1 The Surge arresters shall conform to IEC: 60099-4 except to the extent
modified in the specification and shall also be in accordance with
requirements under Section -GTR.
1.2 The Surge Arrestors shall be designed for use in the geographic and
meteorological conditions as given in Section-GTR and Section-
Project.
a. The surge arresters shall be of heavy duty station class and gapless
type without any series or shunt gaps.
i) The manufacturer will submit Data for rejection rate of ZnO blocks
during manufacturing/operation for the past three years.
5.0 TESTS:
Test reports for all type tests as per IEC-60099-4 including following
additional type tests (additional type tests are required for Surge
Arresters above 72.5 kV class only) shall also be submitted for the
Employer’s review:
Each metal oxide block of surge arresters shall be tested for the
guaranteed specific energy capability in addition to the
routine/acceptance test as per IEC: 60099-4.
3. Wattloss test.
1. Sealing test: Water dip test at 1.5m depth from top of Surge Arrestor
for 30 minutes shall be performed during assembly of Surge
Arrester stacks (followed by other routine tests, i.e. P.D.
Measurement, Reference Voltage, Residual Voltage & IR
measurement).
Surge monitors shall be routinely tested for water dip test at 1.5m
depth for 30 minutes. No water vapors shall be visible on the
monitor glass.
17 Max. radio micro 2500 at 508 500 at 266 500 at 156 500 at 92
interference volts kVrms kVrms kVrms kVrms
voltage for
frequency
between0.5 MHz
and 2 MHz. in all
positions
18 Minimum mm As per As per As per As per
Creepage distance Section-GTR Section-GTR Section-GTR Section-GTR
19 Cantilever kg 500 350 150 150
Strength (for 1
minute withstand
test)
20 Maximum mm 200 200 200 200
deflection at
above cantilever
load
21 Seismic As per As per As per As per
acceleration IS:1893 IS:1893 IS:1893 IS:1893
Note: The above insulation levels are applicable for altitude up to 1000 meters
above M.S.L. For higher altitudes, suitable correction factor as per relevant
IEC shall be applied.
Note: The above insulation levels are applicable for altitude up to 1000 meters
above M.S.L. For higher altitudes, suitable correction factor as per relevant
IEC shall be applied.
1.1 General
This section describes the Fiber Optic Communication equipment characteristics for communication
system to be installed under the project. The sub-systems addressed within this section are:
The equipment supplied shall support existing communication network for Power system operational
requirements.
The security related requirements of the equipment shall be as per DoT (Department of
Telecommunication) guidelines and all similar security requirements as amended by DoT on time to
time basis shall be followed/complied by the vendor at no additional cost to Employer till the
implementation of the project.
The manufacturer shall allow the Employer and/or its designated agencies to inspect the hardware,
software, design, development, manufacturing, facility and supply chain and subject all software to a
security /threat check any time during the supplies of equipment
The contractor shall ensure that the supplied equipments have been got tested as per relevant
contemporary Indian or International Security Standards e.g. IT and IT related elements against
ISO/IEC 15408 standards, for Information Security Management System against ISO 27000 series
Standards from an authorized and certified agency/lab.
In case of any deliberate attempt for a security breach at the time of procurement or at a later stage
after deployment/installation of the equipment or during maintenance, liability and criminal
proceedings can be initiated against the Contractor as per guidelines of DoT and any other
Government department.
The primary function of the equipment is to provide a highly reliable voice and data communication
system for grid operation in support of the SCADA/EMS, RTUs & PMUs and for new technological
requirements of Power System Operation such as Special Protection Scheme, Grid Security Expert
System, Load Management, Advanced Protection System & Substation Automation System. A brief
summary of the system requirements is as follows:
(c) Low speed (300 -1200 bps) data channel support as required
(d) Voice (2 wires, 4 wires) channel support and integration with Employer’s/RLDC’s EPABX
system. The details of EPABX System shall be provided during detailed engineering.
Rev-02
(f) The connectivity envisaged between Substation and Control Centre over TCP-IP using
Ethernet interface for various services of data and voice such as for PMUs, RTUs, VOIP etc.
The SDH node shall be used for interconnection of terminal Substation to the fibre optic network and
shall be based on the Synchronous Digital Hierarchy (SDH) having bit rate of STM-4/16 as specified in
BPS. The contractor shall follow numbering plan for the proposed voice communication system.
The transmission equipment to be supplied shall be a complete SDH node (add-drop multiplexer)
providing all the features e.g. protection and performance monitoring.
This will be used for delivering E1 as per ITU-T G.703 and Giga/fast Ethernet services except repeater
stations. In case other interface such as Asynchronous Sub-channel data card (RS232/V.24/V.28),
Synchronous data card (V.36/X.21), 2 wire voice channel card or 4 wire (E&M) voice channel card
as required, shall be supplied either in the same equipment or as independent PDH equipment.
The Contractor shall supply the equipment as per the technical specification. The deliverables
shall include all installation materials necessary for successful installation and
commissioning of the equipment viz. AC & DC power supply cabling, Krone type/75Ω BNC type
Digital Distribution Frame (DDF) in enclosure, optical patch cords for FODP-to-equipment and
equipment-to-equipment connection, optical attenuator (5dB/10dB), flexible conduits etc. as per site
requirement. Additionally one (1) pair of optical patch cord per SDH node will be supplied as
spare. User Manual, System Guide shall be delivered with each equipment. The Contractor shall
provide all required minor civil works necessary for full connectivity as required.
Equipment redundancy and Automatic Protection Schemes (APS) are specified in the Table 1.
The failure of one element shall not prevent the use of any other that has not failed.
Table 1
Equipment Redundancy Requirements Summary
Power Supply & Converters ------------------------------ 1:1 APS or distributed power supply
The offered equipment shall support automatic switchover function between the redundant
modules and all required modules and hardware to support the automatic switch over shall be
provided by the Contractor.
At any digital signal level, reapplication of a lost signal shall result in automatic
resynchronization and full restoration to normal operation without manual intervention. All
alarms incident to the signal failure, shall be automatically cleared at the equipment, rack and
monitoring levels and normal operation indications restored and reported if applicable.
The offered transmission equipment (SDH node) shall support optical link of at least 250 Km for STM-4
and 225Km for STM-16 without any repeater station in between. If required, wavelength translator/
Rev-02
optical amplifier shall be provided by the contractor.
Aggregate interface shall be STM-4/16, with three (3)/Five (5) MSP protected directions (as required
in BPS). If bidder is offering equipment with multifunction cards such as cross-connect or control card
with optical interface/SFP or tributary interface, such type of multifunction card shall be considered as
Common control card and shall be the part of base equipment. In case optical interface/SFP is embedded
with control card, the adequate number of optical interface/SFPs shall be offered to meet the redundancy
requirements of the specifications. Further, main and protection channel shall be terminated on separate
cards. Aggregate interface of STM-4/16 shall have FC/PC. In case other than FC-PC connector is
provided in the equipment, suitable patch cord with matching connector are to be provided to connect
with FODP.
All software and hardware shall support IPv4 and IPv6 simultaneously (dual stack).
SDH equipment shall support dual power feed with redundancies for Power supply unit and Control unit
in each rack.
Minimum 16 nos. x 2 Mbit/s per card, 120Ω/75Ω tributary interface compliant to ITU-T G.703, G.704
with suitable connector
Ethernet interface shall have minimum 8 nos. per card of RJ-45 port for ingress and egress of Ethernet
data (Ethernet over SDH) at 10/100/1000 Base-T speeds/standards (ITU-T G.7041GFP capsulation).
Ethernet shall support LCAS feature. It shall support full throughput upto 1000 Mbps on Ethernet
port by virtual concatenation of requisite no. of VC-12.There shall be the provision of
“Auto Negotiation” and “Flow control” Enabling/disabling through NMS of the system. Also
there shall be provision of configuring the equipment for unrestricted nxVC12 bandwidth (upto
1000Mbps). The Ethernet interface shall support VLAN (IEEE 802.IP/Q), spanning tree (IEEE 802.ID)
quality of service. The protection scheme for Ethernet traffic should be ERPS based.
Services channel shall be provided as a function of the SDH equipment and shall be equipped
with Service Channel Muldems that shall provide at a minimum: One voice channel (order wire)
with analog interface (0.3 to 3.4 kHz) and one data channel. There shall be a facility to extend
the line system order-wire to any other system or exchange lines.
Synchronization: The substation GPS can be used for extending synchronization to equipment.
Alternately existing network Master Clock can be used for synchronization.
ISM (In Service Monitoring) circuitry shall be provided as a function of the SDH equipment. Local visual
alarm indicators shall be provided on the equipment, as a rack summary alarm panel. Alarms shall be as
per ITU-T Standards G.774, G.783 and G.784.
Shall have Embedded Communication Channel (ECC), ports (Ethernet/RS232) for craft terminal and
management interface and shall support DCC pass through.
Manageable by Craft Terminal programme. It shall support performance monitoring, remote software
upgrade, configuration management from remote as well as local craft terminal. The craft terminal shall
have minimum configuration of 2.4 GHz, 8 GB RAM, 256 MB Video Graphics Memory, DVD RW
drive, 320 GB Hard Disk Drive, keyboard, mouse/trackball etc., serial/USB (2.0) ports to accommodate
printers, IEEE 802.11a/b/g wireless LAN, Bluetooth, Internal/external Data/Fax modem and a battery
back-up of at least 3 hours. VDUs shall be 15" TFT active matrix color LCD with a minimum resolution
of 1024 X 768.
Local Craft Terminal will be provided with requisite software for performing all element level
management functions viz. configuration management, fault management, performance management
etc.
Shall be operated with -48 V DC Power Supply. DC power interface shall be suitable to work on a
nominal voltage of -48V ± 20%.
The bidder shall be required to provide only Optical Interface/SFP to be installed in the existing/third
party SDH equipment at few locations if any. The bidder has to ensure compatibility of the supplied
Optical Interface/SFP for the same.
Manageable by Craft Terminal programme. It shall support performance monitoring, remote software
upgrade, configuration management from remote as well as local craft terminal. The craft terminal shall
have minimum configuration of 2.4 GHz, 8 GB RAM, 256 MB Video Graphics Memory, DVD RW
drive, 320 GB Hard Disk Drive, keyboard, mouse/trackball etc., serial/USB (2.0) ports to accommodate
printers, IEEE 802.11a/b/g wireless LAN, Bluetooth, Internal/external Data/Fax modem and a battery
back-up of at least 3 hours. VDUs shall be 15" TFT active matrix color LCD with a minimum resolution
of 1024 X 768. However, the configuration shall be finalized during detailed engineering as per the latest
industrial standards.
Local Craft Terminal will be provided with requisite software for performing all element level
management functions viz. configuration management, fault management, performance management
etc.
Bidder shall provide the telecom equipment which can be integrated with the existing NMS server/s of
the respective RLDC/ SLDC. The details of existing NMS server/s shall be provided during detailed
engineering or to be ascertained by Bidder conducted during site survey.
(1) Fibre attenuation: The fibre attenuation shall be taken to be the guaranteed maximum fibre
attenuation i.e. 0.21 dB/Km @1550nm and 0.35 dB/km @1310nm.
(2) Splice loss: Minimum 0.05 dB per splice. One splice shall be considered for every 3 kms.
(3) Connector losses: Losses due to connectors shall be considered to be minimum 1.0 dB per link.
(4) Equipment Parameters: The equipment parameters to be considered for link budget calculations
Rev-02
shall be the guaranteed “End of Life (EOL)” parameters. In case, the End of Life parameters are not
specified for the SDH equipment, an End of Life Margin of at least 2 dB shall be considered and a
similar margin shall be considered for optical amplifiers.
(5) Optical path Penalty: An optical path penalty of at least 1 dB shall be considered to account for total
degradations due to reflections, inter symbol interference, mode partition noise and laser chirp.
(6) Maintenance Margin: A maintenance margin of at least 2.5 dB/100Km shall be kept towards
cabling, repair splicing, cable ageing and temperature variations etc.
(7) Other losses: Other losses, if any required specifically for system to be supplied shall also be
suitably considered.
(8) Dispersion: The fibre dispersion shall be taken to be the guaranteed maximum dispersion i.e. 18
ps/nm.Km @1550 nm & 3.5 ps/nm.km @ 1310 nm for DWSM fibres.
(9) Bit Error Rate: The link budget calculations shall be done for a BER of 10-10.
The bidders shall determine the total link loss based on the above parameters and shall submit the
system design (including link budget calculations) for each fibre optic link during detailed engineering.
For finalising the FOTS system design & BOQ, above methodology shall be adopted taking into
account fibre attenuation, dispersion and splice loss determined during the detailed engineering.
Accordingly, additions and deletions from the contract shall be carried out based on unit rates indicated
in the contract.
2.1.4 Technical Requirement of Repeater Shelter
For purposes of this specification, a fibre optic approach cable is defined as the Armoured underground
fibre optic cable required to connect Overhead Fibre Optic Cable (OPGW) between the final in line
splice enclosure on the gantry / tower forming the termination of the fibre cable on the power line and the
Fibre Optic Distribution Panel (FODP) installed within the building. The estimated fibre optic approach
cabling length requirements are indicated in the appendices. However, the Contractor shall supply &
install the optical fibre approach cable as required based on detailed site survey to be carried out by the
Contractor during the project execution and the Contract price shall be adjusted accordingly. Approach
Cable shall consist G.652D DWSM Fibers.
The cable shall be suitable for direct burial, laying in trenches & PVC/Hume ducts, laying under false
flooring and on indoor or outdoor cable raceways. The jacket shall conform to ASTM D1248 for density.
Approach cable shall contain fibres with identical optical/ physical characteristics as those in the OPGW
cables. The cable core shall comprise of tensile strength member(s), fibre support/bedding structure, core
wrap/bedding, and an overall impervious jacket.
The existing cable trenches/ cable raceways proposed to be used shall be identified in the survey report.
The Contractor shall make its best effort to route the cable through the existing available cable trenches.
Rev-02
Where suitable existing cable trenches are not available, suitable alternatives shall be provided after
Employer approval.
Suitable provisions shall be made by the Contractor to ensure adequate safety earthing and insulated
protection for the approach cable.
All required fittings, supports, accessories, ducts, inner ducts, conduits, risers and any item not specially
mentioned but required for laying and installation of approach cables shall be supplied and installed by
the Contractor.
Optical fibre terminations shall be done in Fibre Optic Distribution Panels (FODP) designed to provide
protection for fibre splicing of preconnectorized pigtails and to accommodate connectorized termination
and coupling of the fibre cables. The Contractor shall provide rack /wall mounted Fibre Optic
Distribution Panels (FODPs) sized as indicated in the appendices and shall terminate the fibre optic
cabling up to the FODPs. The location of FODP rack shall be fixed by the Contractor, with the
Employer’s approval.
At each location requiring the termination of at least one fibre pair within a cable, all fibres within that
cable shall be connectorized and terminated in Fibre Optic Distribution Panels in a manner consistent
with the following:
(a) All fibre optic terminations shall be housed using FODPs provisioned with splice organizers and
splice trays. All fibres within a cable shall be fusion spliced to preconnectorized pigtails and fitted to the
"Back-side" of the provided fibre optic couplings.
(b) FODPs shall be suitable for use with each of the cable types provided as part of this contract. FODPs
shall accommodate pass-through splicing and fibre terminations.
(c) FODPs for indoor use shall be supplied in suitable cabinets/racks with locking arrangement.
(d) The FODP shall be of corrosion resistant, robust construction and shall allow both top or bottom entry
for access to the splice trays. Ground lugs shall be provided on all FODPs and the Contractor shall ensure
that all FODPs are properly grounded. The FODP shall meet or exceed ingress protection class IP55
specifications.
(e) Flexible protection shall be provided to the patch cord bunches going out from FODP cabinet to other
equipment cabinet.
Equipment shall operate in accordance with the Environmental Operating limits as shown in Table-2:
Table -2
Environmental Operating Limits
Specification 0 to 45°C
Operation without damage -10 to 55°C
Shipping/storage
-40 to 60°C
Rev-02
Elevation:
Operating to 3,000 m
Non-operating to 10,000 m
Power Distribution and Protection: Power supplies/converters for communications equipment shall use -
48Vdc uninterrupted primary source power. The Employer will furnish only one power source.
Contractor shall provide required distribution panels, circuit breakers, appropriate panel disconnects and
all cabling, fusing, switching required. Distribution Panel feeders, Panel Disconnects, distribution panels
and circuit breakers shall be sized and equipped to support at least 100% expanded load requirements.
The Contractor shall also be responsible for Load Balancing.
Contractor shall provide equipment and rack safety earthing in full compliance with EMI/EMC
requirements as per relevant international standards.
Equipment cabinet (enclosure) shall be designed 19 inch, free standing but shall be mounted on the
floor. The dimensions of the cabinet shall be minimum 2200mmx600mmx600mm. All doors and
removable panels shall be fitted with long life rubber beading. All panels shall be fabricated from
minimum 2.0mm thickness steel sheet. However, for racks with load bearing Aluminium extrusion frame,
door panels and side panels may be fabricated from minimum 1.6mm thickness steel sheet and the top &
bottom panels shall be fabricated from minimum 2.0mm thickness steel sheet. Equipment cabinet
(enclosure) shall be dust and moisture proof as per IP41 specification or better (supporting
certificates/documents shall be submitted during detailed engineering).
The Contractor shall provide all required minor civil works necessary for full connectivity as required in
the Contractor’s scope of work.
Any other miscellaneous items which may be required for successful interfacing for establishment of
end-to-end communication is deemed to be included in the scope of the Contractor.
4 TESTING
All materials furnished and all work performed under this Contract shall be inspected and tested. The
entire cost of testing for factory & site acceptance, routine tests, production tests and other test during
manufacture & site activities specified herein shall be treated as included in the quoted unit price of
materials, except for the expenses of Inspector/Employer’s representative. All tests shall be witnessed by
the Employer and/or its authorized representative (hereinafter referred to as the Employer) unless the
Employer authorizes testing to proceed without witness.
"Type Tests" shall be defined as those tests which are to be carried out to prove the design, process of
manufacture and general conformity of the materials to this Specification. All equipment being supplied
shall conform to type tests as per Annexure-I of technical specification. The test reports submitted shall
be of the tests conducted within last five (5) years. In case the test reports are older than five (5) years, the
Rev-02
Contractor shall repeat these tests at no extra cost to the purchaser. In the event of any discrepancy in the
test reports or any type tests not carried out, same shall be carried out by Contractor without any
additional cost implication to the Employer. Type Tests shall be certified or performed by reputed
laboratories using material and equipment data sheets and test procedures that have been approved by the
Employer.
The detailed requirements for Type Test, Factory Acceptance Test and Site Acceptance Test are attached
at ‘Annexure – I
5 TRAINING
The Contractor will provide a training of suitable duration on supplied SDH equipment for
Employer’s personnel to provide working knowledge of the equipment, operation and diagnostic
tools, supervision and monitoring using local craft terminal. The training may be provided by the
Contractor or its sub-vendor at the site itself, preferably prior to installation, and will include training
materials, presentation equipment, and all associated expenses. No separate charges for training shall be
payable to the Contractor.
6 SUPPORT SERVICES
Throughout design, implementation, factory testing, and field installation and testing, the Contractor shall
supply consulting assistance, as required by the Employer for site preparation, field installation, and other
areas where technical support may be required.
The Contractor shall be responsible for minor facility renovation, and maintenance of the supplied system up
to and including successful completion of the Site Acceptance Test.
After final acceptance of the communications equipment, the Contractor shall offer continuing technical
support and spare parts for the communication equipment for a minimum period of 15 years from
operational acceptance by the employer or 7 years after the declaration of withdrawal of equipment from
production whichever is earlier. However the termination of production shall not occur prior to Operational
Acceptance of the system by the Employer. Some locations have existing SDH & MUX equipment. The
traffic may be switched over to new fibre optic communication equipment in phase manner. The Contractor
shall review the Employer existing equipment make, integration & switch over recommendation and prepare
a detailed field implementation plan.
Consultation with Contractor's technical support personnel and trained field service personnel shall
be readily available on a short-term/long-term basis to assist the Employer personnel in
maintaining, expanding, and enhancing the telecommunication network upon expiration of the
warranty period.
The Employer shall be informed of all alterations or improvements to the hardware supplied under
this Specification. The Employer shall be placed on the Contractor's mailing list to receive
Rev-02
announcements of the discovery, documentation, and solution of hardware/software problems as
well as other improvements that could be made to supplied equipment. The service shall begin at
the time of contract award, and shall continue for a minimum period of 15 years from operational
acceptance by the employer designed life of the equipment or 7 years after the declaration of
withdrawal of equipment from production whichever is earlier. The Contractor shall also include a
subscription to the hardware subcontractors' change notification service from the time of contract
award through the warranty period, with a Employer renewable option for extended periods.
The Contractor shall be required to supply minimum spares for each subsystem as in BPS. The subsystem set
of spare parts is defined to include all equipment modules, subunits and parts required to effect replacement,
repair and restoration to full operational status of a defined unit of a subsystem (i.e. SDH equipment.).
The one year period commencing immediately after the operational acceptance is called the
Warranty Period/Defect liability Period. In addition to the responsibilities covered under Vol-I
Condition of Contracts during Defect Liability Period, the Contractor shall also be responsible for
maintenance of the Fibre Optic Transmission System etc. supplied under this Package.
The Contractor shall provide all required consumable and non-consumable supplies necessary to
support all installation and test activities through final operational acceptance. However, if there are
any problems in the SAT and additional consumables are required, the same shall also be supplied
by the Contractor at no additional cost.
7 Documentation
Rev-02
Annexure - I
The type tests for Telecom Equipment with all types of cards are described below:
Low temperature tests shall be conducted as defined in IEC Publication 60068-2-1, test method Ad, with the following
specifications:
(1) Test Duration: The equipment is started up as soon as thermal equilibrium has been reached and
operated for sixteen (16) hours. Its performance is checked during the test.
(2) Degree of Severity: Test shall be done at 0°C
(3) Acceptance Criteria: No degradation of performance during and after the test.
Low temperature tests shall be conducted as defined in IEC Publication 60068-2-1, test method Ad, with the following
specifications:
Rev-02
(1) Test Duration: The equipment is started up as soon as thermal equilibrium has been reached and
operated for 72 hours. Its performance is checked during the test and after the test as soon as the
thermal equilibrium is reached at the room temperature (Post-test).
(2) Degree of Severity: Test shall be done at -10° C
(3) Acceptance Criteria: Degradation of performance is allowable during the test, however there shall be
no degradation of performance in the post-test.
Dry heat test shall be done as defined in IEC Publication 60068-2-2, test method Bd, with the following specifications:
(1) Test Duration: The equipment is started up as soon as thermal equilibrium has been reached and operated for
96 hours. Its performance is checked during the test.
(2) Degree of Severity: operation to specification range.
(3) Acceptance Criteria: No degradation of performance during and after the test.
Dry heat tests shall be done as defined in IEC Publication 60068-2-2, test method Bd, with the following
specifications:
(1) Test Duration: The equipment is started up as soon as thermal equilibrium has been reached and
operated for 96 hours. Its performance is checked during the test and after the test as soon as the
thermal equilibrium is reached at the room temperature (Post-test).
(2) Degree of Severity: Test shall be done at 55ºC.
(3) Acceptance Criteria: Degradation of performance is allowable during the test, however there shall be
no degradation of performance in the post-test.
Damp heat testing reveals aging with respect to the humidity level and applies basically to electronic equipment. This
test shall be done as defined in IEC Publication 60068-2-3 with the following specifications:
(1) Test Duration: The equipment is started up as soon as thermal equilibrium has been reached and
operated for 10 days. Its performance is checked during the test.
(2) Degree of Severity: Test shall be done at (40 ± 2) °C & (93 ± 3) % RH
(3) Acceptance Criteria: The equipment shall meet the specified requirement and there shall not be any
degradation in BER.
Temperature variation testing shall be as per IEC Publication 60068-2-14 (Gradual Variations, Method Nb). The
equipment shall be powered on and various parameters shall be monitored continuously during the test period.
-End of Table-
2 RF disturbance currents
N/A N/A N/A Yes
CISPR 22
3 RF radiated fields
CISPR 22 Yes
-End Of Table-
Rev-02
(c) Insulation Withstand Voltages
The procedure for this test is described in IEC Publication 60068-2-6. The testing procedure shall be carried out in the
sequence 8.1 + 8.2.1 + 8.1 as described in document 60068-2-6. For the vibration response investigation (clause 8.1 of
60068-2-6), the test shall be carried out over a sweep cycle under the same conditions as for the endurance test
(described later), but the vibration amplitude and the sweep rate may be decreased below these conditions so that the
determination of the response characteristics can be obtained.
The endurance tests conditions are selected according to the vibration withstand requirements.
Transportation tests shall be performed with the equipment packed according to the Contractor's specifications.
The procedure of this test is defined in IEC Publication 60068-2-27 (each test) with a semi-sinusoidal shape (clause
3.1.1.2).
The recommended severity shall be A = 294 m/s2, D = 18 ms. Three shocks per axis per direction shall be applied to
the equipment packed according to the Contractor's specifications.
This test could be performed as an alternative to the shock or Bump test. The procedure is defined in IEC publication
60068-2-32. The equipment shall be packed according to the Contractor's specifications. The drop height shall be
defined in accordance with IEC 68-2-32. The surface of the packing case which comes into contact with the ground is
the surface on which the packing case normally rests; if the packing does not have any features (inscription, special
shape, etc.) identifying this surface, the test is carried out successively on all the surfaces of the packing.
Or Bump Test
This test could be performed as an alternative to Shock test or Free Fall test. The procedure is defined in IEC 60068-2-
29.
The type tests listed below in Table 3 shall be conducted on DWSM fibres to be supplied as part of Approach cable.
The tests specific to the cable type are listed in subsequent sections.
Table 3
Type Tests For Optical Fibres
Rev-02
Table 3
Type Tests For Optical Fibres
The type tests to be conducted on the Fibre Optic Approach cable are listed in Table 4: Type Tests for Fibre Optic
Approach Cable. Unless specified otherwise in the technical specifications or the referenced standards, the optical
attenuation of the specimen, measured during or after the test as applicable, shall not increase by more than 0.05
dB/Km.
Table 4:
Type Tests Fibre Optic Approach Cable
S.NO. Test Name Test Procedure
1 Water Ingress Test (IEC 60794-1-F5 /
EIA 455-82B) Test duration : 24 hours
2 Seepage of filling compound (EIA 455-81A)
Preconditioning : 72 hours,
Test duration : 24 hours.
Rev-02
Table 4:
Type Tests Fibre Optic Approach Cable
S.NO. Test Name Test Procedure
3 Crush Test (IEC 60794-1-E3/ EIA 455-41)
4 Impact Test (IEC-60794-1-E4/ EIA 455-25A)
Table 5:
Factory Acceptance Testing for Fibre Optic Transmission System
Item: Description:
1. Physical inspection for conformance to DRS, BOQ, drawings and appearance of equipment
2. Optical output power
3. Transmitter lightwave spectral analysis
4. Low receive level threshold
5. Generation of bit error rate curve
6. Measurement of analog and digital service channel parameters as well as service channel
functionality
7. Performance of supervision, alarm, Craftsperson interface, diagnostics, loop backs etc.
8. Electrical interface tests which include: output and input jitter, bit error rate, pulse shape,
cable compensation, and line rate tolerance for multiplexers
9. At a minimum tests on Ethernet interface shall include demonstration of ping test,
throughput test, Latency test, Packet Loss test as per RFC 2544
11. Simulation of failure conditions and failover of each redundant unit.
12. VLAN (Layer-2 switching) feature testing configuration.
13. Protection scheme for Ethernet Traffic (ERPS)
14. Test of spare card slots
15. Checks of power supply/converter voltage margins
16. Random inspections to verify the accuracy of documentation
17. Test of spare parts/modules/cards as per applicable tests
Table 6
Rev-02
FAT on NMS (Craft Terminal)
1 Physical inspection of NMS hardware (Craft Terminal) for conformance to approved BoQ,
DRS & drawing
2 Testing of NMS to demonstrate proper operation of all functions: Configuration Management,
Performance Management, Fault Management and Security Management.
Table 7
Factory Acceptance Tests On Approach Cable
Factory Acceptance Test
Attenuation Co-efficient at 1310 nm and 1550 nm
Point discontinuities of attenuation
Visual Material verification and dimensional checks as per approved DRS/Drawings
All equipment shall be tested on site under the conditions in which it will normally operate.
The tests shall be exhaustive and shall demonstrate that the overall performance of the contract works satisfies every
requirement specified. At a minimum Site Acceptance Testing requirement for Telecom equipment, NMS etc. is
outlined in following section. This testing shall be supplemented by the Contractor's standard installation testing
program, which shall be in accordance with his quality plan(s) for Telecom equipment installation.
During the course of installation, the Employer shall have full access for inspection and verification of the progress of
the work and for checking workmanship and accuracy, as may be required. On completion of the work prior to
commissioning, all equipment shall be tested to the satisfaction of the Employer to demonstrate that it is entirely
suitable for commercial operation.
The field installation test shall be performed for all equipment at each location. If any equipment has been damaged or
for any reason does not comply with this Specification, the Contractor shall provide and install replacement parts at its
own cost and expense.
In the installation test report, the Contractor shall include a list of all hardware or components replaced or changed
Table 8
Factory Acceptance Test
Visual check of Quantities and Specific Component Number for each component of FODP and
dimensional checks against the approved drawings.
between the completion of factory tests and the start of field tests and show that documentation and spare parts have
been updated.
Rev-02
The minimal installation testing requirements for fiber optic transmission subsystem are provided in the table below:
Table 9
Fibre Optic Transmission system Installation Testing
Item: Description:
1. Physical Inspection for conformance to drawings, rack elevations and appearance of equipment
and cabling
2. Equipment power supply (DC-DC converter) output voltage measurements
3. Terminal transceiver performance testing (Tx power, Tx spectrum, receive signal strength,
connector losses etc.)
4. Service channel performance
5. Craftsperson interface, alarm and control functional performance
6. Rack and local alarms: No alarms shall be present and all alarms shall be demonstrated to be
functional
7. Network management interface and supervision performance
8. Correct configuration, level setting & adjustments and termination of Input/ output interfaces
9. Proper establishment of Safety and signalling earthing system and resistance to ground to be
checked.
10. Simulation of failure conditions and failover of protected components.
The commissioning tests shall verify that communication can be performed over the fiber optic link under test. Delay
measurement, Bit Error measurements & service channel performance monitoring shall be made on the fibre optic
links to verify compliance with designed link performance.
For Ethernet interface: At a minimum the following test requirements shall be demonstrated
as per RFC 2544:
a) Ping test
b) Throughput test
c) Latency test
d) Packet Loss
The links shall be tested for 12 Hour. In case any link does not meet the performance requirements during 12 hour,
then the cause of failure shall be investigated and the test shall be repeated after rectifying the defects.
This phase of testing shall be conducted by the Contractor and witnessed by the Employer. Field adjustments shall be
made to meet established standard, however if the field adjustments fail to correct the defects the equipments may be
returned to the Contractor for replacement at his own expense. In case any adjustments are required to be made during
the interval of the test then the test shall be repeated.
Prior to commencement of integrated testing the overall system shall be configured as required to provide all the data
and voice channel required to interconnect to control centres and other nodes in existing system. The integrated testing
shall include end-to-end testing of communication.. The intent of integrated testing is to demonstrate that the
equipment is operational end to end under actual conditions, that all variances identified during factory and field
installation and communications testing have been corrected, and that the communication equipment is compatible
Rev-02
with other equipment. The Integrated System Test shall include all fibre optic transmission equipment, the network
management subsystem (Craft Terminal) and other components.
Annexure-II
1 Introduction
This section describes the functional requirement, major technical parameters and all the testing
requirements for telecom shelter system, including its sub-systems, Air-conditioning system, DG Set, PIU &
48V DC Power Supply.
Rev-02
External 4500 2700 3160
1
Internal 4340 2540 3000
1.1.2 General
The shelters shall be protected and insulated to achieve sound proof, thermal resistance and impact
withstand capabilities. The shelters shall be 100% leak and water proof with IP 55 protection. The shelters
shall be maintenance free having minimum life of 15 years. These shelters shall be suitable for outdoor and
may be mounted at any location including ground and rooftop and in any climatic conditions. The shelters
shall be easily assembled and installed at site. The shelters shall be re-locatable as and when required.
For Steel shelters, the thickness of the inner-side and outer steel sheets except floor panel sheets shall be
minimum 0.8 mm and 0.6 mm respectively. For Aluminium shelters, the thickness of both inner side and
outer side aluminium sheets except floor panel sheets shall be minimum 0.91 mm. The outer bottom sheet
shall be hot dip galvanised steel sheets and aluminium sheets of minimum 1.0 mm and 1.2 mm thickness
respectively to avoid rusting of the bottom panel. The sandwich panels shall be manufactured by high
pressure injection technique. The panels to be provided with tubular element precast in panels while foaming
to form an integral part through this precast element GI steel rods of required sizes shall be inserted and
fastened to top and bottom structures. The steel and aluminium sheets of standard and reputed make shall
only be used.
1.1.4 Floor
The floor shall consist of standard PUF sandwich panels suitably reinforced to support the minimum load
capacity of 2000 kg/m2 and having at least 19 mm Marine plywood covered with anti static PVC flooring. In
case of floor panel, 19 mm Marine plywood shall be provided on top of the panel and no steel or aluminium
sheet shall be provided inside the panel. The anti static flooring shall be provided with pacific blue anti static
vinyl robust rolls of at least 2 mm thickness. The floor shall be even surfaced, scratch proof having long life.
The installation of various proposed equipment shall be possible either by direct placement on the floor or
by grouting to the floor or through C rails. The Contractor shall submit the reinforcement and other details
calculations in support of the meeting the load capacity.
1.1.5 Roof
Roofs shall be made of the panels same as specified for walls. A secondary slanting roof of suitable material
shall be provided to protect the primary roof from direct sunlight and rainwater. A minimum down slant of
1:50 shall be maintained from front to back. The secondary roof shall have minimum projections and shall
be hidden by angular profiles on the rooftop to decrease the aerodynamic effect and improve on aesthetics.
The secondary roof shall be suitably clamped/ bolted to the shelter panels to withstand the specified wind
load. The details of the secondary roof and its attachment arrangement shall be submitted for Employer’s
approval during detail engineering. The cable tray shall be attached suitably from the roof and the roof shall
have sufficient strength to support the load of cable trays and the cables installed on the cable tray.
1.1.6 Door
Rev-02
The Shelters shall have one door for main entrance. The door dimensions shall be 1000 mm (W) X 2200 mm
(H). Main door opening outwards shall be provided with external and internal handles/knobs respectively. A
reputed make lock shall be provided in door handle. The make of the lock shall be got approved during
detail engineering. The door can be opened from inside when locked. Door, when locked cannot be removed
even if the hinges are removed. The door shall generally be hinged at right, however, other option may be
also required at some sites to meet the actual site condition. The door shall have aluminium biddings
extrusions in door/jamb profile, replaceable and suitable neoprene rubber gaskets around its border for
proper weather proofing. The door shall also be equipped with a hydraulic auto closure and the door latch /
stopper shall be provided to keep the door in open position. The door shall have a limit switch to indicate
intrusion and switch on one light provided inside the shelter. A canopy of minimum size 1200 mm X 500
mm shall also be fixed up above the external light / door for protection from direct sun/rain. The canopy
shall suitable slope and shall be covered from both sides.
1.1.7 Jointing
All panel to panel connections shall be made with eccentric cam locks or suitable locking system. The wall
to floor and wall to roof jointing shall be made with angular frames of suitable size. The panel to panel
jointing at the corners shall either be suitably angular frames of suitable size or a single corner panel may be
provided. All internal corners shall be jointed suitable angles. All the joints shall be suitable sealed with PU
or silicon sealant to provide 100 % leakage and water proofing. The Contractor shall submit the drawing
indicating details of all joints in support of meeting the specified requirement.
1.1.8 Opening
The shelter shall have provision for openings for required air-conditioners, piping and all electrical and
optical cablings on the wall panels. The details of openings required for different applications and the
locations of the openings shall be decided during detail engineering. All openings shall be custom built
based upon the actual application required at each site. The Contractor shall provide the required cut outs for
above purpose. Any sealed cut outs required for future use may also be provided and the size of this cut out
shall be finalised during detail engineering. All the openings shall be sealed for water and leak proof with
suitable flexible sealing arrangement for the proposed cable connections and also for addition and deletion
of cables/pipes in future. The sealing arrangement shall be fire retardant and type/make/details shall be got
approved by the Employer.
1.1.9 Insulation
The PUF to be used for insulation of the panels shall be CFC free and conforming to latest IS 12436
standards or equivalent International standard. The other parameters shall be as per Table 3.2 as given
below:
Table : 3.2
SNo. Items Required Parameter
1 Thickness 78.6 mm
2 Density 40 kg/m3
3 Compressive Strength 1.2 kg/cm2
4 Tensile Strength 3.6 kg/m2
5 Bending Strength 4.0 kg/m2
6 Adhesion Strength 2.9 kg/m2
7 Dimensional Stability At (-) 25 oC : 0.1%, at 38 oC : 0.1% and at 100 oC :
0.4%
8 Temperature Range (-)15 oC to 95 oC
9 Thermal Conductivity 0.02 kcal/hr/m/oC
Rev-02
Table : 3.2
SNo. Items Required Parameter
10 Fire Resistance As per BS-4735 horizontal burn < 125 mm
11 Water Absorption 0.2 % @100% RH
12 Vapour Permeability 0.08/0.12 g/hr/m2
13 Self Extinguishing Yes
14 Biodegradable Yes
The Contractor shall submit the earlier carried out type tests reports for PUF material. In case the contractor
does not submit the reports or the submitted reports are not meeting the requirements, the contractor shall
carry out the type tests on PUF material for the following:
Thickness, Density, Compressive strength, Tensile Strength, Dimensional Stability, Thermal Conductivity
and Fire resistance.
The installed shelter with one door shall have the heat transmission coefficient K ≤ 0.3.
1.1.11 Colour
The colour shall be stabilised grey on all external sides and off white on all internal sides. The colour of the
slanting roof shall also be stabilised grey. However, the actual colouring scheme shall be finalised during
detail engineering.
Suitable fire & smoke detection system shall be provided in each of the shelters. The offered fire & smoke
detection system shall work on DC supply (-48V) being provided by the Contractor under this contract. In
case, the smoke detector and fire alarm system requires other voltage than the above stipulated voltage (-
48V DC) for operations, suitable converter & hardware shall also be provided by the Contractor. The
Contractor shall provide all required cabling & accessories for full functioning of the offered system with
both power supplies. At least two ionisation type smoke detectors along with fire detection panel shall be
provided below the roof panel in strategic locations inside the shelter. The alarm should activate only if both
fire detectors are actuated to avoid any false alarm. The details, locations and its various logistics shall be
finalised during detail engineering. The operation/activation of the fire detector shall result in the following:
a. An external visual signal and audible alarm sounded outside the shelter.
b. A signal to be given to the telecom equipment panel through potential free dry contact as a local alarm
for its remote monitoring in the control centre.
c. Suitable pilferage proof enclosure for visual and audio alarm outside the shelter.
All the detectors installed shall be tested for actuation and its required operations during SAT. The exact
method of the testing shall be detailed in SAT procedures.
Rev-02
converter & hardware shall be provided by the Contractor. The outside light shall be bulk head type,
powered with ac power supply from ACDB, provided at top of the door and covered with the door canopy.
The bulk head type shall be provided with metallic guard to prevent pilferage. The switch of both internal
and external lights shall be inside the shelter but adjacent to the entrance for easy accessibility. Additionally,
at least one of the normal lights inside the shelter shall be lit up with the opening of the shelter door. One 5
A / 15 A duplex socket with switch shall also be provided in addition to the requisite switches for the normal
and emergency lights.
1.1.15 C – Rails
C-rails made of extruded aluminium alloy of suitable size along with required number of lock-nuts shall be
provided inside and outside the shelter to support various items like lighting, AC Distribution Box (ACDB),
DC Distribution Box (DCDB), Fire detector along with the panel, cables and all other accessories. The C-
rails may also be used for supporting cable trays from the roof, mounting of equipment on the floor and on
the wall. The requirement of C-rails shall be finalised during detail engineering.
The above load capacities have been identified as minimum requirement. However, during detail
engineering, to meet the actual load requirement for cable tray, ACDB, DCDB, C-rails, Air-conditioning
system, battery, batteries chargers, telecom equipment, lighting etc. to be supplied and installed inside the
shelter, the actual localised loading requirement may be higher and the supplied shelter loading capacity
shall meet the actual localised loading requirement at no additional cost to POWERGRID.
Rev-02
1.1.18 Structural Stability
Resistant to various volumes of rain, dust & sand impinging from various directions over different
durations and different speeds.
Resistant to corrosion against water, industrial air and saline air.
Resistant to decomposing vegetation, rodents, termites and micro-organisms.
All cables and cabling of required size and capacity shall be supplied, installed and terminated with
necessary and required accessories among all the equipment/systems being supplied under this Package. The
cables from cable ladder to equipment cable entry height shall be installed in the wall of the shelter in PVC
cable conduits and in flexible conduits from shelter wall to equipment. The cables shall be dressed properly
and suitably attached with the shelter panel. No hanging cables shall be allowed.
1.1.21 Structural
All structural steel shall conform to latest IS: 2062 or equivalent International standard. The ISMBs shall
conform to IS – 808 or equivalent International standard. The structural MS pipes shall conform to IS:1161
or equivalent International standard. The steel work shall be galvanised after full fabrication as per latest IS
standards and the coating thickness shall be greater than 127 micron. All welding shall be as per IS – 816 or
equivalent International standard. All nuts and bolts shall be galvanised and conform to IS : 6639 or
equivalent International standard. All fittings and hardware used in the shelters shall be made of corrosion-
resistant aluminium or galvanised steel as specified in the relevant clauses of this specification.
The requirement of steel/aluminium sections shall also be provided and no separate payment shall be made
in this regard.
1.1.22 Earthing
For satisfactory operation of the equipment inside the shelter, good and proper earthing is required at each
site. The earthing resistance generally varies depending on soil resistivity. The earthing system at each site
shall be provided by the Contractor with earthing resistance not exceeding the five (5) ohms. The
Contractor shall provide the pipe type earthing along with the necessary hardware and accessories required.
Minimum two earth pits shall be made at each location. However, if required resistivity is not met, then,
sufficient nos. of pipe type earthing shall be provided by the Contractor. The Contractor shall submit the
earthing pit diagram for Employer’s approval.
An earthing ring of copper strip of minimum size 25mmX3mm shall be made inside the shelter. Each
equipment shall be connected to above earthing ring through 70sqmm copper cable. The connectivity from
earthing pit to the shelter earthing ring shall be made by the Contractor through two (2) nos. of 50 X 6 mm
GI strips. The connection of GI strips with the copper strips shall be made through flexible copper cable and
bi-metal washers for proper connectivity. The GI strips for earthing pit to shelter shall be buried inside the
ground.
Three days after completion of the earthing pit, the earth resistance shall be measured in the presence of
Employer’s representative and test results for each location shall be submitted for Employer’s approval.
All the equipment shall be connected properly to this earthing system for their safe operation.
Rev-02
1.1.23 Foundation System for Shelter
The Contractor shall design and construct complete foundation system for all finalised shelter locations
depending on the type of soil, including supply and furnishing all the material & labour, tools & tackles,
plant and machineries etc. as required for successful completion of the job. The foundation system shall also
include the following:
Site preparation
Soil characteristics assessment as required for foundation design for each site including detail soil
investigation, if required.
Water level assessment
Raising of site level above maximum flood limit level to avoid any water logging in the shelter area.
Concrete pedestals (in situ) along with base slab for the foundations located on ground and concrete
pedestals for roof top locations along with supply and fixing of necessary holding down / anchor
bolts.
PCC and finish of surface below and around shelter location with suitable slope.
Installation of base frame and sub-frames on the pedestals through ISMB channels.
Stair access for shelter.
Backfill material around foundation and shelter shall be suitable for the purpose for which it is used and
compacted to the satisfaction of the Employer. Excavated material not suitable for use or not required for
backfill shall be disposed off in area as directed by the Employer, including all leads and lifts.
Whenever water table is met during the excavation, it shall be dewatered and water table shall be maintained
below the bottom of the excavation level during excavation, concreting and backfilling.
For roof top shelters, the Contractor shall also prepare the site suitably for shelter installation on the
pedestals. In all cases, each site shall be fully prepared before start of foundation activities up to satisfaction
of the Employer.
The foundation of shelters to be installed on the ground shall consist of RCC pedestals of minimum 600 mm
above levelled ground. The depth of pedestals below the ground shall be minimum 1500 mm including
bottom slab. The size of bottom RCC slab of the foundation shall be minimum 600 mm X 600 mm for a
minimum 250 mm depth. The reinforcement shall be as stipulated at clause 2.4.4 below. The PCC (1:4:8) of
minimum depth 75 mm shall be provided below the bottom slab of minimum size 750 mm X 750 mm. The
size of the pedestals shall be minimum 300 mm X 300 mm. The grade of concrete shall be M20 (1:1.5:3).
The concrete cover for the reinforcement shall be minimum 50 mm.
Rev-02
The foundation of shelters to be installed on the roof top shall consists of RCC pedestals of size minimum
300 mm X 300 mm and 300 mm above roof surface of M20 (1:1.5:3) grade. The bottom of the pedestal shall
be connected and attached with the existing roof structure/slab. The reinforcement shall be as stipulated at
clause 2.4.4 below.
The exposed portion of the concrete pedestals shall be plastered with 1:4 cement plaster for smooth finish.
The above pedestal dimensions are minimum requirement and the Contractor shall provide the required size
of pedestals depending upon the soil bearing capacity and other soil parameters of each site to support the
installed shelter along with all equipment. The detailed design for all above type of foundations shall be
submitted to the Employer and got it approved before commencement of work at site.
The shelter shall be fixed to the pedestals through ISMBs 200 mm minimum and sufficient number of sub-
frames with suitable anchor bolts. The required ISMBs and sub-frames shall be provided by the Contractor
as part of shelter/foundations. The required number of pedestals shall be provided for shelter installations,
however, minimum one pedestal is to be provided at each corner of the shelter. The Contractor shall provide
the required and necessary foundation system at each site irrespective of soil to meet the requirement and
submit the civil/structural/foundation design and drawings along with the load calculation for Employer’s
approval. All required foundation system and related works shall be in Contractor’s scope and no additional
payment shall be paid to the Contractor irrespective of soil characteristics and site conditions.
The suitable staircase shall be provided at each shelter location in front of the door for easy entry into the
shelter as a part of foundation/pedestal system and no separate payment shall be made in this regard.
1.1.26 Concreting
After completion of foundation work at each shelter location, PCC (1:2:4) of depth minimum 100 mm shall
be provided below the shelter position and outer sides for shelter as decided during detail engineering /
execution. There shall be adequate slope in the Shelter area PCC to avoid water logging.
The Contractor shall also provide the RCC platform of about 600 mm height for installation of DG set. The
exact area and the height of RCC required for DG set and shelter area shall be finalised during detailed
engineering. At few locations, PCC platform for DG set may be provided. Quantities of PCC have been
identified in BoQ for above.
The cement concrete used for foundation shall be of grade M-20 corresponding to 1:1.5:3 nominal mix ratio
with 20 mm coarse aggregate. All the properties of concrete regarding its strength under compression,
tension, shear, punching and bend etc. as well as workmanship will conform to latest IS standards or
equivalent International standard.
The Portland cement used in concrete shall conform to 33 grade (IS:269) or 43 grade (IS:8112) or 53 grade
(IS:12269) or equivalent International standards.
The Puzzolena cement used in concrete shall conform to IS : 1489 or equivalent International standard. The
curing time of Puzzolena cement shall be decided at the time of execution of the work under the contract
based on the certificate from a reputed laboratory which will be obtained and submitted by the Contractor.
Cement of only POWERGRID approved make shall be supplied.
The water used for mixing concrete shall be fresh, clean and free from oil, acids and alkalies, organic
materials or other deleterious substances. Portable water is generally preferred.
Rev-02
Reinforcement shall conform to IS: 432 or equivalent International standard for MS bars up to 6 mm and
hard drawn steel wires and to IS : 1139 and IS : 1786 or equivalent International standard for deformed and
cold twisted bars 8 mm and above respectively. All reinforcement shall be clean and free from loose mill
scales, dust, loose rust and coats of paint, oil or other coatings, which may destroy or reduce bond.
Contractor shall supply, fabricate and place reinforcement to shapes and dimensions as indicated or as
required to carry out the intent of drawings and specifications. Reinforcement of only POWERGRID
approved makes shall be supplied.
Form boxes shall be used for casting all types of foundations and pedestals.
The concrete shall be laid down in 150 mm layers and consolidated well, so that the cement cream works, up
to the top and no honey-combing occurs in the concrete. Preferably, a mechanical vibrator shall be employed
for compacting of concrete. However, in case of difficult terrain, manual compaction may be permitted at
the discretion of the Employer. Monolithic casting of foundations must be carried out. After concreting the
pedestal portion to the required height, the top surface should be finished smooth.
Wet locations shall be kept completely dewatered, both during and 24 hours after placing the concrete,
without disturbance of the concrete.
If the concrete surface is found to be defective after the form work has been removed, the damage shall be
repaired with rich cement sand mortar to the satisfaction of the Employer before the foundation is back
filled.
1.1.29 Curing
The concrete shall be cured by maintaining the concrete wet for a period of at least 10 days after placing.
Once the concrete has set for 24 hours, the pit may be backfilled with selected moistened soil and well
consolidated in layers not exceeding 200 mm thickness and thereafter both the backfill earth and exposed
pedestal shall be kept wet for the remainder of the prescribed 10 days. The exposed concrete chimney shall
also be kept wet by wrapping empty cement bags around it and wetting the bags continuously during the
critical 10 days period.
1.1.31 Installation
The shelter shall be installed on the foundation system as specified above and to meet the actual requirement
as per actual site/soil conditions. The installation of shelters shall be carried out in such a way that it shall
meet all specified requirement. The installed shelters shall be suitable for both transporting in assembled
condition to another location and dismantling, transporting to another site and reassembling there.
The Contractor shall make their own arrangement for AC supply / DG set during installation/testing of the
system.
Rev-02
1.1.32 Finish
The final finish of the installed shelter system shall show good workmanship. The panels and floor shall be
totally scratchproof. The floor shall not have any uneven surface. The total shelter shall be air tight, the roof
and all joints shall be leak and water proof and the door shall be easily lockable & unlockable.
The Contractor shall provide the earlier carried type test reports for the PUF material and other
sub systems of the shelter.
The following tests shall be carried out during Factory Acceptance testing (FAT):
FAT on other items shall be carried out as specified in this specifications and relevant standards.
The site acceptance testing shall be carried out for each site. The installed system shall be powered up and
all the equipment shall be tested and commissioned. The various installed system shall be tested for the
specified functional requirements and shall be as per approved drawings. The SAT shall be carried in an
Rev-02
integrated way and not individual equipment basis to demonstrate the integrated functioning of the installed
system. The tests shall be carried out on following minimum items during SAT:
1.1.36 Marking
The following information shall be provided outside the shelter and near the door engraved on a steel metal
plate:
1.2.1 General
The air conditioning system shall be provided in the shelters to be used for housing Telecom equipment,
power interface unit, VRLA batteries, battery charger etc. throughout the country. Repeater Shelters are
placed for amplification of telecom signals in between the fibre optic links. The Contractor may note that
these shelters are generally located in unmanned areas; therefore, the air-conditioning system shall be
rugged, reliable, maintenance free and designed for long life.
Bidder shall furnish the details/document in support of above Technical experience of manufacturer along
with bid.
Both units shall be independent of each other. The units shall run one by one in pre settable time bound
cyclic ON/OFF mode. However, during running of AC unit 1, if the inside temperature of the shelter reaches
to a predefined value, the AC unit 2 shall also start running to maintain the inside temperature to specified
24 oC. After achieving this temperature, the other unit shall again shut off.
Problem/ fault in one of the unit shall not hamper the working of other unit and during such fault in any of
the unit; the alternate unit shall take over and continue to operate till the faulty unit is operational again.
Both units shall never start at the same time. If the condition is such that both units shall start together then
internal time delay of at least 10sec shall be provided in starting of each unit to avoid surge.
In free cooling mode, the refrigerant cycle of AC unit shall be switched off and outside air (after filtration)
shall be circulated inside the conditioned space through the operation of dampers provided with suitable
sensors. It should be possible to run the Free Cooling Unit (FCU) on both AC & -48V DC Power supplies.
This mode shall come into operation in the following conditions;
i. When the ambient temperature is below a preset value, which is to be decided during detailed
engineering.
ii. In case of failure of refrigeration system of both the units.
The failure of free-cooling feature shall not hamper the normal operation of Air Conditioning units.
1.2.4 Operational Life
The air conditioning system to be supplied shall have operational life of 10 years.
1.2.5 Design
The air-cooled self contained package AC system shall be designed as per following conditions:
Rated Capacity : 1.5TR/2TR
Type of Discharge : Free Flow.
Air inlet Temp (Return Air) : 24 0C (DB) RH : 50
Temperature Variation allowed : 1 0C
Ambient Air Design Temp : 45 0C
(entering the Condenser)
No. of Refrigeration Circuits : Two
Type of load Factor : High sensible heat load (SHR>0.9)
Running of both units: Start of IInd unit along with Ist unit in case sensor senses high
temperature.
Further, the free cooling function may be enabled/ disabled with help of the controller.
1.2.11 Earthing
The AC equipment shall be properly earthed by connecting it to the earthing system.
Supply and installation of all required cabling, wiring and termination and accessories including surge
arrestors, motor starters, circuit breakers and switches from the power supply point/ Meter point to the
various units via ACDB shall be carried out by the Contractor.
Rev-02
1.2.13 Testing
The type testing of the air-conditioning system shall conform to latest IS: 8148 standards or equivalent
International standard.
1.3.1 General
The DG sets shall generally be installed on ground and the required RCC/PCC floor shall be provided by the
Contractor. Single Phase DG sets of rated capacity without AMF panel are required. AMF panel shall be the
part of Power Interface Unit (PIU). Most of these DG sets shall be installed at unmanned sites located in
rural/remote villages/towns. The DG set shall have an operational life of 10 years.
The DG set shall be offered from a manufacturer of Diesel Generator set and Diesel Generator set
manufactured by such manufacturer should have been in operation for at least one (1) year as on the
originally scheduled date of bid opening.
Bidder shall furnish the details/document in support of above Technical Experience of manufacturer along
with bid.
The diesel engine shall be direct injection, 4 stroke cycles, multi cylinder, air-cooled/ water-cooled, naturally
aspirated/ turbo charged, instantly started, operating at a nominal speed of 1500 R.P.M. and capable of
developing requisite Brake Horse Power i.e. the rated horsepower of the engine, at the generator
synchronous speed, with all accessories attached, shall not be less than the required power as specified in the
appendices. In addition, the horsepower rating shall take into account the generator efficiency, losses and
maximum rated environmental conditions stipulated in Clause 1.3.19. All moving parts of the engine shall
Rev-02
be mechanically guarded in such a manner that a human finger cannot touch a moving part. The diesel
engine shall be equipped with a dry type air filter system.
1.3.5 Governor
The engine shall be equipped with class A-1 governor or better as per IS 10000 Part-VII or any other
equivalent International standard. The speed regulation shall be as per the above governing class.
The Contractor shall also indicate the fuel consumption of the offered DG sets at 25%, 50%, 75% and 100%
of rated loads along with their bid in the DRS format.
Fuel required to carry out all kind of tests including site acceptance tests shall be supplied by the Contractor.
The engine control shall provide for multiple crank start-up cycles. Each cycle shall be approximately 10-
seconds of cranking followed by 10-seconds of rest. The starting circuit shall automatically be disconnected
after the start up of the engine. If the engine does not start after three (user adjustable number) attempts, the
starting circuit shall be disabled and an alarm indication ("over crank") shall be provided. A potential free
contact shall be provided to interface these alarms with the Equipment NMS.
The starting time of the DG set in ‘AUTO’ mode shall be continuously and linearly adjustable from 5
minutes to 8 hours from the time of power failure sensing. The starting of DG set shall be based on the
condition of the 48V DC battery voltage (being used for telecommunication equipment) and temperature
inside shelter. For this purpose, the required auxiliary contacts from DC power supply system shall be
available in DCPS cabinet and for sensing temperature inside shelter, the required thermostat shall be
Rev-02
provided by the DG Contractor. The exact time setting and other settings of DG start up shall be finalised
during site acceptance on site-to-site basis based on the actual site conditions.
a). Microprocessor based relay with composite meter for digital display of;
i. AC mains Voltage & Generator Voltage
ii. Generator Current
iii. Power Factor
iv. Output KW meter
v. Output AC frequency meter
vi. RPM indication
vii. Over speed indication
viii. Engine hours indication (Cumulative)
b). Mode selector switch for setting the panel on any one position such as OFF or Auto/
Manual/ Test. The operation of the DG set shall be possible in any of the modes.
c). Engine ON/OFF switch (Push button type)
d). Emergency Stop switch (Push button type)
e). ON delay timer for load change over.
f). ON delay timer for engine shut off.
g). Indicating lamps to indicate ‘Mains ON’, ‘Load on Mains’, ‘DG Running’, ‘Load on
DG’, ‘Battery charger ON’
h). Audio visual alarm for
i. Low lubricating oil pressure
ii. High water temperature (for water cooled DG)
iii. High cylinder head temperature (for air cooled DG)
iv. Start failure
v. DG over load.
i) Suitable battery charger complete with voltage regulator, float or booster selector switch, on-off
switch, digital voltmeter and ammeter for charging the battery from mains operating 240V/ 50 Hz
j). MCCB of suitable rating
k) Two no. contactors of suitable ratings (one for DG set and one for AC mains) with overload
relay.
l) Under voltage relay for Mains.
m) Instrument and control fuses.
n) Any other switch, instrument, relay or contactor etc. essential for smooth and trouble
free functioning of DG set with AMF panel. (To be specified by the bidder with complete detail of the
item).
Standard colour codes and numbered ferrules shall be used for wiring the AMF panel. Sensing and control
relays shall be of continuous duty, industrial control grade type. The transfer breaker shall be rated for
Rev-02
continuous duty. The breaker shall be interlocked to ensure non-paralleling SEB power supply and DG
supply.
Following automatic shut down protection system for DG set shall also be integrated in the control panel;
i. Low lubricating oil pressure shut down.
ii. High coolant (water) temperature shut down.
iii. Engine over speed shut down.
iv. Over load shut down.
v. Short Circuit shut down.
vi. Over Voltage shut down
vii. Low Fuel Level
viii. Earth Fault shut down.
ix. Emergency Stop
The AC mains supply shall be of either single Phase or three Phase. The loads connected shall be single
phase in nature.
1.3.11 Alternator
The Contractor shall supply alternators in their offered DG sets only from the reputed manufacturers i.e.
Crompton-Greaves / Kirloskar / FG Wilson / ELGI / KEL makes as per latest BS 5000/ IS 4722 standards.
Details of alternator shall be submitted by the Contractor along with the bid.
The alternator shall be self excited, self regulated, screen protected, double bearing, brushless type, drip
proof, continuous duty type, synchronous and suitable for 1500 RPM. 0.8 P.F lagging, horizontal foot
mounted, with class H insulation.
The alternator shall also have a solid state type Automatic Voltage Regulator (AVR) suitable for single
running with control limits of 1% from no load to full load under normal load changes. It shall be of static
type and complete with cross current compensation. The regulator shall be provided with voltage adjusting
potentiometer and shall be complete with all alarm contacts, internal wiring etc.
The alternator shall be capable of carrying 50% overload for a duration of one minute.
The alternator shall be suitable for 20% over speed for two minutes.
The alternator shall be capable of carrying 10% overloading for one hour in any period of 12 hrs running
without injury.
Rev-02
1.3.13.2 Fresh air intake for the Engine shall be available abundantly; without making the Engine to gasp
for air intake. A chicken mess shall be provided for air inlet at suitable location in enclosure which shall be
finalized during detailed engineering.
1.3.13.3 The Enclosure shall be designed and the layout of the equipment inside it shall be such that there
is easy access to all the serviceable parts.
1.3.13.4 Engine and Alternator used inside the Enclosure shall carry their manufacturer’s Warranty for
their respective Models and this shall not degrade their performance.
1.3.13.5 Exhaust from the Engine shall be let off through Silencer arrangement to keep the noise level
within desired limits. Interconnection between silencer and engine should be through stainless steel flexible
hose/ pipe.
1.3.13.6 All the Controls for Operation of the D.G. Set shall be easily assessable. There should be
provision for emergency shutdown from outside the enclosure.
1.3.13.7 Arrangement shall be made for housing the Battery set in a tray inside the Enclosure.
1.3.14.1 The enclosure shall be fabricated from at least 14 Gauge CRCA sheet steel and of Modular
construction for easy assembling and dismantling. The sheet metal components shall be pre-treated by Seven
Tank Process and Powder coated (PURO Polyester based) both-in side and out side – for long life. The hard-
ware and accessories shall be high tensile grade. Enclosure shall be given a lasting anti-rust treatment and
finished with pleasant environment friendly paint. All the hardware and fixtures shall be rust proof and able
to withstand the weather conditions.
1.3.14.2 Doors shall be large sized for easy access and provided with long lasting gasket to make the
enclosure sound proof. All the door handles shall be lockable type.
1.3.14.3 High quality rock wool of required density and thickness shall be used with fire retardant thermo
– setting resin to make the Enclosure sound proof.
1.3.14.4 Points for Neutral/Body earthing shall be available at two side of the enclosure with the help of
flexible copper wires from alternator neutral, and electrical panel body respectively. The earthing point shall
be isolated through insulator mounted on enclosure.
a. Auto Mode
b. Manual Mode
c. Test Mode
In the ‘AUTO’ mode, the DG Set shall start only after a set time delay when either the primary AC source
has failed or conditions prevail as indicated below;
When the main source power fails, the DG set shall include detection and control to automatically
disconnect the primary AC source, start the DG set and extend power to ACDB after the set time period of
Rev-02
the timer. The time delay is continuously & linearly adjustable at site from 5 minutes to 8 hours as specified
at Clause 5.2.6. The engine shall also start automatically after detecting a predefined temperature (20 oC to
55 oC continuous) inside the shelter or initiation from 48V DC under-voltage contact from DCPS. All
required control like thermostat, extension of potential DC under-voltage contact from DCPS shall be
provided by the Contractor to support the above controls.
All phases of primary AC sources voltage shall be monitored. The automatic start-up system shall detect
failure or abnormal conditions specified and start the generator set. At the time of loss of primary voltage or
an abnormal condition of low phase voltage, a start control shall be initiated. The automatic start shall try the
start-up of the generator set for three successive attempts. If the primary AC returns during the start-up
attempt, the start-up sequence shall be stopped.
If at any time during operation of the generator set the selector switch is set to ‘OFF’ position, the generator
shall shut down and be disabled from starting.
A test operation of DG set shall be possible by putting the control switch in “TEST” position from where the
generator shall initiate an automatic start, just as if there had been a power interruption to the primary power.
Upon removal of the selector switch from “TEST” position, the generator shall initiate an automatic
shutdown sequence. However, there shall be interlock such that Main circuit breaker of DG set is in ‘OFF’
condition while the engine is started in “TEST” position.
Rev-02
installed on rooftop. The exact requirement shall be finalised during detail engineering based on actual site
conditions.
1.3.18.2 Earthing
The Contractor shall suitably connect the DG sets with the integrated earthing system being provided by the
Contractor under this package. The neutral of alternator shall be earthed separately.
1.3.18.3 Trenching
The Contractor shall prepare necessary cable routes for installing cables and earthing system from DG set to
the shelter and earthing pits. The cables shall always be installed inside the GI pipes of suitable size
embedded properly with PCC finish. In case the DG set is installed on ground and the shelter is installed at
roof top, the necessary cable trenching/ GI pipe shall be provided from DG set to the building ground from
where the cables shall be installed in the wall of the building. The cable trays with proper cover and supports
shall be provided from bottom of the trench at the ground near the building up to the shelter installed at the
roof top. The Contractor shall submit the detail drawings for the same for Employer’s approval.
Generally, ACDBs shall be part of Power Interface unit (PIU), however, at few locations, Standalone ACDB
shall be required where PIU is not required. ACDBs shall be wall mounted enclosure/panel as finalized
during detailed engineering. They shall have indicating lamps and voltmeter to indicate three phase voltage
on the bus.
The MCCB and sub-assemblies shall be easily replaceable and maintainable. The MCCBs of requisite
ratings must conform to IEC-60947-2 and IS 13947-2/IEC 60947-2. All MCCBs shall provide over-current,
short circuit protection and coordinate with associated breakers in upstream & downstream such that faults
are cleared reliably with discrimination.
The contractor shall extend safety earth connections from Input ACDB panel & Output ACDB panel to
nearest earthing system being provided under this contract.
Rev-02
1.3.21 Testing of DG sets
1.3.21.1 Type Test
The Contractor shall submit the earlier carried type test reports for the engines, Alternator & enclosure of the
offered DG sets for the highest rating of offered DG set as per the latest relevant IS standards or equivalent
International standard for Employer’s approval. The type tests on Alternators shall be carried out as per
Table 5.10(a) as given below.
Table-5.10(a)
List of Tests for DG Set
SNo. Test Type Factory Site
Test Acceptance Acceptance
Test Test
A. ALTERNATOR
1. Measurement of resistance √
2. Regulation test √ √ √
3. Measurement of open circuit characteristics √
4. Measurement of short circuit characteristics √
5. Efficiency test √
6. Temperature rise test √
7. Occasional excess current test √
8. Over speed test √
9. Insulation resistance (both before & after high √
voltage test)
10. High Voltage test √
11. Determination of deviation of voltage waveform √
sinusoidal
Note : All the above tests as per IS: 4722 or equivalent International standard
B. DG Set (including Alternator)
1. Noise and vibration test For all √
2. Load Test Type √ √ (Note )
tests
3. Functional tests on control panel, starting √ √
provision AVR and speed governor
Note: SNo. 1 above: As per standard IS 12065/12075 or equivalent International standard.
1)During FAT, Load test shall be conducted on each rating of DG sets before dispatch to site as
follows:
a) No load test for 15 minutes
b) 100% Load test for 8 hrs
c) 110% load test for 1 hr
2) During SAT, 6 hours load test shall be carried out with existing load.
Rev-02
SNo. Test Type Factory Site
Test Acceptance Acceptance
Test Test
3) The Oil consumption, governing, noise and vibration shall be recorded during the testing period.
Further during above test, AMF panel associated with highest rating DG set shall be integrated to
check all the functional requirements and other requirements as per technical specifications.
---End of Table---
1.3.22 Marking
Rev-02
Power Interface Unit (PIU) shall integrate the surge protection devices, AMF panel for DG control, AC
voltage stabilizer, and AC distribution panel etc. in a single unit to save the valuable floor space inside the
shelter and to provide quality AC power supply to the various systems including SMPS based DC power
supply system, air conditioning system etc. used in telecom applications.
Suitable circuitry along with all hardware, cables, relays, sensors etc. shall be so provided that it shall be
possible to select the healthy phase(s) automatically and have the output at the stabiliser and the load
requirement can be met. The Contractor shall submit the scheme for Employer’s approval during detail
engineering.
There should be a Manual by pass arrangement for bypassing the Healthy Phase Selector.
Between Requirement
R, Y, B & N Iimp ≥ 50 kA, 10/350 µS for each phase
N & PE Iimp ≥ 100 kA, 10/350 µS
Iimp= Value of Lightning Impulse Current
Rev-02
Between Requirement
R, Y, B & N In ≥ 10 kA, 8/20 µS for each phase
N & PE In ≥ 20 kA, 8/20 µS
In= Value of Nominal Discharge Current.
The protection system for both the above stages shall be reusable after clearance of surge. In case of fault,
provision for manually bypassing the protection system should be available to ensure the operation without
protection system. The manufacturer shall give complete details of the arrangement provided for the purpose
during detail engineering and also ensure and demonstrate the effectiveness of the arrangement. Test
Certificate from a reputed third party lab may be accepted provided the protective devices of both stages
have been tested in the same lab.
Table 6.1
S. No. Items PIU for Urban locations PIU for Rural locations
Output Voltage (Volts) 230 V± 10% (Single 230 V± 10% (Single Phase)
3
Phase)
4 Voltage correction speed 400 V in 1 μsec 400 V in 1 μsec
5 Efficiency (excluding IT) > 96% > 96%
6 Frequency 48 – 52 Hz 48 – 52 Hz
The AMF panel shall be equipped with suitable instrumentation, interlock and protection arrangement,
suitable annunciation and indications etc. as defined in the Section 5.2.7 of this specification for proper start
up, monitoring, control and safe operation of the DG set.
An option for selection of Auto / Manual Mode operation should be provided on the front panel of the PIU.
Operation (Start / Stop) of the DG set in manual mode should be available on the PIU. In manual mode,
AMF logic will be totally bypassed. However during manual mode, the DG protections will not be
bypassed. A change over switch shall also be provided for total bypassing the AMF.
Rev-02
1.4.7 PIU Controller
Contractor shall integrate the Alarms of various Auxiliaries of shelter with the PIU and Alarms shall be
monitored by Central Supervisory Unit. Central Supervisory Unit shall be designed to facilitate better
interface of man and machine. It shall consist of High-Speed micro controller displaying true RMS for all
voltage & current through LCD display. All the inputs to the measurement board shall be duly protected
against surge as per IEEE-62.41. The measurement circuit shall be rated at 1.5 times the maximum input
range. The unit shall be equipped to log 500 events with date and time stamping including DG start and stop
logs. It shall display various site conditions like Mains ON, DG ON, Smoke/ Fire Alarm, Over Load,
Charger MODULE fail, DG Fuel Low, DG fail to start, DG fail to stop, Alternator fail, LLOP, DG overload,
Mains Fail, Site battery low, DG battery low, HCT/HWT, High Shelter temperature etc. Various Mains and
DG related measurements viz. Mains energy measurement, DG energy measurement, DG accumulated
hours, peak energy requirement of site etc. shall also be displayed.
Contractor shall integrate and extend the Potential Free Contacts for monitoring at NOC for following
minimum alarms;
i) Mains Fail
ii) Door Open
iii) High Room Temperature
iv) DCPS battery Low
v) Rectifier Fail
vi) Fire and Smoke
vii) DG Fail to Start
viii) LLOP
ix) Fuel Low
x) DG ON LOAD
xi) DG ON
xii) HCT
xiii) DG Over speed
xiv) DG Fail to Stop
xv) Other Common DG Faults
It must support a RS 232 port for PC interface for programming / reconfiguration of the parameters through
laptop.
The AC mains and DG set shall be connected to PIU unit through MCCBs of suitable ratings.
Rev-02
DG set. DG sets supplied under earlier packages having capacity 15kVA or below may also be available at
sites.
The enclosure (rack) shall be freestanding type of design and shall have sufficient structural strength to
withstand the ultimate mechanical load capacity without any deformity. Cable entry shall be from the
bottom/top of the enclosures. The design of the rack (enclosure) shall be modular allowing easy maintenance
and installation such that replacement or taking out of one subsystem for repair or maintenance shall not
require dismantling of whole system. The rack shall be free of sharp edges or sharp corners. Rack mounting
arrangement shall provide easy access from front, rear and top for installation and maintenance.
Where cables pass through metal panels suitable arrangement including bushings shall be provided to
protect cables from damage. Bus-bars shall be suitably spaced and insulated to prevent any possibility of
short circuit between bus-bar and/ or rack.
With doors in position, all visual alarms and meters shall be clearly visible. In case of hinged doors, meters
and alarm indicators are permitted on the door provided the fixtures on the door do not restrict the
movement of door in any way.
1.4.10.1 Components
The component parts of the equipment shall be of professional grade from reputed manufacturer to ensure
continuous and safe operation of the equipment including its sub systems. The component shall conform to
relevant IEC/IS standards and Complete PIU unit shall ensure compliance to safety as per IEC-60950 or any
other international standard.
1.4.10.3 Earthing
The PIU unit including its subsystems shall be properly earthed by connecting it to the earthing system
being provided by the Contractor under this Package.
1.4.11 MTBF
The mean time between the faults of the PIU and its subsystems shall be more than 70,000 hrs.
1.4.12 Installation
The transportation of PIU unit and its complete installation at respective sites as per attached appendices
shall be carried out by the Contractor. All type of cables or associated accessories shall be supplied and
installed by the Contractor. Connection to SEB supplied AC mains and ACDB etc shall also be carried out
by the Contractor
1.4.13 Testing
Rev-02
1.4.13.1 Type Testing
PIU shall conform to EMI/EMC requirements as per IEC-870-2-1 standards. It shall also conform the
Environmental requirements as per the TEC Standard for Environmental testing i.e. SD: QM-333 Mar 2010
(with amendments, if any) in category B2.
Electrical and mechanical safety and Performance test shall also be carried out on PIU as per specification.
The Contractor can also submit the earlier carried out type test reports on the offered system for above tests.
In order to provide reliable power supply to communication equipment at various locations, 48 V DC Power
Supply (DCPS) system is to be provided as a part of this project. This section describes the technical
requirement of DC power supply & associated Battery.
The DC Power Supply system shall be capable of meeting the load requirements for various Telecom
equipments. The rating of offered SMPS modules shall meet Employer’s requirements of DCPS system as
stipulated in the BoQ.
The DC Power supply system shall have a single DCPS system as per conceptual configuration diagram
given in Fig.3-1, shall be supplied.
Surge protection devices shall be installed in the DCPS panel to provide adequate protection against current
and voltage transients introduced on input mains AC due to load switching and low energy lightning surges.
These protection devices shall be in compliance with IEC 61312, IEC 61024 and VDE 0100-534 for
following surges:
It shall be provided with Class ‘B’ & ‘C’ type surge protection device. The device must be provided with
Class B type lightning current arrester (Switching Type) with a discharge current capacity of at least 50 kA,
10/350 µs, and Class C type surge arrester (linear device) as per IEC 61643-1. The blind spots shall be
avoided in accordance to IEC 61312. The Class ‘C’ surge protection device should be pluggable type,
equipped with features of thermal disconnection, & health indication and potential free contacts for surge
arrestors connected between phase & neutral.
1.5.1 General Technical Requirements for SMPS based DC power supply units
SMPS based DC power supply system is to be used in Auto Float-cum-Boost Charge mode as a regulated
DC Power source. DCPS system is to be installed indoors and shall be provided with IP21 panels. The
System shall consist of the following:
SMPS modules
Rev-02
a) Controller module to control and monitor all DCPS modules.
The Panel, Distribution/Switching arrangement shall be provided for the ultimate system capacity. Ultimate
System capacity is defined as 150% of the present capacity specified. The ultimate capacity is over and
above the requirement of redundancy wherever specified. All factory wiring for the panel shall be for the
ultimate capacity so that only plugging-in of SMPS module shall enhance the DC power output.
The size of fuses, MCBs, switch, bus etc shall be suitable for the ultimate capacity.
The SMPS modules of DCPS system shall be suitable for operation from single phase A.C. mains/DG set
supply. However, the input AC mains supply to DCPS system shall be 3-phase, 4 wire which shall be evenly
distributed among all the offered SMPS modules.
The basic modules shall operate at specified ratings and conform to requirements stipulated in this
specification. The DCPS system shall meet requirement of the latest TEC specification / IEC/BS for other
parameters as applicable.
1.5.1.2 Wiring
All insulated conductors except those within the confines of a printed circuit board assembly shall be of the
rating enough to withstand the maximum current and voltage during fault and overload. All insulated
conductors/cables used shall conform to IS 1554 or equivalent international standard.
High conductivity Cu bus bar shall be provided and shall be sized to take care of the current of ultimate
DCPS system capacity for which it is designed. However, it shall not be less than 25mm X 5mm.
1.5.1.4 Earthing
Two earth terminals shall be provided in the frame of the system. The Contractor shall connect these earth
terminals to the earth bus. All modules and devices shall be connected to these earth terminals. The hinged
door, if provided shall be connected to the panel with braided Cu at two points at least.
The Contractor shall propose a scheme for marking and labelling the inter panel cables by Halogen &
Silicon free labels of polyamide ensuring scratch proof labelling with the use of solvent free ink & latest UV
Technology making it environment friendly printing with a WIPE RESISITANCE according to DIN EN
61010-1/VDE 0411-1 and get it approved from the Employer. A cabling diagram, screen printed or any
other better arrangement ensuring better life expectancy shall be placed in the inside of the front door or any
other convenient place for ready reference of the maintenance staff.
The mechanical and electrical requirements of the Panel are described as below:
The SMPS modules shall be accommodated in panels. The system shall employ a modular configuration to
provide flexibility, keeping in view the future load requirements of DC Power. The system shall be
Rev-02
configured for ultimate capacity as brought out in Section 3.1. The Control, Monitoring, Alarm arrangement
and DC & AC distribution shall be provided suitably in the panel.
The SMPS modules shall be provided as per the load requirement stipulated in the Appendix, BOQ. The
DCPS system shall comprise of N+2 Modules. In case of DCPS system having N=1, the SMPS shall
comprise of N+1 modules. Here N refers to number of SMPS modules to meet the load requirements
specified in the Appendix, BOQ and battery charging current. The current rating of each module shall be
considered as output current of the SMPS module at nominal voltage (48V).
Total Current
N=
Current rating of each SMPS module at 48 V
The Distribution/switching/Alarm unit shall be provided for the ultimate system capacity. All AC, DC or
control/alarm cabling/wiring shall be pre-wired for the ultimate capacity so that mere plugging-in of SMPS
module shall add to the DC power output.
For the enclosures/panel, the front door (if provided) shall not be wider than 80 cm and rear door may be of
hinged or removable type with locking as per standard design of the manufacturer. Keyed locking is
required with identical keys for all enclosures. The enclosures shall not exceed 220 cm in height. The
thickness of the structural frames and load bearing members shall be minimum 2.0 mm and for others shall
be minimum 1.6 mm. The panels/boards shall be equipped with necessary cable gland plates. The degree of
protection of DCPS enclosures shall preferably be IP21.
Conductors in multi conductor cables shall be individually colour coded, and numbered at both ends by
Halogen & Silicon free labels of polyamide ensuring scratch proof labelling with the use of solvent free ink
& latest UV Technology making it environment friendly printing with a WIPE RESISITANCE according to
DIN EN 61010-1/VDE 0411-1within enclosures.
Each panel shall be supplied with 240 VAC, 50Hz single-phase sockets with switch and lighting lamp for
panel illumination.
The Panel shall be designed to allow cooling preferably by natural convection. The Contractor shall submit
detail design of proposed Panel/enclosure and heat dissipation calculations during detailed engineering.
Forced cooling is permitted (DC Fans are permitted in the Panel or SMPS module) for equipment mounted
indoors (buildings/rooms/shelters). Proper filtering shall be provided to control dust ingress. There shall be
an arrangement for automatic Switching-OFF of fans during AC input failure.
AC input supply: The nominal input frequency is 50 Hz, which may vary from 47.5-52.5Hz. The input
voltage shall be as mentioned below:
Field Site Application – Three phase/4Wire (Nominal 415/240 V): 415 + 10 % - 15%. However, at site the
voltage may vary from 160V to 300V (Ph-N). An Auto-Mains Changeover unit shall be provided for each
field site DC power supply system. The Auto-Mains Changeover unit shall accept input from two AC
sources and extend any one of the available healthy sources to the DC Power supply system.
Rev-02
The suitable HVD (High Voltage Disconnector) Protection shall be provided at input of each DCPS system.
This HVD protection shall protect the SMPS modules of DCPS system against the sustained over voltage at
the input.
The module shall be capable of operating in “Auto Float-cum-Boost Charge” mode depending on the
condition of the battery sets being sensed by the Control unit.
(a) The float voltage shall be continuously adjustable & pre-settable at any value in the range of –48 to –
56V or as per battery manufacturer recommendations either at the module or may be set from the
common controller configuration. Further, the prescribed float voltage setting shall be based on
recommendations of the battery supplier.
(b) In Boost charge mode, DCPS shall supply battery & equipment current till terminal voltage reaches set
value, as recommended by the battery supplier & shall change
over to constant voltage mode
(c) The DC output voltage variation shall not be more than 2% for load variation from 25% load to full
load.
The float and boost charge current limit adjustment shall be provided in the DCPS system. The SMPS modules shall be fully
protected against short circuit. It shall be ensured that short circuit does not lead to any fire hazard.
The maximum instantaneous current during start up shall not exceed the peak value of the rectifier input current at full load at the
lowest input voltage specified.
(a) The SMPS modules shall be designed to minimize DC output voltage Overshoot/Undershoot such
that when they are switched on the DC output voltage shall be limited to ± 5% of the set voltage &
return to their steady state within 20 ms for load variation of 25% to 100%.
(b) The DC output voltage overshoot for a step change in AC mains as specified in clause 4.3.12
Electrical Requirements shall not cause shut down of SMPS module and the voltage overshoot shall
be limited to ± 5% of its set voltage and return to steady state within 20ms.
(c) The modules shall be designed such that a step load change of 25 to 100% and vice versa shall
not result in DC output voltage Overshoot/Undershoot of not more than 5% and return to steady
state value within 10 ms without resulting the unit to trip.
Rev-02
1.5.1.14 Electrical Noise
The Rectifier (SMPS) Modules shall be provided with suitable filter at output with discharge arrangements
on shut down of the modules. The Psophometric Noise (e.m.f weighted at 800Hz) with battery connected
across the output should be within 2 mV at full load at nominal input AC supply. For test purposes, this shall
be taken as equivalent to 4mV when the battery is not connected and in accordance to ITU-T Rec. O.41.
Voltage at the output of the Rectifier (SMPS) module, without battery connected, shall not exceed 300 mV
at the switching frequency measured by an Oscilloscope of 50/60 MHz bandwidth (Typical).
SMPS modules shall be suitable for operating in parallel with one or more modules of similar type, make
and rating, other output conditions remaining within specified limits.
The current sharing shall be within ± 10% of the average current per rectifier module individual capacity of
each rectifier module in the system (mounted in the same or different Panels) when loaded between 50 to
100% of its rated capacity for all other working conditions.
1.5.1.16
1.5.1.17 Protection
The SMPS module, which has failed (for any reason) shall be automatically isolated from the rest of the
modules and an alarm shall be initiated for the failure.
In case output DC voltage exceeds –57V or as per the recommendations of the manufacturer of batteries, the
over voltage protection circuit shall operate & shut off the faulty module. A tolerance of ± 0.25V is
permitted in this case.
Shutting off of faulty SMPS module shall not affect the operation of other SMPS modules operating in the
Panel. Operation of over voltage shut down shall be suitably indicated and extended monitoring/control unit.
The circuit design shall ensure protection against the discharge of the Battery through the SMPS module in
any case. The over voltage protection circuit failure shall not cause any safety hazard.
Fuses or miniature circuit breakers (MCB) shall be provided for each SMPS module as follows:
1. Live AC input line
2. Control Circuit
All fuses/circuit breaker used shall be suitably fault rated.
AC input Under/Over voltage protection shall be provided as per clause 3.1.11 for Electrical Requirements.
The DC side of the SMPS should also be provided with surge protection device to protect the SMPS in case
of transients being generated by the loads or due to induction in the DC line from the AC line running
parallel together. The Surge protection device should be able to discharge a current of at least 10 kA of 8/20
µs (Class ‘C’ surge arrestor), pluggable and should have indication to show its health to facilitate the
replacement on fault condition.
Visual indications/display such as LEDs, LCDs or a combination of both shall be provided on each SMPS
module for detection of SMPS module failure.
1.5.1.23 Termination
Suitable termination arrangements shall be provided in the panel for termination of inter cubicle cables from
other equipment such as Employers ACDB, Telecom and other associated equipments and alarm cables.
1.5.1.24 DC Terminations
All terminations including through MCBs shall be through lock and screw type terminations. Load and
batteries shall be connected to DCPS through appropriate MCBs. The isolation of any of the battery from the
load shall create an alarm. DC distribution shall be provided with adequate no. of feeders with appropriate
MCBs (6 Amp thru 32 Amp) for termination of the loads. Actual rating of the MCBs shall be finalized
during the detail engineering. The no. of feeders shall be minimum 10 (ten) nos.
DC distribution may be done either on wall mounted panel or on the DCPS panel. The proper rated MCB
shall be provided at the combined output of the SMPS modules (if not provided at each SMPS module). All
the AC, DC and Control/alarm cabling shall be supplied with the Panel. All DC +ve and –ve leads shall be
clearly marked. All conductors shall be properly rated to prevent excessive heating.
Earthing cables between equipment and grounding bus bars shall be minimum size 70 mm 2 stranded
conductors copper/copper strip, rated at 300 volts. All hinged doors shall be earthed through flexible
earthing braid. Signal and Safety earthing shall be provided separately.
1.5.1.26 Alarms
Following Visual indications/display such as LEDs, LCDs or a combination of both shall be provided to
indicate:
a) Mains available
b) DCPS/SMPSs in Float charge Mode
c) DCPS/SMPSs in Boost Charge Mode
All the protections/alarms shall be within tolerance of 0.25V in case of DC voltage, 1% in case of DC
current and ± 5V for AC voltage
Rev-02
Alarm Indication for remote monitoring:
a) Input AC mains supply fail alarm
b) Battery low voltage (Pre cut off) alarm
c) DCPS module fail
Potential free Contacts in two numbers for each of the above remote monitoring alarms (one for remote
alarm interfaced through communication equipments and one redundant for local monitoring at suitable
location) shall be provided. All these potential free contacts are to be wired and terminated at the suitable
location for interfacing purpose.
There shall be provision to monitor the following parameters through digital meters or digital display units:
The Digital display of meters or LCD based display unit shall be with minimum 31/2 digital display of height
12mm and shall have accuracy 1.5% or better.
The contractor shall supply, install and commission all power cables, control cables, network interface
cables and associated hardware (lugs, glands, cable termination boxes etc.) as required for all equipment.
The contractor shall be responsible for Cable laying and termination at both ends of the cable. The
Contractor shall also be responsible for termination of feeder cables at contractor’s equipment end including
supply of suitable lugs, glands, terminal blocks & if necessary cable termination boxes etc. All cabling,
wiring, and interconnections shall be installed in accordance with the following requirements.
All external power cables shall be stranded Aluminium conductor, armoured XLPE/PVC insulated and
sheathed, 1100V grade as per IS 1554 Part-I.
The safety earth network shall terminate at two/more studs for connecting with the earthing grid. Safety
earthing cables between equipment and enclosure grounding bus bars shall be minimum size 6 sq. mm,
stranded copper conductors, rated at 300 volts. All hinged doors (if provided) shall be earthed through
flexible earthing braid.
For all enclosures requiring AC input power, the green earthing wire from the AC input shall be wired to the
safety earthing stud. The Contractor shall provide all required cabling between enclosures for earthing. The
contractor shall connect safety and signal earths (as applicable) of each enclosure to the Employer provided
nearest earth grid/earth riser through suitable 50X6 sq. mm. GI strips or suitably sized copper cable.
Rev-02
The signal earthing network shall terminate at a separate stud connection, isolated from safety ground. The
stud connection shall be sized for an external earthing cable equipped with a suitable lug.
All earthing connections to equipment shall be made directly to each equipment chassis via earthing lug and
star washer. Use of the enclosure frame, skins, or chassis mounting hardware for the earthing network is not
acceptable.
There shall be provision for monitoring the temperature of battery and consequent arrangement for
Automatic temperature compensation of the SMPS output voltage to match the battery temperature
dependent charge characteristics. The output voltage of the rectifier in Float/Charge operation shall decrease
or increase at the rate of 72 mV (3mV/cell, 24 cell battery) per degree increase or decrease in temperature
over the set voltage or as may be recommended by the VRLA Battery supplier. A tolerance of +/- 5mV may
be acceptable over the specified rate of 72 mV/degree C. The output voltage shall decrease till the open
circuit voltage of the battery is reached. The open circuit voltage range shall be settable between 2.1V/cell
to 2.2V/cell. The increase in output voltage due to decrease in temperature has been taken care of by the
tripping of the unit due to output voltage high (57V) protection. Failure of temperature compensation circuit
including sensors shall create an alarm and shall not lead to abnormal change in output voltage. The nominal
distance between the battery & DCPS system may be 20 metres. The Contractor shall provide the necessary
sensor and cord for the purpose with DCPS system to sense the Battery temperature.
4-P
Batter Feeder
PHASE (PH)
#10
N+ -ve
2 +v
e Eart
Rev-02
1.5.4 Battery Requirements
The supplier, supplying the cells/batteries as per this document shall be responsible to replace/repair free of
charge, the battery/cell becoming faulty, owing to defective workmanship or material as per the provisions
of the bid document
1.5.4.2 Containers
The container material shall have chemical and electro-chemical compatibility and shall be acid resistant.
The material shall meet all the requirements of VRLA batteries and be consistent with the life of battery.
The container shall be fire retardant and shall have an Oxygen Index of at least 28%. The porosity of the
container shall be such as not to allow any gases to escape except from the regulation valve. The tensile
strength of the material of the container shall be such as to handle the internal cell pressure of the cells in the
worst working condition. Cell shall not show any deformity or bulge on the sides under all working
conditions. The container shall be capable of withstanding the rigours of transport, storage and handling.
The containers shall be enclosed in a steel tray.
When the battery is discharged at 10 hour rate, it shall deliver 80% of C (rated capacity, corrected at
27ºCelcius) before any of the cells in the battery bank reaches 1.85V/cell.
All the cells in a battery shall be designed for continuous float operation at the specified float voltage
throughout the life. Float voltage of each cell in the string shall be within the average float voltage/cell
+0.05V band.
The capacity (corrected at 27ºCelcius) shall also not be less than C and not more than 120% of C before any
cell in the battery bank reaches 1.75V/cell. The battery voltage shall not be less than the following values,
when a fully charged battery is put to discharge at C/10 rate:
Rev-02
(b) After Six hours of discharge : 1.92V/cell
(c) After 8 hours of discharge : 1.85V/cell
(d) After 10 hours of discharge : 1.75V/cell
Loss in capacity during storage at an average ambient temperature of 35º Celsius for a period of 6 months
shall not be more than 60% and the cell/battery shall achieve 85% of its rated capacity within 3
charge/discharge cycles and full rated capacity within 5 cycles, after the storage period of 6 months. Voltage
of each cell in the battery set shall be within +0.05V of the average voltage throughout the storage period.
Ampere hour efficiency shall be better than 90% and watt hour efficiency shall be better than 80%.
The battery shall be capable of giving more than 1200 charge/discharge cycles at 80% Depth of discharge
(DOD) at an average temperature of 27º Celsius. DOD (Depth of Discharge) is defined as the ratio of the
quantity of electricity (in Ampere-hour) removed from a cell or battery on discharge to its rated capacity.
The battery sets shall have a minimum expected operational life of 5 years at normal operating conditions or
1200 charge/discharge cycles (whichever is early).
For routine maintenance of battery system, the contractor shall supply one set of following tools:
a. Torque wrench.
b. Tool for opening /closing of pressure regulation valve of battery.
The Contractor shall submit type test reports for the battery for the same make, model & rating as offered as
per the IEC 60896 or equivalent IS/EN/BS/TEC standards. In the event, the type test reports for exact rating
is not available, the Contractor shall submit type test reports for higher rating Battery.
Rev-02
Table A
Type Tests on DCPS
Voltage dips, short interruptions and voltage variations (Level 2 – as per IEC
7 61000-4-11)
8 Conducted Emission (Level - Class A, Group 1 as per IEC CISPR 11)
9 Radiated Emission (Level - Class A, Group 1 as per IEC CISPR 11)
10 Safety Tests (as per IEC 60950)
Table B
List of tests for VRLA battery
Type Test
Sl.
Test As per IEC FAT SAT
No.
60896
√ √ √
1. Verification of marking
- Visual observation
- Dimensional inspection
- Polarity checking
Capacity test √ √ √
2.
3. Suitability for floating battery operation √
4. Endurance in discharge/charge cycles √
5. Charge Retention √
6. Short-circuit current and internal resistance √
7. Mechanical Tests √
-Vibration Test
(procedure as per IEC 60068-2-6)
- Free fall Test
(procedure as per IEC 60068-2-32)
NOTE :
The batteries shall meet the general requirements as per IEC 60896 or equivalent.
The factory/site tests to be carried out on DCPS system/module in the factory and site are listed
respectively in Table C below.
Table C
Lists of tests for FAT/SAT of DCPS
S.No. Test FAT SAT
Tests on DCPS System
1. Mechanical & Visual Check Tests √ √
Rev-02
Table C
Lists of tests for FAT/SAT of DCPS
S.No. Test FAT SAT
2. Insulation Test. √
3. High Voltage Withstand Test √
4. Switch On Test √ √
5. DCPS Low voltage & High voltage limits check Test √ √
6. Pre-alarm test for Battery Voltage Low √ √
7. Battery Low Voltage Disconnect Level Test √ √
8. AC Input Low and High voltage limits check Test √
9. Rectifier Fail Alarm Test √ √
10. Voltage Regulation Test √
11. Current Sharing Test √
12. Total Output Power Test √ √
13. Hot Plug In Test ( if applicable ) √ √
14. Calibration & Parameter settings √ √
15. Automatic Float cum Boost Charge Mode Change Over √ √
Test
16. Battery Path Current Limiting Test √ √
17. Battery Charging and full load Current Test √ √
18. Total Harmonic distortion Test √
19. Burn in Test at 50 ° C (for 8 hrs duration) √
Tests on SMPS module
20 Mechanical & Visual Check Test √
21 Module-On Test √
22 Input low/high voltage cut-off test √
23 Voltage Drop Test √
24 Voltage Regulation Test √
25 Power Output & Current Limit Test √
26 DC High Voltage Test √
27 O/P Voltage Ripple Test √
28 Psophometric Noise Test √
29 Efficiency Test √
30 Power Factor √
31. Input Current Limit √
32. Input AC Frequency Range Test √
33. Rectifier Dynamic Response √
34. Output Short Circuit Test √
35. Hold up Time Test √
Rev-02