TEMPORARY WORKS GEOTECHNICAL DESIGN FOR
LARGE SCALE INFRASTRUCTURE PROJECTS
CHRIS BRIDGES
Temporary Works
Can be defined as “any temporary construction
that may be necessary to allow the permanent
works to be carried out”.
Temporary Works
(a) They represent the interface between design and
   construction.
(b) They are a key factor in achieving the desired result
   safely and with the best cost benefit to the client.
(c) Their design and method solution are often more
   challenging than that for the permanent works.
   Alternatively, the permanent works design must be
   carried out recognising the method of construction that
   will be adopted.
           Temporary Works - Their Role in Construction - J. R. Illingworth (1987)
Typical Works Undertaken
•   Piling platform and crane pad design
•   Haul roads
•   Excavations and earth-retaining structures
•   Rock support design
•   Slope appraisals and designs
•   Foundations for temporary structures including tower
    cranes
Temporary Works - Process
  Contractors    Contractors     Alternatives/             Construction
   Objective     Preferences      Concepts        Design      Role
    Construction
    Contractor
    Alternatives/Concepts
    Design
    ContractorsPreferences
                   Objective
                    Role
    • What
       Available
       Different
       Full-time
       Groundwater
              are solutions
                  the
                  presence
                   material?
                       temporary
                        level available?
                              required?
                                   works required for?
    • Duration
       Available
       Do
       Frequent
       Surcharges
           nothing?
                 ofsite
                   plant?
                     temporary
                        visits? works?
    • Over-arching
       Instrumentation
       Preferred / non-preferred
       Durability      contractual
                           & monitoring
                                    requirements?
                                     sub-contractor?
    • Partial factors / factors of safety
    • Construction sequencing
    • Interaction with permanent works
Risks
•   Time
•   Reliance on third party information
•   Lack of information
•   Consequence of failure
•   Cost
Pile & Crane Platforms
Pile & Crane Platforms
               CFA rig collapsed across main
                London – Paris railway line
                   (Piling & Foundation Specialists)
Pile & Crane Platforms
Bored piling rig
collapsing sideways due
to soft spot on platform
(Piling & Foundation Specialists)
Pile & Crane Platforms
Port of Brisbane – One fatality
Land reclamation using dredged mud cuttings from
Brisbane River.
Dredged mud overlies by approx. 2m of sand cap
Install wick drain and surcharge for ground improvement to
limit future settlement
•Weight: 80 tonnes
•Track size:
 6000mm x 900mm
•equivalent to ~75kPa
Pile & Crane Platforms
• BR 470
Detailed loads for load cases to be
provided by rig contractor/supplier.
Based on Meyerhof – footing
punching through a dense sand layer
over a soft clay.
Examples in BR 470.
Pile & Crane Platforms
Must haves:
• Information on ground conditions (test pits)
• Crane/pile rig loadings etc
• Information on material to form platform
Excavations
•   Batters
•   Sheet piles
•   Cutter soil mixing
•   Soil nails
•   Rock support – dowels, bolts
•   Piles – contiguous, secant, soldier piles, ground anchors
    (temporary & permanent)
Excavations – Soil Nails
Excavations – Soil Nails
Shored Mechanically Stabilised Earth (SMSE) Walls
                                 RSS
                  Soil Nails
Shored Mechanically Stabilised Earth (SMSE) Walls
Excavations – Temporary Ground Anchors
Excavations
Guangxi
“A stitch in time”
Nicholl Highway 2004
What Happened?
Ref.: New Civil Engineer International, May 2005, pp4-7
Conclusions
• Inadequate design and design review
• Poor construction supervision & sequencing
• Ignoring monitoring data
Airport Link Case Studies
• $5bn, 7km Tunnel linking Bowen Hills to the East/West
  Arterial Road (Toombul)
• Widening of existing East/West
      Arterial
• Reconstruction of the Airport
      Roundabout
• Construction of Northern Busway
      to Kedron
Kedron
             Kedron Brook Cut-
             and-cover
             Excavation
         Kedron Park Hotel
         Tunnels
Kedron Brook Cut-and-cover Structure
Contractors Requirements
• Excavation required to 10m below existing
  to allow construction of cut-and-cover
  roof slab
• Required over a 100m length, through
  Kedron Brook to be done in two phases
• Retaining Gympie Road
• Minimum surcharge of 20kPa (contractual requirements)
• Maintain minimum flow through the Kedron Brook (contractual
  requirements)
• Material reuse
• Removable system
Kedron Brook Cut-and-cover Structure
Contractors Requirements
                                              Gympie Road
                               KEDRON BROOK
                     Phase 2
                                               Phase 1
Kedron Brook Cut-and-cover Structure
Contractors Requirements
                                           Flood Wall built on
                                              Phase 1 Slab
                      DIVERTED ON TO THE
                                                        KEDRON BROOK
                      PHASE 1 ROOF SLAB
        PHASE 2
                                                                       PHASE 1
                      KEDRON BROOK
                                    Interface
                                 between Phases
                                     1 and 2
Kedron Brook Cut-and-cover Structure
Contractors Preferences
• Use a system that was readily available with more than
  one/two suppliers
Kedron Brook Cut-and-cover Structure
Alternatives / Concepts
•   CSM
•   Sheet piles - adopted
•   Soil nails – partially adopted
•   Soldier piles
Kedron Brook Cut-and-cover Structure
Design
• Flood risk (RL5m normal flow to
  RL9m flood)
• Analysis undertaken included
  design of sheet piles, rock anchors
  and walers
• Excavation required below shallow
  rockhead
• Rock socket used for temporary
  stability until toe anchor installed
• Permits excavation to below toe of
  wall. Socket then redundant
• Reused sheet piles, steel walers
  for phase 2
Kedron Brook Cut-and-cover Structure
Construction Sequence
Kedron Brook Cut-and-cover Structure
Construction Sequence
Kedron Brook Cut-and-cover Structure
Construction Sequence
Kedron Brook Cut-and-cover Structure
Construction – Phase 1
Kedron Brook Cut-and-cover Structure
Construction – Phase 1
Kedron Brook Cut-and-cover Structure
Construction – Phase 1
Kedron Brook Cut-and-cover Structure
Construction – Phase 1
Kedron Brook Cut-and-cover Structure
Construction – Phase 2
Kedron Brook Cut-and-cover Structure
Construction – Phase 2
Kedron Brook Cut-and-cover Structure
Construction – Phase 2
Kedron Brook Cut-and-cover Structure
Construction – Phase 2
Kedron Brook Cut-and-cover Structure
Construction – Phase 2
Kedron Brook Cut-and-cover Structure
Construction – Phase 2
Kedron Brook Cut-and-cover Structure
March 2010
Kedron Brook Cut-and-cover Structure
March 2010
Kedron Brook Cut-and-cover Structure
August 2010
Kedron Brook Cut-and-cover Structure
October 2011
    Kedron Park Hotel Tunnels
    Contractors Requirements
• Cut-and-cover tunnel
• Cut required to in excess of     Kedron Park
  30m depth with final                Hotel
  structure built within the box
• Church hall within 5m of                       Open Car
                                                   Park
  wall, Church within 15m and                           Moreton Bay
                                                            Fig
  Hotel within 15m
• Access for construction
                                                                      Housing
  plant at the crest (large               Tunnel under
  mobile crane loads etc)                     wall                       Tunnel
                                                     Church and       through wall
                                                        Hall
• Tunnels (roadheader, drill
  and blast) required
  underneath the excavation
  and through one of the walls
Kedron Park Hotel Tunnels
Contractors Preferences - Alternatives / Concepts
• Initial Design – Stacked tunnel, internal
  propping constructed top down. Secant
  piles.
• Issues with constructability and cost
• Enquiry from TJH regarding suitability
  of soil nails
• Preparation of design for 30m+ high
  soil nail wall (24m) / rock cut (6m)
• Revised to 18m soil nail wall and 10m
  contiguous piles due to mined tunnel
  concerns
Kedron Park Hotel Tunnels
Design – Key Issues
•   Tunnelling through walls - constructability
•   Settlement of existing structures
•   Timescales
•   Suitability to gain approval through TJH design review process
    (PBA, IV, CNI)
•   Appropriate modelling techniques
•   Construction plant as crest of wall
•   Tower crane
•   Existing services
•   Protected Trees
    Kedron Park Hotel Tunnels
    Design – Key Issues                                                0           5          10          15          20          25            30           35       40                45       50       55   60   65
•    Initial feasibility design using simple
                                                                  35                                                                                                                                                     35
                                                                                                                                                                                                South Wall
                                                                                                                                                                                                Eastern Side
                                                                           Name: Stiff Clay   Unit Weight: 21 kN/m³ Cohesion: 5 kPa Phi: 25 °
                                                                  30                                                                                                                                                     30
     design packages and methodology.
                                                                           Name: Hard Clay     Unit Weight: 21 kN/m³ Cohesion: 5 kPa Phi: 28 °
                                                                           Name: VLS - LS Siltstone     Unit Weight: 22 kN/m³ Cohesion: 22.5 kPa Phi: 30 °
                                                                           Name: MS Siltstone     Unit Weight: 22 kN/m³ Cohesion: 200 kPa Phi: 40 °
                                                                                                                                        1.333
                                                                  25                                                                                                                                                     25
     Proof of concept.
                                                                                                                                                        Surcharge (Unit Weight): 32 kN/m³
                                                                  20                                                                                                                                                     20
                                                                                                                                                                           Stiff Clay
                                                Elevation (mRL)
•    Detailed design incorporating                                15                                                                                                                                                     15
     excavations through and under.                               10
                                                                                                                                                                               Hard Clay
                                                                                                                                                                                                                         10
•    Nail bond stresses validated using pull-                      5
                                                                                                                                                                                VLS - LS Siltstone
                                                                                                                                                                                                                         5
     out tests during design and construction                      0
                                                                                                                                                                                MS Siltstone
                                                                                                                                                                                                                         0
     phases.
                                                                  -5                                                                                                                                                     -5
                                                                       0           5          10          15          20          25            30           35       40                45       50       55   60   65
                                                                                                                                                 Distance
Kedron Park Hotel Tunnels
Design - Layout
Kedron Park Hotel Tunnels
Design – South Wall Elevation
Kedron Park Hotel Tunnels
Design – East Wall Elevation
Kedron Park Hotel Tunnels
Design – Section
Kedron Park Hotel Tunnels
Design – Tower Crane
Kedron Park Hotel Tunnels
Design – Construction Sequence
Kedron Park Hotel Tunnels
Design - Instrumentation
Kedron Park Hotel Tunnels
Design – Analysis                             0            5           10          15          20          25            30           35       40                45       50       55   60   65
                                         35                                                                                                                                                       35
                                                                                                                                                                         South Wall
                                                                                                                                                                         Eastern Side
                                                  Name:   Stiff Clay   Unit Weight: 21 kN/m³ Cohesion: 5 kPa Phi: 25 °
                                         30                                                                                                                                                       30
                                                  Name:   Hard Clay     Unit Weight: 21 kN/m³ Cohesion: 5 kPa Phi: 28 °
                                                  Name:   VLS - LS Siltstone     Unit Weight: 22 kN/m³ Cohesion: 22.5 kPa Phi: 30 °
                                                  Name:   MS Siltstone     Unit Weight: 22 kN/m³ Cohesion: 200 kPa Phi: 40 °
                                                                                                                 1.333
                                         25                                                                                                                                                       25
                                                                                                                                 Surcharge (Unit Weight): 32 kN/m³
                                         20                                                                                                                                                       20
                                                                                                                                                    Stiff Clay
                       Elevation (mRL)
                                         15                                                                                                                                                       15
                                                                                                                                                        Hard Clay
                                         10                                                                                                                                                       10
                                          5                                                                                                                                                       5
                                                                                                                                                         VLS - LS Siltstone
                                          0                                                                                                                                                       0
                                                                                                                                                         MS Siltstone
                                         -5                                                                                                                                                       -5
                                              0            5           10          15          20          25            30           35       40                45       50       55   60   65
                                                                                                                          Distance
Kedron Park Hotel Tunnels
Design – Analysis
Kedron Park Hotel Tunnels
Design – Analysis
Kedron Park Hotel Tunnels
Design – Analysis
Kedron Park Hotel Tunnels
Design – Analysis
Kedron Park Hotel Tunnels
Design – Analysis
Kedron Park Hotel Tunnels
Kedron Park Hotel Tunnels
Kedron Park Hotel Tunnels
Construction Role
• Full time
• Record progress during
  construction
• Mapping of face to
  correlate testing
• Observe testing
• Record groundwater
• Site photography
• ITP sign off
• Site instructions
Kedron Park Hotel
Tunnels
Construction Sequence
Kedron Park Hotel Tunnels
Construction Role
Kedron Park Hotel Tunnels
Construction Role
                            East Wall
 North Wall
Kedron Park Hotel Tunnels
Construction Role
          GRP Nails
                  East Wall
Kedron Park Hotel Tunnels
Construction Role
Western End
Kedron Park Hotel Tunnels
Construction Role
Kedron Park Hotel Tunnels
Construction Role
• Ultimate Load (Pullout)
  Test
• Acceptance Testing
• Exhumation of test nails
Kedron Park Hotel Tunnels
Construction Role
Kedron Park Hotel Tunnels
Construction Role
            33mm            10mm                       22mm
                    Prediction = 22mm    Prediction = 55mm
                      RS
RS
                                           RS
VLS-LS                                     VLS-LS
Siltstone            VLS-LS
                     Siltstone             Siltstone
   Mid-South Wall    Corner North Wall      Mid-North Wall
                                                     Lateral Movement vs Wall Height
                                                           (Published Results)
                                0.140
                                0.120                                                        Bruce and Jewell, 1986
                                                                                             Durgunoglu et al, 2007
Lateral Wall Movement, dh (m)
                                0.100                                                        Clough & O'Rourke,
                                                                                             1990
                                                                                             Thompson & Miller,
                                                                                             1990
                                0.080                                                        Stocker & Riedinger,
                                                                                             1990
                                                                                             Ho et al, 1989
                                0.060                                                        Shen et al, 1981
                                                                                             Bridges, 2012
                                0.040                                                        Unpublished
                                                                                             dh/H = 0.5%
                                0.020                                                        dh/H = 0.2%
                                                                                             dh = 4H/1000
                                0.000                                                        dh = H/1000
                                        0   5   10       15             20    25   30   35
                                                         Wall Height, H (m)
                                       Wall Height vs Nail Length
                                         (Published Results)
                  35
                  30
                                                                                    Bruce and Jewell, 1986
                  25
                                                                                    Durgunoglu et al, 2007
                                                                                    Thompson & Miller, 1990
Wall Height (m)
                  20                                                                Stocker & Riedinger, 1990
                                                                                    Ho et al, 1989
                                                                                    Shen et al, 1981
                  15                                                                Bridges, 2012
                                                                                    Unpublished
                                                                                    L/H=1.3
                  10
                                                                                    L/H = 1
                                                                                    L/H=0.5
                                                                                    L/H=0.3
                   5
                   0
                       0   2   4   6   8          10       12   14   16   18   20
                                           Nail Length (m)
Kedron Park Hotel Tunnels
Completed Structure
• Two year design life, 4 month
  construction (nail wall).
• 18m deep excavation with further 10m
  deep piled wall below
                                  • Over 1500 soil nails 10 to 15m long
                                    (steel and GRP)
                                  • Backfilled with flowable fill
Temporary Works
(a) They represent the interface between design and
   construction.
(b) They are a key factor in achieving the desired result
   safely and with the best cost benefit to the client.
(c) Their design and method solution are often more
   challenging than that for the permanent works.
   Alternatively, the permanent works design must be
   carried out recognising the method of construction that
   will be adopted.
           Temporary Works - Their Role in Construction - J. R. Illingworth (1987)
QUESTIONS?