DAFTAR HARGA SATUAN UPAH & BAHAN
PEKERJAAN 1 (SATU) PAKET PENGECATAN KANTOR KAS BANK
                        PEMBANGUNAN KALTENG
LIKOTA PALANGKARAYA, RSUD DORIS SYLVANUS, PEMPROP KALTENG, SAMSAT PROP K
      UPAH TENAGA KERJA
                                                                     HARGA SATUAN
        NO.                            TENAGA KERJA         SATUAN
                                                                         (Rp.)
         A         UPAH
               1   Mandor                                   org/hr       200,000.00
               2   Kepala tukang                            org/hr       180,000.00
               3   Tukang Kayu                              org/hr       155,000.00
               4   Tukang Besi Beton                        org/hr       155,000.00
               5   Tukang Besi / IWF                        org/hr       155,000.00
               6   Tukang Batu                              org/hr       155,000.00
               7   Tukang Cat                               org/hr       155,000.00
               8   Tukang Pipa                              org/hr       155,000.00
               9   Tukang Listrik                           org/hr       155,000.00
              10   Pekerja                                  org/hr       130,000.00
      HARGA BAHAN BANGUNAN
                                                                     HARGA SATUAN
        NO.                             MATERIAL            SATUAN
                                                                         (Rp.)
         A
               1   Amplas                                     lbr         15,000.00
               2   Minyak Cat                                  kg         30,000.00
               3   Cat kilat                                   kg
               4   Plamur Tembok Set. MATEX                    kg         32,000.00
               5   Cat dasar                                   kg         46,000.00
               6   Cat tembok Dulux type weather shield        kg        155,000.00
               7   Cat tembok type weather coat (acrylic)      kg        117,000.00
               8   Cat tembok Interior, warna Stand.         liter       124,000.00
               9   Cat tembok Exterior, warna Std.           liter       175,000.00
              10   Cat weather shield                          kg         65,600.00
              11   Cat Plafond                                 kg         54,750.00
              12   Cat seng (zinc chromate)                    kg         31,000.00
              13   Cat besi/kayu Set. Dulux                    kg         83,000.00
              14   Dempul                                      kg         28,000.00
              15   Plitur                                      kg         67,000.00
              16   Thiner impala                               ltr        37,000.00
              17   Thiner ND                                   ltr        48,000.00
              18   Melamic                                     ltr        93,000.00
19   Vemis                                ltr    75,000.00
20   Meni                                 kg     31,000.00
21   Oker                                 kg     10,000.00
22   Lem kayu                             kg     87,000.00
23   Lem kuning                           kg     47,000.00
24   Sealent                            tube     45,000.00
25   Paint Remover                        kg     89,000.00
26   Rol Cat                             bh      45,000.00
27   Sabun/cream pembersih kotoran        kg     15,000.00
28   Cat Duko                             kg     67,000.00
29   Ter/residu                           ltr     4,000.00
30   Kuas                                bh      14,000.00
31   Road line paint (cat marka)          kg     53,000.00
32   Glass bit                            kg     17,500.00
33   Weatherbong emulsion (cat kerb)      kg    120,000.00
34   Termoplast                           kg     17,500.00
35   Water proofing                      m2      85,000.00
36   Wallpaper                           m2      48,000.00
37   Sealent GE / Dow Coming Non Asan   tube     45,000.00
38   Kape                                bh      28,000.00
39   Coumpond                            zak    102,500.00
40   White Sreen Microvision             bh     968,000.00
41   Pasir Beton                         m3     325,000.00
42   Semen                               Kg       1,700.00
43   Gypsum Board 9 mm                   Lbr     87,000.00
44   Sekrup Gypsum                       Kg      47,000.00
45   Lis Plafond Gypsum                  M'      23,000.00
43   Batu Pecah 2-3                      m3     475,000.00
       ANALISA HARGA SATUAN PEKERJAAN
A.4.7.1 1m2 Pengikisan/pengerokan permukaan cat lama
                                                                                                                                                             Jumlah Harga
  No                                  Uraian                                     Kode           Satuan       Koefisien            Harga Satuan    (Rp)
                                                                                                                                                                    (Rp)
  A    TENAGA
       Pekerja                                                                   L.01            OH           0.1500                        130,000.00             19,500.00
       Mandor                                                                    L.04            OH           0.0030                        200,000.00                600.00
                                                                                                         JUMLAH TENAGA KERJA                                       20,100.00
  B    BAHAN
       Amplas                                                                                                 2.0000                             15,000.00         30,000.00
                                                                                                         JUMLAH HARGA BAHAN                                        30,000.00
  C    PERALATAN
                                                                                                         JUMLAH HARGA ALAT
  D    Jumlah (A+B+C)                                                                                                                                               50,100.00
  E    Overhead & Profit (Contoh 15 %)                                                                                   0% x D                                             -
  F    Harga Satuan Pekerjaan (D+E)                                                                                                                                 50,100.00
A.4.7.1. 1 m2 Pengecatan bidang kayu lama (1 lapis cat dasar, 1 lapis cat penutup)
                                                                                                                                                             Jumlah Harga
  No                                  Uraian                                     Kode           Satuan       Koefisien            Harga Satuan    (Rp)
                                                                                                                                                                    (Rp)
  A    TENAGA
       Pekerja                                                                   L.01            OH           0.0700                        130,000.00              9,100.00
       Tukang cat                                                                L.02            OH           0.0090                        155,000.00              1,395.00
       Kepala tukang                                                             L.03            OH           0.0060                        180,000.00              1,080.00
       Mandor                                                                    L.04            OH           0.0030                        200,000.00                600.00
                                                                                                         JUMLAH TENAGA KERJA                                       12,175.00
  B    BAHAN
       Cat menie                                                                                 Kg           0.2000                         32,000.00              6,400.00
       Plamuur                                                                                   Kg           0.0300                         32,000.00                960.00
       Cat dasar                                                                                 Kg           0.1700                         46,000.00              7,820.00
       Cat penutup                                                                               Kg           0.1700                         83,000.00             14,110.00
       Kuas                                                                                      Bh           0.0100                         14,000.00                140.00
       Pengencer                                                                                 Ltr          0.0300                         30,000.00                900.00
       Ampelas                                                                                   Lbr          0.2000                         15,000.00              3,000.00
                                                                                                         JUMLAH HARGA BAHAN                                        33,330.00
  C    PERALATAN
                                                                                                         JUMLAH HARGA ALAT
  D    Jumlah (A+B+C)                                                                                                                                               45,505.00
  E    Overhead & Profit (Contoh 15 %)                                                                                   0% x D                                             -
  F    Harga Satuan Pekerjaan (D+E)                                                                                                                                 45,505.00
A.4.7.1 Pengecatan 1 m2 tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
                                                                                                                                                             Jumlah Harga
  No                                  Uraian                                     Kode           Satuan       Koefisien            Harga Satuan    (Rp)
                                                                                                                                                                    (Rp)
  A    TENAGA
       Pekerja                                                                   L.01            OH           0.0200                        130,000.00              2,600.00
       Tukang cat                                                                L.02            OH           0.0630                        155,000.00              9,765.00
       Kepala tukang                                                             L.03            OH           0.0063                        180,000.00              1,134.00
       Mandor                                                                    L.04            OH           0.0030                        200,000.00                600.00
                                                                                                         JUMLAH TENAGA KERJA                                       14,099.00
  B    BAHAN
       Plamuur                                                                                   Kg           0.1000                         32,000.00              3,200.00
       Cat dasar                                                                                 Kg           0.1000                         46,000.00              4,600.00
       Cat penutup                                                                               Kg           0.2600                        124,000.00             32,240.00
                                                                                                         JUMLAH HARGA BAHAN                                        36,840.00
  C    PERALATAN
       Kuas                                                                                                   0.2000                         14,000.00              2,800.00
       Roll Cat                                                                                               0.3000                         45,000.00             13,500.00
                                                                                                         JUMLAH HARGA ALAT                                         16,300.00
  D    Jumlah (A+B+C)                                                                                                                                               67,239.00
  E    Overhead & Profit (Contoh 15 %)                                                                                   0% x D                                             -
  F    Harga Satuan Pekerjaan (D+E)                                                                                                                                 67,239.00
N.2      1 m2 POLITUR BIDANG KAYU DENGAN CAT KAYU
 A       BAHAN
   1     Cat kayu                                                  Kg      0.3720    83,000.00   30,876.00
   2     Kuas                                                      bh      0.1000    14,000.00    1,400.00
   3     Amplas                                                    lbr     2.0000    15,000.00   30,000.00
                                                                                                 62,276.00
B        TENAGA
     1   Pekerja                                                   Oh      0.0700   130,000.00    9,100.00
     2   Tukang cat                                                Oh      0.0600   155,000.00    9,300.00
     3   Kepala tukang                                             Oh      0.0160   180,000.00    2,880.00
     4   Mandor                                                    Oh      0.0025   200,000.00      500.00
                                                                                                 21,780.00
 C       PERALATAN
 D                   Jumlah Bahan, Tenaga, dan Peralatan (A+B+C)                     84,056.00
 E                                    Overhead & Profit 10 % X D                            -
 F                                  Harga Satuan Pekerjaan (D+E)                     84,100.00
N.3      1 m2 PENGECATAN TEMBOK INTERIOR
 A       BAHAN
   1     Plamir                                                      kg    0.1000    32,000.00    3,200.00
   2     Cat dasar                                                   kg    0.1000    46,000.00    4,600.00
   3     Cat penutup                                               liter   0.2600   124,000.00   32,240.00
                                                                                                 40,040.00
B        TENAGA
     1   Pekerja                                                   Oh      0.0200   130,000.00    2,600.00
     2   Tukang cat                                                Oh      0.0630   155,000.00    9,765.00
     3   Kepala tukang                                             Oh      0.0063   180,000.00    1,134.00
     4   Mandor                                                    Oh      0.0030   200,000.00      600.00
                                                                                                 14,099.00
 C     PERALATAN
     1 Kuas Cat                                                            0.2000    14,000.00    2,800.00
     2 Roll Cat                                                            0.3000    45,000.00   13,500.00
                                                                                                 16,300.00
 D                   Jumlah Bahan, Tenaga, dan Peralatan (A+B+C)                     70,439.00
 E                                    Overhead & Profit 10 % X D                            -
 F                                  Harga Satuan Pekerjaan (D+E)                     70,500.00
N.4      1 m2 PENGECATAN TEMBOK EXTERIOR
 A       BAHAN
   1     Plamir                                                      kg    0.1000    32,000.00    3,200.00
   2     Cat dasar                                                   kg    0.1000    32,000.00    3,200.00
   3     Cat penutup                                               liter   0.2600   175,000.00   45,500.00
                                                                                                 51,900.00
B        TENAGA
     1   Pekerja                                                   Oh      0.0200   130,000.00    2,600.00
     2   Tukang cat                                                Oh      0.0630   155,000.00    9,765.00
     3   Kepala tukang                                             Oh      0.0063   180,000.00    1,134.00
     4   Mandor                                                    Oh      0.0030   200,000.00      600.00
                                                                                                 14,099.00
 C     PERALATAN
     1 Kuas Cat                                                            0.2000    14,000.00    2,800.00
     2 Roll Cat                                                            0.3000    45,000.00   13,500.00
                                                                                                 16,300.00
D                    Jumlah Bahan, Tenaga, dan Peralatan (A+B+C)                     82,299.00
E                                     Overhead & Profit 10 % X D                            -
F                                   Harga Satuan Pekerjaan (D+E)                     82,300.00
N.6      1 m2 PENGECATAN PLAFOND
 A       BAHAN
   1     Cat penutup                                               liter     0.1200      54,750.00     6,570.00
   2     Cat Penutup 2 kali                                        liter     0.2400      54,750.00    13,140.00
   3     Amplas                                                     lbr      0.5000      15,000.00     7,500.00
   4     Rol Cat                                                    bh       0.0100      45,000.00       450.00
                                                                                                      27,660.00
B        TENAGA
     1   Pekerja                                                   Oh        0.0600     130,000.00     7,800.00
     2   Tukang cat                                                Oh        0.0400     155,000.00     6,200.00
     3   Kepala tukang                                             Oh        0.0040     180,000.00       720.00
     4   Mandor                                                    Oh        0.0030     200,000.00       600.00
                                                                                                      15,320.00
 C       PERALATAN
D                    Jumlah Bahan, Tenaga, dan Peralatan (A+B+C)                        42,980.00
E                                     Overhead & Profit 10 % X D                               -
F                                   Harga Satuan Pekerjaan (D+E)                        43,000.00
E.1      1 m3 MEMBUAT LANTAI KERJA BETON 1 PC : 3 PSR : 5 KR
 A       BAHAN
   1     Semen portland                                             kg     218.0000      1,700.00    370,600.00
   2     Pasir beton                                                kg       0.5200    325,000.00    169,000.00
   3     Batu split                                                 kg       0.8700    475,000.00    413,250.00
                                                                                                     952,850.00
B        TENAGA
     1   Pekerja                                                   Oh        1.6500    130,000.00    214,500.00
     2   Tukang batu                                               Oh        0.2500    155,000.00     38,750.00
     3   Kepala tukang                                             Oh        0.0250    180,000.00      4,500.00
     4   Mandor                                                    Oh        0.0800    200,000.00     16,000.00
                                                                                                     273,750.00
 C       PERALATAN
D                    Jumlah Bahan, Tenaga, dan Peralatan (A+B+C)                      1,226,600.00
E                                     Overhead & Profit 10 % X D                                -
F                                   Harga Satuan Pekerjaan (D+E)                      1,226,600.00
D.4      1 m2 PLESTERAN LANTAI 1 pc : 3 ps, tebal = 20 mm
 A       BAHAN
   1     Semen portland                                            kg       10.3680      1,700.00     17,625.60
   2     Pasir pasang                                              m3        0.0310    325,000.00     10,075.00
                                                                                                      27,700.60
B        TENAGA
     1   Pekerja                                                   Oh        0.2600    130,000.00     33,800.00
     2   Tukang batu                                               Oh        0.2000    155,000.00     31,000.00
     3   Kepala tukang                                             Oh        0.0200    180,000.00      3,600.00
     4   Mandor                                                    Oh        0.0130    200,000.00      2,600.00
 C       PERALATAN                                                                                    71,000.00
D                    Jumlah Bahan, Tenaga, dan Peralatan (A+B+C)                        98,700.60
E                                     Overhead & Profit 10 % X D                               -
F                                   Harga Satuan Pekerjaan (D+E)                        98,800.00
G.3      1 m2 LANGIT - LANGIT GYPSUM BOARD, TEBAL 9 mm
 A       BAHAN
   1     Gypsum board (120 x 240 x 9 ) mm                          lbr       0.3640     87,000.00     31,668.00
   2     Sekrup gypsum                                             kg        0.1100     47,000.00      5,170.00
                                                                                                      36,838.00
B        TENAGA
     1   Pekerja                                                   Oh        0.1000    130,000.00     13,000.00
     2   Tukang kayu                                               Oh        0.0500    155,000.00      7,750.00
     3   Kepala tukang                                             Oh        0.0050    180,000.00        900.00
     4   Mandor                                                    Oh        0.0050    200,000.00      1,000.00
 C       PERALATAN                                                                                    22,650.00
D                    Jumlah Bahan, Tenaga, dan Peralatan (A+B+C)                        59,488.00
E     Overhead & Profit 10 % X D          -
F   Harga Satuan Pekerjaan (D+E)   59,500.00
G.2     1 m LIST LANGIT - LANGIT GYPSUM 10 cm
 A      BAHAN
   1    List gypsum profil                                        m    1.1000    23,000.00   25,300.00
   2    Paku                                                      kg   0.0100    47,000.00      470.00
   3    Tepung gypzum                                             kg   0.1500   102,500.00   15,375.00
                                                                                             41,145.00
B       TENAGA
    1   Pekerja                                                   Oh   0.0500   130,000.00    6,500.00
    2   Tukang kayu                                               Oh   0.0500   155,000.00    7,750.00
    3   Kepala tukang                                             Oh   0.0050   180,000.00      900.00
    4   Mandor                                                    Oh   0.0030   200,000.00      600.00
                                                                                             15,750.00
C       PERALATAN
D                   Jumlah Bahan, Tenaga, dan Peralatan (A+B+C)                  56,895.00
E                                    Overhead & Profit 10 % X D                         -
F                                  Harga Satuan Pekerjaan (D+E)                  56,900.00
                                                           DAFTAR KUANTITAS DAN HARGA
                               PEKERJAAN 1 (SATU) PAKET PENGECATAN KANTOR KAS BANK PEMBANGUNAN KALTENG
                   (KANTOR WALIKOTA PALANGKARAYA, RSUD DORIS SYLVANUS, PEMPROP KALTENG, SAMSAT PROP KALTENG)
                                                                                                          HARGA            JUMLAH
    NO                              URAIAN PEKERJAAN                               SAT        VOL         SATUAN            HARGA
                                                                                                           ( Rp )            ( Rp )
     1                                           2                                   3          4             5                 6
I          Kantor Kas Pemerintah Kota Palangka Raya
         1 Pekerjaan Pengupasan Cat Lama                                            M²           245.59        50,100.00      12,304,059.00
         2 Pekerjaan Pengecatan Dinding Interior                                    M²           146.87        70,500.00      10,354,335.00
         3 Pekerjaan Pengecatan Dinding Exterior                                    M²            98.72        82,300.00       8,124,656.00
         4 Pekerjaan Pengecatan Bidang Kayu Lama                                    M²            65.10        45,505.00       2,962,375.50
         5 Pekerjaan Pemasangan Plafond Baru                                        M²             2.33        59,500.00         138,635.00
         6 Pekerjaan Perbaikan Plafond                                              M²            69.64        10,000.00         696,400.00
         7 Pekerjaan Pemasangan List Plafond                                        M´             3.00        56,900.00         170,700.00
         8 Pekerjaan Pengecatan Plafond                                             M²            71.97        43,000.00       3,094,710.00
         9 Pekerjaan Cor Lantai Kerja                                               M³             4.24     1,226,600.00       5,200,784.00
               Total Biaya                                                                                                    43,046,654.50
II         Kantor Kas Pemprop Kalimantan Tengah
         1 Pekerjaan Pengupasan Cat Lama                                            M²           239.20       50,100.00       11,983,920.00
         2 Pekerjaan Pengecatan Dinding Interior                                    M²           140.60       70,500.00        9,912,300.00
         3 Pekerjaan Pengecatan Dinding Exterior                                    M²            98.60       82,300.00        8,114,780.00
         4 Pekerjaan Perbaikan Plafond                                              M²           102.70       10,000.00        1,027,000.00
         5 Pekerjaan Pengecatan Plafond                                             M²           102.70       43,000.00        4,416,100.00
               Total Biaya                                                                                                    35,454,100.00
III        Kantor Kas RSUD Doris Sylvanus
         1 Pekerjaan Pengecatan Dinding Interior                                    M²           216.00       70,500.00       15,228,000.00
         2 Pekerjaan Pengupasan Cat Lama                                            M²            94.80       50,100.00        4,749,480.00
         3 Pekerjaan Pengecatan Plafond                                             M²            94.80       43,000.00        4,076,400.00
               Total Biaya                                                                                                    24,053,880.00
IV         Kantor Kas Samsat Propinsi Kalimantan Tengah
         1 Pekerjaan Pengupasan Cat Lama                                            M²           253.49       50,100.00       12,699,849.00
         2 Pekerjaan Pengecatan Dinding Baru                                        M²           254.00       70,500.00       17,907,000.00
         3 Pekerjaan Pengecatan Plitur Bidang Kayu Dengan Cat Kayu                  M²            55.44       84,100.00        4,662,504.00
         4 Pekerjaan Perbaikan Plafond                                              M²            83.49       10,000.00          834,900.00
         5 Pekerjaan Pengecatan Plafond                                             M²            83.49       43,000.00        3,590,070.00
         6 Pekerjaan Pemasangan Lis Plafond                                         M'             3.30           56900          187,770.00
               Total Biaya                                                                                                    39,882,093.00
              Jumlah Total (I + II + III + IV)                                                                               142,436,727.50
              PPn                                                                                                             15,668,040.03
              Grand Total                                                                                                    158,104,767.53
              Pembulatan                                                                                                     158,105,000.00
              Terbilang :                    Seratus Lima Puluh Delapan Juta Seratus Lima Ribu Rupiah