Home 1
Home 1
that in tropical and subtropical regions 15% power output enhancement may be
achieved (Wen and Narula, 2000). Ondryas et al. (1991) presented that the cost of
installing a gas turbine or combined cycle plant rated at 35 °C is 20-30% higher than
that rated at 6.6 °C, so cooling the compressor inlet to a certain temperature will reduce
the installing cost. In their assessment they had also emphasized compressor inlet
temperature limits which should not be below 0 °C to prevent ice building on the
compressor blades since the chilled air shall be at 100% relative humidity due to the
The performance of combined gas turbine plant under three different blade cooling
schemes: air cooling, open circuit steam cooling (OCSC) and closed loop steam cooling
(CLSC) was discussed by (Najjar et al., 2004), and it was reported that more power is
created when the cooling steam in the closed loop is not thrown away, thus, the power
output with (CLSC) is increased by 6%, accompanied by 19% rise in the efficiency
relative to (OCSC) at similar conditions. On the other hand, (CLSC) results in 11%
enhancement in power and 3.2% in the efficiency relative to air cooling at the same
circumstances.
improvement in operating parameters for both steam and gas turbine and raising
Turbine Inlet Temperature (TIT) to 1427 °C (Bannister et al., 1995, a and b). A
reduction in TIT by 10%, drops the combined specific power by 24% and the efficiency
by 7.1% with air cooling scheme, but if CLSC is used, the decrease in the former will
be 22% and 5.1% in the latter at 10% reduction in TIT (Najjar et al., 2004).
system, which supplies all heating, cooling and part of the electric power for Great
14
Western’s computer and office complex in Northridge, Calif., was, put into operation.
This system consists of three gas-turbine generator sets rated at 560 kW each with one
being used as stand-by. One unit operates continuously to supply the cooling needs of
the computer center. Waste heat from the turbine exhaust at 482 oC is used to power a
355-ton double-effect absorption (it has a COP 40% higher than the single-effect
design) chiller in-addition to providing domestic hot water and space heating. The
second unit is operated 8-10 hours a day during work days to supply cooling to the
A life cycle cost analysis showed the cogeneration system having a payback period
of 5.1 years with a 19.25 percent rate of return, which equates to a dollar savings of
more than 250,000 $/year (Freeman, 1983). To obtain maximum power output during
hot weather, the inlet air to each turbine is cooled to 15 oC, considering that the most
recently installed power generation unit of a single gas turbine of 70 MW capacity (Al-
The total capital cost of the 316.8 MW Pasadena cogeneration plant without inlet
cooling (or turbine inlet cooling) is estimated to be $ 237.6 million on ISO conditions
basis (Punwani et al., 2001). Furthermore, the combined plant power output decreases
Therefore, at 35 °C, the same investment of $ 237.6 million increases the effective
capital cost per MW of the uncooled cogeneration power plant from $ 750,000 to about
$870,000. Cooling turbine blades in cogeneration plants improve the overall efficiency
by 2% which may reflect a saving of $ 30-40 million in fuel costs over a typical 30-
It was found by (Zurigat et al., 2004) that the average Net Present Value (NPV) of
installing fogging systems at the gas turbine inlet, in two different locations in Oman,
15
is $ 4,622,018 in Marmul and $ 6,182,496 in Fahud. Also the purchase and installation
costs are paid pack within the first six months of system operation and for later years,
Based on the literature review presented in the foregoing (see Table 3.1) it is seen
that most studies have considered a single or utmost two inlet air cooling techniques
together and very seldom coupled with economic assessments. Furthermore, very few
assessments of GT power plant performance. Therefore, this work is designed to fill the
gap in the literature by considering a number of GT inlet air cooling techniques and
conduct life cycle cost analysis under local weather conditions of one location in
Jordan.
CHAPTER 4
In this Chapter the mathematical models of the cycles described in Table 1.1 are
developed. The governing equations are presented with reference to the empirical or
theoretical foundations of the parameters involved. The simple gas turbine model is
described first (see Section 4.1) followed by the simple steam turbine model (see
Section 4.2). Then combined cycle model is developed (see Section 4.3) followed by
Simple gas turbine cycle consists of three main components; air compressor,
combustion chamber (C-C) and gas turbine (see Fig. 4.1). Ambient air is compressed in
the compressor in an adiabatic process 1-2 (or 1-2S if it were isentropic process). In the
combustor fuel is injected and burned under isobaric process 2-3, and an increase in
temperature of the gas mixture is achieved at point 3 (see Fig. 4.2). A slight pressure
drop takes place in the combustion chamber, so the pressure at point 3 is smaller than
the pressure at point 2. Finally, the flow is expanded in the turbine, in an adiabatic
process 3-4 (or 3-4S if it were isentropic process), where part of the energy is extracted
to drive the compressor, and the reset is utilized to produce a rotational motion that
could be used in generating electricity or shaft power. The pressure at turbine exit
(point 4) is greater than atmospheric pressure. Also, the turbine exhaust temperature is
very high so the flue gases can rise to a high level in the atmosphere, hence, a reduction
18
in the environmental and health impacts is achievable. This cycle is termed the gas
turbine simple cycle. Mathematical models of different gas turbine components are in
order:
2 3
Combustor
Electrical
Generator
4
1
P3
Temperature (K)
P2
2S 2
4
P4 4S
P1
1
Entropy (kJ/kg.K)
The specific work of the compressor (kJ/kg) can be calculated using the first
(kgwater/kgdry, air), Τ01 is the compressor inlet temperature (in K), Τ02 is the
compressor outlet temperature (in K), m& air is the mass flow rate of the air
(kg/s), hVap , 02 and hVap , 01 are the enthalpies (kJ/kg) of superheated water vapor
⎛ RC − 1 ⎞
η C = 1 − ⎜ 0.04 + ⎟ (4.3)
⎝ 150 ⎠
given in terms of RC , Τ01 and the specific heat ratio γ air (Hameed, 1996) as:
T01 ⎛ γ air −1 ⎞
T02 = T01 + ⎜ R γ air − 1⎟ (4.4)
ηC ⎝ C ⎠
the average inlet-outlet temperature (in K) (Al-Hazmy and Najjar, 2004) as:
20
This is valid within the range 200-800 K. For 800-2200 K range the
The humidity ratio (specific humidity) is given in two forms by Helal (1991)
as
m& Vap
d= (4.7)
m& air
0.622 PVap
d = (4.8)
P − PVap
Where PVap and P are the vapor partial pressure in the moist air and the total
Where RH is the relative humidity and PSat .Vap is the saturated vapor partial
3142.31
Z = 30.59051 − 8.2 log10 T + 0.0024804 T − (4.11)
T
The total pressure at air compressor intake is P01 = Pamb − Δ PAir , Duct
(Hameed, 1996). Where Pamb , ΔPAir , Duct are ambient pressure and pressure drop
across the intake duct (kPa). In this work pressure drop was ignored in simple
21
gas turbine calculations and had been taken into account for cooled gas turbine
as the inlet air cooler poses an appreciable pressure drop. The mass flow rate
of dry air m& air (kg/s) is given in terms of the volumetric flow rate of dry air
Vol air (m3/s) and the specific volume of dry air ν air (m3/kgdry, air) is given by
Volair
m& air = (4.12)
ν air
Tamb
ν air = (0.287 + 0.462 d amb ) (4.13)
Pamb
In the previous equation, the ambient temperature Tamb is in Kelvin and the
ambient pressure Pamb is in kPa. d amb is the ambient air humidity ratio and can
Also, the released heat rate (kW) from the combustion chamber will be:
In the above equations T03 is the turbine inlet temperature (in K), C P , g is the
specific heat of flue gases across the combustor at constant pressure (kJ/kg.K),
(in K):
The fuel air ratio f (kgfuel/kgdry, air), defined by Hameed (1996) as:
m& f
f = (4.17)
m& air
Energy balance equation can be written for an insulated chamber, and the fuel
Where hVap , 03 is superheated water vapor enthalpy at the combustor outlet and
Δhc is the fuel calorific value, both in (kJ/kg). The constant 298 in Eq. (4.18)
Regarding equation (4.14), it should be noted that the flue gases (the
mixture of air, water vapor and fuel) behave as an ideal gas in such cases, so
pressure. Therefore, all the results are concluded by using total pressure. Also,
turbine. The combustor inlet total pressure P02 (kPa) is given by (Molqy,
2000):
Due to the pressure drop in the combustor, the outlet total pressure of
The total mass flow rate (kg/s) cross the combustor and the turbine can be calculated
Where C P , T is the flue gases specific heat (kJ/kg.K), calculated using equation
(4.16) at the turbine inlet-outlet average temperature, T04 is gas turbine outlet
temperature (K).
⎛ RC − 1 ⎞
η T = 1 − ⎜ 0.03 + ⎟ (4.24)
⎝ 180 ⎠
Gas turbine outlet temperature T04 (K) is determined by Cohen (2004) as:
γ gas −1
⎡ ⎤
⎢⎛ 1 ⎞ γ gas
⎥
T04 = T03 + η T T03 ⎢⎜⎜ ⎟⎟ − 1⎥ (4.25)
R
⎢⎣⎝ C ⎠ ⎥⎦
Where γ gas is the specific heat ratio of the flue gases across the turbine. The
outlet total pressure P04 (kPa) from the turbine is described by Cohen (2004)
as:
1
⎛T ⎞ η T ⎛⎜ γ gas −1 ⎞⎟
P04 = P03 ⎜⎜ 04 ⎟⎟ ⎜⎝ γ gas ⎟⎠ (4.26)
⎝ T 03 ⎠
24
As stated earlier the gas turbine exhaust pressure and temperature are above
2004).
The specific net power (kJ/kg) of the gas turbine plant can be evaluated as:
SPGT = WT − WC (4.27)
The net power (kW) of the gas turbine installation is given as:
PGT = N T − N C (4.28)
(2004) as follows:
SPGT
η GT = (4.29)
f Δhc
PGT
η GT = (4.30)
Q + N Aux
increases keeping the relative humidity equal zero while it may increase or
decrease depending on the relative humidity value. In this research Eq. (4.29)
3600 m& f
SFC = (4.31)
PGT
25
Steam turbine power plants had been used widely in the past. Steam plant is
characterized by high efficiency ranging 40-55%. In spite of its high efficiency, steam
turbine power stations have an inherent disadvantage, the production of high pressure
and temperature involves bulky and expensive steam generating equipments (Cohen,
2004). Simple steam turbine power cycle consists of three main components, steam
generator or boiler, steam turbine and condenser (see Fig. 4.3). As shown in Fig. 4.4 the
boiler heat is added under isobaric process (6-7 or 6S-7), water vapour is formed at
elevated temperature and pressure (point 7). Pressure drop can take place in the boiler
furnace and in pipes, so the pressure at point 7 will be at 7`. Finally, the steam is
8S, respectively). Expansion process can be 7`-8 or 7`-8S if the pressure drop is taken in
consideration. The condenser works under vacuum constant pressure 8-5 or 8S-5. This
cycle is called simple steam turbine cycle or Rankin cycle if all the processes
The specific work of a steam turbine (kJ/kg) is given by Hameed (1993) as:
Where m& steam is mass flow rate of steam via steam turbine (kg/s), h07 and h08, S
are steam turbine inlet and outlet enthalpies in an isentropic process (kJ/kg).
26
Steam
Turbine
Electrical
7´ Generator
Hot Side
8
7
Steam
Condenser
Boiler
Cooling Tower
Water
Pump
Cold Side
6 5
P7
P7`
Temperature (K)
7`
6
6S
P8
5 8S 8
In ideal case, h07 = f( P07 , T07 ), h08, S = f( P08 , S 08, S ). Also, P08 = 3.0 to
drop ΔPBoiler , Turbine from the boiler inlet to the steam turbine inlet is
the pressure at the boiler inlet and P07′ = P06 − ΔPBoiler , Turbine is inlet pressure of
2003).
The steam turbine outlet enthalpy h08 (kJ/kg) is calculated by the following
′ − η ST (h07
h08 = h07 ′ − h08, S ) (4.34)
From first law of thermodynamics, the condenser load (kW) in ideal case is
estimated by:
Where h05 is the enthalpy (kJ/kg) at the condenser exit or at the water pump
′ − h06 )
QBoiler = m& steam (h07 (4.38)
subroutine developed by h06 , S = ( P06 , S 06, S ) , where S 06, S is the outlet water
pump entropy in an isentropic process. On the other hand, h06 the boiler inlet
h06, S − h05
h06 = + h05 (4.39)
η w, pump
Where η w, pump is water pump efficiency; η w, pump = (70 − 88)% (Rostom, 1997).
The water pump specific power (kJ/kg) in ideal cycle case is given by Molqy
(2000):
ν 05 ( P06 − P05 )
Ww, pump = (4.42)
η w, pump
Since the inlet water pump pressure P05 is equal to the condenser pressure, the
PST
η STP = (4.45)
QBoiler
Simple steam turbine power station design can be verified by the following
ratios which are given by Molqy (2000). The first ratio is the condenser to the
boiler load ratio which is described to be within the range 45-50% of that if the
pressure drop and the irreversible losses were relatively low, or it may exceed
50% for tough circumstances. The other ratio is the water pump specific work
Combined cycle (gas and steam turbines) is a technique which is extensively used to
enhance overall efficiency and power output of power plants. Utilizing the waste
exhaust gas from gas turbine installation to heat up the boiler or heat recovery steam
generator (HRSG) will greatly decrease the fuel consumption required for the steam
power plant, hence the power plant efficiency will increase. Steam turbine power
stations have efficiency of about 40-55%, gas turbine 30-34% and cogeneration
technique 55-63% (Hameed, 1996). It should be noted that in this study actual
combined cycle is modeled, i.e., pressure drop and irreversibility are taken into
account.
The combined cycle consists of gas turbine power station and steam power plant
operating as follows: the exhaust gases with moderate pressure P04 and high
temperature T04 supply heat to the HRSG, i.e., economizer, steam generator and
superheater (see Fig. 4.5). Water enters the pump at state 10, and it is compressed
isentropically along the process 10-11S or adiabatically along 10-11 to the HRSG inlet
pressure P11 (see Fig. 4.6). Water enters the economizer with the parameters T11 , P11
and leaves it at T5 , P5 where the water state at the steam generator inlet is considered to
be wet saturated vapor. Change in phase takes place in the steam generator and dry
saturated vapor is obtained at the steam generator exit with T6 , P6 . Then steam (or dry
saturated vapor) is driven to the superheater resulting in outlet temperature and pressure
T7 , P7 . The superheated steam with the parameters T7 , P7 enters the steam turbine
where it expands isentropically along 7-8S process or adiabatically through 7-8 process.
where the steam enters the condenser (see Fig. 4.6). The steam at the condenser inlet is
usually considered to be with a high quality (high dryness fraction) and isobaric process
takes place in the condenser 8-9. Condensation process is obtained by rejecting heat to
cooling tower or any other cooling medium. Finally steam leaves the condenser with
low quality and enters the pump (process 9-10) thereby, closing the cycle.
In the considered technique mentioned above, inlet air cooling system is used to cool
the air compressor intake and so, the overall efficiency is boosted. Using an absorption
chiller or any other inlet air cooling technique will decrease the specific work of the
compressor since the cooled air has higher density than uncooled air. Although a
parasitic power is generally needed to drive the cooling machines, this will slightly
affect overall efficiency (Hameed, 1996). In this work the absorption chiller is powered
by steam bled from the steam turbine, i.e., small part of steam is extracted from the
steam turbine with the values T12 , P12 to power the absorption chiller generator. Inlet
and outlet conditions of the bled steam have the values T15 , P15 and T16 , P16
The steam exiting the generator is fed into a heat recovery heat exchanger of cross-
flow mixed stream type (state T17 , P17 ) where it is mixed with that coming from the
condenser (state 9) where it exits at state 10. This will obviously decrease the specific
work of the pump and also the fuel needed for the HRSG, so an increase in the power
and two throttling (expansion valves) as shown in Fig. 4.5. In the generator the solution
temperature and pressure ( TGEN , PGEN ). The strong solution (high concentration of H2O
in the former and high concentration of NH3 in the latter) will leave the generator in
vapor state and passes through the condenser while the weak solution with ( TGEN , PGEN
) will be expanded via weak solution throttling valve, then it will enter the absorber in
low temperature and pressure ( T ABSOR. , PABSOR. ). The strong solution enters the
condenser in vapor state and leaves it in liquid state under condensation temperature
and pressure ( TCOND , PCOND ). The high pressurized strong solution in liquid state is
PEVAP ) and it remains in liquid state. It should be noted that the generator and the
condenser operate under same pressure ( PGEN = PCOND ) while the evaporator and the
absorber operate under lower pressure PEVAP which is equal to PABSOR. . The strong
solution enters the evaporator (constant pressure) in liquid state and leaves it in a vapor
state to enter the absorber. A mixture of vapor strong solution and liquid weak solution
(the former comes from the evaporator and the latter from the generator) enters the
absorber where a heat rejection process takes place resulting in both solutions being in
liquid phase. Finally, the solution pump will elevate the pressure of the mixture
Hot Side
Steam Bleeding
Steam
Condenser
6
Super heater
18
Cold Side
Water
14 Pump 17
10 9
Water Cooling
Exhaust Cross flow H.E Pump Tower
Gas Mixed Stream
Expansion
Valve Condenser 16 15
7´ 6´ 5´
Weak Solution
4´
Expansion
Evaporator
1´ Valve
Solution
Pump
2´
3´
8´
Ambient Air
Absorbe
Strong Solution
Ambient
Fig. 4.5. Combined power station with inlet air cooling using absorption refrigeration
powered by steam bled from steam turbine.
14
Terminal
temperature
18
difference
7
P (bar)
19
Pinch
point
13
5
6
Temperature (K)
11
11S
10
9 8S 8
Entropy (kJ/kg.K)
Fig. 4.6. Temperature-entropy diagram of combined power station with inlet air
cooling using absorption chiller powered by steam bled from steam turbine.
4.3.1. Compressor Inlet Air Cooling Load Calculations
Gas turbine inlet air cooling load (kW), both sensible and latent, can be
Where C P , a , H . E is the specific heat of the air cross the heat exchanger (H.E) at
constant pressure (kJ/kg.K) which is given by Eqs. (4.5) and (4.6), TComp , in is
the cooled air temperature at compressor inlet (K), h fg , H . E is the latent heat of
cooler (evaporator hot side). d amb d Comp , in are ambient and cooled inlet air
saturated with constant temperature (Dawoud et al., 2004). The latent load is
The same mathematical model used in simple gas turbine with humidity
effect in Section 4.1 applies here with a slight difference. Pressure drop at the
air duct intake is assumed constant and is taken into account with respect to
the kind of cooling unit used to cool the compressor inlet air. For example, 64
Pa for evaporative coolers, 10 Pa for fogging coolers, 80 Pa for Aqua
chillers and 80 Pa for electrical coolers (Lucas, 2003). Also, relative humidity
to avoid ice forming at the compressor entrance and avoid the structural
Specific net power, total net power and efficiency augmentation of gas
SPC , GT − SPGT
SPAugm = (4.47)
SPGT
PC , GT − PGT
PAugm = (4.48)
PGT
η C , GT − η GT
η Augm = (4.49)
η GT
to be PST = (30 − 44)% PGT . This may serve as an initial guess or starting
point. Steam turbine specific work (kJ/kg) with steam bleeding is evaluated by
and the pressure is calculated as P07 = P06 − ΔPSH , where pressure drop in the
P06 = P05 − ΔPSG , where pressure drop in steam generator ΔPSG is given within
the range ΔPSG = (2 − 6)% P05 (Molqy, 2000). The economizer exit pressure
economizer ΔPECON is given by Najjar et al. (2004) to be within the range used
in the steam generator, i.e., ΔPSG = (2 − 6)% P05 . Economizer inlet pressure
′′ + (1 − χ 08, S ) h08
h08, S = χ 08, S h08 ′ (4.52)
Where ′ , h08
h08 ′′ and χ 08, S are wet saturated vapor, dry saturated vapor
assumed to be defined. The enthalpy of the bled steam h012 is chosen with
known temperature and pressure; h012 = f (T012 , P012 ) that can cover the
The mass flow rate of water vapor (kg/s) passing through the plant is given by
PST
m& steam = (4.54)
[( h07 − h012 ) + (1 − χ bled ) (h012 − h08 )]η mech η elec
Where η mech is the mechanical efficiency of steam turbine which takes into
which takes into account the electrical losses, is assumed to be equal to η mech
(Molqy, 2000).
The condenser outlet (point 9) state (see Fig. 4.5 and 4.6) is defined by
be written as:
Otherwise
PGT + PST
η combined = (4.57)
Q + N Aux
Where Qav is the available amount of heat (kW) and N Aux the power
still has energy that can be recovered by the water (point 10), i.e., at water
pump intake (see Fig. 4.6). A cross flow heat exchanger-mixed stream was
suggested by Hameed (1993) and Molqy (2000). Two streams were considered
as inputs and one as an output (see Fig. 4.5). The inlet streams are condensed
steam coming from the condenser (state 9) with mass flow rate (kg/s):
The second stream is the extracted steam from the steam turbine after
heating the absorption chiller generator (state 17) shown in Fig. 4.5. The
enthalpy h017 = f (T017 , P017 ) and the mass flow rate (kg/s) is:
The outlet stream is defined by h010 = hmix and assumed pressure P010 = Pmix
which must be less than pressure at point 17. So, the suction process can take
place in cross flow heat exchange-mixed stream. Steam at states 17 and 9 are
absorbed in the exchanger. The enthalpy at the pump inlet h010 is determined
by Helal (1990):
pump discharge is assumed equal to the economizer inlet pressure P011 , so the
( P011 , S 011, S ) . The enthalpy at water pump outlet or at the economizer inlet
h011 can also be evaluated by the following equation (Najjar et al., 2004):
h011 = h010 +
1
η w, pump
(h
011, S − h010 ) (4.61)
1997). Water pump specific work (kJ/kg) is given by Najjar et al. (2004) as:
Molqy (2000) had recommended the ratio of water pump specific work to
steam turbine specific work to range from 3 to 4%. By this relation, the design
of steam turbine and water pump specific work can be validated. It was
pump outlet and inlet should not exceed the limit of 3 °C. It will be seen in the
next Section that simultaneous validation for steam turbine power plant design
can be done via another equation, which is a function of condenser and HRSG
Steam generator inlet and outlet temperatures T05 , T06 respectively are
estimated, since the pressure and temperature are defined. The recovery load
(kW) on the cold side or the required heat in steam turbine power installation
Where Q ECON is the economizer load, QSG is the steam generator load, and
QSH is the superheater load. These loads (kW) are calculated from the first law
of thermodynamics as:
pressure, temperature and dryness fraction i.e. h05 = f ( P05 , T05 , χ 05 ) . The ratio
of steam condenser load to heat recovery steam generator load should range
from 45 to 50%. This range exceeds 50% if the pressure drop and the
irreversible losses were high, and the power plant operates under harsh
Assuming the flue gases to behave as ideal gas the heat recovery steam
The total mass flow rate of cooled gas turbine m& C , total across the HRSG is
ε HRSG is taken to be 0.90. The specific heat of flue gases via the recovery C P , g
follows: T014 = T04 − ΔT04 − 014 , where ΔT04 − 014 is the temperature drop from the
Flue gases temperature (K) at point 18, 19 and 13 (see Fig. 4.5 and 4.6) can be
QSH
T018 = T014 − (4.69)
ε HRSG C P , g m& C , total
QSG
T019 = T018 − (4.70)
ε HRSG C P , g m& C , total
Q ECON
T013 = T019 − (4.71)
ε HRSG C P , g m& C , total
It should be noted that in the above equations the specific heat C P , g was
(Molqy, 1996). Here TECON , in is the economizer inlet temperature (K) (state 11)
أداء اﻟﻤﻨﺸﺄة اﻟﻤﺸﺘﺮآﺔ )ﻋﻨﻔﺔ ﻏﺎزﻳﺔ – ﺑﺨﺎرﻳﺔ( ﻣﻊ ﺗﺒﺮﻳﺪ اﻟﻬﻮاء اﻟﺪاﺧﻞ إﻟﻲ اﻟﻀﺎﻏﻂ
ﺑﺎﺳﺘﺨﺪام اﻟﺘﺒﺮﻳﺪ اﻻﻣﺘﺼﺎﺻﻲ اﻟﻌﺎﻣﻞ ﻋﻠﻰ ﺣﺮارة اﻟﻐﺎز اﻟﻌﺎدم
إﻋﺪاد
ﻋﻼء ﺣﺴﻴﻦ ﻋﺒﺪ اﷲ ﺟﺒﺮ
اﻟﻤﺸﺮف
أ .اﻟﺪآﺘﻮر ﻳﻮﺳﻒ زرﻳﻘﺎت
اﻟﻤﺸﺮف اﻟﻤﺸﺎرك
أ .اﻟﺪآﺘﻮر ﻳﻮﺳﻒ اﻟﻨﺠﺎر
ﻣﻠﺨﺺ
ﺗﻨﺎوﻟ ﺖ ه ﺬة اﻟﺪراﺳ ﺔ ﻋﻤﻠﻴﺘ ﻲ اﻟﻨﻤﺬﺟ ﺔ و اﻟﻤﺤﺎآ ﺎة ﻟﻤﻨﺸ ﺄﺗﻲ ﺗﻮﻟﻴ ﺪ اﻟﻄﺎﻗ ﺔ اﻟﻜﻬﺮﺑﺎﺋﻴ ﺔ اﻟﻤﺸ ﺘﺮآﺔ
)ﻋﻨﻔ ﺔ ﻏﺎزﻳ ﺔ – ﺑﺨﺎرﻳ ﺔ( و)ﻋﻨﻔ ﺔ ﻏﺎزﻳ ﺔ – ﻣﺴ ﺘﺮﺟﻊ ﺣ ﺮاري( ﻣ ﻊ ﺗﺒﺮﻳ ﺪ اﻟﻬ ﻮاء اﻟ ﺪاﺧﻞ اﻟ ﻰ
اﻟﻀﺎﻏﻂ.
ﻋﺪة ﻋﻤﻠﻴﺎت ﺗﻜﻨﻮﻟﻮﺟﻴﺔ ﺗ ﻢ ﺗﻄﺒﻴﻘﻬ ﺎ ﻟﺘﺒﺮﻳ ﺪ اﻟﻬ ﻮاء اﻟ ﺪاﺧﻞ اﻟ ﻰ اﻟﻀ ﺎﻏﻂ ﻓ ﻲ آﻠﺘ ﺎ اﻟﻤﻨﺸ ﺄﺗﻴﻦ ,ﻣﺜ ﻞ
اﻟﺘﺒﺮﻳ ﺪ ﺑﺎﺳ ﺘﺨﺪام اﻷﺛ ﺮ اﻻﻣﺘﺼﺎﺻ ﻲ )أﻣﻮﻧﻴ ﺎ ﻣ ﻊ ﻣ ﺎء( و)ﺑﺮوﻣﻴ ﺪ اﻟﻠﻴﺜ ﻮم ﻣ ﻊ ﻣ ﺎء( ﺑﺎﻻﺿ ﺎﻓﺔ إﻟ ﻲ
اﻟﺘﺒﺮﻳﺪ اﻟﺒﺨﺎري وأﻳﻀﺎ ﺗﻘﻨﻴﺘﻲ اﻟﺘﺮﻃﻴﺐ ﻣﻌﺘﺪﻟﺔ وﻣﺮﺗﻔﻌﺔ اﻟﻀﻐﻂ .ﻟﻘﺪ ﺗ ﻢ إﺳ ﺘﻨﺰاف ﺟ ﺰء ﻣ ﻦ اﻟﺒﺨ ﺎر
ﻓ ﻲ ﻣﻨﺸ ﺄة اﻟﺘﻮﻟﻴ ﺪ اﻟﻤﺸ ﺘﺮآﺔ )ﻋﻨﻔ ﺔ ﻏﺎزﻳ ﺔ – ﺑﺨﺎرﻳ ﺔ( ﻟﺘﻐﺬﻳ ﺔ ﻣﻮﻟ ﺪ ﺁﻟ ﺔ اﻟﺘﺒﺮﻳ ﺪ اﻻﻣﺘﺼﺎﺻ ﻴﺔ ﺑﻴﻨﻤ ﺎ
أﺟﺮﻳﺖ ﻋﻤﻠﻴﺔ اﻟﺘﺴﺨﻴﻦ ﻟﻠﻤﻮﻟﺪ ذاﺗ ﻪ ﺑﻮاﺳ ﻄﺔ ﺣ ﺮارة اﻟﻐ ﺎزات اﻟﻌﺎدﻣ ﺔ ﻓ ﻲ اﻟﻤﻨﺸ ﺄة اﻟﻤﺸ ﺘﺮآﺔ )ﻋﻨﻔ ﺔ
إن اﻟﺒﺮﻧﺎﻣﺞ اﻟﻤﺤﻮﺳﺐ )ﻋﻤﻠﻴﺘﻲ اﻟﻨﻤﺬﺟﺔ و اﻟﻤﺤﺎآﺎة( اﻟﺬي ﺗﻢ إﻋﺪادﻩ ﻓ ﻲ ه ﺬة اﻟﺪراﺳ ﺔ ﻗ ﺪ أﺧﻀ ﻊ
ﻟﻌﺪة إﺧﺘﺒﺎرات وذﻟﻚ ﻟﻤﻌﺮﻓﺔ ﻣﺪى دﻗﺔ هﺬا اﻟﻨﻈﺎم اﻟﻤﻄﻮر.ﻟﻘﺪ ﺗ ﻢ اﻟﺘﺄآﻴ ﺪ ﻋﻠ ﻰ ذﻟ ﻚ ﻣ ﻦ ﺧ ﻼل إدﺧ ﺎل
ﻋ ﺪة ﺑﻴﺎﻧ ﺎت ﺗﻘﻨﻴ ﺔ ﻣﺘﻌﻠﻘ ﺔ ﺑﺎﻟﻌﻨﻔ ﺎت اﻟﻐﺎزﻳ ﺔ اﻟﺼ ﺎدرة ﻋ ﻦ أﺷﻬﺮاﻟﺸ ﺮآﺎت اﻟﺼ ﺎﻧﻌﺔ وﻣﻨﺸ ﺂت اﻟﺘﻮﻟﻴ ﺪ
اﻟﻤﺸ ﺘﺮآﺔ )ﻋﻨﻔ ﺔ ﻏﺎزﻳ ﺔ – ﺑﺨﺎرﻳ ﺔ( إﻟ ﻰ ه ﺬا اﻟﺒﺮﻧ ﺎﻣﺞ وآﺎﻧ ﺖ ﻧﺴ ﺒﺔ اﻟﺨﻄ ﺄ ﻗﺮﻳﺒ ﺔ إﻟ ﻰ اﻟﺼ ﻔﺮ .إن
اﻟﺒﻴﺎﻧﺎت اﻟﻤﺪﺧﻠﺔ ﻓ ﻲ ﺣﺎﻟ ﺔ اﻟﺘﻮﻟﻴ ﺪ اﻟﻤﺸ ﺘﺮك )ﻋﻨﻔ ﺔ ﻏﺎزﻳ ﺔ – ﺑﺨﺎرﻳ ﺔ( ﻗ ﺪ أﺧ ﺬت ﻣ ﻦ ﻣﺤﻄ ﺔ ﺗﻘ ﻊ ﻓ ﻲ
ﺗﻤ ﺖ أﻳﻀ ﺎ دراﺳ ﺔ اﻟﻨﺎﺣﻴ ﺔ اﻹﻗﺘﺼ ﺎدﻳﺔ ﻣ ﻦ ﺗﻜ ﺎﻟﻴﻒ و ﻓﺘ ﺮة إﺳ ﺘﺮﺟﺎع ﻟ ﺮأس اﻟﻤ ﺎل اﻟﻤﻮﻇ ﻒ
ﺑﺎﻹﺿ ﺎﻓﺔ إﻟ ﻰ اﻟﻘﻴﻤ ﺔ اﻟﺤﺎﻟﻴ ﺔ اﻟﺼ ﺎﻓﻴﺔ ﻟﻌ ﺪد ﻣﺨﺘﻠ ﻒ ﻣ ﻦ ﻣﻌ ﺎﻣﻼت اﻟﺘﺤﻮﻳ ﻞ اﻟﻨﻈ ﺎﻣﻲ ﻟﻠﻤﺼ ﺎرﻳﻒ
اﻟﻤﺨﺘﻠﻔﺔ زﻣﻨﻴﺎ .ﻣﻌﺪل اﻟﺤﺴﻮﻣﺎت و اﻟﺘﻀﺨﻢ اﻟﻤﺎﻟﻲ ﺗﻢ أﺧﺬﻩ ﻣﺴﺎوﻳﺎ 0.08و 0.03ﻋﻠﻰ اﻟﺘﻮاﻟﻰ.
إن اﻟﻨﺘ ﺎﺋﺞ اﻟﻨﻬﺎﺋﻴ ﺔ أﺷ ﺎرت إﻟ ﻰ أن ﻣ ﺮدود اﻟﻌﻨﻔ ﺔ اﻟﻐﺎزﻳ ﺔ اﻟﻌﺎﻣﻠ ﺔ ﺑﺈﺳ ﺘﻄﺎﻋﺔ 203 MWوﻓﻘ ﺎ
ﻟﻠﺸﺮوط اﻟﻨﻈﺎﻣﻴﺔ ﻳﺴﺎوى ﺗﻘﺮﻳﺒ ﺎ 50%وذﻟ ﻚ ﺑﺈﺳ ﺘﺨﺪام ﺗﻘﻨﻴﺘ ﻲ اﻟﺘﺒﺮﻳ ﺪ ﺑﺎﻟﺘﺮﻃﻴ ﺐ ﻣﻌﺘﺪﻟ ﺔ أوﻣﺮﺗﻔﻌ ﺔ
اﻟﻀﻐﻂ ﻋﻨﺪ ﻣﺪﺧﻞ اﻟﻀﺎﻏﻂ .إن ﻣﺮدود ﻣﻨﺸﺄة اﻟﺘﻮﻟﻴﺪ اﻟﻤﺸﺘﺮآﺔ )ﻋﻨﻔ ﺔ ﻏﺎزﻳ ﺔ – ﻣﺴ ﺘﺮﺟﻊ ﺣ ﺮاري(
و )ﻋﻨﻔﺔ ﻏﺎزﻳﺔ – ﺑﺨﺎرﻳﺔ( آﺎن ﻣﺴﺎوﻳﺎ ﺗﻘﺮﻳﺒﺎ إﻟ ﻰ 56%و 60%ﻋﻠ ﻰ اﻟﺘ ﻮاﻟﻰ وذﻟ ﻚ ﺑﺈﺳ ﺘﺨﺪام ﺁﻟ ﺔ