04 Operation
04 Operation
Table of Contents:
4 Operation ...........................................................................................................2
4.1 Anchor Windlass ...............................................................................................2
4.1.1 Definitions. ........................................................................................................3
4.1.2 Operating controls.............................................................................................3
4.1.3 Anchoring procedure.........................................................................................4
4.1.4 Adjustment of chain length at anchoring and heave-in operation .....................6
4.1.5 Warnings. ..........................................................................................................8
4.1.6 Background. ......................................................................................................9
4.1.7 Windlass performance vs. chain criteria .........................................................10
4.2 Mooring operation ...........................................................................................11
4.3 Mooring patterns .............................................................................................13
4.4 Split Mooring Drum .........................................................................................14
4.4.1 Operation ........................................................................................................15
4.5 Precautions .....................................................................................................16
4.6 References......................................................................................................17
Aker Pusnes AS
CONFIDENTIAL
SHOULD NOT BE DISTRIBUTED AND / OR BE MADE AVAILABLE TO THIRD PARTIES WITHOUT OUR WRITTEN CONSENT
Technical Information
Subject Issued by: Date: Rev.No.: TI No.:
KHØ 03.02.05
Operating Instruction
Aker Pusnes AS Anchor Windlass
RevBy: Rev Date 05 TI 0026
Arendal, Norway KHØ 04.03.08
Table of contents:
___________________________________________________________________
1. Purpose Page 2
2. Definitions. Page 2
3. Description. Page 2
5. Warnings. Page 6
6. Background. Page 7
6.1 IMPORTANT. Page 7
6.2 Windlass performance vs. chain criteria. Page 8
_______________________________________________________________
Figure above is from booklet “Effective Mooring” used with permission from OCIMF
KHØ 03.02.05
Operating Instruction
Aker Pusnes AS Anchor Windlass
RevBy: Rev Date 05 TI 0026
Arendal, Norway KHØ 04.03.08
1 Purpose.
The purpose of this procedure is to ensure safe operation of Aker Kværner Pusnes anchor
windlass.
2 Definitions.
3 Description.
Operating controls
Each anchor winch is equipped with a sign plate as shown on Fig. 3-1 or Fig 3-2.
For winches equipped with interlock for “High Speed” it should be impossible to run
the winch in “High Speed” when connected to the cable lifter unit. This interlock
function must never be tampered!
For winches without interlock of “High Speed” the operator himself is responsible
that the anchor winch is run in “Low Speed” mode when connected to the cable lifter
unit.
Fig. 3-1 Layout of controls for Fig. 3-2 Layout of controls for anchor
anchor winch WITHOUT interlock winch WITH interlock for “High
for “High Speed” Speed”
KHØ 03.02.05
Operating Instruction
Aker Pusnes AS Anchor Windlass
RevBy: Rev Date 05 TI 0026
Arendal, Norway KHØ 04.03.08
Some hydraulic motors are one speed motors only, in this case the lever D is not
positioned on the valve block for the operating control.
4 Anchoring procedure.
1. Start hydraulic power pack (HPU) and select “Working Pressure”
2. Remove covers, etc. from the chain locker and hawse pipe.
6. Switch the speed selector valve “D”, Fig. 3-1, 3-2, to “Low Speed” position.
7. Connect the clutch between the cable lifter unit and the anchor winch.
For winches with interlock function this is performed with the lever “F”, Fig. 3-2.
For winches without interlock connection this operation has to be done manually.
9. Keep the anchor in stowed position by means of the winch motor power, and then
release the cable lifter brake.
10. Remove the anchor lashing. Release the chain stopper bar, if necessary by lifting the
anchor weight with the winch.
KHØ 03.02.05
Operating Instruction
Aker Pusnes AS Anchor Windlass
RevBy: Rev Date 05 TI 0026
Arendal, Norway KHØ 04.03.08
11. Keep the winch in "Low Speed" and carefully lower the anchor to the water surface by
means of the winch motor.
13. For further pay-out of the anchor, two procedures may be chosen:
4.1) Walking the anchor out by the winch motor.
4.2) Drop the anchor by using the cable lifter brake.
1. Make sure that the vessel is not drifting off with a Speed Over Ground (S.O.G.) which
is higher than the winch motor speed. (appr. 9 m/min)
If S.O.G. is higher than the winch motor speed the anchor and chain should be
dropped by means of the cable lifter brake to avoid any damage to the winch gear or
motor.
2. Ensure that the pressure setting on the hydraulic power pack is set to “Stand-By
High” position. (If “Working pressure” is selected, the oil can be overheated and the
high temp alarm is released).
2a. Option:
Integrated system with HPU by others: Select Working Pressure.
7. Disconnect the clutch between the cable lifter unit and winch.
8. Stop HPU.
1. When the anchor is at water level, apply the cable lifter brake and disconnect the
cable lifter unit from the anchor winch.
KHØ 03.02.05
Operating Instruction
Aker Pusnes AS Anchor Windlass
RevBy: Rev Date 05 TI 0026
Arendal, Norway KHØ 04.03.08
) Note!
ABSOLUTELY AVOID a too high speed during this operation.
5. Stop HPU.
2. Make sure the anchor chain tension is as small as possible, i.e. that the leading angle
of chain is close to the vertical. If high tension, start main engine and use the propeller
to slacken the chain tension.
3. When slack chain / low tension, connect the clutch between cable lifter unit and
anchor winch. Check that the clutch is properly engaged.
6. Move the operation lever “E” in “Heave” direction and release the cable lifter brake.
KHØ 03.02.05
Operating Instruction
Aker Pusnes AS Anchor Windlass
RevBy: Rev Date 05 TI 0026
Arendal, Norway KHØ 04.03.08
9. When necessary adjustment of length is obtained, stop heaving; apply the chain
stopper bar, the cable lifter brake and disconnect the windlass coupling.
10. When hauling-in the whole chain length reduce the speed to a minimum the last
metres of heaving. When the anchor flukes have found their position in the hawse
pipe, the power of the winch could be increased to maximum to ensure that the
anchor is properly stowed.
11. Keep full heave-in power while setting the cable lifter brake.
12. Apply the chain stopper bar and lash the anchor with strong wire or chain and ensure
that these lashings can take a load of at least 3 times the anchor weight.
Tighten the lashings with a turnbuckle or another suitable arrangement and make sure
that the anchor is absolutely secured in "housed position".
13. Disconnect the clutch between the cable lifter unit and the anchor winch.
5. Warnings.
Note!
) Never do anchor handling with the winch in “High Speed” mode.
The pulling capacity is reduced and high tension in chain may cause
severe damage of the motor.
Note!
) If a temporary stop in the anchor operation, always engage the cable
lifter brake.
When finished, engage the chain stopper bar, the cable lifter brake
and disconnect the coupling between cable lifter unit and anchor
winch.
PRECAUTIONS:
KHØ 03.02.05
Operating Instruction
Aker Pusnes AS Anchor Windlass
RevBy: Rev Date 05 TI 0026
Arendal, Norway KHØ 04.03.08
Note!
The brake lining thickness, and the brake adjustment, is extremely
) important for a safe operation of the cable lifter brake performance.
Lack of adjustment can end up in loss of anchor as the brake no
longer has a sufficient holding load.
Note!
Never attempt to break loose the anchor from the bottom using the
) propeller unless the chain rests in chain stopper.
Note!
Switch to "Stand by - Low" pressure for longer waiting periods to
) avoid heat generation in the oil, stop the pumps when the operation
is completed.
(Not applicable to option: “HPU by others”)
6 Background.
As the angle between the chain and the vertical is 45 degree or less
it is of utmost importance to keep a low tension in chain. At this
stage the azimuth movement of the vessel will affect the chain
tension very much.
) A lift from a heavy sea or swell will induce a pulling force in the
chain, which is much higher than the pulling force of the hydraulic
motor. That will cause the motor to render at a speed far beyond the
maximum permissible speed and damage the motor. The oil flow in
this case will be more than ten times the capacity of the safety valve
in the motor, which will not be able to bleed off.
KHØ 03.02.05
Operating Instruction
Aker Pusnes AS Anchor Windlass
RevBy: Rev Date 05 TI 0026
Arendal, Norway KHØ 04.03.08
Fig 4-1
6.2 Windlass performance vs. chain criteria
) Note!
Example:
Chain diameter : 100 mm
Minimum Breaking Load (MBL) : 7060 kN (~720 ton).
Holding capacity of chain stopper : 80% of chain MBL = 5648 kN (~576 ton). 1)
Brake holding load of cable lifter : 45% of chain MBL = 3177 kN (~324 ton) 1)
Pulling force of cable lifter:
- Nominal: 46,6 x (dchain)2 : (46,6 x 1002)/1000 = 466 kN (~47,5 ton) 1)
- Maximum: Nominal pull x 1,5 : 466 x 1,5 = 699 kN (~71,2 ton) 1)
1)
These values are all specified by the classification societies and will be the (minimum) design criteria for
all new vessels provided not a higher specification is agreed upon between owner and yard.
Note!
) For any cable lifter unit the maximum pulling capacity is less than
10% of the chain MBL.
)
Note!
Keep in mind following relations between the anchor windlass and the
strength of the anchor chain.
Example:
Chain diameter : 100 mm
Minimum Breaking Load (MBL) : 7060 kN (~720 ton).
Holding capacity of chain stopper : 80% of chain MBL = 5648 kN (~576 ton). 1)
Brake holding load of cable lifter : 45% of chain MBL = 3177 kN (~324 ton) 1)
Pulling force of cable lifter:
- Nominal: 46,6 x (dchain)2 : (46,6 x 1002)/1000 = 466 kN (~47,5 ton) 1)
- Maximum: Nominal pull x 1,5 : 466 x 1,5 = 699 kN (~71,2 ton) 1)
1)
These values are all specified by the classification societies and will be the (minimum)
design criteria for all new vessels provided not a higher specification is agreed upon between
owner and yard.
Note!
) For any cable lifter unit the maximum pulling capacity is less than
10% of the chain MBL.
Aker Pusnes AS
Page 10 of 17
CONFIDENTIAL
SHOULD NOT BE DISTRIBUTED AND / OR BE MADE AVAILABLE TO THIRD PARTIES WITHOUT OUR WRITTEN CONSENT
Doc. Type: Issued by/Date:
Doc. No.: TI 0026 Rev by/Date:
1. Start the pumps on the power unit. Ref. operating instruction for this
power unit.
) Note!
Always start the pumps in accordance with the Hydraulic power unit
instruction manual.
2. Winch operation
Each winch is equipped with a separate sign as Figure 4 Mooring
Winch and Figure 5 Anchor Winch.
Aker Pusnes AS
Page 11 of 17
CONFIDENTIAL
SHOULD NOT BE DISTRIBUTED AND / OR BE MADE AVAILABLE TO THIRD PARTIES WITHOUT OUR WRITTEN CONSENT
Doc. Type: Issued by/Date:
Doc. No.: TI 0026 Rev by/Date:
) Note!
During pay out observe that the wire is not pulled off the drum
faster than the speed capacity of the winches. In other words, do
not try to over speed the motor. This will cause vacuum in the
motor which will damage the seals.
Aker Pusnes AS
Page 12 of 17
CONFIDENTIAL
SHOULD NOT BE DISTRIBUTED AND / OR BE MADE AVAILABLE TO THIRD PARTIES WITHOUT OUR WRITTEN CONSENT
Doc. Type: Initial issued/Date: KHO 02. Jan 05
Doc. No.: 03OP00_0005 Rev by/Date:
That will cause bending and damage to the warping end shaft (winch
main shaft).
Fig. 1
)
Note!
Always fix the line on a pully in front of the warping end.
Aker Pusnes AS
Page 13 of 17
CONFIDENTIAL
SHOULD NOT BE DISTRIBUTED AND / OR BE MADE AVAILABLE TO THIRD PARTIES WITHOUT OUR WRITTEN CONSENT
Doc. Type: Initial issued/Date: KHO 02. Jan 05
Doc. No.: 03OP00_0009 Rev by/Date:
To obtain the above features, the split drum is divided in two separate
parts by means of a dividing flange with a slot placed which divided the
drum in to parts. Normally the biggest part is used for storage and is
called the STORAGE PART, and the smallest for tensioning called the
TENSION PART.
When used correctly, a split drum permit the operator always to use the
first layer when the ship is moored, independent of how many layers
there are left on the storage part.
Normally, the hoisting load and the brake holding load are specified on
the first layer of a drum.
Tension
Split
Flange
Figure 6
Aker Pusnes AS
Page 14 of 17
CONFIDENTIAL
SHOULD NOT BE DISTRIBUTED AND / OR BE MADE AVAILABLE TO THIRD PARTIES WITHOUT OUR WRITTEN CONSENT
Doc. Type: Initial issued/Date: KHO 02. Jan 05
Doc. No.: 03OP00_0009 Rev by/Date:
4.4.1. Operation
1. Pay out the rope and make fast to a pulley onshore or on a buoy.
Instead of hauling in immediately, a further 10 m or so of slack is to be
paid out.
2. Then start to heave in the slack. Guide the rope manually into the slot
the first or second time the slot comes round.
Wind the remaining slack on to the tension part and make sure there is
at least three turns or more. In this case, there will be no tension
transferred through the slot even when operated at full brake holding
load.
3. Some times the rope has to be transferred from the storage part to the
tension part while the rope is under tension.
Use a lever and manual power or a manual- or air driven power block
with a hook fastened to the rope when guiding the rope through the slot.
4. Haul in the rope to desired load and apply the drum brake.
)
Note!
Observe that manhandling the rope from the storage part to the tension
part through the split flange can be dangerous.
If the rope tension is too high to enter the tension part, the rope tension
must be reduced.
Aker Pusnes AS
Page 15 of 17
CONFIDENTIAL
SHOULD NOT BE DISTRIBUTED AND / OR BE MADE AVAILABLE TO THIRD PARTIES WITHOUT OUR WRITTEN CONSENT
Doc. Type: Initial issued/Date: KHO 03. Feb 05
Doc. No.: 03OP00_0010 Rev by/Date:
4.5. Precautions
1. If a winch is being used, e.g. the warping head, with the drum disengaged and
the brake set, the drum bearings and main shaft bearings have to take a
considerable part of the braking load. Is the mooring wire made fast ashore and
under tension the loads on the bearings may be considerably.
2. Always keep the brake tightened during voyages in cold climates. If a brake has b
been left released for some time and got soaked, the water could later on have
frozen to ice which causes low or no brake effect.
3. A soaked brake lining or grease on the brake rim will reduce the brake effect. Run
the drum fast with the brake a little tightened until the water vaporises or the
grease has been ”burnt” away.
Aker Pusnes AS
Page 16 of 17
CONFIDENTIAL
SHOULD NOT BE DISTRIBUTED AND / OR BE MADE AVAILABLE TO THIRD PARTIES WITHOUT OUR WRITTEN CONSENT
Doc. Type: Initial issued/Date: KHO 03. Feb 05
Doc. No.: 03OP00_0010 Rev by/Date:
4.6. References
"Effective Mooring"
Aker Pusnes AS
Page 17 of 17
CONFIDENTIAL
SHOULD NOT BE DISTRIBUTED AND / OR BE MADE AVAILABLE TO THIRD PARTIES WITHOUT OUR WRITTEN CONSENT