0% found this document useful (0 votes)
75 views1 page

Resthouse Model

This document is a bill of materials that lists the materials, quantities, unit costs, and total costs for a construction project. It includes costs for general requirements like temporary facilities, siteworks like excavation and backfilling, structural works such as columns and beams, roofing works, masonry works, and plastering. The total cost for structural works is PHP 630,062.35 and the total cost for all items is over PHP 1 million.

Uploaded by

ZENY FORTIN
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
75 views1 page

Resthouse Model

This document is a bill of materials that lists the materials, quantities, unit costs, and total costs for a construction project. It includes costs for general requirements like temporary facilities, siteworks like excavation and backfilling, structural works such as columns and beams, roofing works, masonry works, and plastering. The total cost for structural works is PHP 630,062.35 and the total cost for all items is over PHP 1 million.

Uploaded by

ZENY FORTIN
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

BILL OF MATERIALS

==============================================================================================================================
DESCRIPTION QTY UNIT UNIT COST (PHP) TOTAL COST
MATERIALS LABOR SUB-TOTAL
==============================================================================================================================
A. GENERAL REQUIREMENTS
1. Temporary Facilities
Electrical Consumption 1.00 lot 6,000.00 6,000.00 6,000.00
Site Office and Warehouse 1.00 lot 25,000.00 25,000.00 25,000.00
31,000.00

B. SITEWORKS
1. Earthwork
Excavation 30.00 cu.m 500.00 500.00 15,000.00
Backfill & Embankment 30.00 cu.m 300.00 120.00 420.00 12,600.00
2. Site Preparation Works -
Gravel Bedding at Slab-on-grade 3.00 cu. m 1,200.00 200.00 1,400.00 4,200.00
Gravel Bedding at Isolated Footings 1.00 cu. m 1,200.00 200.00 1,400.00 1,400.00
Gravel Bedding at Wall Footings 0.50 cu. m 1,200.00 200.00 1,400.00 700.00

33,900.00
C. STRUCTURAL WORKS
1. Column & Stair Footings
Rebar Works 190.00 kgs. 47.00 15.00 62.00 11,780.00
Form Works 20.00 sq. m 396.38 158.55 554.93 11,098.61
Concrete Works 6.55 cu. m 3,600.00 1,440.00 5,040.00 33,012.00
2. Wall Footings / Footing Tie-Beams - -
Rebar Works 481.00 kgs. 47.00 15.00 62.00 29,822.00
Form Works 34.00 sq. m 407.84 163.13 570.97 19,413.04
Concrete Works 4.00 cu. m 3,600.00 1,440.00 5,040.00 20,160.00
3. Slab-on-grade
Rebar Works 230.00 kgs. 47.00 15.00 62.00 14,260.00
Form Works 60.00 sq. m 49.52 19.81 69.33 4,159.68
Concrete Works 5.90 cu. m 3,600.00 1,440.00 5,040.00 29,736.00
4. Columns / Shearwalls
GROUND FLOOR
Rebar Works 420.00 kgs. 47.00 15.00 62.00 26,040.00
Form Works 70.00 sq. m 202.20 80.88 283.08 19,815.67
Concrete Works 4.20 cu. m 3,600.00 1,440.00 5,040.00 21,168.00
SECOND FLOOR
Rebar Works 280.00 kgs. 47.00 15.00 62.00 17,360.00
Form Works 70.00 sq. m 329.09 131.64 460.73 32,251.17
Concrete Works 3.30 cu. m 3,600.00 1,440.00 5,040.00 16,632.00

5. Beams and Girders


GROUND FLOOR
Rebar Works 390.00 kgs. 47.00 15.00 62.00 24,180.00
Form Works 34.00 sq. m 329.09 131.64 460.73 15,664.85
Concrete Works 3.20 cu. m 3,600.00 1,440.00 5,040.00 16,128.00
SECOND FLOOR -
Rebar Works 390.00 kgs. 47.00 15.00 62.00 24,180.00
Form Works 34.00 sq. m 329.09 131.64 460.73 15,664.85
Concrete Works 3.20 cu. m 3,600.00 1,440.00 5,040.00 16,128.00

6. Second floor slab


Rebar Works 595.00 kgs. 47.00 18.80 65.80 39,151.00
Formworks 1.00 ls 40,000.00 16,000.00 56,000.00 56,000.00
Concrete Works 8.20 cu. m 3,600.00 1,440.00 5,040.00 41,328.00

7. Stairs
Rebar Works 170.00 kgs. 47.00 18.80 65.80 11,186.00
Form Works 25.00 sq. m 1,360.44 544.18 1,904.62 47,615.46
Concrete Works 3.20 cu. m 3,600.00 1,440.00 5,040.00 16,128.00

630,062.35
D. ROOFING WORKS
Rib-type Color Roofing .5mm thk 1.00 ls 70,700.00 21,210.00 91,910.00 91,910.00
ROOF FRAMING 1.00 ls 65,000.00 19,500.00 84,500.00 84,500.00
Gutter 16.00 LM 500.00 200.00 700.00 11,200.00
Side Flushing 40.00 LM 300.00 120.00 420.00 16,800.00
204,410.00
E. MASONRY WORKS
1. Concrete Block Laying & MORTAR
Interior 100 mm thk CHB 200.00 sq. m 500.00 200.00 700.00 140,000.00
2. PLASTERING -
Use for exterior and interior applications. 420.00 sq.m. 80.00 32.00 112.00 47,040.00
3. SEPTIC TANK -
Septic Tank 2.50 cu.m. 5,185.00 2,074.00 7,259.00 18,147.50

205,187.50
F. Floor Topping / FINISHING

ground floor 57.00 sq.m. 180.00 72.00 252.00 14,364.00


second floor 57.00 sq.m. 180.00 72.00 252.00 14,364.00

28,728.00
G. STEEL RAILLINGS
1. Stair & Veranda Railings (without tiles) 1.00 lot 30,000.00 12,000.00 42,000.00 42,000.00
42,000.00

H. THERMAL AND MOISTURE PROTECTION


1. Waterproofing

Septic Tank 1.00 lot 1,000.00 400.00 1,400.00 1,400.00


Bathroom, Kitchen and Laundry 1.00 lot 1,000.00 400.00 1,400.00 1,400.00

Sub-Total 2,800.00

I. DOORS, WINDOWS AND GLASSES

1. Doors
D-01 (sliding) (with installation) 2.00 set 9,600.00 9,600.00 19,200.00
D-02 (alluminum door with doorknob and hinges) (with installation) 3.00 set 2,000.00 2,000.00 6,000.00
D-03 (panel door with doorknob and hinges) 4.00 set 9,000.00 1,500.00 10,500.00 42,000.00
2. Windows
W-01 ( 1.0 x 1.5 m , combination of awning and sliding type) (with installation) 8.00 pc 3,900.00 3,900.00 31,200.00
W-02 (0.60m x 1.60m fixed glass window) (with installation) 1.00 pc 2,500.00 2,500.00 2,500.00
W-03 (0.5 x 0.5m awning type for CR) (with installation) 2.00 pc 1,500.00 1,500.00 3,000.00
103,900.00
J. FINISHES

1. Concrete Finishes
Concrete Neutralizer 25.00 gal 415.00 166.00 581.00 14,525.00
Flat Latex 5.00 pail 3,200.00 1,280.00 4,480.00 22,400.00
Semi-Gloss Latex 9.00 pail 3,700.00 1,480.00 5,180.00 46,620.00
Masonry Putty 1.00 pail 1,200.00 480.00 1,680.00 1,680.00
Painting Accessories 1.00 ls 5,000.00 2,000.00 7,000.00 7,000.00
Sand Paper 1.00 ls 3,000.00 1,200.00 4,200.00 4,200.00

2. Ceiling and CeilingFinishes


CF-01 Fiber Cement Board with Permacoat Flat Latex on Latex Primer with 150.00 sq.m. 400.00 300.00 700.00 105,000.00
light gauge metal framing spaced at 400mm OC

Paint
Hardiflex
Metal Furring
Blind Rivets
Black Screw
Concrete Nail 1"
Fiber Glass Mesh Tape

201,425.00

K. PLUMBING WORKS

PLUMBING FIXTURES

water closet with lavatory 2.00 pc 8,500.00 1,700.00 10,200.00 20,400.00


kitchen countertop with sink 1.00 pc 20,000.00 8,000.00 28,000.00 28,000.00
floor drain 8.00 pc 75.00 30.00 105.00 840.00
faucet 4.00 pc 100.00 40.00 140.00 560.00
bidet set w/ hose 2.00 pc 600.00 120.00 720.00 1,440.00
shower head 2.00 pc 2,000.00 400.00 2,400.00 4,800.00

- -
PLUMBING PIPE AND FITTINGS 1.00 lot 60,000.00 24,000.00 84,000.00 84,000.00
- 140,040.00
L. ELECTRICAL WORKS

1-pole switch 6.00 PCS 130.00 52.00 182.00 1,092.00


2-pole switch 2.00 PCS 200.00 80.00 280.00 560.00
3-pole switch 3.00 PCS 300.00 120.00 420.00 1,260.00
3-way switch 2.00 PCS 175.00 70.00 245.00 490.00
pin lights 18.00 PCS 189.00 75.60 264.60 4,762.80
LED bulbs 13.00 PCS 250.00 100.00 350.00 4,550.00
receptacles 13.00 PCS 35.00 14.00 49.00 637.00
GFCI 2.00 PCS 1,300.00 520.00 1,820.00 3,640.00
SPO 4.00 PCS 250.00 100.00 350.00 1,400.00
2-gang outlet 17.00 PCS 180.00 72.00 252.00 4,284.00
10-branches Panel board (Premium type) 1.00 pc 4,000.00 1,600.00 5,600.00 5,600.00
100 amps (bolt on breaker) 1.00 PC 1,200.00 480.00 1,680.00 1,680.00
30 amps (bolt on breaker) 5.00 PCS 350.00 140.00 490.00 2,450.00
20 amps (bolt on breaker) 3.00 PCS 350.00 140.00 490.00 1,470.00
15 amps (bolt on breaker) 2.00 PCS 350.00 140.00 490.00 980.00
ceiling mounted light fixtures 3.00 PCS 1,200.00 480.00 1,680.00 5,040.00
utility box 34.00 PCS 30.00 12.00 42.00 1,428.00
black THHN#12 Gauge 2.00 box 4,000.00 1,600.00 5,600.00 11,200.00
black THHN#10 Gauge 1.00 box 6,000.00 2,400.00 8,400.00 8,400.00
white THHN#12 Gauge 1.00 box 4,000.00 1,600.00 5,600.00 5,600.00
white THHN#10 Gauge 1.00 box 6,000.00 2,400.00 8,400.00 8,400.00
green TW#12 50.00 meters 25.00 10.00 35.00 1,750.00
junction box 40.00 pcs 30.00 12.00 42.00 1,680.00
square box 10.00 PCS 65.00 26.00 91.00 910.00
electrical PVC pipe 1/2 50.00 PCS 90.00 36.00 126.00 6,300.00
30- amps bolt on breaker with case 1.00 pc 450.00 180.00 630.00 630.00
1/2 PVC male adaptor with locknut 100.00 pcs 20.00 8.00 28.00 2,800.00
electrical tape 50.00 pcs 45.00 18.00 63.00 3,150.00
92,143.80
M. TILE WORKS (FLOORING ONLY, CR,SHOWER)

Unglazed Tiles 30x30 200.00 pc 50.00 20.00 70.00 14,000.00


Cement Mortar 5.00 bag 230.00 92.00 322.00 1,610.00
Tile Adhesive 6.00 bag 269.00 107.60 376.60 2,259.60
Tile Grout 2.00 pack 60.00 24.00 84.00 168.00
18,037.60
GRAND TOTAL 1,733,634.25