Architectural
Architectural
RECONSTRUCTION OF SCHOOLS
IN FATA
1. ARCHITECTURAL DRAWINGS
2. STRUCTURAL DRAWINGS
DONOR:
IMPLEMENTING AGENCY:
PREPARED BY:
SHAKIR ULLAH
FAZLI IMRAN
DRAWING TITLE
MODULE M 3
LIST OF TITLE
DRG NO:
NOTE:
ARCHITECTURAL DRAWINGS
DONOR:
FATA SECRETARIAT
IMPLEMENTING AGENCY:
PREPARED BY:
SHAKIR ULLAH
REVIEWED BY:
FAZLI IMRAN
DRAWING TITLE
MODULE M 3
TITLE
DRG NO:
NOTE:
IMPLEMENTING AGENCY:
14 GATE & BOUNDARY WALL DETAILS AG-ARCH-M3-14
REHABILITATION & RECONSTRUCTION UNIT (RRU)
FAZLI IMRAN
DRAWING TITLE
MODULE M 3
LIST OF DRAWINGS
DRG NO:
NOTE:
A B C D E F G H
88'-3"
6" 13' 13' 12'-1012" 12'-1012" 9'-6" 13' 13' 6"
6"
1
17'
26'-9"
1'
2 1'
8'-9"
DONOR:
SHAKIR ULLAH
REVIEWED BY:
FAZLI IMRAN
DRAWING TITLE
MODULE M 3
COLUMN LAYOUT PLAN
DRG NO:AG-ARCH-M3-01
NOTE:
sec
A-A sec
A 2'-0" Wide Projection B C D E B-B F G 2'-0" Wide Projection H
88'-3"
13' 13' 12'-1012" 12'-1021" 9'-6" 13' 13'
6" 6"
6" W W W W W2 W W
1
6'
2'-9" 6' 7'-6" 6' 2'-9" 3' 6' 7'-3" 6' 2'-9" 2'-9" 6' 7'-6" 6' 2'-9"
1'-6" 1'-6"
4' 1' 4'
SCHEDULE OF OPENING
No of Steps = 22
BLACK BOARD
BLACK BOARD
BLACK BOARD
Tread = 12"
CLASS ROOM CLASS ROOM
Riser = 6"
CLASS ROOM
S/NO TYPE SIZE LEVEL W.R.T
17' 25'-0"x16'-0" 25'-0"x16'-0" 25'-0"x16'-0"
FFL
10'
01 D 4'-0"x9'-6" ±0'-0"
05 W1 4'-0"x6'-6" +3'-0"
+6'-0" Stairs
8'-9" VERANDAH
9' 06 W2 6'-0"x3'-6" +3'-6" Mumty
9'-0" WIDE
STEEL RAILING STEEL RAILING
+ 2'-0"
3 DONOR:
6"
RAMP UP 3' 3'
(1:10) FATA SECRETARIAT
STEPS
UP
20'-0" 5' 36'-0"
2'-0" Wide Projection
4'-0" WIDE IMPLEMENTING AGENCY:
sec sec PLINTH PROTECTION
A-A B-B
REHABILITATION & RECONSTRUCTION UNIT (RRU)
PREPARED BY:
FAZLI IMRAN
DRAWING TITLE
MODULE M 3
GROUND FLOOR PLAN
DRG NO:AG-ARCH-M3-02
NOTE:
sec
A-A sec
B-B 2'-0" WIDE
A B C D E F G H
PROJECTION
88'-3"
6" 13' 13' 12'-1021" 12'-1012" 9'-6" 13' 13' 6"
6" W W W W W2 W W
1
6'
2'-9" 6' 7'-6" 6' 2'-9" 3' 6' 7'-3" 6' 2'-9" 1'-6" 1'-6" 2'-9" 6' 7'-6" 6' 2'-9" SCHEDULE OF OPENING
4'
No of Steps = 22
4' 1' 4'
S/NO TYPE SIZE LEVEL W.R.T
Tread = 12" FFL
Riser = 6"
01 D 4'-0"x9'-6" ±0'-0"
BLACK BOARD
BLACK BOARD
BLACK BOARD
CLASS ROOM CLASS ROOM CLASS ROOM
17' 25'-0"x16'-0" 25'-0"x16'-0" 25'-0"x16'-0" 02 D1 3'-6"x7'-0" ±0'-0"
10'
03 D2 2'-6"x7'-0" ±0'-0"
26'-9" 04 W 6'-0"x6'-6" +3'-0"
9" 1'-6" 1'-6" 9" 1' 1'-6" 1'-6" 9" 9" 1'-6" 1'-6" 9"
4' 4' 4'-6" 4' 4' 4' 4' 4'-3" 4' 4' DN. Up 4' 4' 4'-6" 4' 4'
05 W1 4'-0"x6'-6" +3'-0"
9'
2 +6'-0" Stairs
D W1 W1 D D W1 W1 D D W1 W1 D 06 W2 6'-0"x3'-6" +3'-6" Mumty
IMPLEMENTING AGENCY:
2'-0" WIDE
sec sec REHABILITATION & RECONSTRUCTION UNIT (RRU)
PROJECTION A-A B-B
PREPARED BY:
SHAKIR ULLAH
FIRST FLOOR PLAN
SCALE : 81" = 1'-0"
REVIEWED BY:
FAZLI IMRAN
DRAWING TITLE
MODULE M 3
FIRST FLOOR PLAN
DRG NO:AG-ARCH-M3-03
NOTE:
sec
B-B
A B C D E F G H
88'-3"
6" 13' 13' 12'-1012" 12'-1012" 9'-6" 13' 13' 6"
6"
W2
1
6'
1'-6" 1'-6"
4'
4' 1' 4'
No of Steps = 22 SCHEDULE OF OPENING
Tread = 12" 2'-0"
Riser = 6" WIDE PROJECTION
S/NO TYPE SIZE LEVEL W.R.T
17'
FFL
01 D 4'-0"x9'-6" ±0'-0"
10'
02 D1 3'-6"x7'-0" ±0'-0"
26'-9"
03 D2 2'-6"x7'-0" ±0'-0"
2' DN.
9' 04 W 6'-0"x6'-6" +3'-0"
2 D1
3'-6"
9" 05 W1 4'-0"x6'-6" +3'-0"
+6'-0" Stairs
06 W2 6'-0"x3'-6" +3'-6" Mumty
8'-9" VERANDAH
9'-0" WIDE
DONOR:
6" STEEL RAILING 1'-6" HIGH
3 PARAPET WALL 2'-6" HIGH
FATA SECRETARIAT
MUMTY PLAN
PREPARED BY:
SCALE : 81" = 1'-0"
SHAKIR ULLAH
REVIEWED BY:
FAZLI IMRAN
DRAWING TITLE
MODULE M 3
MUMTY PLAN
DRG NO:AG-ARCH-M3-04
NOTE:
1'-6"
2'-6"
6"
10'-6"
28'
6"
10'-6"
F.L
2'
G.L
FRONT ELEVATION
SCALE : 81" = 1'-0"
2'-6"
6"
8'
1'-6"
DONOR:
2'-6"
6"
FATA SECRETARIAT
IMPLEMENTING AGENCY:
10'-6"
REHABILITATION & RECONSTRUCTION UNIT (RRU)
SHAKIR ULLAH
FAZLI IMRAN
DRAWING TITLE
F.L
MODULE M 3
2'
G.L FRONT & REAR ELEVATION
REAR ELEVATION
SCALE : 81" = 1'-0" DATE --/--/-- SCALE AS SHOWN ON DRAWING
DRG NO:AG-ARCH-M3-05
NOTE:
2'-6"
4'-6"
1'-6"
2'-6"
1'-6"
9'-6"
35'
1'-6"
DONOR:
FATA SECRETARIAT
IMPLEMENTING AGENCY:
9'-6"
REHABILITATION & RECONSTRUCTION UNIT (RRU)
PREPARED BY:
SHAKIR ULLAH
F.L
REVIEWED BY:
DRAWING TITLE
DRG NO:AG-ARCH-M3-06
NOTE:
DETAIL "X"
ALL DIMENSIONS & LEVELS ARE IN FEET &
INCHES UNLESS OTHERWISE INDICATED.
(OPTION - 01)
PAINT DETAILS
1 1/2" TH.BRICK TILES
SET.& GROURTED IN C/S (1:2) (OPTION - 02) 1. PREPARATION OF SURFACE + FIRST
4" TH. AVG. MUD FILLING. 13 8" MOSAIC Steel Railing COAT + 2 SUBSEQUENT COATS OF
POLYTHINE SHEET 3" P.C.C (1:3:6)
HOT BITUMEN RCC SLAB Verandah WEATHERSHIELD PAINT ON ALL
RCC SLAB EXTERIOR SURFACES, WHERE
REQUIRED, COMPLETE IN ALL RESPECT ,
2'-6" 2'-6"
RCC BASE IN ACCORDANCE WITH RELEVANT ITEM
1'-6" 1312 " x 6" OF SPECIFICATIONS AND AS DIRECTED
1'-112" 6" Detail "A" 1'-121"
BY ENGINEER INCHARGE.
SHAKIR ULLAH
2' Grid of 58 " x 58" Square Bars.
PCC (1:3:6) Drain Grids are a little bit adjustable.
G.L G.L
REVIEWED BY:
1" THICK MARBLE FLOORING
3"PCC 1:3:6
4" SAND FILLING PLINTH FAZLI IMRAN
4" 4"
COMPACTED EARTH PROTECTION
DRAWING TITLE
MODULE M 3
SECTION AT A-A SECTION AT A-A
SCALE : 41" = 1'-0"
A B C D E F G H
88'-3"
6" 13' 13' 12'-1012" 12'-1012" 9'-6" 13' 13' 6"
6"
1
SLOP E
E SLOP SLOP
E
SLOP E
E SLOP SLOPE
'A'
SL
O
PE
SL
PE
O
PE
PE
SL
17'
RIDGE
SLO
SLOPE
Y
LLE
VA
EY VA
PE
SL
SL
LL
PE
LL
O
O
O
EY
PE
PE
O
SL
26'-9"
VA
SL
2
SL
PE
O
O
PE
SL
PE
PE
SL
O
SLO
8'-9"
PE
SL
PE
SLO
SLO
SLOPE
PE
PE
O
SL
6"
3
DONOR:
PCC GOLLA
ALL ARROUND
18"X18" DUCT
FATA SECRETARIAT
(OPTION - 01)
1 1/2" TH.BRICK TILES
SET.& GROURTED IN C/S (1:2)
4" TH. AVG. MUD FILLING. (OPTION - 02) IMPLEMENTING AGENCY:
POLYTHINE SHEET 13 8" MOSAIC
HOT BITUMEN 3" P.C.C (1:3:6)
RCC SLAB REHABILITATION & RECONSTRUCTION UNIT (RRU)
RCC SLAB
SHAKIR ULLAH
FAZLI IMRAN
DRG NO:AG-ARCH-M3-08
NOTE:
E F E F
10'-6"
10'-6"
6" 9'-6" 6" 6" 9'-6" 6"
W2 W2
6" 6"
01 01
4' 4'
17' 17'
10'
10'
26'-9" 26'-9"
DN. Up DN.
9' 9'
2' 2'
02 02 D1
DONOR:
FATA SECRETARIAT
PREPARED BY:
SHAKIR ULLAH
03 03
6" 6"
REVIEWED BY:
FAZLI IMRAN
DRAWING TITLE
GROUND & FIRST FLOOR
STAIR CASE PLAN MODULE M 3
No of Steps = 22 STAIR CASE PLAN
Tread = 12" MUMTY STAIR CASE PLAN
Riser = 6" SCALE 14" = 1'-0"
DATE --/--/-- SCALE AS SHOWN ON DRAWING
SCALE 41" = 1'-0"
DRG NO:AG-ARCH-M3-09
NOTE:
PAINT DETAILS
(OPTION - 01)
1 1/2" TH.BRICK TILES 1. PREPARATION OF SURFACE + FIRST
SET.& GROURTED IN C/S (1:2) (OPTION - 02)
4" TH. AVG. MUD FILLING. 13 8" MOSAIC
COAT + 2 SUBSEQUENT COATS OF
POLYTHINE SHEET 3" P.C.C (1:3:6) WEATHERSHIELD PAINT ON ALL
HOT BITUMEN RCC SLAB
RCC SLAB EXTERIOR SURFACES, WHERE
REQUIRED, COMPLETE IN ALL RESPECT ,
IN ACCORDANCE WITH RELEVANT ITEM
OF SPECIFICATIONS AND AS DIRECTED
2'-6"
BY ENGINEER INCHARGE.
DETAIL "B"
4'-6" SCALE : 12" = 1'-0"
3'
VERANDAH
10'-6"
1'-6"
5'
Railing post
11"
1
2" THICK MARBLE SKIRTING PREPARED BY:
1" THICK MARBLE
STAIR LOBBY 3'-9" 2'-9"
ON TREAD
Detail "Z" SEE F.L
SHAKIR ULLAH
1 DRG No:AG-ARCH-M3-15
2" THICK MARBLE
ON RISER
2'
PCC (1:3:6) Drain
G.L
1" THICK MARBLE FLOORING REVIEWED BY:
3"PCC 1:3:6
4" SAND FILLING
COMPACTED EARTH FAZLI IMRAN
PLINTH
PROTECTION
DRAWING TITLE
DETAIL "A"
SECTION AT B-B SCALE : 12" = 1'-0" MODULE M 3
SCALE : 41" = 1'-0" Drain
SECTION AT B-B
(Stair Case Detail Section)
DRG NO:AG-ARCH-M3-10
NOTE:
1' 1'
2"
6'-6"
9'-6"
2"
2" Thick Plaster Frame
1
2" THICK MARBLE SKIRTING
2'-10" 3'
DONOR:
Class Room
FATA SECRETARIAT
IMPLEMENTING AGENCY:
PREPARED BY:
G.L
SHAKIR ULLAH
REVIEWED BY:
MODULE M 3
TYPICAL CLASS ROOM DETAIL
DRG NO:AG-ARCH-M3-11
NOTE:
A
ALL DIMENSIONS & LEVELS ARE IN FEET &
4'
2" 3" INCHES UNLESS OTHERWISE INDICATED.
3" 2" SEE DETAIL "J-J"
3'-2"
18Guage Steel 18Guage Steel
2"
B C
1'-10"
2" 2"
5"
Wooden Top Rail Wooden Top Rail Top Rail (212 "x114") Top Rail (212"x114") Top Rail 212"x114 ")
Top Rail (212"x1 14")
(5"x1½") (5"x1½")
Out
3'-10"
Wooden Frieze Rail Wooden Frieze Rail 2'-1021 " Steel Frieze Rail
Steel Frieze Rail (212"x114")
9'-6"
9'-6"
4"
221" 2'-1021"
Steel Frieze Rail (212"x114 ") Steel Frieze Rail (212"x114")
(4"x1½") (4"x1½") (212"x114")
221 "
Out In
1'-7"
212"x114 " ms pipe 18 swg Out In 212"x1 14" ms pipe 18 swg Side Side
1'-8" 1'-8"
MDF Panel MDF Panel 27"x20" Side Side 21"x20"
7' 7' 7' 212 " 7'
Steel Lock
Wooden Lock Wooden Lock Steel Lock Rail(212"x114") Steel Lock Rail(212"x114") Steel Lock Rail(212 "x114")
4"
212"
Rail(212"x114")
Rail(4"x1½") Rail(4"x1½")
3'-10"
F.L
8"
212 " 1
Bottom Rail(8"x1½") Bottom Rail(8"x1½") Bottom Rail(212"x1 14") Bottom Rail(22"x1 14") 212 " Bottom Rail(212"x114") Bottom Rail(212 "x114")
A B C
Door Elevation (D) Door Section At A-A Mumty Door Elevation (D1) Toilet Door Elevation (D2) Toilet Door Section At C-C
DONOR:
SECTION OF D (4'-0" )
FATA SECRETARIAT
IMPLEMENTING AGENCY:
Wooden Beading
REVIEWED BY:
Glass(5mm Thick)
3 3
18 Guage M.S Sheet wilded with 8"x 8" sq-bar
FAZLI IMRAN
DRG NO:AG-ARCH-M3-12
NOTE:
D E D 6" ALL DIMENSIONS & LEVELS ARE IN FEET &
Z- Section 1 12" x 1" pipe
6' Z- Section 1 12" x 1" pipe
INCHES UNLESS OTHERWISE INDICATED.
18 guage
18 guage 4'
2" 2" 2" 6'
2'-9" 2'-9" 2" 2" 3'-8" 2" 1'-9"
18 Guage Steel Frame (2"x5") 18 Guage Steel Frame (2"x5") 18 Guage Steel Frame (2"x5")
2" 18Guage Steel Frame 18GUAGE Steel
hollow filled 1:3:6 hollow filled 1:3:6 hollow filled 1:3:6 (2"x5") Frame (2"x5")
2"
Glass(5mm thick) 1'-6" Glass(5mm thick) 1'-6" Glass(5mm thick) 1'-6"
Welded 83" x 83" square pipe Welded 38" x 38" square pipe 2" Glass(5mm thick) Glass(5mm thick)
2 "x 5" Hollow
Frame 2"
1"
2" 2 "x 5" Hollow Wire Guaze 8 MS Square Box
1
2"x 18" MS Frame
Flat Grill 1'-4" 22 SWG
M.S.T 2" x 5"
18 guage 6'-6" 2" M.S.T 2" x 5" 6'-6" 1
2" MS Square Pipe Frame
Aluminum Louvers 18 guage
Openable Glass(5mm thick)
3' high 2" frame
Openable Glass Panel 1'-4" 9'-6" 4'-6"
4'-8" Z- Section 1 12" x 1" pipe Openable Openable Openable Glass Panel
M.S.T 2" x 5" 18 guage
18 guage Louvers 2"
Glass(5mm thick)
1'-4" Welded 38" x 38" square pipe
Fixed Wire Guaze Panel
M.S.T 2" x 5" Fixed Wire Guaze Panel
18 guage 1" THICK 2"
MARBLE SILL 2" Z- Section 1 12" x 1" pipe 2"
Z- Section 1 12" x 1" pipe 18 guage
18 guage
D E D
Brick Wall
3' 3' 3'
F.L
Window Section At D-D Window Elevation (W) Window Elevation (W) Window Elevation (W1) Window Section At D-D
(First Floor Back Side) (First Floor Back Side) (Ground Floor) 1/4" = 1'-0" 1/4" = 1'-0"
5" 2"
3"
TYPICAL SECTION OF
DONOR:
DOOR & WINDOW FRAME
(18 GUAGE G.I SHEET PRESS FARMED SECTIONS)
Glass(5mm thick)
1
2" MS Square Pipe Frame PREPARED BY:
1 x1
2" 8" MS Glass(5mm thick) 1
4' 3'-6" 3'-2" 8" MS Square Box Louvers
Window Section (W) Flat Grill 6" C/C
Openable Glass Panel SHAKIR ULLAH
MODULE M 3
WINDOWS ELEVATIONS & SECTIONS
DRG NO:AG-ARCH-M3-13
NOTE:
3"
3"
3"
121"
7'-10"
7' 5'-10" 6'-7" 7'-4"
5'-10" 7'
ELEVATION
WASH TERRAZZO
8"
NSL
6" 13 21" x 18"
BRICK MASONARY 12"x18" R.C.C
COLUMN COLUMN
6" 1'-121" 12"x18" R.C.C 112"
1'-9" 1'-121" COLUMN 1'-3"
9" THICK BRICK
6" 1'-6" 4 21" MASONRY WALL
3" P.C.C (1:4:8)
1'-6" 9" GATE 1'-6" 1'-9"
2'
PLAN DONOR:
FATA SECRETARIAT
1'
IMPLEMENTING AGENCY:
PREPARED BY:
3'
N.S.L
SHAKIR ULLAH
2 2
8#4 12"
REVIEWED BY:
1 1
5 #4 (B/W) FAZLI IMRAN
3' 3' (Adjustable at site)
5 #4 (B/W ) 1'-6"
#3 @8" C/C
DRAWING TITLE
12"
2" MODULE M 3
P.C.C 3" GATE & BOUNDARY WALL DETAILS
SECTION 2-2
FOUNDATION PLAN FOR 2" 3' 2"
DRG NO:AG-ARCH-M3-14
1'-3" SAND FILLING
WICKET GATE NOTE:
6"
LAWN LEVEL 2'-4 21"x5'-9"
3" PCC 1:2:8
X
9" - 6" ALL DIMENSIONS & LEVELS ARE IN FEET &
6" INCHES UNLESS OTHERWISE INDICATED.
ROAD LEVEL
9"
3'
5"
6'-10"
A A
- -
1"x1" 18 SWG
MS TUBE 5"
9"
B
1" THICK MARBLE FLOORING -
3"PCC 1:3:6
4" Sand Filling
1
2" THICK Compacted Earth 01
RCC Column MARBLE -
SKIRTING 112" INSIDE 1'-3"
PREPARED BY:
SHAKIR ULLAH
12" LONG 34 " 2" WIDE STOPPER
SLIDING BOLT
18" LONG 1" �
MS SLIDING BOLT MS L(1" x1") FRAME REVIEWED BY:
18 SWG.MS SHEET 18 SWG OF WICKET GATE
18 SWG.MS SHEET MS SHEET
FAZLI IMRAN
HOLD FAST
4" 6" 3" 3"
DRAWING TITLE
A A
- -
2�" MS PULLEY
20'-0"
20-0"
2½" MS PIPE
HOOK DONOR:
9"
FATA SECRETARIAT
1
2" thick Marble
2½" MS PIPE
IMPLEMENTING AGENCY:
2'-8"
DRG NO:AG-ARCH-M3-16
NOTE:
3'
20' 5'
PLAN E
E
1
5 "x5 "
8
2 2" M.S PIPE
8
MS Square Bar
3'
20' 5'
ELEVATION E
Scale = 41" = 1'-0"
RAILING DONOR:
FATA SECRETARIAT
3'
IMPLEMENTING AGENCY:
4"PCC (1:3:6)