Construction Risk Lecture Notes
Construction Risk Lecture Notes
TIPS
1. Where multiple layers of insurance – should get agreement that first layer would take the lead on
any dispute so no in-fighting between insurers
2. Insurance bonds – risk allocation device. Look at wording of recourse provision. If it says bond
can be called where there is a ‘claim’ then risk lies with the party providing the bond.
3.
DAY 1
RISK MANAGEMENT
- ‘No dispute’ report – developed by a research group created by the construction industry in
order to try and reduce the number of disputes in the construction area.
o Terms of reference: examine each major risk inherent in contracts and recommends
who should carry the risk
o Report found that basic principles should reflect Abrahamsom principles – party who
can best manage the risk should adopt it (the correct allocation of risk will deliver a
better project); standard form contracts should be used (and preferably unamended)
o Are the no dispute findings still relevant today? Are they applied in our industry
today?
What is risk?
- Risks will change over time. Risks that are identified today may not be risks that will be a
problem in years to come. E.g., covid – who could have identified that covid would have
caused the disruptions that it did?
Risks in construction project
- The risks include (per Abrahamsom, 1973) - the physical work, delay, supervision, damage
and injury, shortage of resources, government policy, conflict, industrial relations, payment,
inflation, disputes and Law
- In 2023:
o Escalation
o Pandemic
o Supply chain uncertainty
o Contractor, subcontractor insolvency
o Climate change
o ESG
o Modern slavery
PERCEPTION OF RISK
What constitutes risk in the first place and the reaction of a particular stakeholder to it will be informed
by:
- objectives
- personal and organisational value systems
- past experiences
- recent events
- custom and fashion
Key risks for principal:
- Contractor solvency
- Feasibility
- Within budget
- On time
- Satisfy end user requirements
- Fit for purpose
- Comply with approvals / law
Key risks for contractor
- Escalation
- Supply chain
- Certainty of payment
- Paid for extras
- Achieve margin
- Contract fairly administered
- Site available
- Complete without interruption
- OH&S requirements
- No residual liability
Key areas of risk for financier
- Completion risk – the risk that development and construction of a project will not progress to
the achievement of required levels of actual or demonstrated capacity by a specified date at
costs sufficient to generate cash flow necessary to service debt and pay operating expenses'
- Drivers
o Commercial banks lend for a margin
o no upside
o significant down side
o assume only measured risks
o control over key project decisions
o take control of project ASAP in time of difficulty
RISK MANAGEMENT
- What causes disputes?
o An outcome resulting from an unacceptable risk allocation
- Multidisciplinary approach
- Workshop
- Basis for procurement
- Risk allocation
o If parties go through the exercise of risk management, then can id the specific event
and allocate it to the party most able to manage it.
o Contract negotiation should occur in the context of risk management rather then in a
vacuum – need to identify the risk, analyse the risk (likelihood of risk / cost associated
with risk) and then treat the risk (i.e., principal to accept risk / contractor to accept risk
/ procurement strategy)
- Risk management is not to be done at the beginning of the project, risk management should
be monitored and reviewed throughout the life of the project
Abrahamson Principles
- The No Dispute working group adopted the Abrahamson principals for allocating obligations
and/or risks for all projects
o Principal should not ask a Contractor to price an unquantifiable risk that is within the
control of the Principal
o 'balanced contracts' where risk allocation follows Abrahamson principles work better
and are less prone to claims/disputes
o The limitations of the No Dispute – Risk Allocation Model are:
Some risks impossible to respond to in this way
Why give equal weight to each Abrahamson principle – Principle 1 is clearly
paramount
Some result contrary to common sense.
- Davenport
o Not capable of practical application
o Risks not capable of clear definition and ambiguity results
o Involves introduction into contract law of principles of economic theory and equity
o Each risk is more complex than Abrahamson theory pretends eg. latent conditions
Latent condition risk not capable of being allocated to one party
o Abrahamson principles assume that a 'preponderant economic benefit' can be
determined in each instance
o Davenport proposes a risk table
In absence of agreement, following events do not entitle contractor to relief
Weather
IR
Shortages of labour/materials
Escalation
Latent conditions
Common for Contractor to be provided in contract with some relief for some
of these events
Relief is usually one or more of: EOTs; Reimbursement of extra costs; off site
overheads and profit
- Look at the AUS standard form contracts (For a comparison of AS2124-1992, AS4000-1997,
MW1-2003 and PC1-1998 see 'Understand Australian Construction Contracts' by Bailey and
Bell)
- NEC3 contracts –
o Pascoe re NEC3:
Jointly consider risks on a regular basis
Statement of over-arching principles
Early warning requirement
Risk reduction meeting
Updating of risk register
DAY 2
- Why?
o No other party will take it
o Divesting the risk does not represent value for money
o High risk of bounce back
Therefore pay but no divestment
Therefore no value for money
- Inadvertent retaining of risk
o Existence of risk not appreciated
o Risk appreciated, but incorrectly assessed
o Risk appreciated but absence of divestment mechanism
o Ineffective divestment mechanism
- Reclaimed risk
o Intervention (finger in the pie)
o RFIs (Request for Information)
o Commercial indulgence
o Inattention
o Non (or delayed) responsiveness
o Waiver
o Critical contract administration risk
Pricing risk
- Principal
o Risks that arise: inaccurate estimates or budget and value engineering exercises
o Principal may think have priced risk in by asking Kr to accept it and paying a premium
but if they accept lowest bid / incompetent tenderer, then really have retained the risk.
- Contractor
o Pricing methodology is different to contracting methodology.
o Careful build up of price, claim by claim, item by item.
o Experience is as important than tools
o Process
Brainstorming by estimating team (with reference to past papers)
Tender prepared in a standard format and contingencies are included
o Integrated approach – risk identification and pricing
o Micro
Estimate prepared on a trade by trade basis with contingency for each trade
or major cost element
o Micro + Macro
Each cost centre review past projects
o Construction Period
Review proposed programme and allow contingency for delay and to cover
LDs
o Time
Complete by X date
Masquerading as a reliable date
Risk leakage mechanics
Extension of time
Prevention principle
Programs
o Quality/Performance
Prescriptive v performance
Specification v output
Methodology
‘Finger in the pie’
Design and construct
o Other risks
o accountability
Particular methodologies
- PPP
o State engages with SPV. SPV usually has both equity and debt support. Construction
is funded by equity and debt and debt is repaid once the asset is operational. It is
paid for the provision of the service during a concession term and the asset returns to
the State once the concession period has finished. The SPV is not paid on
completion of the asset, rather then SPV is paid during the concession term. There
are KPIS with respect to quality which are measured during the concession term and
to the extent that the KPIs are not met, the service fee is reduced.
o Fail safe risk allocation for the construction as SPV adopts all risk during the
construction period.
- Alliance
o What is the promise? To try very hard
o Other end of the spectrum is an alliance. There is a no dispute mechanism in the
alliance (in the absence of wilful misconduct or fraud)
o Payment is by reimbursement with painshare / gainshare allocation based on
margin/profit
o Difference is in the accountability and risk – accountability is shared and no liability
between the Ps
o Usual characteristics of alliancing:
Risks cannot be adequately defined
Cost of transferring risks is prohibitive
Urgent start required (before risks are fully identified)
Owner has a capacity to influence delivery
Collective risk management will produce a better outcome
- What about a hybrid between PPP and alliancing?
o Consider Marko Misko’s proactive risk and issue settlement model (PRISM)
- ECI
o Hybrid
Phase 1 – Quasi alliance (cost-reimbursable)
Phase 2 – Design and construct
The risk allocation in this model switches
- D&C
o Need to consider whether novation required (for design)
- Management
o Construction management
o Project management
o EPCM (Engineering, Procure and Construction Management)
o Managing Contractor
- Scope definition
o Detailed documentation
Drawings
Preliminaries
Specification
o OR Performance bases (PPR)
o Need to consider risk bounce back – inconsistency between documents (particularly
where team has relied on precedence)
- Schedule definition
o Date for PC / Date of PC
o EOT regime
o Contract programme and updates
o Unilateral power to extend
o Definition of PC
- Liquidated damages
o Often time related
o Could be other criteria
Production capacity
Running costs
Downtime
Power output / noise
o Benefit to Principle: ability to levy the LDs as soon as the breach occurs and also
saves the Principle time/cost in proving breach and establishing loss
o Benefit to Kr: provides certainty and caps loss
o Common law constraints on LDs (cannot impose LDs if they are penal in nature):
Dunlop Pneumatic Tyre Co v New Garage and Motor Co Ltd [1915] AC 79
Paciocco v ANZ (2016) 333 ALR 569
In Paciocco the court made it much harder to establish whether a
rate is penal – need to compare the rate, the estimated damages and
the other legitimate commercial interests the counterparty has in
performance (these commercial interests are not defined, e.g.
reputation loss etc.) Therefore much harder to establish penal
because can say that the higher rate takes into account commercial
interests
- Warranties
o Historical significance
Warranty v condition – type of relief
Condition – termination
Warranty - damages
Is this still relevant today?
o Best approach – use more flexible language (as opposed to X warrants Y)
X promises Y
X will ensure that Y occurs
If Y occurs then X will…
o Don’t forget about implied warranties
Good and workmanlike
Due Diligence
Reasonable time
Fit for purpose? This is often contentious for design consultants because PI
will not respond to warranties which extent the designer’s obligations beyond
what is required at CL (e.g., work performed with due care and skill).
o Statutory devices
Statutory implied warranties
Goods Act
Domestic Building Contracts Act
Australian Consumer Law
Most common misleading or deceptive conduct – gets you around ‘no
reliance’ clauses on pre contractual docs etc and also LOL does not apply
Usually non excludable
o At common law, damages are assessed once and for all at the date of the breach
Risk of predicting future loss with plaintiff
Inflation not taken into account
Indemnity may be expressed
As continuing, applying to each loss or expense as incurred
As continuing beyond termination of the contract or completion of the
project
So that ongoing losses are recoverable
o Contractual indemnities overcome limitation periods
Design life warranty
eg.warranty that certain structures will be designed so as to be fit for
purpose for 50 years
Breach
Limitation period
o 6 years
o 12 years if a deed
o 10 years building action in Vic and NSW
Keating on Building Contracts - 'where there is an obligation to indemnify
against loss, the cause of action does not arise until the loss has been
established, so the limitation period runs from the date when the liability or
loss indemnified against is established or incurred. This may be after the
expiry of the ordinary limitation period…'
Indemnity will provide a cause of action which accrues from the date
The loss is incurred
The date the liability is pronounced
Essential to be coupled with long design life warranties
o Beware of privity
Indemnity is a contractual right
Only the parties may receive and enforce the benefit
Obligations to indemnify non parties not enforceable by non parties
Look at who the indemnity is with – if it is a TP not enforceable under
contract
If having a TP indemnity to overcome privity issues, use a deed poll
(e.g., this indemnity is a deed poll separate to the other clauses of
the contract) because deed poll is enforceable by parties who aren’t
a part to the contract
- EXCLUSION CLAUSES
o CL interpretation rules
o Tension between history/practice and modern articulation of CL
o Need to add in everything to be excluded (explicit – negligence)
This results in bulky clauses
o Modern view – perhaps does not need to be so rigid
Consider - Darlington Futures v Delco – consider exclusion and limitation
clause as per other clauses – how would a reasonable business person
interpret this clause in the context of the contract as a whole?
DAY 3
- Security
o Reasons for provision
security for performance
off site materials – security released when off site materials are brought onto
site
early expenditure on project may require an advance payment bond
o Types
Cash
Benefits for the principal – easily accessible
Benefits for the builder – may be convenient / simple – no need to
negotiate with bank or TP
Disadvantage for builder – affects cashflow and if principal goes
insolvent, builder may rank as unsecured creditor and lose money
Retention
Bank guarantees
Insurance bonds
o Making a call
o Enjoining a call
Notes 8.9.23
Exam tips
Professional risks
- Is it better to have a highly prescriptive consultant contract or rely on the duty of care owed in
CL to exercise due care, skill and diligence in performing the work?
o Better to rely on the duty – a highly prescriptive contract may actually limit the role of
the consultant.
- There is a tension in professional services where the contract requires a consultant to
promise a particular outcome – how can a consultant promise a particular outcome when they
don’t know what that outcome might be? What the consultant should do is promise to
exercise care, skill and diligence when completing the work. There is no prescriptive outcome,
rather the consultant just promises to perform services with due care, skill and diligence.
- If a client suffers loss and seeks compensation from a consultant, what are the two most
important contract terms in pursuing the claim?
o ‘known circumstances’ – look at slide 22 – very broad definition
o ‘assumed liability’ – look at slide 23 – insurance won’t apply to any contractually
assumed liability unless such liability would have attached to the insured at law (note,
this would include liability which is allocated by a judgement – if the professional is
awarded damages against them, insurance should respond).
Known circumstances
Will not insure against known cicrs at the time of placing the policy
Assumed liability
- NOTE, outcome promise may make it more difficult to recover from the insurers then loss
arising from a process promise.
o Outcome promise – The works will comply with the Principal’s specification
o Process promise – X will exercise due, care and skill in performing the works
- If there is an exclusion like 4.3 on page 23 (Day 3 notes) – and the professional entered into a
deed with a bank who was funding a project, the professional’s only liability to the bank would
arise by way of the deed (i.e, no duty of care is owed between professional and bank) so
exclusion clause would most likely operate
o LDs are the result of an outcome promise. The professional has promised to
complete by the date of PC however, could you argue that you failed to meet that
date because you did not work diligently and therefore, insurance will apply.
Slide 24
- Sets out the difference between contractors and professionals are covered under PI
- Contarctors insurance covers the product (i.e., all have to demonstrate is that product is
faulty, don’t have to identify fault and question of proof is easy – either the product works or it
doesn’t) whereas professionals insurance covers the process (i.e., have to prove that
professional was negligent – need to use experts to prove breach because they will establish
the baseline against which negligence to be measured)
Slide 27
Slide 28
- One form of strict liability which is covered by the insurance policy – misleading and deceptive
conduct will be covered by PI because it is liability arising under law
- Uninsured liability – refer above. PI does not insure against outcome promises/contractually
assumed risk. This is very broad and most contracts include outcome promises.
o Agreed liability to others – liability assumed under a deed where no duty of care
exists at law
o Higher duties – where professional promises that they will act in accordance with best
standard or care as opposed to liable where negligent. Elevated duty of care (I
promise to provide services at the standard of world’s best practice) – If professional
sued for failing to comply with elevated duty of care but was no negligent, then will
not be insured. Very unlikely that this risk will ever eventuate.
o Preventing insurer’s recovery rights – if the insured takes away the insurers rights of
subrogation, then the insurance will not apply (this will occur where the insured enters
into a deed of release for e.g.)
Subrogation = steps in the shoes of
This will occur when releasing subconsultant as part of a settlement;
releasing client at the end of the project; releasing (original) client of deed of
novation
- Losing money
o Set off – where the consultant has a debt and wants to sue to recover the money and
the client then counterclaims for breach of duty (the suing of set off often triggers a
counterclaim which but for the set off claim would not have been raised)
o Never ending projects
o Unpaid variations – scope considerations
o Painful clients – termination for convenience can resolve this risk
- Disputes / litigation
o Vague and unclear clauses - especially re scope of services
o Unfair, oppressive contract terms
- Choice of client
Scope of PI insurance
- Liability to compensate TP for civil liability (but typically not covered for no fault contractual
assumed liability)
Standard of service
- ACL specifies the required standard of services (slide 50) – contract has to be under $100K /
domestic contract for this legislation to apply (to be deemed a consumer under the act)
o This doesn’t apply to architects and engineers because usually architects and
engineers are apply their services to TP not to their clients (??)
- What is the problem with FFP?
o FFP is an outcome promise (so an insurance risk)
o FFP is vague and may change (litigation risk)
o What is the purpose and when is the purpose ascertained? The purpose may change
over time so how can you assume risk for it.
Liability limitations
PROPORTIONATE LIABILITY
- NOTE proportionate liability does not apply to personal injury or fraud claims
- The solvency risk lies with the Pl under the proportionate liability legislation
- Proportionate liability is not triggered when the claim does not arise out of a failure to exercise
duty or care of M&D conduct (i.e. it does not apply where claims are of strict liability)
- When making a claim against the professional – what does the claimant need to know?
o Can the professional pay for this out of its own pocket?
o If not, is there PI insurance?
o Is this type of claim covered?
o What is the policy’s limit of cover?
o Is the policy eroded by defence costs?
o What is the policy excess?
o Can the professional pay the excess?
o Who is the insurers?
o What is the insurer’s approach likely to be?
- S 28(3) – if insured fails to disclose a relevant matter – this does not void the policy. Look at
28(3) which says that the insurer is entitled to reduce its liability to the position it would have
been id non-disclosure had not occurred (i.e., premium would most likely be increased so no
big difference for insured)
- S 41(3) – (use this where insurer sitting on the fence) If insured gives insurer a reasonable
time to make a decision to settle the claim, and the insurer doesn’t give the insured an
answer, the insured can settle and this will not void the insurance.
- S 45 – an other insurance exclusion clause is void unless the insurance contract identifies the
other insurance policy which they are excluding.
- S 54 – discussed above