See discussions, stats, and author profiles for this publication at: https://www.researchgate.
net/publication/325119730
 Soil Nailing for Slope Stabilization: An Overview
Article · December 2016
CITATIONS                                                                                                  READS
22                                                                                                         40,116
3 authors, including:
            Ravindra Budania
            Malaviya National Institute of Technology Jaipur
            7 PUBLICATIONS 40 CITATIONS
              SEE PROFILE
 All content following this page was uploaded by Ravindra Budania on 14 May 2018.
 The user has requested enhancement of the downloaded file.
ISSN XXXX XXXX© 2016 IJESC
 Research Article                                                                                                   Volume 6 Issue No. 12
                               Soil Nailing for Slope Stabilization: An Overview
                                                                    Ravindra Budania1, Dr. R.P Arora2
                                                               M. Tech Scholar, CE, CTAE, Udaipur, India1
                                                              Associate Professor, CE, CTAE, Udaipur, India2
Abstract:
Soil nailing is an in-situ reinforcement technique by passive bars which can withsand tensile forces, shearing forces and bending
moments. This technique is used for retaining walls and for slope stabilization. Its behaviour is typical of that of composite materials
and involves essentially two interaction mechanisms. The soil- reinforcement friction and the normal earth pressure on the
reinforcement. The mobilization of the lateral friction requires frictional properties for the soil, while the mobilization of the normal
earth pressure requires a relative rigidity of the inclusions.          early 1960s was the premier prototype to use steel bars and
                                                                        shotcrete to reinforce the ground. With the increasing use of the
Keywords: Stabilization, Nails, Centralizers                            technique, semi-empirical designs for soil nailing began to
                                                                        evolve in the early 1970s. The first systematic research on soil
I. INTRODUCTION                                                         nailing, involving both model tests and full-scale field tests, was
                                                                        carried out in Germany in the mid-1970s. Subsequent
A landslide (landslip) is a geological phenomenon that comprises development work was initiated in France and the United States
a wide range of ground movements, such as rock falls, deep in the early 1990s.
failure of slopes etc. Landslides can occur in offshore, coastal
and onshore environment. It can be controlled by the use of                  • Tunnelling Method in the 1960’s.One of the first
proper slope stabilization techniques. Soil stabilization is a term               applications of soil nailing was in 1972 for a railroad
in which the natural soil is changed in order to meet the                         widening project near Versailles, France, where an 18 m
engineering purposes by means of physical, chemical, biological                   (59 ft) high.
and combined method of either two of them or all three. Weight               • In Germany, the first use of a soil nail wall was in 1975.
bearing capacity and the performance of the in-situ soil and sand            • The United States first used soil nailing in 1976 for the
can be increased by soil stabilization techniques (Sharma 2015).                  support of a 13.7 m deep foundation excavation in
Soil nailing is an advance technique of slope stabilization                       dense silty sands.
amongst other techniques. Soil nailing is the technique used in              • In India use of soil nailing technology is gradually
slope stabilization and excavation with the use of passive                        increasing and guidelines have been made by IRC with
inclusions, usually steel bars, termed as soil nail. Soil nailing is              the help of Indian Institute of Science, Bangalore.
typically used to stabilize existing slopes or excavations where
top-to-bottom construction is advantageous compared to other III.CONCEPT OF SOIL NAILING:-
retaining wall systems (Taib, 2010). Soil nails are structural
reinforcing elements installed to stabilize steep slopes and The function of soil nailing is to strengthen or stabilize the
vertical faces created during excavations. Commonly used soil existing steep slopes and excavations as construction proceeds
nails are made of steel bars covered with cement grout. The grout from the top to bottom. Soil nails develops their reinforcing
is applied to protect the steel bars from corrosion and to transfer action through soil-nail interaction due to the ground
the load efficiently to nearest stable ground. Some form of deformation which results in development of tensile forces in soil
support, usually wire mesh-reinforced shotcrete, is provided at nail. The major part of resistances comes from development of
the construction face to support the face between the nails and to axial force which is basically a tension force. Conventionally,
serve as a bearing surface for the nail plates (Palmeira et al., shear and bending have been assumed to provide little
2008).                                                                  contribution in providing resistance (Dey, 2015). The effect of
                                                                        soil nailing is to improve the stability of slope or excavation
II.ORIGIN OF THE SOIL NAILING TECHNIQUE                                 through
The soil nailing technique was developed in the early 1960s,                          a)        Increasing the normal force on shear plane and hence
partly from the techniques for rock bolting and multi-anchorage                       increase the shear resistance along slip plane in friction soil.
systems, and partly from reinforced fill technique (FHWA,                             b)        Reducing the driving force along slip plane both in
1998). The New Austrian Tunneling Method introduced in the                            friction and cohesive soil.
International Journal of Engineering Science and Computing, December 2016                    3877                                      http://ijesc.org/
In soil nailing, the reinforcement is installed horizontally or             results in increment of the normal force coming on slip plane and
gently inclined parallel to the direction of tensile strain so that it      reduces the driving shear force. The soil nails are embedded in
develops maximum tensile force develops. Soil nails are passive             passive region through which it resists the pull-out of nail from
inclusions, which improve shearing resistance of soil. The soil             slope through friction between nails and soil. Based on the above
nail system can be divided into active and passive region as                two mechanisms, the required amount of nail length should be
shown in Figure. During the slope failure, active region tends to           placed in resistive zone. In addition, the combined effect of nail
deform which results in axial displacement along soil nails                 head strength and tension force generated in active zone must be
which are placed across the slip plane. This results in the                 adequate to provide the required nail tension at the slip surface
development of tensile forces in soil nail in the passive zone              (Byrne et al. 1998).
which resists the deformation of active zone. This tension force
Figure.1. Conceptual soils nail behavior (Byrne et al., 1998)               Figure.2. Soil nails reinforcement Bars
    • Construction of soil nailing structures •                             4.1.2. Centralizers- Centralizers are devices made of polyvinyl
    Constructional elements •    Constructional procedure                   chloride (PVC) or other synthetic materials that are installed at
                                                                            various locations along the length of each nail bar to ensure that
4.1. Elements of nailed structure:-                                         a minimum thickness of grout completely covers the nail bar.
Various components of a grouted soil nail are:-
4.1.1. Steel reinforcing bars – The solid or hollow steel
reinforcing bars (with minimum strength of 415 kPa) are the
main component of the soil nailing system. These elements are
placed in pre-drilled drill holes and grouted in place.
                                                                            Figure.3. Typical Centralizers
International Journal of Engineering Science and Computing, December 2016          3878                                       http://ijesc.org/
4.1.3. Grout – Shotcrete or grout can be continuous flow of
mortal or concrete mixes projected at high speed perpendicularly
onto the exposed ground surface. Grout is injected in the
predrilled borehole after the nail is placed to fill up the annular
space between the nail bar and the surrounding ground.
Generally, neat cement grout is used to avoid caving in drillhole;
however, sand-cement grout is also applied for open-hole drilling
(Shong, 2005).
                                                                            Figure.5. Typical cross-section of a drilled soil nail wall
                                                                            (Byrne et al., 1998) Constructional Procedure
Figure.4. Grout is being placed with the help of pipes
                                                                            •        Excavation
4.1.4. Nail head – The nail head is the threaded end of the soil
nail that protrudes from the wall facing. It is a square shape              Prior to any excavation, surface water controls should be
concrete structure which includes the steel plate, steel nuts, and          constructed to prevent surface water from flowing into the
soil nail head reinforcement. This part of structure provides the           excavation, as this condition will adversely affect construction
soil nail bearing strength, and transfers bearing loads from the            and potentially cause instability of the excavated face. Collector
soil mass to soil nail.                                                     trenches behind the limits of the excavation usually intercept and
                                                                            divert surface water. Initial excavation is carried out to a depth
4.1.6. Temporary and permanent facing – Nails are connected                 for which the face of the excavation may remain unsupported for
to the excavation or slope surface by facing elements. Temporary            a short period of time, e.g. 24 to 48 hours. The depth for each
facing is placed on the unsupported excavation prior to                     excavation reaches slightly below the elevation where nails will
advancement of the excavation grades. It provides support to the            be installed. The width of the excavated platform or bench is
exposed soil, helps in corrosion protection and acts as bearing             such that it can provide sufficient access to the installation
surface for the bearing plate. Permanent facing is placed over the          equipment. The initial lift is typically taken as 1 to 1.2 m high.
temporary facing after the soil nails are installed.                        The excavated face profile should be reasonably smooth and not
                                                                            too irregular to minimize excessive shotcrete quantities.
4.1.7. Drainage system – Vertical geo-composite strip drains are
used as drainage system media. These are placed prior to
application of the temporary facing for collection and
transmission of seepage water which may migrate to the
temporary facing.
                                                                            Figure.6. Excavation of small cut (Byrne et al., 1998)
                                                                            Drilling Nail Holes:-
                                                                            There are two types of processes which can be carried out after
                                                                            excavation for putting the nails. The nail can be directly pushed
                                                                            into the soil using suitable equipment, in which the nail itself
                                                                            makes its way forward. Alternatively, a hole can be drilled prior
                                                                            to putting the nail by using some drilling equipment. Some of the
                                                                            drilling equipments used for this method are listed below.
International Journal of Engineering Science and Computing, December 2016          3879                                       http://ijesc.org/
                                                                            and admixtures are mixed in a batch plant and conveyed to the
• Drill bit machine                                                         nozzle by a hydraulic pump. Both shotcrete methods produce a
• Rope core drill                                                           mix suitable for wall facings. Dry mix and wet mix shotcrete use
• Air leg rock drill                                                        a water-cement ratio of about 0.4 and produce roughly the same
                                                                            mix quality, although shotcrete obtained with the wet mix
• Horizontal drill machine
                                                                            process yields a slightly greater flexural strength.
                                                                            Figure.9. Construction of Temporary Shotcrete Facing
                                                                            (Byrne et al., 1998)
Figure.7. Drilling Nail Holes (Byrne et al., 1998) Nail
Installation and Grouting:-
                                                                            Construction of Subsequent Levels:-
                                                                            The steps mentioned above are repeated for the remaining
Nail bars are placed in the pre-drilled holes. Centralizers are
                                                                            excavation stages. At each excavation stage, the vertical drainage
placed around the nails prior the insertion of nails to maintain
                                                                            strip is unrolled downward to the subsequent stage. A new panel
proper alignment within the hole and also to allow sufficient
                                                                            of WWM is then placed overlapping at least one full mesh cell.
protective grout coverage over the nail bar. Grout pipe is also
                                                                            The temporary shotcrete is continued with a cold joint with the
inserted in the drill hole at this stage. A grouting pipe is normally
                                                                            previous shotcrete lift. At the bottom of the excavation, the
attached with the nail reinforcement while inserting the nail into
                                                                            drainage strip is tied to a collecting toe drain.
the drilled hole. Sometimes additional correctional protection is
used by introducing corrugated plastic sheathing The normal
range of water/cement ratio of the typical grout mix is from 0.45
to 0.5. The grout is commonly placed under gravity or low
pressure. The grouting is from bottom up until fresh grout return
is observed from the hole.
                                                                            Figure.10. Construction of Subsequent Levels (Byrne et al.,
                                                                            1998)
                                                                            Construction of Permanent Facing:-
                                                                            The final facing is constructed after the bottom of the excavation
                                                                            is reached and nails are installed. Final facing consists of cast-
                                                                            inplace (CIP) reinforced concrete, reinforced shotcrete, or
                                                                            prefabricated panels. Generally, conventional concrete bars or
Figure.8. Nail Installation and Grouting (Byrne et al., 1998)               WWM is provided as reinforcement in permanent facing. When
                                                                            CIP concrete and shotcrete are used for the permanent facing,
Construction of Temporary Shotcrete Facing                                  horizontal joints between excavation stages are avoided to the
                                                                            maximum extent possible.
The temporary shotcrete facing is placed to temporarily restrain
the exposed soil in cut face. It consists of 3-4 inches of shotcrete
reinforced with a single layer of welded wire mesh. Two types of
shotcrete methods are commonly used: dry mix and wet mix. In
the dry mix method, the aggregate and cement are blended in the
dry and fed into the shotcrete gun while the mix water is added at
the nozzle. In the wet mix method, the aggregate, cement, water,
International Journal of Engineering Science and Computing, December 2016          3880                                       http://ijesc.org/
Figure.11. Construction of Permanent Facing (Byrne et al.,
1998)
• VARIOUS TYPES OF SOIL NAILING:-
Various types of soil nailing methods that are employed in the
field are listed below:
      • Grouted Nail: After excavation, first holes are drilled
            in the wall/slope face and then the nails are placed in
            the predrilled holes. Finally, the drill hole is then filled
            with cement grout.
      • Driven Nail: In this type, nails are mechanically driven            Figure. 12. Roadway Cuts (lazarte et al., 2015)
            to the wall during excavation. Installation of this type
            of soil nailing is very fast; however, it does not provide      6.2. Road Widening Under Existing Bridge Abutments Soil
            a good corrosion protection. This is generally used as          nail walls can be advantageous for underpass widening when
            temporary nailing.                                              the removal of an existing bridge abutment slope is necessary.
      • Self-Drilling Soil Nail: Hollow bars are driven and                 While the cost of installing a soil nail wall under a bridge
            grout is injected through the hollow bar simultaneously         abutment may be comparable to that of other applicable
            during the drilling. This method is faster than the             systems, the advantage of soil nailing is that the size of the soil
            grouted nailing and it exhibits more corrosion                  nail drill rig is relatively small.
            protection than driven nail.
      • Jet-Grouted Soil Nail: Jet grouting is used to erode the
            ground and for creating the hole to install the steel
            bars. The grout provides corrosion protection for the
            nail.
•    Applications
     Soil nail can be used in the following applications: (lazarte
     et al., 2015)
6.1. Roadway Cuts
Soil nailing is attractive in roadway cuts because a limited
excavation and reasonable right-of-way (ROW) and clearing
limits are required. These factors help to reduce the
environmental impacts along the transportation corridor. The
impact to traffic may also be reduced because the equipment for
installing soil nails is relatively small.
                                                                            Figure.13.      Road Widening              under        Existing
                                                                                    Bridge Abutments (lazarte et al., 2015)
                                                                            Repair and Reconstruction of Existing Retaining Structures
                                                                            Soil nails can be used to stabilize and/or strengthen failing or
                                                                            distressed retaining structures. For example, some mechanically
                                                                            stabilized earth (MSE) walls may exhibit excessive deformation
                                                                            due to poor design, poor construction, or both. Soil nails can be
                                                                            installed directly through the face of an MSE wall if the existing
                                                                            face is sufficiently stable to resist drilling. The selection of an
                                                                            appropriate bearing plate to support soil nails stabilizing MSE
                                                                            and masonry walls is very important. The bearing plate must be
International Journal of Engineering Science and Computing, December 2016          3881                                         http://ijesc.org/
able to fully transfer loads without damage to the existing                  be
facing.                                                                      appropri
                                                                             ate for
•   Advantage and Disadvantages of soil nailing                              applicat
                                                                             ions
Advantages associated with soil nailing fall into three main                 where
categories: Construction, Performance, and Cost. (lazarte et al.,            very
2015)                                                                        strict
                                                                             deforma
Construction                                                                 tion
                                                                             control
•         Soil nail walls require smaller rows than most other               is
competing systems. This is also true for ground anchors as soil              required
nails are typically shorter.                                                 for
•         Soil nail walls are less disruptive to traffic and cause
less environmental impact compared to other construction
techniques such as drilled shafts or soldier pile walls, which
require relatively large equipment. • The installation of soil nail
walls is relatively fast.
•         Soil nail wall installation is not as restricted by
overhead limitation as in the case of soldier pile installation. This
advantage is particularly important when construction occurs
under a bridge.
•         Soil nailing may be more cost-effective at sites with
remote access because the smaller equipment is more readily
mobilized.
•         Soil nails are installed using equipment that is
multipurpose and can be used for other substructure elements
such as underpinning or protection of adjacent, movement-
sensitive structures.
 Performance
 Soil nail walls are relatively flexible and can accommodate
comparatively large total and differential movements. • The
measured deflections of soil nail walls are usually within
tolerable limits in roadway projects when the construction is
properly controlled. • Soil nail walls have performed well during
seismic events. • Soil nail walls have more redundancy than
anchored walls because the number of reinforcing elements per
unit area of wall is larger than for anchored walls.
Cost
•        Conventional soil nail walls tend to be more economical
than conventional concrete gravity walls taller than
approximately 12 to 15 ft.
•        Soil nail walls are typically equivalent in cost or more
costeffective than ground anchor walls when conventional soil
nailing construction procedures are used.
•   Soil nail disadvantages
Some of the potential disadvantages of soil nail walls are (Liew
Shaw-Shong, 2005):
   • Soil nail
        walls
        may not
International Journal of Engineering Science and Computing, December 2016   3882        http://ijesc.org/
         structures and utilities located behind the proposed
         wall, as the system requires some soil deformation to
         mobilize resistance. Deflections can be reduced by post
         tensioning but at an increased cost.
    •    Existing utilities may place restrictions on the location, inclination,
         and length of soil nails.
    •    Soil nail walls are not well suited where large amounts of
         groundwater seep into the excavation because of the requirement to
         maintain a temporary unsupported excavation face.
    •    Permanent soil nail walls require permanent, underground
         easements.
    •    Less suitable for course grained soil and soft clayey soil, which have
         short self-support time, and soils prone to creeping.
    •    Suitable only for excavation above groundwater.
IV. REFERENCES
[1]. Babu, GL Sivakumar, R. S. Rao, and S. M. Dasaka.
"Stabilisation of vertical cut supporting a retaining wall using
soil nailing: a case study." Proceedings of the Institution of Civil
Engineers-Ground Improvement 11.3 (2007): 157-162.
[2]. Byrne, R. J., Cotton, D., Porterfield, J., Wolschlag, C. and
Ueblacker, G. (1998) “Soil Manual for design and construction
monitoring of soil nail wall” Manual of the Federal Highway
Administration Division, (No. FHWA0-SA-96-069R.)
[3]. Lazarte, C. A., Robinson, H., Gómez, J. E., Baxter, A.,
Cadden, A., & Berg, R. (2015). Soil Nail Walls Reference Man
ual (No. FHWA-NH I-14-007).
[4]. Liew, S. S., & Liong, C. H. (2006). Two Case Studies on Soil
Nailed Slope Failures. In submitted) International Conference on
Slopes, Malaysia.
[5]. Palmeira, E. M., Tatsuoka, F., Bathurst, R. J., Stevenson, P.
E., & Zornberg, J. G. (2008). Advances in geosynthetics
materials and applications for soil reinforcement and
environmental protection works. Electron J Geotech Eng, Spec
Issue State of the Art in Geotech Eng, 13, 1-38.
[6]. Shaw-Shong, L. (2005). Soil nailing for slope strengthening.
Geotechnical Engineering, Gue & Partners Sdn Bhd, Kuala
Lumpur, Malaysia.
[7]. Taib, S. N. L. (2010). A Review of Soil Nailing Design
Approaches. UNIMAS E-Journal of Civil Engineering, 1(2).
[8]. Jewell, R. A. and Pedley, M. J. (1992) “Analysis for soil
reinforcement with bending stiffness” Journal of Geotechnical
Engineering, ASCE, Vol. 118, No. 10, pp. 1505-1528.
            Journal of Engineering Science and Computing, December 2016       3883   http://ijesc.org/
[9]. Sharma, P. “Theoretical analysis of soil nailing: design,
performance and future aspects (2015)”. International Journal of
Engineering Research and General Science
International
   View publication stats
                      Journal of Engineering Science and Computing, December 2016   3884   http://ijesc.org/