NEOM Clearing & Scaling ITP Guide

The document outlines an inspection and test plan for clearing and scaling work. It details various inspection and testing methods for activities like document review, material receiving, site preparation, installation of anchor bolts, and testing of installed anchor bolts. Inspection and acceptance criteria are provided for each activity.

Uploaded by

Vishnudas Mg
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
439 views2 pages

NEOM Clearing & Scaling ITP Guide

The document outlines an inspection and test plan for clearing and scaling work. It details various inspection and testing methods for activities like document review, material receiving, site preparation, installation of anchor bolts, and testing of installed anchor bolts. Inspection and acceptance criteria are provided for each activity.

Uploaded by

Vishnudas Mg
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Contractor’s

INSPECTION AND TEST PLAN FOR CLEARING & SCALING


NEOM QUALITY MANAGEMENT SYSTEM Main Contractor: Mofarreh Alharbi & Partners & BATCO JV
NEOM QMS-PRO-005-001 CONSTRUCTION OF PROJECT (ITP) FOR
CLEARING & SCALING Sub-Contractor: N/A Logo
Contract Rev.
Contract No.: 4800000657/00 Design & Build of Rock Stabilization Wadi Interceptors ITP No.: 02-181100-4800000-MAH-CIV-ITP-002 Rev.02 03 Date: 19-June-23
Title: No.:

Level of Participation Points


S Controlling Document/ Acceptance
Activity Phase Inspection / Test Method Remark66
No. Reference Standard Criteria Main NEOM
NEOM Q&E
Con. PMC

1 Document Review
Method Statement Reference No. Approved Method statement
1.1 Method Statement Document Review 02-181100-4800000657-MAH-CIV- in Code A or Code B with H R/H R/H
MST-000001 comments

1.2 Shop Drawing Document Review As per Approved Shop Drawings Approved Shop Drawing H R/H R/H
Materials Approval No. Approved in Code A or
1.3 Material Approval Document Review 02-181100-4800000657-MAH-CIV- Code B with comments. H R/H R/H
MAT-000002
Pre-qualification of Inspection & Approved in Code A or
1.4 Document Review Approved Laboratory H R/H R/H
Testing Laboratory / Third Party Code B with comments
2 Material Receiving Inspection, Sampling and Testing
Approved Material in Code
A or Code B with comments
List all Required Materials Received Document Review,
2.1 Materials Submittal /Approved MIR / Approved Material H H W
on Site Material Inspection
Inspection Request (MIR)

NEOM Bay Spécification Section NEOM Bay Spécification


2.2 Material Storage and Handling Visual Inspection H S S
017843 /1.4 Section 017843 /1.4
3 Main Activities / Work Execution
Approved Survey ITP / NEOM Bay Approved Work Inspection
3.1 Survey setting out Survey Inspections / Visual Inspection Specification 017300 section 3.3 & Request (WIR) as per H W S
3.4 Approved Survey ITP
Approved/Signed Inspection
NEOM Bay Spécification Section
3.2 Site Cleaning & Preparation Survey Inspections / Visual Inspection Checklist (JV-CIV-ICL-001- H S S
311000 – Site Clearing
01)
Approved Work Inspection
Installation of Anchor Bolt and Fixing Approved Survey ITP, Drawing /Test
3.2.1 Survey Inspections / Visual Inspection Request (WIR) as per H H S
Polyamide Rope Reports
Approved Survey ITP
Testing
Visual Inspection / Third-Party Test (Bearing Third Party Test Reports / Approved Work Inspection
3.2.2 (Anchor Bolt with attached H H H
Capacity / Shear Tests) Manufacturer Recommendations Request (WIR)
Polyamide Rope after Installation)
Approved Survey ITP, Approved Approved/Signed Inspection
Scaling Work (Manual & Mechanical
3.3 Survey Inspections / Visual Inspection Method Statement, Approved Checklist (JV-CIV-ICL-001- H W S
Scaling)
Drawing 01)
Approved/Signed Inspection
Mucking & shifting of scaling Approved Survey ITP, Approved
3.4 Survey Inspections / Visual Inspection Checklist (JV-CIV-ICL-001- H S S
material Method Statement
01)
Approved Work Inspection
3.5 Final Inspection Survey Inspections / Visual Inspection Approved As-built Drawing H H H
Request (WIR)
ITP Approval Signature
Sub-Contractor (If Applicable) Main Contractor PMC NEOM Q&E
Name: Name: KAILASH PATIL Name: Name:

Signature: Signature: Signature: Signature:

Date: Date: Date: Date:


GENERAL NOTES:

Legend:

S: Responsible for carrying out random surveillance of inspection or


H: Contractor must not proceed without approval. R: Responsible for reviewing certification or reports. W: Responsible for / and witnessing all inspection or test.
test/Random Check.

DO C U ME NT CO D E : NE OM - NEN - SO P- 008_F R M 11 RE VI SIO N C OD E: 0 1 . 00 PAG E 1 OF 2


©NEOM [2021]. All rights reserved.
Contractor’s
INSPECTION AND TEST PLAN FOR CLEARING & SCALING
NEOM QUALITY MANAGEMENT SYSTEM Main Contractor: Mofarreh Alharbi & Partners & BATCO JV
NEOM QMS-PRO-005-001 CONSTRUCTION OF PROJECT (ITP) FOR
CLEARING & SCALING Sub-Contractor: N/A Logo
Contract Rev.
Contract No.: 4800000657/00 Design & Build of Rock Stabilization Wadi Interceptors ITP No.: 02-181100-4800000-MAH-CIV-ITP-002 Rev.02 03 Date: 19-June-23
Title: No.:

Level of Participation Points


S Controlling Document/ Acceptance
Activity Phase Inspection / Test Method Remark66
No. Reference Standard Criteria Main NEOM
NEOM Q&E
Con. PMC
The first (3) of each inspection or testing activities listed require 100% participation of client site inspection personnel. After this period, client inspection may adjust the level of client participation based on the contractor's performance.
Hold: QA/QC team shall be notified of the schedule of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC Team/Client representative in attendance.
Review: Required qualification/certification/reports shall be submitted for the QA/QC team review and approval.
Witness: QA/QC team shall be notified of the schedule of inspection or test in advance. If the QA/QC Team/Client representative doesn’t come on time for inspection, the activity can proceed.
Surveillance: QA/QC team to monitor work in progress without notice from the construction organization/Random check selection.
Review/Hold: QA/QC team shall review and approve all required documents before commencement of the work.

Legend:

S: Responsible for carrying out random surveillance of inspection or


H: Contractor must not proceed without approval. R: Responsible for reviewing certification or reports. W: Responsible for / and witnessing all inspection or test.
test/Random Check.

DO C U ME NT CO D E : NE OM - NEN - SO P- 008_F R M 11 RE VI SIO N C OD E: 0 1 . 00 PAG E 2 OF 2


©NEOM [2021]. All rights reserved.