ANNEX 7 / Telecommunications
Sub-sector: GSM System with the following main characteristics:
Capacity: 25000 subscribers
Coverage: Entire Baghdad city and 50 km along 6 main roads from it).
No. of BTS sites : 60
Interconnection between sites and with PSTN: Low – medium
capacity microwave links
Required Grade of Service: not more than 2% blocking
Assumed average traffic per subscribers: about 40 mErlang
Status of the project: In final negotiation stage with the bidders. The contract
is to be signed with the successful bidder before 10th of April 1999 at the
latest (in a provisional mode).
Estimated time of completion of the project: 6-9 months from effective date
of the contract.
Estimated total cost of the project: 22 – 25 Million USD.
Important Note: Full detail of each of following general items will be given
once the final contract is signed with the successful bidder.
Code Item Description Unit Quantity Complementary
Items
07-04-00100 MSC/VLR complete Subsystem 1 Note (1)
with:
07-04-00110 - Power Supply Set 1
Equipment 1
07-04-00120 - air-conditioning Set 1
07-04-00130 - batteries Set
07-04-00200 HLR Subsystem 1 Note(1)
07-04-00210 AUC Subsystem 1
07-04-00220 EIR Subsystem 1
07-04-00230 SMS Subsystem 1
07-04-00240 VM Subsystem 1
07-04-00300 BSC Equipment Subsystem 3 Note(1)
complete with:
07-04-00310 - Power Supply Lot
Equipment (set)
07-04-00320 - Air-conditioning Lot
Equipment (set)
07-04-00330 - Batteries (set) Lot
07-04-00400 BTS Equipment (2/2/2 Station 60 Note(1)
1
TRX Type) complete Note(2)
with:
07-04-00420 - Power Supply Set
Equipment
07-04-00430 - Air-conditioning
Equipment Set
07-04-00430 - Batteries Set
07-04-00440 - Antennas Set
07-04-00450 - Feeders Set
07-04-00500 Microwave Links with Link 68 Note(1)
appropriate capacities to Note(2)
connect the BTS’s to
BSC’s and to MSC and
to 5 PSTN exchanges in
Baghdad.
Complete with:
07-04-00520 - Indoor & Outdoor
equipment Set
07-04-00530 - Antennas Set
07-04-00540 - Feeders Set
07-04-00550 - Power Supplies Set
07-04-00600 OMC for BSS Equipment Subsystem 1 Note(1)
(Servers , PC’s , NMS
Equipment .. etc. , )
(system)
07-04-00700 OMC for NSS Subsystem 1 Note(1)
Equipment
(Servers , PC’s , NMS
Equipment .. etc. , )
(system)
07-04-00800 NMS for the Microwave Subsystem 1 Note(1)
links with necessary
PC’s, Software etc.
07-04-00900 Billing System & Subsystem 1 Note(1)
Customer Care System:
complete with the
necessary servers, PC’s,
Printers, Software etc.
07-04-01000 Radio Network Planning Subsystem 1 Note(1)
tool/platform
2
Including necessary
Hardware and Software
07-04-01200 SIM Card Issuing and Set 2
Personalization
system/tool
07-04-01300 Virgin SIM Cards Units 25000
07-04-01400 GSM Handsets Units 25000
07-04-01500 Miscellaneous:
07-04-01510 - Shelters for BTS’s Unit 30
and Microwave Links
Equipment
07-04-01520 - Towers 40 m Unit 20
07-04-01530 - Masts 10-15 m Unit 40
07-04-01540 - Maintenance Vehicles Unit 10
04-04-01550 - Full Documentation Set 3
on all systems
07-04-01600 Spare Parts for all Lot 1 lot
Subsystems:
10% of the total cost of
the equipment
07-04-01700 Test Equipment 3 Sets
including:
Spectrum Analyzer,
GSM test set, Power
metes, Frequency
Counter, Digital Analyser
… etc. and as relevant
and absolutely necessary
for system operation and
maintenance.
07-04-01800 Installation and Lot 1
Commissioning including
the necessary installation
tools and materials.
07-04-01900 Training by the Lot 2 Note 3
manufacturer personal
including Factory
training, Local training
and On-job training
3
07-04-02000 Training Platform Lot 1
(Simplified) for local
training including
necessary hardware,
software and training aids
and material
NOTES:
Note (1): Appropriate equipment room will be provided and properly
furnished and equipped in all sites.
Note (2): Procurement and preparation of BTS and Microwave antenna sites
is the responsibility of ITPC. In many cases existing ITPC towers and
facilities will be used. The responsibility of erection of new towers and mast
will be agreed upon with the supplier. In some cases shelters will be used
either on the ground or on rooftops to provide the necessary space to install
the BTS and Microwave links equipment.
Note (3): Existing and newly recruited engineers shall be employed for the
project. No problem whatsoever is envisaged in this aspect due to high
availability of unemployed engineers in the local market. Special incentives
will be given to help in this matter.